RAINPOWER AS 0 2013-03-15 Issued first time E. Larsen J. Jensen Rev Date Description Written by Dept Appr R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov installation.doc PROCEDURE FOR INSTALLATION OF THE GOVERNOR SN POWER CHEVES HEPP PELTON TURBINE Unit 1 and 2 Document No.: RP-H-N-I-P-001 ARA000273-O1N

Upload: david-jaramillo-payano

Post on 09-Sep-2015

216 views

Category:

Documents


0 download

DESCRIPTION

bmnm nm nmnmmmmm

TRANSCRIPT

  • RAINPOWER AS

    0 2013-03-15 Issued first time E. Larsen J. Jensen

    Rev Date Description Written by Dept Appr

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    PROCEDURE FOR INSTALLATION OF THE GOVERNOR

    SN POWER CHEVES HEPP

    PELTON TURBINE Unit 1 and 2

    Document No.: RP-H-N-I-P-001 ARA000273-O1N

  • Document

    PROCEDURE

    SN POWER Cheves HEPP - Pelton turbine unit 1 and 2

    Document no.: ARA000273-O1N

    KH doc. no.: Revision No.: 0

    Page 2 of 11 Subject: Installation procedure for governor

    First issued date: 2013-03-15

    This document and the design is the property of Rainpower and must not be used nor disclosed to any third party without Rainpower

    permission.

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    Order no.

    221304 Index R010

    Customer

    SN Power Project Doc. No.

    Activity

    Code Site

    Cheves HEPP Pelton Turbine File Name

    CONTENT

    1 PURPOSE ........................................................................................................ 3

    2 DEFINITIONS ................................................................................................. 3

    3 RESPONSIBILITY AND ROLES ................................................................. 4

    4 DESCRIPTION ............................................................................................... 5

    4.1 Instruction manual ............................................................................................. 5

    4.2 EHS (Environmental Health and Security) ....................................................... 6

    5 REFERENCES ................................................................................................ 6

    5.1 Drawings ............................................................................................................ 7

    5.2 Site Installation Control Forms ......................................................................... 7

    6 DEVIATIONS .................................................................................................. 7

    7 ENCLOSURES ................................................................................................ 7

    8 INSTRUCTION MANUAL ............................................................................ 8

  • Document

    PROCEDURE

    SN POWER Cheves HEPP - Pelton turbine unit 1 and 2

    Document no.: ARA000273-O1N

    KH doc. no.: Revision No.: 0

    Page 3 of 11 Subject: Installation procedure for governor

    First issued date: 2013-03-15

    This document and the design is the property of Rainpower and must not be used nor disclosed to any third party without Rainpower

    permission.

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    1 PURPOSE

    The procedure describes the installation steps for the Pelton turbine governors

    supplied by Rainpower AS, hereafter named RP, for SN Power - Cheves HEPP

    turbine 1 and 2, hereafter named SNP.

    The procedure is designed to ensure that the installation will be performed in

    accordance with Contractual requirements and to a high standard of

    workmanship. Sketches and diagrams are included to support the installation

    sequences described herein.

    The procedure is made for the 1st unit, and may be revised for the next unit if

    changes are regarded as favourable for the progress of work.

    2 DEFINITIONS

    Site Installation Control Form (SICF) forms to verify and record performance of the installation steps. Tolerances, as built dimensions from

    drawings and measured dimensions at site are included in the forms as

    appropriate. The sheets are designated as Form 1, Form 2, etc.

    Control comparison with specified requirements to verify compliance.

    Technical information documents that specify detailed requirements. This may be the Contract, drawings and other relevant information in order to

    secure the performance of the installation work.

    Inspection Plan (TP) document describing the various inspections to be performed during site installation with reference to the Installation Procedure

    and applicable SICF.

  • Document

    PROCEDURE

    SN POWER Cheves HEPP - Pelton turbine unit 1 and 2

    Document no.: ARA000273-O1N

    KH doc. no.: Revision No.: 0

    Page 4 of 11 Subject: Installation procedure for governor

    First issued date: 2013-03-15

    This document and the design is the property of Rainpower and must not be used nor disclosed to any third party without Rainpower

    permission.

