rochester station project db contract documents part ... · rochester station project part 3‐2...

216
Rochester Station Project DH34463 DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS July 18, 2013

Upload: others

Post on 08-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

 

 

 

 

 

 

 

Rochester Station Project 

 

DH34463 

DB CONTRACT DOCUMENTS 

PART 3 

 

PROJECT REQUIREMENTS 

 

July 18, 2013 

Page 2: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

New York State Department of Transportation 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This page is intentionally blank.

Page 3: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

New York State Department of Transportation 

 

 

SECTON 1.  RAILROAD PROPERTY ACCESS REQUIREMENTS .................................................................... 1 1.1  Access Requirements onto Amtrak Property .................................................................................... 1 

1.2  Access Requirements for CSXT Property .......................................................................................... 1 

SECTION 2  ENVIRONMENTAL COMPLIANCE ........................................................................................... 1 2.1   Scope ................................................................................................................................................. 2 

2.2   Compliance with Approved NEPA Action ......................................................................................... 2 

2.3   Environmental Requirements ........................................................................................................... 2 

SECTION 3.  COMMUNITY OUTREACH REQUIREMENTS ........................................................................... 5 SECTION 4  BASIS OF PAYMENT REQUIREMENTS .................................................................................. 76 4.1  CPM Schedule Submittals ................................................................................................................. 7 

4.2  Milestones for Item 800.0600012 Design Build Construction Work ................................................ 8 

4.3  Milestone Progress Payments ........................................................................................................... 9 

4.4  CPM Schedule Requirements ............................................................................................................ 9 

4.5  CPM Schedule Updates and Revisions ............................................................................................ 10 

4.6  Extra Work ...................................................................................................................................... 11 

4.7  Four Week Look Ahead Schedule ................................................................................................... 12 

SECTON 5.  SITE REQUIREMENTS ........................................................................................................... 12 5.1  General Site Requirements ............................................................................................................. 12 

5.2  Codes and Standards ...................................................................................................................... 13 

5.3  Foundation ...................................................................................................................................... 13 

5.4  Structures ........................................................................................................................................ 13 

5.5  Utilities ............................................................................................................................................ 14 

5.6  Design Loading and Loading Combinations .................................................................................... 16 

5.7  Materials ......................................................................................................................................... 16 

5.8  Site Layout and Circulation ............................................................................................................. 16 

5.9  Other Site Components................................................................................................................... 18 

SECTION 6.  GEOTECHNICAL REQUIREMENTS ........................................................................................ 18 6.1  Standards and References .............................................................................................................. 19 

6.2  Personnel Qualification Requirements ........................................................................................... 20 

6.3  Design Requirements ...................................................................................................................... 22 

6.9  Geotechnical Instrumentation and Construction Monitoring Plan ................................................ 25 

6.10  Foundation Design Report .............................................................................................................. 28 

6.6  Construction Requirements ............................................................................................................ 37 

SECTION 7.  TEMPORARY FACILITY REQUIREMENTS .............................................................................. 58 SECTION 8.   TRACK AND PLATFORM REQUIREMENTS ............................................................................ 59 

Page 4: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

New York State Department of Transportation 

 

 

8.1   Track Requirements ....................................................................................................................... 59 

8.2   High Level Platform Requirements ................................................................................................ 60 

8.3   Bridge Modification Requirements ................................................................................................ 60 

SECTION 9  ARCHITECTURAL REQUIREMENTS ....................................................................................... 63 9.1  Code Requirements and Design Standards ..................................................................................... 63 

9.2  Description of Proposed Facility ..................................................................................................... 64 

9.3  Façade Elements ............................................................................................................................. 65 

9.4  Station Ground Level....................................................................................................................... 65 

9.5  Station Concourse Level .................................................................................................................. 68 

9.6  Space Allocation .............................................................................................................................. 69 

9.7‐ Information Systems ............................................................................................................................ 75 

9.8  Finishes and Materials .................................................................................................................... 76 

9.9  Public Art Installations .................................................................................................................... 77 

9.10  Historic Canopy and SHPO Coordination ........................................................................................ 77 

SECTION 10.  VERTICAL CIRCULATION REQUIREMENTS ........................................................................... 78 10.1  Pedestrian Concourse ..................................................................................................................... 79 

10.2  Baggage Ramps ............................................................................................................................... 79 

SECTION 11.   SUSTAINABILITY REQUIREMENTS ....................................................................................... 79 11.1  Sustainable Strategies ..................................................................................................................... 80 

11.2  Energy Consumption ....................................................................................................................... 82 

11.3  Life Cycle Analysis ........................................................................................................................... 82 

11.4  Material Selection ........................................................................................................................... 82 

11.5  Commissioning ................................................................................................................................ 82 

11.6  Documentation ............................................................................................................................... 83 

SECTION 12.MECHANICAL REQUIREMENTS ............................................................................................... 84 12.1  General ............................................................................................................................................ 84 

12.2  Codes and Standards ...................................................................................................................... 85 

12.3  Vibration Isolation / Seismic Design ............................................................................................... 85 

12.4  Mechanical Identification ............................................................................................................... 86 

12.5  HVAC SYSTEMS ................................................................................................................................ 86 

12.6  PLUMBING SYSTEMS ....................................................................................................................... 91 

12.7  Fire Protection ................................................................................................................................ 97 

SECTION 13.  ELECTRICAL REQUIREMENTS ............................................................................................... 98 13.1  General Requirements .................................................................................................................... 98 

SECTION 14.  COMMUNICATIONS REQUIREMENTS ............................................................................... 178 

Page 5: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

New York State Department of Transportation 

 

 

SECTION 15. FACILITY PARKING AND TRAFFIC REQUIREMENTS ............................................................... 210 15.1  Parking .............................................................................................................................. 210 15.2  Pay Stations ................................................................................................................................... 210 

15.3  Bus Access ..................................................................................................................................... 210 

15.4  Accommodations for Bicylists ....................................................................................................... 211 

SECTION 16. FRA TIGER Grant Submittal Requirements .......................................................................... 211   

Page 6: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐1 

Part 3 Project RequirementsJuly 18, 2013

 

 

SECTON 1. RAILROAD PROPERTY ACCESS REQUIREMENTS 

The Design Builder must adhere to the railroad property access requirements while working on property under the control of either Amtrak or CSXT. 

1.1  Access Requirements onto Amtrak Property 

A. The Design Builder is required to obtain a Temporary Permit to Enter (TPE) from Amtrak.  

B. All field personnel must attend Amtrak contractor safety/security training 

a. Available Online: http://www.amtrakcontractor.com  

C. The Design Builder  is  required  to  submit  an overall  Site  Specific Work Plan and Hazard Analysis (SSWP/Hazard) Form to Amtrak Engineering for review and approval.  

D. Temporary  fencing  and  barricades  of work  zones  is  required.    All  fencing must  be  approved  by Amtrak. 

E. Station  operations  and  areas must  remain  open  for  its  normal  operations.    Temporary  station operations staging shall be reviewed and approved by Amtrak. 

F. Mandatory Personal Protective Equipment (PPE) for all workers worn at all times including:  

a. Hard Hat, High  visibility Orange  Safety  Vest with  reflective  striping  (vest must  be  break‐away), Safety Glasses or goggles, Work boots, Hearing protection and Visible Safety Trained ID card.   

G. The Design Builder shall provide to Amtrak Engineering the following: 

a. 2 week minimum look ahead schedule of planned work activities, updated weekly. 

b. Specific work plans for safe operations prior to work activities being progressed.  

c. The Design Builder  shall  create perform a written daily  Job Safety Briefing with all  crafts, workers, and anyone  involved on the project prior to any work beginning the briefing shall include  all  tasks  and  be  updated  as major  changes  in work  occur,  the  briefing  shall  be performed by the Employee in charge who shall keep the briefing in his/her possession and presented to Amtrak or FRA officials if requested. 

H. Amtrak Engineering will provide Station Operation Coordination and Inspection services as it relates to Amtrak’s interests.  

1.2  Access Requirements for CSXCSXT Property 

A. CSXCSXT Railroad is responsible for all flagging operations and separate coordination by the Design Build with CSXCSXT is required.  

B. All field personnel must attend CSXCSXT contractor safety/security training, which is different from the Amtrak training.  

B.C. The    Department  will  enter  into  a  separate  agreement  with  CSXT  to  provide  flagging  for  the construction of this project. 

SECTION 2  ENVIRONMENTAL COMPLIANCE 

Page 7: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐2 

Part 3 Project RequirementsJuly 18, 2013

 

 

2.1   Scope 

An  essential  component  of  the  Project  is  the  comprehensive  integration  of  environmental compliance into all design and construction activities by the Design‐Builder. Except as otherwise detailed herein, the Design‐Builder shall be responsible for preparing its design, carrying out its construction activities and undertaking other activities as needed  to ensure  compliance with the  Project’s  Environmental  documentation  and  all  applicable  environmental  laws  and regulations.  This Project Requirement identifies certain required actions by the Design‐Builder to  ensure  that  the  Environmental  Requirements  are  complied with  throughout  the  Project activities. 

2.2   Compliance with Approved NEPA Action 

NEPA environmental approval for the subject project has been granted based on analysis and documentation of potential environmental impacts of the identified preferred alternative. This analysis  is summarized along with any  identified environmental commitments and depicted  in the May 2013 Federal Railroad Administration  (FRA) Categorical Exclusion Worksheet  for  the subject  project.  If  during  detailed  design  and/or  construction  the  Design‐Builder  introduces design elements, variations, or methodologies  that potentially  induce environmental  impacts that differ from those  identified  in the approved Categorical Exclusion Worksheet or  is unable to comply with established environmental commitments then the NEPA process for this project will need  to be  re‐evaluated by  the Design‐Builder and  reviewed by  the Department prior  to proceeding with construction. This requirement also applies to proposed variations which may affect resources covered under Section 106, Section 4(f), and other applicable federal and state environmental regulations. The need to re‐evaluate the NEPA process may  impact the overall project schedule. 

2.3   Environmental Requirements 

2.3.1   General 

A) Unless otherwise  indicated  in the Contract Documents, the Department will be responsible for obtaining all Environmental Approvals as identified in this Section. In the event the Design‐Builder requests changes to the permits obtained by the Department, the Design‐ Builder shall be responsible for the preparation of all information including materials, investigations, testing and documentation, as necessary  to  support  said permit modification  request. Based on  the Design‐Builder’s provision of  said  information,  the Department will undertake  the  requested permit modification with the respective permitting agencies on the Design‐Builder’s behalf. The Department will not be responsible for any delay or additional cost associated with the Design‐Builder’s requested permit modification; 

B) The Design‐Builder shall procure all Environmental Approvals as needed for all Design‐ Builder located areas, including staging, borrow and disposal sites, and any other areas used by the Design‐Builder, for its convenience, in the construction of the Project; 

Page 8: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐3 

Part 3 Project RequirementsJuly 18, 2013

 

 

C) The Design‐Builder shall be responsible for obtaining all new Environmental Approvals. For any such approvals  required  to  be  obtained  by  the  Design‐Builder  that  must  formally  be  issued  in  the Department's name, the Department will cooperate with the Design‐Builder as reasonably requested by the  Design‐Builder,  including  execution  and  delivery  of  appropriate  applications  and  other documentation prepared by Design‐Builder in a format approved by the Department; 

D) The Design‐Builder shall be solely responsible for violations of any Environmental Requirements; 

E) The Design‐Builder shall indemnify the Department and the State of New York for any fines, violations or damages incurred by reason of failure of the Design‐Builder to comply with Environmental Approvals. 

2.3.2   Environmental Plans 

The Design‐Builder  shall be  responsible  for preparing  the  following documents  in  conformity with all Environmental applicable standards, regulations, permits and requirements.   For each documents  listed, the Design‐Builder shall  identify the frequency of submission of compliance reports to the Department. 

A) Health and safety plan (HASP); 

B)A) Soil  Erosion  and  Sediment  Control  Plan  complying  with  the  New  York  State  SPDES General Permit  for Stormwater Discharges  from Construction Activities  (GP‐0‐10‐001) This plan is to include but is not limited construction entrance(s), construction phasing, drawings showing  size  and  location  of  permanent  (seeding,  pavement)  and  temporary  (silt  fence, temporary seed) erosion controls, and details. 

C)B) Stormwater pollution prevention plan (SWPPP) 

D)C) Contaminated Soil Sampling and Analysis Plan  (for areas of excavation  in  the  railroad bed) 

E)D) Based on the results of the Contaminated Soil Sampling and Analysis Plan the following plans may be required (see NYSDOT Standard Specification  Section 205): 

• Contaminated Material Handling Plan (CMHP) 

• Field Organic Vapor Monitoring Plan (FOVMP) 

• Disposal Plan 

2.3.3   Environmental Plan Deliverables 

At  a minimum,  the  deliverables  shall  include  the  items  listed  in  Table  2‐1  –  Environmental Compliance Deliverables, for the Department’s review. Each of the deliverables  listed  in Table 2‐1  ‐  Environmental  Compliance  Deliverables,  shall  be  provided  to  the  Department  by  the earlier of: (i) 30 days after NTP; and (ii) 30 days prior to the relevant on site activity,  including start of construction. 

Page 9: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐4 

Part 3 Project RequirementsJuly 18, 2013

 

 

 

Table 2‐1 – Environmental Compliance Deliverables 

Deliverable  Number of Copies 

Hardcopy  Electronic 

Health and safety plan  1  1 

Stormwater pollution prevention plan & NOI  1  1 

Soil Erosion and Sediment Control Plan  1  1 

Contaminated Soil Sampling and Analysis Plan  1  1 

2.3.4   Soil Erosion and Sediment Control 

The Design‐Builder shall provide the department with a SWPPP and Notice of Intent complying with  the New York State SPDES General Permit  for Stormwater Discharges  from Construction Activities  (GP‐0‐10‐001)  60  days  prior  to  any  ground  disturbance  for  the  Department’s signature.    The  Department  will  apply  for  coverage  under  the  SPDES  General  Permit  for Stormwater  Discharges  from  Construction  Activities.  The  Design‐Builder  shall  review  final SWPPP and sign/complete Contractor/Subcontractor SPDES Permit Certification form (CONR 5). Discharges  covered  under  the  SPDES  general  permit  shall  not  commence  until  the  date authorized on the SPDES Acknowledgement Letter. 

2.3.5   Performance 

The Design‐Builder  shall perform of  all  activities  required under each of  the  foregoing plans until final acceptance of the Project, except to the extent that the plans provide for activities to be undertaken by the Department or third parties. Provisions  in said plans for activities to be undertaken by  the Department  or  third  parties  are  subject  to  prior written  approval  by  the Department. 

2.3.6   Environmental Approvals and Identified Permits 

All environmental design approvals for this project shall be acquired prior to construction.  The following is an initial list of permits that have been identified as necessary for this project: 

A) SPDES General Permit for Stormwater Discharges from Construction Activities 

B) NYSDEC Waste transporter permit. 

The Design Builder is responsible for identifying and acquiring all necessary permits required to complete the proposed Work including permits not identified in this list. 

Page 10: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐5 

Part 3 Project RequirementsJuly 18, 2013

 

 

2.3.7   Asbestos Containing Materials (ACMs) 

Based  on  laboratory  analyses  of  bulk  samples  collected,  ACMs  are  present  in  the  existing Station. 

2.3.8   Inaccessible/Assumed ACMs 

Inaccessible/Assumed ACMs were found within the former passenger tunnel as ceiling plaster, 9”  x  9”  floor  tile  and mastic  and  thermal  pipe  insulation.    Refer  to  ”Hazardous Materials Investigations”  found  on  the  project    website:  https://www.dot.ny.gov/main/business‐center/designbuildproject  for a  list of  inspections and samplings performed  to determine  the presence of asbestos‐containing materials  (ACM). The Design‐Builder  shall be  responsible  for the  identification,  removal  and  disposal  of  all  asbestos  containing  materials  (ACMs) encountered in the inaccessible areas if such areas will be disturbed during the performance of the Work.  The  removal  and  disposal  of  ACMs  shall  be  performed  in  accordance  with  the Contract Documents and the applicable safety and health codes. 

The Design‐Builder shall be responsible for providing any necessary asbestos inspection, project design  and  abatement project/air monitoring  services  as part  of  this  contract  in  accordance with 12 NYCRR 56. NYSDOL asbestos licensure and applicable staff certification(s) are required for structure rehabilitation work where confirmed or presumed asbestos‐containing materials are  impacted.    All  necessary  asbestos  inspection,  project  design  and  project/air monitoring work  shall be  conducted  in  conformance with policy and guidance provided  in NYSDOT TEM Section 4.4.19 ‐ Asbestos Management. 

2.3.9   Hazardous Waste/Contaminated Soils 

A Contaminated Soil Sampling and Analysis plan shall be completed for all proposed excavation areas within  the  railroad bed.   The Design‐Builder  shall be  responsible  for  the  identification, removal and disposal of all hazardous waste or contaminated  soil encountered. The  removal and disposal of Hazardous Waste or Contaminated soils shall be performed in accordance with the Contract Documents and the applicable regulations.   

A Contaminated Soil Sampling and Analysis plan for the station area has been completed. Refer to ”Hazardous Materials Investigations” found on the project  website: 

https://www.dot.ny.gov/main/business‐center/DesignBuildProject 

SECTION 3.  COMMUNITY OUTREACH REQUIREMENTS 

Outreach has been and will be critical to obtain the full support of all project stakeholders and the community.   The Design‐Builder shall provide support to the Department  inclusive of, but not limited to, the following groups. 

A. Rochester Station Executive Steering Committee NYSDOT  has  formed  an  Executive  Steering  Committee  to  guide  the  design  of  Rochester Station  as  it  progresses.   Mayor  Tom  Richards  of  the  City  of  Rochester,  United  States 

Page 11: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐6 

Part 3 Project RequirementsJuly 18, 2013

 

 

Congresswoman Louise Slaughter, and Commissioner Joan McDonald of the New York State Department of Transportation comprise the Committee, along with technical advisory from representatives of Amtrak, Trailways of New York, and Parsons Brinckerhoff. The  Design‐Builder  shall  aide  NYSDOT  to  keep  the  Committee  up  to  date  on  the development of  the design  and  construction by making presentations  to  the Committee.  The Design‐Builder  shall  respond  to  comments  and  incorporate  input  and  guidance  from Committee members. 

B. Council for Persons with Disabilities The Council  for Persons with Disabilities  is an advisory council  to  the County Executive of Monroe County and to the Mayor of the City of Rochester.  The Council has provided input and  guidance  developing  a  preliminary  design  that  fulfills  the  needs  of  persons  with disabilities in Rochester and Monroe County as they utilize Rochester Station.  The Design‐Builder  shall  be  required  to  meet  with  and  present  to  the  Council  as  the  design  and construction progresses. 

C. Rochester Cycling Alliance The Rochester Cycling Alliance is a cycling advocacy group focused on promoting cycling in Rochester,  development  of  cycling  roads  and  trails,  and  distributing  information  about safety and cycling in general. The Design‐Builder shall assist the Department as needed  in presenting the final design to the Rochester Cycling Alliance for their input. 

D. Reconnect Rochester Reconnect  Rochester  is  a  transit  advocacy  group  focused  on  promoting  mobility  and physical connections between downtown Rochester and the surrounding neighborhoods. The Design‐Builder shall assist the Department as needed  in presenting the final design to Reconnect Rochester for their input. 

E. Other Groups The  Design‐Builder  shall  provide  support  to  the  Department  and  the  Executive  Steering Committee to meet with community groups such as: 

a. The City of Rochester a.b. Area universities,  b.c. RGRTA,  c.d. High Falls Business Improvement District,  d.e. Rochester Downtown Development Corporation e.f. Monroe County Department of Transportation g. Empire State Passenger Association f.h. The  City  of  Rochester’s  Public  Art  Committee  and  the  Rochester  Arts  and  Cultural 

Commission  to assist NYSDOT  in defining,  judging,  soliciting Artists, and commissioning of Public Art pieces to be installed on the project site. 

Page 12: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐7 

Part 3 Project RequirementsJuly 18, 2013

 

 

SECTION 4  BASIS OF PAYMENT REQUIREMENTS 

The scheduling    of    submittals,    procurement    and    construction    is   the responsibility of the Design Builder.  Progress payments shall be subject to the requirements of DB §109‐2.  All Work, including Phase II, if included in the contract,  shall  be  monitored  by  a  detailed  Critical  Path  Method  Schedule "CPM  Schedule".   The Design Builder shall submit the CPM Schedule to NYSDOT’s Project Manager for approval.  The CPM Schedule shall meet the requirements of DB §108 and Part 2‐ Appendix 1.     The approved CPM Schedule  is used  to assist NYSDOT    in  appraising  the  reasonableness  of  the  proposed  schedule,  as  well  as,  its  compliance  with  Contract    requirements.        This    approved  CPM    Schedule    shall    be    the    basis    for    the  evaluation    of   Design  Builder    performance    and    approval  of  Progress  Payments  for  Item 800.0600012 Design Build Construction Work.     Progress Payments will be made according to the approved CPM  schedule as each Milestone  is  completed  to  the  satisfaction of NYSDOT’s Project Manager.   

The    CPM    Schedule    is    the    Design  Builder's    committed    plan    to    complete    all   Work  (including  punch  list  items)  within  the  allotted  time.  The  CPM  Schedule  shall  be  based  on  and  derived  from  detailed  schedules  used  to  monitor all Contract activities.  

4.1 CPM Schedule Submittals 

A. Preliminary   Schedule:       No    later   than   14   calendar   days   after   Notice to Proceed,   the  Design Builder  shall  submit  the Preliminary Schedule for NYSDOT review and approval of the  Design Builder's  planned  activities  during the first 90 calendar days.  The Preliminary Schedule shall  indicate  the cost of activities and milestones expected  to be completed or partially completed before submission and approval of the complete CPM Schedule.  

B. CPM Baseline Schedule:  No later than 30 calendar days after Award of Contract, the Design Builder shall submit CPM Schedule depicting the Design Builder's Work plan for the entire Contract.  The Design Builder shall submit to the NYSDOT’s Project Manager for review and approval the following: 

1. Logic Diagram:   A detailed CPM Time‐Scaled Network Logic Diagram. 

2. Cost Loaded CPM  for  Item 800.0600012 Design Build Construction Work.     The Design Builder will create a proposed  list of Milestones  including Manadatory Milestones and the percentage of  the  total price bid  for  Item 800.0600012 Design Build Construction Work  associated with  each Milestone.      The  Design  Builder may  propose  to  include Milestones  in addition  to  the mandatory Milestones.   The Department will  review  the Design  Builder’s  proposed  Milestones  and  Associated  Progress  Payments  for reasonableness prior to approval.  These approved Milestones and Associated Progress Payments  for  Item 800.0600012 Design Build Construction Work are  the basis  for  the Design Builder’s Cost  Loaded CPM Schedule.     Any  revisions and modifications  to  the approved CPM Schedule must be approved by NYSDOT’s Project Manager in writing. 

3. Cost  Report:   A  Cost  Report  generated  from  the  cost  loaded  CPM  Schedule  is  to  be submitted 14 calendar days after approval of the   Line Item Breakdown,  in accordance with Paragraph F.(3).  

Page 13: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐8 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. Narrative:  A written narrative explaining the schedule and the Design Builder's general approach for meeting interim and completion milestone dates.  

4.2 Milestones for Item 800.0600012 Design Build Construction Work 

A. The  Design  Builder  shall  include  the  following  mandatory  Milestone  and  required Completions in the CPM Schedule: 

Activity ID 

Activity Description  Follows  Logic 

Tie  Duration  Responsible Party 

Progress Payment Structure

P0010 Submission of Health and Safety Plan 

  FS 2 months from the Notice To 

Proceed 

Design Builder 

 

Proposed by Design 

Builder/Approved by NYSDOT 

 

P0020 

Temporary Facility, Site 

Work, Demolition of the existing Building and 

appurtenances. 

P0001P0010 FS 

Proposed by Design 

Builder/Approved by NYSDOT 

 

P0030  Station Building  P0002P0020 FS 

P0040  Tunnel  P0003P0030 FS

P0050  Station Platform  P0004P0040 FS 

P0060  Platform Tracks  P0005P0050 FS 

P0070  Substantial Completion  P0006P0060 FS 

32 months from Notice To Proceed 

P0080 

Project Completion, in accordance with DB 109‐

11.3 

P0007P0070 FS 

36 months from the Notice To 

Proceed  

B. The Design Builder’s Preliminary, Baseline, and Monthly Update schedules shall incorporate the mandatory Milestone  Completion  Dates.    The  Department’s  approval  of  the  Design Builder’s  schedule(s),  in part, will be  subject  to  the Design Builder’s  compliance with  the Milestone Schedule.   

C. Failure    of    the    Design  Builder    to    submit    the    CPM    Preliminary,    Baseline, Update Schedules  and  any  required  revisions  thereto within  the  time  limits    stated,    shall    be  sufficient    cause    to   withhold    approval   of    the   Design Builder's    invoices  for progress payment(s)  until  such  delinquent  submittal  is made    and  accepted  by NYSDOT’s  Project Manager. 

Page 14: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐9 

Part 3 Project RequirementsJuly 18, 2013

 

 

4.3  Milestone Progress Payments 

The  Design Builder  shall  furnish  a  breakdown  of  the  total  price  bid for Item 800.0600012 Design  Build  Construction Work  by    assigning    dollar    values    to    each   milestone,   which  cumulatively  equals  the  total   amount.    Upon  approval  by  the  NYSDOT’s Project Manager,  the   percentages associated with each   milestone shall   be   used    in   the   Cost   Report   as   a  basis  for  determining  progress  payments.    The  Design Builder's  overhead  and  profit  shall  be  prorated  through  all  activities.   

4.4  CPM Schedule Requirements  

A. The   CPM   Schedule   shall    include   all   of   the   Design Builder's   submittals,   procurement  and   construction   work   activities   with   sufficient   detail   such   that all  interfaces with all direct and related parties to the Work are shown.  

1. The   Work   of    the   Design Builder,   Subcontractors,   Suppliers,   CSX, Amtrak   and   all  others  that  affect  progress  shall  be  shown  and  identified on the schedule by using Activity Codes.  

2. Procurement  activities  shall  be  shown,  including  submittal  and  approval      of      shop   drawings,   fabrication   and   delivery   of   the material.  

3. Interruption    of    service,    delivery    of    NYSDOT/Amtrak/CSX‐furnished equipment, project phasing and any other Technical Provision requirements shall be shown.  

B. The  CPM  Schedule  shall  contain  sufficient  construction  activities  to  represent  the Work, subject to the approval of the NYSDOT’s Project Manager.  

C. The  CPM  Schedule  shall  be  of  the  precedence  type.    Activity  precedence  relationships consistent with proper logic shall be shown with lag codes.  

D. Logic  and  activity  time  durations  shall  be  established  by  the  Design Builder  consistent    with       Contract       requirements       and       reflective       of       proper   coordination   between  trades.       Logic   shall   show   how   the   start   of   a   given   activity    is   dependent   on   the  completion   of   preceding   activities   and    its    completion  restricts  the  start of  following activities.  No activity shall have a duration greater than 30 calendar days.     

E. The start date of the CPM Schedule shall be the Notice to Proceed.  The completion  date  of  the  CPM  Schedule  shall  be  the  Contract  completion  date as specified in Part 1 Design Build Agreement, which shall be input as the "Project Must Finish No Later Than" date.  All intermediate milestones required in the Contract shall be shown in proper logical sequence and  input as "Start‐No‐ Earlier‐Than" or "Finish‐No‐Later‐Than" dates.   The Design Builder may add milestones with the approval of NYSDOT’s Project Manager.  

F. Activities shall be described such that the Work is readily identifiable for assessment of start and completion, as well as  intermediate status. Descriptions   shall   utilize   Activity   Codes  for   physical    locations    such   as   column  lines,  stations and elevations where possible  to define the Work.     Activity description of "start", "continue",   "completion",   "X%",   "Y%",  "Z%" or similar non‐specific descriptions will not be allowed.  

Page 15: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐10 

Part 3 Project RequirementsJuly 18, 2013

 

 

G. The CPM Schedule shall be calculated  in working days.   The working day to calendar date correlation  shall be based upon  the Design Builder's proposed work week with adequate allowance  for  weekends,  legal  holidays  and  any  special  requirements  of  the  Contract.  Durations for activities shall not be less than one work day.    Multiple shifts per day should be shown using multiple resources.  

H. Seasonal  weather  conditions  shall  be  considered  in  the  planning  and  scheduling  of  all  Work    influenced   by   high   or    low   ambient    temperatures    for    the   completion   of   all  Work   within    the    allotted   Contract    time.     Appropriate  allowances  shall be made  for anticipated time  losses, due to normal rain and snow conditions by statistically expanding the estimated  time durations  for weather  sensitive activities.   Additionally, allowance  for lower  productivity  during  bad  weather  periods  shall  be  made  by  increasing  activity   durations   by   an   appropriate   amount.      All   allowances   for anticipated time losses shall be stated in the baseline narrative.  

I. The review period shown in the Schedule for submittals shall conform with review periods stated in the Approved Project Quality Control Plan. 

J. Constraint     dates     are     permitted     only     on     Milestone     activities,     unless otherwise approved by NYSDOT’s Project Manager.  

K. All  activities  with the  exception  of  Work  start  and  end  nodes  shall  have  predecessors and  successors.    The  start  of  an  activity  shall  have  a  start‐to‐  start      or      finish‐to‐start   relationship   with   preceding   activities.      The  completion  of  an  activity  shall  have  a  finish‐to‐start  or  finish‐to‐finish  relationship  with  a  succeeding  activity.    Start‐to‐finish relationships are not acceptable.  

L. CPM   Schedules   which   have   been   resource   leveled   are   permissible  provided  the  effects  of  leveling  are  incorporated  in  the  schedule  using  "Start‐no‐Earlier Than" date constraint. 

4.5  CPM Schedule Updates and Revisions 

A. The   Design Builder    shall   update    the   CPM   Schedule   monthly,   whether   or   not    the  NYSDOT’s Project Manager   has   accepted   the   schedule,   to   reflect   actual   construction  progress.  The update shall include the historical record of actual start and  finish  dates  for  activities  in  progress,  or  completed,  percent  complete  based on a unit of measure and remaining duration based on the amount of  work days required to complete the activity.  

B. A monthly progress meeting  shall be held.   At  this meeting, attended by    the   NYSDOT’s Project Manager,   all   progress   during    the    calendar   month    shall   be   addressed   and  reviewed  for  incorporation  into  the  schedule  by  the  Design Builder.   Within  a  period  of  10  calendar  days  from  the  date  of  this  progress  meeting, the Design Builder shall submit  the  schedule update  to  the NYSDOT’s Project Manager   with    the    agreed   upon  changes  for approval.       The approved updated CPM schedule shall be    the   basis  for  the progress payment.  

C. A   CPM   Progress   Narrative   Report   shall be submitted   as  part   of   the   update   analysis shall include, but not be limited to:  

Page 16: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐11 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. Description of cost and schedule status.  

2. Discussion  of  current  and  anticipated  delaying  problem  areas  and  their  estimated impact.  

3. Schedule slippage and/or progress along the critical path  in terms   of   days   ahead   or  behind   the   allowable   dates,   and    if   the   Work    is   behind schedule, progress along other paths with negative float.  

4. Logic changes and an explanation of the  revisionsthe revisions.    Revisions  to  activities  not   worked   on   during   the   period,    including   changes    in   duration, or revisions to activity  relationships are  to be  considered    logic  revisions.   Out‐of‐sequence activities are  not  acceptable  and  shall  be  corrected  in  logic  revisions  prior  to  submission  to NYSDOT.  

D. When,  in  the  NYSDOT’s Project Manager's  opinion,  the  CPM  Schedule  fails  to  reflect  the   Design Builder's   actual   plan   and   method   of   operation,   or    the   Design Builder's  completion  date  as  indicated  by  the  CPM  is  more  than  1  month  behind  the  Contract  completion  date, NYSDOT’s Project Manager  may  require  the  Design Builder  to  submit for review within 2 weeks, a revised CPM Schedule for completion of the remaining Work within the Contract completion date.  

E. Bar Chart:  The length of the bar shall equal the Baseline Schedule.  Status shown should be based on the Update Schedules.  

F. When  it becomes apparent activities must be added  to  the CPM Schedule,  they must be added  in  a method  that  completion  dates  of  any  succeeding  baseline  activities  are  not affected.  All revisions must be submitted to NYSDOT’s Project Manager for approval before incorporation into the CPM Schedule.  

4.6  Extra Work   

To  insure  that  the  CPM  Schedule  shall  continue  to  accurately  reflect  the  Design Builder's  plan  for  the  Work  and  that  it  incorporates  the  impact  of  all  Extra  Work as soon as the Work scope can be defined, the following procedure shall be   followed   to    incorporate   Extra  Work  (including  deletions  of  Work)  in  the  Schedule.  

When   an   Extra   Work   proposal    is   submitted   by   the   Design Builder,   the   Design Builder  must  identify  in  a  CPM‐type  sketch,  additional  work  required  as  a  result  of  the  proposal and  its  interrelationship  to  the  CPM  Schedule.    This  sketch  shall  show  all    activities,    logic  revisions,   duration    changes,    and    associated    cost    changes    for   performing  the Work  in question.  Upon  NYSDOT’s Project Manager's approval of the sketch, the  Design Builder  shall  incorporate  the  revisions  into  the  Baseline  Schedule  and  the  Monthly Cost Report at the next  Schedule  update.    No  additional  compensation  will  be  paid  the  Design  Builder  for preparing these revisions.    Any request for Extension of Time must be verified by CPM Analysis and be in accordance with DB 108‐6 “EXTENSIONS OF CONTRACT TIME”.   

Page 17: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐12 

Part 3 Project RequirementsJuly 18, 2013

 

 

4.7  Four Week Look Ahead Schedule  

The  Design Builder  shall  provide  with  the  monthly  schedule  update,  or  more  frequently if required by NYSDOT, a Four Week Look Ahead Schedule to be used   for   coordination   of   the  Design Builder’s  work  with  Railroad  operation,  other  work  groups and at regular Progress Review Meetings.  

This  Four Week  Look  Ahead  Schedule  shall  contain  early  start  and  early  finish  dates  for  all activities scheduled or planned for start and/or completion in the upcoming 4 week period.  It shall include design, submittal, procurement and construction activities, as applicable. 

SECTON 5. SITE REQUIREMENTS 

5.1  General Site Requirements 

A. Prior  to  construction  activities,  the  Design  Builder  and  Department  representative  shall identify existing site  features to remain such as trees,  landscape, walks, etc; and establish protection measures to for duration of project. 

B. Develop phased erosion and sediment control plan meeting the guidelines of the New York Standards  and  Specifications  for  Erosion  and  Sediment  Controls;  maintain  erosion  and sediment  controls  through  duration  of  construction.    Provide  stabilized  entrances  to prevent mud  and  sediment  from  leaving  the  site,  regularly  sweep  and  sprinkle water  to avoid mud and dust concerns on local streets and neighboring properties. 

C. Provide  a  Storm Water  Pollution  Prevention  Plan  (SWPPP)  in  accordance  with  NYSDEC Standards and Design Guidelines. Site discharges to a combined sewer operated by Monroe County Pure Waters.     SWPPP  shall  include  temporary and permanent measures and will require review and approval by  local MS4 officerMonroe County Pure Waters and NYSDEC Department MS4 officer prior to construction.    Install stormwater measures  in accordance with approved SWPPP and Notice of Intent and Notice of Termination. 

D. Existing features in the work area; including buildings, walks, pavements, curbs, lighting and other  site  amenities  should  be  demolished  and  disposed  in  accordance  with  City ordinances,  obtain  needed  demolition  permits.  Coordinate  utility  disconnects with  each utility provider.   Clear site of  trash, debris, vegetation,  trees  (other  than  those which can remain), and any materials not incorporated in the project design; dispose of in accordance with City ordinances. 

E. Provide site security with a fence and lockable gates for all phases of construction.   F. Provide  safe,  reliable  ingress/egress,  traffic  circulation  and  pedestrian  circulation  for  all 

public  use  areas  including  temporary  and  permanent  station  and  amenities  through  all phases of construction. 

G. Provide parking  lots and site  roadways  in accordance with Amtrak Standard Program and Planning Standards and Guidelines.   

Page 18: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐13 

Part 3 Project RequirementsJuly 18, 2013

 

 

G.H. Based  on  geotechnical  report,  provide  a  pavement  design  for  parking  areas  in accordance  with  NYSDOT  pavement  design  guidelines.    For  all  pavements  that  will accommodate bus  traffic upon completion of any phase, provide a heavy duty pavement design  to accommodate  the  largest vehicles anticipated  for use by  the  local and  regional transportation providers. 

H.I. Provide  shelters  and  amenities  to  accommodate  taxi,  shuttle bus,  local bus  and  regional transportation service in accordance with Amtrak Standard Program and Planning Standards and Guidelines.   

I.J. Provide concrete walks and curbing in accordance with ADA Standards for Accessible design and Amtrak Standard Program and Planning Standards and Guidelines.   

J.K. Provide  bicycle  parking  in  accordance  with  Amtrak  Standard  Program  and  Planning Standards and Guidelines and City of Rochester Bicycle Master Plan. 

K.L. Provide a detailed Landscaping Plan prepared by a professional landscape designer architect in accordance with Amtrak Standard Program and Planning Standards and Guidelines; install landscaping components in accordance with approved plan.   

5.2  Codes and Standards 

A. New York State Building Code 2010 B. ACI 318‐08 “Building Code Requirements for Structural Concrete and Commentary” C. ACI 530 Building Code Requirements for Buildings D. AISC Manual of Steel Construction E. ASCE 7‐10 Minimum Design Loads for Buildings and Other Structures 

5.3  Foundation 

A. Geotechnical  report  and  available  soil  data will  be  given  in  an  addendum  as  it  becomes available. 

B. Building  foundation  recommendation  will  be  provided  in  the  Geotechnical  Report.  The Design‐Builder  may  design  the  foundations  using  the  existing  building’s  caissons. Information about the caissons will be available in the Geotechnical Report. 

C. Tunnel  and  platform  foundation  and  fill  recommendations  will  be  available  in  the Geotechnical Report. 

5.4  Structures 

A. Building  structure  shall  be  determined  and  designed  by  a  NYS  licensed  Professional Engineer.  Building structural system shall comply with all applicable codes and regulations even if not explicitly listed in this document. 

Page 19: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐14 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. Building structural system shall be designed to accommodate the architectural aesthetic as presented  in these documents and optimize the space as described  in the Amtrak Station Program and Planning – Standards and Guidelines.  

5.5  Utilities 

A. Provide  utility  service  for  temporary  station.    Facility  to  utilize  electric  heat.    Temporary station to utilize overhead wiring, electric and communication service to permanent station to be underground. 

B. Design Builder to provide the services of an underground utility locating service to find and map potential obstructions over entire site prior to construction. 

C. Water service – Provide new water mains appropriately sized for:  

a. projected domestic use,  

b. Sprinklers in accordance with mechanical section, 

c. Site  hydrants,  if  required,  to  provide  protection  in  accordance with NYS  Building Code. 

D. Existing 1 ½” water service, located on Joseph Avenue should be abandoned in accordance with Bureau of Water standards.  Existing service may be used for service to the temporary facility. 

D.  

E. Fire protection main, domestic service main, backflow prevention and related facilities shall meet  Ten  States  Standards,  City  Bureau  of Water  Department  regulations  and Monroe County/NYS  Health  Department  regulations.  It  is  anticipated  water  service  for  the completed  station will  utilize  existing  12”  cement  lined  cast  iron water main  on  North Clinton  Avenue.    Include  application/approval  and  fees  for  Site  Plan  Review,  Backflow Preventer related activities. 

Maintain and protect existing water  facilities on Central Avenue  throughout all phases of the project.   

E.F. Provide  and  install  new  sanitary  collection  piping  sized  to  accommodate  all  proposed facilities.    Sanitary  facilities  shall meet  Ten  States  Standards,  City  Sanitary  Department regulations  and Monroe  County  Pure Waters  and  /NYS  Health  Department  regulations. SiteFacility  discharges  to  combined  sewer,  new  sanitary  service  should  be  approved  by Monroe County Pure Waters, Development Review Office.  All permit fees shall be included.  Maintain and protect existing sewer  facilities on Central Avenue  throughout all phases of the project. 

Page 20: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐15 

Part 3 Project RequirementsJuly 18, 2013

 

 

G. Stormwater collection shall meet the SWPPP requirements identified in Site Design section. The existing drainage patterns convey the site drainage to the exterior of the site through sheet draining and closed drainage systems. In the Phase I portion of the development, the majority of the runoff is collected in closed drainage and conveyed east to Joseph Avenue, with  the west  portion  of  the  site  sheet  draining  to  North  Clinton  Avenue.    Preliminary estimates  of  peak  runoff  rates  were  calculated  using  minimal  time  of  concentrations. Though  this project may not  require coverage under  the NYSDEC SPDES program General Permit, the project shall be advanced with storm water quantity controls in accordance with the New York State Storm Water Management Design Manual. 

Based on preliminary calculations and HydroCAD modeling, it is estimated that Phase I will require approximately 0.15‐2.0 ac‐ft of storage to reduce developed peak discharge rates in a manner which  they will not exceed existing peak discharge  rates. This storage could be accommodated  in  surface  ponds,  if  space  and  grades  permit  in  the  final  site  layout.  Alternatively, the model suggests the use of 500‐700  linear feet of 48” diameter pipe at a slope of 0.10% to obtain the required storage.  

Phase II of the project requires a comparable amount of stormwater storage capacity in the Phase I development area as the Phase I construction. Changes to the drainage patterns are minimal and yield nearly  the  same peak discharge  rates and  required  storage amount.  In the remaining area of the Phase  II development, stormwater  in the existing and proposed condition is sheet drained or conveyed through closed drainage to the west towards North Clinton Avenue.  

Based  on  preliminary  calculations  and  HydroCAD  modeling,  Phase  II  shall  require approximately 0.15‐2.0 ac‐ft (as noted in the Phase 1) of storage to reduce developed peak discharge  rates  to  Joseph Avenue  in  a manner which  they will  not  exceed  existing  peak discharge rates. Additionally, Phase II shall require approximately 0.01‐0.02 ac‐ft to reduce developed  peak  discharge  rates  to  North  Clinton  Avenue;  this  could  be  accommodated through surface level ponds or the use of 40‐80  linear feet of 48” diameter pipe at a slope of 0.10%.  

F. Detention systems in Phase I and/or Phase II could utilize design ponds if space permits or buried pipes with varying diameter outlet pipes to obtain  the desired peak discharge rate for each storm event.   

Electric and gas service shall be coordinated and installed in accordance with the standards and guidelines Rochester Gas and Electric and the City.    Include all applications, approvals and fees in accordance with RGE Services Installation Group.   

Page 21: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐16 

Part 3 Project RequirementsJuly 18, 2013

 

 

H. Coordinate  and  install  private  utilities  (including  but  not  limited  to  electric,  gas, communications) in accordance with the standards and guidelines of the utility provider and the City. 

G.I.   Coordinate  demolition  plan  with  each  utility  to  review  existing  active  infrastructure, existing abandoned  infrastructure and/or the potential  for hazardous materials associated with  any  existing  infrastructure.      Develop  utility  demolition  plan  for  all  utilities  in accordance with findings. 

H.J. Coordinate with Amtrak IT for power and conduit sizing/location for the temporary station and new station. 

K. Coordinate with Trailway’s IT for power and conduit sizing/location for the new station.  

L. Coordinate  communications  with  Frontier  Communications  1‐877‐433‐3806.     Minimum notification is 5‐7 business days to come out and set up the temporary connection. 

 

5.6  Design Loading and Loading Combinations 

A. All  loads  and  load  combinations  shall  be  compliant  and  adhere  to  the  New  York  State Building Code 2010 and ASCE 7‐10. 

5.7  Materials 

Refer to Part 8 – Project Specifications. 

5.8  Site Layout and Circulation   

The Rochester  Station Project  shall promote ease of  transfer between  transportation modes and  circulation  throughout  its exterior  site, but must also  segregate different uses  for  safety reasons.  Intercity and potential  future city bus operations cannot  share access or  space with cars and shuttles. Drop off/pickup for passengers must be separated from general parking and shall share access with both short term parking and taxi/shuttle bus movements.   The Design‐Builder  shall  ensure  pedestrians  are  protected  and  separated  from  vehicular  movements wherever possible. 

It is desirable to promote a visual presence of the new station along the North Clinton frontage in order to create a visual connection with downtown Rochester along that street to the south. To ensure the shortest possible passenger travel distance, the station building should be sited as close as possible to the center line of tracks, while adhering to the twenty‐five foot minimum clearance  from  the  centerline  of  the  nearest  track  bed.    The  goal  of  a  ‘seamless  journey’ through  the  station  building  to  the  boarding  area  shall  be  achieved with  this  configuration.  There are other mandates that shall  impact the  location of the station building and other site features including, but not limited to: 

Page 22: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐17 

Part 3 Project RequirementsJuly 18, 2013

 

 

A. Replacement of the existing  low‐level platform with an ADA compliant high  level center island platform  for passenger access  to Amtrak service  to Empire, Maple Leaf, and Lake Shore Corridors. 

B. Minimize customer travel distance between station functions and the platform. C. Consolidation of  traffic movements’ onto  the Central Avenue  frontage  in Phase One  to 

eliminate sight distance conflicts at Joseph Avenue and North Clinton Avenue. D. Segregation of baggage and passenger traffic. E. Provision of ramps to accommodate baggage movements in lieu of elevators. F. The new  station building must maintain  a minimum of  twenty‐five  feet  clear envelope 

from the centerline of the southernmost track with additional 10’ setback recommended wherever possible to minimize flagging and lower construction costs for the building. 

G. Provide ADA accessible path connecting all site and program elements. H. Provide a covered path to transport baggage from the Baggage Work Area to the exterior 

baggage ramp and into the Concourse without exposing baggage to weather. I. Provide a covered path to transport baggage from the Concourse to the Platform without 

exposing baggage to weather. J. Provide  a  covered  area  for  passengers  to  board  Trailways  buses.    Since  wheelchair 

boarding is at the very rear of the bus, the bus canopy extends to cover the entire length of the buses. 

K. Install large skylight units in both the baggage and bus boarding canopies to allow natural light into these large shaded areas. 

L. Allow for the installation of bicycle share facilities. M. Widen North Clinton and Joseph Avenues to provide street side bus stops for RGRTA bus 

routes.    Provide  bus  shelters  at  these  layovers  for  waiting  passengers,  including  a minimum of 10 bicycle rack spaces per bus shelter. 

M.N. Allow  sufficient  additional  space  beneath  the  bus  shelters  that  shall  be  provided  for RGRTA  bus  stops  for  the  future  installation  of  bicycle  share  facilities  by  the  City  of Rochester. 

N.O. Provide queue space for a minimum of four (4) taxis, two (2) university shuttle vans, and other paratransit services 

P. Allow  for space  for a minimum of  five  (5) passenger drop off and pick up spaces at  the Station entry, and provide a minimum of thirteen (13) short‐term parking spaces near the Station entry. 

O.Q. Allow  for  a minimum  of  ten  (10)  bicycle  lockers  at  the  Station  building,  beneath  the Phase  II canopy, along with space  for a minimum of  (20) bicycles at U‐shaped racks and tamper‐resistant public bicycle work stand and separate public bicycle pump. 

The  site  layout  shall  incorporate  softscape  wherever  possible,  eliminating  any  unnecessary paving  in accordance with the City of Rochester’s Project Green policy, especially at the North Clinton Avenue frontage.  North Clinton has been identified by the City as one of the proposed “Green  Corridors”  that  shall  feature  integrated  bicycle  and  pedestrian  circulation.    The landscape  shall  include  trees  along  the  street  line  and  along  pedestrian  paths  to  create  an urban  environment  that  is  pleasant  and  friendly  for  bicyclists  and  pedestrians.    The Design‐Builder  shall  balance  the  requirements  of  both  the  City  of  Rochester  and  Amtrak  security 

Page 23: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐18 

Part 3 Project RequirementsJuly 18, 2013

 

 

concerns,  including small  trees compatible with an urban setting  that do not allow  for hiding places.  Landscaped islands shall be incorporated in the parking areas to soften the hardscape.  LED  site  lighting  shall be  supplemented with  additional pedestrian  level  lighting  along major circulation routes.   The Design‐Builder shall provide  life‐cycle cost analysis for LED site  lighting or other proposed substitute.   Loading dock and trash and recycling storage shall be screened from public view. 

Exterior  to  the  station building, a Kiss and Ride Drop‐Off  location,  taxi  stand, and  short‐term parking are sited along the Central Avenue frontage. For ease of arrival and departure, the pick‐up and drop‐off lanes are designed at a minimum of twelve feet wide. Similarly, the taxi berths are minimally  twenty  feet  in  length with  an  additional  five  feet  for maneuvering.  Sidewalks throughout  the  site  shall  be  a  minimum  of  8  feet  wide,  and  crosswalks  shall  receive  a thermoplastic stamped asphalt decorative  treatment.   The Design‐Builder shall provide speed tables at major pedestrian crossings  for both  traffic calming and  for ease of accessible  travel with bollards for pedestrian safety. 

5.9  Other Site Components  

A place for both garbage and recycling storage and retrieval via a loading dock shall be provided onsite concealed and screened from public view.  It shall be the Design‐Builder’s responsibility to  ensure  the  loading  dock  and  access  to  the  garbage  and  recycling  storage  complies with required  truck access dimensions.   Additional station maintenance  items, such as snow plow, ice melt, and additional baggage  floats and carts shall be accommodated with a minimum of three  hundred  square  feet  of  covered  exterior Amtrak  storage  space per Amtrak  Functional Space Requirements, issued on 12/30/2012.  

In order to further sustainable initiatives, a Construction and Building Site Waste Management Plan shall be in place to ensure 50% recycling and/or salvaging of existing material.  Throughout the site, low maintenance landscaping shall be integrated to minimize impervious surfaces.  The Design‐Builder shall grade areas away from structures to prevent ponding, while mitigating the flow of runoff over impervious surfaces. 

SECTION 6.  GEOTECHNICAL REQUIREMENTS 

The  Design‐Builder  shall  be  responsible  for  geotechnical  design  and  construction  of  all permanent  and  temporary  structures,  including  assessing  available  information,  geotechnical analysis and reporting, geotechnical instrumentation and monitoring, and protection of existing infrastructure,  structures  and  utilities  in  accordance with  the  requirements  of  the  Contract Documents.  

These  requirements are  considered as a minimum and do not  include all possible conditions that may be encountered in the Design‐Builder’s final design. 

The NYSDOT has performed  subsurface  investigations  in  the  vicinity of  the proposed  station building. Boring logs and laboratory test data from these previous subsurface investigations are provided  in Part 7 – Project Data.   The soil and  rock samples obtained during  these previous subsurface  investigations  are  available  for  inspection  by  the Design‐Builder  at  request.    The 

Page 24: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐19 

Part 3 Project RequirementsJuly 18, 2013

 

 

Design‐Builder shall be responsible for making any arrangements to view the samples from the previous subsurface  investigations, by  first seeking  the prior consent of  the NYSDOT’s Project Manager. Information from these previous subsurface investigations shall be considered part of the Contract Documents only to the extent that they are used to represent soil conditions at the depths indicated within the respective borings drilled at the approximate locations shown.  Presentation of this  information  in no way  implies that subsurface conditions are the same at other locations and different times.  The Design‐Builder shall form its own interpretation of the existing geotechnical data and  satisfy  itself as  to  the nature and behavior of  the ground and sub‐soil, the  form and nature of the Site, and nature of the Work that may affect  its detailed design, construction method, and tools. 

6.1  Standards and References 

The  Design‐Builder  shall  perform  geotechnical  activities  in  accordance  with  the  Contract Requirements, the applicable Standards, Codes and Manuals listed below. 

ACI ‐ American Concrete Institute 

ACI 318 – Building Code for Reinforced Concrete 

AISC ‐ American Institute of Steel Construction 

Specification for Structural Steel Building, Load and Resistance Factor Design 

AMTRAK 

AMTRAK Station Program and Planning, Standards and Guidelines, Station Manual 2.2 

AREMA – American Railway Engineering and Maintenance of Way Association 

AREMA Manual for Railway Engineering 

Page 25: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐20 

Part 3 Project RequirementsJuly 18, 2013

 

 

ASTM – American Society of Testing Materials 

ASTM D1143 – Standard Method of Testing Piles under Axial Compressive Load 

ASTM D3689 – Standard Test Methods  for Deep Foundation Under Static Axial Tensile Load 

ASTM D3966 – Standard Test Methods for Deep Foundation Under Lateral Load 

ASTM  D6760  –  Standard  Test  Method  for  Integrity  Testing  of  Concrete  Deep Foundations by Ultrasonic Crosshole Testing 

AWS – American Welding Society 

AWS D1.1 – Structural Welding Code – Steel 

AWS D1.3 – Structural Welding Code – Sheet Steel 

AWS D1.4 – Structural Welding Code – Reinforcing Steel 

Burlington Northern & Santa Fe Railway/Union Pacific Railroad 

Guidelines for Temporary Shoring 

FHWA 

Static Pile Load Test Manual  

Micro‐pile Design and Construction Guideline 

New York State Building Code (2010) 

SEI – Structural Engineering Institute 

Minimum Design Loads for Buildings and Other Structures 

6.2  Personnel Qualification Requirements 

A. Foundation Lead Designer 

The  Design‐Builder  shall  provide  a  Foundations  Lead  Designer  who  shall  be  a  Professional Engineer  licensed  in  the  State  of  New  York  to  lead  the  Project  geotechnical  team.    The Foundations  Lead Designer  shall be  in  charge of all geotechnical Work, and  shall perform or directly  oversee  all  geotechnical Work,  and  shall  sign  or  co‐sign  and  stamp  all  geotechnical related design, analysis, released for construction documents, As‐Built Plans and other related documents.    The  Foundations  Lead  Designer  shall  have  a minimum  of  15  years  of  recent experience that include the exploration, analysis, design, and construction of the following:  

1. Current LRFD methodology and requirements;  2. Tunnel  and  Track  structures  and  foundations of  the magnitude  and  type  that will be 

used;  3. Planning and conducting subsurface exploration for rail stations;  

Page 26: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐21 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. Site  characterization,  including  the  development  of  design  soil/rock  profiles  with relevant  properties  for  the  purpose  of  foundation  type  and  size  selection,  analysis, design, and construction;  

5. Analysis  and  design  of  structure  foundations  for  static  as well  as  dynamic  (seismic) loading; 

6. Planning and conducting load tests and integrity testing for deep foundations including micropiles and drilled shafts;   

7. Soil‐foundation‐structure interaction analysis; and  8. Derivation of parameters for, and design and construction of, temporary and permanent 

earth support structures. B. Seismic Specialist 

The  Design‐Builder  shall  provide  a  Seismic  Specialist  who  shall  be  a  qualified  Professional Engineer licensed in the State of New York.  The seismic specialist shall have a minimum of 15 years practicing earthquake engineering.  The seismic specialist shall have a background in both structural and geotechnical disciplines. The prior project experience of  the  Seismic  Specialist shall  include  at  a minimum:  ground motion  evaluation,  spatial  variability,  and  soil  structure interaction  effects,  liquefaction  analyses,  finite  element  modeling  of  complete  soil‐pile‐structure interaction including pile‐to‐pile interaction and kinematic effects. 

C. Geotechnical Instrumentation Engineer 

The  Design‐Builder  shall  provide  a  Project  Geotechnical  Instrumentation  Engineer.    The Geotechnical Instrumentation Engineer shall be a licensed Professional Engineer in the State of New York and shall have at least 10 years of experience in instrumentation work similar to the scope  of  that  in  this  Project.    The  Geotechnical  Instrumentation  Engineer  experience  shall include: 

1. Demonstrate competence in geotechnical engineering area of practice. Experience in installing and monitoring geotechnical and structural instruments for similar ground condition and type of structures in this project. Instrumentation type shall include: deep benchmark; deformation monitoring points; grid crack gauge; geophone; top of rail monitoring point; fiber optics, inclinometers, and data acquisition systems. 

2. Experience in analyses, evaluation, and interpretation of geotechnical and structural instrumentation data. 

3. Reference  two  projects  of  similar  magnitude  where  the  proposed  Geotechnical Instrumentation Engineer has preformed similar duties and responsibilities. 

