RSU No. 24 Charles M. Sumner Learning Campus April 14, 2020 CONSTRUCTION DOCUMENTS Mariaville Waltham Eastbrook Franklin Sullivan Sorrento Gouldsboro Winter Harbor Steuben

Upload: others

Post on 25-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

1

RSU No. 24 Charles M. Sumner Learning Campus

April 14, 2020

CONSTRUCTION DOCUMENTS

Mariaville Waltham Eastbrook Franklin Sullivan Sorrento Gouldsboro Winter Harbor Steuben

2

PLAN DEVELOPMENTS – AUDITORIUM

3

PLAN DEVELOPMENTS – AUDITORIUM

4

PLAN DEVELOPMENTS – AUDITORIUM

Stage Lighting House Lights (auditorium + cafeteria) Control Booth

5

AUDITORIUM – VIEW OF STAGE

6

NURSE CLINIC

7

SECURITY

8

TECHNOLOGY

9

INTERIOR ELEVATIONS – Main St.

10

INTERIOR ELEVATIONS – Main St.

11

FIELD IRRIGATION

Field Stand Pipes

Existing Water Main c. 1900

New Water Main

12

BUDGET & BID ALTERNATES

Bid Alternates 1. Standpipes in Stairwells 2. Reserve Water Tank at Rte. 1 3. Bleachers at MS Gym, Cross-court Backboards, Gym Equipment 4. ¼ Mile Stone Dust Running Track 5. Dust Collection System in Materials Labs 6. Auditorium Lighting and Rigging 7. Pathways Kitchen Equipment 8. Sinks and Additional Casework at MS Classrooms 9. Window Treatments

13

COMMISSIONING AGENT SELECTED

Contract will include - Drawing Review Before Bid - Commissioning Plan for Bid Documents - MEP Commissioning During

Construction - Start Up Commissioning - Envelope Commissioning and Window

Testing - Training Plan Review & Support - Post-Occupancy Review

14

PREQUALIFICATION OF CONTRACTORS

Ad: April 17-22 Prequalification Package or Letter of Intent: May 8 Notification to Contractors: May 15 GC’s who have expressed interest: Sheridan Construction Nickerson and O’Day, Inc. Bowman Constructors PC Construction

15

SCHEDULE

Milestone Date

75% Coordination & Reprice February 28, 2020

Interview / Hire Commissioning Agent March 2020

Prequalify General Contractors April 2020

Interview / Hire Clerk of the Works May 2020

Progress Submission & Estimate April 27, 2020

Permit Submission to SFM April 27, 2020

QA/QC April 27 – May 15

100% Submission w/ Final Estimate May 15 , 2020

Design Approval SBOE June 10, 2020

Bidding (5 weeks) June – July 2020

Contracting July 2020

Construction Start Early August 2020

Bond Date Spring 2021

Substantial Completion June 2022

Furniture / IT / Equipment Install July 2022

Occupy Building August 2022

*Planning Board Approval N/A