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    3 RESPONSIBILITY AND ROLES

    RP is responsible to provide its subsuppliers and SNP with appropriate information to perform the installation work

    RP acts as supervisor for the installation company, hereafter named IC who is performing the installation work

    The RP supervisor is located at site as long as deemed necessary to terminate the installation work and in accordance with contractual

    obligations

    RP is responsible to see that all SICF are filled in and approved by IC after accomplishment of each step whenever recording is required

    RP shall witness and approve the SICF

    RP may hand the SICF to SNP for review and approval

    If some changes in installation sequences are requested by RP, the changes shall be submitted to SNP for his approval during site meetings whenever

    meetings are carried out on regularly basis. A design amendment may be

    issued and signed by the two (2) parties

    RP is responsible for issuing this procedure, and for preparation of revisions to the document as necessary to capture any changes or corrections to the

    procedure

  • Document

    PROCEDURE

    SN POWER Cheves HEPP - Pelton turbine unit 1 and 2

    Document no.: ARA000273-O1N

    KH doc. no.: Revision No.: 0

    Page 5 of 11 Subject: Installation procedure for governor

    First issued date: 2013-03-15

    This document and the design is the property of Rainpower and must not be used nor disclosed to any third party without Rainpower

    permission.

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    4 DESCRIPTION

    4.1 Instruction manual

    The sequences of the installation work are given in the Instruction Manual that

    is included in the procedure refer section 8.

    The Instruction Manual expresses the specific steps of work for installation of

    the equipment, and provides reference to relevant documents and SICF as

    appropriate.

    The Instruction Manual includes columns for:

    The actual item and activity number

    The specific activity to be carried out with number

    The company responsible for the activity

    Detailed description of the activity

    Sketches and references to relevant drawings, documents and SICF

    To avoid confusion or conflicts, no design values or tolerances that are stated on the drawings are repeated in the manual, however nominal

    values and tolerances may be included in the SICF

  • Document

    PROCEDURE

    SN POWER Cheves HEPP - Pelton turbine unit 1 and 2

    Document no.: ARA000273-O1N

    KH doc. no.: Revision No.: 0

    Page 6 of 11 Subject: Installation procedure for governor

    First issued date: 2013-03-15

    This document and the design is the property of Rainpower and must not be used nor disclosed to any third party without Rainpower

    permission.

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    4.2 EHS (Environmental Health and Security)

    The section is addressing only particular risks (if applicable) related to the

    tests and work explained in this procedure.

    For details how to mitigate risks, refer to applicable procedures and site safety

    plan issued by RP. Safety plan issued by SNP overrules the RP plan whenever

    interpretations about the understanding are raised.

    Note that pre-work hazard assessments should be performed prior to any task

    to determine any and all safety issues and their elimination, control or

    mitigation with special care to:

    Rotating equipment/machinery

    Electrical hazards

    Flood/drowning hazards

    Pressurized substances (oil, nitrogen, air, water)

    Fire (cable/electrical fire, oil fire)

    Noise

    Overhead/lifting hazards

    For safety purposes SNP should check, test or certify, as appropriate, all

    handling and lifting equipment to be used during the installation work.

    This equipment is supposed to be permanent equipment installed at site.

    IC shall present valid certificates for handling of lifting tools for SNP and RP.

    5 REFERENCES

    Contract between SN Power and the Consortium Rainpower AS, Jeumont and

    ABB.

    General requirements for welded constructions, RP doc. No. 30103.

    Procedure for flushing of oil pipes to governor and main inlet valve MIV RP doc. 24993

  • Document

    PROCEDURE

    SN POWER Cheves HEPP - Pelton turbine unit 1 and 2

    Document no.: ARA000273-O1N

    KH doc. no.: Revision No.: 0

    Page 7 of 11 Subject: Installation procedure for governor

    First issued date: 2013-03-15

    This document and the design is the property of Rainpower and must not be used nor disclosed to any third party without Rainpower

    permission.

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov

    installation.doc

    5.1 Drawings

    INDEX TITLE DRAWING NUMBER

    R670 Mech./Hydraulic Over Speed Device RP-D-N-I-P-014

    R510 Piping Arrangement RP-D-N-I-P-001

    R010 Hydraulic diagram RP-D-N-I-P-013

    5.2 Site Installation Control Forms

    Title

    Form No

    Verification of cleanliness and shooting plastic bullets 1

    Pressure Oil Pipes - Test Result 2

    Cable check 3

    6 DEVIATIONS

    None.

    7 ENCLOSURES

    None.

  • Cheves HEPP Instruction for installation of the governor

    No. ITEM ACTIVITY

    No.

    of

    step

    Resp

    JOB STEPS REFERENCE

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov installation.doc

    8 INSTRUCTION MANUAL

    1 INSTALLA-

    TION OF THE

    GOVERNOR

    1-1 Preconditions 1 SNP/

    CW

    The erection area shall be cleaned and drained for water.

