roosevelt hs community meeting presentation (june 18, 2015

11
Roosevelt High School ModernizaƟon COMMUNITY MEETING JUNE 2015

Upload: dc-department-of-general-services

Post on 28-Jul-2015

344 views

Category:

News & Politics


4 download

TRANSCRIPT

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

PROGRAM SUMMARYTOTAL SIZE: 331,000 SF

TEACHING SPACES: 62• 25 CORE CLASSROOMS• 7 SCIENCE CLASSROOMS/LABS• 3 TECHNOLOGY LABS• 10 SPECIAL EDUCATION• 2 ART CLASSROOMS• 2 MUSIC CLASSROOMS• GYMNASIUM• DANCE STUDIO• FITNESS/WEIGHT ROOM• HEALTH CLASSROOM• 2 JROTC CLASSROOMS• 3 CAREER TECHNOLOGY LABS• COSMETOLOGY LAB AND CLASSROOM• CULINARY LAB AND DINING ROOM

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

REOPENING 13TH STREET ENTRANCEAFTER 25 YEARS

RESTORING CUPOLA TO 1930’S DETAIL

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

NEW PAVILION ENTRANCEFOR STAY AND ATHLETICS

NEW AMPHITHEATER AT EAST PLAZA

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

ATRIUM, HEART OF THE SCHOOL

ELECTROCHROMIC GLAZING

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

GYM, THE MILK HOUSE

BLEACHERS EXPANDED TO SEAT 1,000

HOME OF THE ROUGH RIDERS

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

WATERWORKS COURTYARDREOPENED AFTER 1970’S INFILL ADDITION

SERVES AS TEACHING TOOL FOR STORM WATER

MANAGEMENT. RAIN IS COLLECTED FROM

ROOF AND STORED IN 3 CISTERNS, WITH A TOTAL

CAPACITY OF 55,000 GALLONS, FOR FLUSHING

TOILETS.

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

TYPICAL CLASSROOMS

ART CLASSROOM

COSMETOLOGY CLASSROOM

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

GALLERY, HEART OF THE ARTS WINGSKYLIGHTS AND WINDOWS BRING LIGHT TO 1970’S ADDITION

BAND CLASSROOM

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

SITE WORK ALONG 13TH STREET

ARTS WING

NEW BUS DROP-OFF

NEW STORM WATER UTILITY TIE-INS

NEW ACCESSIBLE PATH

BIORENTIONGARDENS

AUDITORIUMWING

ACADEMIC WING

ATHLETICWING

Roosevelt High School Moderniza onCOMMUNITY MEETING

JUNE 2015

NEXT STEPSRoosevelt Summer Schedule• Con nue with construc on.

Summer Sweep of MacFarland • Bathroom improvements, support sewer concerns.• Support the rodent control eff orts

Monthly construc on updates throughout the summer• Progress photos will be posted on the DGS website • Hard copies will be available at Main Offi ce at MacFarland • Reconvene SIT in the fall through construc on comple on

DGS Contact Darrell Pressley [email protected] 202-997-9017