The  Geotechnical  Instrumentation  Engineer  shall  supervise  instrument  installations, instrumentation  acceptance  tests,  data  collection,  data  interpretations.   The  Geotechnical Instrumentation Engineer shall be available  for consultation  for the duration of the Contract.  The role of geotechnical instrumentation engineer includes, but is not limited to: 

1. Prepare  detailed  step‐by‐step  procedures  and  schedule  with  bar  chart  for  the installation of all instruments specified. 

Page 27: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐22 

Part 3 Project RequirementsJuly 18, 2013

 

 

2. Be on‐site, supervise, and conduct the pre‐installation and post‐installation acceptance tests of each type of instrument. 

3. Review instrumentation data daily 

4. Be on‐site and supervise at least the first three installations of each type of instrument. 

5. Supervise  interpretations  of  geotechnical  instrumentation  data  and  prepare instrumentation Interpretation Reports. 

6. Supervise instrumentation monitoring and management/dissemination of reduced data to others. 

7. Supervise removal or abandonment of instrumentation. 

6.3  Design Requirements 

The Design‐Builder shall at a minimum provide the following:  

A. Geotechnical work plan  

B. Geotechnical investigation plan  

C. Geotechnical data report  

D. Subsurface investigation records  

E. Seismic assessment report  

F. Geotechnical instrumentation and construction monitoring plans  

G. Foundation design reports 

6.4  Geotechnical Work Plan 

The  Design‐Builder  shall  prepare  a  geotechnical  work  plan  for  the  project.  The  plan  shall identify the required geotechnical scope of work that the Design‐Builder plans to complete for the  design  and  construction  of  the  Project.  The  geotechnical  work  plan  shall  include  the following: 

A. Design‐Builder’s knowledge and understanding of the geotechnical, geologic, hydrogeology and seismic settings of the Project Site and how the nature and behavior of the soil, rock, groundwater and subsurface conditions will affect the investigation, design and methods of construction;  

B. Anticipated methods of analysis and design for the foundation of the station building, high‐level platform and cut‐and‐cover tunnel and a discussion of the foundation optimization process and rationale for selection of the foundation types;  

C. Identify key Project constraints and describe how the geotechnical activities will be designed and constructed to meet these constraints;  

D. Identification of all principal geotechnical deliverables and activities;  

Page 28: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐23 

Part 3 Project RequirementsJuly 18, 2013

 

 

E. A narrative describing the approach to quality control during design and construction of the geotechnical Works;  

F. A risk register identifying all major design and construction risks of the geotechnical activities, and describe how these risks are managed and mitigated;  

G. Resumes of the Foundations Lead Designer, Geotechnical Instrumentation Engineer, and Seismic Specialist;  

H. Minimum numbers, depths, types of subsurface investigations to be carried out for the station building, high‐level platform and the tunnel design, including a narrative of the in‐situ tests and laboratory tests to be carried out;  

I. Minimum numbers, and types of axial load tests for each foundation type, size and subsurface condition;  

J. Minimum numbers, and types of lateral load tests for each foundation type and subsurface condition;  

K. Minimum percentage and/or numbers of piles as tested piles to be dynamically tested; L. Crosshole sonic logging shall be done on all drilled shafts. 

6.5  Geotechnical Subsurface Investigation Plan 

The Design‐Builder shall prepare a geotechnical  investigation plan,  including specifications  for performing the Work. The geotechnical investigation plan shall include the criteria or rationale used  in developing the plan, and shall  identify the  locations of all field  investigation sites, and borings, together with their depths, sampling intervals, and a description of both the field and laboratory testing programs. The geotechnical  investigation plan shall be prepared and signed and  sealed by  the Design‐Builder’s  Foundation  Lead Designer. The geotechnical  investigation plan shall include details of borehole abandonment procedures and a list of all permits required to perform the geotechnical investigation. 

The Design‐Builder  shall  plan  and  conduct  subsurface  investigations  in  accordance with  the AREMA’s Standards  for geotechnical  subsurface  investigation  (Volume 2, Chapter 8, Part 22), and as deemed necessary by  the Design‐Builder’s  Foundation  Lead Designer  to establish  the geotechnical  conditions  and  to perform  all  geotechnical  and  foundation design  and  analysis. Borings  shall  be  uniformly  distributed  or  located  in  accordance  with  the  loading  pattern imposed by the structure. The minimum number of borings is listed below.  

 

Subject Area  Minimum Number of Borings

Station Building 3, not overlapping the borings included in 

GDR 

High‐Level Platform  Every 200 ft 

Page 29: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐24 

Part 3 Project RequirementsJuly 18, 2013

 

 

Baggage Ramp (Adjacent to Station Building)  2 

Pedestrian/Baggage Tunnel  2 

The Design‐Builder  is responsible to obtain all necessary permits from Amtrak and CSX and to conduct the field investigation without affecting railroad operation.   

The Design‐Builder  shall determine  the  coordinate  location and ground  surface elevation  for each boring and field investigation position, and shall show the coordinates, station and offset, and elevation for each individual boring log or investigation record. Coordinates and station and offsets for the borings shall be referenced to Amtrak Mile Post 371.0 stationing. Elevations shall be  referenced  to  the  Project  datum  and  horizontal  control  system.  Boring  horizontal coordinates shall be accurate  to +/‐ 1.0  foot; vertical coordinates shall be accurate  to +/‐ 0.5 foot. 

6.6  Geotechnical Data Report 

The  Design‐Builder  shall  prepare  a  geotechnical  data  report,  signed  and  sealed  by  the Foundations Lead Designer.   The geotechnical data report shall serve as a factual depiction of the subsurface conditions and at a minimum it shall include:  

a. Local geology and groundwater condition b. A detailed description of the investigation methods;  c. Complete records (typed logs) with summary tables of investigation;   d. Complete records with summary tables of laboratory test results;   e. Exploratory  hole  location  plan,  showing  locations  of  any  existing  (pre‐award) 

exploratory holes for which data was used by the Design‐Builder plus locations of post‐award  exploratory  hole  locations  undertaken  by  the  Design‐Builder;  and  Plots  of laboratory test results versus elevations for separate areas and soil types. 

6.7  Subsurface Investigation Records 

The  Design‐Builder  shall  be  responsible  for  keeping  a  continuous  and  accurate  log  of  the materials  encountered  and  a  complete  record  of  the  operation  of  progressing  the  casing. Where  driving  is  used,  a  record  of  the  number  of  blows  required  to  advance  the  sampling barrel, each 6 inches in the soil where each sample is taken, shall be kept. Detailed description of soil and rock samples shall be provided per requirements in AREMA Specification, Volume 2, Chapter 8, Part 22. Records shall be kept per AREMA’s specification, Volume 2, Chapter 8, Part 22. 

The  Design‐Builder  shall  use  Bentley  gINT®  or  similar  commercial  software  to  develop  and maintain an electronic database of subsurface information including in‐situ test and laboratory test results, and to produce boring records. 

6.8  Seismic Assessment Report 

Page 30: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐25 

Part 3 Project RequirementsJuly 18, 2013

 

 

Prior to issue to the Amtrak, the Design‐Builder shall ensure that the seismic assessment report is peer‐reviewed by a suitably qualified specialist in this field, and the findings and conclusions of  the peer  review  shall be  included  in an appendix  to  the Seismic Assessment Report.   The seismic  specialist  who  will  perform  the  review  of  this  report  shall  meet  the  minimum requirements specified in section 3.2. 

A.  Seismic Site Response Analyses ‐ Site‐specific seismic response analysis shall be performed to  develop  design  free‐field  response  spectra  in  accordance  with  AREMA  and  Amtrak Guidelines.    The Design‐Builder  shall develop dynamic  soil/rock properties  for use  in  the seismic  analysis  based  on  PS‐Logging  data  as well  as widely‐used  empirical  correlations.  Spatial variation of ground motions shall be accounted for, as applicable. 

B.  Soil Structure Interaction ‐ Seismic soil structure interaction evaluation of deep foundations shall  include  determination  of  the  maximum  imposed  curvatures  and  bending  from earthquake  ground  motions  and  structure  response,  including  free‐field  soil  strains modified  for  soil‐foundation‐structure  interaction  coupled  with  deep  foundation deformations associated with earthquake loads imparted to the foundation by the structure (i.e. inertial response). 

C.  Liquefaction ‐ Evaluation of liquefaction potential shall be performed.  Should this show that liquefaction is a potential hazard at the Site, the risk potential on the station building, high‐level platform and the tunnel shall be evaluated by the Design‐Builder, and any remediation solutions  proposed  by  the  Design‐Builder  shall  be  demonstrated  by  analytical  and  field methods.  

6.9  Geotechnical Instrumentation and Construction Monitoring Plan 

A.  Monitoring of Existing Structures and Utilities 

The Design‐Builder shall develop, implement, and maintain a geotechnical instrumentation and construction  monitoring  plan  to  monitor  vibrations,  accelerations,  vertical  settlement,  and lateral  movement  of  temporary  support  structures  and  adjacent  ground,  and  existing infrastructure  during  construction  including  the  existing  station  building,  tracks,  utilities  and other infrastructures within the zone of influence of construction.  

Wherever vibration‐producing activities could affect a structure, building, or utility, the Design‐Builder shall prepare a Vibration Monitoring and Control Plan to address the potential impacts to nearby  receptors due  to  construction or demolition activities associated with  this Project.  The term “receptor” includes buildings, structures, utilities, and sensitive operations/processes for which construction  impacts or Work above recommended  limits may be detrimental.   The plan shall include ground vibration threshold limits. 

The monitoring plan shall address how the Design‐Builder intends to complete vibration‐related activities and meet the following minimum requirements: 

1. Develop  a  list  of  all  anticipated  vibration  producing  activities  and  where  they  are expected to occur; 

2. Develop a list of all potentially impacted receptors from these activities; 

Page 31: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐26 

Part 3 Project RequirementsJuly 18, 2013

 

 

3. Provide a vibration  susceptibility analysis  for each  identified  receptor, and establish a vibration control  limit to preclude damage,  including threshold damage, to each of the identified receptors.  

4. Provide a plan for notifying the public of potential vibration impacts, responsible Project personnel, receptors requiring precondition surveys, and vibration monitoring activities; 

5. Monitor construction related vibrations at the nearest and most critical receptor(s), and notify  appropriate  project  personnel  immediately  if  established  vibration  limits  are exceeded; 

6. Provide  instrumentation  locations,  monitoring  procedures,  and  a  description  of  the monitoring devices and/or manufacturers’ brochures in the submitted plan; 

7. Assess  any  sensitive  community  or  business  operations  that  may  be  affected  by vibrations; 

8. Provide  recommendations  for  vibration‐limiting  methods  to  meet  the  established maximum safe vibration levels.  

9. List of receptors shall include, but not limited to: • Utilities 

• Tracks 

• Nearby bridges 

• Buildings 

• Newly constructed elements 

• Existing structures within zone of influence of vibration producing activities 

B.  Construction Monitoring 

The  Design‐Builder’s  construction  monitoring  plan  shall  include  details  of  the  proposed program  of  instrumentation  and monitoring, monitoring  frequency,  assesses  the  impacts  to existing structures and utilities, establishes threshold values of the monitored parameters, and describes  the  response  plan  that  will  be  implemented  when  threshold  parameters  are exceeded.  A system of construction monitoring shall be established to include the following: 

1.  Monitoring of settlement of the permanent structures and surrounding area both during and  after  construction.    In  all  cases, monitoring  shall  be  initiated well  in  advance  of construction to establish baseline readings. 

2.   Measurement of lateral movement of permanent structures. 

3.  Measurement of vibration levels of the permanent structures and surrounding area both during and after construction.  Ambient vibration monitoring shall be conducted well in advance of construction to establish baseline readings. 

The  extent  of  the  monitoring  program  will  depend  on  the  size  and  type  of  the  affected structures.  A detailed monitoring program shall be prepared for each structure affected by the work, subject to review by Amtrak. 

Page 32: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐27 

Part 3 Project RequirementsJuly 18, 2013

 

 

Where adjacent properties may be affected by the works, the monitoring program shall allow for readings on fixed points on the structures and buildings, to allow both total and differential settlements to be assessed and lateral movements to be determined.  The monitoring program shall also allow for access to conduct vibration monitoring on adjacent properties. 

C.  Instrumentation 

The instrumentation and monitoring program shall include appropriate types and quantities of monitoring  instruments  capable  of  measuring  horizontal  and  vertical  movements,  tilt  of adjacent structures, and vibrations, as applicable.  Instrumentation to be used in the monitoring programs to control and assist design and construction shall include: 

1.  Inclinometers 

2.  Deep benchmark 

3.  Deformation monitoring points 

4.  Grid crack gauge 

5.  Geophone 

6.  Top of rail monitoring point 

The  types  and  numbers  of  instruments will  depend  on  factors  including  the  size,  type  and location of proposed work.   The design and distribution of  instrumentation shall demonstrate an  understanding  of  the  need,  purpose  and  advantages  of  using  each  proposed  type. Responsibilities  for design, procurement,  installation,  recording, maintenance and protection, and monitoring  plan,  criteria  and  performance  requirements  shall  be  clearly  stated  in  the specifications and Contract Documents.  These shall also contain the procedures to be followed when readings during construction reach any specified threshold values, or when construction changes are deemed necessary.  The detailed instrumentation plan and response plans shall be developed by the Design‐Build Contractor and submitted for review and approval by Amtrak. 

The Design‐Builder shall be  responsible  for ensuring  that all  instruments used  for  the Project are  calibrated within  the  12 months  prior  to  its  use  on  the  Project  and  as  required  by  the manufacturer,  unless  the  Project  Specification  or  other  Contract  requirements  state  that  a more recent calibration is required. 

D.  Instrumentation Data Reporting 

The Design‐Builder shall ensure  that  the  instrumentation can be read remotely and  that data shall be uploaded  to a website provided by  the Design‐Builder, and which shall be accessible remotely by both the Design‐Builder and Amtrak.  Remote‐access functionality shall include the ability  to  extract  data  and  to  isolate  an  individual monitoring  point  or multiple  points.  The presentation  system  shall  include  the  functionality  to modify  the  extents  and  scale  of  data plotting such that arbitrary views are available.  

The Design‐Builder  shall  provide weekly  construction  instrumentation monitoring  reports  to Amtrak. Monitoring reports shall be interpretive in nature, and shall enumerate any corrections applied to the data including, but not limited to any notification measures taken regarding data.  

Page 33: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐28 

Part 3 Project RequirementsJuly 18, 2013

 

 

The  weekly  reports  shall  include  clear  and  explicit  statements  of  exceedances  of  any  pre‐determined  threshold  values.  The  Design‐Builder  shall  maintain  the  instrumentation  and monitor the measurements during and after construction up to Final Acceptance. 

6.10  Foundation Design Report 

The Design‐Builder shall prepare a  foundation design  report  for all structures  included  in  the Project.   The  foundation design report shall detail the analysis and design of each  foundation element,  including  any  foundation  optimization  process  such  as  foundation  element  pile spacing,  and  shall  detail  the  anticipated  total  and  differential  settlements  over  time.    The foundation design report shall be signed and sealed by the Foundations Lead Designer. 

The following information shall be included in the Foundation Design Report. 

A.  Subsurface Information 

1.  As drilled boring  location plan and subsurface profiles within  the  footprint of  the new station building and the high‐level platform and along new tunnel alignment, and cross‐sections, as appropriate 

2.  Description of geology and subsurface conditions within the Project site 

3.  Summary of lab and field test results 

B.  Recommended Geotechnical Design Parameters  

1.  Evaluation  of  the  engineering  properties  of  all  soil  and  rock  types,  including  the expected  average  and  range  of  soil  and  rock  strengths,  index  properties  and deformation properties 

C.  Design Method and Foundation Recommendations 

1.  Design assumptions 

2.  Design methods 

3.  Software used 

4.  Design criteria 

5.  Selection of foundation systems 

6.  Summary of loads 

7.  Summary of resistance 

8.  Foundation  recommendations,  including  type,  size, depth, arrangement of  foundation elements 

D.  Construction Considerations   

1.  Obstructions 

2.  Planned field testing programs, including pile and drilled shaft integrity and load testing 

3.  Slope stability, support of excavation and groundwater control considerations   

Page 34: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐29 

Part 3 Project RequirementsJuly 18, 2013

 

 

4.  Time‐related  settlement  and  lateral  deformation  and  determination  of  the  resulting effects on adjacent structures  

5.  Protection of existing structures and utilities 

6.5.1  Station Building and High‐Level Platform Foundation Design  

The  Design‐Builder  shall  design  and  construct  permanent  foundations  based  on  the requirements of AREMA Railway Engineering Manual. In addition to the applicable subsections from AREMA  cited below,  it must be noted  that  the  requirements per design building  codes listed in Section 2 will also be considered, with the stricter requirements applying. 

It is anticipated that shallow foundation may not be desirable for this project, subject to further evaluations.  Deep  foundation may  prove  to  be more  appropriate  from  technical,  cost  and constructability  aspects.  Shallow  foundation  is  not  permitted  for  the  support  of  the  Station building columns, high level platform, and baggage platform. 

Deep foundations will include both drilled shafts and micropiles. Driven piles are not permitted due to the concerns of vibration induced during pile driving which may have detrimental impact to the railroad tracks.  

When  designing  deep  foundations  to  be  installed  in  populated  areas,  consideration will  be given  to  the  impact  of  noise  and  vibration  to  the  environment.  Specific  noise  and  vibration limits  will  be  established  to  conform  to  local  codes  and  project  requirements.  Ground consolidation,  existing  structure  settlements,  and  disturbance  to  local  residents  due  to  the installation of deep foundations will be maintained within limits as specified herein. 

Drilled shafts will be designed for static loading in accordance with the requirements of AREMA Volume  II,  Chapter  8,  Part  4  and  24.  Micropiles  will  be  designed  in  accordance  with  the requirements  of  FHWA Micropile Design  and  Construction Guideline  due  to  the  absence  of AREMA guidelines on micropile. 

Seismic  design  of  foundations  shall  be  in  accordance with  Chapter  9  of  AREMA  Volume  II, considering the effects of inertial loading from the superstructure and kinematic effects due to loading  from  the  soil  (soil‐structure  interaction). When  liquefaction of  soils can occur,  lateral resistance calculations will assume zero soil support or residual strength for liquefied soils from the  design  water  level  to  the  bottom  of  the  zone  of  potential  liquefaction.  The  lateral displacement (transverse and longitudinal) in either direction at the superstructure level will be limited to a value consistent with the design  limits of the superstructure. The calculations  for the horizontal movement of the foundations, substructure, superstructure and bearings will be based on elastic seismic loads (R =1). A detailed structural analysis shall be provided to include induced foundation lateral and axial loadings as well as vertical loading on batter piles, stability and pile bending stress determinations during the occurrence of liquefaction. 

The differential settlement of the station building and the high‐level platform shall not exceed 1/4 inches and the angular distortion is less than 1/500. 

A.  Drilled Shaft 

Page 35: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐30 

Part 3 Project RequirementsJuly 18, 2013

 

 

Drilled  shafts  shall  be  designed  in  accordance with  the  requirements  of  AREMA  Volume  2, Chapter 8, Part 24. Drilled shaft shall be analyzed for both vertical capacity and the lateral load capacity. For vertical capacity, axial compression and uplift resistance shall be designed using static analysis methods in accordance with AREMA. Deep foundation capacity and serviceability requirements  under  seismic  loading  will  conform  to  the  requirements  specified  in  AREMA Volume II, Chapter 9.  

Drilled shafts shall also be designed to adequately resist the  lateral  loads transferred to them from  the  structure  without  exceeding  the  allowable  deformation  of  the  structure  or overstressing the foundation elements. The  lateral  load resistance of the  individual and group of drilled shaft elements shall be analyzed. The analysis shall consider nonlinear soil pressure‐displacement  relationships,  soil/structure  interaction,  group  action,  groundwater,  and  cyclic and  static  and  dynamic  load  conditions.  The  performance  evaluation  of  drilled  shaft  shall include the determination of vertical and horizontal movements, rotation, axial load, shear, and bending moment for the foundation elements. 

The lateral resistance of a single drilled shaft and a group of shafts shall be analyzed for all limit states.   Group efficiency and  lateral  load  reduction  factors  shall be  considered based on  the shaft spacing as specified in the AREMA Specifications. 

The design of drilled shaft shall consider the  limits on total and differential settlement caused by  the  structure  loads.  Settlement  induced  by  the  drill  shaft  group  in  the  subsoil  shall  be evaluated.  In  addition,  settlement  of  the  individual  drill  shaft  shall  also  be  evaluated.  The foundation shall be designed to keep the settlement within the allowable values as specified in AREMA. 

The drilled shaft design shall consider the effect of negative skin friction from existing ongoing ground settlement, liquefaction, construction dewatering, or shaft installation. Downdrag loads shall be determined by considering the load transfer distribution along the drilled shaft as well as the group  layout. The magnitude of the downdrag  load shall be applied as additional dead load on the deep foundation.  

An adequate amount of testing  as specified in Section 4.7.2.1 will be required for drilled shaft to  evaluate  foundation  capacity  and  integrity,  to  verify  design  assumptions,  to  determine foundation  installation  characteristics,  to  evaluate  the  foundation  installation  system performance, and to establish  foundation depths. The testing and monitoring shall  include all necessary test shafts, dynamic testing, static load testing, non‐destructive integrity testing and quality control testing. Testing and monitoring of drilled shaft shall be  in accordance with the applicable ASTM and AREMA.  

For  drilled  shaft  foundations,  include  the  following  information  in  the  Foundation  Design Report: 

1.  Nominal Axial Compressive Resistance and resistance factors 

2.  Factored Axial Compressive Resistance 

3.  Nominal Uplift Resistance and resistance factors 

Page 36: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐31 

Part 3 Project RequirementsJuly 18, 2013

 

 

4.  Factored Uplift Resistance 

5.  Top of Drilled Shaft elevation 

6.  Top of Rock Socket Elevation 

7.  Tip of Drilled Shaft Elevation 

8.  Drilled Shaft Diameter 

9.  Rock Socket Diameter 

10. Reinforcement Cage cross sections 

11. Concrete and reinforcement steel properties 

B.  Micropiles 

Micropiles  are  defined  as  small  diameter  drilled  and  grouted  non‐displacement  pile with  a reinforcing  casing  and  a  center  reinforcing  bar.  Permanent  casings  and  load  testing  are required. Micropiles shall be analyzed  for both vertical capacity and the  lateral  load capacity. For  vertical  capacity,  axial  compression  and  uplift  resistance  shall  be  designed  using  static analysis methods in accordance with FHWA micropile design and construction guidelines. Deep foundation capacity and serviceability requirements under seismic  loading will conform to the requirements specified  in AREMA Volume  II, Chapter 9. A micropile specialty Subcontractor  is required for design and construction of micropiles.  

Micropiles shall also be designed to adequately resist the lateral loads transferred to them from the  structure without exceeding  the  allowable deformation of  the  structure or overstressing the  foundation elements. The  lateral  load  resistance of  the  individual and group of micropile elements  shall  be  analyzed.  The  analysis  shall  consider  nonlinear  soil  pressure‐displacement relationships,  soil/structure  interaction, group  action, groundwater, and  cyclic and  static and dynamic  load  conditions.  The  performance  evaluation  of  micropile  shall  include  the determination of vertical and horizontal movements,  rotation, axial  load,  shear, and bending moment for the foundation elements. 

The design of micropile shall consider the limits on total and differential settlement caused by the  structure  loads.  Settlement  induced  by  the  micropile  group  in  the  subsoil  shall  be evaluated.  In  addition,  settlement  of  the  individual  drill  shaft  shall  also  be  evaluated.  The foundation shall be designed to keep the settlement within the allowable values as specified in FHWA micropile design and construction guidelines. 

The micropile design  shall  consider  the effect of negative  skin  friction  from existing ongoing ground settlement,  liquefaction, construction dewatering, or micropile  installation. Downdrag loads shall be determined by considering the  load transfer distribution along the micropile as well as  the group  layout. The magnitude of  the downdrag  load shall be applied as additional dead load on the deep foundation. 

Subcontractor  shall  submit  documentation  before  the  start  of  construction  that  he  has successfully  completed at  least  three micropile projects and at  least  installed 150 micropiles within the last three years with micropile diameters and lengths similar to those anticipated for 

Page 37: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐32 

Part 3 Project RequirementsJuly 18, 2013

 

 

this  project.    Documentation  shall  include  the  general  contractor  and  owner’s  name  and current contact information with descriptions of each project.  A design geotechnical engineer is required to design micropiles.  The design engineer shall be a licensed Professional Engineer in the State of New York and shall have at least 10 years of experience in designing micropiles and  drilled  foundations with  capacities  and  in  subsurface  conditions  similar  to  those  of  this project.  

Double  corrosion  protection  shall  be  provided  to micropile  central  reinforcing  steel  bar  in accordance with  FHWA‐SA‐97‐070  recommendations. Maintain a minimum of 3  inches grout cover  to  the  reinforcing  bar  along  the  entire  length  of  the  micropile.  Galvanize  exposed reinforcing  and  permanent  casing  that  connect  directly  to  caps  in  accordance  with  FHWA micropile design and construction guidelines.    

For Micropile foundations, include the following information in the Foundation Design Report: 

1.  Micropile  layout, diameter,  inclination, minimum  reinforcing  casing  and  center  rebar, and pile to cap connection 

2.  Micropile tip elevations, and bond lengths. The rock socket shall have a minimum bond length of ten feet in Class 1b rock. Neglect tip resistance in tension and compression 

3.  Nominal Axial Compressive Resistance and resistance factors 

4.  Factored Axial Compressive Resistance 

5.  Nominal Uplift (tension) Resistance and resistance factors 

6.  Factored Uplift Resistance 

7.  Nominal Lateral Resistance and resistance factors 

8.  Factored Lateral Resistance   

Do not install reinforcing casing or begin drilling within six times pile diameter, center to center or five feet, whichever is greater until grout in piles reaches initial set. Grout the micropiles the same day the bond length is drilled. 

C.  Existing Drilled Shaft 

During the preliminary field  investigation, two test pits were excavated along the west side of the  existing  station  building  to  expose  existing  drilled  shaft  foundations.  A  total  of  two foundation cores were retrieved from the existing drilled shaft, one at each test pit. Laboratory testing was  performed  on  the  core  samples  including  petrography  and  uniaxial  compressive strength with static moduli. The laboratory testing results are included in the Geotechnical Data Report of the Request for Proposal package. The Design‐Builder shall assess the condition of the existing drilled shaft and evaluate the possibility of reusing the existing foundation to support the new building structure.   

6.5.2  Foundation Load Testing  

The  Design‐Builder  shall  carry  out  sufficient  axial  load  tests  to  verify  the  design  nominal resistance  for each production micropile/shaft  type, diameter  and  subsurface  condition  type 

Page 38: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐33 

Part 3 Project RequirementsJuly 18, 2013

 

 

(specifically, either  founded within soil only, or  founded within or upon  rock).   For each  type and diameter of micropile/shaft per subsurface condition type, a minimum of 5% of the total number of micropiles/shafts but no less than one static load test shall be performed. 

After  completion  of  a micropile/shaft  load  test,  the  Design‐Builder  shall  be  responsible  for either fully removing the test pile from the ground or for cutting off the test pile at 2 feet below final grade. 

A.  Load Testing for Drilled Shaft 

Install one  load  test drilled shaft prior  to  installation of production drilled shafts.   Select  test locations  to  represent different  subsurface conditions and/or  construction methods. Perform axial compression  load  test  for each drilled shaft size based on site variability.    If  the Design‐Builder chooses to alter construction methods, an additional axial load test will be required on a  test shaft constructed with  the new method.   Perform axial  load  tests using Osterberg Cell load equipment in accordance with ASTM D1143.  

Perform  integrity  testing  on  all  test  shafts  and  production  shafts.    At  a minimum,  integrity testing requirements shall comprise Crosshole Sonic Log (CSL) testing on all drilled shafts. 

B.  Load Testing for Micropiles 

Install load test micropile to demonstrate micropile subcontractor’s ability to successfully install micropiles.    Select  test  locations  to  represent  different  subsurface  conditions  and/or construction methods.   Perform axial compression  load  test  for each micropile size based on site variability.  If the Design‐Builder chooses to alter construction methods, an additional axial load test will be required on a test micropile constructed with the new method.  

C.  Load Testing Report 

The  Design‐Builder  shall  prepare  a  Micropile/Shaft  Geotechnical  Nominal  Resistance  Test Implementation  Report  containing  test  procedures,  instrumentation  plan  including measurements  along  the  micropiles/shafts,  calibration  procedures,  test  micropile/shaft locations, micropile/shaft sizes, and  types being  tested and equipment used.   At a minimum, drilled shaft load test piles shall be instrumented along the length to establish load transfer (t‐z) curves for each soil layer and (q‐z) curve for the bearing layer(s). Include crosshole sonic logging results for drilled shafts.  

The  Design‐Builder  shall  prepare  a  Micropile/Shaft  Geotechnical  Nominal  Resistance  Test Results  Report  containing  test  results  per micropile/shaft  size  and  type  tested;  production micropile/shaft installation, and production piling acceptance criteria.  The Design‐Builder shall interpret  the  load  test  results and use  them  in  the Design of Foundation  such  that  the axial deformations of the micropile/shaft do not exceed the structural limit. 

6.5.3  Support of Excavation (Temporary Shoring for Cut‐and‐Cover Tunnel Construction) 

The  Design‐Builder  shall  design  the  temporary  shoring  system  for  the  construction  of  the proposed cut‐and‐cover tunnel in accordance with the guidelines of AREMA Volume II, Chapter 8, Part 28  and  the publication of Burlington Northern &  Santa  Fe Railway  (BNSF) and Union Pacific  Railroad  (UPRR)  on  temporary  shoring.  Where  conflicts  exist,  the  most  stringent 

Page 39: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐34 

Part 3 Project RequirementsJuly 18, 2013

 

 

specification should be applied. These shoring systems will be designed to resist all anticipated dead  and  live,  vertical  and  lateral  loads.  These  loads  will  include  those  induce  by  soil, groundwater, live load, surcharge and construction equipment. 

The temporary shoring system shall include anchored soldier beam with lagging wall. Open cut is not allowed. If anchored systems with tie‐backs are used, the relative locations between tie‐backs and existing/future utilities need to be evaluated to ensure no conflict. Ground anchors shall  be  cement‐grouted  tiebacks  designed,  furnished,  installed,  tested  and  stressed  in accordance with the AREMA requirements.  

Temporary  loadings  need  to  be  considered  in  design.  Temporary  loads  include,  but  are  not limited  to  construction  surcharge,  ground  and  groundwater  pressure,  and  live  load  from railroad tracks. 

Loads due to soils shall be derived using the maximum values of the saturated densities. Lateral earth pressures will be estimated on the basis of the anticipated movement of the structure. Active  and  passive  earth  pressure  based  on  Coulomb  earth  pressure  theory will  be  used.  If there is no movement expected, at‐rest earth pressure will be used. The design of the retaining structures  shall  be  based  on  the  maximum  lateral  pressures  that  will  develop  behind  the structures.  

Hydrostatic  pressure  induced  by  the  groundwater  table  shall  be  included  in  the  lateral pressures.  

Lateral pressure induced by surcharge loads applied at the ground surface behind the wall shall be included as appropriate. These surcharge loads will be evaluated on a site‐specific basis, and will include uniform surcharges, strip loads, line loads, point loads, area loads, train loads, and construction equipment loads. 

Structures and structural members shall be designed to have design strengths at all sections at least equal to the required strengths calculated for the loads and forces in such combinations as stipulated  in AREMA Volume  II, Chapter 8, Part 2, which  represents  various  combinations of loads and group loads that are applicable and the load combination that requires the maximum strength shall be used. Stability analyses shall be conducted in accordance with AREMA Volume II, Chapter 8, Part 28 for all temporary shoring structures.  

For  an  anchored  system with  tiebacks,  requirements on embedment depth,  allowable  stress and tiebacks need to be satisfied in accordance with the AREMA specification.   

For braced excavation, it shall be designed using the apparent earth pressure diagram indicated in AREMA Volume II, Chapter 8, Part 28.5.5. 

Calculated deflections of  temporary shoring system and  top of rail elevation shall not exceed the criteria outlined in Table 1 of Design Guideline for Temporary Shoring (BNSF and UPRR). 

Horizontal distance from shoring to track C/L measured 

Maximum horizontal movement of shoring system 

Maximum acceptable horizontal or vertical 

Page 40: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐35 

Part 3 Project RequirementsJuly 18, 2013

 

 

When evaluation indicates that the support of excavation system may be insufficient to protect structures adjacent to support of excavation, direct support of structures by underpinning shall be evaluated.  Underpinning methods to be evaluated include: 

1.  Pit underpinning 

2.  Jacked pile underpinning 

3.  Micropile underpinning 

For support of excavation, include the following information in the support of excavation design report: 

1.  Location of support o excavation system  

2.  Support of excavation type 

3.  Support of excavation shoring member size 

4.  Support of excavation embedment depth 

5.  Bending stiffness (EI) and axial stiffness (AE) of bracing elements 

6.  Lateral earth pressure distribution 

7.  Design  calculation  of  tieback,  including  anchor  number  and  location;  load  for  each ground  anchor;  Inclination  angle;  type  and  size  of  ground  anchor; minimum  bonded length; and minimum stressing length 

8.  Design of grout mix including non‐shrink additives and compressive strength test results from a certified testing laboratory 

6.5.4  Cut‐and‐Cover Tunnel 

A pedestrian/luggage tunnel connecting the station building and the high‐level platform will be designed and constructed for the project. The approximate dimension inside the tunnel is 20 ft wide,  11  ft  high with  an  invert  at  approximately  18  ft below  grade. Although  there may be different ways to construct the tunnel, only the cut‐and‐cover method is allowed and assumes that sufficient track outages will be staged to allow for construction. Sufficient track outage  is defined as  the  two  tracks between  the  station building and  the high‐level platform  removed from service for a time period of ________.   

The construction sequence for the cut‐and‐cover tunnel is: 

at a right angle from track  movement of rail 

12’ < S < 18’  3/8”  1/4” 

18’ < S < 24’  1/2”  1/4” 

Page 41: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐36 

Part 3 Project RequirementsJuly 18, 2013

 

 

1.  Remove the two tracks between the station building and the high‐level platform  from service 

2.  Install support of excavation along the perimeter of the cut‐and‐cover tunnel 

3.  Construct the cut‐and‐cover tunnel 

4.  Restore ground and track substructure and track and restore service to the two tracks 

The Design‐Builder will design the cut‐and‐cover tunnel in accordance with the requirements of AREMA.  

The  required  loading  and  forces  for  design  shall  follow  the  Structural  Design  Guidelines  in Section 5  taking  into  account  the  effects  of  construction  staging  on  existing  and  new construction.  In  addition  to  the  loads  and  forces  in  Section 5,  the  following  loads  should be considered. 

1.  Computation of backfill pressures shall be as per AREMA, Volume  II, Chapter 8, Part 5. Concentrated loads on below grade walls to include, but not limited to, railroad loading and foundations, shall be superimposed. 

2.  Loads due to soils will be derived using the maximum values of the saturated densities. The submerged densities will be used for soil unless the  location  is above the standing water table. 

3.  Horizontal  ground pressure  for  tunnels  in  soil  shall be determined  from  at‐rest earth pressure theory. Horizontal ground pressure for mixed‐face profiles in soil and rock are not expected.   

4.  The  effects  of  hydrostatic  pressure  and  buoyancy  shall  be  considered whenever  the presence of groundwater  is  indicated. During construction and backfill operations,  the elevation of groundwater shall be   observed   and   controlled   so   that   the   calculated  total  weight  of  structure  and  backfill  shall always exceed the calculated uplift due to buoyancy by at  least 10%. The design shall  take  into account  the effect of hydrostatic pressure  pertaining  to  possible  construction  sequences.  The  backfill    shall    be  considered  as  the  volume  contained  within  vertical  planes  defined  by  the outside limits of the structure. No value shall be assigned to contact soil friction. 

Construction joints shall be formed at such locations where they won’t reduce the effectiveness of the lining to resist pressure from surrounding earth or rock. Expansion joints are not required where construction joints are provided. Waterstops shall be provided as necessary.  

The Design‐Builder  shall over‐excavate  a minimum of 5  ft below  the design elevation of  the bottom  of  the mud  slab  and  backfill  with  structural  fill which  is  compacted  in  lifts  to  the elevation of the mud slab bottom.  

The  differential  settlement  of  the  cut‐and‐cover  tunnel  shall  not  exceed  1/4  inches  and  the angular distortion is less than 1/500.  

6.5.5  Track Foundation 

Page 42: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐37 

Part 3 Project RequirementsJuly 18, 2013

 

 

The foundation below the ballast/sub‐ballast shall be designed per the requirements of AREMA, Volume I, Chapter 1, Part 1. 

Site  investigation shall be done  in two phases, preliminary site  investigation and detailed site investigation  per  AREMA  requirements.  Review  of  available  subsurface  information  in  the subject area shall be performed at the preliminary site investigation stage. A more detailed site investigation  program  shall  be  developed  and  executed  to  collect  information  on  soil,  rock, groundwater,  subsurface  drainage  and  topography.  It  shall  also  include  investigation  of  the ballast roadbed interface, particularly “ballast pockets”, their density and drainage. 

Where  the  subgrade material  is  considered unsuitable,  the material  shall be over‐excavated, replaced with  structural backfill, and  compacted  in accordance with  the  requirements of  the project specification on excavation and fill.    

6.6  Construction Requirements 

A.  Deep Foundation Installation Records 

As  part  of  the  As‐Built  Plans,  the  Design‐Builder  shall  provide  installation  records  for  all foundations installed.   

For drilled shafts, the installation records shall include drilling equipment used, temporary and permanent  casing,  materials  encountered,  bottom  cleaning,  SID  results,  top  and  bottom elevations,  shaft and  socket dimensions, and  concrete placement  time.   For all drilled  shafts with rock sockets or bearing on rock, the rock socket and the base of the drilled shaft shall be inspected  utilizing  an  underwater  video  recorder  or  other means  f  of  inspection which will provide equal or better inspection results. The video recorder shall be capable of capturing the depth of the recording. A digital copy of the video recording shall be submitted to the client as part of the drilled shaft installation record. 

B.   Dewatering and Groundwater Control 

The Design‐Builder shall be responsible for developing a substantially dry and stable subgrade for  the prosecution of  subsequent operations by  implementing dewatering and groundwater control measures  as  appropriate.  The  groundwater  condition  shall  be maintained  in  a way causing no damage to adjacent facilities, railroad infrastructure and other work.  

C.   Condition Surveys (Pre‐ and Post‐ construction survey) 

1.  Pre‐Construction Condition Survey 

The  Design‐Builder  shall  conduct  a  pre‐construction  inspection  and  survey  of  the  existing condition  of  all  structures  and  properties  for  the  purposes  of  generating  photographic  and video  documentation  of  existing  damage,  leaks  and  cracks.    The  pre‐construction  condition survey shall form the basis against which all new cracks, existing progressive cracks, or damage will  be measured.    The  spatial  extent  of  the  pre‐construction  survey  shall  encompass  the Project Limits plus certain areas beyond the Project Limits, as detailed herein.   

The  full  spatial  extent  of  the  Design‐Builder’s  pre‐construction  condition  survey  necessarily depends upon the Design‐Builder’s design and proposed means and methods of construction.  

Page 43: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐38 

Part 3 Project RequirementsJuly 18, 2013

 

 

In  its preparation  for  the pre‐construction  survey,  the Design‐Builder  shall be  responsible  for predicting  anticipated  vibration  and  settlement  effects  at  various  offset  distances  from  the Project Limits, and  for ensuring  that  the pre‐construction condition  survey encompasses at a minimum all properties within areas that are identified by the Design‐Builder to be potentially prone to: (i) ground vibration  levels, expressed as resultant peak particle velocity,  in excess of 0.50 inches per second; and (ii) predicted ground settlements of greater than ¼ inch. .  

The  Design‐Builder  shall  submit  to  the  client  the  records  and  photographic  and  video documentation of the pre‐construction condition survey, which shall be signed and stamped by a Professional Engineer registered in the State of New York. 

2.  Post‐Construction Condition Survey 

The  Design‐Builder  shall  conduct  a  post‐construction  condition  survey  of  the  zone  and properties  covered by  the pre‐construction  conditions  survey  (see  Section 5.5.1 herein). The post‐construction  condition  survey  shall  be  performed  by  the  Design‐Builder  at  Physical Completion, and it shall compare the post‐construction conditions with the conditions recorded in  the  pre‐construction  condition  survey.    The  location  and  scope  of  the  post‐construction condition  survey  shall match  those  of  the  pre‐construction  condition  survey.    The  complete documentation  of  the  post‐construction  survey,  describing  the  comparison  with  the preconstruction conditions and signed by a Professional Engineer registered in the State of New York, shall be submitted to the client. 

 

The  Design‐Builder  shall  be  responsible  for  geotechnical  design  and  construction  of  all permanent  and  temporary  structures,  including  assessing  available  information,  geotechnical analysis and reporting, geotechnical instrumentation and monitoring, and protection of existing infrastructure,  structures  and  utilities  in  accordance with  the  requirements  of  the  Contract Documents.  These requirements are considered as a minimum and do not include all possible conditions that may be encountered in the Design‐Builder’s final design. 

NYSDOT  has  performed  subsurface  investigations  in  the  vicinity  of  the  proposed  station building. Boring logs and laboratory test data from these previous subsurface investigations are provided  in Part 7 – Project Data.   The soil and  rock samples obtained during  these previous subsurface  investigations  are  available  for  inspection  by  the Design‐Builder  at  request.    The Design‐Builder shall be responsible for making any arrangements to view the samples from the previous subsurface  investigations, by  first seeking  the prior consent of  the NYSDOT’s Project Manager.    Information from these previous subsurface  investigations shall be considered part of the Contract Documents only to the extent that they are used to represent soil conditions at the depths indicated within the respective borings drilled at the approximate locations shown.  Presentation of this  information  in no way  implies that subsurface conditions are the same at other locations and different times.  The Design‐Builder shall form its own interpretation of the existing geotechnical data and  satisfy  itself as  to  the nature and behavior of  the ground and sub‐soil, the  form and nature of the Site, and nature of the Work that may affect  its detailed design, construction method, and tools. 

Page 44: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐39 

Part 3 Project RequirementsJuly 18, 2013

 

 

6.1  Standards and References 

The  Design‐Builder  shall  perform  geotechnical  activities  in  accordance  with  the  Contract Requirements, the applicable Standards, Codes and Manuals. 

ACI ‐ American Concrete Institute 

ACI 318 – Building Code for Reinforced Concrete 

AISC ‐ American Institute of Steel Construction 

Specification for Structural Steel Building, Load and Resistance Factor Design 

AMTRAK 

AMTRAK Station Program and Planning, Standards and Guidelines, Station Manual 2.2 

AREMA – American Railway Engineering and Maintenance of Way Association 

AREMA Manual for Railway Engineering 

ASTM – American Society of Testing Materials 

ASTM D1143 – Standard Method of Testing Piles under Axial Compressive Load 

ASTM D3689 – Standard Test Methods  for Deep Foundation Under Static Axial Tensile Load 

ASTM D3966 – Standard Test Methods for Deep Foundation Under Lateral Load 

ASTM  D6760  –  Standard  Test Method  for  Integrity  Testing  of  Concrete  Deep Foundations by Ultrasonic Crosshole Testing 

AWS – American Welding Society 

AWS D1.1 – Structural Welding Code – Steel 

AWS D1.3 – Structural Welding Code – Sheet Steel 

AWS D1.4 – Structural Welding Code – Reinforcing Steel 

Burlington Northern & Santa Fe Railway/Union Pacific Railroad 

Guidelines for Temporary Shoring 

FHWA: 

Static Pile Load Test Manual  

Micro‐pile Design and Construction Guideline 

New York State Building Code (2010) 

SEI – Structural Engineering Institute 

Minimum Design Loads for Buildings and Other Structures 

NYSDOT 

A. Access Management Requirements 

Page 45: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐40 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. Annual Report titled "Axle Factor Update" C. Approved Materials List D. Highway Design Manual – Chapters 20 and 21 (CADD Standards and Procedures) E. Comprehensive Pavement Design Manual F. Consultant Instructions G. Design Consultant Manual H. Engineering Bulletins I. Engineering Instructions and Directives J. Environmental Procedures Manual (EPM) / The Environmental Manual (TEM) K. General Design and Construction Requirements for Occupancies L. Geotechnical Engineering Bureau Manuals and Publications  M. GCP‐17, Procedure for the Control of Granular Materials N. Land Surveying Standards and Procedures Manual O. Manual for Uniform Record Keeping P. Materials Bureau  ‐ Applicable Sampling and Testing Manuals,  Inspection Manuals, and 

Materials Methods. Q. New York State Supplement to the Manual on Uniform Traffic Control Devices R. Prestressed Concrete Construction Manual  S. Project Development Manual T. Reference Marker Manual U. Rules  and  Regulations  Governing  the  Accommodation  of  Utilities  within  the  State 

Highway Right of Way V. Special Specifications W. Standard Sheets  X. Standard Specifications for Construction and Materials Y. Steel Construction Manual (SCM) Z. U.S. Customary Standard Sheets AA. Work Zone Traffic Control Manual 

The above  is a partial  listing of applicable NYSDOT Engineering Manuals and Guidelines. The Design Builder  shall perform  the Work  in  conformance with  all  current NYSDOT  Engineering Manuals and Guidelines. 

6.2  Design Requirements 

The Design‐Builder shall at a minimum provide the following:  

A. Geotechnical Work Plan   

B. Geotechnical investigation plan  

C. Geotechnical data report   

D. Subsurface investigation records  

E. Seismic assessment report  

F. Geotechnical instrumentation and construction monitoring plans  

G. Foundation design reports   

Page 46: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐41 

Part 3 Project RequirementsJuly 18, 2013

 

 

6.3  Geotechnical Work Plan 

The  Design‐Builder  shall  prepare  a  geotechnical  work  plan  for  the  project.  The  plan  shall identify the required geotechnical scope of work that the Design‐Builder plans to complete for the  design  and  construction  of  the  Project.  The  geotechnical  work  plan  shall  include  the following: 

A. Design‐Builder’s knowledge and understanding of the geotechnical, geologic, hydrogeology and seismic settings of the Project Site and how the nature and behavior of the soil, rock, groundwater and subsurface conditions will affect the investigation, design and methods of construction;  

B. Anticipated methods of analysis and design for the foundation of the station building, high‐level platform  and  cut‐and‐cover  tunnel  and  a discussion  of  the  foundation optimization process and rationale for selection of the foundation types;  

C. Identify  key  Project  constraints  and  describe  how  the  geotechnical  activities  will  be designed and constructed to meet these constraints;  

D. Identification of all principal geotechnical deliverables and activities;  

E. A narrative describing the approach to quality control during design and construction of the geotechnical Works;  

F. A  risk  register  identifying  all  major  design  and  construction  risks  of  the  geotechnical activities, and describe how these risks are managed and mitigated;  

G. Resumes  of  the  Foundations  Lead Designer, Geotechnical  Instrumentation  Engineer,  and Seismic Specialist;  

H. Minimum  numbers,  depths,  types  of  subsurface  investigations  to  be  carried  out  for  the station building, high‐level platform and the tunnel design,  including a narrative of the  in‐situ tests and laboratory tests to be carried out;  

I. Minimum  numbers,  and  types  of  axial  load  tests  for  each  foundation  type,  size  and subsurface condition;  

J. Minimum numbers, and types of lateral load tests for each foundation type and subsurface condition;  

K. Minimum  percentage  and/or  numbers  of  driven  piles  as  tested  piles  to  be  dynamically tested;  

L. Crosshole  sonic  logging  shall  be  done  on  all  drilled  shafts  according  to  NYSDOT specifications.    Thermal  integrity  profiling  shall  be  done  on  all  demonstration  shafts,  in addition  to  the  first  three production  shaft of each diameter  size. Thermal  integrity data shall  be  collected  continuously  and  remotely  through  embedded  sensors.    Location  of embedded sensors arrays shall be assumed similar to Crosshole sonic locations. 

Page 47: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐42 

Part 3 Project RequirementsJuly 18, 2013

 

 

6.4  Geotechnical Subsurface Investigation Plan 

The Design‐Builder shall prepare a geotechnical  investigation plan,  including specifications  for performing the Work. The geotechnical investigation plan shall include the criteria or rationale used  in developing the plan, and shall  identify the  locations of all field  investigation sites, and borings, together with their depths, sampling intervals, and a description of both the field and laboratory testing programs utilized. The geotechnical investigation plan shall be prepared and signed and  sealed by  the Design‐Builder’s  Lead Designer. The geotechnical  investigation plan shall  include details of borehole abandonment procedures and a  list of all permits required to perform the geotechnical investigation. 

The Design‐Builder  shall  plan  and  conduct  subsurface  investigations  in  accordance with  the AREMA’s Standards  for geotechnical  subsurface  investigation  (Volume 2, Chapter 8, Part 22), NYSDOT’s  Standards  for  subsurface  exploration  programs,  and  as  deemed  necessary  by  the Design‐Builder’s  Lead  Designer  to  establish  the  geotechnical  conditions  and  to  perform  all geotechnical  and  foundation  design  and  analysis.  Borings  shall  be  uniformly  distributed  or located  in  accordance  with  the  loading  pattern  imposed  by  the  structure.  The  minimum number of borings is listed below.  

 

Subject Area  Minimum Number of Borings

Station Building 3, not overlapping the borings included in 

GDR 

High‐Level Platform  Every 200 ft 

Baggage Ramp (Adjacent to Station Building)  2 

Pedestrian/Baggage Tunnel  2 

The Design‐Builder  is responsible to obtain all necessary permits from Amtrak and CSX and to conduct the field investigation without affecting railroad operation.   

 

The Design‐Builder  shall determine  the  coordinate  location and ground  surface elevation  for each boring and field investigation position, and shall show the coordinates, station and offset, and elevation for each individual boring log or investigation record. Coordinates and station and offsets for the borings shall be referenced to Amtrak Mile Post 371.0 stationing. Elevations shall be  referenced  to  the  Project  datum  and  horizontal  control  system.  Boring  horizontal coordinates shall be accurate  to +/‐ 1.0  foot; vertical coordinates shall be accurate  to +/‐ 0.5 foot. 

Page 48: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐43 

Part 3 Project RequirementsJuly 18, 2013

 

 

6.5  Geotechnical Data Report 

The  Design‐Builder  shall  prepare  a  geotechnical  data  report,  signed  and  sealed  by  the Foundations Lead Designer.   The geotechnical data report shall serve as a factual depiction of the subsurface conditions and at a minimum it shall include:  

Local geology and groundwater condition 

a. A detailed description of the investigation methods;  

b. Complete  records  (typed  logs  using  NYSDOT  log  format)  with  summary  tables  of investigation;   

c. Complete records with summary tables of laboratory test results;   

d. Exploratory  hole  location  plan,  showing  locations  of  any  existing  (pre‐award) exploratory holes for which data was used by the Design‐Builder plus locations of post‐award  exploratory  hole  locations  undertaken  by  the  Design‐Builder;  and  Plots  of laboratory test results versus elevations for separate areas and soil types. 

6.6  Subsurface Investigation Records 

The  Design‐Builder  shall  be  responsible  for  keeping  a  continuous  and  accurate  log  of  the materials  encountered  and  a  complete  record  of  the  operation  of  progressing  the  casing. Where  driving  is  used,  a  record  of  the  number  of  blows  required  to  advance  the  sampling barrel, each 6 inches in the soil where each sample is taken, shall be kept. Records shall be kept using the NYSDOT Subsurface Exploration Log Form (US Units). Detailed description of soil and rock samples shall be provided per requirements in AREMA Specification, Volume 2, Chapter 8, Part 22. Records shall be kept per AREMA’s specification, Volume 2, Chapter 8, Part 22. 

The  Design‐Builder  shall  use  Bentley  gINT®  or  similar  commercial  software  to  develop  and maintain an electronic database of subsurface information including in‐situ test and laboratory test results, and to produce boring records. 

6.7  Seismic Assessment Report 

Prior  to  issue  to  the  NYSDOT,  the  Design‐Builder  shall  ensure  that  the  seismic  assessment report  is  peer‐reviewed  by  a  suitably  qualified  specialist  in  this  field,  and  the  findings  and conclusions  of  the  peer  review  shall  be  included  in  an  appendix  to  the  Seismic Assessment Report.    The  seismic  specialist  who  will  perform  the  review  of  this  report  shall meet  the minimum requirements specified in General Instructions to Proposers. 

A. Seismic Site Response Analyses ‐ Site‐specific seismic response analysis shall be performed to  develop  design  free‐field  response  spectra  in  accordance  with  AREMA  and  Amtrak Guidelines.    The Design‐Builder  shall develop dynamic  soil/rock properties  for use  in  the seismic  analysis  based  on  PS‐Logging  data  as well  as widely‐used  empirical  correlations.  Spatial variation of ground motions shall be accounted for, as applicable. 

B. Soil Structure Interaction ‐ Seismic soil structure interaction evaluation of deep foundations shall  include  determination  of  the  maximum  imposed  curvatures  and  bending  from earthquake  ground  motions  and  structure  response,  including  free‐field  soil  strains 

Page 49: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐44 

Part 3 Project RequirementsJuly 18, 2013

 

 

modified  for  soil‐foundation‐structure  interaction  coupled  with  deep  foundation deformations associated with earthquake loads imparted to the foundation by the structure (i.e. inertial response). 

C. Liquefaction ‐ Evaluation of liquefaction potential shall be performed.  Should this show that liquefaction is a potential hazard at the Site, the risk potential on the station building, high‐level platform and the tunnel shall be evaluated by the Design Builder, and any remediation solutions  proposed  by  the  Design‐Builder  shall  be  demonstrated  by  analytical  and  field methods.  

6.8  Geotechnical Instrumentation and Construction Monitoring Plan 

A. Monitoring  of  Existing  Structures  and  Utilities  ‐  The  Design‐Builder  shall  develop, implement, and maintain a geotechnical instrumentation and construction monitoring plan to  monitor  vibrations,  accelerations,  vertical  settlement,  and  lateral  movement  of temporary  support  structures  and  adjacent  ground,  and  existing  infrastructure  during construction including the existing station building, utilities and other infrastructures within the zone of influence of construction.  

Wherever vibration‐producing activities could affect a structure, building, or utility, the Design‐Builder  shall  prepare  a  Vibration  Monitoring  and  Control  Plan  to  address  the potential  impacts  to  nearby  receptors  due  to  construction  or  demolition  activities associated with  this Project.   The  term  “receptor”  includes buildings,  structures, utilities, and  sensitive  operations/processes  for  which  construction  impacts  or  Work  above recommended  limits  may  be  detrimental.    The  plan  shall  include  ground  and  air‐blast vibration threshold limits.  

B. The  monitoring  plan  shall  address  how  the  Design‐Builder  intends  to  complete vibration‐related activities and meet the following minimum requirements: 

1. Develop  a  list  of  all  anticipated  vibration  producing  activities  and  where  they  are expected to occur; 

2. Develop a list of all potentially impacted receptors from these activities; 

3. Provide a vibration  susceptibility analysis  for each  identified  receptor, and establish a vibration control  limit to preclude damage,  including threshold damage, to each of the identified receptors.  

4. Provide a plan for notifying the public of potential vibration impacts, responsible Project personnel, receptors requiring precondition surveys, and vibration monitoring activities; 

5. Monitor construction related vibrations at the nearest and most critical receptor(s), and notify  appropriate  project  personnel  immediately  if  established  vibration  limits  are exceeded; 

6. Provide  instrumentation  locations,  monitoring  procedures,  and  a  description  of  the monitoring devices and/or manufacturers’ brochures in the submitted plan; 

Page 50: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐45 

Part 3 Project RequirementsJuly 18, 2013

 

 

7. Assess  any  sensitive  community  or  business  operations  that  may  be  affected  by vibrations; 

8. Provide  recommendations  for  vibration‐limiting  methods  to  meet  the  established maximum safe vibration levels.  

9. List of receptors shall include, but not limited to: 

• Utilities 

• Nearby bridges 

• Buildings 

• Newly constructed elements 

• Existing  structures  within  zone  of  influence    of  vibration  producing activities 

C. Construction Monitoring  ‐ The Design‐Builder’s construction monitoring plan shall  include details of the proposed program of instrumentation and monitoring, monitoring frequency, assesses the impacts to existing structures and utilities, establishes threshold values of the monitored  parameters,  and  describes  the  response  plan  that will  be  implemented when threshold  parameters  are  exceeded.    A  system  of  construction  monitoring  shall  be established to include the following: 

1. Measurement of ground water levels and ground water pressure. 

2. Monitoring of settlement of the permanent structures and surrounding area both during and  after  construction.    In  all  cases, monitoring  shall  be  initiated well  in  advance  of construction to establish baseline readings. 