    All civil works shall be finished, and if required floors, walls

    roofs etc. shall be painted prior to start installation of the

    governor system.

    2 SNP/

    CW

    The erection area shall be lighted, electric power supply and

    compressed air shall be available.

    3 RP/

    SNP

    Components will be received and stored in/out-door according

    to instruction/agreement between RP and SNP.

    The components will be moved to the erection areas according

    to Contractual schedule and installation sequences.

    1-2 General 1 IC/RP All bolt threads will be lubricated prior to inserting bolts/nuts.

    All bolt connections will be tightened according to torque

    values indicated on applicable drawings.

    2 OIL PRESSURE

    UNIT (OPS)

    WITH

    ACCUMULA_

    TOR

    2-1 Preparations 1 RP/IC/

    CW

    The OPS shall be moved to the machinery hall floor in order to

    be reached by the machinery hall over-head crane.

    The floor where the OPS shall be installed shall be inspected

    and prepared to installation of the OPS.

    Prepare as necessary caterpillars to move the OPS on the floor.

    2-2 Installation The OPS shall be lowered by means of the machinery hall over-head crane through the hoisting hatch to final level

    Prior to off loading the OPS, the caterpillars, if needed, shall be placed underneath the OPS. The OPS will be

    moved to the correct position on the floor

    The OPS will be fastened to the floor using concrete anchor bolts drilled in the floor.

    All outlets are plugged and they shall remain plugged until the installation of the piping is completed

  • Cheves HEPP Instruction for installation of the governor

    No. ITEM ACTIVITY

    No.

    of

    step

    Resp

    JOB STEPS REFERENCE

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov installation.doc

    3 OVERSPEED

    DEVICE

    3-1 Preparations

    1 RP/IC The combined shaft system is aligned.

    3-2 Installation 1 IC/RP The over speed device assembly shall be installed according to

    drawing.

    4 PIPING 4-1 Preparations 1 RP/IC The necessary amount of pipes and couplings shall be present

    prior to installation.

    The same applies to special tools for couplings according to the

    Walform system.

    Installation Procedure for Walform Tube Fittings.

    Drawing No. RP-D-N-I-P-001 Piping Arrangement.

    4-2 Installation 1 RP/IC The necessary amount of pipes and couplings shall be present

    prior to installation, drawing RP-D-N-I-P-001.

    The couplings shall be of the Walform type and assembled in

    accordance with the Walform Tube Fittings procedure Special tools for couplings connections according to

    instructions from the Walform system shall be present.

    Every single coupling shall be check for proper assembly prior

    to pressurizing the pipe lines. The check shall be verified with

    mark-up each coupling.

    4-3 Cleaning 1 RP/IC The cleaning will be carried out in two (2) steps:

    1 Bullet cleaning 2 Flushing

    4-4 Bullet cleaning 1 RP/IC A high pressure Plastic gun shoots plastic bullets through the different parts of the piping

    Cleaning shall be verified in SICF, Form 1

    4-5 Flushing 1 RP/IC The second step cleaning shall be carried out by the hydraulic

    flushing method. The flushing shall be carried out in

    accordance with written procedure. The cleanliness values shall

    be recorded in SICF, Form 1.

    Procedure for flushing and pressure test of the oil piping

    system - RP 24993

    SICF, Form 1 Verification of cleaning.

  • Cheves HEPP Instruction for installation of the governor

    No. ITEM ACTIVITY

    No.

    of

    step

    Resp

    JOB STEPS REFERENCE

    R:\Kjeller\Projects\Cheves.pel\Order-2010\16 Site and HMS\Installation procedures\Gov & OPS\RP-H-N-I-P-001_Rev 0 Gov installation.doc

    4-6 Pressure testing 1 RP/IC The pressure testing shall be performed with the same loop

    arrangement as for the flushing.

    The pressure test shall be carried out in accordance with written

    procedure.

    The result of the pressure test shall be recorded on SICF,

    Form 2

    SICF, Form 2 Pressure Test Result.

    5 OIL TANK 5-1 Cleaning 1 RP/IC The cleanliness of the oil sump tank is verified during FAT in

    workshop.

    However the tank may be inspected at site by removing the

    inspection hatch and visually check inside prior to oil filling.

    5-2 Oil type 1 RP/IC Recommended oil for operation of the OPS and flushing shall

    be hydraulic oil according to ISO-VG 46.

