rsu no. 24 construction documents charles m. sumner … committee/20200414... · 2020. 4. 14. ·...
TRANSCRIPT
1
RSU No. 24 Charles M. Sumner Learning Campus
April 14, 2020
CONSTRUCTION DOCUMENTS
Mariaville Waltham Eastbrook Franklin Sullivan Sorrento Gouldsboro Winter Harbor Steuben
12
BUDGET & BID ALTERNATES
Bid Alternates 1. Standpipes in Stairwells 2. Reserve Water Tank at Rte. 1 3. Bleachers at MS Gym, Cross-court Backboards, Gym Equipment 4. ¼ Mile Stone Dust Running Track 5. Dust Collection System in Materials Labs 6. Auditorium Lighting and Rigging 7. Pathways Kitchen Equipment 8. Sinks and Additional Casework at MS Classrooms 9. Window Treatments
13
COMMISSIONING AGENT SELECTED
Contract will include - Drawing Review Before Bid - Commissioning Plan for Bid Documents - MEP Commissioning During
Construction - Start Up Commissioning - Envelope Commissioning and Window
Testing - Training Plan Review & Support - Post-Occupancy Review
14
PREQUALIFICATION OF CONTRACTORS
Ad: April 17-22 Prequalification Package or Letter of Intent: May 8 Notification to Contractors: May 15 GC’s who have expressed interest: Sheridan Construction Nickerson and O’Day, Inc. Bowman Constructors PC Construction
15
SCHEDULE
Milestone Date
75% Coordination & Reprice February 28, 2020
Interview / Hire Commissioning Agent March 2020
Prequalify General Contractors April 2020
Interview / Hire Clerk of the Works May 2020
Progress Submission & Estimate April 27, 2020
Permit Submission to SFM April 27, 2020
QA/QC April 27 – May 15
100% Submission w/ Final Estimate May 15 , 2020
Design Approval SBOE June 10, 2020
Bidding (5 weeks) June – July 2020
Contracting July 2020
Construction Start Early August 2020
Bond Date Spring 2021
Substantial Completion June 2022
Furniture / IT / Equipment Install July 2022
Occupy Building August 2022
*Planning Board Approval N/A