3. Measurement of lateral movement of permanent structures. 

4. Measurement  of  vibration  levels  of  the  permanent  structures  and  surrounding  area both during and after construction.   Ambient vibration monitoring shall be conducted well in advance of construction to establish baseline readings. 

D. The extent of the monitoring program will depend on the size and type of the affected structures.  A detailed monitoring program shall be prepared for each structure affected by the work, subject to review by NYSDOTAmtrak. 

E. Where adjacent properties may be affected by the works, the monitoring program shall allow for readings on fixed points on the structures and buildings, to allow both total and differential  settlements  to  be  assessed  and  lateral movements  to  be  determined.    The monitoring program shall also allow for access to conduct vibration monitoring on adjacent properties. 

F. Potential Instrumentation 

The instrumentation and monitoring program shall include appropriate types and quantities of monitoring  instruments capable of measuring horizontal and vertical movements, tilt of adjacent  structures,  soil  pore  pressures,  vibrations,  and  noise,  as  applicable.  

Page 51: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐46 

Part 3 Project RequirementsJuly 18, 2013

 

 

Instrumentation  to be used  in  the monitoring programs  to  control  and  assist design  and construction could include: 

1. Piezometers and observation wells 

Inclinometers  

Deep benchmark 

Deformation monitoring points 

Grid crack gauge 

Geophone 

Top of rail monitoring point 

2. Survey stations on structures and at ground level locations 3. Tiltmeters 4. Deep settlement points and extensometers 5. Strain and load‐measuring devices 6. Seismographs, geophones, and others. 

The types and numbers of  instruments will depend on factors  including the size, type and location  of  proposed  work.    The  design  and  distribution  of  instrumentation  shall demonstrate  an  understanding  of  the  need,  purpose  and  advantages  of  using  each proposed  type.  Responsibilities  for  design,  procurement,  installation,  recording, maintenance and protection, and monitoring plan, criteria and performance requirements shall  be  clearly  stated  in  the  specifications  and  Contract  Documents.    These  shall  also contain  the  procedures  to  be  followed  when  readings  during  construction  reach  any specified  threshold  values,  or  when  construction  changes  are  deemed  necessary.    The detailed  instrumentation plan and  response plans  shall be developed by  the Design‐Build Contractor and submitted for review and approved by NYSDOTAmtrak. 

The  Design‐Builder  shall  be  responsible  for  ensuring  that  all  instruments  used  for  the Project are calibrated within the 12 months prior to  its use on the Project and as required by the manufacturer, unless the Project Specification or other Contract requirements state that a more recent calibration is required. 

G. Instrumentation Data Reporting 

The Design‐Builder shall ensure  that  the  instrumentation can be read remotely and  that data shall be uploaded  to a website provided by  the Design‐Builder, and which shall be accessible remotely  by  both  the  Design‐Builder  and  the  NYSDOT.    Remote‐access  functionality  shall include  the  ability  to  extract  data  and  to  isolate  an  individual monitoring  point  or multiple points. The presentation system shall include the functionality to modify the extents and scale of data plotting such that arbitrary views are available.  

The Design‐Builder shall provide weekly construction instrumentation monitoring reports to the NYSDOT.  Monitoring  reports  shall  be  interpretive  in  nature,  and  shall  enumerate  any corrections applied  to  the data  including, but not  limited  to any notification measures  taken 

Page 52: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐47 

Part 3 Project RequirementsJuly 18, 2013

 

 

regarding data.   The weekly reports shall  include clear and explicit statements of exceedances of any pre‐determined threshold values. The Design‐Builder shall maintain the instrumentation and monitor the measurements during and after construction up to Final Acceptance. 

6.9  Foundation Design Report 

The Design‐Builder shall prepare a  foundation design  report  for all structures  included  in  the Project.   The  foundation design report shall detail the analysis and design of each  foundation element,  including  any  foundation  optimization  process  such  as  foundation  element  pile spacing,  and  shall  detail  the  anticipated  total  and  differential  settlements  over  time.    The foundation design report shall be signed and sealed by the Foundations Lead Designer. 

The following information shall be included in the Foundation Design Report. 

A. Subsurface Information 

1.  As drilled boring  location plan and subsurface profiles within  the  footprint of  the new station building and the high‐level platform and along new tunnel alignment, and cross‐sections, as appropriate 

2.  Description of geology and subsurface conditions within the Project site 

3.  Summary of lab and field test results 

B. Recommended Geotechnical Design Parameters  

1.  Evaluation  of  the  engineering  properties  of  all  soil  and  rock  types,  including  the expected  average  and  range  of  soil  and  rock  strengths,  index  properties  and deformation properties 

C. Design Method and Foundation Recommendations 

1.  Design assumptions 

2.  Design methods 

3.  Software used 

4.  Design criteria 

5.  Selection of foundation systems 

6.  Summary of loads 

7.  Summary of resistance 

8.  Foundation  recommendations,  including  type,  size, depth, arrangement of  foundation elements 

D. Construction Considerations   

1.  Obstructions 

2.  Planned field testing programs, including pile and drilled shaft integrity and load testing 

3.  Slope stability, support of excavation and groundwater control considerations   

Page 53: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐48 

Part 3 Project RequirementsJuly 18, 2013

 

 

4.  Time‐related  settlement  and  lateral  deformation  and  determination  of  the  resulting effects on adjacent structures  

5.  Protection of existing structures and utilities 

 

Deep Foundations‐ (Vertical Capacity, Group Spacing and Performance; Settlement; Downdrag; Lateral Load Capacity; Wave Equation Analysis; Deep Foundation Testing and Monitoring) 

A. Drilled Shaft 

• Driven Pile 

B. Foundation Load Testing  

• Load Testing for Drilled Shaft • Load Testing for Driven Pile • Load Testing Report 

C. Support of Excavation 

• Support of Excavation Systems  • (Design Load ‐ Vertical Load and Lateral Pressure, Stability; Deflection; Groundwater Control)  • Sheetpile • Soldier Pile with Lagging • Earth Slope • Rock Anchors • Construction Consideration 

D. Cut‐and‐Cover Tunnel 

• Functional Requirements  • (Water Tightness; Corrosion Control; Fire Life Safety) • Design Loads  • (Vertical  Loads;  Short‐Term Horizontal  Loads;  Long‐Term Horizontal  Loads, Dynamic  Earth 

Pressures; Water Pressure; Loading on Underground Reinforced Concrete Box Structures) • Rock Classification • Ground Strength and Deformation Parameters • Temporary/Permanent Support Design • Settlement Evaluation and Damage Assessment • Protection Measures • Construction Consideration 

E. Construction Requirements 

F. Deep Foundation Installation Records 

G. Support of Excavation Installation Records 

H. Cut‐and‐Cover Structure Installation Records 

I. Dewatering and Groundwater Control 

Page 54: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐49 

Part 3 Project RequirementsJuly 18, 2013

 

 

Condition Surveys (Pre‐ and Post‐ construction survey) 

Station Building and High‐Level Platform Foundation Design  

The  Design‐Builder  shall  design  and  construct  permanent  foundations  based  on  the requirements  of  AREMA  Railway  Engineering  Manual.  In  addition  to  the  applicable subsections  from AREMA cited below,  it must be noted  that  the  requirements per design building  codes  listed  in  Section  2 will  also  be  considered, with  the  stricter  requirements applying. 

It is anticipated that shallow foundation may not be desirable for this project, subject to further  evaluations. Deep  foundation may prove  to be more  appropriate  from  technical, cost and constructability aspects. Shallow foundation is not permitted for the support of the Station building columns, high level platform, and baggage platform. 

Deep  foundations will  include both drilled  shafts  and micropiles. Driven piles  are not permitted  due  to  the  concerns  of  vibration  induced  during  pile  driving which may  have detrimental impact to the railroad tracks.  

When designing deep foundations to be installed in populated areas, consideration will be  given  to  the  impact  of  noise  and  vibration  to  the  environment.  Specific  noise  and vibration  limits will  be  established  to  conform  to  local  codes  and  project  requirements. Ground consolidation, existing structure settlements, and disturbance to local residents due to the installation of deep foundations will be maintained within limits as specified herein. 

Drilled shafts will be designed for static loading in accordance with the requirements of AREMA Volume II, Chapter 8, Part 4 and 24. Micropiles will be designed in accordance with the requirements of FHWA Micropile Design and Construction Guideline due to the absence of AREMA guidelines on micropile. 

Seismic design of foundations shall be in accordance with Chapter 9 of AREMA Volume II, considering the effects of  inertial  loading from the superstructure and kinematic effects due  to  loading  from  the  soil  (soil‐structure  interaction). When  liquefaction  of  soils  can occur,  lateral resistance calculations will assume zero soil support or  residual strength  for liquefied  soils  from  the  design  water  level  to  the  bottom  of  the  zone  of  potential liquefaction. The lateral displacement (transverse and longitudinal) in either direction at the superstructure  level  will  be  limited  to  a  value  consistent  with  the  design  limits  of  the superstructure.  The  calculations  for  the  horizontal  movement  of  the  foundations, substructure,  superstructure and bearings will be based on elastic  seismic  loads  (R =1). A detailed structural analysis shall be provided to include induced foundation lateral and axial loadings  as  well  as  vertical  loading  on  batter  piles,  stability  and  pile  bending  stress determinations during the occurrence of liquefaction. 

The differential settlement of the station building and the high‐level platform shall not exceed 1/4 inches and the angular distortion is less than 1/500. 

Drilled Shaft 

Page 55: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐50 

Part 3 Project RequirementsJuly 18, 2013

 

 

Drilled shafts shall be designed in accordance with the requirements of AREMA Volume 2, Chapter 8, Part 24. Drilled shaft shall be analyzed for both vertical capacity and the lateral load capacity. For vertical capacity, axial compression and uplift resistance shall be designed using  static  analysis methods  in  accordance with AREMA. Deep  foundation  capacity  and serviceability  requirements  under  seismic  loading  will  conform  to  the  requirements specified in AREMA Volume II, Chapter 9.  

Drilled shafts shall also be designed to adequately resist the lateral loads transferred to them  from the structure without exceeding the allowable deformation of the structure or overstressing  the  foundation  elements.  The  lateral  load  resistance  of  the  individual  and group of drilled shaft elements shall be analyzed. The analysis shall consider nonlinear soil pressure‐displacement relationships, soil/structure  interaction, group action, groundwater, and  cyclic and  static and dynamic  load  conditions. The performance evaluation of drilled shaft shall  include the determination of vertical and horizontal movements, rotation, axial load, shear, and bending moment for the foundation elements. 

The lateral resistance of a single drilled shaft and a group of shafts shall be analyzed for all limit states.  Group efficiency and lateral load reduction factors shall be considered based on the shaft spacing as specified in the AREMA Specifications. 

The design of drilled shaft shall consider the  limits on total and differential settlement caused by  the  structure  loads.  Settlement  induced by  the drill  shaft group  in  the  subsoil shall  be  evaluated.  In  addition,  settlement  of  the  individual  drill  shaft  shall  also  be evaluated. The  foundation  shall be designed  to keep  the  settlement within  the allowable values as specified in AREMA. 

The drilled shaft design shall consider the effect of negative skin  friction  from existing ongoing  ground  settlement,  liquefaction,  construction  dewatering,  or  shaft  installation. Downdrag loads shall be determined by considering the load transfer distribution along the drilled  shaft  as well  as  the  group  layout.  The magnitude  of  the  downdrag  load  shall  be applied as additional dead load on the deep foundation.  

An adequate amount of testing  as specified in Section 4.7.2.1 will be required for drilled shaft  to  evaluate  foundation  capacity  and  integrity,  to  verify  design  assumptions,  to determine  foundation  installation  characteristics,  to  evaluate  the  foundation  installation system performance, and to establish foundation depths. The testing and monitoring shall include  all  necessary  test  shafts,  dynamic  testing,  static  load  testing,  non‐destructive integrity testing and quality control testing. Testing and monitoring of drilled shaft shall be in accordance with the applicable ASTM and AREMA.  

For drilled shaft foundations, include the following information in the Foundation Design Report: 

1.  Nominal Axial Compressive Resistance and resistance factors 

2.  Factored Axial Compressive Resistance 

3.  Nominal Uplift Resistance and resistance factors 

Page 56: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐51 

Part 3 Project RequirementsJuly 18, 2013

 

 

4.  Factored Uplift Resistance 

5.  Top of Drilled Shaft elevation 

6.  Top of Rock Socket Elevation 

7.  Tip of Drilled Shaft Elevation 

8.  Drilled Shaft Diameter 

9.  Rock Socket Diameter 

10.  Reinforcement Cage cross sections 

11.  Concrete and reinforcement steel properties 

2.   Micropiles 

Micropiles are defined as small diameter drilled and grouted non‐displacement pile with a  reinforcing casing and a center  reinforcing bar. Permanent casings and  load  testing are required.  Micropiles  shall  be  analyzed  for  both  vertical  capacity  and  the  lateral  load capacity.  For  vertical  capacity,  axial  compression  and  uplift  resistance  shall  be  designed using static analysis methods  in accordance with FHWA micropile design and construction guidelines. Deep foundation capacity and serviceability requirements under seismic loading will  conform  to  the  requirements  specified  in  AREMA  Volume  II,  Chapter  9.  A micropile specialty Subcontractor is required for design and construction of micropiles.  

Micropiles  shall also be designed  to adequately  resist  the  lateral  loads  transferred  to them  from the structure without exceeding the allowable deformation of the structure or overstressing  the  foundation  elements.  The  lateral  load  resistance  of  the  individual  and group  of micropile  elements  shall  be  analyzed.  The  analysis  shall  consider  nonlinear  soil pressure‐displacement relationships, soil/structure  interaction, group action, groundwater, and cyclic and static and dynamic load conditions. The performance evaluation of micropile shall  include the determination of vertical and horizontal movements, rotation, axial  load, shear, and bending moment for the foundation elements. 

The  design  of micropile  shall  consider  the  limits  on  total  and  differential  settlement caused by  the  structure  loads.  Settlement  induced by  the micropile  group  in  the  subsoil shall  be  evaluated.  In  addition,  settlement  of  the  individual  drill  shaft  shall  also  be evaluated. The  foundation  shall be designed  to keep  the  settlement within  the allowable values as specified in FHWA micropile design and construction guidelines. 

The micropile  design  shall  consider  the  effect  of  negative  skin  friction  from  existing ongoing ground settlement, liquefaction, construction dewatering, or micropile installation. Downdrag loads shall be determined by considering the load transfer distribution along the micropile as well as the group layout. The magnitude of the downdrag load shall be applied as additional dead load on the deep foundation. 

Subcontractor shall submit documentation before the start of construction that he has successfully completed at least three micropile projects and at least installed 150 micropiles within the last three years with micropile diameters and lengths similar to those anticipated 

Page 57: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐52 

Part 3 Project RequirementsJuly 18, 2013

 

 

for this project.  Documentation shall include the general contractor and owner’s name and current  contact  information  with  descriptions  of  each  project.    A  design  geotechnical engineer  is  required  to  design  micropiles.    The  design  engineer  shall  be  a  licensed Professional Engineer in the State of New York and shall have at least 10 years of experience in designing micropiles and drilled foundations with capacities and in subsurface conditions similar to those of this project.  

Double corrosion protection shall be provided to micropile central reinforcing steel bar in accordance with FHWA‐SA‐97‐070  recommendations. Maintain a minimum of 3  inches grout  cover  to  the  reinforcing  bar  along  the  entire  length  of  the  micropile.  Galvanize exposed reinforcing and permanent casing that connect directly to caps in accordance with FHWA micropile design and construction guidelines.    

For Micropile  foundations,  include the  following  information  in the Foundation Design Report: 

1.  Micropile  layout, diameter,  inclination, minimum  reinforcing  casing and  center rebar, and pile to cap connection 

2.  Micropile  tip  elevations,  and  bond  lengths.  The  rock  socket  shall  have  a minimum bond  length of  ten  feet  in Class 1b  rock. Neglect  tip  resistance  in  tension  and compression 

3.  Nominal Axial Compressive Resistance and resistance factors 

4.  Factored Axial Compressive Resistance 

5.  Nominal Uplift (tension) Resistance and resistance factors 

6.  Factored Uplift Resistance 

7.  Nominal Lateral Resistance and resistance factors 

8.  Factored Lateral Resistance   

Do not install reinforcing casing or begin drilling within six times pile diameter, center to center or  five  feet, whichever  is  greater until grout  in piles  reaches  initial  set. Grout  the micropiles the same day the bond length is drilled. 

  3.  Existing Drilled Shaft 

During the preliminary field  investigation, two test pits were excavated along the west side of the existing station building to expose existing drilled shaft  foundations. A total of two  foundation cores were  retrieved  from  the existing drilled  shaft, one at each  test pit. Laboratory testing was performed on the core samples  including petrography and uniaxial compressive strength with static moduli. The  laboratory testing results are  included  in the Geotechnical Data  Report  of  the  Request  for  Proposal  package.  The Design‐Builder  shall assess the condition of the existing drilled shaft and evaluate the possibility of reusing the existing foundation to support the new building structure.   

Foundation Load Testing  

Page 58: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐53 

Part 3 Project RequirementsJuly 18, 2013

 

 

The  Design‐Builder  shall  carry  out  sufficient  axial  load  tests  to  verify  the  design  nominal resistance  for each production micropile/shaft  type, diameter  and  subsurface  condition  type (specifically, either  founded within soil only, or  founded within or upon  rock).   For each  type and diameter of micropile/shaft per subsurface condition type, a minimum of 5% of the total number of micropiles/shafts but no less than one static load test shall be performed. 

After  completion  of  a micropile/shaft  load  test,  the  Design‐Builder  shall  be  responsible  for either fully removing the test pile from the ground or for cutting off the test pile at 2 feet below final grade. 

Load Testing for Drilled Shaft 

Install one  load  test drilled shaft prior  to  installation of production drilled shafts.   Select  test locations  to  represent different  subsurface conditions and/or  construction methods. Perform axial compression  load  test  for each drilled shaft size based on site variability.    If  the Design‐Builder chooses to alter construction methods, an additional axial load test will be required on a  test shaft constructed with  the new method.   Perform axial  load  tests using Osterberg Cell load equipment in accordance with ASTM D1143.  

Perform  integrity  testing  on  all  test  shafts  and  production  shafts.    At  a minimum,  integrity testing requirements shall comprise Crosshole Sonic Log (CSL) testing on all drilled shafts. 

Load Testing for Micropiles 

Install load test micropile to demonstrate micropile subcontractor’s ability to successfully install micropiles.    Select  test  locations  to  represent  different  subsurface  conditions  and/or construction methods.   Perform axial compression  load  test  for each micropile size based on site variability.  If the Design‐Builder chooses to alter construction methods, an additional axial load test will be required on a test micropile constructed with the new method.  

Load Testing Report 

The  Design‐Builder  shall  prepare  a  Micropile/Shaft  Geotechnical  Nominal  Resistance  Test Implementation  Report  containing  test  procedures,  instrumentation  plan  including measurements  along  the  micropiles/shafts,  calibration  procedures,  test  micropile/shaft locations, micropile/shaft sizes, and  types being  tested and equipment used.   At a minimum, drilled shaft load test piles shall be instrumented along the length to establish load transfer (t‐z) curves for each soil layer and (q‐z) curve for the bearing layer(s). Include crosshole sonic logging results for drilled shafts.  

The  Design‐Builder  shall  prepare  a  Micropile/Shaft  Geotechnical  Nominal  Resistance  Test Results  Report  containing  test  results  per micropile/shaft  size  and  type  tested;  production micropile/shaft installation, and production piling acceptance criteria.  The Design‐Builder shall interpret  the  load  test  results and use  them  in  the Design of Foundation  such  that  the axial deformations of the micropile/shaft do not exceed the structural limit. 

C.  Support of Excavation (Temporary Shoring for Cut‐and‐Cover Tunnel Construction) 

The  Design‐Builder  shall  design  the  temporary  shoring  system  for  the  construction  of  the proposed cut‐and‐cover tunnel in accordance with the guidelines of AREMA Volume II, Chapter 

Page 59: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐54 

Part 3 Project RequirementsJuly 18, 2013

 

 

8, Part 28  and  the publication of Burlington Northern &  Santa  Fe Railway  (BNSF) and Union Pacific  Railroad  (UPRR)  on  temporary  shoring.  Where  conflicts  exist,  the  most  stringent specification should be applied. These shoring systems will be designed to resist all anticipated dead  and  live,  vertical  and  lateral  loads.  These  loads  will  include  those  induce  by  soil, groundwater, live load, surcharge and construction equipment. 

The temporary shoring system shall include anchored soldier beam with lagging wall. Open cut is not allowed. If anchored systems with tie‐backs are used, the relative locations between tie‐backs and existing/future utilities need to be evaluated to ensure no conflict. Ground anchors shall  be  cement‐grouted  tiebacks  designed,  furnished,  installed,  tested  and  stressed  in accordance with the AREMA requirements.  

Temporary  loadings  need  to  be  considered  in  design.  Temporary  loads  include,  but  are  not limited  to  construction  surcharge,  ground  and  groundwater  pressure,  and  live  load  from railroad tracks. 

Loads due to soils shall be derived using the maximum values of the saturated densities. Lateral earth pressures will be estimated on the basis of the anticipated movement of the structure. Active  and  passive  earth  pressure  based  on  Coulomb  earth  pressure  theory will  be  used.  If there is no movement expected, at‐rest earth pressure will be used. The design of the retaining structures  shall  be  based  on  the  maximum  lateral  pressures  that  will  develop  behind  the structures.  

Hydrostatic  pressure  induced  by  the  groundwater  table  shall  be  included  in  the  lateral pressures.  

Lateral pressure induced by surcharge loads applied at the ground surface behind the wall shall be included as appropriate. These surcharge loads will be evaluated on a site‐specific basis, and will include uniform surcharges, strip loads, line loads, point loads, area loads, train loads, and construction equipment loads. 

Structures and structural members shall be designed to have design strengths at all sections at least equal to the required strengths calculated for the loads and forces in such combinations as stipulated  in AREMA Volume  II, Chapter 8, Part 2, which  represents  various  combinations of loads and group loads that are applicable and the load combination that requires the maximum strength shall be used. Stability analyses shall be conducted in accordance with AREMA Volume II, Chapter 8, Part 28 for all temporary shoring structures.  

For  an  anchored  system with  tiebacks,  requirements on embedment depth,  allowable  stress and tiebacks need to be satisfied in accordance with the AREMA specification.   

For braced excavation, it shall be designed using the apparent earth pressure diagram indicated in AREMA Volume II, Chapter 8, Part 28.5.5. 

Calculated deflections of  temporary shoring system and  top of rail elevation shall not exceed the criteria outlined in Table 1 of Design Guideline for Temporary Shoring (BNSF and UPRR). 

Horizontal distance from  Maximum horizontal  Maximum acceptable 

Page 60: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐55 

Part 3 Project RequirementsJuly 18, 2013

 

 

When evaluation indicates that the support of excavation system may be insufficient to protect structures adjacent to support of excavation, direct support of structures by underpinning shall be evaluated.  Underpinning methods to be evaluated include: 

1.  Pit underpinning 

2.  Jacked pile underpinning 

3.  Micropile underpinning 

For support of excavation, include the following information in the support of excavation design report: 

1.  Location of support o excavation system  

2.  Support of excavation type 

3.  Support of excavation shoring member size 

4.  Support of excavation embedment depth 

5.  Bending stiffness (EI) and axial stiffness (AE) of bracing elements 

6.  Lateral earth pressure distribution 

7.  Design  calculation  of  tieback,  including  anchor  number  and  location;  load  for  each ground  anchor;  Inclination  angle;  type  and  size  of  ground  anchor; minimum  bonded length; and minimum stressing length 

8.  Design of grout mix including non‐shrink additives and compressive strength test results from a certified testing laboratory 

D.  Cut‐and‐Cover Tunnel  

A pedestrian/luggage tunnel connecting the station building and the high‐level platform will be designed and constructed for the project. The approximate dimension inside the tunnel is 20 ft wide,  11  ft  high with  an  invert  at  approximately  18  ft below  grade. Although  there may be different ways to construct the tunnel, only the cut‐and‐cover method is allowed and assumes that sufficient track outages will be staged to allow for construction. Sufficient track outage  is defined as  the  two  tracks between  the  station building and  the high‐level platform  removed from service for a time period of ________.   

The construction sequence for the cut‐and‐cover tunnel is: 

shoring to track C/L measured at a right angle from track 

movement of shoring system  horizontal or vertical movement of rail 

12’ < S < 18’  3/8”  1/4” 

18’ < S < 24’  1/2”  1/4” 

Page 61: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐56 

Part 3 Project RequirementsJuly 18, 2013

 

 

1.  Remove the two tracks between the station building and the high‐level platform  from service 

2.  Install support of excavation along the perimeter of the cut‐and‐cover tunnel 

3.  Construct the cut‐and‐cover tunnel 

4.  Restore ground and track substructure and track and restore service to the two tracks 

The Design‐Builder will design the cut‐and‐cover tunnel in accordance with the requirements of AREMA.  

The  required  loading  and  forces  for  design  shall  follow  the  Structural  Design  Guidelines  in Chapter   ___   taking    into   account   the   effects   of   construction   staging   on   existing   and  new construction. In addition to the loads and forces in Chapter ___, the following loads should be considered. 

1.  Computation of backfill pressures shall be as per AREMA, Volume  II, Chapter 8, Part 5. Concentrated loads on below grade walls to include, but not limited to, railroad loading and foundations, shall be superimposed. 

2.  Loads due to soils will be derived using the maximum values of the saturated densities. The submerged densities will be used for soil unless the  location  is above the standing water table. 

3.  Horizontal  ground pressure  for  tunnels  in  soil  shall be determined  from  at‐rest earth pressure theory. Horizontal ground pressure for mixed‐face profiles in soil and rock are not expected.   

4.  The  effects  of  hydrostatic  pressure  and  buoyancy  shall  be  considered whenever  the presence of groundwater  is  indicated. During construction and backfill operations,  the elevation of groundwater shall be   observed   and   controlled   so   that   the   calculated  total  weight  of  structure  and  backfill  shall always exceed the calculated uplift due to buoyancy by at  least 10%. The design shall  take  into account  the effect of hydrostatic pressure  pertaining  to  possible  construction  sequences.  The  backfill    shall    be  considered  as  the  volume  contained  within  vertical  planes  defined  by  the outside limits of the structure. No value shall be assigned to contact soil friction. 

Construction joints shall be formed at such locations where they won’t reduce the effectiveness of the lining to resist pressure from surrounding earth or rock. Expansion joints are not required where construction joints are provided. Waterstops shall be provided as necessary.  

The Design‐Builder  shall over‐excavate  a minimum of 5  ft below  the design elevation of  the bottom  of  the mud  slab  and  backfill  with  structural  fill which  is  compacted  in  lifts  to  the elevation of the mud slab bottom.  

The  differential  settlement  of  the  cut‐and‐cover  tunnel  shall  not  exceed  1/4  inches  and  the angular distortion is less than 1/500.  

Page 62: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐57 

Part 3 Project RequirementsJuly 18, 2013

 

 

6.10  Construction Requirements 

Deep Foundation Installation Records 

As  part  of  the  As‐Built  Plans,  the  Design‐Builder  shall  provide  installation  records  for  all foundations installed.   

For drilled  shafts,  the  installation  records  shall  include drilling equipment used,  temporary and permanent  casing, materials encountered, bottom  cleaning, SID  results,  top and bottom elevations,  shaft and  socket dimensions, and  concrete placement  time.   For all drilled  shafts with rock sockets or bearing on rock, the rock socket and the base of the drilled shaft shall be inspected  utilizing  an  underwater  video  recorder  or  other means  f  of  inspection which will provide equal or better inspection results. The video recorder shall be capable of capturing the depth of the recording. A digital copy of the video recording shall be submitted to the client as part of the drilled shaft installation record. 

Dewatering and Groundwater Control 

The Design‐Builder shall be responsible for developing a substantially dry and stable subgrade for  the prosecution of  subsequent operations by  implementing dewatering and groundwater control measures  as  appropriate.  The  groundwater  condition  shall  be maintained  in  a way causing no damage to adjacent facilities, railroad infrastructure and other work. 

Condition Surveys (Pre‐ and Post‐ construction survey) 

Pre‐Construction Condition Survey 

The  Design‐Builder  shall  conduct  a  pre‐construction  inspection  and  survey  of  the  existing condition  of  all  structures  and  properties  for  the  purposes  of  generating  photographic  and video  documentation  of  existing  damage,  leaks  and  cracks.    The  pre‐construction  condition survey shall form the basis against which all new cracks, existing progressive cracks, or damage will  be measured.    The  spatial  extent  of  the  pre‐construction  survey  shall  encompass  the Project Limits plus certain areas beyond the Project Limits, as detailed herein.   

The  full  spatial  extent  of  the  Design‐Builder’s  pre‐construction  condition  survey  necessarily depends upon the Design‐Builder’s design and proposed means and methods of construction.  In  its preparation  for  the pre‐construction  survey,  the Design‐Builder  shall be  responsible  for predicting  anticipated  vibration  and  settlement  effects  at  various  offset  distances  from  the Project Limits, and  for ensuring  that  the pre‐construction condition  survey encompasses at a minimum all properties within areas that are identified by the Design‐Builder to be potentially prone to: (i) ground vibration  levels, expressed as resultant peak particle velocity,  in excess of 0.50 inches per second; and (ii) predicted ground settlements of greater than ¼ inch. .  

The  Design‐Builder  shall  submit  to  the  client  the  records  and  photographic  and  video documentation of the pre‐construction condition survey, which shall be signed and stamped by a Professional Engineer registered in the State of New York. 

Post‐Construction Condition Survey 

Page 63: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐58 

Part 3 Project RequirementsJuly 18, 2013

 

 

The  Design‐Builder  shall  conduct  a  post‐construction  condition  survey  of  the  zone  and properties  covered by  the pre‐construction  conditions  survey  (see  Section 5.5.1 herein). The post‐construction  condition  survey  shall  be  performed  by  the  Design‐Builder  at  Physical Completion, and it shall compare the post‐construction conditions with the conditions recorded in  the  pre‐construction  condition  survey.    The  location  and  scope  of  the  post‐construction condition  survey  shall match  those  of  the  pre‐construction  condition  survey.    The  complete documentation  of  the  post‐construction  survey,  describing  the  comparison  with  the preconstruction conditions and signed by a Professional Engineer registered in the State of New York, shall be submitted to the client. 

 

SECTION 7.  TEMPORARY FACILITY REQUIREMENTS  

The  Design  Builder  shall  enable  Amtrak  to  provide  uninterrupted  service  to  Rochester passengers.    The  Design‐Builder  shall  establish  an  operational  and  fully  ADA  compliant temporary station facility prior to the demolition of the existing Rochester Station.  This station shall include: 

A. A triple‐wide trailer containing essential station operation functions: 1. Accessible entries on  the parking  lot and  track  sides of  the  station,  including  stairs, 

ramps, platforms with guardrails and handrails. 

2. A Waiting Area of 950 sf, containing between 38 and 44 fixed seats. 

3. Men’s and Women’s single‐occupancy ADA accessible public restrooms. 

4. Dual height drinking fountain 

5. Provisions for a minimum of 3 vending machines and 1 Quik‐Trak self‐service ticketing machine 

6. Amtrak standard wall‐mounted PIDS display 

7. A minimum ceiling height of 9 feet throughout 

8. A  ticketing office with a single workstation and pass‐through stainless steel baggage counter  with  built‐in  scale  relocated  from  the  existing  station.    Ticketing  shall  be secured from Waiting with glass panels while open and a roll‐down grille when closed. 

9. Ticketing shall be secured from the Baggage area with a door. 

10. Baggage  area  shall  be  directly  accessible  from  the  exterior with  a  roll‐up  door.    A separate ramp shall be provided for use for baggage only. 

11. Passenger and baggage paths to the boarding platform shall be segregated. 

12. Back‐of‐house  spaces  to  include  an  office  with  closets  and  utility  connections, employee  break  area  with  kitchenette  and  a  minimum  of  8  lockers,  and  unisex employee restroom. 

13. Include  interior  and  exterior windows  in  all  locations  depicted  on  the  preliminary plans. 

14. Temporary station facility must have a security system compatible with Amtrak SDP. 

Page 64: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐59 

Part 3 Project RequirementsJuly 18, 2013

 

 

15. Provide an exterior storage shed for equipment, minimum 10 feet x 20 feet 

16. Include screened dumpster enclosure for both garbage and recycling. 

17. Provide bollards at the station entry to protect passengers from vehicular traffic. 

B. Provide a separate trailer for IT requirements 

C. Design‐Builder shall provide adequate accessible parking spaces during construction in the parking  location closest to the station entry.   The Design‐Builder shall allow  for potential relocation  and  restriping  of  accessible  parking  throughout  construction,  as  the  location closest to station entry may change. 

D. The  existing  low  level  platform  will  be  extended  and  utilized  for  the  duration  of construction.   Design‐Builder shall provide a continuously safe and accessible path to the boarding platform for the duration of construction.  

E. Provide barriers at  trailer hitches  to protect passengers  from  injury and equipment  from vandalism. 

F. All trailers shall be weather tight and protected from extreme cold and drifting snow. 

G. All trailers shall have provisions to prevent water and sewer lines from freezing in extreme temperatures. 

H. The Design‐Builder shall provide code compliant exterior  lighting surrounding the station, parking areas, pedestrian paths, and platform throughout all phases of construction. 

SECTION 8.   TRACK AND PLATFORM REQUIREMENTS 

  8.1    Track Requirements 

A.  The Design Builder shall contact CSXT and arrange Roadway Worker Protection Training for all employees that will work within 15 feet of  live tracks at any time. The Contractor shall establish  requirements with  the  CSXT  Resident  Engineer  in  charge  and  follow  all  safety requirements of CSXT in terms of flagging, fouling, rigging and trackway access restrictions. Contractor  shall prepare  site‐specific work plans  for  review and approval by CSXT before commencing work when  the work or  any part of  the  equipment used  in  conducting  the work is within 15 feet of live tracks. 

B.  The Design Builder shall survey the proposed  locations of the new main and siding tracks. The Design Builder shall dig a minimum of two test pits along the alignment of each of the new tracks, a minimum of 6 feet deep, and have the soil conditions evaluated on‐site by a licensed geotechnical engineer  for suitability  for supporting heavy haul railroad roadbeds. Issue findings, including data, and recommendations in a letter report to NYSDOT. 

C.   The Design Builder shall advance order adequate materials to construct the new main and siding tracks to the limits indicated in the Contract Drawings. These materials shall include, but  not  be  limited  to, new  136RE welded  rail,  timber  ties,  Pandrol  plates with  clips  and screw spikes, insulated joints, field weld kits, ballast, subballast and other track materials. 

Page 65: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐60 

Part 3 Project RequirementsJuly 18, 2013

 

 

D.  The Design  Builder  shall  prepare  the  roadbed  by  consolidation  to  project  specifications, followed by installation of subballast and bottom ballast layers for all tracks, including those to be built later by CSXT, within the limits shown.  

E.  The Design Builder shall construct tracks S1, S2 and M1 to the limits shown on the Contract Drawings,  in  full  compliance with  CSXT  flagging  and  contractor  safety  requirements.  All tracks shall be  fully welded, with no  joints except  insulated  joints remaining when  turned over.  All  tracks  shall  be  surfaced  and  aligned  to  final  profile  and  alignment  and  in compliance with Amtrak MW1000 requirements for new construction. For 200 feet at each end of each track at project work limits, the track shall have ballast in place to the bottom of tie below final elevation so that CSXT forces may complete the final  lift after they have installed the connecting tracks.  

F.   The Design Builder shall install grade crossings at the locations indicated for the purpose of construction access and permanent emergency personnel and emergency vehicular access. Permanent Emergency Crossings shall be full depth   extruded rubber rail seal mounted on both  sides  of  each  running  rail  and  must  be  new  at  the  conclusion  of  the  contract. Temporary  crossings  shall  be made  of  timber  and  asphalt, with  safety  and maintenance being the responsibility of the Design‐builder for the duration of the contract. 

 

8.2    High Level Platform Requirements 

A.  Platforms shall be designed and  installed to an elevation 48  inches above the final top‐of‐rail plane, at a setback from track centerline that considers track curvature, superelevation, and  railcar dynamic  loading. Given  that  track will be on superelevated curves and spirals, the Design Builder  shall analyze  the  track alignment and  calculate horizontal and vertical platform edge elevations at 10‐foot  intervals along both platforms. The final edge distance to center of track must be submitted to and approved by NYSDOT. 

B.  Platforms shall be installed in compliance with Amtrak and ADA standards. 

 

8.3    Bridge Modification Requirements 

A. The  Design  Builder  shall  be  responsible  for  all  Work  necessary  for  the  design  and construction of all permanent and  temporary  structures,  including  the widened bridge at Clinton Avenue and  the  structural  retrofitting of  the  floor  system at St. Paul Street.   The design  and  construction  of  all  structural  systems  and  components  shall  provide functionality, durability, safety, and aesthetics to match existing facilities.  

B. The scope of work for bridge modification includes the following items: 

• Widening of internal portions of the existing Clinton Avenue Bridge to the limits shown on  the  Indicative Plans  to accommodate  the proposed  locations of  the new main and 

Page 66: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐61 

Part 3 Project RequirementsJuly 18, 2013

 

 

siding tracks.  The components of the bridge widening shall be designed, at a minimum, Cooper E60 at the location of the widening. 

• Retrofit of existing structural floor system at St. Paul Street Bridge to the  limits shown on  the  Indicative  Plans  to  strengthen  the  bridge.  The  bridge modifications  shall  be designed to increase the strength of the bridge to a minimum rating of Cooper E60.   

C. The Indicative Bridge Plans, provided to the Design Builder, convey a conceptual solution to the Project’s needs that the Design Builder may choose to consider in developing a design.  The Design Builder’s adaptation of the design concepts shown in the Indicative Plans are not mandatory, but are representative of the general project configuration.  The Design Builder shall develop design solutions that achieve the Project Requirements.  

D. Prior  to design and construction activities,  the Design Builder  shall  familiarize  themselves with  the condition of all bridges within  the project area and  shall perform all  survey and field measurements necessary to support the design of bridge modifications and support of the high  level platform across  the bridges.     The design  for  the modification  to bridges at Clinton Avenue and St. Paul shall be similar to and compatible with design to the existing structures.     The design of  the high  level platform  identified  in Section 8.2 above and  the bridge widening at Clinton Avenue shall be designed and constructed to be compatible.  The design of the widened section of the Clinton Avenue bridge and the loading of the high level platform  shall be determined and used  together  to provide an appropriate design of  the proposed high level platform across the bridge and bridge widening.    

E. Bridge  structure  modifications  shall  be  determined  and  designed  by  a  NYS  licensed Professional Engineer.  Bridge structural systems shall comply with all applicable codes and regulations even if not explicitly listed in this document. 

 F. All  loads  and  load  combinations  shall  be  compliant  and  adhere  to  Amtrak  and  CSXT 

guidelines  and  the  American  Railway  Engineering  and Maintenance  of Way  Association Manual for Railway Engineering (AREMA) 

 

G. In addition to these requirements, the Design Builder must comply with all other applicable engineering  codes and  standards,  including  those of  the  various  Federal,  State, and  local jurisdictions.  

Page 67: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐62 

Part 3 Project RequirementsJuly 18, 2013

 

 

H. The Design builder must comply with all regulation and obtain all permits necessary  from the  City  of  Rochester  to  complete  the  required work  including MPT  and  any work  zone protection. 

 I. All work shall conform  to current versions of  the  following documents.   Where necessary 

the State shall provide or make available to the Design Builder either the full document or guidance extracted  from  it.    In  the event of  a  conflict between  the  codes  and  reference documents  listed  below,  the  more  stringent  requirements,  as  determined  by  the Department, shall apply. 

 AASHTO: 

• A Guide for Accommodating Utilities within Highway Right‐of‐Way 

• A Policy on Design Standards ‐ Interstate System 

• A Policy on Geometric Design of Highways and Streets 

• Construction Handbook for Bridge Temporary Works 

• Guide Design Specifications for Bridge Temporary Works 

• Guide Specification for Bridge Railings (1989) 

• Guide Specification for Fatigue Evaluation of Existing Steel Bridges 

• Guide Specifications for LRFD Seismic Bridge Design 

• LFRD Bridge Construction Specifications 

• LFRD Bridge Design Specifications 

• Manual for Assessing Safety Hardware (MASH) 

• Manual for Bridge Evaluation 

• Manual for the Condition Evaluation of Bridges 

• Manual on Subsurface Investigations 

• Roadside Design Guide 

• Standard Specifications for Highway Bridges 

• Standard  Specifications  for  Structural  Supports  for  Highway  Signs,  Luminaires  and Traffic Signals   

AEMA 

• Recommended Performance Guidelines AMTRAK 

• Engineering  Practices  3014 Maintenance  and  Protection  of  Railroad  Traffic  During Contractor Operations 

• Engineering Practices  Section 01141A  Safety and Protection of Railroad Traffic and Property 

Page 68: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐63 

Part 3 Project RequirementsJuly 18, 2013

 

 

SECTION 9  ARCHITECTURAL REQUIREMENTS 

The new Rochester Station shall be a multi‐phase intermodal facility constructed on the site of the existing Amtrak Rochester Station (ROC) temporary facility built in 1978.  The overall design shall  provide  a  landmark  structure  at  the  entry  to  downtown  Rochester,  reflective  of  the character of the former 1914 Claude Bragdon Union Station on this site.   

The  building  and  site  design  shall  be  fully  accessible  and  shall  present  a  unified  setting, exhibiting  cohesion  between  both  Phases  I  and  II  of  construction.    The Design‐Builder  shall ensure the final design reflects the existing and developing architectural standards and facility requirements  of Amtrak  and  Trailways.  The  architectural  design  shall  be  efficient  and  avoid surplus and redundancy for a cost‐efficient end result, while also responding to  input that has been received from the Rochester community. 

9.1  Code Requirements and Design Standards 

A code analysis report shall be prepared by the Design‐Builder indicating how each element of the project shall comply with all applicable codes and standards.  This report shall be based on the most current edition of each code or standard  in effect at the time of commencement of construction  of  the  facility.    Specific  attention  should  be  given  to  the  requirement  for compliance with all aspects of the IgCC. Where codes or standards may be considered to be in conflict, the more stringent requirement shall be applied. 

A. Building Code of New York State, 2010 Edition 

B. Electrical Code of New York State, 2010 Edition 

C. Mechanical Code of New York State, 2010 Edition 

D. Plumbing Code of New York State, 2010 Edition 

E. Fire Code of New York State, 2010 Edition 

F. Property Maintenance Code of New York State, 2010 Edition 

G. Energy Conservation Construction Code of New York State (ECCCNYS), 2010 Edition H. National Fire Protection Association  (NFPA) No. 130: Standard  for Fixed Guideway Transit 

and Passenger Rail Systems 

I. Occupational Safety and Health Administration (OSHA) 

J. American with Disabilities Act (ADA) 

K. ADAAG 2006 Edition for Transportation Facilities 

L. American National Standard Institute (ANSI) 

M. Zoning Code of the City of Rochester N. City of Rochester’s Project Green plan O. State  of  New  York  Executive  Order  No.  4:  Establishing  a  State  Green  Procurement  and 

Agency Sustainability Program 

P. State  of  New  York  Executive  Order  No.  88:  Directing  State  Agencies  and  Authorities  to Improve the Energy Efficiency of State Buildings 

Page 69: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐64 

Part 3 Project RequirementsJuly 18, 2013

 

 

Q. New  York  State  Department  of  Transportation  Leadership  in  Transportation  and Environmental Sustainability “GreenLITES” Certification Program  

R. Amtrak Station Program & Planning  ‐ Standards and Guidelines:   Station Manual, Version 2.2 

S. Amtrak Engineering Stations – Standard Design Practices (SDP), issued June 14, 2012 

T. Amtrak Medium Station Prototype drawings and documents 

U. International Green Construction Code  (IgCC), 2013 Edition  (Note:  IGCC requirements and their application are outlined within the Amtrak Engineering Stations – SDP.) 

V. Amtrak Environmental Health and Safety Report, 2011 

W. Amtrak Graphic Signage Standard Manual 

X. Amtrak Police Department’s Corporate Security Design Recommendations 

Y. Amtrak Premise Distribution Standards (ATT) 

9.2  Description of Proposed Facility   

The proposed Rochester Station concept recalls significant visual aspects of the  former Union Station complex that previously occupied the site and was demolished  in the mid‐1970s, with attention given to the scale and proportion of the current project program and budget relative to the scale and program of the former station.   There  is a strong community support for this design approach.   Accordingly,  the proposed design shall  recreate  the  three major north and south facing arched windows that were a central part of Claude Bragdon’s design,  inspired by the driving wheels of a locomotive.   

The Design‐Builder shall allow for this endeavor to be constructed in two phases.  Phase I shall address  the  new  Amtrak  station  functions,  generally  including,  but  not  limited  to  site improvements, parking, and access  to a new high  level center  island platform.   Phase  II shall consist  of  station  expansion  to  create  the  Trailways  portion  of  the  station,  bus  loop,  and redevelopment  of  southern  parcel  of  the  site  and  additional  parking  where  the  existing Trailways facility is situated.  Although construction of the Rochester Station shall consist of two distinct phases,  it  is  imperative that the finished product be aesthetically unified and that the first phase stands on its own both functionally and aesthetically.  

A preliminary design has been developed with attention to the goals of the community to foster livability, sustainability, and  future development  in  the Station’s neighborhood.   To provide a landmark structure at the end of Downtown Rochester, the station building shall be sited such that  it  sits within  the  “downtown  sightline”  corridor,  providing  unencumbered  views  of  the station when  traveling North  Clinton  Avenue  and  providing  connectivity  to  the  new  RGRTA Mortimer Street Transit Center and other downtown  landmarks.   Additionally,  to provide  the shortest  practical  passenger  and  baggage  travel  distance  possible,  the  station  shall  be  sited both parallel and as close as possible to the existing tracks. 

The Rochester  Station building  shall  consist of  a  ground  level  and  concourse  level within  an approximate 12,000 square foot building footprint accommodating the program requirements of  Amtrak  and  Trailways  operations.    Shared  functions  such  as  the waiting  area  and  public 

Page 70: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐65 

Part 3 Project RequirementsJuly 18, 2013

 

 

restrooms shall occupy prominent areas of  the ground  floor,  facing  the downtown Rochester corridor.   Every effort shall be made  to consolidate common spaces between  the  two  to  the degree functionally desirable by the separate mode operators to achieve a cost‐effective design that is functionally responsive to the program requirements.   Further, the facility shall be fully ADA compliant and shall promote easy transfer between modes of transportation. 

Utilities, storage, and, most critically, clear and visually unobstructed circulation between  the station building  and  the platform  shall be housed below  grade  at Concourse  Level.  The  two levels shall be connected by vertical circulation elements: stairs, escalator, and elevator at both ends of the Concourse.  These circulation elements shall be easily identified and shall be nearby upon entering the station.   

Improvements shall also be made to the area  immediately surrounding the station building to incorporate pedestrian, bicycle, and vehicular circulation, as well as storage for buses and cars.  The  site  design  shall  incorporate  softscape  to  the  greatest  extent  possible,  eliminating  any unnecessary  paving  and  providing  a  friendly  space  for  pedestrians,  especially  within  the “downtown sightline” corridor. 

9.3  Façade Elements 

A central element to the glazed triple arch station façade  is a clock suspended  in front of the center arch.  The Design‐Builder shall design to accommodate, and shall coordinate and install the historic clock from the former 1914 Bragdon station, if that clock becomes available.   

 

If  this historic clock does not become available,  the Design‐Builder shall provide and  install a clock  as  depicted  on  the  Preliminary  Design  documents.    The  Design‐Builder  shall  be responsible  for  furnishing  and  installing  a  functioning  clock  of  the  scale  indicated  on  the Preliminary Design documents and of a quality consistent with the historic clock.   Design and fabrication drawings shall be subject to the approval of the Department. 

9.4  Station Ground Level 

The Preliminary Design documents include a functional station building layout.  The main areas to be located on the first floor of the station shall include: 

A. Waiting Area B. Customer Information Kiosk C. 2 Retail Spaces D. Vending Area and an on‐site ATM E. Public Toilet Facilities, including Family Restroom and drinking fountains F. Separate Ticketing for Amtrak and Trailways G. Separate Baggage Handling for Amtrak and Trailways H. Amtrak Baggage Claim with a  concealed  roll‐down  security  shutter  (closed open  type 

with no view inside) I. Amtrak Offices and Break Room J. Separate Employee Restrooms for Amtrak and Trailways 

Page 71: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐66 

Part 3 Project RequirementsJuly 18, 2013

 

 

K. Trailways Offices and Break Room 

A generous waiting area  is  important  to  the  station building  layout.   The  remaining program elements are to be placed around it for ease of circulation.  At completion of Phase II, waiting shall  total  approximately  2,750  SF  with  seating  for  approximately minimum  of  151  shared Amtrak and Trailways patrons.  Several convenience and comfort amenities shall be offered to patrons, including ATM, Quik‐Trak Self‐Ticking, Vending, and Wi‐Fi connectivity. It is critical that a closely coordinated arrangement of concourse access, ticketing, and waiting be achieved to create a feeling of connectivity between these elements. 

Two tenant retail spaces shall be  located directly off the waiting room, with storefronts facing the  main  entrance  of  the  station  building.    The  Design‐Builder  shall  provide  “vanilla  box” construction  inside  the  space,  finishing  the  perimeter  walls  with  taped  and,  spackled,  and painted gypsum board, a concealed roll‐down security shutter (closed open type with no view inside),  lighting and emergency  fixtures, electrical panel, and HVAC.   Each  tenant  space  shall have  a  separate  rear  entrance  to  allow  for  deliveries  and  trash  removal  out  of  public  view.   Tenancy  leasing  shall  be  coordinated  by  the  Amtrak  Real  Estate  division  and  based  on  the demographics and needs of ridership.  The Design‐Builder shall be responsible for ensuring that each retail tenant space and the Trailways spaces are metered separately from Amtrak space.   The Design‐Builder shall provide temporary and movable taped, spackled, and painted gypsum board partitions as shown on the Preliminary Design drawings.   These partitions will allow the Department to utilize the retail spaces for display for promotional, marketing, or local artwork until such time as tenant agreements have been signed. 

Ticketing for Amtrak must be immediately visible and easily identified upon entering the station building.  With connectivity to the waiting area and the auxiliary comfort facilities, the ticketing area is the transition point between the public and private programs ‐ The ticketing area must service  the  public  while  supporting  the  back  of  house  functions  behind  the  scenes.    The ticketing office shall provide: 

A. ADA‐compliant  ticketing  area  for  two  staff  positions,  with  one  baggage  check‐in workstation. Stations shall be 6 linear feet long each. 

B. Low counter for baggage transfer scale 

C. Cash drawers in built‐in casework and desktops with operable glass cover for schedules 

D. Baggage scale E. Rear countertop with cabinetry for storage of supplies 

F. Provide and install clear and frosted glass transaction windows per Amtrak Standards 

G. CCTV monitors shall be visible from all ticketing workstations 

H. Telephone and data connections for computers, phones, printers 

I. Power for CPU’s, ticketing terminals, and ticket printers 

J. Direct access to the Baggage Work Room and Baggage Claim.  Note: Baggage Claim must receive finished gypsum board ceiling (no suspended acoustic panel system) to ensure the security of items stored in this room. 

K. Access to Waiting Room 

Page 72: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐67 

Part 3 Project RequirementsJuly 18, 2013

 

 

Other Amtrak back‐of‐house spaces include: 

A. Lead Clerk’s office, near Ticketing, with closet to house safe 

B. Records Storage 

C. Employee Break Room sized to fit 5 people at one time, including a kitchenette with full‐size refrigerator,  (8) 18” D x 12” W  full‐height  lockers with ventilated doors.   Room to include PA system interface. 

Public restrooms shall be sized to exceed code requirements for minimum number of plumbing fixtures, accommodating the increase in demand when a train and/or bus arrive at the station.  The Design‐Builder shall include at least 2 additional water closets and 1 additional lavatory for each sex beyond code minimum.  Additionally, a family restroom shall be provided whether or not it is required by code.  All restrooms (Men’s, Women’s, Family, and Employee) shall include: 

A. Electric hand driers,  B. Soap dispensers,  

C. Toilet paper dispensers,  

D. Waste receptacles,  

E. Tilt mirrors,  

F. Sanitary disposal,  

G. Coat hooks.  Public restrooms (Men’s, Women’s, and Family) shall also include: 

A. Fold down changing tables,  B. Stainless steel toilet and urinal partitions 

C. Stainless steel toilet room accessories.   

A  dual  level  ADA  compliant  cooled  drinking  fountain  shall  be  located  outside  the  public restrooms, along with a TTY phone.  All lavatories shall be ADA accessible. 

Programmed baggage work and equipment areas shall be confined to the back‐of‐house, with public access to the baggage claim space off the waiting area via a concealed roll‐down security grille.  The baggage work areas must be sized appropriately to accommodate floats, carts, and other  equipment  used  to  transport  baggage  from  the  station  to  the  platform.    A minimum turning radius of twelve feet for baggage floats shall be accommodated in this space.   

A. Provide adjacency to Ticketing 

B. Include baggage scale in Baggage Claim 

C. Baggage Equipment and Work Area must have access to the exterior. 

D. Accommodate the existing Rochester Station equipment: 

1. Firearms Float:  (1) 84” L x 44” W x 72” H 

2. Standard Float: (1) 120” L [171” overall with tow bar down] x 44” W x 64 ½” H;  

3. Standard Float: (1) 84” L [129” overall with tow bar down] x 44” W x 64 ½” H 

Page 73: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐68 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. Electric Truck: (1) CarryAll 6 at 132” L x 48” W x 70” H 

E. Accommodate new Amtrak equipment: 

1. Low‐Boy Float: (2) 97”L [123” overall with tow bar down] x 46” W x 50 ½” H 

2. Electric  Truck  with  wheel  base  and  undercarriage  clearance  to  clear  the proposed ADA accessible ramp slope. 

3. Design‐Builder shall investigate and document the existing Electric Truck on site.  If existing Electric Truck does not have adequate  clearance,  the Design‐Builder shall  provide  (2)  new  Electric  Trucks  with  wheel  base  and  undercarriage clearance to clear the proposed ADA accessible ramp slope. 

Phase II of the station building shall include Trailways operations. The layout of this space shall facilitate easy  transfer between Trailways  inter‐city buses and  the Amtrak  trains. The Design‐Builder  shall  ensure  that  the  Phase  II  expansion  reads  as  a  continuation  of  Phase  I  station building rather than a later addition to the exterior, as well as providing continuity of finishes, furniture,  color,  texture,  and  equipment  on  the  interior.    The  expansion  shall  be  seamless.  Trailways ticketing to include: 

A. ADA‐compliant ticketing area with two staff positions with baggage express managed by one agent. 

B. Provide storage for packages waiting to load onto buses in a secure space with access to both the exterior and the ticketing space. 

C. Cash drawers in built‐in casework and desktops with operable glass cover for schedules D. Baggage scale E. Rear countertop with cabinetry for storage of supplies F. Provide and install acrylic transaction windows G. CCTV monitors shall be visible from all ticketing workstations H. Telephone and data connections for computers, phones, printers 

I. Power for CPU’s, ticketing terminals, and ticket printers 

J. Access to Waiting Room 

Other Trailways back‐of‐house spaces include: 

A. Dispatch office, near Ticketing and with views of the Waiting Area 

B. Four private offices 

C. Employee Break Room sized to  fit 10 people at one time,  including a kitchenette with full‐size refrigerator, (8) 18” D x 12” W full‐height lockers with ventilated doors.  Room to include PA system interface. 