    5-3 Oil filling 1 RP/IC Filling the oil tank shall be done in accordance with the

    governor O&M manual.

    New oil will be filled through a filtration unit. It is assumed that

    no samples for cleanliness documentation should be regarded as

    necessary.

    The mobile filtration unit shall be used when filling all units.

    6 ELECTRONIC

    AND CONTROL

    CUBICLES

    6-1 Installation 1 RP/IC The governor electronic cubicle is located together with the

    panels for unit local control and shall be installed according to

    drawing.

    The control cubicle is installed according to drawing.

    7 CABLING 7-1 Installation and

    test

    1 RP/IC

    Cabling and labels shall in principle be installed according the

    relevant wiring diagrams.

    Ensure that all connections are properly connected to the

    terminals in the cabinets.

    Crimping sleeves shall be adapted to all cables.

    Cable check shall be done by hook-up in the wiring/cable

    diagrams and verified in SICF, Form 3.

    SICF, Form 3 Verification of cabling

  • QUALITY INSPECTION PLAN GOVERNOR

    Dok. nr. / Doc. No.

    ARA000273-PRI

    Rev.

    0

    Side / Page

    1 av / of

    5 Sign. dato / Date

    Retten til utnyttelse av denne beskrivelse tilhrer Rainpower ASA og m ikke kopieres, utleveres eller forelegges uvedkommende uten tillatelse fra Rainpower. This document and the design is the property of Rainpower ASA and must not be used nor disclosed to any part without Rainpowers permission.

    Ordre nr. / Order No.

    400409 Kunde / Customer

    SN Power Prosj. dok. nr. / Proj. Doc. No.

    RP-Q-N-I-P-001 Indeks / Index

    R010 Anlegg / Site

    Cheves Filnavn / File Name

    ARA000273-PRI Rainpower and Rainpowers customer shall be able to inspect all stages in the process at supplier and sub-suppliers. These inspections might happen any time at any location. All NDT shall be reported, also indications that has been repaired.

    0 05.01.12 First Issue TFa Rev. Dato / Date Beskrivelse / Description Sign. Avd. / Dept. Godkj. / Appr.

  • QUALITY INSPECTION PLAN

    1 2 3 4 5 6 7 8 9 10 11

    Index Name, drwg. No. & item No. Production stage Inspection Procedure Location

    Respons-ible Witness

    Report form RC Remarks

    R010 Governor Assembled FINAL Commissioning procedure SITE RP CLIENT PROT x Drytest on site.

    R490 GOPS 600 Hydraulic controls

    Assembled VI FUNCT PRESSURE

    FAT Report SUPL RP CLIENT PROT x Assembled test. FAT

    R450 Accumulators Assembled VI FUNCT PRESSURE

    FAT Report SUPL RP CLIENT PROT x Assembled test. FAT

    R620 Electronic governor HY14P Assembled VI FUNCT FAT Report SUPL RP CLIENT PROT x

    Assembled test FAT

    R670 Overspeed trip device Assembled VI FUNCT FAT Report SUPL RP CLIENT PROT x

    Calibrated before test at site.

  • 3 of 5

    Enclosure to document no. ARA000273-PRI The enclosure gives guidelines for filling in as well as explanations for use of the inspection plan. The paragraph numbers refer to column number. 1 INDEX Numbering of inspection activity and/or item designation according to Rainpower project index list. 2 NAME, DRAWING AND ITEM NO. The name of the part or the parts. Drawing and item number has to be specified when it is suitable to identify the part or parts 3 PRODUCTION STAGE E.g., designed, welded, machined. 4 INSPECTION Inspection or testing to be performed. The following abbreviations are used: CA = Chemical analysis

    MAT = Material test

    TT = Tensile testing

    CIT = Charpy impact test

    HT = Heat treatment

    BT = Bend test

    CR = Contract review

    PQR = Welding procedures qualification

    WPS = Welding procedure

    WELDER = Qualification of welders

    NDT-OP = Qualification of NDT inspectors

    CALC = Checking and approval of calculations

    RESSTR = Residual stress analysis

    DRAW = Checking and approval of drawings and specifications

    PURCH = Review of purchase orders

    RECEIPT = Receiving inspection

    CERT = Certificate check

    VI = Visual inspection

    NDT = Extent of non-destructive testing

    ACCEPT = Acceptance criteria

    UT = Ultrasonic testing

  • RT = Radiographic testing

    MT = Magnetic particle testing

    PT = Penetrant testing

    HB = Hardness test

    DT = Dimension and form control

    BAL = Balancing

    PRESSURE = Pressure testing

    LEAKAGE = Tightness inspection

    FUNCT = Function testing

    FINAL = Final testing

    5 PROCEDURE Reference to the document which describes the inspection or testing procedure. 6 LOCATION Location for the inspection or test. MS = Machine shop