9.5  Station Concourse Level 

The  infrastructure of the station building shall be  furnished  in Phase  I.   These spaces shall be designed and sized to meet the  future needs of Phase  II when construction  is complete.   The Concourse Level spaces shall be fully waterproofed.  Spaces shall include: 

Page 74: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐69 

Part 3 Project RequirementsJuly 18, 2013

 

 

A. Passenger Concourse to Platform B. Mechanical Room C. Electrical Room D. Secure Communications Room E. Secure Amtrak PIDS Server Room F. Secure Amtrak Revenue Server Room G. MRL Control Closet H. Water Service Space, if needed I. Fire Pump Space, if needed J. Separate Secure Storage for Amtrak and Trailways K. Fire Extinguishing provisions, per NFPA 10 L. Crawlspace area for systems runs to the Ground Level above 

The  concourse  level  utility  spaces  shall  be  completely  secured  from  the  public with  locking access‐controlled doors and a small corridor.   The Baggage Ramp shall be separated from the Concourse  with  double  doors  that  shall  open  automatically  for  approaching  baggage  carts during the hours of normal station operation. 

9.6  Space Allocation 

Space allocation has been developed  through direct observation of  the existing  facilities and discussions between NYSDOT, Amtrak, and Trailways.   The spatial allocations have also being developed considering the projected ridership growth at the Station. 

The following programming information was gathered by NYSDOT.  This includes: 

A. Amtrak  Rochester  Station  Functional  and  Space  Requirements,  Issued November  30, 2012 – 3 pages 

B. Trailways Rochester Station Functional and Space Requirements, Received  January 28, 2013 – 1 page 

C. Preliminary Design Program Comparison – This  table compares  requested Amtrak and Trailways  program  elements  with  the  areas  provided  in  the  Preliminary  Design documents.   

The  Design‐Builder  shall  provide  a  final  design  that  reconciles  the  functional,  spatial,  and aesthetic requirements of all parties, including Amtrak, Trailways, and the Department with all final decisions made by the Department. 

Page 75: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐70 

Part 3 Project RequirementsJuly 18, 2013

 

 

AMTRAK ROCHESTER STATION FUNCTIONAL AND SPACE REQUIREMENTS, ISSUED 12/30/2012 

Page 76: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐71 

Part 3 Project RequirementsJuly 18, 2013

 

 

AMTRAK  ROCHESTER  STATION  FUNCTIONAL  AND  SPACE  REQUIREMENTS,  ISSUED  12/30/2012

Page 77: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐72 

Part 3 Project RequirementsJuly 18, 2013

 

 

AMTRAK ROCHESTER STATION FUNCTIONAL AND SPACE REQUIREMENTS, ISSUED 12/30/2012

Page 78: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐73 

Part 3 Project RequirementsJuly 18, 2013

 

 

TRAILWAYS ROCHESTER STATION FUNCTIONAL AND SPACE REQUIREMENTS, RECEIVED 12/28/2012 

Note: The consolidated design presented in the Preliminary Design documents 

does not include overall square footage of this size due to the inclusion of shared Trailways and Amtrak spaces, such as Waiting Area, Restrooms, Circulation, 

and Utility Spaces.

Page 79: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐74 

Part 3 Project RequirementsJuly 18, 2013

 

 

PRELIMINARY DESIGN PROGRAM COMPARISON 

 

 

Page 80: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐75 

Part 3 Project RequirementsJuly 18, 2013

 

 

9.7‐  I Innformation Systems 

A full signage package shall be prepared by the Design‐Builder for approval by The Department.  The Design‐Builder  shall  be  responsible  for  signage  plans,  details,  and  complete  installation throughout  the  facility.    All  signage  shall  comply with  ADA  and  ADAAG  guidelines.   Design‐Builder  shall  refer  to  Amtrak  Graphic  Signage Manual  and  shall  provide  a  full  package  of compliant signage for The Department’s review and approval.  The package shall include: 

A. Parking lot circulation, rules, and parking space directive and informational signage B. ADA Parking Signage C. Parking Pay Station Signage D. Room Identification signs adjacent to or on each Interior and Exterior doors to be six inches 

with room name and number. Name to be removable on office signage. E. Building Sign and number to be wall mounted above the new main entrance as indicated on 

the drawings and as per Amtrak and Trailways Standards. F. All  code  compliant and OSHA  required  signage  shall be  installed on all equipment, walls, 

and  doors  throughout  the  Utility  spaces,  Electrical  Room,  Communication  and  Server Rooms, and MRL Control Room 

G. Interior Wayfinding Signage / Directional Information H. Restriction  Signage  at  all  Electrical  Room,  Security  Room,  Communication  and  Server 

Rooms, and any other Utility Room door I. Employee Only signage where appropriate J. Information  about  connection  services  and  tourist  information  and  pamphlets  to  be 

provided at the Customer Information Kiosk K. Area shall be clearly defined where retail tenants may install a storefront sign L. Passenger Information Display Systems (PIDS) per Amtrak standards 

1. LED Variable Message Signs located on the platform and at each bus berth 

2. 40” Minimum LED Television monitors displaying departure  information within Waiting Area, Concourse, and at train and bus boarding Platforms. 

M. Public Announcement System per Amtrak standards 

1. Delayed announcement playback 

2. Unidirectional microphone to eliminate squeal 

3. Signal to noise ratio of 10 dB 

4. Master paging locations: 

Lead Clerk’s Office  Amtrak Ticketing 

Amtrak Train Information Operator Console 

Trailways Ticketing  Trailways Dispatch Office 

Page 81: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐76 

Part 3 Project RequirementsJuly 18, 2013

 

 

N. Where a public address system  is  installed, an ADA compliant method of transmitting the same  information  visually  shall  also  be  provided.    Where  a  public  information  display system is installed, an ADA compliant method of transmitting the same information audibly shall also be provided. 

O. Entertainment 

o 40” Minimum LED Television monitors to display cable television 

o Ceiling mounted music speaker system to broadcast music 

P. The Design‐Builder shall protect, preserve, and reinstall the original historic plaque from the former 1914 Bragdon Station that currently hangs on the north wall of existing  facility on this  site.    This  plaque  shall  be  carefully  removed,  cleaned,  and  installed  in  a  prominent location within the new Station facility.   In addition to reinstallation of the historic plaque, the Design‐Builder  shall  provide  an  two  (2)  interpretive wall‐mounted  plaque within  the Station Building describing the historic significance of the station site and the former 1914 Bragdon Station that was demolished  in the 1970s.   The plaque shall be approximately 24 inches by 36 inches. 

9.8  Finishes and Materials 

A. Materials shall be durable, heavy duty, easily cleanable and maintainable to ensure a high standard of appearance and  function  for  the  life of  the  facilities, and shall be suitable  for the environment. 

B. All utilities,  conduits, ductwork, and other  systems provisions  shall be  concealed and not exposed to view in any space that is accessible to the public. 

C. All  drywall  from  finished  floor  to  eight  feet  to  be  high  impact  abuse  resistant  type  5/8” thick. 

D. Accents added to reflect the past design strategies of the original building  E. Interior finishes to be provided as indicated on the drawings, specifications, and as directed 

by Amtrak Engineering Stations – Standard Design Practices (SDP). F. Exterior walls shall be finished with 4” brick veneer and cast stone veneer and trim.  On the 

interior  face,  walls  shall  be  finished  with  high‐abuse  gypsum  board  with  a  decorative ceramic tile treatment up to approximately ten feet (10’‐0”) above the finished floor level at all  areas  exposed  to  the  public.  The  Design‐Builder  shall  provide  continuous  insulation; insulation shall be mounted within the wall cavity outside sheathing board. 

G. All fully interior walls exposed to the public shall also be finished with a decorative ceramic tile treatment up to approximately ten feet (10’‐0”) above the finished floor level. 

H. All stainless steel throughout the full scope of work shall be Type 316 per Amtrak standards. G.I. R‐values of Walls and Roof  to be constructed  to meet R‐26 & R‐30 values  respectively  to 

provide a thermally efficient building envelope. H.J. Materials  used  for waterproofing  shall  be  resistant  to  deterioration  from  contaminated 

groundwater. Vapor barriers shall be provided for all slabs in contact with the ground. 

Page 82: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐77 

Part 3 Project RequirementsJuly 18, 2013

 

 

I.K. Sound‐deadening  material  shall  be  used  on  horizontal  and  vertical  surfaces  wherever possible. 

J.L. Flooring: Office spaces to be industrial commercial grade carpet tile, Break Rooms to be bio‐based vinyl composition tile, Public and Private Toilet rooms to be ceramic tile.  The Design‐Builder shall ensure that the concrete slab has properly cured at all public areas scheduled to receive terrazzo flooring, including but not limited to Waiting Areas, Baggage Claim, and that  the manufacturer’s  recommended vapor barrier has been  installed per all applicable instructions and all install conditions have been met. 

K.M. Window blinds to be installed in all windows, at both exterior and interior wall locations within the private Amtrak and Trailways portions of the building. 

N. All products  to be ENERGY STAR  to  the maximum extent possible  in accordance with  the IGCC, New York State Executive Orders No. 4 and 88, and Amtrak’s SDP. 

O. Soffit  panels  and  linear metal  ceiling  system  shall  be  provided  at  the  underside  of  all exterior roof and canopy surfaces to ensure a finished look and to provide pest control.  At any horizontal  surface where  it  is not possible  to  install  soffit panels or  the  linear metal ceiling system,  the Design‐Builder must provide pest control measures as specified within Part 8 to prevent bird roosting and other pest problems. 

L.P. Special attention  shall be paid  to  the wall and  ceiling  finishes and  treatments within  the Waiting  Areas.    The Design‐Builder  shall  provide  acoustically  absorptive materials where possible, along with decorative trim, concealed lighting coves, and the like, commensurate with  the  look  of  the  interior  renderings  that were  prepared  for  Preliminary  Design  and presented to the Executive Steering Committee and other interested parties. 

9.9  Public Art Installations 

A major goal of the project is to establish points of interest along North Clinton Avenue within the “downtown sightline” corridor.  As part of the Design‐Builder’s contract, the installation of two monumental public art pieces shall be  included  in the scope of work for the project.  The artwork shall not be finalized before the Design‐Build contract is awarded.  It is anticipated the artwork will be  incorporated  into the project as shown on the Phase  II site plan along what  is called the “Downtown Sightline” Axis.  These locations are the center island within the drop‐off / pick‐up  loop and  the corner of North Clinton and Cumberland Streets.   Per  the Community Outreach  section  of  this  document,  the Design‐Builder  shall  be  available  and  shall  allow  for meetings with the City of Rochester’s Public Art Committee and the Rochester Arts and Cultural Commission  to assist NYSDOT  in defining,  judging,  soliciting Artists, and commissioning  these pieces of Art. 

9.10  Historic Canopy and SHPO Coordination  

At  the existing  low  level boarding platform,  the steel  frame of  the platform canopy  from  the 1914 Bragdon station still stands  in  its original  location.   Amtrak has  recently  installed a  roof surface on a portion of this frame and has completed  lead paint abatement on the portion of 

Page 83: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐78 

Part 3 Project RequirementsJuly 18, 2013

 

 

the  canopy  where  the  roofing  was  installed.    The  Design‐Builder  shall  leave  in  place  the unabated portion of the canopy from a point a minimum of twenty feet west of the proposed loading dock at the new Station Building.   The Design‐Builder shall carefully remove, preserve and protect, and deliver the balance of the existing canopy to an offsite storage location to be determined by NYSDOT  in  coordination with  the City of Rochester.   Once  removed  from  the site, the abated portion of the canopy shall become property of the City of Rochester. 

The Design‐Builder shall provide two  interpretive panels discussing historic  importance of the site, station and the existing portion of canopy to remain.   The art work for the panels will be provided  by  NYSDOT  and  shall  comply  with  New  York  State  Historic  Preservation  Office guidelines. 

SECTION 10.  VERTICAL CIRCULATION REQUIREMENTS 

To provide a safe and accessible path of travel between the site, station, and platform, vertical circulation  is  a  vital  component  of  the  program.    This  shall  take  the  form  of  ramps,  stairs, escalators, and elevators.   The station‐side vertical circulation elements shall share the axis of the  main  corridor  and  the  concourse  for  clarity  of  circulation  and  cost  control,  relating horizontal  and  vertical  circulation  elements  to  each  other.    For  passengers  at  the  station building,  the  Design‐Builder  shall  provide  stairs,  an  escalator,  and  an  elevator  down  to  the Concourse Level.   From the Concourse,  the Design‐Builder shall an additional set of stairs, an escalator,  and  an  elevator  to  take  patrons  to  the  platform  level.    All  circulation  shall  be designed to comply with the Building Code of New York State, Amtrak Station Standards, and ADAAG regulations. 

Additionally, at both the Station and Platform ends of the Concourse, the Design‐Builder shall provide ADA compliant concrete ramps to be used for baggage transport to and from Amtrak trains.    The  ramps  shall  have  a  non‐slip  surface,  stainless  steel  handrails,  and  sufficient clearance  to permit a baggage cart with  floats  to pass a person on  foot.   By restricting  these ramps  to ADA  compliant  slope,  they  shall provide  redundancy  for both accessible  travel and egress.    The  Design‐Builder  shall  be  required  to  verify  the  final  design  complies  with  all applicable  Building  Code  of  New  York  State  and  NFPA  130  standards  for  egress  between stairways, ramps, and areas of refuge at each end of the proposed platform. 

Elevators  shall  be APTA‐Grade,  4,000‐lb  capacity, machine  room‐less models.    The  elevators must permit the use of a standard 30”x72” Hospital Rolling Stretcher.   Elevators shall be front and  reverse  opening  where  necessary.    All  elevator  passenger  cabs  and  doors  shall  be  a minimum of 75%  clear glass  for  security purposes and  finished as described within Amtrak’s SDP.     

Amtrak standards mandate a minimum six foot width at stairs and ramps between sets of hand and guardrails for the convenience of a passenger with baggage.  The rise of a typical step shall be six inches, while the tread shall be twelve inches.  Twelve inch rounded returns shall be used on the ends of handrails, and intermediate landings shall be provided. 

Escalators shall be provided at both the station and platform ends of the concourse.  With a 30° incline and speed of 100fpm, APTA grade reversible escalators must be at  least forty  inches  in 

Page 84: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐79 

Part 3 Project RequirementsJuly 18, 2013

 

 

width  to allow  for baggage with  six  foot clear  landings at either end.   All escalators must be rated for heavy use in a fully outdoor environment, even though enclosure shall be provided, to provide resistance to harsh weather conditions at the project location. 

10.1  Pedestrian Concourse  

Amtrak  service  shall  operate  on  a  new  high  level  center  island  platform  for  ADA‐compliant passenger  boarding,  accessible  via  concourse.    The  proposed  concourse  is  an  underground connection between the main components of the station program; it must be treated as a well‐lit, spacious corridor that  is visually connected to the station house and waiting areas.   It shall be an integral part of the visual connection between station and platforms, acting as the main corridor  for  the  entire  station  building.    The  Design‐Builder  shall  maintain  a  twenty  foot minimum width and ten foot minimum height within the Concourse.   Baggage and pedestrian movements  shall  be  segregated  with  a  stainless  steel  handrail  within  the  concourse.  The Design‐Builder  shall  install  panelized  glass  paver  sidewalk  vaults  above  the  entry  to  the Concourse to permit natural light below grade.   

The Concourse  shall be  finished with highly durable  surfaces,  including  linear metal  ceilings, anti‐slip  terrazzo  flooring,  and  ceramic  wall  tile.    Supplemental  artificial  lighting  shall  be incorporated to provide a bright circulation space at all times of day. 

10.2  Baggage Ramps 

The  concourse  shall  also  provide  immediate  access  to  exterior  baggage  ramps.    Baggage movements must be segregated from passenger movements, requiring separate corridors and access. The design  shall  include a  ramp on  the  station  side, where  there  is  sufficient area  to permit  a  switch  back  layout  and  at  the  platform  where  a  straight  run  ramp  shall  be implemented.      The baggage  ramp  shall be used  solely  for  the  transport of baggage, with  a minimum width of  eight  feet,  turning  radius of  twelve  feet,  and  an ADA  compliant  slope  to accommodate the maneuvering of baggage  floats.   Building baggage ramps to ADA standards for  slope  (adhering  to  a  maximum  allowable  finished  slope  of  1:12),  runs,  landings,  slip resistance,  and  handrails  shall  provide  redundancy  for  accessible  travel  in  the  event  of  an elevator  or  escalator  outage  and  shall  provide  additional  egress  capacity  in  emergency situations. 

SECTION 11.   SUSTAINABILITY REQUIREMENTS 

Sustainable design has been and shall remain a project philosophy across all disciplines through Final Design and Construction.  The Design‐Builder’s documentation for Rochester Station shall fully  comply  with  the  International  Green  Construction  Code  (IgCC)  and  shall  follow  the sustainable  building  practices  outlined  by  Amtrak  Engineering  Stations  –  Standard  Design Practices (SDP), NYSDOT’s GreenLITES program and New York State Executive Orders 4 and 88 (E04,  EO88).  Additionally,  Amtrak  Station  Standards  utilize  major  elements  of  the  IgCC  to ensure that the cost of ownership and maintenance of new stations is considered in the design.  

The Preliminary Design documents  include a spreadsheet titled, Sustainable Strategy Analysis, dated  April  24,  2013.    Compliance  strategies  shall  include,  but  not  be  limited  to,  the  items 

Page 85: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐80 

Part 3 Project RequirementsJuly 18, 2013

 

 

included  in that document.   The Design‐Builder shall provide proof of compliant strategies for meeting  IgCC,  Executive  Order,  NYSDOT,  and  NYSERDA worksheet  requirements  during  the design process and shall be required to implement a transparent program to communicate on a monthly  basis  proof  of  compliance  with  the  agreed  upon  strategies  throughout  the Construction and Commissioning process.  

If the Design‐Builder determines that any specified strategy will not be  feasible or achievable for  this  project,  the  Design‐Builder  shall  be  responsible  for  fully  documenting  this determination  in a manner acceptable to NYSDOT.   NYSDOT shall be notified  in writing of any proposed changes, and no change shall be permitted without their permission.  If both NYSDOT and  the Design‐Builder determine a  strategy will not be pursued,  the Design‐Builder  shall be responsible  for  confirming  that  the project will  still meet  the  requirements of  the  Executive Orders without that strategy.   This may require the  incorporation of additional strategies and shall be the responsibility of the Design‐Builder.  

11.1  Sustainable Strategies 

Strategies that shall be included in this project, among others, shall be: 

A. Perform a Pre‐design Site Inventory to determine which trees and shrubs shall remain or be relocated on site. 

B. Incorporate  porous  paving  to  the  greatest  extent  possible.   Water  drainage  shall  be funneled  to  the  greatest  extent  possible  into  landscaped  areas,  planting  beds,  and bioswales throughout the site. 

C. Install an energy display in the public Waiting Area of the station. 

D. Provide  Energy  Star  equipment  throughout  the  project,  wherever  an  Energy  Star product is available.   

E. Provide  Full  Commissioning  of  all  energy  consuming  systems  to  achieve  the  optimal energy performance and indoor air quality for this building type. 

F. Provide for the storage and collection of recyclables. 

G. Install real‐time Building Monitoring System equipment to allow operators to maintain targets set during the Commissioning process and to help sustain occupant comfort and well‐being.   

H. Establish minimum indoor air quality (IAQ) performance to enhance indoor air quality in buildings, thus contributing to the comfort and well‐being of the occupants. 

I. Provide  additional  outdoor  air  ventilation  to  improve  indoor  air  quality  for  improved occupant comfort, well‐being and productivity. 

J. Reduce indoor air quality problems resulting from the construction process. 

K. Utilize computer modeling to “right size” mechanical systems. 

L. Install machine‐room less elevators for greater energy efficiency. 

M. The Design‐Builder shall investigate and prepare a study of potential on‐site renewable energy  systems  to  reduce  the  environmental  impact  associated  with  energy 

Page 86: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐81 

Part 3 Project RequirementsJuly 18, 2013

 

 

consumption and evaluate their cost‐effectiveness.  If a reasonable payback period can be proven for a particular renewable system, the Design‐Builder shall implement. 

N. Minimize light trespass from the building and site, reduce sky‐glow to increase night sky access,  improve nighttime  visibility  through glare  reduction, and  reduce development impact on nocturnal environments.  

O. Eliminate  the  use  of  potable  water,  or  other  natural  surface  or  subsurface  water resources available on or near the project site, for  landscape  irrigation. Provide means to capture rainwater for reuse for irrigation purposes. 

P. At a minimum, 75% of plantings used must be native, low maintenance, and resistant to drought, pests, and disease.   

Q. Do not provide any landscape irrigation system that uses potable water. 

R. Utilize high‐efficiency plumbing fixtures to reduce potable water use for building sewage conveyance.  Fixtures should use, at minimum, 10% less water than the requirements of the Energy Policy Act of 1992. 

S. Verify  that  the building’s energy  related systems are  installed, calibrated and perform according  to  the  owner’s  project  requirements,  basis  of  design,  and  construction documents. 

T. All  HVAC&R  and  fire  suppression  systems  shall  be  designed  without  using Hydrofluorocarbons and Halon. 

U. Implement a Construction Waste Management Plan for the recycling and/or salvage of at least 75% of non–hazardous construction material. 

V. Specify  building  products  that  incorporate  recycled  content materials  to  the  greatest extent  feasible,  thereby  reducing  impacts  resulting  from extraction  and processing of virgin materials. 

W. To the greatest extent feasible, specify materials that have been extracted, harvested, recovered as well as manufactured within 500 miles of the project site for a minimum value contained within IgCC. 

X. Select  materials  with  low  volatile  organic  compounds  (VOCs)  content,  including architectural coatings, sealants, and adhesives.  

Y. Permanent  entryway  systems  shall  be  installed  in  the  primary  direction  of  travel  to capture dirt, dust and particulates from entering the enclosed portions of the building. 

Z. Provide a high level of lighting and thermal system control by individual occupants or by specific groups in enclosed multi‐occupant spaces to promote the productivity, comfort and well‐being of building occupants. 

AA. Utilize daylight dimming devices  and occupancy  sensors  to  reduce  lighting  and HVAC demand where practical and appropriate. 

BB. Provide for the building occupants a connection between indoor spaces and the outdoor through  the  introduction  of  daylight  and  views  into  the  regularly  occupied  enclosed areas of the building 

Page 87: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐82 

Part 3 Project RequirementsJuly 18, 2013

 

 

CC. Install thermally broken window systems with insulated, low‐E double glazing units and a high R‐Value. 

DD. Shade  fenestration  to  the greatest extent possible  to  limit heat gain and glare and  to maximize indirect lighting. 

EE. Insulate all wall and ceiling assemblies to guard against thermal loss and gain.  

11.2  Energy Consumption  

The Design‐Builder shall comply with the mandate contained in New York State Executive Order 88 to reduce the average Energy Use Intensity of the new Rochester Station Project by at least 20% from a baseline defined within the Order’s text.  Additionally, the facility shall comply with the requirement for submetering of all energy using systems. 

The Design‐Builder shall utilize  the NYSDOT Draft Energy Analysis Guidelines  for Project‐Level Analysis, dated November 25, 2003, as a guideline for quantitative energy analysis. 

11.3  Life Cycle Analysis  

Per IgCC, the new facility and equipment shall include state‐of‐the‐art energy conserving design features  that  are  shown  to  be  cost‐effective.  These  features  shall  be  incorporated  and discussed  during  design meetings  and  verified  as  the  design  progresses.    Feasibility  shall  be established based on a defined payback period.    In accomplishing  life cycle cost analysis,  the Design‐Builder shall be required to use established principles and procedures as well as realistic maintenance  and  repair  costs  from  established  sources.    Conventional  sustainable  design systems such as passive solar and day lighting do not require a life cycle cost analysis. 

11.4  Material Selection  

The Design‐Builder  shall  comply with  the mandate  for green procurement  contained  in New York State Executive Order 4 to utilize products that reduce energy and resource consumption, reduce  or  eliminate  the  use  of  hazardous  substances  and  the  generation  of  hazardous substances, and  reduce pollution and waste.   The Design‐Builder  shall  reference and  comply with the IgCC, as well as the approved specifications available on the New York State Office of General Services website for the implementation of Executive Order 4. 

11.5  Commissioning  

In order  to verify and ensure  that  fundamental building elements and  systems are designed, installed, and calibrated to operate both as intended and as efficiently as possible, the Design‐Builder shall retain  the services of an  independent Commissioning Agent.   The scope of work required for Commissioning shall include the following:   

A. Review the design intent and the basis of the design documentation 

B. Incorporate commissioning requirements into the Final Design documents 

C. Create and implement the Commissioning Plan  

D. All  required  documentation  shall  be  coordinated  with  The  Department,  the Commissioning Agent and the Preliminary Design Engineer 

Page 88: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐83 

Part 3 Project RequirementsJuly 18, 2013

 

 

E. Verify  the  installation,  functional  performance,  training,  and  operation,  and maintenance documentation 

F. Complete a Commissioning Report 

G. Complete an Operations and Maintenance Manual 

H. Provide training to the facility staff. 

11.6  Documentation  

Compliance with the  IgCC and New York State Executive Orders No. 4 and 88 are mandatory.   The  Design‐Builder  shall  provide  complete  documentation  sufficient  to  demonstrate compliance with  both  Executive  Orders  upon  request  by  the  State,  as well  as  the  NYSDOT GreenLITES Project  Environmental  Sustainability Rating  System  Scorecard  and NYSERDA New Construction Program Pre‐Qualified HVAC and Lighting Worksheets.   No  formal submission of documentation to USGBC/LEED or the State’s Green Building Working Group is required at any phase of the construction process.  Documentation of compliance shall include, though not be limited to, the following items: 

A. The Design‐Builder shall provide a Commissioning Agent and Commissioning Plan.   

B. The  Design‐Builder  shall  create  a  Sustainability  Compliance  Plan  to  ensure  both  the completion and compliance of all of the following documents listed in this document.   

1. Include all of the sustainable building goals established by the Design Team. 

2. List all implementation strategies. 

3. Document  equivalence  with  IgCC,  as  well  as  with  Amtrak  Sustainability Guidelines. 

4. Document compliance with NYSDOT GreenLITES. 

5. Document compliance with New York State Executive Orders No. 4 and 88. 

6. Document compliance with NYSERDA’s New Construction Program utilizing Pre‐Qualified HVAC and Lighting Worksheets. 

7. If  a  required  strategy  is  deemed  infeasible  or  unachievable  by  both  the  The Department  and  the Design‐Builder,  the Design‐Builder  shall demonstrate  and fully document and justify this hardship in a manner that shall demonstrate that compliance with the Executive Orders and the IgCC is still achieved. 

8. Describe how the plan shall be executed. 

9. Lay out a construction schedule. 

10. List  all  systems  and  components  that  shall  be  included  and  documentation required for each. 

11. Detail all of  the participants  in  the process, along with  their  specific  roles and responsibilities. 

12. Update this plan and providing progress reports to the Department as the design and construction progresses to reflect all approved revisions. 

Page 89: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐84 

Part 3 Project RequirementsJuly 18, 2013

 

 

C. Commissioning  Specifications  for  incorporation  into  the  Construction  Documents, including but not limited to: 

1. Incorporate Design  Intent and Basis of Design from the Design Team members, including all energy consuming equipment 

2. Indoor Air Quality Protocol 

3. Indoor Air Quality Testing Procedures 

4. Construction Indoor Air Quality Management Plan 

5. Start‐up and Check‐out Checklists and Procedures for Building Systems 

6. Functional Performance Testing Procedures for Building Systems 

7. Testing, Adjusting, and Balancing Plan 

D. Operations and Maintenance Management Plan, including but not limited to: 

1. Systems and Energy Management Manual 

2. IAQ Management Plan for O&M 

3. Facility  Maintenance  Manual,  including  preventative  and  unscheduled maintenance and green housekeeping procedures 

4. Environmental Tobacco Smoke policy 

5. Integrated Pest Control Plan 

E. Commissioning Report must be prepared, documenting effective implementation of the Commissioning Plan and Specifications, including but not limited to: 

1. Documentation of all IAQ Testing 

2. Construction Indoor Air Quality Report 

3. Operations and Maintenance Plans, Manuals, and Policies 

F. The Design‐Builder shall prepare a Final Sustainability Compliance Report documenting the implementation of the Sustainability Compliance Plan and completion of all Testing, Reports,  Manuals,  and  Policies,  as  well  as  any  future  requirements  for  ongoing compliance. 

SECTION 12.  MECHANICAL REQUIREMENTS 

12.1  General 

These  criteria  shall  encompass  the  work  required  to  design,  furnish,  install  and  test  the mechanical systems for Rochester Station.  

Utilize plumbing,  fire  suppression,  cooling, heating  and  ventilation equipment  and processes that are  sustainable and aid  in  satisfying  sustainability  requirements  for compliance with  the IGCC, NYSERDA  incentives, New  York  State  Executive Order  and NYSDOT  requirements,  and Amtrak Standards. 

Page 90: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐85 

Part 3 Project RequirementsJuly 18, 2013

 

 

12.2  Codes and Standards 

The following codes and standards shall apply to design and construction of this project.   Use most recent issue unless otherwise noted: 

A. Amtrak Engineering Stations Standard Design Practices (SDP) – 6/20/12Station Program and Planning – Standards and Guidelines Appendix G Mechanical Systems v 2.2 March 2008 

B. ANSI/ASHRAE 62.1‐2010, Ventilation for Acceptable Air Quality 

C. ASHRAE 90.1–2010,  Energy Standard for Buildings Except Low‐Rise Residential Buildings 

D. ASHRAE Fundamentals Handbook 

E. ASTM A 653/A 653M, Galvanized Sheet Steel 

F. International Green Construction Code  (IgCC), 2013 Edition  (Note:  IGCC requirements and their application are outlined within the Amtrak Engineering Stations – SDP.) 

G. State  of  New  York  Executive  Order  No.  4:  Establishing  a  State  Green  Procurement  and Agency Sustainability Program 

H. State  of  New  York  Executive  Order  No.  88:  Directing  State  Agencies  and  Authorities  to Improve the Energy Efficiency of State Buildings 

I. New  York  State  Department  of  Transportation  Leadership  in  Transportation  and Environmental Sustainability “GreenLITES” Certification Program  

J. New York State Building Code, Mechanical Code, Plumbing Code, Fuel Gas Code, Fire Code, Energy Conservation Code  

K. NYSDOT Design Guidelines 

L. NFPA 13 Installation of Sprinkler Systems  

M. NFPA 31 Installation of Oil Burning Equipment 

N. NFPA 54 National Fuel Gas Code O. NFPA 70 National Electrical Code P. NFPA 72 National Fire Alarm Code 

Q. NFPA 85 Boiler and Combustion System Hazards 

R. NFPA 90A Installation of Air Conditioning and Ventilating Systems 

S. NFPA 101 Life Safety Code 

T. NFPA 130 Transit and Passenger Rail Systems 

U. NFPA 900 Building Energy Code V. Rochester Gas & Electric Co. Standards, Rules & Regulations 

W. SMACNA HVAC Duct Construction Standards‐‐Metal and Flexible, latest edition. 

12.3  Vibration Isolation / Seismic Design 

Provide seismic, vibration and wind restraints for HVAC components as required by code. 

Equipment  producing  vibrations  shall  be  isolated  from  the  structure  by  spring  or  rubber‐in‐shear  vibration  isolators.   All pipe  and ducts  connected  to equipment mounted on  vibration 

Page 91: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐86 

Part 3 Project RequirementsJuly 18, 2013

 

 

isolators  shall  contain  flexible  connections  or  provisions  made  for  vibration  isolating  type supports.  Identify on drawings where vibration isolators are to be provided. 

Equipment  to be mounted on  the  floor  shall be placed on  reinforced concrete housekeeping pads.  Minimum pad height shall be six inches; all equipment to be suspended from ceiling shall be provided with suspension type hangers consisting of combination of spring and neoprene in series. 

12.4  Mechanical Identification 

HVAC and plumbing equipment, ductwork and piping shall be labeled using plastic or aluminum labels with  ¼  inch  letter  size  if  viewing  distance  is  less  than  24  inches, ½  inch  for  viewing distances up to 72 inches, and proportionately larger lettering for greater viewing distances.  

Each  equipment  item  that  is  scheduled  on  the  design  documents  shall  be  identified  by  its scheduled designation. Labels  shall have a background color  that contrasts with  the  lettering color. Lettering shall be sized as noted above. 

Pipes  shall  be  labeled  with  pre‐coiled  pipe  labels  to  partially  or  fully  cover  the  pipe circumference  and  attached  without  fasteners  or  adhesive.    Pipe  labels  shall  show  the identification  of  piping  service  using  the  same  designations  or  abbreviations  used  on  the construction documents, pipe size, and flow direction.  Labels shall be located adjacent to each valve,  control  device,  branch  connection  (excluding  short  takeoffs  for  fixtures  and  terminal units),  near  penetrations  through  partitions,  and  near  equipment  connections  and terminations. Spacing shall be at maximum intervals of 25 feet along each run.  

Ductwork labels shall be attached by fasteners, and shall show flow direction and duct content designation or  abbreviations used on  construction documents.  Labels  shall be  attached near points where ducts  enter  into  concealed  spaces  and  attach  to  equipment,  and  at maximum intervals of 25 feet where ducts are exposed or concealed by removable ceiling system.   

12.5  HVAC SYSTEMS 

12.5.1  Hot Water Heating System 

A. The primary heating  system  shall be by hot water.   Air handling units, wall heaters, unit heaters, duct heaters or combination heating/cooling units may be employed as required by the application.   Convective  type wall heaters are preferred  to  force‐flow  types provided units are available in the required capacity. 

B. Heating  indoor design dry‐bulb  temperatures  for all  indoor  spaces  shall be maintained at 68°F.   Design heating  load will be based on ASHRAE Winter Outdoor Design Dry Bulb 95% and 80% of maximum building ventilation load. 

C. Two fire tube type boilers shall be provided.   Each shall be sized to meet 80% of the design day heating  load as a minimum.   The boilers shall be equipped with duel fuel, modulating type power assisted burners that shall be capable of operation on natural gas and No. 2 fuel oil.  The  burners  shall  be  designed  to  swing  out  allowing  full  burner  face  access without having to disconnect fuel piping or wiring. The burners shall have full  IRI gas and oil trains 

Page 92: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐87 

Part 3 Project RequirementsJuly 18, 2013

 

 

and a combined burner management and flame safeguard system. The burner management system shall be capable of providing lead/lag changeover and fuel selection functions. 

D. The boiler  flue venting  shall be accomplished  through a pre‐manufactured  stainless  steel flue  system.  The  flue  system  shall  be  designed  in  accordance with  NFPA  requirements. Design shall  include make‐up air  to  the boiler  room  to provide  for boiler combustion and ventilation requirements. 

E. As an alternate to boilers closed loop ground source heat pumps may be utilized if they are cost  effective  and  contribute  to  achieving  IGgCC  Compliance  and  project  sustainability goals. 

F. Provide water  treatment  for  the  hot water  heating  system  to  prevent  scale,  corrosion, fouling and microbiological growth. 

G. Provide  a  primary‐secondary  pumping  system.  Distribution  pumps  shall  have  a  standby pump sized equal. Provide variable speed base‐mounted centrifugal distribution pumps to serve the hot water heating system(s).   

H. All hot water heating equipment shall be thermostatically controlled.  Control transformers shall be provided where required. 

12.5.2  HVAC Systems 

A. Air conditioning equipment shall be variable‐air‐volume  (VAV) self‐ contained air handling units or split system type.  Provide cooling with DXchilled water coils and heating primarily with hot‐water coils.   Energy  recovery unit(s)  shall be  shall be provided  for both  sensible and  latent energy transfer where required by ASHRAE 90.1 and where  justified for energy savings in compliance with the IGgCC, NYSERDA incentives, New York State Executive Order and NYSDOT requirements, and Amtrak Standards.  The energy recovery unit(s) shall include but  not  be  limited  to  the  following  functions:  mechanical  cooling,  heating,  active dehumidification, and total energy recovery.   Closed  loop ground source heat pumps may be  utilized  if  they  are  cost  effective  and  contribute  to  IGgCC  compliance  and meeting sustainable strategy goals. 

B. All  enclosed  occupied  building  areas  shall  be  provided with  heating,  ventilating  and  air conditioning  in  accordance with  code  requirements  and  applicable  standards  and  design criteria  listed.  HVAC  controls  shall  provide  for  occupant  comfort  control.    Mechanical systems  shall  have  control  settings  for  occupied,  unoccupied,  and  temporary  override. Interior  spaces  shall  be  zoned  together  and  separately  from  exterior  spaces.  Each conference  room,  break  room/lunchroom,  and  training  room  shall  be  separately  zoned.  The spaces shall be zoned such that spaces with dissimilar use and occupancy are not on the same terminalair‐handling unit.   

C. Hot water,  chilled water,  refrigerant  and  condensate  piping  shall  be  selected,  installed, sized and insulated per NFPA and ASHRAE standards.   

D. Building  pressurization  shall  be  maintained  positive  relative  to  outdoors  at  all  times.  Pressurization shall be highest  in  the  ticketing area and  lower  in  the public waiting areas. 

Page 93: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐88 

Part 3 Project RequirementsJuly 18, 2013

 

 

The office areas shall be designed to provide a positive pressure relative to waiting areas.  Restrooms,  Janitor  Closets  and  mechanical  and  electrical  equipment  rooms  shall  be maintained at negative pressure relative to adjacent areas, from which they shall draw air for ventilation. Restroom shall be exhausted at a rate of 750 cfm min. per urinal and 150 cfm min. per water closet.  Janitor closets shall be exhausted at a rate of 150 cfm minimum.  Maximum flow rate through an undercut door shall be 150 cfm.  

E. Exhaust  and makeup  air  ventilation  shall  be  provided  in  accordance with  all  applicable codes and NFPA and ASHRAE standards. Exhaust air shall discharge outdoors. 

F. Mechanical  systems  designs  shall  insure  that  airborne  and  waterborne  contaminant emissions  will  meet  all  applicable  codes  and  regulations.  The  percentage  of  air reciralculated  into the occupied spaces of the facility shall take ASHRAE recommendations into account to avoid sick building syndrome and other undesirable effects associated with stagnant air. 

G. Air shall be supplied and returned to fans and air handling units by galvanized sheet steel ducts.   Exposed ductwork shall be painted spiral duct. Provide elbows, transitions, offsets, branch  connections,  and  other  construction  fabricated  of  galvanized,  sheet  steel.   Ducts that  serve  ceiling  air  outlets  in  air  conditioned  spaces  shall  be  externally  insulated galvanized  steel with  short  runs  of  insulated  flexible  ducts.  Flexible  duct  runs  shall  not exceed 5 ft in length and shall only be used in concealed locations. Ductwork shall be fitted with  volume  control  dampers  at  supply  and  return  branches  to  provide  for  accurate  air balancing. Fire and smoke dampers shall be provided in fire partitions.   Duct access panels shall be provided  for duct mounted equipment. Air devices  shall be  factory‐fabricated of corrosion‐resistant  steel or  aluminum  to distribute  the  specified  amount of  air uniformly over  the  conditioned  space.  All  air  intake  louvers  shall  be  fitted  with  thermostatically controlled motorized dampers. 

H. Static pressure classifications shall conform to the following: 

1. Supply Ducts:  3‐inch wg . 

2. Return Ducts:  2‐inch wg , negative pressure. 

3. Exhaust Ducts:  2‐inch wg , negative pressure. 

I. Provide duct  accessories  according  to  applicable details  shown  in  SMACNA's  "HVAC Duct Construction Standards‐‐Metal and Flexible" for metal ducts. Provide duct access panels for access  to both  sides of duct  coils.   Provide duct access panels downstream  from volume dampers, fire dampers, turning vanes, and equipment unless noted otherwise.  

J. Externally  insulate  concealed  supply  ductwork.    Externally  insulate  concealed  return ductwork as required by code and ASHRAE.  Insulation for concealed ducts shall be blanket fiberglass.    Insulation  for  exposed  ductwork  in  mechanical  rooms  shall  be  rigid  board insulation. Insulate exposed ductwork outside of mechanical rooms with  liner.   Outside air ductwork shall be insulated externally with mineral‐fiber blanket for concealed and mineral‐fiber board for exposed ductwork.   Provide field applied glass cloth  jacket on all  insulation and a vapor barrier on ducts subject to cold temperatures.  Provide insulation thickness as 

Page 94: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐89 

Part 3 Project RequirementsJuly 18, 2013

 

 

required to meet the minimum R‐value per code but supply and outside air ductwork shall have R‐4.2 min.Supply and outside air ductwork shall be  insulated externally with mineral‐fiber blanket  for  concealed  and mineral‐fiber board  for exposed ductwork.   Provide  field applied  glass  cloth  jacket  on  all  insulation  and  a  vapor  barrier  on  ducts  subject  to  cold temperatures.  Provide thickness as required to meet the minimum R‐value per code.  

K. In  acoustical  tile  ceilings  provide  square,  fully  adjustable  air  pattern  supply  diffusers.  At perimeters provide  linear  slot  diffusers. Where  air  is  to  be  distributed  in  high  bay  areas (20'+) provide high velocity drum type diffusers.  Insulate the backs of all supply air diffusers installed in ceilings with blanket fiberglass insulation. 

L. Air filters shall be of the following types: Under 5,000 cfm shall be replaceable media; 5,000 cfm  and  over  shall  be  primary  ‐  bag  type,  80‐85%  efficiency with  prefilter  –  replaceable media. 

M. All mechanical equipment shall be  located to allow easy access.   Provide access doors  for equipment accessed through walls, partitions, or fixed ceilings.   Locate equipment such as VAV boxes above the ceiling in corridors to the extent possible. 

N. Start‐up:  After  completion  of  installation,  prepare  services  for  starting‐up  by  testing appropriately for proper operation.   Engage a factory‐authorized service representative to inspect,  test  and  adjust  components,  assemblies,  and  equipment  installations  on major equipment.  Perform startup checks according to manufacturer’s written instructions. 

L.O. Provide complete Testing, Adjusting and Balancing (TAB) of all air and water distribution systems for HVAC  equipment.    Provide  a  report  conforming  to  the most  recent  procedural  standards  for Testing, Adjusting and Balancing requirements of AABC, NEBB, or TABB. 

12.5.3  Air Curtains 

Heated air curtains shall be provided at all train entrances and exits as well as all overhead door service  area  entrances.    Air  curtains  shall  be  designed  for  the  local winter wind  velocity  as identified  in  the  latest  version  of  the  ASHRAE  Fundamentals.    Air  curtains  supply  air temperature shall be tempered to a minimum of 50°F DB.   

12.5.4  Fuel Oil System 

A. No. 2 fuel oil shall be pumped to the boilers from an exterior underground oil tank capable of storing one  (1) month’s oil at  fully  loaded boiler operation. The  tank shall be dual wall fiberglass design and be provided with leak detection system. Ancillary tank equipment such as oil fill boxes, vents, manholes, oil level indicators, anti‐siphon valves, and alarms shall be provided.  The fuel oil transfer pumps shall be skid mounted duplex type each being capable of providing sufficient oil for both boilers operating 100% loaded. 

A. 12.5.3  Diesel Emissions and Emergency Ventilation 

B. A.  Diesel  Emissions  and  Emergency  VentilationWhere  a  closed  or  partially  enclosed overbuild is utilized, a ventilation system shall be designed to accommodate normal operations as well as life safety requirements.  

Page 95: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐90 

Part 3 Project RequirementsJuly 18, 2013

 

 

C.B. Diesel  emissions  and  emergency  ventilation  systems  shall  be  analyzed  and  designed pursuant  to  requirements  of  the  Amtrak  Station  SDPStation  Program  and  Planning Standards and Guidelines Appendix G.  

12.5.45  HVAC Controls 

A. Provide a Building Management  System  (BMS) based on a distributive  type Direct Digital Control (DDC).  The system shall be capable of peer to peer communication on a primary or primary/  secondary,  BACnet  or  Lontalk,  open  protocol  network.  Provide  an  operator workstation  to  permit  interface with  the  network  via  dynamic  color  graphics with  each mechanical  system,  building  floor  plan,  and  control  device  depicted  by  point‐and‐click graphics. Access to the network shall be available through a local workstation or a portable personal computer able  to be plugged  into  the system devices and  remotely  through  the use of the Internet.  Provide means for the BMS to integrate into existing Amtrak systems. 

B. The  Internet  access  shall  be made  possible  through  the  creation  of  a  Rochester  Station specific web  site.   The  control  system  shall be  furnished with all  software, programming, hardware and start‐up services necessary for the implementation of the web site.  The web site access shall allow full BMS control from a remote personal computer without the need for  additional  software  and  through  standard  internet  protocol  and  graphics  and  be password secured.  

C. The  BMS  shall  consist  of  sensors,  indicators,  actuators,  final  control  elements,  interface equipment, other apparatus, accessories, and software connected to distributed controllers operating  in  multiuser,  multitasking  environment  on  token‐passing  network  and programmed to control mechanical systems and equipment. 

D. Microprocessor controlled HVAC equipment shall be furnished with all necessary  interface equipment and  software necessary  for  full BMS  control and monitoring.   This equipment would  include  but  not  be  limited  to  boilers,  chillers,  pumps,  exhaust  fans,  variable frequency drives, heat  recovery units, packaged  rooftop units,  and  air handling units. All sensors and controls devices shall be electronic.  Where torque requirements do not allow for the use of electronic actuators, electric actuators shall be used.     

E. A  CO2  detection  system  shall  be  provided  in  order  to  control  the  rate  of  outdoor  air ventilation. The system shall  initiate an audio/visual alarm and send an alarm signal to the BMS.Provide CO2 sensors as required per code and ASHRAE standards. 

F. Provide damper and valve actuators with position indicators and manual overrides. 

G. The  Building Management  System  (BMS)  shall meet  but  not  be  limited  to  the  following criteria: 

1. Ability to conform to peak load criteria for energy cost savings. 

2. Automated  equipment  maintenance  scheduling  resulting  in  lower  anticipated equipment life cycle costs. 

3. Benefits of monitoring equipment performance to be within acceptable limits. 

Page 96: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐91 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. Utility usage patterns. 

5. Temperature setbacks corresponding to occupancy and utilization patterns. 

6. Uniform and limited control of temperature settings. 

7. Filter performance monitoring and replacement pattern data accumulation. 

8. Ability to monitor and record indoor and outdoor conditions affecting HVAC systems, as well as alarms, failures, and abnormal operating conditions. 

9. Ability to automatically control selected equipment such as rooftop units, air handlers, pumps, fans, boilers, heaters, valves, and automated dampers. 

10. Ability  to perform utility  accounting by displaying  and  recording water, electrical  and natural gas usage. 

11. The BMS  input/output hardware shall be capable of receiving and sending both digital and analog signals. 

12. All functions of the BMS shall be monitored by means of color coded graphics displays on monitors. 

13. The  BMS  operating  environment  shall  be  the  current  version  of Windows  operating system. 

12.6  PLUMBING SYSTEMS 

The plumbing system consists of all fixtures, potable cold and hot water piping and equipment, piping insulation, water heating equipment, sanitary waste and vent piping systems, and other specialty piping and equipment within 6 feet of the building. Provide working space around all equipment.    Provide  concrete  pads  under  all  equipment.    Provide  all  required  fittings, connections and accessories required for a complete and usable system.   

12.6.1  Domestic Water Distribution 

Domestic  water  distribution  consists  of  the  following  elements:  Piping,  Piping  specialties, Valves, Insulation, Meters and Gauges.  

Provide  a domestic  cold, hot  and hot water  re‐circulating water distribution  system without supply  interruptions. Provide natural gas domestic water heater(s) with adequate capacity for serving fixtures.  Provide in‐line circulator for hot water re‐circulating water distribution system. Provide service valves, unions, meters and gauges, and access panels sufficient for maintenance per  the  plumbing  code  and  regulations.  Provide  service  valves  to  separately  shut  off  each fixture, each toilet group each wing or functional area of the building.  Provide identification for piping and equipment.   Provide ice‐maker connector box for refrigerators.  

Perform a flow test to determine system requirements prior to system design.  

Page 97: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐92 

Part 3 Project RequirementsJuly 18, 2013

 

 

12.6.2  Piping Materials 

Hot, Cold and Recirculation Water Piping 2 1/2” and Smaller: Aboveground, shall be ASTM B 88, Type L drawn‐temper copper tubing with soldered joints.  Below ground or within slabs, provide ASTM B 88,  Type K  annealed‐temper  copper  tubing  with  soldered  joints.    Use  the  fewest possible joints below ground and within slabs. 

Hot,  Cold  and  Recirculation Water  Piping  3”  and  Larger:  Provide ASTM A 53/A 53M,  Type  S, Grade A or B, Schedule 40, galvanized.  Include ends matching joining method. 

12.6.3  Piping Specialties 

Hammer Arrestors: Install Hammer Arrestors, also known as shock absorbers, on the cold and hot water distribution  systems, where  the  action of quick operating  valves  could  result  in  a water hammer condition.   

Hose Bibs/Hydrants: Freeze proof wall hydrants  shall be provided every 200  feet around  the perimeter of the station building.  Provide hose bibs in mechanical rooms.  

Pressure reducing valves shall be provided where water pressure  is above 60 psi at the water service entry area. 

Dielectric  Fittings:  Install  dielectric  fittings  for  pipe  connections  where  there  are  dissimilar metals. 

12.6.4  Valves 

General‐Duty Valve Applications:  Provide the following valve types: 

A. Shutoff Duty: Use bronze ball valves for piping NPS 3 and smaller.  Use cast‐iron gate valves with flanged ends for piping NPS 4 and larger. 

B. Throttling Duty: Use bronze ball valves or butterfly valves for piping NPS 3 and smaller.  Use cast‐iron globe or gate valves with flanged ends for piping NPS 4 and larger. 

C. Hot‐Water‐Piping, Balancing Duty:  Calibrated balancing valves. 

D. Drain Duty: Hose‐end drain valves. 

E. Provide sectional valve close to water main on each branch and riser serving plumbing fixtures or equipment.   Use ball valves for piping NPS 3 and smaller.   Use gate valves for piping NPS 4 and larger. 

F. Provide shutoff valve on each water supply to equipment and on each water supply to plumbing fixtures without supply stops.  Use ball valves for piping NPS 3 and smaller.  Use gate valves for piping NPS 4 and larger. 

G. Provide  drain  valves  for  equipment,  at  base  of  each water  riser,  at  low  points  in horizontal piping, and where required to drain water piping. 

H. Provide hose‐end drain valves at low points in water mains, risers, and branches. 

Page 98: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐93 

Part 3 Project RequirementsJuly 18, 2013

 

 

I. Provide  calibrated balancing  valves  in each hot‐water  circulation  return branch  and discharge  side  of  each  pump  and  circulator.    Set  calibrated  balancing  valves  partly open to restrict but not stop flow. 

C.  

12.6.5  Drain Duty:  Hose‐end drain valves. 

A. Provide  sectional valve close  to water main on each branch and riser serving plumbing fixtures or equipment.  Use ball valves for piping NPS 3 and smaller.  Use gate valves for piping NPS 4 and larger. 

B. Provide shutoff valve on each water supply to equipment and on each water  supply  to plumbing  fixtures without  supply  stops.   Use ball  valves  for  piping NPS 3 and smaller.  Use gate valves for piping NPS 4 and larger. 

C. Provide drain valves for equipment, at base of each water riser, at low points in horizontal piping, and where required to drain water piping. 

D. Provide hose‐end drain valves at low points in water mains, risers, and branches. 

E. Provide  calibrated  balancing  valves  in  each  hot‐water  circulation  return  branch  and discharge side of each pump and circulator.   Set calibrated balancing valves partly open to restrict but not stop flow. 

12.6.65  Water Service 

A. A Reduced Pressure Backflow Preventer shall be provided for the incoming water service and on mechanical system water make‐up lines. 

B. Shutoff valve, hose‐end drain valve, strainer, pressure gage, and test tee with valve, shall be inside the building at the domestic water service.   

C. Provide cast‐iron sleeve with water stop and mechanical sleeve seal at each service pipe penetration  through  a  foundation  wall.    Select  number  of  interlocking  rubber  links required to make installation watertight.   

12.6.67  Cleaning 

Clean and disinfect potable domestic water piping as  follows:   Disinfect and purge  the water supply as prescribed by authorities having jurisdiction prior to use. Procedures shall be at least equivalent to either AWWA C651 or AWWA C652.  

12.6.7 Piping Insulation: 

A. Provide pipe insulation thickness as required by code.  

B. Provide minimum ½” thick insulation on cold water piping. 

C. Provide vapor retarder on all piping subject to water temperatures below 70 deg F. 

D. Provide heavy PVC fitting covers on all fittings. 

Page 99: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐94 

Part 3 Project RequirementsJuly 18, 2013

 

 

E. Provide insulation on all piping subject to condensation formation. 

12.6.8  Plumbing Fixtures 

A. Provide  quantity  and  type  of  plumbing  fixtures  required  for  the  occupancy,  use,  and functions described for this facility.  

B. General:    Plumbing  fixtures  consist  of  the  following  elements: Water  Closets, Urinals, Lavatories, Sinks, Service Sinks, Showers, Basins, Drinking fountains. 

C. Provide durable and efficient plumbing fixtures that operate smoothly and easily without leaks,  stoppages  or  other  malfunctions.  Conform  to  code  including  accessibility requirements. 

D. All plumbing fixtures, where applicable, shall be of a water saving design. 

E. All drainage piping shall have adequate slope toward the collection points. 

F. Trap primers shall be used as required by local codes and shall be installed on lines with consideration to the frequency of operation. 

G. Exterior hose bibs shall be key‐type with freeze protection. 

H. All janitor and custodial rooms shall have floor mounted mop basin with bucket holding supported spout and short flexible hose connection and rack for storing mops.   Provide stainless steel wall guards where installed against gypsum wallboard construction.  

I. Provide all water supplies with key operated service valves. 

J. Water  Closets:  Provide  wall‐hung  Low‐Flush  water  closets  with  hard‐wired  sensor‐operated electronic  flushometers  throughout  the  facility  in  sufficient quantity  to  serve occupant load. 

K. Urinals: Provide wall‐hung Low Flow urinals with hard‐wired sensor operated electronic flushometers in all men’s rooms in sufficient quantity to serve occupant load.  

L. Lavatories:  Provide  wall‐hung  lavatories  in  staff  areas  and  under‐mount  countertop lavatories  in  public  restrooms. Hard‐wired  sensor  operated  electronic  faucets  shall  be installed for washing hands.  

M. Sinks: Provide stainless steel countertop sinks in break rooms.   

N. Drinking  Fountains:  Provide  wall  hung  electric  water  coolers  outside  of  grouped restrooms, with accessibility compliance.  

O. Not Allowed: 

1. Battery operated flushometers and faucets. 

2. Flexible  Elastomeric  insulation  on  piping  containing  fluids with  temperatures  greater than 100 deg F. 

3. Air admittance valves. 

Page 100: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐95 

Part 3 Project RequirementsJuly 18, 2013

 

 

12.6.9  Sanitary Drainage System 

A. General:   Sanitary waste consists of the following elements: Piping, Cleanouts, and Drains. 

B. All floor/area drain piping shall be sized based on the maximum expected flow loading with a generous allowance for fouling due to gravity flow velocities. 

C. Provide  a  floor  drain  at  all  equipment  having  a  condensate  drain,  including  air  handling units with cooling coils and other mechanical equipment. 

D. Above‐ground Waste pipe & fittings:  Provide cast iron hub and spigot, with neoprene joint seals.   

E. Below‐ground Waste pipe & fittings:  Provide schedule 40 PVC.  

F. Vent pipe &  fittings: Provide cast  iron hub and  spigot, with neoprene  joint  seals.   Where approved for use, plenum‐rated schedule 40 CPVC per ASTM D 2665 may be provided.  

G. Minimum pipe size used underground shall be 3”. 

H. Service Pipe  Installation: Provide  cast‐iron  sleeve with water  stop  and mechanical  sleeve seal at each service pipe penetration through a foundation wall. 

I. Cleanouts: 

1. Provide cleanouts at all changes in direction of 45° or greater, every 50 feet on piping 4” and less, and every 100 feet for piping over 4”. 

2. Provide cleanouts at the base of all risers. 3. Provide wall cleanouts at gang toilets. 

J. Drains: 

1. General: All  floor drainage  systems  shall be coordinated with  the under  floor building elements.  

1.2. Floor drains in toilet rooms shall be stainless steel type.  

2.3. All  floor  drains  shall  be  installed with  trap  primers.    Electronic  trap  primers  shall  be provided where water supply is not based on operation of toilet fixture flush valves. 

3.4. Miscellaneous Areas (sanitary waste): 

4.a. Restrooms: Provide at least one floor drain in each room. 

5.b. Mechanical Rooms.   Provide a minimum of one  floor drain  in each mechanical room.    Provide  additional  floor  drains where  required  to  eliminate  horizontal drainage piping from equipment exceeding 10 feet. 

12.6.10  Rain Water Drainage 

A. Rain water drainage consists of the following elements: Piping, Cleanouts, and Insulation. 

B. Provide drainage for disposal of rain water and clear wastes, as required by the code. 

Page 101: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐96 

Part 3 Project RequirementsJuly 18, 2013

 

 

C. Drainage  for outdoor areas that are completely surrounded by construction that prevents natural drainage (e.g. areaways) or that are so sloped as to result in accumulation of water or ponding.  

D. Drainage of  interior areas where ground water may accumulate naturally,  including sump pits and elevator pits.  

E. Prevent  inadvertent  ponding  by  protecting  drain  openings  from  clogging,  using  raised strainers with minimum height of 4  inches wherever possible and  flat gratings  in all other locations. 

F. Maintenance  of  Drainage:    Pipes  sloped  at  1/8  inch  per  foot, minimum,  downward  in direction of flow.  

F.G. Drainage Outlets: 

1. Drainage Outlets: 

2.1. Secondary Drainage:  Drain to completely redundant drain piping system. 

3.2. Scuppers:  Drain to grade adjacent to building, rain water drainage system, street gutter, or dry well located in landscaped area. 

4.3. Areaways and Courtyards:   Drain  to  rain water drainage system, sump pit with pump, dry well located in landscaped area, or water retention pond.  

5.H.Above‐ground Rain Water Piping:  Use one or both of the following: 6.1. Cast iron pipe, hub and spigot, with neoprene joint seals. 7.2. Cast iron pipe, hubless, with neoprene gaskets and stainless steel clamps.  

8.I. Below‐ground Rain Water Piping:  Use one or both of the following:  9.1. Cast iron pipe, hub and spigot, with neoprene joint seals. 10.2. PVC pipe and fittings, with solvent welded or gasketed joints.  

11.J. Roof drains, Area drains, and Floor drains:  Use galvanized steel, cast iron, or stainless steel. 

12.K. Insulation:    Provide ½”  thick  insulation with  vapor  retarder on  roof drain bodies  and horizontal leaders inside the facility. 

12.6.11  Natural Gas Piping 

A. Provide natural gas for use by HVAC and plumbing in accordance with code.  

B. Obtain natural gas pressures from the local gas utility provider.  Provide pressure regulators accordingly.  

C. Coordinate  required  inlet  pressure  with  equipment  manufacturer  and  size  gas  piping accordingly per code.  

D. Drips  and  Sediment  Traps:  Provide  drips  at  connections  to  equipment  and  other  points where condensate may collect and at  the outlet of  service meters.   Locate where  readily accessible for cleaning and emptying.  Do not install where condensate would be subject to freezing. 

Page 102: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐97 

Part 3 Project RequirementsJuly 18, 2013

 

 

E. Provide unions  in pipes NPS 2 and  smaller, adjacent  to each valve, at  final  connection  to each piece of equipment. Unions are not required on flanged devices. 

F. Provide shutoff valves at each piece of equipment.  Locate shutoff valves upstream of drip and sediment traps. 

G. Provide vent piping for gas pressure regulators and gas trains, extend outside building, and vent  to  atmosphere.    Terminate  vents  with  turned‐down,  reducing‐elbow  fittings  with corrosion‐resistant insect screens in large end. 

H. Prepare, prime and paint exterior gas piping with yellow oil‐based enamel paint.  

I. Above‐ground  gas  pipe  shall  be ASTM A  53/53M,  black  steel,  Schedule  40,  Type  E  or  S, Grade B with threaded or welded joints.  

12.7  Fire Protection 

A. Provide  an  integrated  fire  alarm  and  automatic  suppression  system  capable  of  notifying building  occupants  and  controlling  any  fire  that  may  start  inside  the  facility.    Provide working space around all equipment.  Provide concrete pads under all equipment.  Provide all  required  fittings,  connections  and  accessories  required  for  a  complete  and  usable system.  Provide portable fire extinguishers and recessed fire rated extinguisher cabinets in accordance with NFPA 10. 

B. Provide systems complying with the code and with the latest versions of NFPA as they apply to the space and/or application being served. 

C. Coordinate building systems and services with the Fire Protection and Alarm systems such that  there  shall be, where appropriate, automatic  shutdown of  the affected  system(s) or service(s) should any of the fire protection systems are activated.  (e.g. air handling system shutdown where the associated fire protection system is activated).  

D. Clean Agent Systems:    In areas within the building where high value electronics or critical functions occur, clean agent systems may be used. 

E. Standpipe Design  and  Installation:    The  construction  shall provide  a  standpipe  system  as required by code and NFPA 14‐2007.   

F. Sprinkler Systems 

1. Provide  automatic  fire  sprinkler  or  fire  extinguishing  systems  to  provide  complete coverage throughout the facility.   Provide wet pipe sprinkler systems unless otherwise required by code.     

2. Provide  quick‐response  recessed  sprinklers with  ordinary  temperature  rating  in  areas with finished ceilings.   Provide white sprinklers and escutcheon plates to match ceiling color.    

3. Provide sprinkler head wire guards in storage rooms, mechanical rooms and other areas where heads could be subjected to damage from material handling.  

Page 103: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐98 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. The  incoming  sprinkler  service  shall  be  provided  with  a  double  check  backflow preventer. 

5. The  systems  shall be  completely hydraulically designed  to meet  the density  and  flow requirements  set‐forth  in NFPA 13, 30 and 30A.   The areas of  the building  shall have Hazard Classifications per NFPA 13 and code. Confirm water pressure at the site prior to finalizing Fire Sprinkler construction documents. 

6. System Testing:  After the system has been installed, a pre‐test and final acceptance test shall  be  performed.  The  testing  shall  be  in  accordance with  the  requirements  of  the appropriate NFPA sections and local and state requirements. 

7. Pipe: Use one or more of the following: 

o Materials permitted by code 

o Copper pipe with soldered joints. o Steel pipe with threaded, grooved, or welded joints.  

8. Fittings:  Use one or more of the following: 

o Materials permitted by code 

o Copper. 

o Steel. 

o Cast iron. 

SECTION 13.  ELECTRICAL REQUIREMENTS 

13.1  General Requirements 

13.1  General Requirements 

A. Furnish  and  install  all electrical  items of work  required  for  a  complete,  fully operational, energy  efficient  and  low maintenance  electrical  system  in  Rochester  Station.  The  design shall  consider equipment  life expectancy, energy  costs,  future expansion, maintainability, and maintenance costs. 

B. In addition to these requirements, the contractor shall refer to Amtrak Engineering Stations Standard Design Practices (SDP) for additional requirements. 

C. All electrical equipment and materials  furnished and  installed under this Contract shall be compatible in all respects with the other equipment in the respective system. 

D. The  design  shall  meet  or  exceed  all  current  industry  standards  and  applicable  codes. Electrical equipment, attachments and  supports  shall be designed  to meet or exceed  the requirements of the Building Code of New York State. 

E. The  room  sizes  for  the  electrical  and  communication  rooms  shown  on  the  Conceptual Drawings are  for guidance only. The Design Professional  shall determine  the actual  room 

Page 104: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐99 

Part 3 Project RequirementsJuly 18, 2013

 

 

sizes and locations. Any changes to the room sizes must be justifiable and approved by the Department.   Similarly, the ratings and sizes of the electrical equipment, if shown, are the minimum  requirements;  the  actual  ratings  and  sizes  shall  be  determined  by  the  Design Professional. 

F. Electrical  one‐line  diagrams,  communication  riser  diagrams,  security  riser  diagrams  and closed  circuit  television  (CCTV)  riser  diagrams  are  provided  for  conceptual  reference  of anticipated systems. Final design of these systems  including sizes, quantities and  locations of all devices should be performed by the Design‐Build Contractor and coordinated with all agencies (Amtrak and Trailways). 

G. In  the  case  of  any  conflict  between  the  Specifications,  Codes,  Standards,  Drawings, Comprehensive User’s Requirements and/or the Project Requirements for the same subject, the Design‐Builder shall comply with the most stringent requirement. 

H. All Electrical equipment  shall be of heavy‐duty  industrial‐grade quality.   Catalog  cuts and samples  of  equipment  (such  as wires/cables,  devices  and  fittings)  shall  be  submitted  to Amtrak for information. All electrical equipment shall be UL Listed. 

I. All  electrical  equipment  including  but  not  limited  to  distribution  equipment,  conduit, wires/cables,  fixtures,  panels,  and  receptacles  shall  be  furnished  and  installed  with permanent nameplates or  tags  that shall  identify  the equipment, voltage, circuit number, source, phase orientation, and destination of power flow as applicable. 

J. For any  repetitive  type of  installation  such as  lighting  fixtures a  sample mock‐up  shall be installed for review and approval by the Department before commencement of remaining associated. 

K. Design for all electrical and data cabling for the concourse level shall comply with NFPA 130‐2010 Section 5.4 Wiring Requirements. 

L. Provide tables and schedules listing the manufacturers, ratings and details of all overcurrent protective  devices  and  electrical  equipment  (including  but  not  limited  to  switchboards, panels, disconnects and  transformers). Provide  full‐size drawings showing  the  locations of all panels (distribution boards, subdistribution boards, panelboards (typical)) on each floor. Use Amtrak standard panel schedules and fill in all information. 

M. All  wires,  cables,  busses,  lugs  and  electrical  connections  shall  be  copper.  Lugs  shall  be suitable for copper cables only. 

N. All  electrical  distribution  equipment  shall  be  fully  rated  for  the  available  short  circuit current.  Series  rated  equipment  and  systems  are  not  acceptable.  The  Design‐Build Contractor shall perform a short circuit current study using an  industry approved software application.  All  busses,  motor  loads,  cable  lengths  and  inputs  to  this  study  shall  be accurately reflected on this study. 

O. The  Contract  documents  detail  the minimum  requirements  for  equipment, material  and installation procedures. All equipment and material that  is  furnished and  installed, and all installation procedures, must meet or exceed these minimum requirements. 

Page 105: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐100 

Part 3 Project RequirementsJuly 18, 2013

 

 

P. There shall not be any plumbing (water, sewer, or drain), gas, sprinkler, steam or hydraulic lines  passing  through  any  electrical  or  Communications  equipment  rooms.  In  all  other locations,  a  minimum  of  12”  separation  in  all  directions  shall  be  maintained  between electrical raceway and plumbing, steam, hydraulic, and other lines and their appurtenances. 

Q. All Amtrak Standard Drawings  included  in  the RFP documents  shall be part of  the design package. 

R. Upon completion of equipment  installation, the Design‐Builder shall  fill  in and waterproof all  openings  in  an  approved  manner.  All  waterproofing  shall  be  maintained  when penetrating exterior walls, ceilings, roofs and slabs. 

S. UPS‐backed electrical panels  in the Communications Rooms shall only feed the equipment inside the respective room. UPS backed panels feeding computer workstations outlets and other  loads  outside  the  communication  rooms  shall  not  be  installed  inside  the communications rooms. 

T. Power,  lighting, and  receptacle panels and disconnects  shall not be  installed  in  the  same rooms as Communications panels, UPSs and transformers  if they are not dedicated for the equipment in that room. 

U. Coordinate the design with all other trades and also furnish and install power as required to all  mechanical,  architectural,  instrumentation  and  controls,  communications,  and  other equipment, including but not limited to electrically operated skylights, doors, gates, grilles, all  cranes  (including  jib  and  monorail  cranes).  Provide  General  Arrangement  drawings showing the coordination of all equipment. 

V. Follow NFPA 70 (NEC) Article 408.3(E) for electrical equipment phase arrangement. 

W. Electrical  equipment  requiring  examination,  adjustment,  servicing  or maintenance while energized  shall be  field marked  to warn qualified personnel of potential electric arc  flash hazards in accordance with NEC Article 110.16. 

13.2  Codes and Standards 

A. NFPA 

a. NFPA 70 (2011): National Electrical Code 

b. NFPA 72 (2010): National Fire Alarm and Signaling Code 

c. NFPA 130 (2010): Standard for Fixed Guideway Transit and Passenger Rail Systems 

B. Amtrak 

a. Amtrak Station Program and Planning – Standards and Guidelines 

b. Amtrak Engineering Stations Standards Design Practices (SDP) 

c. Amtrak Premise Distribution System Standards  

C. Standards  for materials  listed  in Specifications  (NEMA, UL, ANSI, etc.)  shall be  referenced under each  specification  section where applicable  in order  to ensure durable and quality 

Page 106: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐101 

Part 3 Project RequirementsJuly 18, 2013

 

 

materials are provided and  installed on  the project. Non‐applicable  references  should be deleted in order to eliminate confusion. 

D. Symbols on drawings shall comply with current ANSI standards. 

 

13.3  Calculations and Coordination Drawings 

A. Calculations ‐ The Design‐Builder shall provide the following design calculations certified by a licensed Professional Engineer for Department records: 

1. Load calculations ‐ The complete electrical system shall be sized for the connected load plus  an  additional  30%  spare  capacity.  This  includes but  is  not  limited  to  all  feeders, switchboards,  distribution  boards,  subdistribution  boards,  panelboards,  transformers, and uninterruptible power supplies. 

2. Voltage Drop calculations: 

a. The system working voltages shall satisfy ANSI C84.1. 

b. The  total  voltage  drop  from  the  power  source  (main  circuit  breaker)  to  the utilization device shall not exceed 5% except as noted below in 3) and 4). 

c. The total voltage drop in the main and sub feeders shall not exceed 3%. 

d. The voltage drop in the branch circuit conductors shall not exceed 3%. 

e. The motor  feeder  total voltage drop  shall not exceed 4%. Fire water pump motor feeder voltage drop on inrush shall not exceed 15%. 

f. The voltage drop on separately derived systems  for sensitive electronic equipment such as computers shall not exceed the limits as per NEC Article 647.4D. 

3. Short circuit current calculations ‐ The short circuit ratings of all the power distribution equipment shall be based on short circuit study calculations, with minimum ratings as per Section 13.6. The Design‐Builder shall obtain,  in writing,  the available short circuit current  at  the  utility  from  Rochester  Gas &  Electric.  Provide  a  detailed  short  circuit current  calculation  from  Rochester  Gas  &  Electric’s  transformer  vault  to  the  final panelboard or disconnect switch on each bus and feeder on the one‐line diagram, taking into account all transformers, motors, feeder and branch circuit lengths. 

B. Coordination study ‐ The over‐current protective devices shall be sized and set based on a coordination study developed at the design development phase. The study shall contain the fault and load current values listed at key points on the one‐line diagram to determine the necessary equipment fault ratings. Ground fault protection shall be furnished and installed on the main circuit breaker and on all feeder breakers. Zone selective  interlocking shall be used  to achieve  the best possible  coordination with  the downstream breakers. Provide a coordination  study  showing  that  the  primary‐side  circuit  breaker  can  handle  the  inrush current of any associated transformer(s). The design professional shall propose solutions to 

Page 107: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐102 

Part 3 Project RequirementsJuly 18, 2013

 

 

any  problems  and  demonstrate  that  coordination  can  be  achieved  with  the  proposed devices. 

C. Furnish  and  install  seismic  restraints &  vibration  isolation  for  all  supporting  systems  for electrical equipment, including but not limited to conduit racks and lighting fixtures. 

D. Coordination Drawings – Before commencing on the electrical work at the station, the DB contractor shall prepare a set of coordination drawings displaying all HVAC, plumbing, fire protection,  fire detection, electrical power, electrical  lighting and electrical equipment. All ‘clashes’  of  system  shall  be  clearly  identified  to  the  engineer  for  expeditious  review; otherwise  it  is  assumed  that  the  entire  drawing  is  coordinated  with  no  ‘clashes’.  In preparing the Coordination Drawings the following should be followed: 

1. Underground Plans: Shall clearly show all elements of HVAC, Plumbing, Fire Protection, Fire Detection, Communication and Electrical being routed under the slab of referenced floor. 

2. Floorplans:  Shall  clearly  show  all  elements  of  HVAC,  Plumbing,  Fire  Protection,  Fire Detection,  Communication  and  Electrical  being  routed  above  the  slab  of  referenced floor and below the ceiling. 

3. Reflected  Ceiling  Plans:  Shall  clearly  show  all  elements  of  HVAC,  Plumbing,  Fire Protection, Fire Detection, Communication and Electrical being at or above the ceiling of the reference floor. 

13.4 Area Types 

A. Classified  (Hazardous)  Areas  ‐  The  area  classifications  given  here  are  the  minimum requirements. The Design‐Builder shall make a comprehensive study of  the entire Amtrak Station  to  identify  all  areas  that  are  required  to  be  classified  and  determine  their classifications. The extent of classification shall be as per area classification drawings based on  the  comprehensive  study.  All  classification  drawings  shall  be  certified  by  a  licensed Professional  Engineer  and  shall  be  submitted  to  the  Department  for  information.  Area classifications shall be based on the use of diesel fuel or as noted. The study shall include: 

1. calculations to determine the actual extent of the classified areas; 

2. explanation of NEC classifications; 

3. fueling regulations and considerations; 

4. design criteria for electrical systems in hazardous locations; 

5. ventilation requirements; 

6. temperature limits of diesel fuels before ignition/detonation; 

7. references. 

B. The study should comply with all applicable local and national codes. The following areas in Rochester Station  shall be considered  to be Class 1, Division 1, Group  ‘D’  throughout  the area regardless of height unless otherwise noted below: 

Page 108: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐103 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. All areas TBD. 

2. Wherever possible, all electrical equipment shall be installed outside the classified areas except where  required by  the Codes or equipment  restrictions. All  feeder and branch circuit conduits shall be installed exposed.  

3. Wet  Areas  ‐  (Wherever  possible,  except where  required  by  the  Codes  or  equipment restrictions,  the electrical equipment  shall be  installed outside of  the wet areas or at least out of the direct path of water.) 

4. The following open areas plus the 25’ periphery around them: 

o Outdoors, including under canopies and platforms; 

o Under skylights; 

o Any other areas required by the Codes. 

o Enclosed (the indicated area only): 

o Water  meter room; 

o Sewer ejector pump room; 

o High‐pressure wash room; 

o Elevator pit; 

o Escalator pit; 

o Sump pits; 

o Restrooms, toilets and personnel wash areas; 

o Any other areas required by the Codes. 

o Harsh/corrosive atmosphere areas: 

o Battery charging room; 

o Boiler room; 

o Any other areas required by the Codes. 

o Wet and classified: 

o Pits 

13.4  Maintenance requirements 

A. Provide workspace around all electrical and communication equipment as required by the National Electric Code and referenced Amtrak Standards. 

B. All  lighting  fixtures  shall  be  accessible with  a  stepladder  (up  to  10  feet)  or  a  scissors‐lift (higher than 10 feet) for lamp replacement and other maintenance. 

C. Free space on both sides of a panelboard shall be minimum 2’‐0”. Exception:  if  there  is a minimum of 3’‐0” from the top of the panel to the ceiling, and if there is sufficient entrance 

Page 109: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐104 

Part 3 Project RequirementsJuly 18, 2013

 

 

space at  the  top panel surface  for conduit  for spare breakers,  then  the minimum spacing may be 6” between panels. 

D. Furnish and install personnel access and exit doors as per Code requirements in all electrical equipment rooms. 

E. All equipment shall be installed to permit easy access for operation and maintenance. 

F. There  shall  be  no  electrical  distribution  equipment  in  the  communications  rooms  not dedicated for communications equipment. 

13.5  Mounting of equipment 

A. Mounting arrangement (general): 

1. Unless  otherwise  noted,  mount  all  electrical  equipment  as  per  applicable  codes, manufacturer’s recommendations and the attached Specifications; 

2. Where panelboards are installed in stud walls, install horizontal metal studs for securing panelboard to wall. Anchoring panelboards to gypsum walls with mechanical anchors is not acceptable. 

3. No equipment shall interfere with operation of the facility, especially the movement of the buses and personnel; 

4. Maintain proper clearances around all equipment as required by code and maintenance considerations; 

5. Furnish  and  install  bollards  to  protect  exterior  panelboards,  transformers  and  other electrical distribution equipment exposed to vehicle travel; 

6. Provide dedicated space  for conduit runs at the ceiling,  including minimum 25% space (of  the width  of  the  rack)  for  installing  future  additional  conduit without  obstructing access  to  existing  conduit  or  other  equipment.  Ceiling  conduit  runs  shall  not  cast shadows; 

7. Furnish and install seismic restraints and vibration isolation as required per seismic zone and applicable Codes. 

B. Lighting Fixtures: 

1. Mounting  heights  of  fixtures  in  areas  with  finished  ceilings  shall  be  based  on  the Architectural drawings (installed above the required clearances shown on the drawings). 

2. Mounting  heights  of  fixtures  in  areas  without  finished  ceilings  shall  be  based  on Electrical drawings. 

3. Wall  mounted  fixtures  (interior  and  exterior)  shall  be  indicated  on  the  Electrical drawings for proper elevation and correctly displayed on all Architectural drawings. 

4. Lighting fixtures shall not be installed in classified areas unless they are suitable for use in Class 1, Division 1, Group D locations; 

Page 110: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐105 

Part 3 Project RequirementsJuly 18, 2013

 

 

5. Do not  install  lighting fixtures above anything that would block the  light from reaching the  work  plane.  Relocate  the  fixtures  if  required,  adding  fixtures  as  necessary  to maintain the required lighting levels; 

6. The  arrangement  of  lighting  fixtures  shall  be  coordinated  with  the  layout  of  the areas/rooms in which they are installed. Refer to Coordination Drawing requirements. 

C. Receptacles 

1. Install the computer receptacles at desk height.  

2. Install  all  counter  receptacles  8”  above  the  finished  counter  height,  coordinate with architectural millwork. 

3. Mount all receptacles 18” AFF, unless otherwise detailed on the plan drawings. 

4. All receptacles shall be NEMA 5‐15R unless noted otherwise, rated at 15A 120 volts. 

5. Ground  Fault  Circuit  Interupting  (GFCI)  receptacles  shall  be  located  on  the  Contract Drawings and elsewhere where required by Code. 

6. Dedicated  circuit  receptacles  are  shown  on  the  plan  for  specific  devices.  These receptacles shall have a dedicated 120 volt, 20 ampere single pole circuit dedicated to these locations.  

7. All  receptacles  shall  be  coordinated  with  the  Architect  for  color  of  faceplate  and receptacle. 

D. Lighting Switches:  

1. Install all  lighting switches  in the office area 48” above finished floor to the top of the operating handle. 

2. Where  there  is  a  single  door,  install  the  lighting  switches  near  the  door  strike  plate. Where there is a double door, install the lighting switches on the end of the right‐hand‐side of the door swing. 

3. All switches shall be  installed so that “ON”  is  in the position with the switch toggle up and “OFF” is in the position with the switch toggle down. 

4. Install switches  in separate single boxes  if the voltage between the exposed  live metal parts of adjacent switches exceeds 300 volts. 

E. Panel Boards ‐ Install panel boards on channels. 

F. Distribution Panel‐ Allocate floor space for Distribution Panels, minimum 25% or enough for one additional vertical section, whichever  is greater. Distribution Panels shall be mounted on a 4” concrete housekeeping pad with a 3” extension  from  the  front/sides/back of  the distribution panel enclosure. 

G. Transformers ‐ Install transformers on vibration isolators.  

H. Generator(s)  ‐  Install  the  generator(s)  on  vibration  isolators.  Also  refer  to  the  attached Specifications. 

Page 111: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐106 

Part 3 Project RequirementsJuly 18, 2013

 

 

I. Rubber mats ‐ Furnish and install rubber mats in front of electrical equipment in each room containing electrical distribution equipment. 

J. Disconnect Switches ‐ Install disconnect switches on channels.  

K. Owner‐furnished/ Design‐Builder‐installed equipment: 1. Kiosks:  DB  Contractor  shall  coordinate  with  Amtrak  and  provide  required  electrical 

connections in quantity and type at each kiosk location. 

2. Passenger Information Display System: DB Contractor shall coordinate with Amtrak and provide required electrical connections in quantity and type at each kiosk location. 

3. Vending Machines: DB Contractor  shall  coordinate with Amtrak  and provide  required electrical connections in quantity and type at each kiosk location. 

4. ATM:  DB  Contractor  shall  coordinate  with  Amtrak  and  provide  required  electrical connections in quantity and type at each kiosk location. 

5.  

13.6 Electrical Service: 

Furnish  and  install  a  3‐phase,  4‐wire  surge‐protected  electrical  service  into  the  Temporary Station, permanent Station and a temporary service for site construction power from the utility company  (Rochester Gas &  Electric).  The preferred  service  voltage  is 480/277V.  The Design‐Builder  shall  construct,  furnish,  and  install  all  required  equipment  as  per  Rochester  Gas  & Electric’s final service layout (ruling): 

A. If  the  service  layout  calls  for  transformer  vaults  and  network  protector  (NWP) compartments, the requirement could be: 

1. Transformer Vaults, either: 

• Below grade in the sidewalk and/or Amtrak property; or 

• Above grade inside Amtrak property (with direct access to the outside). 

2. Network Protector Compartments ‐ Above grade inside Amtrak property. Install the NWP  compartments  inside  the  Amtrak  building  per  Rochester  Gas  &  Electric requirements. 

3. If the service layout calls for pad‐mounted transformers, the requirement would be: 

• Pad Mounted Transformers  ‐  Installed above grade on  concrete pads  inside Amtrak  property.  Furnish  and  install  bollards  and  a  fence  to  protect  the equipment  on  the  pad.  There  shall  be  direct,  independent  access  to  the transformers from the sidewalk. 

• Or any other Rochester Gas & Electric requirement. 

In  any  of  the  above  cases,  furnish  and  install  property  line  boxes  (PLBs)  as  per Rochester  Gas  &  Electric  requirements,  and  cables  from  the  PLBs  to  the  NWP compartments.  The  final  location  of  the  transformers,  vaults  and  NWP 

Page 112: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐107 

Part 3 Project RequirementsJuly 18, 2013

 

 

compartments  shall  be  based  on  Rochester  Gas  &  Electric’s  final  service  layout (ruling).  The  Design‐Builder  shall  coordinate  the  design  and  construction  of  the network  protector  rooms  and  transformer  vaults  or  pads  with  Rochester  Gas  & Electric,  and  build  as  per  Rochester  Gas  &  Electric’s  requirements.  Crabs  for connecting Rochester Gas & Electric cables to AMTRAK cables shall be as approved by Rochester Gas & Electric. 

4. Tenant  Electrical  Service:  Provide  necessary  infrastructure  for  tenant  spaces. Coordinate requirements with Rochester Gas & Electric.  

5. Metering: Coordinate locations of electrical meters with Rochester Gas & Electric. 

6. Service Rating (Capacity) 

a. The service shall be based on the total connected load plus a 30% (of connected load)  spare  capacity.  The  spare  capacity  shall  be  included  in  the  sizing  of  the service/feeder breakers, distribution boards, subdistribution‐boards panelboards uninterruptible  power  supplies  and  other  electrical  equipment,  Furnish  and install  30%  spare  breakers  in  the  switchboard  distribution  boards, subdistribution boards and panelboards. 

b. The minimum  number  of  service  takeoffs  shall  be  determined  per  the  total connected load requirements plus a spare capacity of 30% of the total connected load.  Each  takeoff  shall  be  limited  to  a maximum  of  4000A  regardless  of  the Rochester Gas & Electric supply voltage.  If there are multiple takeoffs, then the takeoffs shall have equal Ampere  ratings. Each  takeoff shall  include 30% spare capacity. 

c. Rochester Gas & Electric approval for service equipment shall be obtained prior to  installation.    Coordination  with  Rochester  Gas  &  Electric,  furnishing  and installing all  required equipment as  specified, and  complete  installation as per Rochester  Gas  &  Electric  standards  shall  be  the  responsibility  of  the  Design‐Builder. 

d. The Design‐Builder shall prepare and submit a load request letter (via email) for electrical  service  to  the  Department  for  signature  and  transmission  to  the electrical  utility  (Rochester Gas &  Electric).  A  sample  letter  shall  be  furnished upon request. A  load breakdown  letter  listing the connected and demand  loads (winter  and  summer), must  be  furnished  to  Rochester Gas &  Electric  refer  to Exhibit “A” for a blank form 

e. Fuse  cut  outs  shall  be  furnished  and  installed  for  the  fire  alarm  systems  and other  stand  alone  panels  and  as  required  by  the  City  of  Rochester  Fire Department in coordination with Communications Engineering Division. The fire alarm control panel shall monitor the indication of ATS power failure. 

f. The service feeders shall be installed in ducts between the point of entry and the main switchboard or transformer vault(s), whichever  is applicable. All electrical service work shall comply with all of Rochester Gas & Electric’s regulations. The 

Page 113: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐108 

Part 3 Project RequirementsJuly 18, 2013

 

 

installation of  service equipment and  the number of network protector  rooms and transformer vaults shall be based on the approved  final service  layout and approved shop drawings. 

g. Rochester  Gas &  Electric’s  equipment  (transformers,  switchgear  and  network protectors)  shall  be  brought  to  and  installed  in  the  electrical  vault/network protector room (where applicable) by the Design‐Builder under Rochester Gas & Electric supervision.  

h. There  shall  be  no  breaks  in  the  service  lateral  or  metering  conduits  unless approval is obtained in writing from Rochester Gas & Electric.  Conduits and pull boxes are considered breaks in the conduit. 

i. Furnish and install cable limiters as per Rochester Gas & Electric’s requirements where three or more sets of service cables are used between the PLB and the CT cabinets. The cable limiters shall be installed on both ends of the service cables.  

13.6.2  Electrical Distribution Rooms, Electrical Panel Rooms and Electrical Closets 

A. All electrical distribution equipment shall be installed inside dedicated electrical equipment rooms, unless shown otherwise on the plans.  Provide 25% spare wall space in the electrical distribution and panel rooms for future use.   Provide electrical closets at various  locations for distribution boards and panelboards. 

B. Mechanical ventilation is required for all electrical equipment rooms. The preferred method of cooling/ventilating electrical equipment rooms  is with ventilation/exhaust fans. Refer to the Mechanical OPR  for  temperature  limits.  If such  temperature  limits cannot be reached via fans, submit an alternate scheme for approval. 

C. Provide equipment replacement clearances and removal routes in all electrical rooms. 

13.6.3 Main Distribution Switchboard 

A. The  main  disconnect  will  be  a  100%  rated  draw‐out  circuit  breaker  of  the  required overcurrent and short circuit interrupting ratings: 

1. Main circuit breakers shall not work in conjunction with current limiters at available short circuit current levels up to and including 200kA; 

2. For  available  short  circuit  current  levels more  than  200kA,  circuit  breakers  with integral current limiters shall be accepted; 

3. The main and switchboard distribution circuit breakers shall be electronic‐trip, with adjustments for long‐term, short‐term, instantaneous and ground fault conditions.  

4. Furnish and  install undervoltage  relays with voltage and  time  settings on all main circuit breakers to trip the breakers in the event of an undervoltage condition. 

Page 114: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐109 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. Circuit  breakers  shall  be  installed  for  over‐current  protection  of  all  switchboards, distribution boards, subdistribution boards and panelboards. Branch circuit protection shall be by breakers only. 

C. Switchboard shall have a minimum of 50% spare feeder poles. 

D. Coordinate all  tripping curves  (long  term, short  term,  instantaneous, and ground  fault)  to the  specific  facility  electrical  conditions.  Submit  a  detailed  coordination  study.  Where required  the DB Contractor  should  consider  the use of electronic  trip  circuit breakers  to assist in the coordination study. 

E. The switchboard busses shall be copper, and rated  for and braced to withstand minimum 200,000A  of  available  short  circuit  current  (Rochester  Gas  &  Electric  short  circuit  plus rotating  or  other  equipment  contribution),  or  more  if  determined  by  the  short  circuit current calculations required.  

F. Circuit monitors: Square D CM4000T series with remote monitoring capability (or approved equal)  shall  be  installed  on  the  switchboard/main  distribution  board.  A  IP  based communications interface shall enable a PC to communicate remotely with a circuit monitor through a dedicated IP address: furnish and install the necessary phone, ethernet and data outlets in the vicinity of the switchboard. The circuit monitors shall be installed on the line sides  of  the main  breakers  on  both  the  Rochester  Gas &  Electric  and  generator  power supplies. 

G. Building Management System (BMS) 

1. The BMS shall monitor all line‐to‐line and line‐to‐neutral voltages (on the line side of the main disconnect,  in order to monitor Rochester Gas & Electric power),  line and neutral currents, kilowatts and kilowatt‐hours used, voltage  frequency, and power factor at all switchboards. 

2. The BMS shall  record all of  the  required values with  timestamps, and shall output the  information  in a format suitable for  inclusion  in a report. The BMS shall record any  alarms  with  the  time  of  occurrence.  These  alarms  shall  consist  of  voltages greater or  less than 5% of the standard  incoming Rochester Gas & Electric voltage. The BMS shall also record currents that exceed the transformer rating. 

3. All monitored  variables  shall  be made  available  to  the  BMS  system  through  an industry standard communications protocol such as BACNET, MODBUS, or approved equal,  along with  any  required hardware  and/or  software  interface,  such  that  it is compatible with the BMS system being furnished and installed. 

4. Refer  to  Section 15,  Instrumentation  and Controls,  for more details  regarding  the BMS. 

13.6.4  Distribution System 

A. Power  Distribution  ‐The  power  in  the  Amtrak  Station  shall  be  distributed  preferably  at 480/277V.  In case power  is obtained at a different voltage  from Rochester Gas & Electric, 

Page 115: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐110 

Part 3 Project RequirementsJuly 18, 2013

 

 

the voltage shall be stepped up or down (as applicable) to 480/277V. Refer to Section 13.6 Utility Service for additional requirements. 

B. Furnish and install step‐down transformers of adequate capacity for all equipment requiring 208/120V power supply including but not limited to: 

1. Convenience receptacles; 

2. Communications equipment; 

3. Security equipment; 

4. Clock and Kronos system; 

5. Computer loads; 

6. Any other equipment needing 208/120V power supply; 

7. Fire detection system. 

C. Short Circuit Current Ratings of Equipment  ‐ The short circuit current  ratings of all power distribution  equipment  shall  be  based  on  a  short‐circuit  current  study  prepared  and furnished by the Design Professional. The available short circuit current at Rochester Gas & Electric  shall be obtained  in writing  from  the Electric Utility. However, all circuit breakers shall  have  the  following  minimum  short  circuit  current  interrupting  ratings,  RMS symmetrical: 

1. Distribution Boards (DBs): 65,000A;  

2. Subdistribution Boards: 42,000A;  

3. Panelboards: 22,000A  

Where  the  short  circuit  current  exceeds  the  above  minimum  values  based  on  the calculations,  the  circuit  breakers  shall  be  rated  at  the  next  higher  standard  interrupting rating above the calculated short circuit current value. 

D. Distribution panels and panelboards: 

1. In order  to minimize  the  sizes of  the  service  switchboards and  the number of  feeder runs,  furnish and  install distribution boards of adequate  capacity  (plus  spare)  in each Electrical Room to feed the local panelboards.  

2. All electrical panels  (henceforth defined panelboards)  shall be  furnished and  installed with main breakers, and copper phase, neutral and ground bus bars. Ground and neutral busses shall be one hundred percent (100%) rated.  No panels shall have more than 42 single pole breakers excluding the 3‐pole main breaker. Every panel’s feeder shall have appropriately sized neutral (minimum size equal to phase cable size; larger if required to handle nonlinear loads) and ground cables. 

3. Feeders for all panels shall be sized as per the main circuit breaker frame rating, not the trip rating (Example: a 400AF/300AT panel will have its feeder sized for 400A, not 300A). 

Page 116: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐111 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. Furnish and  install dedicated electrical panels  in  rooms/areas  that have  concentrated loads or special electrical requirements.  

5. Panelboards  for nonlinear  loads  (including computers) shall have 200% rated neutrals. Adjust the neutral busses in all required electrical equipment accordingly. 

6. Furnish and  install one UPS‐backed 100A, 3‐Phase, 4‐wires, 208/120VAC, 42 Breakers electrical  panel  inside  the  Communications  Room  to  feed  dedicated  20  Amp  circuit outlets (1 duplex and 1 quad for telephone equipment; 1 duplex and 1 quad for paging equipment;  1  quad  125VAC  and  1  single  250VAC  for  each  data  cabinet),  and  all dedicated circuit outlets required. 

7. Furnish and  install one UPS‐backed 100A, 3‐Phase, 4‐wires, 208/120VAC, 42 Breakers electrical panel inside the PIDS Server Room to feed dedicated 20 Amp circuit outlets (1 duplex  and  1  quad  for  telephone  equipment;  1  duplex  and  1  quad  for  paging equipment;  1  quad  125VAC  and  1  single  250VAC  for  each  data  cabinet),  and  all dedicated circuit outlets required in the Revenue Server room. 

8. All panels feeding computer loads shall be protected against voltage and current surges and  lightning  strikes as per  spec  IEEE/ANSI  standard C62.41 Category A and B  testing levels, and shall meet UL spec 1449. Maximum allowable surge levels shall be calculated and affixed to  the system.   The surge protector shall be  type SPB as manufactured by MCG Electronics or approved equal. 

E. Transformers: 

1. All transformers shall be delta‐wye. 

2. All  transformers  shall  be  sized  with  30%  spare  capacity  of  the  full  connected  load. Dedicated primary and secondary protection breakers  shall be  furnished and  installed for all  transformers. The main  circuit breaker of a panel or distribution board on  the secondary side of the transformer does not constitute secondary protection by Amtrak standards, and shall not be accepted. Also refer to the attached Specifications. 

3. The design shall compensate for harmonics currents created by nonlinear  loads by the reduction or elimination of the harmonics currents. Isolation transformers for nonlinear loads  shall  be UL  listed  1561  for K‐factor operation,  triple‐shielded  for high  common mode  noise  attenuation,  and  filtered  for  high‐frequency  noise  attenuation.  K‐rated isolation  transformers  shall  be  type  “Ultra‐K”  as manufactured  by  Controlled  Power Company or approved equal. 

4. Neutral wires and busses for computer and other nonlinear  loads shall be 200% rated, from the isolation transformer, to the disconnect switch, to the panel, and to the load. 

5. All transformer coil windings shall be copper. 

F. Disconnect switches: 

1. A dedicated horsepower‐rated, heavy‐duty,  industrial‐grade disconnecting means shall be  furnished and  installed  for all electrical equipment  including packaged units and all other  mechanical,  communications  and/or  architectural  equipment  covered  in  the 

Page 117: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐112 

Part 3 Project RequirementsJuly 18, 2013

 

 

complete Project Requirements,  regardless  if  the equipment  is  supplied by Amtrak or the Design‐Builder.  Furnish and  install power  for all of  the equipment  installed by all other  disciplines  as  required,  and/or  as  per  the  manufacturer’s  recommendations. Furnish and  install  local  isolating  switches  for all electrical equipment within 5’ of  the equipment with  an  enclosure  rated  for  the  area  in which  it  is  installed. Wherever  a manufacturer  has  not  furnished  a  disconnect means,  furnish  and  install  a  dedicated external horsepower‐rated disconnect sized as per the NEC. 

2. Furnish  and  install  Code  sized  disconnects  for  all  Owner‐furnished/Owner‐installed, Owner‐furnished/Design‐Builder‐installed and Design‐Builder‐ furnished/Design‐Builder‐installed power equipment. 

G. Raceway, Boxes and Fittings ‐ Unless otherwise noted, all cables and wires shall be installed in raceways.  

1. Raceways shall be of the following types: 

a. Hot‐dip galvanized rigid steel conduits (HDG RSC) with hot‐dip galvanized malleable iron (HDG) fittings and HDG cast iron boxes; 

b. Hot‐galvanized  steel  electrical metallic  tubing  (HG  EMT) with  raintight  galvanized steel compression fittings and galvanized stamped steel boxes. 

c. Underground fiberglass or PVC ducts in ductbanks. 

d. Zero‐halogen‐jacketed  galvanized  liquidtight  flexible  metallic  conduit,  galvanized liquidtight fittings and galvanized stamped steel boxes. 

e. Infloor ducts for built‐in type furniture only, where required by the furniture layout. 

2. Furnish and install HDG cast iron boxes for any transition between HDG RSC and any of the other raceway types. 

3. Any raceway passing  through any particular area on  its way  to  its destination shall be rated for use in that area (e.g., wet, classified, corrosive), and not only for the final area in which the load is located. 

4. All  PVC  conduits  routed  horizontally  underground  (or  under  slab)  shall  transition vertically  to  HDG  RSC with  a  large  radius  HDS  RSC  elbow  and  extend  6”  above  the finished  floor  slab.  The  metallic  portion  of  the  conduit  run  shall  be  painted  with corrosion resistant paint. Bonding bushings shall be  installed on each conduit and a #6 AWG bare copper boding conductor  shall be connected  to  the nearest grounding bus bar. 

5. Concrete‐encased  fiberglass or PVC ducts  shall be used  for  the  following applications. The  minimum  size  of  fiberglass  or  PVC  ducts  shall  be  4”  with  a  minimum  of  two fiberglass or PVC ducts (at least one spare) per run or as noted below. 

6. Incoming underground service  feeders. Furnish and  install a minimum of two spare 4” PVC ducts. 

Page 118: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐113 

Part 3 Project RequirementsJuly 18, 2013

 

 

a. From  the  PLB  to  the  transformer  vaults  where  there  are  transformer  vaults  and Network Protector Rooms. 

b. From  the  PLB  to  the  CT  Cabinet  where  there  are  no  transformer  vaults  and  no Network Protector Rooms. 

c. From the pad ‐mounted transformers to the PLBs, and then to the CT cabinets in the EDR, where there are pad‐mounted transformers. 

7. Classified locations: 

a. Dry areas: HDG RSC, explosion proof HDG cast iron boxes and couplings, HDG sealing fittings. 

b. Wet  areas  and  harsh/corrosive  atmosphere  locations:  HDG  RSC,  explosion  proof HDG cast iron boxes and couplings, HDG sealing fittings, all polyurethane coated. 

8. Nonclassified locations: 

a. Wet areas and harsh/corrosive atmosphere  locations: HDG RSC, HDG cast  iron boxes and HDG malleable iron fittings, all polyurethane coated. 

b. Under the concrete slab  ‐ Polyurethane‐coated HDG RSC and fittings, minimum size 1”, maximum 2”,  from  the  load  side of  the  local disconnect  switch  to  the shop equipment (e.g., brake lathes and other heavy machinery). Only if: 

1. The slab thickness is 12” minimum; and 

2. There is no vehicle travel in the area. 

a. The  locations  of  the  conduit  shall  be  clearly  indicated  in  the  vicinity  of installation. 

b. In hung  ceiling  areas, behind  the  sheetrock walls  for devices only:  galvanized, zero‐halogen‐jacketed flexible metallic conduit. 

c. Dry  industrial areas exposed  to vehicle  travel,  including  the maintenance area, up to 12’ AFF: HDG RSC, HDG cast iron boxes and HDG fittings. 

d. For emergency circuits consisting of: power, communications (including the fire alarm  equipment,  fuse  cut‐out  boxes  and  CCTV  equipment),  emergency lighting,(including  illuminated  exit  signs),  and  the  fire water  pump: HDG  RSC, HDG cast iron boxes and HDG fittings. 

e. Remaining nonclassified dry  locations: hot galvanized EMT and galvanized steel raintight compression fittings and galvanized stamped steel boxes. 

9. All steel raceways shall be electrically continuous and grounded. 

10. Furnish and install overhead exposed raceways on racks in maintenance and other areas throughout the Station. 

11. All conduits feeding lighting fixtures on the outside walls shall be concealed. 

Page 119: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐114 

Part 3 Project RequirementsJuly 18, 2013

 

 

12. There shall not be any underground or underfloor ducts within the Station except where noted. 

13. All raceways shall be as per the National Electrical Code  in approved sizes. Conduits of diameter ¾” and greater are to be used. Smaller diameter conduits are not allowed. 

14. Hangers from the ceiling steel or concrete for the conduit supporting trapezes shall be furnished  and  installed.  Use  hot‐dip  galvanized  steel  in  dry  and  noncorrosive atmosphere areas, and Type 304 stainless steel everywhere else. 

15. In  areas  without  hung  ceilings,  raceways  shall  be  installed  exposed  in  all  of  the rooms/areas on that floor. In areas with hung ceilings, raceways shall be installed above the  hung  ceilings  for  all  lighting,  receptacle  and  power  systems.  The  vertical  runs running under the hung ceiling shall be concealed within the walls. All device boxes shall be mounted flush in the walls. 

16. Waterproof  all  incoming  ducts.  Seal  all  ducts  containing  cables  with  watertight expandable plugs, OZ/Gedney type “CSBG” or approved equal. Seal all spare ducts with watertight caps. 

17. Raceway shall not run through any structural members. 

18. No  electrical  raceway  (conduit,  tubing,  or  trough)  shall  be  installed  inside  any  utility room, space, shaft  (elevator room, hoist way and shaft, gas meter room, pump room, machinery space/room, communications room, control room or space), computer room is  not  dedicated  for  the  electrical  equipment  in  that  room. Do  not  through‐feed  any other raceway in any such areas. 

19. Sealing fittings shall be installed at maximum 80 foot intervals for all conduit runs longer than 80 feet that pass through classified (hazardous) areas. 

20. Conduit  seals  and  drain  fittings  shall  be  installed  as  per  Code  in  conduit  runs  from classified areas to unclassified areas on all sides of the classified area. 

21. All electrical equipment, feeders (conduits) and wiring  installed  in classified areas shall be  suitable  for  Class  1,  Division  1, Group  ‘D’  locations.  Threaded,  rigid  steel  hot‐dip galvanized  conduits,  explosion‐proof  fittings,  couplings,  boxes,  hubs,  sealing  fittings, sealing  compounds and other associated  requirements per both  the Building Code of New York State and the NEC (NFPA 70 Articles 500 thru 505 and 511 thru 516) shall be used in these areas. 

22. Conduit  shall  not  block  or  interfere with  the  operation  of windows,  doors,  skylights, HVAC equipment, communications equipment and other electrical equipment. Do not install conduit directly below skylights or across windows or other openings.  

13.6.5 Wiring 

A. All cables and wires shall be installed in the applicable type of raceway. 

Page 120: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐115 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. Wiring for the following electrical systems shall be installed in their own dedicated raceway systems: emergency compact fluorescent lighting, explosion proof lighting, explosion proof receptacles,  communications,  fire  alarm  panel,  fire water  pump,  computers,  telephone, telecommunications, data, clock, paging, CCTV, and security systems. 

C. Cover all cable connections in the manholes and property line boxes with heavy‐duty, thick‐wall, waterproof, heat‐shrink splice insulation with integral silicone sealant. 

D. The minimum size wire shall be No. 12 AWG, rated at 15A maximum. No. 10 AWG wire shall be rated at 20A maximum. All larger wire/cable sizes shall be rated as per the NEC. All wires and  cables  shall be  rated at 75°C. The branch circuit wires  tapped off  the home  runs  for lighting fixtures shall be minimum No. 12 AWG, and those for receptacles shall be minimum No.  10 AWG. All wires  and  cables  (including  ground wires)  shall  be  sized  as  required  to account  for  the  load  and  the  voltage  drop,  and  shall  fit  the  terminals  of  the  device  or equipment  properly.  Cutting  strands  off  of  the  wire/cable  to  fit  the  terminals  is  not permitted.  In  the event  that  the  feeder  cables/wires do not  fit  the equipment  terminals, furnish and install a transition to cables/wires that will. 

E. All wiring size No. 10 AWG and smaller shall be solid. All wiring size No. 8 AWG and  larger shall be stranded. 

F. Install a pull cord in each empty conduit/tube.  The pull cord shall be rated for 200 pounds and be marked for every foot.  

G. Each  electrical  raceway  shall  contain  insulated  grounding  conductor(s).  Isolated  ground circuits  shall  contain  two  grounding  conductors:  one  for  the  system  ground,  and  one dedicated  isolated  equipment  ground.  The  system  ground  conductor  shall  have  green insulation, and the isolated equipment ground conductor shall have green insulation with a yellow stripe.  

13.6.6  Enclosures 

A. Switchboard enclosures shall be NEMA 1A gasketed. 

B. All  electrical  equipment  enclosures  (including  panel  and  distribution  boards,  disconnect switches,  enclosed  circuit  breakers)  for  dry  and  nonclassified  areas  shall  be  combination NEMA 12/3R, hot‐dip galvanized after fabrication.  

C. All equipment enclosures for wet and corrosive atmosphere locations shall be minimum 12 gauge NEMA 4X type 304 stainless steel. 

D. All equipment enclosures for dry classified (hazardous)  locations shall be NEMA 7, suitable for Class 1, Division 1, Group D locations. 

13.6.7  Grounding and Ground Fault Protection 

A. All  electrical  equipment  shall  be  grounded  as  per  the  NEC,  IEEE  standards,  and  Amtrak Specifications and Standard Drawings. 

Page 121: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐116 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. The  grounding  system  shall  consist of  the  following  systems bonded  together. Rochester Gas & Electric, the utility company, shall approve the grounding system.  

C. A building ground  loop consisting of a bare 4/0 ground cable with necessary ground  rods shall be designed to provide a ground resistance shall be less than 5 Ohms.  

D. The main grounding busses in electrical and communication rooms shall be made of copper and be a minimum of ¼” thick and 20” long. 

E. Bonding of the following structures shall be done in an approved manner: 

1. The water pipe on the street side of water meter; 

2. Steel pilings and the metal frame of the building bonded together with cable; 

3. Concrete encased grounding electrode system; 

4. Grounding rod. 

F. All below‐grade ground connections shall be done using the  ‘Cadweld’ process.   All above ground connections shall be with pressure type connectors.  All connectors shall be covered with epoxy paint or taped.  

G. All ground connections shall be as per AMTRAK Standards. 

H. Rochester Gas & Electric’s neutral  shall be  grounded  as per  code on  the  line  side of  the service equipment.   

I. Each  transformer  shall  have  its  secondary  neutral  grounded  for  a  separately  grounded system. (For transformers on the load side of the service). 

J. Exposed non‐current carrying metal parts and cord and plug connected electric equipment, as well as  some electric equipment  (track of electrically operated  cranes,  frames of non‐electric elevators, metal partitions, etc), that might accidentally become energized shall be grounded through an equipment grounding conductor. 

K. Computer room grounding shall be as per Amtrak, TIA/EIA and IEEE standards. 

L. Ground fault protection shall also be installed downstream breakers of the main disconnect to prevent a ground fault on any one feeder from interrupting power to all feeders. 

M. All panels, motors, starters, the metal hung ceiling system, and other permanently mounted electrical equipment shall be permanently and effectively grounded. 

N. Furnish and install bonding jumpers in all boxes and enclosures. 

O. After installation, the grounding system shall be tested. All related tests and measurements should be performed by the Design‐Builder in the presence of the Engineer. 

Page 122: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐117 

Part 3 Project RequirementsJuly 18, 2013

 

 

13.6.8  Heat Tracing  

A. The  temporary  station  trailers  shall have  all exposed plumbing piping  subject  to  freezing heat traced with a minimum of 8 watts per linear foot along all exposed piping.  

B. The DB Contractor shall perform calculations to ensure the necessary amount of circuits are provided. The design shall be coordinated directly with the plumbing contractor. 

 C. The DB Contractor shall provide a heat trace control panel, heat trace wiring and necessary 

appurtenances in order to make a complete operational system.  

13.7  Generator  

A. Furnish and install a generator in an exterior location along an exterior wall. The generator shall use fuel oil and shall have independent fuel supply and exhaust systems as well as its own HVAC systems for the room and for the engines. The engine shall be radiator cooled. The  installations  shall  meet  all  the  Code  requirements  and  manufacturer’s  installation recommendations; 

B. The  generator  shall meet  all  EPA  Tier  emission  requirements  for  the  rated  size  of  the electrical output of the engine generator as classified in the state environmental regulations for air pollution. 

C. The whole system (the engine, generator and all other major auxiliary equipment) shall be built, tested and shipped by the same manufacturer; 

D. Furnish and install a day tank with rupture basin.  

E. The  system  shall  include  all  necessary  accessories  including  a  silencer,  overcurrent protection,  exhaust  system,  over‐voltage  protection,  detailed  instrumentation  panel (voltage,  ampere,  kW  and  run  time  electronic  recording  meters),  battery  and  battery chargers, local and remote annunciator, keep‐warm system, and fuel pumps; 

F. The  remote  annunciator  shall  be  installed  within  the  station.  The  DB  Contractor  shall coordinate with Amtrak for the proper location. 

G. The  generator  shall  have  the  ability  of  being  exercised  (manual/automatic)  on  a  regular basis. 

H. All  accessories  for  the  generator  that  require  power  (fuel  pumps,  heaters,  and  other equipment) shall be fed from the generator; 

I. The  parameters  of  the  complete  integrated  engine‐generator  system  (consisting  of  the engine‐generator set(s), automatic transfer switch(es), switchboards, uninterruptible power supplies,  and  all  appurtenances  (fuel  pumps,  heaters,  damper  motors,  et  al))  shall  be monitored by the BMS. The monitored parameters shall include, but not be limited to: 

1. System and appurtenances electrical and mechanical parameters; 

Page 123: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐118 

Part 3 Project RequirementsJuly 18, 2013

 

 

2. System  and  appurtenances  fluids  (fuel,  oil,  coolant,  antifreeze,  et  al)  parameters (pressures, levels, temperatures, et al); 

3. Operational  records  (event  history,  run  times  and  durations,  system  warnings  and shutdowns, et al); 

4. Time delays; 

5. System and appurtenances parameters (including serial and model numbers); 

6. System and appurtenances diagnostics; 

7. System and appurtenances warnings; 

8. NFPA 110 Alarms; 

9. Digital inputs; 

10. Switchgear inputs; 

11. Digital outputs; 

12. User‐defined faults and status indicators (refer to the I&C and Communications OPRs) 

13. Any other system parameters as per the manufacturer’s recommendations. 

J. A power failure shall start the generator automatically. 

K. The generator shall be sized based on 100% of the total sum of items 1) through 7) below, plus 20%  spare of  this  sum.  If  the calculated value  is not a  standard  frame  size,  the next higher standard generator frame size shall be furnished and installed: 

1. 100% of whichever  is  greater:  the heating  system plus  the  ventilation  system, or  the cooling system plus the ventilation system. Include all appurtenances for each system in the determination. 

2. 100% of the nameplate rating of the fire water pump and associated equipment. 

3. 100% of the rated connected fluorescent lighting load 

4. 120% of the rated connected HID and LED lighting load. 

5. 140% of the nameplate ratings of all UPSs. 

6. All general convenience duplex receptacles as per the NEC. 

7. 4W/ft2 for all remaining loads. 

L. The  nameplate  (input)  power  ratings,  not  BHPs,  of  all  load  motors  shall  be  used  in determining the rating of the generator.  

13.7.2  Automatic Transfer Switches (ATS) 

A. The generator shall be connected to the distribution system via an automatic transfer and bypass  isolation switch, ASCO 7000 Series with Group 5 control panel (or approved equal) 

Page 124: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐119 

Part 3 Project RequirementsJuly 18, 2013

 

 

and all required accessories. The Design Professional shall determine the actual number of bypass‐isolation ATSs required; 

B. The power supply to the Fire Alarm Panel shall be made as per the requirements of the City of Rochester Fire Department.  A fuse‐cutout box shall be installed after the ATS, which will be  installed  between Rochester Gas &  Electric  power  and  the  generator.    Power will  be tapped from the line side of the main breaker.  An additional 30‐amp spare fuse‐cutout box shall be  installed  for  future use.   The entire  installation  shall be approved by  the City of Rochester  Fire  Department  and written  approval  shall  be  submitted  to  the  Department Additional auxiliary contacts shall be furnished and  installed  in the ATS for monitoring the switch position and/or power failure as required by Section 14 Communications. 

C. All  Automatic  Transfer  Switches  shall  be  equipped  with  accessories  to  detect  fault conditions (short‐circuit, ground‐fault, and/or other faults) downstream, and shall prevent the transfer from Rochester Gas & Electric to the Generator in that situation. 

D. The ATS enclosure  shall be  furnished and  installed with an  integral generator‐side  circuit breaker of the required AIC with ground‐fault protection relay. 