    SFS = Steel fabrication shop

    SUPPL = Supplier's workshop

    SITE = Erection site

    STOCK = Warehouse department

    7 RESPONSIBILITY The letter designation, possible group number for the organization unit, who is responsible for the inspection or test performance. SUPPL = Suppliers workshop

    RP = Rainpower

    BUYER = The customer

    8 WITNESSING Representation, if any, by a party other than he who performs the inspection test. Internal party is given by the letter designation, external as follows: RP = Rainpower

    CONS = Consultant or classification society

    CLIENT = The customers representative

    _____ = Hold point, i.e. the process must not proceed until passed by the witness

  • as indicated by underlining.

    9 REPORT FORM Reference to form numbers. PROCESS = Signature in Process Description

    PROT = Inspection record

    10 REPORT TO BUYER Cross for reports to be forwarded to the buyer.

  • Performed

    Witnessed

    Approved

    Approved

    01_Form 1 _ Cleaning pipes

    Site Installation Control Form Ordre Nr. /Order No

    221304 Indeks/Index

    R010/K010 Kunde/Customer

    SN Power Rapport nr./report no.

    Form 1 Byggested/Fab. site

    Sak/subject

    Cheves HEPP Uni 1 and 2

    Side /Page av / of

    1 1 Tegn. nr. /Drwg. No.

    Dato / Date Sign

    Pos. nr /Part No

    MIV and Governor during installation

    Del / Part

    Survey of pipe cleaning with plastic bullets and oil

    Unit No.

    Cleaning with plastic bullets PIPE LINE

    CLEANING RESULT

    Other pipe lines No. 1 (to be determined at site)

    Other pipe lines No. 2 (to be determined at site)

    Other pipe lines No. 3 (to be determined at site)

    Other pipe lines No. 4 (to be determined at site)

    Flushing with oil LOOP SERVOMOTORS

    RESULT CLEANLINESS TEMPERATURE LEVEL

    Servo 1

    Servo 2

    Other pipe lines (to be determined at site)

    Other pipe lines (to be determined at site)

    Acceptance criteria:

    Cleanliness level

    NAS 1638 class 7

    Temperature for VG 64 oil

    60 65

    Velocity

    6 m/s

    Pump capacity (6 m/s and internal pipe dia. 8mm)

    300 l/min

  • Performed

    Witnessed

    Approved

    Approved

    02_Form 2 _ Pressure test pipes

    Site Installation Control Form Ordre Nr. /Order No

    221304 Indeks/Index

    R010/K010 Kunde/Customer

    SN Power Rapport nr./report no.

    Form 2 Byggested/Fab. site

    Sak/subject

    Cheves HEPP Unit 1 and 2

    Side /Page av / of

    1 1 Tegn. nr. /Drwg. No.

    Dato / Date Sign

    Pos. nr /Part No

    MIV and Governor during installation

    Del / Part

    Pressure tests of misc. pipe lines

    Unit No.

    Pressure tests of miscellaneous pipe lines

    PIPE LINE

    PRESSURE (bar)

    Other pipe lines No. 1 (to be determined at site)

    Other pipe lines No. 2 (to be determined at site)

    Other pipe lines No. 3 (to be determined at site)

    Other pipe lines No. 4 (to be determined at site)

    Acceptance criteria:

    Test pressure

    bar

    Holding time

    min

    Medium Water

  • Performed

    Witnessed

    Approved

    Approved

    03_Form 3 _ Survey of cabling

    Site Installation Control Form Ordre Nr. /Order No

    221304 Indeks/Index

    K500 Kunde/Customer

    SN Power Rapport nr./report no.

    Form 3 Byggested/Fab. site

    Sak/subject

    Cheves HEPP Unit 1 and 2

    Side /Page av / of

    1 1 Tegn. nr. /Drwg. No.

    Dato / Date Sign

    Pos. nr /Part No

    MIV and Governor during installation

    Del / Part

    Survey of cabling

    Unit No.

    Survey of cabling

    WIRING DIAGRAM

    RESULT

    Wiring Diagram SSG

    Wiring Diagram Turbine and MIV Equipment

    Wiring Diagram OPS

    Wiring Diagram Governor