E. The Automatic Transfer Switch(es) shall be installed in the Emergency Power Supply System (Generator) Room.  

13.7.3  Power to the following shall be fed through UPSs 

A. BMS; 

B. Generator control panel; 

C. Equipment included in section 6.10; 

D. Egress lighting; 

E. All circuits required for telecommunications equipment. 

13.8 Lighting 

The Design Builder (DB) must adhere to the following criteria encompassing the work required to  design,  furnish,  and  install  complete  and  operational  lighting  systems  for  the  Rochester Intermodal Transportation Center  (RITC) Project. The DB  shall  conduct  all work necessary  to provide  all  lighting  related  systems  located  inside  the  project  limits.  This  includes  all work related  to  the  exterior  site  areas  (parking  lots,  roadways,  intersections,  crosswalks, walkways/sidewalks, bus drop offs, security, building façade, train platform, plaza, etc.) and the entire  interior  of  the  train  facility.  The  DB  shall  also  provide  all  lighting  associated  with temporary  works  for  usage  of  the  train  facility  and  its  amenities  throughout  the  entire construction of the new facility.  

A. General Requirements  a. Features included under this requirement include new Light Emitting Diode (LED) 

interior and exterior luminaires, poles, mounting equipment, procurement, containment, installation, programming, focusing, commissioning, and any record 

Page 125: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐120 

Part 3 Project RequirementsJuly 18, 2013

 

 

information necessary for delivering a complete and functional system. The DB shall coordinate all aspects of the lighting (functional and accent) for all project requirements and for all applicable governing standards.   

b. The DB shall employ a professional lighting designer with a minimum of 2 (TWO) successful train facility lighting project experiences and a minimum of 10 (TEN) years of experience in interior and exterior lighting design. Said individual or firm shall also employ a lighting designer / lighting engineer who is lighting certified (LC) and who is a current member of the Illuminating Engineering Society (IES), with a minimum of 5 (FIVE) years of site and interior lighting design experience. These skills are to be used together to provide a unified visual concept combining the aesthetics and technical requirements of the project, along with electrical and structural engineering.   

c. The DB shall coordinate with Amtrak and NYSDOT and their affected agencies to ensure the appropriate design methods, procedures, submittals, plan preparation, analysis, review and comment processes, approval procedures, specifications, and construction requirements are met.  

d. The DB shall prepare the necessary aesthetics, designs, and engineering studies, as well as applicable design reports to describe and justify all lighting components to be incorporated into the Project 

 e. Lighting shall be designed to satisfy security requirements and to provide a pleasant 

and bright environment. Lighting shall be provided such that all areas throughout the facility are illuminated. The lighting shall be designed to be functional, yet complementary to those other aesthetic features in the space that provide an atmosphere of relative comfort, pleasantness and cleanliness of surroundings, and a sense of personal safety and security. Style of fixtures shall complement the overall architectural design of the station and platform. The DB lighting designer shall coordinate all aesthetic designs with the Architect.  

f. The lighting system shall be designed to be relatively simple and minimize initial capital cost, as well as frequency and expense of maintenance.   

g. Lighting shall permit safe use of the facility on a 24 hour per day, 365 day per year basis.   

h. Adequate lighting levels, uniformity ratios, contrast, and other visibility attributes necessary to stimulate productivity, facilitate the use of facilities by patrons or the completion of tasks in a timely yet safe manner, and maintain the appropriate surveillance levels under all ambient lighting conditions shall be provided. Tables E‐1, E‐2, and E‐3 of this document categorize by Room/Area/Locations for required 

Page 126: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐121 

Part 3 Project RequirementsJuly 18, 2013

 

 

lighting levels. Lighting shall meet or exceed recommendations in this guide in accordance with all applicable IESNA Recommended Practices.  

i. The lighting system shall be energy efficient and comply with the Energy Conservation Construction Code of New York State, all IESNA Recommended Practices, ASHRAE and ANSI standards.    

j. Lighting fixture locations shall permit easy accessibility for repair, maintenance, and periodic cleaning  

k. Any required illumination shall be arranged and wired so that the failure of any single lighting unit or circuit shall not leave the area in total darkness.  

l. Lighting shall be designed to avoid “spill” light, objectionable glare, and light trespass in accordance with IESNA Recommended Practices.  

m. Lighting designs shall effectively control glare or other extraneous reflections in the visual field.  

n. Lighting fixtures shall be vandal resistant in spaces where the fixtures are easily accessible to patrons or the general public.  

o. The DB shall provide lighting materials that: i. Are new at the time of installation ii. Meet all visual and aesthetic goals of the project iii. Are long life and energy efficient iv. Are compatible with the electrical characteristics (voltage, phases, wires) of 

the power supply available.  v. Are easily maintained by the in‐house personnel using current equipment. 

 p. At a minimum, the drawings and specifications shall cover the following lighting 

aspects: i. Interior Lighting Location plans ii. Exterior Lighting Location plans iii. Luminaire location callouts iv. Interior luminaire Mounting Details v. Exterior Luminaire Mounting Details vi. Luminaire Specifications and Technical Data vii. Pole Specifications and Technical Data 

 B. Codes and Standards 

 The following codes and standards shall be used in addition to the electrical codes and standards listed in section 13.1 of this document. 

Page 127: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐122 

Part 3 Project RequirementsJuly 18, 2013

 

 

a. New York State Building Code 2010 

b. Energy Conservation Construction Code of New York State 

c. Amtrak Station Program and Planning – Standards and Guidelines, Version 2.2 

d. Amtrak Engineering Stations Standard Design Practices (SDP)  

e. Amtrak Police Department Corporate Security Guidance, Practices and Recommendations 2011 

f. Illuminating Engineering Society of North America (IESNA) Publications: 

i. HB‐10  IESNA The Lighting Handbook 

ii. RP‐1  Practice for Office Lighting 

iii. RP‐8  Practice for Roadway Lighting 

iv. RP‐16  Nomenclature and Definitions 

v. RP‐20  Lighting for Parking Facilities 

vi. RP‐33  Lighting for Exterior Environments 

vii. DG‐5  Lighting for Walkways and Class 1 Bikeways 

viii. LM‐79  Photometric Measurements of Solid State Lighting Products 

ix. LM‐80  Measuring Lumen Maintenance of LED Sources 

x. TM‐10  Obtrusive Light 

xi. TM‐11  Light Trespass 

xii. TM‐15  Lighting Classification System, with Addendum A (BUG Ratings) 

xiii. G‐1   Guideline on Security Lighting for Public Spaces 

g. Underwriters Laboratories Inc. (UL) Publications 

i. 1598  Standard for Luminaires 

ii. 773  Plug‐in Locking Type Photocontrols for use with Area Lighting 

h. American  Society  of  Heating,  Refrigerating  and  Air‐Conditioning  Engineers,  Inc. (ASHRAE) 

i. Energy  Standard  for  Buildings;  Standard  90.1‐2010  with  all  applicable addenda 

i. ASTM International (ASTM) 

i. A123/A123M  Specification  for  Zinc  (Hot‐Dip  Galvanized)  Coatings  on  Iron and Steel Products 

ii. A167  Specification  for  Stainless  and  Heat‐Resisting  Chromium‐  Nickel Steel Plate, Sheet, and Strip 

Page 128: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐123 

Part 3 Project RequirementsJuly 18, 2013

 

 

iii. A3661/A366M   Specification  for  Steel  Sheet,  Carbon,  Cold‐Rolled,  Commercial Quality 

C. Quality of Illumination 

1. Lighting designs shall be free from distracting and uncomfortable glare; care shall be exercised  to  prevent  specular  reflection  on  signage,  direct  glare  from  exposed lamps, high brightness areas of individual fixtures and reflections in glazing or other specular surfaces. 

2. Lighting design shall promote safety, security and well being. 

3. The lighting source shall utilize energy efficient, long life, and low maintenance Light Emitting  Diode  (LED)  lighting  technologies.  The  LED’s  shall  be  of  the  latest technology  and  of  the  highest  quality.  The  LED  luminaires  shall  be  of  a  constant lumen output and color temperature. 

4. In order  to  address  the most up  to date  lighting  technologies,  the DB Entity  shall present to Amtrak the proposed  lighting scheme utilizing LED  luminaires. This shall include: 

a. Interior  luminaires with  a minimum  of  50,000  hours  of maintenance  free operation attaining 70% of the initial lumen output (L70). 

b. Exterior  luminaires with  a minimum  of  70,000  hours  of maintenance  free operation attaining 70% of the initial lumen output (L70) 

c. Documentation  illustrating  the  LED  luminaires  have  been  tested  in accordance with IES‐LM‐79 and IES‐LM‐80 

d. LED lifespan data analysis, specific to the led junction temperature during the lifespan test period 

5. Uniformity  ratios  shall  not  exceed  the  recommended  levels  as  directed  by  this document and IESNA. 

6. Interior  correlated  color  temperature  (CCT)  of  the  light  sources  shall  be  between 3000 and 3500 Kelvin (K) with a color rendering index (CRI) minimum of 80. 

7. Exterior  correlated  color  temperature  (CCT) of  the  light  sources  shall be between 4000 and 4500 Kelvin (K) with a color rendering index (CRI) minimum of 70. 

8. Lamps of the same type within each area of  illumination shall have the same color temperature.  In areas where different types of light fixtures are required, the color temperature  of  each  type  shall  be  matched  as  close  as  practicable  to  ensure uniformity of color. 

9. Special  care  shall  be  taken  to  avoid  objectionable  glare  to  streets,  tracks  and adjacent properties.   Light fixtures shall be positioned to minimize spill  light.   Light fixtures shall be provided with optics to prevent spill light and glare in the direction of adjacent properties.   Furnish and  install  lighting fixtures specifically designed for rooms with video display terminals (VDTs) to reduce glare on the VDT screens. 

Page 129: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐124 

Part 3 Project RequirementsJuly 18, 2013

 

 

10. All exterior  luminaires  shall have U0 BUG  rating optics  to minimize night  sky  light pollution and be “Dark Sky” compliant.  

11. All  security  lighting  shall meet  the  requirements of  the Amtrak Police Department Corporate Security Guidance, Practices and Recommendations 2011. 

D. Quality of Materials 

a. The  luminaires  for the project shall be constructed of the highest quality materials and designed to provide a minimum of 20 years of operation.   

b. Manufacturers of lighting fixtures, poles, and accessories shall have a minimum of 10 years of reputable performance in the industry.  

c. All luminaires shall be designed to allow heat dissipation through the fixtures housing and away from the LED’s, effectively keeping the LED light engines below the LED manufacturer’s recommended maximum operation temperature for extended life and minimal LED failures.  

d. All  exterior  luminaires,  along  with  those  interior  luminaires  that  require  an occasional wash  down  or will  be  accessible  to water,  shall  be UL  Listed  for Wet Locations and for Direct Spray.   

e. No interior luminaires shall be constructed using a fiberglass or polymer housing.  All luminaires  shall be cast, extruded, or  rigidly  formed aluminum with  stainless  steel hardware. 

f. All poles  shall be galvanized  round  tapered  steel constructed; base plate welds  to the  bottom  of  the  pole  shall  be  continuous  around  both  the  outside  and  inside diameters.    All  the  poles  shall  include  a  grounding  lug  positioned  in  the  pole opposite  the  reinforced hand hole.   Additionally,  all poles  greater  than 30  feet  in height shall incorporate an internal vibration dampener to minimize vibration during steady winds or structural vibrations.  All pole hardware shall be stainless steel. 

g. All  exterior  pole mounted  luminaires  shall withstand  a minimum  3G  vibration,  as defined in ANSI 136.31. 

h. All  steel  poles,  bases,  arms,  and miscellaneous mounting  brackets  shall  be  hot‐dipped galvanized in accordance with ASTM A123 / A123M ‐ 12 standards. All steel shall  be  completely  hot‐dipped  galvanized  after  fabrication.    Any  holes  that  are required  for  mounting  of  accessories  on  the  pole  must  be  made  during  the manufacturing process and before any galvanizing or surface finishing is performed. 

i. All  lighting  poles  on  the  project  shall  be  designed  to meet AASHTO  LTS with  the maximum weight and EPA of  the  luminaires, arms,  ITS equipment, cameras, other luminaires, signs, or any other accessories deemed necessary to be mounted to the 

Page 130: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐125 

Part 3 Project RequirementsJuly 18, 2013

 

 

poles included in the calculations. Pole shop drawings must be signed and sealed by a Professional Engineer. 

j. All  materials  must  be  corrosion‐resistant  aluminum,  unless  otherwise  indicated.  Each component shall be formed or supported to prevent warping and sagging. 

k. Enclosures shall be rigidly formed or cast, weather tight (if exterior grade) that will not warp, sag, or deform in use. 

l. Enclosures  shall  be  smooth  operating  and  free  of  light  leakage  under  operating conditions.   

m. Exterior  site  area  and  roadway  luminaires  shall  be  designed  to  prevent  doors, frames,  lens,  and  other  components  from  falling  accidentally  during maintenance and when  secured  in operating position. These  luminaires  shall also have a driver that can be accessed easily without the use of tools. 

n. All exterior grade fixture hardware shall be stainless steel. 

o. All exterior  luminaires  shall be UL  listed  for wet  locations and a minimum of  IP65 rated.  

p. All  finish colors  for poles, arms, brackets, and  luminaires shall be coordinated with the Architect. 

q. Luminaire  Manufacturer  submittals  shall  include  at  a  minimum  the  following information: 

i. Product  Data;  description,  materials,  dimensions,  weights,  effective projected area (EPA) 

ii. Electrical data; LED drivers, Printed Circuit Boards, LED Chips, LED Modules, wiring diagrams 

iii. Catalogue cuts and manufacturer drawings iv. Operation and Maintenance Data v. UL Documentation vi. Independently tested photometric data vii. Computerized printout of calculations viii. Written Warranties ix. Product Samples, as deemed necessary by the engineer 

 r. Pole Manufacturer submittals shall include at a minimum the following information: 

 i. Product  Data;  description,  materials,  dimensions,  weights,  effective 

projected area (EPA) ii. Catalogue cuts and manufacturer drawings 

Page 131: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐126 

Part 3 Project RequirementsJuly 18, 2013

 

 

iii. Written Warranties iv. Product Samples, as deemed necessary by the engineer v. Signed and Stamped Product Certificates vi. Design calculations certified by a Professional Engineer (PE) 

 E. Lighting Calculations 

a. DB Contractor shall design and calculate all  lighting  levels within the entire project limits.  IES  standards  shall  be  used  on  the method  to  calculate  illumination  levels unless otherwise noted elsewhere in this document. 

b. The  DB  shall  obtain  Amtrak’s  consent  on  the  use  of  software  programs  and techniques. The use of proven and commonly available software familiar to Amtrak is encouraged. For lighting calculations the DB is required to utilize Lighting Analysts AGI32 or Radiance lighting analysis and simulation software for full detailed reports to demonstrate compliance with reference standards utilizing IES format files, along with  reflectances.  Compliance  calculations  and  checks  are  required.  The DB  shall detail each geometric design condition for exterior and  interior  lighting, along with clearly outlining the design criteria used. These different analysis components shall demonstrate  compliance  with  relevant  standards  or  references.  These  shall  be demonstrated  through graphical output, which also  includes numerical  summaries for the analysis grid areas.  

c. For  both  interior  and  exterior  calculations  the  light  loss  factors  (LLFs)  shall  be calculated based on the environmental conditions of the respective area and on the specific  characteristics of  each  component of  the  lighting  system  (lamps, ballasts, lighting  fixtures)  including  voltage  drop,  luminaire  reflectance  and  transmittance changes,  lamp outages,  lamp  lumen depreciation,  luminaire dirt depreciation, and lamp  mortality  rates.  The  maintenance  and  parking  areas  of  the  facility  are especially  dirty  due  to  exhaust  fumes,  grease  and  other  pollutants.  Therefore,  all LLFs  must  be  carefully  determined  in  order  to  achieve  the  minimum  required maintained footcandle levels. 

d. Submit a detailed  list of all LLFs and provide  justification  for  the determination of each variable.  

e. The required maintained illumination levels are listed in Table E‐1, E‐2, and E‐3. The illumination  levels  shall  be measured  in  accordance  to  all  applicable  IESNA  and project standards and guidelines. 

F. Temporary Lighting 

a. Lighting  requirements  for both exterior and  interior  rooms and areas are  listed  in Table E‐3 located in this section. 

b. Provide for sufficient quality  illumination for orderly and predictable movement for all the operations of facility. 

Page 132: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐127 

Part 3 Project RequirementsJuly 18, 2013

 

 

c. The  DB  shall  develop  temporary  lighting  plans  that  include  interior  and  exterior lighting,  meeting  or  exceeding  all  applicable  codes  and  standards  listed  in  this section. 

d. Fluorescent  luminaires  shall  be  limited  to  2  foot  and  4  foot  linear  T‐8  or  T‐5 fluorescent  lamp  light  sources  with  a  3500K  CCT  and  program  start  electronic ballasts, and Compact Fluorescents (CFL) with a 3500K CCT. 

e. Exterior  luminaire  shall  be  of  a  High  Pressure  Sodium  (HPS), Metal  Halide  (MH), Amalgam (Cold Weather) Compact Fluorescent light sources. 

f. Exterior  wall  packs  should  be  utilized  for  ramps  and  stairs  located  near  the temporary structure.  

g. No incandescent lamps should be used. 

G. Interior Lighting a. The illumination levels for various areas shall be provided as shown in Table E‐1.  The 

HB‐10 reference shall be used for areas that may not be included in the table. 

b. The  interior  lighting  shall  comprise  a  variety  of  LED  luminaires,  including  but  not limited to: Wall Washers, Linear, 4‐6 inch Round Recessed, 2x2 recessed troffers, 2x4 recessed troffers, soffit/cove. 

c. Interior lighting design should incorporate indirect lighting where appropriate. 

d. Interior  lighting  design  should  incorporate  lighting  of  walls  and  other  vertical surfaces where appropriate. 

e. Special  fixtures  like pendants, under cabinet and  focused spots should be used  for specific task related activities.  

f. Direct view of  the  fixtures  light  source  should be avoided whenever possible. This can be accomplished by the fixture design, lensing, and cove/soffit lighting.  

H. Exterior Lighting a. Provide  a  uniform  nighttime  illumination  on  the  circulation  roadways  to  enable 

motorists  to  quickly,  distinctly  and  comfortably  view  the  roadway  alignment, vehicles,  obstacles,  or  obstructions  at  extended  distances  ahead,  even  during inclement weather.   

b. Lighting Poles  for parking and roadway  lighting shall be  located  inside of curbs, on traffic islands and walks, and along parking lot perimeter.  Placement shall present a minimum obstruction  to movement and parking of  cars.   Poles  shall be protected from physical damage by the concrete pole foundation base which extends not less than 2’‐6” above grade and not more than 3’‐0”. 

c. Lighting poles  for any pedestrian  scale  luminaires  shall be mounted with  the base and cover sitting directly on a finished surface or if placed in a grassy area, with a 4” to 6” exposed foundation base.  

Page 133: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐128 

Part 3 Project RequirementsJuly 18, 2013

 

 

d. Light  Pole  positioning  shall  be  required  to  meet  lighting  uniformity  ratios,  be coordinated with  the proposed  landscaping  scheme and prevent off‐property  spill light. 

e. Exterior Stairway and Ramp  luminaires are dependent on the  location.   Either pole mounted or wall mounted luminaires shall be used, whichever is more appropriate.  

f. Landscape  lighting  shall  be  complimentary  and  not  overpower  the  architectural features  of  the  train  facility.  Applicable  references  are HB‐10  and  RP‐33. Modest lighting  on  tree  canopies  and  shrubs  shall  be  coordinated  with  the  landscape architect.  The  LED  lighting  fixtures  shall  be  selected  from  reputable  landscape lighting manufacturers, only lighting fixtures intended for landscape lighting shall be used for landscape lighting. Special care shall be given as to not cause unintentional glare to drivers and pedestrians. 

g. Public art  installation  lighting shall be coordinated with  the artist and authority  to ensure a pleasing illuminated sculpture. Applicable references are HB‐10 and RP‐33. Special  care  shall  be  given  as  to  not  cause  unintentional  glare  to  drivers  and pedestrians.  

I. Emergency Lighting and Exit Signs 

1. Emergency lighting design shall conform to the NEC, CEC, NFPA 101, NFPA 130, IESNA Lighting Handbook, and the New York State Building Code. 

2. Exit  lighting  fixtures  and  signs  shall  be  provided  to  illuminate  and  mark  the designated egress passageways, stairways, and the entrances and exits to stairways.  Exit sign fixtures shall be wall or bracket mounted at a mounting height visible to all occupants  within  the  occupied  spaces.    Exit  lighting  fixtures  and  signs  shall  be separately wired from other electrical loads (to the emergency panelboard) and shall be connected to the UPS system. 

3. Emergency  lighting  for  stairways  and  escalators  shall  be  designed  to  emphasize illumination on the top and bottom steps or  landings.   All escalator steps newel and comb lighting shall be on emergency feeder circuits in accordance with NFPA 130.   

4. Emergency lighting fixtures and exit lights and signs in underground occupancies shall be located so as to minimize the possibility of being obscured by stratified smoke in a fire. 

5. Emergency  lighting  and  exit  signs  shall  be  incorporated  on  the  train  platform, illuminating and marking safe passage to the emergency exit ways. 

6. Exit signs shall be internally illuminated with a LED light source. 

J. Lighting Control System   

1. Control  artificial  lighting  automatically  where  practical  by  selecting  from  among various  lighting  control  devices.    The most  useful  controls  for  increasing  lighting energy‐efficiency  are  timers,  dimmers,  photocells,  day‐light  harvesters,  and 

Page 134: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐129 

Part 3 Project RequirementsJuly 18, 2013

 

 

occupancy  sensors.  Select  control  strategies  based  upon  the  following  types  of lighting situations. 

2. Office lighting should be controls by wall switch occupancy sesors. 

3. Exterior  area  and  road  lighting  shall  utilize  a  photocontrol  and  time  clock  switch system  that  automatically  activates  the  luminaire  before  dusk  and  deactivates  the luminaire past dawn. 

4. Continuous  Lighting  is  designed  to  continuously  illuminate  an  area  during  a combination of hours of darkness and hours of operation.   Examples of continuous lighting could be  found at station stops, platforms, vehicle approaches, and parking lots.  Suitable controls for continuous lighting are timers and photocells. 

5. Standby Lighting  is similar  in design  to continuous  lighting, except not continuously operated.     Standby  lighting  is  turned on automatically when activity  is detected  in the area or manually as necessary to occupy a space.  Standby lighting is suitable only for “instant on” lamps.  Examples of standby lighting could be found in utility closets, offices, or restrooms.  Suitable controls for standby lighting include discrete “on/off” switches, occupancy sensors, and dimmers. 

 

TABLE E-1 INTERIOR ILLUMINATION LEVELS TABLE 

Room #/Area 

Room Name 

Average Maintained Horz. (FC) 

Horz. Location (FEET AFF) 

Average to Minimum Ratio 

(AVG:MIN) 

Average Maintained Vert. (FC) 

Vert. Location (FEET AFF) 

Phase 

1A  Waiting  15  2.5  3:1  5  2.5  PH I 

1B  Waiting  15  2.5  3:1  5  2.5  PH I 

1C  Waiting  15  2.5  3:1  5  2.5  PH II 

2  Queue  15  2.5  3:1  5  2.5  PH I 

3  Ticketing  30  3.0  3:1  10  5.0  PH I 

4  Vestibule  15  0.0  2:1  7.5  5.0  PH I 

5 Baggage Work Rm 

30  3.0  3:1  15  5.0  PH I 

6 Baggage Claim 

20  3.0  3:1  10  5.0  PH I 

7 Baggage 

Equipment 30  0.0  3:1  10  4.0  PH I 

8  Retail  40  2.5  3:1  15  2.5  PH I 

Page 135: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐130 

Part 3 Project RequirementsJuly 18, 2013

 

 

9  Retail  40  2.5  3:1  15  3  PH I 

10  Staff  15  4.0  3:1  5  4.0  PH I 

11  Bathroom  15  3.5  2:1  5  3.5  PH I 

12  Bathroom  15  3.5  2:1  5  3.5  PH I 

13  Office  30  2.5  1.5:1  15  3.5  PH I 

14  Corridor  10  0.0  3:1  3  4.0  PH I 

15     NOT USED 

16  Bathroom  15  3.5  2:1  5  3.5  PH I 

17  Bathroom  15  3.5  2:1  5  3.5  PH I 

18  Bathroom  15  3.5  2:1  5  3.5  PH I 

19     NOT USED 

20 Outdoor Storage 

SEE TABLE E‐2 

21 Outdoor Storage 

SEE TABLE E‐2 

22     NOT USED 

23     NOT USED 

24     NOT USED 

25     NOT USED 

26     NOT USED 

27  Corridor  10  0.0  3:1  3  4.0  PH I 

28 MRL Closet 

Ctrl 30  0.0  3:1  30  5.0  PH I 

29  Storage  10  0.0  2:1  3  4.0  PH I 

30  Storage  10  0.0  2:1  3  4.0  PH I 

31  PIDS Server  30  0.0  3:1  30  5.0  PH I 

32 Revenue Server 

30  0.0  3:1  30  5.0  PH I 

33  Comm.  30  0.0  3:1  30  5.0  PH I 

34  Electrical  30  0.0  3:1  30  5.0  PH I 

35     NOT USED 

Page 136: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐131 

Part 3 Project RequirementsJuly 18, 2013

 

 

36  Mechanical  30  0.0  3:1  30  5.0  PH I 

37     NOT USED 

38  Office  30  2.5  1.5:1  15  3.5  PH II 

39  Office  30  2.5  1.5:1  15  3.5  PH II 

40  Office  30  2.5  1.5:1  15  3.5  PH II 

41  Office  30  2.5  1.5:1  15  3.5  PH II 

42  Staff  15  4.0  3:1  5  4.0  PH II 

43  Bathroom  15  3.5  2:1  5  3.5  PH II 

44  Dispatch  30  2.5  1.5:1  15  3.5  PH II 

45  Ticketing  30  3.0  3:1  10  5.0  PH II 

46  Baggage  20  3.0  3:1  10  5.0  PH II 

47  Corridor  10  0.0  3:1  3  4.0  PH II 

  Elevator Interior 

15  0.0  3:1  5  5.0  PH I 

   Escalators  15  0  2:1  7.5  5  PHI 

  Stairs and Ramps 

15  0  2:1  7.5  5  PHI 

  

ATM'S, PIDS, Phone, 

Fountains 

20  3  3:1  10  4  PH I 

TABLE E-2 EXTERIOR ILLUMINATION LEVELS TABLE 

Tag Number 

Area Name 

Minimum 

Maintained Horz. (FC) 

 Average Maintained  Horz. (FC) 

Min. Maintained Vert. (FC) 

Maximum to 

Minimum Ratio (Max:Mi

n) 

Average to 

Minimum Ratio (Avg:Mi

n) 

Veiling Luminance Ratio (Lmax:La

vg) 

Phase 

EL‐1 Parking Lots 

0.5     0.25  15:1       PH I and PH II

EL‐2  Roadways     0.9        6:1  0.4 PH I and 

Page 137: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐132 

Part 3 Project RequirementsJuly 18, 2013

 

 

PH II

EL‐3 

Crosswalks and 

Intersections 

   1.8        6:1    PH I and PH II

EL‐4  Plaza  1  3  0.5          PH I and PH II

EL‐5 Baggage Canopy 

1  3  0.5          PH I and PH II

EL‐6A Platform (Covered) 

5  10        2:1    PH I and PH II

EL‐6B Platform (Open) 

5  10        2:1    PH I and PH II

EL‐7 Platform at Edge  

10  20        2:1    PH I and PH II

EL‐8 Pedestrian Tunnel 

3  15*        2:1    PH I and PH II

EL‐9 Building Façade 

   3‐5             PH I and PH II

EL‐10 Bus Drop Off (Open) 

   0.8  0.4     3:1    PH I and PH II

‐ Stairs and Ramps 

5  10        2:1    PH I and PH II

‐  Sidewalks     1        4:1    PH I and PH II

Room 20 ‐ 21 

Outdoor Storage 

1  3  0.5          PH I and PH II

Page 138: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐133 

Part 3 Project RequirementsJuly 18, 2013

 

 

* measured at 5’-0” AFF.

TABLE E-3 TEMPORARY STATION ILLUMINATION LEVELS TABLE 

Room #/Area Average 

Maintained Horz. (FC) 

Horz. Location (FEET AFF) 

Average to Minimum Ratio 

(AVG:MIN) 

Average Maintained Vert. (FC) 

Vert. Location (FEET AFF) 

1A  15  2.5  3:1  5  2.5 

1B  15  2.5  3:1  5  2.5 

2  15  2.5  3:1  5  2.5 

3  15  4.0  3:1  5  4.0 

4  20  3.0  3:1  10  5.0 

5  30  3.0  3:1  10  5.0 

6  30  2.5  1.5:1  15  3.5 

7  10  0.0  2:1  3  4.0 

8  15  3.5  2:1  5  3.5 

9  15  3.5  2:1  5  3.5 

10  15  3.5  2:1  5  3.5 

11  10  0.0  2:1  3  4.0 

EXTERIOR STAIRS, RAMPS 

10  0  2:1  2.5  5 

 

 

13.9  Receptacles 

A. Receptacles  shall  be  fed  from  receptacles  panels  only. Alternate  the  circuits  and  phases between adjacent receptacles. 

B. Unless otherwise noted, furnish and  install at  least one receptacle  in each room or area  in the Station. However, there shall be no receptacles in the shower areas and the Hazardous Material (Hazmat) Storage Room. Actual quantities and types of receptacles shall be as per the following sections. 

C. On each receptacle’s faceplate, furnish and install labeling indicating the panelboard name and circuit number. 

Page 139: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐134 

Part 3 Project RequirementsJuly 18, 2013

 

 

D. Explosion proof  receptacles  shall not be  fed  from  the  same circuits  feeding nonexplosion proof receptacles. 

E. Provide  electrical  floor  boxes  with  integrated  receptacles  where  indicated  on  the  plan. Coordinate location of floor boxes with layout of seating. 

F. Unless otherwise noted, for all other receptacles refer to the applicable section. 

G. Receptacles  for  electrical  equipment  and  appliances  shall  be  furnished  and  installed throughout  the  Station  per  equipment  requirements,  as  per  the  Comprehensive  User’s Requirements and as noted in the following sections. 

H. Independent  outlet  boxes  shall  be  used  for  different  types  of  receptacles,  such  as convenience, isolated ground, GFCI and all other receptacles. 

I. Each receptacle’s pin configuration shall match that of the connected equipment’s plug. 

J. Receptacle  spacing  indicated  in  the  following  sections,  is  between  the  centers  of  the receptacles. 

K. Installation: 

1. In general, the receptacle type shall be suitable for the type of area in which it is to be furnished  and  installed,  e.g.  explosion‐proof  in  classified  areas,  weatherproof  and corrosion resistant in wet or harsh/corrosive atmosphere locations. 

2. Coordinate receptacle locations with cubicle, equipment and furniture layouts. Relocate receptacles where furniture and other equipment  interfere with receptacle access, but do not exceed the maximum spacing requirements. 

3. Install  the  receptacles  so  that  they  do  not  interfere with  the  opening/closing  of  the gates, grilles, doors, windows, and other barriers. 

4. Branch circuits  for receptacles  installed  inside Communications cabinets  (including but not limited to file server and data cabinets) shall be run above each cabinet on a cable ladder and then down into the cabinet using flex conduit. 

13.9.2  General Purpose Duplex Convenience Receptacles 

A. Unless otherwise noted below, furnish and install one 20A, 125VAC general purpose duplex convenience receptacle every 10’ on walls or fence posts in each area and room throughout the Station except for the wet areas, corrosive atmosphere areas, hazardous areas, and the maintenance areas  (refer to the  following sections  for the specific requirements  for those areas). Where the room or area perimeter  is  less than 10’, there shall be one 20A general purpose  duplex  convenience  receptacle  installed  there  (or  as  required  in  the  following sections). 

B. General Purpose convenience duplex receptacles shall be installed in addition to any other receptacles required in this OPR (such as IG, quad, reel or power receptacles) and as shown on the Conceptual Drawings. Furnish and install additional dedicated receptacles for Owner‐

Page 140: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐135 

Part 3 Project RequirementsJuly 18, 2013

 

 

furnished/Design‐Builder‐installed equipment  (refer  to Appendix A  for more  information) and for Design‐Builder‐furnished/Design‐Builder‐installed equipment. 

C. Where receptacles are to be mounted a certain distance apart on the walls, the following shall apply: 

1. All entrances, open or barriered, shall be counted as part of the walls. 

2. Barriers include but are not limited to doors, fences, grilles and gates. 

3. Where the space’s or room’s enclosure consists of a fence (wholly or in part), install the receptacles on the fence posts. 

4. Adjust the spacing and number of receptacles if necessary so that the receptacle spacing does not exceed the maximum requirement. 

D. Where the spacing criteria causes a receptacle to fall at an entrance to the space or room, install the receptacle adjacent to the entrance on the nearest wall or fence post. 

E. Space  receptacles  evenly  apart  unless  otherwise  required  by  equipment  or  room restrictions. 

F. Where  a  space’s  or  room’s  perimeter  falls  between  integer  multiples  of  the  required receptacle spacing, the number of receptacles to be furnished and installed shall be as per the next higher  integer multiple.  In no case shall  receptacles be spaced at more  than  the maximum distance indicated or noted. For example, a four‐wall room that has a perimeter of 12’ and has a maximum receptacle spacing requirement of 10’ has a perimeter‐to‐spacing ratio of 1.2, and the next higher integer is 2, so therefore the room shall have 2 receptacles in it. 

G. Furnish and install general purpose convenience duplex receptacles in the following areas as noted: 

1. Every 6’ on centers in the following areas: 

2. Every 20’ in the following areas: 

3. One in each of the following areas: 

13.9.3  Power Receptacles 

A. Furnish  and  install  the  following  types  of mechanically‐interlocked  power  receptacles  as indicated,  in addition  to  the other  required  types of  receptacles. Refer  to  the Conceptual Drawings  for  information regarding the power receptacles. Refer  to  the Equipment List  in Appendix A for the quantities of the equipment. There shall be only one interlocked power receptacle per circuit for the following: 

1. Isolated Ground (IG) and Quadplex Receptacles: 

a. IG receptacles shall be furnished and installed as follows: o Furnish  and  install  IG  receptacles  panels  for  all  computer  workstations,  file 

servers  and  computer  data  racks,  and  feed  each  from  a  dedicated  isolation 

Page 141: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐136 

Part 3 Project RequirementsJuly 18, 2013

 

 

transformer  and  a  dedicated  UPS.  The  power  feeds  to  computer  and  other electronics equipment shall meet current industry standards. 

o All  IG  receptacles  shall  be  UPS‐conditioned  receptacles,  hospital‐grade,  and colored orange, and duplex (unless otherwise noted). 

o Neutrals  for  all  IG  receptacles,  isolation  transformers,  IG  receptacles panelboards,  subdistribution‐boards,  distribution  boards  and  associated disconnect switches shall be rated at 200% of the circuit breaker ampacity and higher if required to compensate for voltage drop. 

o IG receptacles shall be installed as per the manufacturer’s directions. Furnish and install  an  isolated  ground wire  and  a  common  building  ground wire  to  each isolated ground receptacle. 

o IG receptacles shall be mounted 4’ high on the shop area wall, at desk height in the offices, and shall be located adjacent to the computer data outlets. 

o For  each  IG  receptacle  furnished  and  installed,  also  furnish  and  install  one dedicated 20A  specification grade non‐IG general purpose quadplex  receptacle not farther than one foot (1’‐0”) from the IG receptacle. 

b. Furnish and install the following dedicated, 20A, 125VAC IG receptacles as indicated below  in  addition  to  the  required  general  purpose  duplex  receptacles.  Refer  to Section  14  Communications  Requirements,  Communications  Specifications  and Communications Conceptual Drawings for more details: 

o Furnish and  install one  IG duplex receptacle  for each computer, VDT and CCTV monitor, and as per the Communications OPR requirements. 

o Main Communications Room: 

o Dedicated duplex IG receptacles:  

1) One, for the security equipment. 

2) One, below each telephone terminal board (TTB). 

o Quadplex IG receptacles, each on a dedicated 20A lockable circuit breaker: 

1) One, for the Telephone Switch.  

2) Two, for the paging system. 

3) Two, for the CCTV cabinets. 

o Dedicated  IG  Data  Cabinet  receptacles.  Install  on  the  inside  bottom  of  each cabinet (To Be Further Developed): 

1) Data Cabinet #01 (Cables): One quadplex NEMA 5‐20R. 

2) Data Cabinet #02 (Data Equipment): 

a) Two duplex NEMA 5‐20R 

b) Two NEMA L6‐20R twistlock 

Page 142: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐137 

Part 3 Project RequirementsJuly 18, 2013

 

 

o One dedicated quadplex IG receptacle per each piece of wall mounted telephone equipment along the walls near the equipment and at each desk.  

o Communications Closets: 

1) One dedicated duplex  IG receptacles, below each telephone terminal board (TTB).   

2) One  dedicated  quadplex  IG  receptacle  per  each  piece  of  wall  mounted telephone equipment along the walls near the equipment and at each desk. 

3) Dedicated  IG Data Cabinet receptacles.  Install on the  inside bottom of each cabinet: 

4) Three quadplex IG receptacles on dedicated lockable 20A circuit breakers.  

o One  duplex  IG  receptacle  plus  one  quadplex  non‐IG  receptacle  for  each  data outlet (data drop). Refer to the Communications OPR for  information regarding the data outlets. 

o Property  Protection  Booths/Guard  Booths  (PPBs):  One  dedicated  IG  duplex receptacle for each piece of Communications and security equipment that is not hardwired, and as per Communications OPR requirements. 

o One  dedicated  duplex  IG  receptacle  at  each  "KRONOS",  timekeeping  unit  and punch clock  location. Refer to Section 14 Communication Requirements for the Kronos locations. 

o Telco Room:  

1) Two dedicated  IG  receptacles  for each data cabinet, mounted 84” AFF on the wall behind each cabinet: 

• One 250VAC, 30A single.  

• One 125VAC, 20A quadplex. 

2) One  dedicated  quadplex  IG  receptacle  per  each  piece  of  wall mounted telephone equipment along the walls near the equipment and at each desk. 

3) For  the  Telco’s  multiplexer  equipment  furnish  and  install:  two NEMA  L5‐20R,  125VAC  receptacles,  each  connected  to  a  20A dedicated  breaker;  and  two  NEMA  L6‐30R,  250VAC  receptacles, each  connected  to  a  dedicated  30A  two‐pole  breaker.  These receptacles  shall  be  fed  from  the  Main  Communications  Room panel  fed  via  the  UPS.  These  receptacles  shall  be mounted  near each cabinet.  

B. 20A, 125VAC duplex GFCI receptacles: 

Page 143: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐138 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. Furnish  and  install GFCI  receptacles  as  noted.  Except  in wet  locations,  the  Elevator Machine Room and Elevator Pit, GFCI receptacles are in addition to the other types of receptacles required by Section 14 and the Conceptual Drawings: 

o At sinks in the toilets and washrooms: 

a. One GFCI receptacle where there is only one sink; 

b. One GFCI receptacle between each pair of sinks where there are two or more sinks, up to two receptacles. 

o In all lunch rooms/areas, kitchens and at sinks and as otherwise noted. 

o On maximum 6’ centers in the Destination Sign Room. 

o On maximum 10’ centers in the following areas: 

• Elevator Machine Room. 

• Elevator pit. 

• All  areas  classified  as  wet  or  harsh/corrosive  atmosphere locations. 

o In the Kitchen (Specific quantities TBD): 

• Six 20A, 250V duplex GFCI receptacles with dedicated 20A, 208V circuit breakers. 

• Ten 20A 125V duplex GFCI receptacles with dedicated 20A circuit breakers  for  two  (2)  commercial  refrigerators,  two  slicers,  two cash  registers,  two  food  warmers,  and  two  steam  tables. Locations  are  to  be  coordinated  with  the  Architectural  kitchen equipment layout. 

o One within 1’ of each nonclassified‐area sump pit. 

o For each water fountain and water cooler (exception: if the unit is hardwired, furnish  and  install  a  specification  grade  single  receptacle  fed  from  a GFCI circuit breaker in the panelboard). 

o For  roof mounted  equipment:  one  dedicated GFCI  receptacle  per  piece  of equipment,  mounted  at  the  equipment  location  regardless  of  any  other requirement for receptacles in any other discipline’s OPR. 

o One, surface mounted on each outdoor highmast lighting pole base. 

o As required by the Codes. 

o Where a piece of equipment requires GFCI protection and a GFCI receptacle is  not  available  in  that  voltage  or  current  rating,  furnish  and  install  a dedicated  heavy‐duty  specification  grade  receptacle  and  dedicated  GFCI circuit  breaker  of  the  required  poles,  voltage  and  ampere  ratings  for  that 

Page 144: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐139 

Part 3 Project RequirementsJuly 18, 2013

 

 

equipment.  If  a GFCI breaker  is not  available  in  that  configuration,  furnish and install a hardwired GFCI device near the receptacle. 

C. Other  Receptacles  ‐  Furnish  and  install  the  following  receptacles  as  indicated.  All receptacles listed below shall be specification‐grade, rating as per equipment requirements: 

D. Heat Tracing ‐ Furnish and install heat tracing/freeze protection on all water lines, drainage lines (including but not limited to those for heat recovery units), steam lines, hydraulic lines (including but not limited to bus washer soap detergent lines and those for elevators), and valves and/or  traps,  that are outside heated areas and within 10’ of  the overhead  roll‐up doors  in  all  directions  inside  the  Station.  Also  furnish  and  install  heat  tracing/freeze protection on all Generator Room  sprinkler, hydraulic and other  lines  subject  to  freezing when the radiator grille is open.  

E. UPS Systems: 

1. Furnish  and  install  UPS  conditioned  power.  The  UPSs  shall  be  as  manufactured  by Powerware (or approved equal). Each UPS shall be limited to 50kVA. The UPSs shall also be sized with 30% spare capacity of the connected loads in kVA. 

2. The UPSs shall also be fed from the generator. 

3. Each  emergency‐lighting  UPS  shall  provide  a minimum  of  90 minutes  of  emergency lighting during a power outage. 

4. All  other  UPSs  shall  provide  a minimum  of  30 minutes  of  power  to  the  applicable equipment during a power outage.  

5. Unless  otherwise  noted,  furnish  and  install UPS‐backed  power  to  all  of  the  following equipment:  

o Receptacles servicing the file server; 

o Receptacles servicing data and communications racks;  

o All  computer  workstations  (isolated  ground  receptacles),  including  those near lifts in the maintenance areas;  

o All access control equipment including file servers, client workstation, system controller and power supply panels; 

o Trak system; 

o Building Management System (BMS); 

o All CCTV equipment including camera power supplies; 

o Telecommunications equipment; 

o Emergency  HID  lighting.  The  UPSs  feeding  the  HID  emergency  lighting fixtures must  be  rated  for  reactive  loads  and  shall  be  able  to  handle  the harmonics created by the ballasts. 

o Wireless access points. 

Page 145: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐140 

Part 3 Project RequirementsJuly 18, 2013

 

 

6. Unless  otherwise  noted,  furnish  and  install  UPS‐backed  power  to  all  of  the equipment in the following rooms, including receptacles and lighting:  

o All computer and data rooms;  

o All communications rooms;  

o TELCO room; 

o Server rooms; 

o Communication closets. 

7. An  alarm  system  shall be  incorporated  in  the UPS  system  and broadcast  a  visible alarm across all LAN screens in the Station, and shall sound a loud audible alarm at the server console, a 24‐hr manned position either  in the maintenance office or at the guard shack console whenever the UPS system takes over from Rochester Gas & Electric power.  The  alarm message on  the workstation  screens  shall  indicate  that power is down, and shall warn system administrators and users to log off and power down their systems.  The broadcast shall include estimated time to shutdown.  

8. The  UPS  system  shall  be  network‐monitorable.    The  UPS  shall  be  grounded  as required  by  the  manufacturer.    The  UPS  shall  be  installed  so  as  not  to  create electrical/electronic interference with the file server or any other equipment.  

9. All  central or  rack‐mounted UPS devices  shall  include an  SNMP network  interface card  and  temperature  alarm module,  connected  to  the  Local  Area  Network  for remote management purposes. 

F. Lightning  Protection  ‐  Furnish  and  Install  lightning  protection  and  surge  arresters  as  per NFPA 780 including but not limited to the roof perimeter, highmast lighting poles, lowmast lighting poles, outdoor CCTV  camera poles, and any metallic equipment mounted on  the roof. Refer to the attached Specifications for more information. 

G. Surge Protection  for Communications Panelboards  ‐ Surge protectors  shall be  installed at each communications equipment panelboard, MCG type “LS” series or approved equal. The surge  protectors  shall  offer minimum  three  redundant  protection  paths  per  phase,  solid copper  bus  bar  construction,  field  replaceable  modules  with  lifetime  warranty,  high headroom  varistors  with  high‐speed  thermal  disconnect,  EMI/RFI  filtering,  continuously monitored protection  circuits,  internal  and external  status  indicators, minimum 14‐gauge steel NEMA 4 enclosure, and shall meet UL1449 and NEMA LS1. 

H. Temporary Station: 

1. Provide Temporary Utility Power 

2. All details will be provided in future submission of this document. 

3. Coordinate all requirements with Amtrak TBD 

J. Other Requirements 

Page 146: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐141 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. Furnish and install power to all mechanical, communications and control equipment including but not  limited to: VAV boxes, fire/smoke dampers, electric duct heaters, supply/exhaust fans, boilers, elevators, compressors. 

2. Electric  hook‐ups  for  portable  equipment  (e.g.  portable welding machines,  et  al) shall be safe and meet Code. 

A. Furnish  and  install  all electrical  items of work  required  for  a  complete,  fully operational, energy  efficient  and  low maintenance  electrical  system  in  Rochester  Station.  The  design shall  consider equipment  life expectancy, energy  costs,  future expansion, maintainability, and maintenance costs. 

B. All electrical equipment and materials  furnished and  installed under this Contract shall be compatible in all respects with the other equipment in the respective system. 

C. The  design  shall  meet  or  exceed  all  current  industry  standards  and  applicable  codes. Electrical equipment (including elevators and escalators) attachments and supports shall be designed to meet or exceed the requirements of the Building Code of New York State. 

D. The  room sizes  for  the EDR, Generator Room, Electrical closets, EPRs, and subdistribution rooms shown on  the Conceptual Drawings are  for guidance only. The Design Professional shall determine the actual room sizes and locations. Any changes to the room sizes must be justifiable and approved by the Department.   Similarly, the ratings and sizes of the electrical equipment,  if shown, are the minimum requirements; the actual ratings and sizes shall be determined by the Design Professional. 

E. In  the  case  of  any  conflict  between  the  Specifications,  Codes,  Standards,  Drawings, Comprehensive User’s Requirements and/or the Project Requirements for the same subject, the Design‐Builder shall comply with the most stringent requirement. 

F. All Electrical equipment  shall be of heavy‐duty  industrial‐grade quality.   Catalog  cuts and samples  of  equipment  (such  as wires/cables,  devices  and  fittings)  shall  be  submitted  to Amtrak for information. All electrical equipment shall be UL Listed. 

G. All  electrical  equipment  including  but  not  limited  to  distribution  equipment,  conduit, wires/cables,  fixtures,  panels,  and  receptacles  shall  be  furnished  and  installed  with permanent nameplates or  tags  that shall  identify  the equipment, voltage, circuit number, source, phase orientation, and destination of power flow as applicable. 

H. For  any  repetitive  type  of  installation  such  as  lighting  fixtures,  receptacles  and  reel receptacles,  a  sample  mock‐up  shall  be  installed  for  review  and  approval  by  the Department. 

I. Design for the Environment where required by law. Follow ASHRAE requirements. 

J. Provide tables and schedules listing the manufacturers, ratings and details of all overcurrent protective  devices  and  electrical  equipment  (including  but  not  limited  to  switchboards, panels, disconnects and  transformers). Provide  full‐size drawings showing  the  locations of all panels (distribution boards, subdistribution boards, panelboards (typical)) on each floor. Use Amtrak standard panel schedules and fill in all information. 

Page 147: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐142 

Part 3 Project RequirementsJuly 18, 2013

 

 

K. All  wires,  cables,  busses,  lugs  and  electrical  connections  shall  be  copper.  Lugs  shall  be suitable for copper cables only. 

L. All  electrical  distribution  equipment  shall  be  fully  rated  for  the  available  short  circuit current. Series rated equipment and systems are not acceptable. 

M. The  Contract  documents  detail  the minimum  requirements  for  equipment, material  and installation procedures. All equipment and material that  is  furnished and  installed, and all installation procedures, must meet or exceed these minimum requirements. 

N. There shall not be any plumbing (water, sewer, or drain), gas, sprinkler, steam or hydraulic lines  passing  through  any  electrical  or  Communications  equipment  rooms.  In  all  other locations,  a  minimum  of  12”  separation  in  all  directions  shall  be  maintained  between electrical raceway and plumbing, steam, hydraulic, and other lines and their appurtenances. 

O. All Amtrak Standard Drawings  included  in  the RFP documents  shall be part of  the design package. 

P. Upon completion of equipment  installation, the Design‐Builder shall  fill  in and waterproof all  openings  in  an  approved  manner.  All  waterproofing  shall  be  maintained  when penetrating exterior walls, ceilings, roofs and slabs. 

Q. UPS‐backed electrical panels  in the Communications Rooms shall only feed the equipment inside the respective room. UPS backed panels feeding computer workstations outlets and other  loads  outside  the  communication  rooms  shall  not  be  installed  inside  the communications rooms. 

R. Power,  lighting, and  receptacle panels and disconnects  shall not be  installed  in  the  same rooms as Communications panels, UPSs and transformers  if they are not dedicated for the equipment in that room. 

S. Coordinate the design with all other trades and also furnish and install power as required to all  mechanical,  architectural,  instrumentation  and  controls,  communications,  and  other equipment, including but not limited to electrically operated skylights, doors, gates, grilles, all  cranes  (including  jib  and  monorail  cranes).  Provide  General  Arrangement  drawings showing the coordination of all equipment. 

T. Lighting,  power  and  receptacle  requirements  for  all  prefabricated  outdoor  enclosures including  the  temporary  trailer  shall  comply  with  the  requirements  set  forth  in  the applicable  sections  of  this  Part  3  Project  Requirements.  Refer  to  the  Architectural Specifications for more details. 

U. Follow NFPA 70 (NEC) Article 408.3(E) for electrical equipment phase arrangement. 

V. Electrical  equipment  requiring  examination,  adjustment,  servicing  or maintenance while energized  shall be  field marked  to warn qualified personnel of potential electric arc  flash hazards in accordance with NEC Article 110.16. 

13.2    Codes and Standards 

A. For applicable codes and standards refer to the attached Specifications.  

Page 148: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐143 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. Symbols on drawings shall comply with current ANSI standards. 

C. All  installations that have to be approved by the Fire Department of the City of Rochester, including  the power supply  to  the  fire water pump and  the  fire alarm panel, shall comply with Fire Department requirements. 

D. Calculations ‐ The Design‐Builder shall provide the following design calculations certified by a licensed Professional Engineer for Department records: 

1. Load calculations ‐ The complete electrical system shall be sized for the connected load plus  an  additional  30%  spare  capacity.  This  includes but  is  not  limited  to  all  feeders, switchboards,  distribution  boards,  subdistribution  boards,  panelboards,  transformers, and uninterruptible power supplies. 

2. Voltage Drop calculations: 

a. The system working voltages shall satisfy ANSI C84.1. 

b. The  total  voltage  drop  from  the  power  source  (main  circuit  breaker)  to  the utilization device shall not exceed 5% except as noted below in 3) and 4). 

c. The total voltage drop in the main and sub feeders shall not exceed 3%. 

d. The voltage drop in the branch circuit conductors shall not exceed 3%. 

e. The motor  feeder  total voltage drop  shall not exceed 4%. Fire water pump motor feeder voltage drop on inrush shall not exceed 15%. 

f. The voltage drop on separately derived systems  for sensitive electronic equipment such as computers shall not exceed the limits as per NEC Article 647.4D. 

3. Short circuit current calculations ‐ The short circuit ratings of all the power distribution equipment shall be based on short circuit study calculations, with minimum ratings as per Section 13.6. The Design‐Builder shall obtain,  in writing,  the available short circuit current  at  the  utility  from  Rochester  Gas &  Electric.  Provide  a  detailed  short  circuit current  calculation  from  Rochester  Gas  &  Electric’s  transformer  vault  to  the  final panelboard or disconnect switch on each bus and feeder on the one‐line diagram, taking into account all transformers, motors, feeder and branch circuit lengths. 

E. Coordination study ‐ The over‐current protective devices shall be sized and set based on a coordination study developed at the design development phase. The study shall contain the fault and load current values listed at key points on the one‐line diagram to determine the necessary equipment fault ratings. Ground fault protection shall be furnished and installed on the main circuit breaker and on all feeder breakers. Zone selective  interlocking shall be used  to achieve  the best possible  coordination with  the downstream breakers. Provide a coordination  study  showing  that  the  primary‐side  circuit  breaker  can  handle  the  inrush current of any associated transformer(s). The design professional shall propose solutions to any  problems  and  demonstrate  that  coordination  can  be  achieved  with  the  proposed devices. 

F. Lighting calculations: 

Page 149: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐144 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. IES  standards  shall  be  used  to  calculate  illumination  levels  unless  otherwise  noted elsewhere in this document. 

2. Light‐loss‐factors (LLFs) shall be calculated based on the environmental conditions of the respective  area  and on  the  specific  characteristics of each  component of  the  lighting system  (lamps, ballasts,  lighting  fixtures)  including voltage drop,  luminaire  reflectance and  transmittance  changes,  lamp  outages,  lamp  lumen  depreciation,  luminaire  dirt depreciation,  and  lamp  mortality  rates.  The  maintenance  and  parking  areas  of  the facility are especially dirty due to exhaust fumes, grease and other pollutants. The metal halide  lamp has a particularly severe  lamp  lumen depreciation curve that must also be factored into the calculations. Therefore, all LLFs must be carefully determined in order to achieve the minimum required maintained footcandle levels. 

3. Coefficients  of  utilization  (CUs)  shall  be  determined  based  on  the  lighting  fixture manufacturer’s  photometric  data,  taking  into  account  the  Room  and  Ceiling  Cavity Ratios, and room boundary reflectances.  

4. Submit a detailed list of all LLFs and CUs and provide justification for the determination of each variable.  

5. Luminaires shall be selected,  located, and aimed so as to minimize objectionable glare and  interference (calculate the Visual Comfort Probability of each area and conform to the  latest  IES  Lighting  Handbook).  Furnish  and  install  lighting  fixtures  specifically designed  for  rooms with  video  display  terminals  (VDTs)  to  reduce  glare  on  the  VDT screens. 

6. The required average maintained illumination levels are listed in Table E‐1 and E‐2 along with  the  light  sources.  The  illumination  levels  shall be measured  in  accordance  to  all applicable IESNA standards and guidelines. 

G. Structural Design Calculations ‐ Furnish and install seismic restraints & vibration isolation for all supporting systems  for electrical equipment,  including but not  limited  to conduit racks and lighting fixtures. 

13.3 Area Types 

A. Classified  (Hazardous)  Areas  ‐  The  area  classifications  given  here  are  the  minimum requirements. The Design‐Builder shall make a comprehensive study of  the entire Amtrak Station  to  identify  all  areas  that  are  required  to  be  classified  and  determine  their classifications. The extent of classification shall be as per area classification drawings based on  the  comprehensive  study.  All  classification  drawings  shall  be  certified  by  a  licensed Professional  Engineer  and  shall  be  submitted  to  the  Department  for  information.  Area classifications shall be based on the use of diesel fuel or as noted. The study shall include: 

1. calculations to determine the actual extent of the classified areas; 2. explanation of NEC classifications; 3. fueling regulations and considerations; 4. design criteria for electrical systems in hazardous locations; 

Page 150: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐145 

Part 3 Project RequirementsJuly 18, 2013

 

 

5. ventilation requirements; 6. temperature limits of diesel fuels before ignition/detonation; 7. references. 

B. The study should comply with all applicable local and national codes. The following areas in Rochester Station  shall be considered  to be Class 1, Division 1, Group  ‘D’  throughout  the area regardless of height unless otherwise noted below: 

1. All areas TBD. 

2. Wherever  possible,  all  electrical  equipment  shall  be  installed  outside  the classified areas except where  required by  the Codes or equipment  restrictions. All feeder and branch circuit conduits shall be installed exposed.  

3. Wet  Areas  ‐  (Wherever  possible,  except  where  required  by  the  Codes  or equipment restrictions, the electrical equipment shall be installed outside of the wet areas or at least out of the direct path of water.) 

4. The following open areas plus the 25’ periphery around them: 

o Outdoors, including under canopies and platforms; o Under skylights; o Any other areas required by the Codes. o Enclosed (the indicated area only): o Water  meter room; o Sewer ejector pump room; o High‐pressure wash room; o Elevator pit; o Escalator pit; o Sump pits; o Restrooms, toilets and personnel wash areas; o Any other areas required by the Codes. o Harsh/corrosive atmosphere areas: o Battery charging room; o Boiler room; o Any other areas required by the Codes. o Wet and classified: o Pits 

13.4  Maintenance requirements 

A. Provide  workspace  around  all  electrical  equipment  as  required  by  the  National  Electric Code. 

B. All  lighting  fixtures  shall  be  accessible with  a  stepladder  (up  to  10  feet)  or  a  scissors‐lift (higher than 10 feet) for lamp replacement and other maintenance. 

C. Free space on both sides of a panelboard shall be minimum 2’‐0”. Exception:  if  there  is a minimum of 3’‐0” from the top of the panel to the ceiling, and if there is sufficient entrance 

Page 151: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐146 

Part 3 Project RequirementsJuly 18, 2013

 

 

space at  the  top panel surface  for conduit  for spare breakers,  then  the minimum spacing may be 6” between panels. 

D. Roll‐up doors shall be  furnished and  installed  in the EDR of sufficient height and width to allow the installation and removal of equipment, and the use of man‐lifts in the room. 

E. Furnish and install personnel access and exit doors as per Code requirements in all electrical equipment rooms. 

F. The switchboards shall be installed in the center of the EDR, so they are accessible from the front, rear and the sides.  

G. All equipment shall be installed to permit easy access for operation and maintenance. 

H. There  shall  be  no  switchgear,  transformers,  panels  or  any  other  electrical  distribution equipment in the communications rooms not dedicated for communications equipment. 

13.5  Mounting of equipment 

A. Mounting arrangement (general): 

1. Unless  otherwise  noted,  mount  all  electrical  equipment  as  per  applicable  codes, manufacturer’s recommendations and the attached Specifications; 

2. No equipment shall  interfere with operation of the  facility, especially the movement of the buses and personnel; 

3. Maintain  proper  clearances  around  all  equipment  as  required  by  code  and maintenance considerations; 

4. Furnish and  install bollards to protect panelboards, transformers and other electrical distribution equipment exposed to vehicle travel; 

5. Provide dedicated space for conduit runs at the ceiling, including minimum 15% space (of the width of the rack)  for  installing  future additional conduit without obstructing access  to  existing  conduit  or  other  equipment.  Ceiling  conduit  runs  shall  not  cast shadows; 

6. Furnish and install, from each of panels in the EDR, one 1” conduit, extended from the panel to the outside of the EDR. Cap and label the conduits. 

7. Furnish  and  install  seismic  restraints  and  vibration  isolation  as  per  the Mechanical Engineering Specifications and as required by Codes. 

B. Lighting Fixtures: 

1. Mounting  heights  of  fixtures  in  the  maintenance  areas  shall  be  based  on  the Architectural  drawings  (installed  above  the  required  clearances  shown  on  the drawings). 

2. Lighting  fixtures  shall not be  installed  in classified areas unless  they are  suitable  for use in Class 1, Division 1, Group D locations; 

Page 152: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐147 

Part 3 Project RequirementsJuly 18, 2013

 

 

3. The bottoms of the  lighting  fixtures  in the utility rooms and other areas with  forklift access must clear whichever is greater: 

4. 10’ AFF; or 

5. The height of the door(s) 

6. Do not install lighting fixtures above anything that would block the light from reaching the  work  plane.  Relocate  the  fixtures  if  required,  adding  fixtures  as  necessary  to maintain the required lighting levels; 

7. The  arrangement  of  lighting  fixtures  shall  be  coordinated  with  the  layout  of  the areas/rooms in which they are installed. 

C. Receptacles 

1. Install the computer receptacles at desk height.  

2. Mount all receptacles 18” AFF, unless otherwise detailed on the plan drawings. 

D. Lighting Switches:  

1. Install all lighting switches in the office area 48” above finished floor to the top of the operating handle. 

2. Where  there  is a single door,  install  the  lighting switches near  the door strike plate. Where  there  is a double door,  install  the  lighting  switches on  the end of  the  right‐hand‐side of the door swing. 

E. Distribution and Panel Boards ‐ Install distribution and panel boards on channels. 

F. Switchboards‐ Allocate floor space for future switchgear, minimum 25% or enough for one additional vertical section, whichever is greater. Also refer to the attached Specifications. 

G. Transformers ‐ Install transformers on vibration isolators.  

H. Generator(s)  ‐  Install  the  generator(s)  on  vibration  isolators.  Also  refer  to  the  attached Specifications. 

I. Rubber mats ‐ Furnish and install rubber mats in front of electrical  equipment in each room containing  electrical  distribution  equipment,  including:  EDR;  EPRs;  electrical  closets; UPS room; ATS Room; and Generator Room. 

J. Disconnect Switches ‐ Install disconnect switches on channels. The mounting height shall be 4’‐0” AFF  to  the bottom of  the  switch  in Station garage areas, and 5’‐0” AFF  in all other areas. 

K. Owner‐furnished/ Design‐Builder‐installed equipment: 

1. See Appendix A  for power and  voltage  ratings  (single or  three phase), quantities and locations  of  owner  furnished  equipment.  Furnish  and  install  power,  dedicated disconnects and/or receptacles for all such equipment. 

2. The  power  requirements  for  all  Owner‐furnished/Design‐Builder  Installed  equipment shown  in  Appendix  A  are  over  and  above  the  receptacle  requirements  described  in 

Page 153: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐148 

Part 3 Project RequirementsJuly 18, 2013

 

 

Section 13.9. For all Owner‐furnished/Design‐Builder  Installed equipment,  furnish and install  a  dedicated  receptacle  (compatible  with  the  plug  on  the  equipment)  in  the respective  area  or  room  indicated  in  Appendix  A,  plus  the  receptacles  required  in Section 13.9. 

3. Install  a horsepower‐rated heavy‐duty disconnect  switch  for  all motorized equipment near the equipment. 

4. Feed  all  equipment  to  be  hardwired  via  a  horsepower‐rated  heavy‐duty  disconnect switch. 

L. Existing Conditions ‐ To be coordinated 

13.6 Electrical Service: 

13.6.1  Utility 

Furnish and install a 3‐phase, 4‐wire surge‐protected electrical service into the Station from the utility  company  (Rochester  Gas  &  Electric).  The  preferred  service  voltage  is  480/277V.  The Design‐Builder shall construct, furnish, and install all required equipment as per Rochester Gas & Electric’s final service layout (ruling): 

A. If  the  service  layout  calls  for  transformer  vaults  and  network  protector  (NWP) compartments, the requirement could be: 

1. Transformer Vaults, either: 

• Below grade in the sidewalk and/or Amtrak property; or 

• Above grade inside Amtrak property (with direct access to the outside). 

2. Network Protector Compartments ‐ Above grade inside Amtrak property. Install the NWP  compartments  inside  the  Amtrak  building  per  Rochester  Gas  &  Electric requirements. 

3. If the service layout calls for pad‐mounted transformers, the requirement would be: 

• Pad Mounted Transformers  ‐  Installed above grade on  concrete pads  inside Amtrak  property.  Furnish  and  install  bollards  and  a  fence  to  protect  the equipment  on  the  pad.  There  shall  be  direct,  independent  access  to  the transformers from the sidewalk. 

• Or any other Rochester Gas & Electric requirement. 

In  any  of  the  above  cases,  furnish  and  install  property  line  boxes  (PLBs)  as  per Rochester  Gas  &  Electric  requirements,  and  cables  from  the  PLBs  to  the  NWP compartments.  The  final  location  of  the  transformers,  vaults  and  NWP compartments  shall  be  based  on  Rochester  Gas  &  Electric’s  final  service  layout (ruling).  The  Design‐Builder  shall  coordinate  the  design  and  construction  of  the network  protector  rooms  and  transformer  vaults  or  pads  with  Rochester  Gas  & Electric,  and  build  as  per  Rochester  Gas  &  Electric’s  requirements.  Crabs  for 

Page 154: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐149 

Part 3 Project RequirementsJuly 18, 2013

 

 

connecting Rochester Gas & Electric cables to AMTRAK cables shall be as approved by Rochester Gas & Electric. 

4. Service Rating (Capacity) 

a. The service shall be based on the total connected load plus a 30% (of connected load)  spare  capacity.  The  spare  capacity  shall  be  included  in  the  sizing  of  the service/feeder breakers, distribution boards, subdistribution‐boards panelboards uninterruptible  power  supplies  and  other  electrical  equipment,  Furnish  and install  30%  spare  breakers  in  the  switchboard  distribution  boards, subdistribution boards and panelboards. 

b. The minimum  number  of  service  takeoffs  shall  be  determined  per  the  total connected load requirements plus a spare capacity of 30% of the total connected load.  Each  takeoff  shall  be  limited  to  a maximum  of  4000A  regardless  of  the Rochester Gas & Electric supply voltage.  If there are multiple takeoffs, then the takeoffs shall have equal Ampere  ratings. Each  takeoff shall  include 30% spare capacity. 

c. Rochester Gas & Electric approval for service equipment shall be obtained prior to  installation.    Coordination  with  Rochester  Gas  &  Electric,  furnishing  and installing all  required equipment as  specified, and  complete  installation as per Rochester  Gas  &  Electric  standards  shall  be  the  responsibility  of  the  Design‐Builder. 

d. The Design‐Builder shall prepare and submit a load request letter (via email) for electrical  service  to  the  Department  for  signature  and  transmission  to  the electrical  utility  (Rochester Gas &  Electric).  A  sample  letter  shall  be  furnished upon request. A  load breakdown  letter  listing the connected and demand  loads (winter  and  summer), must  be  furnished  to  Rochester Gas &  Electric  refer  to Exhibit “A” for a blank form 

e. Fuse  cut  outs  shall  be  furnished  and  installed  for  the  fire  alarm  systems  and other  stand  alone  panels  and  as  required  by  the  City  of  Rochester  Fire Department in coordination with Communications Engineering Division. The fire alarm control panel shall monitor the indication of ATS power failure. 

f. The service feeders shall be installed in ducts between the point of entry and the main switchboard or transformer vault(s), whichever  is applicable. All electrical service work shall comply with all of Rochester Gas & Electric’s regulations. The installation of  service equipment and  the number of network protector  rooms and transformer vaults shall be based on the approved  final service  layout and approved shop drawings. 

g. Rochester  Gas &  Electric’s  equipment  (transformers,  switchgear  and  network protectors)  shall  be  brought  to  and  installed  in  the  electrical  vault/network protector room (where applicable) by the Design‐Builder under Rochester Gas & Electric supervision.  

Page 155: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐150 

Part 3 Project RequirementsJuly 18, 2013

 

 

h. There  shall  be  no  breaks  in  the  service  lateral  or  metering  conduits  unless approval is obtained in writing from Rochester Gas & Electric.  Conduits and pull boxes are considered breaks in the conduit. 

i. Furnish and install cable limiters as per Rochester Gas & Electric’s requirements where three or more sets of service cables are used between the PLB and the CT cabinets. The cable limiters shall be installed on both ends of the service cables.  

13.6.2  Electrical Distribution Rooms, Electrical Panel Rooms and Electrical Closets 

A. All electrical distribution equipment shall be installed inside dedicated electrical equipment rooms.    Provide  25%  spare wall  space  in  the  electrical  distribution  and  panel  rooms  for future  use.    Provide  electrical  closets  at  various  locations  for  distribution  boards  and panelboards. 

B. Mechanical ventilation is required for all electrical equipment rooms. The preferred method of cooling/ventilating electrical equipment rooms  is with ventilation/exhaust fans. Refer to the Mechanical OPR  for  temperature  limits.  If such  temperature  limits cannot be reached via fans, submit an alternate scheme for approval. 

C. Provide equipment replacement clearances and removal routes in all electrical rooms. 

13.6.3 Main Disconnect and Switchboard 

A. The  main  disconnect  will  be  a  100%  rated  draw‐out  circuit  breaker  of  the  required overcurrent and short circuit interrupting ratings: 

1. Main circuit breakers shall not work in conjunction with current limiters at available short circuit current levels up to and including 200kA; 

2. For  available  short  circuit  current  levels more  than  200kA,  circuit  breakers  with integral current limiters shall be accepted; 

3. The main and switchboard distribution circuit breakers shall be electronic‐trip, with adjustments for long‐term, short‐term, instantaneous and ground fault conditions.  

4. Furnish and  install undervoltage  relays with voltage and  time  settings on all main circuit breakers to trip the breakers in the event of an undervoltage condition. 

B. Circuit  breakers  shall  be  installed  for  over‐current  protection  of  all  switchboards, distribution boards, subdistribution boards and panelboards. Branch circuit protection shall be by breakers only. 

C. Each switchboard shall have the required number of spare feeder breakers, specifics TBD. 

D. Coordinate all  tripping curves  (long  term, short  term,  instantaneous, and ground  fault)  to the specific facility electrical conditions. Submit a detailed coordination study. 

E. The switchboard busses shall be copper, and rated  for and braced to withstand minimum 200,000A  of  available  short  circuit  current  (Rochester  Gas  &  Electric  short  circuit  plus 

Page 156: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐151 

Part 3 Project RequirementsJuly 18, 2013

 

 

rotating  or  other  equipment  contribution),  or  more  if  determined  by  the  short  circuit current calculations required.  

F. Circuit monitors: Square D CM4000T series (with remote monitoring capability) or approved equal  shall  be  installed  on  the  switchboard/main  distribution  board.  A  communications interface  shall enable  a PC  to  communicate  remotely with  a  circuit monitor  through  the circuit monitor communications port: furnish and install the necessary phone, ethernet and data outlets in the vicinity of the switchboard. The circuit monitors shall be installed on the line sides of the main breakers on both the Rochester Gas & Electric and generator power supplies. 

G. Building Management System (BMS) 

1. The BMS shall monitor all line‐to‐line and line‐to‐neutral voltages (on the line side of the main disconnect,  in order to monitor Rochester Gas & Electric power),  line and neutral currents, kilowatts and kilowatt‐hours used, voltage  frequency, and power factor at all switchboards. 

2. The BMS shall  record all of  the  required values with  timestamps, and shall output the  information  in a format suitable for  inclusion  in a report. The BMS shall record any  alarms  with  the  time  of  occurrence.  These  alarms  shall  consist  of  voltages greater or  less than 5% of the standard  incoming Rochester Gas & Electric voltage. The BMS shall also record currents that exceed the transformer rating. 

3. All monitored  variables  shall  be made  available  to  the  BMS  system  through  an industry standard communications protocol such as BACNET, MODBUS, or approved equal,  along with  any  required hardware  and/or  software  interface,  such  that  it is compatible with the BMS system being furnished and installed. 

4. Refer  to  Section 15,  Instrumentation  and Controls,  for more details  regarding  the BMS. 

13.6.4  Distribution System 

A. Power  Distribution  ‐The  power  in  the  Amtrak  Station  shall  be  distributed  preferably  at 480/277V.  In case power  is obtained at a different voltage  from Rochester Gas & Electric, the voltage shall be stepped up or down (as applicable) to 480/277V. 

B. Furnish and install step‐down transformers of adequate capacity for all equipment requiring 220V three‐phase and single‐phase power supply. Refer to Appendix “A” for information. 

C. Furnish and install step‐down transformers of adequate capacity for all equipment requiring 208/120V power supply including but not limited to: 

1. Convenience receptacles; 

2. Communications equipment; 

3. Security equipment; 

4. Clock and Kronos system; 

Page 157: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐152 

Part 3 Project RequirementsJuly 18, 2013

 

 

5. Computer loads; 

6. Any other equipment needing 208/120V power supply; 

7. Fire detection system. 

D. Short Circuit Current Ratings of Equipment  ‐ The short circuit current  ratings of all power distribution  equipment  shall  be  based  on  a  short‐circuit  current  study  prepared  and furnished by the Design Professional. The available short circuit current at Rochester Gas & Electric  shall be obtained  in writing  from  the Electric Utility. However, all circuit breakers shall  have  the  following  minimum  short  circuit  current  interrupting  ratings,  RMS symmetrical: 

1. Main Switchboard(s): 200,000A; 2. Distribution Boards (DBs): 65,000A; 3. Subdistribution Boards: 42,000A; 4. Panelboards: 22,000A 

Where  the  short  circuit  current  exceeds  the  above  minimum  values  based  on  the calculations,  the  circuit  breakers  shall  be  rated  at  the  next  higher  standard  interrupting rating above the calculated short circuit current value. 

E. Distribution boards, subdistribution boards and panel boards: 

1. In order to minimize the sizes of the service switchboards and the number of feeder runs, furnish and install distribution boards of adequate capacity (plus spare) in each EPR  or  electrical  closet  to  feed  the  local  panelboards. Do  not  feed  the  individual panelboards directly from the main service switchboards. 

2. All electrical panels  (henceforth defined as any distribution boards, subdistribution boards, panel boards) and MCCs shall be furnished and installed with main breakers, and copper phase, neutral and ground bus bars.  No panels shall have more than 42 single pole breakers excluding  the 3‐pole main breaker. Every panel’s  feeder  shall have appropriately sized neutral  (minimum size equal  to phase cable size;  larger  if required to handle nonlinear loads) and ground cables. 

3. Feeders for all panels shall be sized as per the main circuit breaker frame rating, not the  trip  rating  (Example: a 400AF/300AT panel will have  its  feeder  sized  for 400A, not 300A). 

4. Furnish  and  install  dedicated  electrical  panels  in  rooms/areas  that  have concentrated loads or special electrical requirements.  

5. Panelboards  for  nonlinear  loads  (including  computers)  shall  have  200%  rated neutrals. Adjust the neutral busses in all required electrical equipment accordingly. 

6. Two spare panelboards along with  incoming  feeders of adequate capacity  for each panelboard shall be furnished and installed in the main EDR, the details of which are: 

Page 158: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐153 

Part 3 Project RequirementsJuly 18, 2013

 

 

7. In  each  separately  derived  isolated  ground  system,  the  main  isolated  ground distribution  board  and  each  isolated  ground  panel  board  shall  also  contain  an isolated ground bus in addition to the common ground bus. 

8. Furnish and install one UPS‐backed XXA, 3‐Phase, 4‐wires, 208/120VAC, 42 Breakers electrical panel  inside  the Main Communications Room  to  feed dedicated 20 Amp circuit outlets (1 duplex and 1 quad for telephone equipment; 1 duplex and 1 quad for paging equipment; 1 quad 125VAC and 1 single 250VAC for each data cabinet), and all dedicated circuit outlets required in the Computer room and Telco room. 

9. Furnish and install TBD UPS‐backed XX A, 3‐Phase, 4‐wires, 208/120VAC, 12 Breakers electrical panel, one each inside each Communications Closet to feed four dedicated 20A  receptacles  (1  duplex  and  1  quad  installed  on  the wall  18  inches  above  the finished floor below each telephone terminal board, and 1 quad installed on the wall 84 inches above the finished floor at the rear of each data cabinet/rack to feed the power strip installed on the cabinet/rack).  

10. All  panels  feeding  computer  loads  shall  be  protected  against  voltage  and  current surges and lightning strikes as per spec IEEE/ANSI standard C62.41 Category A and B testing levels, and shall meet UL spec 1449. Maximum allowable surge levels shall be calculated  and  affixed  to  the  system.    The  surge  protector  shall  be  type  SPB  as manufactured by MCG Electronics or approved equal. 

F. Transformers: 

1. All transformers shall be delta‐wye. 

2. All  transformers shall be sized with 30% spare capacity of  the  full connected  load. Dedicated  primary  and  secondary  protection  breakers  shall  be  furnished  and installed  for  all  transformers.  The main  circuit  breaker  of  a  panel  or  distribution board  on  the  secondary  side  of  the  transformer  does  not  constitute  secondary protection  by  Amtrak  standards,  and  shall  not  be  accepted.  Also  refer  to  the attached Specifications. 

3. The design shall compensate  for harmonics currents created by nonlinear  loads by the  reduction or elimination of  the harmonics  currents.  Isolation  transformers  for nonlinear loads shall be UL listed 1561 for K‐factor operation, triple‐shielded for high common mode noise attenuation, and filtered for high‐frequency noise attenuation. K‐rated isolation transformers shall be type “Ultra‐K” as manufactured by Controlled Power Company or approved equal. 

4. Neutral wires  and  busses  for  computer  and  other  nonlinear  loads  shall  be  200% rated, from the isolation transformer, to the disconnect switch, to the panel, and to the load. 

5. All transformer coil windings shall be copper. 

G. Disconnect switches: 

Page 159: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐154 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. A  dedicated  horsepower‐rated,  heavy‐duty,  industrial‐grade  disconnecting means shall be furnished and installed for all electrical equipment including packaged units and all other mechanical, communications and/or architectural equipment covered in  the  complete Project Requirements,  regardless  if  the equipment  is  supplied by Amtrak  or  the Design‐Builder.  Furnish  and  install  power  for  all  of  the  equipment installed  by  all  other  disciplines  as  required,  and/or  as  per  the  manufacturer’s recommendations.  Furnish  and  install  local  isolating  switches  for  all  electrical equipment within 5’ of the equipment with an enclosure rated for the area in which it  is  installed. Wherever  a manufacturer  has  not  furnished  a  disconnect means, furnish  and  install  a dedicated external horsepower‐rated disconnect  sized  as per the NEC. 

2. Furnish and  install Code sized disconnects for all Owner‐furnished/Owner‐installed, Owner‐furnished/Design‐Builder‐installed  and  Design‐Builder‐  furnished/Design‐Builder‐installed power equipment. 

H. Raceway, Boxes and Fittings ‐ Unless otherwise noted, all cables and wires shall be installed in raceways.  

1. Raceways shall be of the following types: 

o Hot‐dip  galvanized  rigid  steel  conduits  (HDG  RSC)  with  hot‐dip  galvanized malleable iron (HDG) fittings and HDG cast iron boxes; 

o Hot‐galvanized steel electrical metallic tubing (HG EMT) with raintight galvanized steel compression fittings and galvanized stamped steel boxes. 

o Underground fiberglass or PVC ducts in ductbanks. 

o Zero‐halogen‐jacketed galvanized liquidtight flexible metallic conduit, galvanized liquidtight fittings and galvanized stamped steel boxes. 

o Infloor  ducts  for  built‐in  type  furniture  only, where  required  by  the  furniture layout. 

2. Furnish and install HDG cast iron boxes for any transition between HDG RSC and any of the other raceway types. 

3. Any raceway passing through any particular area on  its way to  its destination shall be  rated  for use  in  that area  (e.g., wet, classified, corrosive), and not only  for  the final area in which the load is located. 

4. Concrete‐encased  fiberglass  or  PVC  ducts  shall  be  used  for  the  following applications.  The  minimum  size  of  fiberglass  or  PVC  ducts  shall  be  4”  with  a minimum of  two  fiberglass or PVC ducts  (at  least one  spare) per  run or  as noted below. Refer to Specification Section XX for more details. 

5. Incoming underground service feeders. Furnish and  install a minimum of two spare 4” fiberglass or PVC ducts. 

Page 160: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐155 

Part 3 Project RequirementsJuly 18, 2013

 

 

o From the PLB to the transformer vaults where there are transformer vaults and Network Protector Rooms. 

o From  the PLB  to  the CT Cabinet where  there are no  transformer vaults and no Network Protector Rooms. 

o From the pad ‐mounted transformers to the PLBs, and then to the CT cabinets in the EDR, where there are pad‐mounted transformers. 

6. Power feeds from electrical rooms to all outdoor facilities (including but not limited to: outdoor compactor/trash area, property protection booths, hazardous materials rooms, staircases, enclosures, and equipment storage sheds) except exterior lighting and exterior receptacles: underground fiberglass or PVC ducts. 

7. Under the concrete slab. 

8. Classified locations: 

o Dry areas: HDG RSC, explosion proof HDG  cast  iron boxes and  couplings, HDG sealing fittings. 

o Wet areas and harsh/corrosive atmosphere locations: HDG RSC, explosion proof HDG cast iron boxes and couplings, HDG sealing fittings, all polyurethane coated. 

9. Nonclassified locations: 

o Wet  areas  and  harsh/corrosive  atmosphere  locations: HDG  RSC, HDG  cast iron boxes and HDG malleable iron fittings, all polyurethane coated. 

o Under  the  concrete  slab  ‐  Polyurethane‐coated  HDG  RSC  and  fittings, minimum  size 1”, maximum 2”,  from  the  load  side of  the  local disconnect switch  to  the  shop  equipment  (e.g.,  brake  lathes  and  other  heavy machinery). Only if: 

1. The slab thickness is 12” minimum; and 

2. There is no vehicle travel in the area. 

o The  locations  of  the  conduit  shall  be  clearly  indicated  in  the  vicinity  of installation. 

o In hung ceiling areas, behind the sheetrock walls for devices only: galvanized, zero‐halogen‐jacketed flexible metallic conduit. 

o Dry  industrial  areas  exposed  to  vehicle  travel,  including  the maintenance area, up to 12’ AFF: HDG RSC, HDG cast iron boxes and HDG fittings. 

o For emergency circuits consisting of: power, communications  (including  the fire alarm equipment, fuse cut‐out boxes and CCTV equipment), emergency lighting,(including illuminated exit signs), and the fire water pump: HDG RSC, HDG cast iron boxes and HDG fittings. 

o Remaining  nonclassified  dry  locations:  hot  galvanized  EMT  and  galvanized steel raintight compression fittings and galvanized stamped steel boxes. 

Page 161: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐156 

Part 3 Project RequirementsJuly 18, 2013

 

 

10. All steel raceways shall be electrically continuous and grounded. 

11. Furnish and  install overhead exposed raceways on racks  in maintenance and other areas throughout the Station. 

12. All conduits feeding lighting fixtures on the outside walls shall be concealed. 

13. There  shall not be any underground or underfloor ducts within  the Station except where noted. 

14. All raceways shall be as per the National Electrical Code in approved sizes of: ¾”, 1”, 1¼”, 1½”, 2”, 2½”, 3”, 3½” and 4” only. 

15. Hangers from the ceiling steel or concrete for the conduit supporting trapezes shall be  furnished  and  installed.  Use  hot‐dip  galvanized  steel  in  dry  and  noncorrosive atmosphere areas, and Type 304 stainless steel everywhere else. 

16. In  areas without  hung  ceilings,  raceways  shall  be  installed  exposed  in  all  of  the rooms/areas on  that  floor.  In areas with hung  ceilings,  raceways  shall be  installed above the hung ceilings  for all  lighting, receptacle and power systems. The vertical runs running under the hung ceiling shall be concealed within the walls. All device boxes shall be mounted flush in the walls. 

17. Waterproof  all  incoming  ducts.  Seal  all  ducts  containing  cables  with  watertight expandable plugs, OZ/Gedney  type “CSBG” or approved equal. Seal all spare ducts with watertight caps. 

18. Raceway shall not run through any structural members. 

19. No electrical raceway (conduit, tubing, or trough) shall be installed inside any utility room,  space,  shaft  (elevator  room,  hoist way  and  shaft,  gas meter  room,  pump room,  machinery  space/room,  communications  room,  control  room  or  space), computer room  is not dedicated  for the electrical equipment  in that room. Do not through‐feed any other raceway in any such areas. 

20. Sealing  fittings shall be  installed at maximum 80  foot  intervals  for all conduit  runs longer than 80 feet that pass through classified (hazardous) areas. 

21. Conduit seals and drain  fittings shall be  installed as per Code  in conduit runs  from classified areas to unclassified areas on all sides of the classified area. 

22. All electrical equipment,  feeders  (conduits)  and wiring  installed  in  classified  areas shall be suitable for Class 1, Division 1, Group ‘D’ locations. Threaded, rigid steel hot‐dip  galvanized  conduits,  explosion‐proof  fittings,  couplings,  boxes,  hubs,  sealing fittings, sealing compounds and other associated requirements per both the Building Code of New York State and the NEC  (NFPA 70 Articles 500 thru 505 and 511 thru 516) shall be used in these areas. 

23. Conduit shall not block or interfere with the operation of windows, doors, skylights, HVAC equipment,  communications equipment  and other electrical equipment. Do not install conduit directly below skylights or across windows or other openings.  

Page 162: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐157 

Part 3 Project RequirementsJuly 18, 2013

 

 

13.6.5 Wiring 

A. All cables and wires, except those dedicated for the outdoor highmast and lowmast lighting fixtures and highmast  lighting pole receptacles, shall be  installed  in the applicable type of raceway. 

B. Wiring for the following electrical systems shall be installed in their own dedicated raceway systems: emergency compact fluorescent lighting, explosion proof lighting, explosion proof receptacles,  communications,  fire  alarm  panel,  fire water  pump,  computers,  telephone, telecommunications, data, clock, paging, CCTV, and security systems. 

C. Cover all cable connections in the manholes and property line boxes with heavy‐duty, thick‐wall, waterproof, heat‐shrink splice insulation with integral silicone sealant. 

D. The minimum size wire shall be No. 12 AWG, rated at 15A maximum. No. 10 AWG wire shall be rated at 20A maximum. All larger wire/cable sizes shall be rated as per the NEC. All wires and  cables  shall be  rated at 75°C. The branch circuit wires  tapped off  the home  runs  for lighting fixtures shall be minimum No. 12 AWG, and those for receptacles shall be minimum No.  10 AWG. All wires  and  cables  (including  ground wires)  shall  be  sized  as  required  to account  for  the  load  and  the  voltage  drop,  and  shall  fit  the  terminals  of  the  device  or equipment  properly.  Cutting  strands  off  of  the  wire/cable  to  fit  the  terminals  is  not permitted.  In  the event  that  the  feeder  cables/wires do not  fit  the equipment  terminals, furnish and install a transition to cables/wires that will. 

E. Install a pull cord in each empty conduit/tube. 

F. Each  electrical  raceway  shall  contain  insulated  grounding  conductor(s).  Isolated  ground circuits  shall  contain  two  grounding  conductors:  one  for  the  system  ground,  and  one dedicated  isolated  equipment  ground.  The  system  ground  conductor  shall  have  green insulation, and the isolated equipment ground conductor shall have green insulation with a yellow stripe.  

G. All  fire  water  pump  supply  conductors  (from  both  Rochester  Gas  &  Electric  and  the generator) routed through inside the building shall be encased within 2 inches of concrete, or within an enclosed construction dedicated to each fire water pump circuit, and shall have a minimum one hour fire resistance rating. 

H. Only  for  the outdoor highmast and  lowmast  lighting  fixtures, and  the  receptacles at each highmast pole, cable suitable  for direct burial, may be used  for the power  feeds  from the respective panelboards. Run  the  cables  in  conduits when AFF within  the  Station building line, and above grade outdoors. 

13.6.6  Enclosures 

A. Switchboard enclosures shall be NEMA 1A gasketed. 

B. All  electrical  equipment  enclosures  (including  panel  and  distribution  boards,  disconnect switches,  enclosed  circuit  breakers)  for  dry  and  nonclassified  areas  shall  be  combination NEMA 12/3R, hot‐dip galvanized after fabrication.  

Page 163: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐158 

Part 3 Project RequirementsJuly 18, 2013

 

 

C. All equipment enclosures for wet and corrosive atmosphere locations shall be minimum 12 gauge NEMA 4X type 304 stainless steel. 

D. All equipment enclosures for dry classified (hazardous)  locations shall be NEMA 7, suitable for Class 1, Division 1, Group D locations. 

13.6.7  Grounding and Ground Fault Protection 

A. All  electrical  equipment  shall  be  grounded  as  per  the  NEC,  IEEE  standards,  and  Amtrak Specifications and Standard Drawings. 

B. The  grounding  system  shall  consist of  the  following  systems bonded  together. Rochester Gas & Electric, the utility company, shall approve the grounding system. Ground resistance shall be less than 5 Ohms: 

1. The water pipe on the street side of water meter; 

2. Steel pilings and the metal frame of the building bonded together with cable; 

3. Concrete encased grounding electrode system; 

4. Grounding rod. 

C. All below‐grade ground connections shall be done using the  ‘Cadweld’ process.   All above ground connections shall be with pressure type connectors.  All connectors shall be covered with epoxy paint or taped.  

D. All ground connections shall be as per AMTRAK Standards. 

E. Rochester Gas & Electric’s neutral  shall be  grounded  as per  code on  the  line  side of  the service equipment.   

F. Each  transformer  shall  have  its  secondary  neutral  grounded  for  a  separately  grounded system. (For transformers on the load side of the service). 

G. Exposed non‐current carrying metal parts and cord and plug connected electric equipment, as well as  some electric equipment  (track of electrically operated  cranes,  frames of non‐electric elevators, metal partitions, etc), that might accidentally become energized shall be grounded through an equipment grounding conductor. 

H. Computer room grounding shall be as per TIA/EIA and IEEE standards. 

I. The main grounding grid bus  in the EDR, EPRs and other electrical rooms shall be copper, sized as per Code but minimum 4” x ¼“. 

J. Ground fault protection shall also be installed downstream breakers of the main disconnect to prevent a ground fault on any one feeder from interrupting power to all feeders. 

K. All panels, motors, starters, the metal hung ceiling system, and other permanently mounted electrical equipment shall be permanently and effectively grounded. 

L. Furnish and install bonding jumpers in all boxes and enclosures. 

Page 164: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐159 

Part 3 Project RequirementsJuly 18, 2013

 

 

M. After installation, the grounding system shall be tested. All related tests and measurements should be performed by the Design‐Builder in the presence of the Engineer. 

13.7  Generator Service and Power Distribution 

13.7.1  Generator 

A. Furnish and  install a generator  in a dedicated Emergency Power Supply System (Generator and ATS) room, preferably next to the EDR, along an exterior wall. The generator shall use fuel oil and shall have independent fuel supply and exhaust systems as well as its own HVAC systems  for  the  room  and  for  the  engines.  The  engine  shall  be  radiator  cooled.  The installations  shall  meet  all  the  Code  requirements  and  manufacturer’s  installation recommendations; 

B. The generator shall meet all EPA Tier 2 emission requirements. 

C. The whole system (the engine, generator and all other major auxiliary equipment) shall be built, tested and shipped by the same manufacturer; 

D. Furnish  and  install  a  day  tank  with  rupture  basin.  Refer  to  Section  12  Mechanical Requirements for fueling details; 

E. The  system  shall  include  all  necessary  accessories  including  a  silencer,  overcurrent protection,  exhaust  system,  over‐voltage  protection,  detailed  instrumentation  panel (voltage,  ampere,  kW  and  run  time  electronic  recording  meters),  battery  and  battery chargers, local and remote annunciator, keep‐warm system, and fuel pumps; 

F. The remote annunciator shall be installed in Rm. XX; 

G. The  generator  shall  have  the  ability  of  being  exercised  (manual/automatic)  on  a  regular basis; 

H. All  accessories  for  the  generator  that  require  power  (fuel  pumps,  heaters,  and  other equipment) shall be fed from the generator; 

I. The  parameters  of  the  complete  integrated  engine‐generator  system  (consisting  of  the engine‐generator set(s), automatic transfer switch(es), switchboards, uninterruptible power supplies,  and  all  appurtenances  (fuel  pumps,  heaters,  damper  motors,  et  al))  shall  be monitored by the BMS. The monitored parameters shall include, but not be limited to: 

1. System and appurtenances electrical and mechanical parameters; 

2. System  and  appurtenances  fluids  (fuel,  oil,  coolant,  antifreeze,  et  al)  parameters (pressures, levels, temperatures, et al); 

3. Operational  records  (event history,  run  times and durations,  system warnings and shutdowns, et al); 

4. Time delays; 

5. System and appurtenances parameters (including serial and model numbers); 

6. System and appurtenances diagnostics; 

Page 165: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐160 

Part 3 Project RequirementsJuly 18, 2013

 

 

7. System and appurtenances warnings; 

8. NFPA 110 Alarms; 

9. Digital inputs; 

10. Switchgear inputs; 

11. Digital outputs; 

12. User‐defined  faults  and  status  indicators  (refer  to  the  I&C  and  Communications OPRs) 

13. Any other system parameters as per the manufacturer’s recommendations. 

J. A power failure shall start the generator automatically. 

K. The generator shall be sized based on 100% of the total sum of items 1) through 7) below, plus 20%  spare of  this  sum.  If  the calculated value  is not a  standard  frame  size,  the next higher standard generator frame size shall be furnished and installed: 

1. 100% of whichever is greater: the heating system plus the ventilation system, or the cooling  system  plus  the  ventilation  system.  Include  all  appurtenances  for  each system in the determination. 

2. 100% of the nameplate rating of the fire water pump and associated equipment. 

3. 100% of the rated connected fluorescent lighting load 

4. 120% of the rated connected HID and LED lighting load. 

5. 140% of the nameplate ratings of all UPSs. 

6. All general convenience duplex receptacles as per the NEC. 

7. 4W/ft2 for all remaining loads. 

L. The  nameplate  (input)  power  ratings,  not  BHPs,  of  all  load  motors  shall  be  used  in determining the rating of the generator.  

13.7.2  Automatic Transfer Switches (ATS) 

A. The generator shall be connected to the distribution system via an automatic transfer and bypass  isolation switch, ASCO 7000 Series with Group 5 control panel (or approved equal) and all required accessories. The Design Professional shall determine the actual number of bypass‐isolation ATSs required; 

B. The power supply to the Fire Alarm Panel shall be made as per the requirements of the City of Rochester Fire Department.  A fuse‐cutout box shall be installed after the ATS, which will be  installed  between Rochester Gas &  Electric  power  and  the  generator.    Power will  be tapped from the line side of the main breaker.  An additional 30‐amp spare fuse‐cutout box shall be  installed  for  future use.   The entire  installation  shall be approved by  the City of Rochester  Fire  Department  and written  approval  shall  be  submitted  to  the  Department 

Page 166: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐161 

Part 3 Project RequirementsJuly 18, 2013

 

 

Additional auxiliary contacts shall be furnished and  installed  in the ATS for monitoring the switch position and/or power failure as required by Section 14 Communications. 

C. All  Automatic  Transfer  Switches  shall  be  equipped  with  accessories  to  detect  fault conditions (short‐circuit, ground‐fault, and/or other faults) downstream, and shall prevent the transfer from Rochester Gas & Electric to the Generator in that situation. 

D. The ATS enclosure  shall be  furnished and  installed with an  integral generator‐side  circuit breaker of the required AIC with ground‐fault protection relay. 

E. The Automatic Transfer Switch(es) shall be installed in the Emergency Power Supply System (Generator) Room.  

13.7.3  Power to the following shall be fed through UPSs 

A. BMS; 

B. Generator control panel; 

C. Equipment included in section 6.10; 

D. Egress lighting; 

E. All circuits required for telecommunications equipment. 

13.8  Lighting 

Lighting System Requirements; the following general requirements shall be incorporated in the lighting design for all areas: 

A. Lighting designs Tables E‐1 and E‐2 of this document categorize by Room/Area/Locations for required lighting levels or reference to follow including specific lighting sources (types) that shall be used in said areas. 

B. The  lighting  system  design  shall  be  designed  to  be  relatively  simple  and minimize  initial capital cost, as well as frequency and expense of maintenance. 

C. Lighting  shall  be  designed  to  be  functional,  yet  complementary  to  those  other  aesthetic features  in  the  space  that  provide  an  atmosphere  of  relative  comfort,  pleasantness  and cleanliness of surroundings, and a sense of personal safety and security. 

D. Adequate lighting levels, uniformity ratios, contrast, and other visibility attributes necessary to stimulate productivity, facilitate the use of facilities by patrons or the useful completion of tasks in a timely yet safe manner, and maintain the appropriate surveillance levels under all ambient lighting conditions shall be provided. 

E. Shall  be  energy  efficient  and  comply with  the  IGCC,  all  IESNA  Recommended  Practices, ASHRAE and ANSI standards. 

F. Lighting  shall be designed  to  satisfy  security  requirements and  to provide a pleasant and bright environment. 

G. Lighting fixture locations shall permit easy accessibility for re‐lamping and periodic cleaning. 

Page 167: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐162 

Part 3 Project RequirementsJuly 18, 2013

 

 

H. Any  required  illumination  shall  be  arranged  and wired  so  that  the  failure  of  any  single lighting unit or circuit shall not leave the area in total darkness. 

I. Lighting shall be designed to avoid “spill” light, objectionable glare, and light trespass. 

J. Lighting  fixtures shall be vandal‐resistant  in spaces accessible to patrons or to the general public. 

K. Lighting designs shall effectively control glare or other extraneous reflections  in the visual field. 

L. Lighting  shall  meet  or  exceed  recommendations  in  this  guide  in  accordance  with  all applicable IESNA Standard Practices. 

M. Manufacturers of lighting fixtures, poles, and accessories there of shall have a minimum of 10 years of reputable performance in the industry. 

N. Quality of Illumination 

1. Lighting designs shall be free from distracting and uncomfortable glare; care shall be exercised  to  prevent  specular  reflection  on  signage,  direct  glare  from  exposed lamps, high brightness areas of individual fixtures and reflections in glazing or other specular surfaces 

2. Uniformity ratios shall not exceed the recommended levels as directed by IESNA. 

3. The  color  temperature of  light  fixtures  shall be within  the  ranges  specified  in  the contract  specifications.    Lamps of  the  same  type within  each  area of  illumination shall  have  the  same  color  temperature.    In  areas where  different  types  of  light fixtures are required, the color temperature of each type shall be matched as close as practicable to ensure uniformity of color. 

4. Special  care  shall  be  taken  to  avoid  objectionable  glare  to  streets,  tracks  and adjacent properties.   Light fixtures shall be positioned to minimize spill  light.   Light fixtures  shall be provided with  internal  shielding and  located  to prevent  spill  light and  glare  in  the  direction  of  adjacent  properties.    Light  fixtures within  50’‐0”  of elevated freeways and overpasses shall be designed to provide absolute cutoff in the direction of moving traffic. 

O. Facility  Illumination  Level  ‐  The  illumination  levels  for  various  areas  shall  be  provided  as shown  in Tables E‐1 and E‐2.   The normal method  for  calculating  these  levels  shall be  in accordance with  the  IESNA  Lighting Handbook with modifications  or  other  requirements stated  herein.    The  “point  to  point” method  of  computing  illumination  shall  be  used  to verify and substantiate illumination and uniformity lighting levels. 

P. Circulation Roadway Lighting  ‐ Provide a uniform nighttime  illumination on the circulation roadways  to  enable  motorists  to  quickly,  distinctly  and  comfortably  view  the  roadway alignment,  vehicles,  obstacles,  or  obstructions  at  extended  distances  ahead,  even  during inclement weather.   The  lighting design shall comply with  the  latest applicable codes and IESNA Recommended Practices. 

Page 168: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐163 

Part 3 Project RequirementsJuly 18, 2013

 

 

Q. Street  and/or Motorway  Lighting  ‐  Street  and/or motorway  lighting  shall  conform  to  the standards and/or design requirements of the local and/or State jurisdiction. 

R. Parking Lot Lighting  

1. Lighting at surface parking lots shall meet the recommendations in the latest edition of the IESNA RP‐20, Lighting for Parking Facilities 

2. Lighting Poles shall be located inside of curbs, on traffic islands and walks, and along parking lot perimeter.  Placement shall present a minimum obstruction to movement and parking of cars.  Where poles are placed near automobile traffic or parking, they shall be protected from physical damage by a concrete base of at least 2’‐0” diameter which extends not less than 2’‐6” above grade 

3. Light  Pole  positioning  shall  be  as  required  to meet  lighting  uniformity  ratios,  be coordinated with  the  proposed  landscaping  scheme  and  prevent  off‐property  spill light. 

S. Exterior  Stairway  Lighting  ‐  The  types  of  luminaires  to  be  used  are  dependent  on  the location.  Either pole mounted or wall mounted luminaires shall be used whichever is more appropriate. See Table E‐1 and E‐2 for recommend illumination levels for exterior stairways. 

T. Security Lighting  ‐ Lighting shall be provided such that all areas throughout the facility are illuminated to ensure against unwanted visitors.   Fixture shall be vandal resistant. Refer to Table E‐1 and E‐2 for illumination levels. 

U. Light Pollution Mitigation  ‐ The designer must design  the exterior  lighting using  the  latest IESNA‐TM‐11 documentation as a guideline to control the light trespass.  All luminaires used shall have a U0 BUG rating (Full Cutoff) in accordance with the IESNA. 

V. Emergency Lighting and Exit Signs: 

1. Emergency lighting design shall conform to the NEC, CEC, NFPA 101, NFPA 130, IESNA Lighting Handbook, and the New York State Building Code. 

2. Emergency lighting shall be designed to maintain a minimum of 10 lux (1fc) horizontal illumination at the finished floor elevation throughout the areas of pedestrian egress. 

3. Exit  lighting  fixtures  /  signs  shall  be  provided  to  illuminate  the  designated  egress passageways,  stairways, and  the entrances/exits  to  stairways.   Exit  lighting  fixtures shall be wall or bracket mounted at a mounting height visible to all occupants within the occupied spaces.  Exit lighting fixtures / signs shall be separately wired from other electrical  loads  (to  the emergency panelboard)  and  shall be  connected  to  the UPS system. 

4. Emergency  lighting  for  stairways  and  escalators  shall  be  designed  to  emphasize illumination on the top and bottom steps or  landings.   All escalator steps newel and comb lighting shall be on emergency feeder circuits in accordance with NFPA 130.  A minimum of 1 10 lux (1fc). 

Page 169: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐164 

Part 3 Project RequirementsJuly 18, 2013

 

 

5. Emergency lighting fixtures and exit lights / signs in underground occupancies shall be located so as  to minimize  the possibility of being obscured by stratified smoke  in a fire. 

W. Lighting Control System ‐ Control artificial lighting automatically where practical by selecting from  among  various  lighting  control  devices.    The  most  useful  controls  for  increasing lighting  energy‐efficiency  are  timers, dimmers, photocells,  and occupancy  sensors.  Select control strategies based upon the following types of lighting situations: 

1. Lighting designed to continuously  illuminate an area during a combination of hours of  darkness  and  hours  of  operation.    Examples  of  continuous  lighting  could  be station stops, platforms, vehicle approaches, and parking lots.  Suitable controls for continuous lighting are timers and photocells. 

2. Standby Lighting  is similar  in design to continuous  lighting, except not continuously operated.     Standby  lighting  is turned on automatically when activity  is detected  in the area or manually as necessary  to occupy a  space.   Standby  lighting  is  suitable only  for  “instant on”  lamps.   Examples of  standby  lighting  could be utility  closets, offices, or restrooms.  Suitable controls for standby lighting include discrete “on/off” switches, occupancy sensors, and dimmers. 

X. Lighting Fixtures ‐ The luminaires for the project shall be constructed of the highest quality materials  and  designed  to  provide  a  minimum  of  20  years  of  operation.    All  exterior luminaires, along with those interior luminaires that require an occasional wash down, shall be  UL  Listed  for  Wet  Locations  and  for  Direct  Spray.    The  luminaires  chosen  shall incorporate  the most effective source  for  the application and shall be easily maintainable and removable without the use of tools.  No interior luminaries shall be constructed using a fiberglass  or  polymer  housing.    All  luminaires  shall  be  cast  or  extruded  aluminum with stainless steel hardware. 

Y. Poles,  Bracket  Arms,  and Miscellaneous  Hardware  ‐  All  poles  shall  be  galvanized  round tapered  steel constructed  to provide  the ultimate  security during  inclement weather.   All the poles shall include a grounding lug positioned in the pole opposite the reinforced hand hole.  Additionally, all poles shall incorporate an internal vibration dampener to minimized vibration  during  steady  winds  or  structural  vibrations.    The  bracket  arms  shall  be constructed  using  2  inch  schedule  40  tubing  bent  to  the  desired  shape  and  completely galvanized after  fabrication.   Any holes  that are  required  for mounting off accessories on the pole must be made during  the manufacturing process  and before  any  galvanizing or surface finishing is performed. All pole hardware shall be stainless steel. 

13.9  Receptacles 

13.9.1  Typical for All Types of Receptacles 

A. For  details  regarding  the  receptacles  and  their  appurtenances  refer  to  the  attached Specifications, Section XX, and to the Conceptual Drawings To Be Developed. 

Page 170: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐165 

Part 3 Project RequirementsJuly 18, 2013

 

 

B. Receptacles  shall  be  fed  from  receptacles  panels  only. Alternate  the  circuits  and  phases between adjacent receptacles. 

C. Unless otherwise noted, furnish and  install at  least one receptacle  in each room or area  in the Station. However, there shall be no receptacles in the shower areas and the Hazardous Material (Hazmat) Storage Room. Actual quantities and types of receptacles shall be as per the following sections. 

D. On each receptacle’s faceplate, furnish and install labeling indicating the panelboard name and circuit number. 

E. Explosion proof  receptacles  shall not be  fed  from  the  same circuits  feeding nonexplosion proof receptacles. 

F. Unless otherwise noted, for all other receptacles refer to the applicable section. 

G. Receptacles  for  electrical  equipment  and  appliances  shall  be  furnished  and  installed throughout  the  Station  per  equipment  requirements,  as  per  the  Comprehensive  User’s Requirements and as noted in the following sections. 

H. Independent  outlet  boxes  shall  be  used  for  different  types  of  receptacles,  such  as convenience, isolated ground, GFCI and all other receptacles. 

I. Each receptacle’s pin configuration shall match that of the connected equipment’s plug. 

J. Receptacle  spacing  indicated  in  the  following  sections,  is  between  the  centers  of  the receptacles. 

K. Installation: 

1. In general, the receptacle type shall be suitable for the type of area in which it is to be furnished and installed, e.g. explosion‐proof in classified areas, weatherproof and corrosion resistant in wet or harsh/corrosive atmosphere locations. 

2. Coordinate  receptacle  locations  with  cubicle,  equipment  and  furniture  layouts. Relocate receptacles where furniture and other equipment interfere with receptacle access, but do not exceed the maximum spacing requirements. 

3. Install the receptacles so that they do not interfere with the opening/closing of the gates, grilles, doors, windows, and other barriers. 

4. Branch  circuits  for  receptacles  installed  inside Communications  cabinets  (including but not limited to file server and data cabinets) shall be run above each cabinet on a cable ladder and then down into the cabinet using flex conduit. 

13.9.2  General Purpose Duplex Convenience Receptacles 

A. Unless otherwise noted below, furnish and install one 20A, 125VAC general purpose duplex convenience receptacle every 10’ on walls or fence posts in each area and room throughout the Station except for the wet areas, corrosive atmosphere areas, hazardous areas, and the maintenance areas  (refer to the  following sections  for the specific requirements  for those areas). Where the room or area perimeter  is  less than 10’, there shall be one 20A general 

Page 171: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐166 

Part 3 Project RequirementsJuly 18, 2013

 

 

purpose  duplex  convenience  receptacle  installed  there  (or  as  required  in  the  following sections). 

B. General Purpose convenience duplex receptacles shall be installed in addition to any other receptacles required in this OPR (such as IG, quad, reel or power receptacles) and as shown on the Conceptual Drawings. Furnish and install additional dedicated receptacles for Owner‐furnished/Design‐Builder‐installed equipment  (refer  to Appendix A  for more  information) and for Design‐Builder‐furnished/Design‐Builder‐installed equipment. 

C. Where receptacles are to be mounted a certain distance apart on the walls, the following shall apply: 

1. All entrances, open or barriered, shall be counted as part of the walls. 

2. Barriers include but are not limited to doors, fences, grilles and gates. 

3. Where the space’s or room’s enclosure consists of a fence (wholly or in part), install the receptacles on the fence posts. 

4. Adjust  the  spacing  and number of  receptacles  if necessary  so  that  the  receptacle spacing does not exceed the maximum requirement. 

D. Where the spacing criteria causes a receptacle to fall at an entrance to the space or room, install the receptacle adjacent to the entrance on the nearest wall or fence post. 

E. Space  receptacles  evenly  apart  unless  otherwise  required  by  equipment  or  room restrictions. 

F. Where  a  space’s  or  room’s  perimeter  falls  between  integer  multiples  of  the  required receptacle spacing, the number of receptacles to be furnished and installed shall be as per the next higher  integer multiple.  In no case shall  receptacles be spaced at more  than  the maximum distance indicated or noted. For example, a four‐wall room that has a perimeter of 12’ and has a maximum receptacle spacing requirement of 10’ has a perimeter‐to‐spacing ratio of 1.2, and the next higher integer is 2, so therefore the room shall have 2 receptacles in it. 

G. Furnish and install general purpose convenience duplex receptacles in the following areas as noted: 

1. Every 6’ on centers in the following areas: 

2. Every 20’ in the following areas: 

3. One in each of the following areas: 

13.9.3  Power Receptacles 

A. Furnish  and  install  the  following  types  of mechanically‐interlocked  power  receptacles  as indicated,  in addition  to  the other  required  types of  receptacles. Refer  to  the Conceptual Drawings  for  information regarding the power receptacles. Refer  to  the Equipment List  in Appendix A for the quantities of the equipment. There shall be only one interlocked power receptacle per circuit for the following: 

Page 172: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐167 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. Isolated Ground (IG) and Quadplex Receptacles: 

a. IG receptacles shall be furnished and installed as follows: 

o Furnish and install IG receptacles panels for all computer workstations, file servers and computer data racks, and feed each from a dedicated isolation transformer and a dedicated UPS. The power feeds to computer and other electronics equipment shall meet current industry standards. 

o All IG receptacles shall be UPS‐conditioned receptacles, hospital‐grade, and colored orange, and duplex (unless otherwise noted). 

o Neutrals  for  all  IG  receptacles,  isolation  transformers,  IG  receptacles panelboards,  subdistribution‐boards,  distribution  boards  and  associated disconnect switches shall be rated at 200% of the circuit breaker ampacity and higher if required to compensate for voltage drop. 

o IG  receptacles  shall  be  installed  as  per  the  manufacturer’s  directions. Furnish and install an isolated ground wire and a common building ground wire to each isolated ground receptacle. 

o IG  receptacles  shall  be mounted  4’  high  on  the  shop  area wall,  at  desk height  in  the offices, and  shall be  located adjacent  to  the computer data outlets. 

o For each IG receptacle furnished and  installed, also furnish and  install one dedicated  20A  specification  grade  non‐IG  general  purpose  quadplex receptacle not farther than one foot (1’‐0”) from the IG receptacle. 

b. Furnish  and  install  the  following  dedicated,  20A,  125VAC  IG  receptacles  as indicated  below  in  addition  to  the  required  general  purpose  duplex receptacles.  Refer  to  Section  14  Communications  Requirements, Communications Specifications and Communications Conceptual Drawings for more details: 

o Furnish and install one IG duplex receptacle for each computer, VDT and CCTV monitor, and as per the Communications OPR requirements. 

o Main Communications Room: 

o Dedicated duplex IG receptacles:  

1) One, for the security equipment. 

2) One, below each telephone terminal board (TTB). 

o Quadplex  IG  receptacles,  each  on  a  dedicated  20A  lockable  circuit breaker: 

1) One, for the Telephone Switch.  

2) Two, for the paging system. 

3) Two, for the CCTV cabinets. 

Page 173: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐168 

Part 3 Project RequirementsJuly 18, 2013

 

 

o Dedicated  IG Data  Cabinet  receptacles.  Install  on  the  inside  bottom  of each cabinet (To Be Further Developed): 

1) Data Cabinet #01 (Cables): One quadplex NEMA 5‐20R. 

2) Data Cabinet #02 (Data Equipment): 

a) Two duplex NEMA 5‐20R 

b) Two NEMA L6‐20R twistlock 

o One dedicated quadplex  IG  receptacle per each piece of wall mounted telephone  equipment  along  the walls near  the equipment  and  at  each desk.  

o Communications Closets: 

1) One  dedicated  duplex  IG  receptacles,  below  each  telephone terminal board (TTB).   

2) One  dedicated  quadplex  IG  receptacle  per  each  piece  of  wall mounted telephone equipment along the walls near the equipment and at each desk. 

3) Dedicated IG Data Cabinet receptacles. Install on the inside bottom of each cabinet: 

4) Three  quadplex  IG  receptacles  on  dedicated  lockable  20A  circuit breakers.  

o One duplex  IG  receptacle plus one quadplex non‐IG  receptacle  for each data  outlet  (data  drop).  Refer  to  the  Communications  OPR  for information regarding the data outlets. 

o Property Protection Booths/Guard Booths (PPBs): One dedicated IG duplex receptacle for each piece of Communications and security equipment that is not hardwired, and as per Communications OPR requirements. 

o One dedicated duplex  IG  receptacle at each  "KRONOS",  timekeeping unit and  punch  clock  location.  Refer  to  Section  14  Communication Requirements for the Kronos locations. 

o Telco Room:  

1) Two dedicated  IG  receptacles  for each data cabinet, mounted 84” AFF on the wall behind each cabinet: 

• One 250VAC, 30A single.  

• One 125VAC, 20A quadplex. 

2) One  dedicated  quadplex  IG  receptacle  per  each  piece  of  wall mounted telephone equipment along the walls near the equipment and at each desk. 

Page 174: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐169 

Part 3 Project RequirementsJuly 18, 2013

 

 

3) For  the  Telco’s  multiplexer  equipment  furnish  and  install:  two NEMA  L5‐20R,  125VAC  receptacles,  each  connected  to  a  20A dedicated  breaker;  and  two  NEMA  L6‐30R,  250VAC  receptacles, each  connected  to  a  dedicated  30A  two‐pole  breaker.  These receptacles  shall  be  fed  from  the  Main  Communications  Room panel  fed  via  the  UPS.  These  receptacles  shall  be mounted  near each cabinet.  

B. 20A, 125VAC duplex GFCI receptacles: 

1. Furnish  and  install GFCI  receptacles  as  noted.  Except  in wet  locations,  the  Elevator Machine Room and Elevator Pit, GFCI receptacles are in addition to the other types of receptacles required by Section 14 and the Conceptual Drawings: 

o At sinks in the toilets and washrooms: 

a. One GFCI receptacle where there is only one sink; 

b. One GFCI receptacle between each pair of sinks where there are two or more sinks, up to two receptacles. 

o In all lunch rooms/areas, kitchens and at sinks and as otherwise noted. 

o On maximum 6’ centers in the Destination Sign Room. 

o On maximum 10’ centers in the following areas: 

• Elevator Machine Room. 

• Elevator pit. 

• All  areas  classified  as  wet  or  harsh/corrosive  atmosphere locations. 

o In the Kitchen (Specific quantities TBD): 

• Six 20A, 250V duplex GFCI receptacles with dedicated 20A, 208V circuit breakers. 

• Ten 20A 125V duplex GFCI receptacles with dedicated 20A circuit breakers  for  two  (2)  commercial  refrigerators,  two  slicers,  two cash  registers,  two  food  warmers,  and  two  steam  tables. Locations  are  to  be  coordinated  with  the  Architectural  kitchen equipment layout. 

o One within 1’ of each nonclassified‐area sump pit. 

o For each water fountain and water cooler (exception: if the unit is hardwired, furnish  and  install  a  specification  grade  single  receptacle  fed  from  a GFCI circuit breaker in the panelboard). 

Page 175: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐170 

Part 3 Project RequirementsJuly 18, 2013

 

 

o For  roof mounted  equipment:  one  dedicated GFCI  receptacle  per  piece  of equipment,  mounted  at  the  equipment  location  regardless  of  any  other requirement for receptacles in any other discipline’s OPR. 

o One, surface mounted on each outdoor highmast lighting pole base. 

o As required by the Codes. 

o Where a piece of equipment requires GFCI protection and a GFCI receptacle is  not  available  in  that  voltage  or  current  rating,  furnish  and  install  a dedicated  heavy‐duty  specification  grade  receptacle  and  dedicated  GFCI circuit  breaker  of  the  required  poles,  voltage  and  ampere  ratings  for  that equipment.  If  a GFCI breaker  is not  available  in  that  configuration,  furnish and install a hardwired GFCI device near the receptacle. 

C. Other  Receptacles  ‐  Furnish  and  install  the  following  receptacles  as  indicated.  All receptacles listed below shall be specification‐grade, rating as per equipment requirements: 

D. Heat Tracing ‐ Furnish and install heat tracing/freeze protection on all water lines, drainage lines (including but not limited to those for heat recovery units), steam lines, hydraulic lines (including but not limited to bus washer soap detergent lines and those for elevators), and valves and/or  traps,  that are outside heated areas and within 10’ of  the overhead  roll‐up doors  in  all  directions  inside  the  Station.  Also  furnish  and  install  heat  tracing/freeze protection on all Generator Room  sprinkler, hydraulic and other  lines  subject  to  freezing when the radiator grille is open.  

E. UPS Systems: 

1. Furnish and  install UPS conditioned power. The UPSs  shall be as manufactured by Powerware (or approved equal). Each UPS shall be limited to 50kVA. The UPSs shall also be sized with 30% spare capacity of the connected loads in kVA. 

2. The UPSs shall also be fed from the generator. 

3. Each emergency‐lighting UPS shall provide a minimum of 90 minutes of emergency lighting during a power outage. 

4. All other UPSs  shall provide a minimum of 30 minutes of power  to  the applicable equipment during a power outage.  

5. Unless otherwise noted, furnish and install UPS‐backed power to all of the following equipment:  

o Receptacles servicing the file server; 

o Receptacles servicing data and communications racks;  

o All  computer  workstations  (isolated  ground  receptacles),  including  those near lifts in the maintenance areas;  

o All access control equipment including file servers, client workstation, system controller and power supply panels; 

Page 176: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐171 

Part 3 Project RequirementsJuly 18, 2013

 

 

o Trak system; 

o Building Management System (BMS); 

o All CCTV equipment including camera power supplies; 

o Telecommunications equipment; 

o Emergency  HID  lighting.  The  UPSs  feeding  the  HID  emergency  lighting fixtures must  be  rated  for  reactive  loads  and  shall  be  able  to  handle  the harmonics created by the ballasts. 

o Wireless access points. 

6. Unless  otherwise  noted,  furnish  and  install  UPS‐backed  power  to  all  of  the equipment in the following rooms, including receptacles and lighting:  

o All computer and data rooms;  

o All communications rooms;  

o TELCO room; 

o Server rooms; 

o Communication closets. 

7. An  alarm  system  shall be  incorporated  in  the UPS  system  and broadcast  a  visible alarm across all LAN screens in the Station, and shall sound a loud audible alarm at the server console, a 24‐hr manned position either  in the maintenance office or at the guard shack console whenever the UPS system takes over from Rochester Gas & Electric power.  The  alarm message on  the workstation  screens  shall  indicate  that power is down, and shall warn system administrators and users to log off and power down their systems.  The broadcast shall include estimated time to shutdown.  

8. The  UPS  system  shall  be  network‐monitorable.    The  UPS  shall  be  grounded  as required  by  the  manufacturer.    The  UPS  shall  be  installed  so  as  not  to  create electrical/electronic interference with the file server or any other equipment.  

9. All  central or  rack‐mounted UPS devices  shall  include an  SNMP network  interface card  and  temperature  alarm module,  connected  to  the  Local  Area  Network  for remote management purposes. 

F. Lightning  Protection  ‐  Furnish  and  Install  lightning  protection  and  surge  arresters  as  per NFPA 780 including but not limited to the roof perimeter, highmast lighting poles, lowmast lighting poles, outdoor CCTV  camera poles, and any metallic equipment mounted on  the roof. Refer to the attached Specifications for more information. 

G. Surge Protection  for Communications Panelboards  ‐ Surge protectors  shall be  installed at each communications equipment panelboard, MCG type “LS” series or approved equal. The surge  protectors  shall  offer minimum  three  redundant  protection  paths  per  phase,  solid copper  bus  bar  construction,  field  replaceable  modules  with  lifetime  warranty,  high headroom  varistors  with  high‐speed  thermal  disconnect,  EMI/RFI  filtering,  continuously 

Page 177: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐172 

Part 3 Project RequirementsJuly 18, 2013

 

 

monitored protection  circuits,  internal  and external  status  indicators, minimum 14‐gauge steel NEMA 4 enclosure, and shall meet UL1449 and NEMA LS1. 

H. Temporary Station: 

1. Provide Temporary Utility Power 

2. All details will be provided in future submission of this document. 

3. Coordinate all requirements with Amtrak TBD 

I. IT Trailer: 

1. Provide Temporary IT connections 

2. All details will be provided in future submission of this document. 

3. Coordinate all requirements with Amtrak TBD 

J. Other Requirements 

1. Furnish and install power to all mechanical, communications and control equipment including but not  limited to: VAV boxes, fire/smoke dampers, electric duct heaters, supply/exhaust fans, boilers, elevators, compressors. 

2. Electric  hook‐ups  for  portable  equipment  (e.g.  portable welding machines,  et  al) shall be safe and meet Code. 

3. Automatic Fare Collection/Revenue Equipment  

a. Automatic  Fare  Collection/Revenue  Equipment,  needs  power.  Furnish  and install  all  required  power  equipment  (  including  but  not  limited  to  cables, circuit breakers, HDG RSC, boxes, fittings, disconnect switches) to feed power to all of the indicated equipment. 

b. The Design‐Builder shall make the system fully operational. 

Page 178: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐173 

Part 3 Project RequirementsJuly 18, 2013

 

 

TABLE E-1 ILLUMINATION LEVEL TABLE To Be Further Developed

Area Foot-candles,

Maintained

NOTES: 1. Any area or room not covered in above Table E‐1 shall be provided with a minimum of 

30 foot‐candles illumination level. The light source shall be suitable for the type of area. 2. All lighting fixtures shall be supplied and installed with lamps and ballasts. 3. All highmast and  lowmast pole  lighting fixtures shall be furnished with  installed house‐

side shields to block light from falling onto neighboring properties.  4. Emergency lighting levels shall be as per NFPA 101, Life Safety Code. 5. All  illumination  levels  shall  be  achieved without  natural  light  (sunlight  or moonlight) 

contribution, and shall be measured on a dark night. 

Page 179: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐174 

Part 3 Project RequirementsJuly 18, 2013

 

 

TABLE E‐2 LAMP TABLE To Be Further Developed 

Lamp type Wattage/ size 

No. 

Of lamps per 

fixture 

Area of use Ballast 

type 

Maximum number of fixtures per 277V single phase circuit 

NOTE: 

1. Lighting fixtures with other kinds of compact fluorescent  lamps may be used for some specialized  applications  like  emergency  lighting  units  with  battery  backup.  The maximum number of compact fluorescent lamps per circuit shall not exceed 12. 

2. HID fixtures count as one lamp per fixture. 3. Fluorescent lighting fixtures may have one, two, three or four lamps only. 4. Linear fluorescent lamps shall be 4’ long only. 

Page 180: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐175 

Part 3 Project RequirementsJuly 18, 2013

 

 

Definitions: 

1. Utility Room: EDR, EPR, Electrical Closet, Generator Room, Electrical Vault. 

2. EDR (Electrical Distribution Room): switchboard room. 

3. EPR  (Electrical Panel Room): where  the panel and distribution boards dedicated  for a particular  area  in  the  facility  are  located.  There  shall  be  several  EPRs  per  floor. Disconnect switches shall be  located next to the  loads served by them, not  in the EPR, unless the loads are in the EPR. 

4. Electrical Closet: same as EPR. 

5. Panelboard (PB): an electrical panel that only feeds branch circuit loads and has a main breaker  that  does  not  exceed  250A.  This  includes  lighting  panels,  receptacle  panels, power panels and communications panels. 

6. Distribution Board (DB): an electrical panel that has a main breaker exceeding 250A, or feeds at least one other panel (regardless of main breaker size). 

7. Lighting Panel  (LP): an electrical panel  that only  feeds  lighting branch circuits. Lighting fixtures shall be fed only from Lighting Panels. There shall be separate LPs for indoor and outdoor lighting fixtures. 

8. Receptacle Panel (RP): an electrical panel that only feeds either convenience, computer or reel receptacle branch circuits. Receptacles shall be fed only from Receptacle Panels. There shall be separate RPs for reel, computer, and convenience receptacles. 

9. Power  Panel  (PP):  an  electrical  panel  that  feeds  motors,  power  equipment,  power receptacles and miscellaneous electrical loads. 

10. Computer Workstation: any computer  (data outlet)  location,  regardless of area  in  the entire Station. 

11. Provide: furnish and install the required electrical equipment. 

12. Raceway: conduit, tubing, trough, cable tray or duct. 

13. Mechanical Equipment Rooms: Boiler rooms, compressor rooms, fire water pump room, tire repair areas/rooms, HVAC equipment rooms, water meter room, gas meter room. 

14. Dedicated receptacle: one receptacle per circuit breaker. 

15. Dedicated disconnect: only one piece of equipment per disconnect. 

16. Office: any room, area or space with a desk. 

17. Outlet: receptacle.  

Page 181: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐176 

Part 3 Project RequirementsJuly 18, 2013

 

 

Abbreviations: 1. RSC:  Rigid Steel Conduit 2. HDG: hot‐dip galvanized 3. EMT:  Electrical Metallic Tubing 4. PVC:  Polyvinyl Chloride 5. FG:  Fiberglass 6. IBC:  International Building Code 7. Designer/Engineer: Designer and Engineer 8. UL: Underwriters Laboratories 9. IG: isolated ground 10. AFF: Above finished floor. 11. HG: Hot galvanized. 12. Typ: Typical 13. PPB: Property Protection Booth/Guard Booth 14. AF: Circuit breaker Amperes‐frame size 15. AT: Circuit breaker Amperes‐trip setting 16. GFCI: Ground fault current interrupter/interrupting 17. P&E: Plant and Equipment (maintenance) 18. OPR: Owner’s Project Requirements 19. EPA: Environmental Protection Agency 20. BHP: Brake horsepower 21. GOC: Garage operating center 22. MOC: Farebox repair shop 23. a/k/a: also known as 24. CWA: Constant wattage autotransformer 25. DOB: Department of Buses 26. AFC: Automatic Fare Collection 27. HPS: High pressure sodium 28. PSMH: Pulse start metal halide. 29. IEEE: Institute of Electrical and Electronics Engineers 30. TIA/EIA: Telecommunications Industry Association 31. rec.: receptacle 

 

Page 182: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐177 

Part 3 Project RequirementsJuly 18, 2013

 

 

Exhibit A 

Rochester Gas & Electric Load Request Letter To Be Further Developed 

 Exhibit B 

Typical Panelboard Schedule 

Notes: 

1. The voltage shown in the table is for a 208VAC, 3‐phases, 4‐wires system. However, this table  shall  also be used  for 480VAC, 3‐phases, 4‐wires  systems, with  the  appropriate changes to the voltage designation at the top right of the table. 

2. For total Volt‐Amp calculations, use the highest phase current (out of Phases A, B, C). 

Page 183: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐178 

Part 3 Project RequirementsJuly 18, 2013

 

 

SECTION 14.  COMMUNICATIONS REQUIREMENTS 

14.1   

  Facility Requirements 

The Design Builder (DB) must adhere to the following criteria encompassing the work required to design, furnish, install and test/commission the following systems; 

• Telecommunications System  • Public Address System • Fire Alarm System • Digital Signage 

The work  required under  this  section  is applicable  to  the Temporary Station Trailers and  the final Station configuration for Phase I and II. 

Before  commencing  on  the  design  and  installation  of  any  work  in  this  section,  the  DB Contractor shall meet with the proper agency  (Fire Department, Amtrak  IT, Amtrak Police) to coordinate  the  location  of  devices  and  infrastructure  and  ensure  compliance  to  referenced Amtrak standards. 

14.2   Standards and Codes 

Amtrak Premise Distribution System Standards V1.0 

Amtrak Police Department ‐ Corporate Security Standard Design Practice 2011 

Amtrak Engineering Stations Standard Design Practices (SDP) June 2012 

ANSI TIA/EIA‐568 

NFPA 70 – National Electrical Code 2011 

NFPA 72 – National Fire Alarm and Signaling Code 

14.3  Telecommunication System 

A. Design,  furnish and  install  incoming  telecommunication  service, network connectivity and structured  cabling  facilities  to  support  Telecommunication  Systems  (voice  and  data) requirements for the Temporary Station and Station (Phase I and II).    

B. The design portrayed on  the Contract Documents provides  a  representation of expected layouts  and  topology  of  systems.  DB  Contractor  shall  coordinate  specific  requirements, location of devices and final configuration of all system with Amtrak and Trailways.  

Page 184: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐179 

Part 3 Project RequirementsJuly 18, 2013

 

 

C. Coordinate  with  the  Authority's  Telecommunications  Services  to  provide  the  required services from the Telephone Company.    

D. Horizontal Copper Cabling 

A. All horizontal cabling shall  from  telecommunications outlet  (TO) and workstation area outlet (WAO) shall be category 6. 

B. All horizontal cabling shall be designed and arranged in star topology. 

C. All horizontal cabling above accessible ceiling shall be installed exposed and mounted on J‐hooks. J‐hook spacing shall not exceed five (5) feet horizontally. 

D. Telecommunication Outlets (TO) shall have a minimum of a 1 ¼” conduit extending from TO to above the ceiling. Conduit shall have a 90 degree bend perpendicular to the wall toward  the  center  of  the  room.  The  end  of  the  conduit  shall  have  a  nylon  bushing. Rough ends of conduits are not acceptable. 

E. All horizontal cabling from TO/WAO shall be terminated in a Category 6 RJ45‐100 patch panel  in  the  telecommunications  room  (TR).  This  portion  of  the  telecommunications wiring system that extends from the telecommunication outlet (TO) in the work area to the telecommunications wiring closet is considered the Horizontal Link.  

F. All Horizontal Links should be terminated  in a telecommunications room that  is on the same  floor. Ground  level  telecommunication outlets are  shown  to be  terminated  in a wall mounted  telecommunication  IT wall mount cabinet. DB Contractor  to coordinate with Amtrak IT department for the following design options (OR): 

i. Acceptable to have a wall mount cabinet on Ground Level of Station to connect to Telecommunication Room (TR)/Communication Room on Concourse Level.  

ii. Requirement for a dedicated Communication Closet on Ground Level of Station. 

iii. Acceptable  to  have  all  horizontal  links  routed  to  Concourse  Level Telecommunicaiton (TR) / Communication Room on Concourse Level. 

G. All Horizontal Links shall not exceed 90 meteres (295 feet). 

H. Quick‐Trak Kiosks are subject to Payment Card Industry Data Security Standard (PCI DSS) requirements.  Refer  to  Amtrak  Premise  Distribution  System  Standards  V1.0  Section 2.3.3 for requirements of these Telecommunication Outlets (TO). All cabling associated with these outlets shall be installed in rigid galvanized steel conduit. 

I. Telecommunication Outlets  (TO) should be provided at vending  locations as shown on the plans. These TOs shall follow the PCI DSS standards also. All cabling from these TOs should be coordinated with  the Telecommunication provider and  terminated near the demarcation point. TOs are provided  in the case that data connectivity are required at vending. All  cabling associated with  these outlets  shall be  installed  in  rigid galvanized steel conduit. 

Page 185: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐180 

Part 3 Project RequirementsJuly 18, 2013

 

 

J. Color coding of voice and LAN jacks shall be per the Amtrak Premise Distribution System Standards V1.0 

K. Labeling of all cabling shall be Amtrak Premise Distribution System Standards V1.0 

L. Listing of acceptable manufacturers  for cable,  jacks, patch panels and patch‐cords are listed in Amtrak Premise Distribution System Standards V1.0. 

M. All horizontal cable on the Concourse Level shall be comprised of a low‐smoke jacket to meet the intent of the wiring requirements of NPFA 130. 

E. Backbone Cable Distribution Systems 

A. Where Communication Closets are  located, utilize backbone  type cable distribution  to interconnect the Communication Closets to the Telecommunication Room (TR). 

B. Refer to Amtrak Premise Distribution System Standards V1.0for cabling specifications. 

C. All  Backbone  Cables  Distribution  Systems  shall  be  routed  in  rigid  galvanized  steel conduit. 

D. At a mimimum backbone cabling shall be: 

i. 50 pair of twisted shielded copper cabling 

ii. 24 strands of single mode fiber optic cable 

iii. 24 strands of multi‐mode fiber optic cable 

F. Temporary Station Telecommunication Design 

A. Coordinate  with  local  telecommunication  service  provider  for  service  to  Temporary Station  Trailers. Route  incoming  telecommunication  service  from  site  into designated demarcation point within trailers. 

B. Furnish and Install a wall mounted cabinet to house Amtrak provided active equipment (switch, server, router). 

C. Route  all  horizontal  cabling  from  Telecommunication  Outlets  to  wall  mounted  IT cabinet. Terminate all cables on approved patch panel and  label per AMTRAK PREMISE DISTRIBUTION SYSTEM STANDARDS V1.0. 

D. Provide a eight (8) foot by four (4) foot marine grade plywood backboard painted with three  (3)  coats of  fire  retardant white paint. Use  this  surface  to mount  any  required punchdown blocks or additional IT infrastructure that will not be housed within the wall mounted IT cabinet. 

G. Telecommunications  Room  (TR)  /  Communications  Room  shall  serve  as  the  main distribution center  for  telecommunication systems and  the gateway  to  the network.   This room will also house the Authority's future fiber optic transmission equipment.   It shall be furnished with but not be limited to the following: 

1. Provide Telephone Terminal Board on wall (labeled "AMTRAK‐Telephone") to terminate horizontal  telephone  cables  from  telephone/fax  sets, multi‐pair  riser  cables  between 

Page 186: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐181 

Part 3 Project RequirementsJuly 18, 2013

 

 

main  Communications  rooms  and  Communications  closets  and  between  main Communications rooms and Telco closet, and cables from zone paging speakers.  Install terminal boards on  the wall 24  inches above  the  finished  floor.   Provide an additional Telephone Terminal Board on wall (labeled "AMTRAK‐Fiber Optic") to terminate cables from  the  future authority's  fiber optic network.   Furnish and  install protection blocks, punch down blocks and cable rings as required for both terminal boards. 

2. Furnish and  install  three  (3) data cabinets, one  for data distribution and one  for data equipment  and  one  for  future  IT  components.  Use  the  data  distribution  cabinet  to terminate horizontal data cables from computer workstation outlets, vertical backbone multi‐pair  copper  and  fiber  optic  cables,  and  all  required  connectivity hardware/equipment. 

3. All walls shall be provided with marine grade plywood painted with  three  (3) coats of fire  retardant white paint. Plywood  shall extend  from one  (1)  foot above  the  floor  to nine (9) feet above the floor. 

4. All active  IT component/equipment  (servers, switches, routers, etc.) shall be  furnished and  installed  by Amtrak’s Network Operations Group  unless  noted  otherwise  on  the Contract Drawings. 

5. All  equipment  cabinets  shall  be  located  so  that  the  cabinet  front  and  rear meet  the requirements indicated in Amtrak Premise Distribution System Standards. 

6. Provide overhead cable  ladder system  inside the room above equipment cabinets and telephone terminal board for exposed cables run from/to equipment. 

7. Refer  to  Section  13  Electrical  Requirements,  for  details  regarding  the  dedicated electrical panel inside the main Communications room to feed dedicated panels and all dedicated  circuit  outlets  required  in  the Computer  room  and  Telco  room. All  circuits required  for  telecommunications  equipment  shall  be  connected  from  the  building's emergency  generator  and  UPS  system.    UPS  backed  electrical  panel  in  the communications rooms shall  feed only the equipment within the corresponding room. UPS backed panels feeding computer workstations outlets and other  loads outside the communication rooms shall not be installed inside the room. The outlets for telephone and paging equipment shall be installed on wall 18 inches above the finished floor below the telephone terminal board to feed the telephone switch and paging equipment. The electrical outlets for the data distribution and data equipment cabinets shall be installed at the inside bottom of each cabinet to feed power strips installed in the cabinet. 

8. Provide a telecommunications grounding system bus bar that is tied back to the nearest building's  electrical  grounding  system.    All  metallic  racks,  cabinets,  cable  ladders, raceways, Network/Telecommunications equipment shall be properly grounded as per TIA/EIA‐607, NEC codes (Articles 250 & 800). 

9. Provide  two  4‐inch  rigid  conduits  between  main  Communications  room  and  every Communications closet and Satellite communications room to  install backbone copper and multimode fiber cables. 

Page 187: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐182 

Part 3 Project RequirementsJuly 18, 2013

 

 

H. Passenger  Information  Display  System  (PIDS)  Server  Room  shall  serve  as  the  main distribution center  for PIDS systems and  the gateway  to  the network.   This room shall be designated as a Communication Closet and be connected to the Telecommunication Room (TR) with the necessary backbone cabling described above. It shall be furnished with but not be limited to the following: 

1. Furnish and install one (1) data cabinets for housing the PIDS video display drivers, patch panels  and  necessary  equipment  to  provide  an  active  electronic  signage  system throughout the station. 

2. All walls shall be provided with marine grade plywood painted with  three  (3) coats of fire  retardant white paint. Plywood  shall extend  from one  (1)  foot above  the  floor  to nine (9) feet above the floor. 

3. All  active  IT  component/equipment  (servers,  switches,  routers,  etc.)  shall  be coordinated with Amtrak’s preferred vendor. Refer  to Section 14.8 Digital Signage  for applicable details. 

4. All  equipment  cabinets  shall  be  located  so  that  the  cabinet  front  and  rear meet  the requirements indicated in Amtrak Premise Distribution System Standards. 

5. Provide overhead cable  ladder system  inside the room above equipment cabinets and telephone terminal board for exposed cables run from/to equipment. 

6. Refer  to  Section  13  Electrical  Requirements,  for  details  regarding  the  dedicated electrical panel inside the main Communications room to feed dedicated panels and all dedicated  circuit  outlets  required  in  the Computer  room  and  Telco  room. All  circuits required  for  telecommunications  equipment  shall  be  connected  from  the  building's emergency  generator  and  UPS  system.    UPS  backed  electrical  panel  in  the communications rooms shall  feed only the equipment within the corresponding room. UPS backed panels feeding computer workstations outlets and other  loads outside the communication rooms shall not be installed inside the room. The outlets for telephone and paging equipment shall be installed on wall 18 inches above the finished floor below the telephone terminal board to feed the telephone switch and paging equipment. The electrical outlets for the data distribution and data equipment cabinets shall be installed at the inside bottom of each cabinet to feed power strips installed in the cabinet. 

7. Provide a telecommunications grounding system bus bar that is tied back to the nearest building's  electrical  grounding  system.    All  metallic  racks,  cabinets,  cable  ladders, raceways, Network/Telecommunications equipment shall be properly grounded as per TIA/EIA‐607, NEC codes (Articles 250 & 800). 

I. Revenue  Server  Room  shall  serve  as  the  main  distribution  center  for  Quik‐Trak  Kiosk systems and the required electronic media revenue systems.  This room shall be designated as a Communication Closet and be  connected  to  the Telecommunication Room  (TR) with the  necessary  backbone  cabling  described  above.  It  shall  be  furnished with  but  not  be limited to the following: 

Page 188: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐183 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. Furnish and install one (1) data rack for housing the revenue equipment as required by Amtrak. 

2. All walls shall be provided with marine grade plywood painted with  three  (3) coats of fire  retardant white paint. Plywood  shall extend  from one  (1)  foot above  the  floor  to nine (9) feet above the floor. 

3. All  active  IT  component/equipment  (servers,  switches,  routers,  etc.)  shall  be coordinated with Amtrak’s preferred vendor. Refer  to Section 14.8 Digital Signage  for applicable details. 

4. All  equipment  cabinets  shall  be  located  so  that  the  cabinet  front  and  rear meet  the requirements indicated in Amtrak Premise Distribution System Standards. 

5. Provide overhead cable  ladder system  inside the room above equipment cabinets and telephone terminal board for exposed cables run from/to equipment. 

6. All electrical circuits shall be derived from the PIDS Server room adjacent to this room. 

7. Provide a telecommunications grounding system bus bar that is tied back to the nearest building's  electrical  grounding  system.    All  metallic  racks,  cabinets,  cable  ladders, raceways, Network/Telecommunications equipment shall be properly grounded as per TIA/EIA‐607, NEC codes (Articles 250 & 800). 

J. Elevator Control Rooms  

1. Furnish and install necessary cabling for elevator cab intercom. 

2. Coordinate call down number for elevator cab intercom. 

3. All walls shall be provided with marine grade plywood painted with  three  (3) coats of fire  retardant white paint. Plywood  shall extend  from one  (1)  foot above  the  floor  to nine (9) feet above the floor. 

K. Revenue  Server  Room  shall  serve  as  the  main  distribution  center  for  Quik‐Trak  Kiosk systems and the required electronic media revenue systems.  This room shall be designated as a Communication Closet and be  connected  to  the Telecommunication Room  (TR) with the  necessary  backbone  cabling  described  above.  It  shall  be  furnished with  but  not  be limited to the following: 

1. Furnish and install one (1) data rack for housing the revenue equipment as required by Amtrak. 

2. All walls shall be provided with marine grade plywood painted with  three  (3) coats of fire  retardant white paint. Plywood  shall extend  from one  (1)  foot above  the  floor  to nine (9) feet above the floor. 

3. All  active  IT  component/equipment  (servers,  switches,  routers,  etc.)  shall  be coordinated with Amtrak’s preferred vendor. Refer  to Section 14.8 Digital Signage  for applicable details. 

Page 189: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐184 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. All  equipment  cabinets  shall  be  located  so  that  the  cabinet  front  and  rear meet  the requirements indicated in Amtrak Premise Distribution System Standards. 

5. Provide overhead cable  ladder system  inside the room above equipment cabinets and telephone terminal board for exposed cables run from/to equipment. 

6. All electrical circuits shall be derived from the PIDS Server room adjacent to this room. 

7. Provide a telecommunications grounding system bus bar that is tied back to the nearest building's  electrical  grounding  system.    All  metallic  racks,  cabinets,  cable  ladders, raceways, Network/Telecommunications equipment shall be properly grounded as per TIA/EIA‐607, NEC codes (Articles 250 & 800). 

L. Submittals: The following is the minimum product data to be submitted: 

A. Category 6 cable 

B. Single‐mode fiber optic cable 

C. Multi‐mode fiber optic cable 

D. Category 6 patch panels 

E. Fiber optic patch panels 

F. Fiber optic cable terminations 

G. IT racks 

H. IT cabinets 

I. Data jacks 

J. Face plates 

14.4  Public Address System 

A. The  Public  Address  System  design  portrayed  on  the  Contract  Documents  provides  a representation of expected  layouts and  topology of  security  systems. DB Contractor  shall coordinate specific  requirements,  location of devices and  final configuration of all  system with Amtrak.  

B. Category Design,  furnish  and  install  paging  speakers  and  structured  cabling  to  support  a telephone  accessible  and  central  amplified  (70V)  zone  paging  system.    The  system  shall consist of the following: 

1. Provide overhead paging speakers throughout the facility and the roof area (indoor and outdoor  versions  as  required)  to  generate  at  least  15  dBA  signal  output  over  the ambient  noise.    Provide  all  required  speaker  brackets,  and  hardware  for  mounting speakers. Mount paging speakers on the lighting poles, in the car parking area.  

2. Ceiling paging speakers shall be provided with wall mounted volume control unit in the office  areas,  supervisors’  rooms,  lunch  rooms  and  conference  rooms.  Provide  all required brackets, back boxes and hardware for mounting speakers. 

Page 190: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐185 

Part 3 Project RequirementsJuly 18, 2013

 

 

3. Speakers  shall be  grouped  in  zones  and  cabling  to  zone  speakers  shall be distributed from  the  terminal  board  inside  the main  Communications  room  (see  Section  7.2.2).  Furnish  and  install  two  pair  cable  to  each  zone  speakers  and  terminal  blocks  to terminate zone speaker wiring.  Each zone speaker cable shall be tagged to identify the zone  and phasing on  the  cable  and  terminal block.  Speaker wiring/zoning  shall be  as follow: TBD 

4. Zone speakers wiring to the parking areas shall be provided with a wall mounted volume control unit mounted on the paging terminal board inside the Communications room. 

5. Determine  and  tap  the wattage  level  at  speakers  as  per  the  listening  area  coverage, ambient noise level in the listening area and speaker spacing. Provide design calculation documenting speaker wattage  tap, speaker quantity and power amplifier  requirement for each zone coverage.  

6. Paging shall be done using dedicated paging microphones and /or telephones.     

8. AMTRAK’s Telecommunications Services shall furnish and install zone paging controller, telephone  access paging module, paging  amplifiers,  and  telephone  switch. AMTRAK’s Telecommunications Services will program paging zones.  

C. Submittals: The following is the minimum product data to be submitted: 

1. Speakers 

2. Amplifiers 

3. Cabling 

4. Mounting brackets 

14.5  Fire Alarm System 

A. The  Fire  Alarm  System  design  portrayed  on  the  Contract  Documents  provides  a representation of expected  layouts and  topology of  security  systems. DB Contractor  shall coordinate specific  requirements,  location of devices and  final configuration of all  system with the local Fire Department.  

B. Provide a manual and automatic, zone coded and non‐zone coded supervised, addressable fire  alarm  and  detection  system  for  the  entire  building.  The  system  shall  have  alarm verification,  self‐checking  features,  voice  announcement,  and  equipment  for  future expandability and  central office  connection/equipment  for alarm  transmission  to  the Fire Department.  The  fire  alarm  system  shall  be  coded.  The  system  shall  be  designed  and installed in accordance with the latest National Fire Protection Agency (N.F.P.A.) codes, the New  York  State  Building  code  and  any  other  applicable  agencies  having  jurisdiction, including but not  limited  to  the AMTRAK Office of System Safety and  the Federal Transit Administration.  The  complete  fire  detection  and  alarm  system  shall  include  but  not  be limited to the following:  

Page 191: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐186 

Part 3 Project RequirementsJuly 18, 2013

 

 

1. Addressable Fire Alarm Control Panel(s) of the multiplex type system with the capability of sounding  fire alarms through  indicating devices and displaying alpha‐numeric alarm through a liquid crystal display, shutting down equipment and sufficient alarm points to individually  annunciate  the  activation  of  smoke  detectors,  duct  detectors,  heat detectors, manual pull stations, sprinkler water flow/valve tamper switches, and other initiation and supervisory devices. The main fire control panel shall be wall mounted in the Main  Lobby,  near  the main  entrance  of  the  facility where  accessible  by  the  Fire Department.  

2. Remote  annunciator  panels  shall  be  installed  in  24  hours manned  locations  and  at building entry point:  

3. An eight inch bell and three illuminated signs with 3 inch letter imprinted ("Fire”) to be installed at  the  top of main control panels and  remote annunciator panels  to  indicate alarms. Fire alarm sign shall be lit steady on fire alarm. The bell shall be activated for fire alarms.  

4. Provide  addressable  double  action  type manual  pull  stations.    These  units  shall  be installed  by  every  exit/entry  door  and  hallways  as  recommended  by  the  NFPA  72 guidelines. Each pull station shall be provided with protective cover, tamper‐proof clear polycarbonate shield and frame with horn.  

5. Provide  addressable  smoke/heat  detectors  of  the  photoelectric  type/  135oF  fixed temperature  type  respectively.  These  units  shall  be  installed  for  area  fire  detection. However final placing of these units shall be based on the type of ceiling, air movement, physical  obstacles,  etc  and  the  NFPA  72E  guidelines.  Provide  addressable  smoke detectors  in  Electrical  Distribution  Rooms/Closets,  Emergency  Generator  Rooms, Communications  Rooms/Closets,  Computer  Rooms,  Mechanical  Equipment  Rooms, Elevator Machine Rooms/Shafts/Lobbies, Battery Charging Rooms and Haz‐Mat Storage Building. Provide addressable heat detectors in areas where substances can rapidly burn and reach high temperatures. 

6. Provide  photoelectric  type  addressable  duct  smoke  detectors  for  HVAC  and  HRU system.    Duct  smoke  detectors  are  required  in  the  supply  side  of  supply  air  system greater  than 2000  cfm, and both  supply and  return  sides of  re‐circulating air handler system  greater  than  15,000  cfm.    Duct  smoke  detectors  shall  be  interlocked  to shutdown the associated HVAC and HRU equipment. 

7. Provide Water  flow switches of  the vane  type and pressure  type  for  the sprinkler and fire  pump  systems  (water  flow  alarms  and  high/low  pressure  indications).    Provide tamper switches where required. 

8. Provide horns/strobes and  strobes of  the wall or  ceiling mounted  type  in  compliance with  NFPA  72  guidelines.  The  horn/strobe  units  shall  incorporate  circuitry  for synchronized  strobe  flash. The  strobes  shall be  clear unfiltered or  clear  filtered white light. The horns shall be field programmable in order to provide multiple distinctive tone patterns (Code3 Temporal for fire alarms). 

Page 192: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐187 

Part 3 Project RequirementsJuly 18, 2013

 

 

9. Provide all required control relay modules to interlock re‐circulating air handler system equipment rated 15,000 cfm or greater, supply air system equipment rated 2,000 cfm or greater, exhaust  fans,  smoke hatches at  the  top of  the  shaft,  roll‐up doors, elevators, escalators,  other  systems  as  required  by  applicable  codes.  Coordinate  with Instrumentation and Controls for interlocking/shutdown.  

10. Provide monitor modules  to make  non‐addressable  devices  function  as  addressable devices, so that each field device and  its protection zone are properly  identified at the main  fire  alarm  control  panel.    The  main  fire  alarm  control  panel  shall  have  the capability  to  receive  and  annunciate  the  following  equipment/sub  system  panels indication signals:  

11. All  stand‐alone  fire  suppression  system  panels  indication  signals  (alarm,  trouble  and supervisory) 

12. Provide battery back up for the complete fire alarm system. The battery back‐up power supply shall be capable of operating  the system under normal  load  for a period of 24 hours followed immediately by a period of five minutes in alarm condition. 

C. Submittals: The following is the minimum product data to be submitted: 

1. Fire Alarm Control Panel 

2. Riser Diagram of all devices and wiring requirements. 

3. Manual pull stations 

4. Smoke detectors 

5. Heat detectors 

6. Annunciator Panels 

7. Horn‐Strobe devices 

8. Visual devices 

9. Fire Alarm cables. 

14.6  Digital Signage 

A. The DB Contractor shall coordinate with Amtrak for locations and quantity of digital signage and Passenger Information Display Systems (PIDS) to be installed at the Temporary Station and permanent Station.   

B. The DB Contractor shall contract with Amtrak’s preferred vendor for Passenger Information Display System (PIDS) through Amtrak’s Master Service Agreement.  

C. The DB Contractor will provide the necessary  infrastructure from the PIDS Server Room to locations of PIDS displays in the station (temporary and permanent) and the platform. 

D. The  DB  Contractor  will  coordinate  directly  with  Amtrak’s  preferred  vendor  to  quantify design  infrastructure  requirements  including: number of  conduits,  size of  conduits,  cable 

Page 193: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐188 

Part 3 Project RequirementsJuly 18, 2013

 

 

counts,  IT  rack  space  allocation,  power  requirements  and  all  appurtenances  to make  a cohesive solution. 

D. The DB  Contractor will  coordinate with  locations  of  digital  signage  to  provide  adequate infrastructure to each location. Coordinate data cabling quantity and sizes along with power requirements at each sign.  

E. Submittals: The following is the minimum product data to be submitted: 

1. Riser diagram of all signage and PIDS with cabling and power shown 

Page 194: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐189 

Part 3 Project RequirementsJuly 18, 2013

 

 

Facility Requirements 

14.1.1  Security System 

Design, furnish and install security system for the entire building, including integrated Access Control and Intrusion Alarm Monitoring, and Closed Circuit Television (CCTV) systems.  

The integrated access control and alarm monitoring system shall make access granted/denied decisions  to  restricted  areas  and  building's  perimeter/roof  doors,  define  time  zones  and access  levels/groups,  import/export  Amtrak's  employee  data  base,  detect  unauthorized entries within restricted areas and building's perimeter/roof doors, detect alarm points from motion detectors and dry contacts, generate reports of each alarm type, time and  location.  The  system  shall  also  interface  with  CCTV  system  for  alarm  recording  and  alarm  call‐up features.   The system shall include but not be  limited to the following devices, modules and equipment: 

Combined card reader and keypad with rain shield (as  indicated in Table (7‐1) [k1][SEA2]shall be provided  at  exterior  of  all  building's  perimeter  employee  entry/exit  doors,  stairwell entry/exit doors from roof, emergency exit doors, Employee Parking Area Entrance, outside of  main  communications  room,  all  communications  closets  and  computer  room  for authorized access.  The card reader shall be capable of reading the AMTRAK’s Employee Pass and  Identification  Card  (EPIC).    The  card  reader  installation  shall meet ADA  requirements.  Card readers for Employee Parking Area Entrance shall be  installed such that the driver will be  able  to  swipe his  EPIC  card  from his driving position.    The  card  reader  system  shall be interlocked with  the Semaphore arm  control units at  the Employee Parking Area Entrance, such  that  a  valid  swipe  shall  cause  the  corresponding  Semaphore  arm  to  open.  Provide Semaphore  arm  bypass  switches  in  the  Property  Protection  booths.  Coordinate  with Architectural,  Instrumentation  and  Controls,  and  Electrical  for motorized  Semaphore  arm requirements. 

Magnetic locks shall be provided at building's perimeter employee entry/exit doors, stairwell entry/exit doors and emergency exit doors where card readers are required.  Magnetic locks shall  be  released when  access  is  granted  by  the  system  from  card  reader,  request‐to‐exit device activation, electromechanical exit panic hardware in an emergency, or upon fire alarm system activation.  Coordinate with Architectural discipline for door hardware requirements. 

Push button and motion detector devices shall be provided for request‐to‐exit at  interior of all employee entry/exit doors (in  lobby and vestibules) and other doors where card readers are required, except stairwell doors and emergency exit doors. The push button  installation shall meet ADA requirements. 

Coordinate with Architectural discipline for provision of an electromechanical panic hardware and  a  sign  "AUTHORIZED  AND  EMERGENCY  EXIT  ONLY.    ALARM  WILL  SOUND  FOR UNAUTHORIZED USE" on every stairwell’s exit door and every emergency exit door  leading from building.   The panic hardware shall be  integrated with the access control and security 

Page 195: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐190 

Part 3 Project RequirementsJuly 18, 2013

 

 

alarm  system  for  providing  access  for  authorized  employees  egress  and  ingress  from  card readers installed both outside and inside of the building as well as allow immediate egress in an emergency.  A strobe shall be installed at the interior of emergency exit doors to indicate alarm  for  unauthorized  egress.    The  unauthorized  exit  alarm  signal  shall  also  be  remotely transmitted  to  the  alarm monitoring  system  inside  the  security  booth  and  CCTV  system indicated for alarm recording and alarm call‐up features. 

Magnetic door contacts shall be provided for door status and security alarm monitoring on all building's perimeter employee entry/exit doors,  stairwell entry/exit doors, emergency exit doors, and all interior doors of rooms with high security profiles. Magnetic door contacts for all building’s perimeter roll‐up doors are not required. 

Magnetic  door  contacts  installed  on  entry/exit  doors,  stairwell  entry/exit  doors  and emergency exit doors where card readers are required for building access and egress shall be connected  to  the  dual  card  reader  module.    All  other  magnetic  door  contacts,  motion detectors,  glass  sensors,  and  other  alarm  devices  shall  be  connected  to  the  input  control modules. Magnetic  door  contacts  installed  in  view  of  a  surveillance  camera  shall  also  be connected to CCTV system for alarm recording and alarm call‐up features.  

Provide motion detectors for security alarm monitoring in all storage rooms. 

Provide glass sensors for vision windows. 

Provide a head end lockable enclosure (in main Communications room) to house the system interface modules.    It  shall  house  the  dual  card  reader  interface modules,  input  control modules, output control modules, power supplies for interface modules and magnetic locks. The head end enclosure shall also house the  intelligent system controller  interface module, network  interface  module,  and  power  supplies  for  interface  modules.    Provide  required cabling between head end enclosure and the access control/alarm devices.  Tamper switches shall be provided on the head end enclosure. Tamper switch and power supply failure from enclosure shall be monitored by the system.  The access system controller shall be interfaced with the fire alarm system to allow egress in case of fire. 

Provide a database server/client workstation computer in the main communications room for the  security  alarms  and  access  controls  system.  The  database  server/client  workstation computers shall communicate with the AMTRAK’s employee database server  located at the ADDRESS TBD  for database synchronization and alarm/diagnostics reporting.   Provide WAN connections  between  ADDRESS  TBD  and  the  facility.  Provide  LAN  connections  for  client workstation computers, database server/client workstation computer and intelligent system controller  (head  end  enclosure)  in  the  facility.    Provide  required  software  for  the  security alarms and access controls system computers.   

Provide security workstation computer in TBD Rms. 

Provide alarm printers and a report printer inside the main communications room. 

Page 196: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐191 

Part 3 Project RequirementsJuly 18, 2013

 

 

The closed circuit television (CCTV) system shall include but be not limited to: 

Digital  color  video  cameras  in  housings  for monitoring  all  perimeter  entrances  and  areas vulnerable to intruders, as indicated on the conceptual drawings. Cameras shall be integrated with door alarm contacts for alarm recording and alarm call‐up features. Camera housings in the fuel area shall be the explosion proof type. 

Provide Pan/Tilt/Zoom digital cameras  in housings  in  front of  the building at  the employee parking area and on poles at the visitor parking area. Provide Pan/Tilt/Zoom digital cameras in housings in the maintenance area inside the facility on overhead tracks. 

Power  supply  for  the  cameras  shall provide  sufficient voltage and wattage at each  camera and  camera  indoor/outdoor housing  to operate properly.  It  shall  supply 24VAC and 28VAC with selectable output tap. It shall be equipped with a circuit breaker on each output for over current protection, with self‐reset when fault is corrected. Each camera shall be fed from an individual breaker on the power supply. 

The lens shall be a vari‐focal lens and equipped with auto iris.   The lens focal length and “f” stop shall be determined during the survey of camera locations. 

Survey and determine the exact location of each camera before installation to insure that the selected  location will provide optimum view of  the area  to be monitored. Coordinate  final locations with AMTRAK. 

Video matrix switcher equipment with alarm  inputs  (wiring  from security system alarm dry contacts for alarm recording and alarm call‐up features) and pan‐tilt‐zoom camera controller unit. It shall accommodate at least 256 cameras for current and possible future addition. 

All CCTV equipment (cameras, video switchers, video controllers and monitors) shall be from the same manufacturer. 

State of the art proven digital video recorder/server  in a  locked console cabinet  in the main Communications  room. The unit  shall be  capable of  recording and  storing  images, without human  intervention,  for 30 days. Provide a  flat screen monitor and LAN connection  for the digital video  recorder/server.   Provide  the  required  software  to  integrate with  the  security alarm  monitoring  and  access  control  system  computers  for  video  monitoring  and  alarm management. 

Provide a pull box with a 5 ft. of wire slack coiled inside, at each camera location. 

Design, furnish and  install networks connectivity and structured cabling facilities to support Telecommunication Systems (voice and data) requirements for the building.  Coordinate with the Authority's Telecommunications Services to provide the required "T1" lines, central office lines and public telephone services from the Telephone Company.  Approximately, a total of four  "T1"  lines will be needed  for  voice  and data  transmission over network between  the 

Page 197: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐192 

Part 3 Project RequirementsJuly 18, 2013

 

 

building  and  AMTRAK  Communications  Network.  The  design  shall  include  provisions  for continuation of communication services in case of "T1" or power failure.  

Provide a  separate "Telco Closet", a "Communications Room", and "Computer Room", and additional  "Communications  Closets"  as  needed  and  as  shown  on  the  drawings,  to  keep horizontal data cable length under 300 feet between each data outlet and its corresponding data cabinet.  

"Communications Room" shall serve as  the main distribution center  for  telecommunication systems and the gateway to the network.   This room will also house the Authority's  future fiber  optic  transmission  equipment.    It  shall  be  furnished with  but  not  be  limited  to  the following: 

Provide  Telephone  Terminal  Board  on  wall  (labeled  "AMTRAK‐Telephone")  to  terminate horizontal  telephone  cables  from  telephone/fax  sets, multi‐pair  riser  cables between main Communications  rooms  and  Communications  closets  and  between main  Communications rooms and Telco closet, and cables from zone paging speakers.  Install terminal boards on the wall 24 inches above the finished floor.  Provide an additional Telephone Terminal Board on wall  (labeled  "AMTRAK‐Fiber Optic")  to  terminate  cables  from  the  future  authority's  fiber optic network.   Furnish and  install protection blocks, punch down blocks and cable rings as required for both terminal boards. 

Furnish  and  install  two  (2)  data  cabinets,  one  for  data  distribution  and  one  for  data equipment.  Use  the  data  distribution  cabinet  to  terminate  horizontal  data  cables  from computer workstation outlets, vertical backbone multi‐pair copper and fiber optic cables, and all required connectivity hardware/equipment. 

Designate  a  floor  space  for  a  telephone  switch,  a  19"  paging  equipment  cabinet,  a  CCTV cabinet,  four 23"  fiber optic equipment cabinets, a storage cabinet, a desk and a chair. The communications room shall not be less than 450 sq. feet[k3]. 

LAN and wireless  switches, DSU’s and  routers  shall be  furnished and  installed by Amtrak’s Network Operations Group. 

All equipment cabinets shall be located so that the cabinet front and rear are a minimum of four  feet  from walls  and  the  cabinet  side  is  a minimum  of  two  feet  from  the  side wall, allowing easy access for equipment installation and maintenance on cabinets. 

Provide  overhead  cable  ladder  system  inside  the  room  above  equipment  cabinets  and telephone terminal board for exposed cables run from/to equipment. 

Refer  to  Section  13  Electrical  Requirements,  for  details  regarding  the  dedicated  electrical panel  inside  the main  Communications  room  to  feed  dedicated  panels  and  all  dedicated circuit  outlets  required  in  the  Computer  room  and  Telco  room.  All  circuits  required  for telecommunications equipment shall be connected from the building's emergency generator 

Page 198: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐193 

Part 3 Project RequirementsJuly 18, 2013

 

 

and UPS system.   UPS backed electrical panel  in the communications rooms shall  feed only the  equipment  within  the  corresponding  room.  UPS  backed  panels  feeding  computer workstations outlets and other loads outside the communication rooms shall not be installed inside the room. The outlets for telephone and paging equipment shall be installed on wall 18 inches above  the  finished  floor below  the  telephone  terminal board  to  feed  the  telephone switch  and  paging  equipment.  The  electrical  outlets  for  the  data  distribution  and  data equipment  cabinets  shall be  installed  at  the  inside bottom of  each  cabinet  to  feed power strips installed in the cabinet. 

Provide  a  telecommunications  grounding  system  bus  bar  that  is  tied  back  to  the  nearest building's electrical grounding system.   All metallic racks, cabinets, cable  ladders, raceways, Network/Telecommunications  equipment  shall  be  properly  grounded  as  per  TIA/EIA‐607, NEC codes (Articles 250 & 800). 

Provide  two  4‐inch  rigid  conduits  between  main  Communications  room  and  every Communications  closet  and  Satellite  communications  room  to  install  vertical  backbone copper and multimode fiber cables, as per drawings. 

Communications Closets shall serve as distribution centers for telecommunication system and shall be furnished with but not be limited to the following: 

Provide Telephone Terminal Boards on wall  to  terminate horizontal  telephone  cables  from telephone  sets,  multi‐pair  riser  cables  between  the  main  Communications  room  and Communications closets. Terminal boards shall be installed on wall 24 inch above the finished floor. 

Furnish and  install one  (1) data cabinet,  for data distribution and data equipment. Use  the data cabinet to terminate horizontal data cables from computer workstation outlets, vertical backbone  multi‐pair  copper  and  fiber  cables,  and  all  required  connectivity hardware/equipment. 

LAN and wireless switches, DSU’s, routers etc. shall be furnished and installed by the Amtrak Network Operations Group. 

Provide  overhead  cable  ladder  system  inside  the  room  above  equipment  cabinets  and telephone terminal board for exposed cables run from/to equipment. 

Refer  to  Section  13  Electrical  Requirements,  for  details  regarding  the  dedicated  electrical panels and all circuits required  for telecommunications equipment shall be connected  from building's emergency generator and UPS system. 

Provide a  telecommunications grounding bus bar  that  is  tied back  to  the nearest building's grounding  system.    All  metallic  racks,  cabinets,  cable  ladders,  raceways, Network/Telecommunications  equipment  shall  be  properly  grounded  as  per  TIA/EIA‐607, NEC codes (Articles 250 & 800). 

Page 199: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐194 

Part 3 Project RequirementsJuly 18, 2013

 

 

Computer Room shall be furnished with but not be limited to the following:  

Provide  required  data  cabling  to  the  data  distribution  cabinet  located  inside  the Communications rooms/closets. See Table 7.1[k4]. 

Furnish  and  install  a  file  server  cabinet.   Provide overhead  cable  ladder  system  inside  the room above file server cabinet for exposed cables run from/to equipment. 

Refer  to  Section  13  Electrical  Requirements,  for  details  regarding  the  two  (2)  dedicated 125VAC/20A quad outlets connected to the building’s UPS/Emergency Generator Power. The quad  outlets  shall  be  installed  at  the  inside  bottom  of  the  server  cabinet.  The  dedicated circuits shall be fed from the electrical panel inside the main communications room indicated in Section 14 Communication Requirements.  

Computers, file servers etc shall be furnished and installed by Amtrak. 

Telco Closet shall be furnished with but not be limited to the following: 

Provide  Telephone  Terminal Boards  (labeled  "Telco") on wall  to  terminate multi‐pair  riser cables between  the main Communications  room and Telco  room, and Telco's  feeder cables (both copper and fiber cables) from utility manhole.  

Provide 1‐100 pair cable  in rigid conduit and one empty 2  inch conduit for Telco's cable run between  terminal boards  inside Telco Closet and  the main Communications  room and  the satellite communications room, as shown on the drawings. 

Designate  a  floor  space  for  one  equipment  cabinet  (for  Hi‐Cap  and  POTS  multiplexer equipment) to be furnished and installed by the Telephone Company. 

Provide  overhead  cable  ladder  system  inside  the  room  above  equipment  cabinets  and telephone terminal board for exposed cables run from/to equipment. 

Refer  to  Section  13  Electrical  Requirements,  for  details  regarding  the  dedicated  outlets connected  from  the  building's  UPS/Emergency  Generator  system  for  Telco's  multiplexer equipment be  installed on  cabinet.    The dedicated  circuits  shall be  fed  from  the  electrical panel  inside  the  main  Communications  room  indicated  in  Section  14  Communication Requirements. 

Provide a  telecommunications grounding bus bar  that  is  tied back  to  the nearest building's grounding  system.    All  metallic  racks,  cabinets,  cable  ladders,  raceways, Network/Telecommunications  equipment  shall  be  properly  grounded  as  per  TIA/EIA‐607, NEC codes (Articles 250 & 800). 

Horizontal telephone cabling shall include but not limited to: 

Page 200: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐195 

Part 3 Project RequirementsJuly 18, 2013

 

 

Provide required horizontal telephones cables (Category 6 cables) from the Communications room/closet telephone terminal board to each outlet located at every workstation computer and telephone outlets as indicated in Table 7‐1[k5].   The horizontal telephone cables shall be terminated on RJ‐45 jacks. The telephone jacks shall be in color of Red. 

Provide emergency  type  telephone sets as needed and shown. Furnish and  install  required horizontal  telephones  cables  from  the  Communications  room/closet  telephone  terminal board to each emergency type telephone set.  See Table 7‐1[k6]. 

Provide  a  junction  box  and  empty  1‐inch  conduit  runs  from  the  Telephone  Company's demarcation board  inside Telco  room  to  the public pay  telephone  locations as  indicated  in Table  7‐1[k7].    Coordinate  with  architectural  work  for  locations  of  the  public  telephones.  Coordinate with electrical work to provide the required electrical outlets for ADA compliant pay  telephones.    The  Telephone  Company  shall provide  all  required  telephone  cables  and equipment. 

Provide  a  telephone  terminal  box  and  a  12  pair  cable  in  1  inch  conduit  run  to  every vending/kitchen  room  from  the  telephone  company's  demarcation  board  inside  the  Telco room for outside‐line telephone services to be used by the vendors.  

Provide telephone cables from the Communications room/closet telephone terminal board to the  locations  indicated  in Table 7‐1[k8]  for  remote monitoring of  system equipment  control panels such as HVCMS control system, and other systems, such as compressor, and generator. The  horizontal  telephone  cables  shall  have  10  foot  of  slack  cable  coiled  near  equipment control panels. 

Provide  telephone  cables  and outlets next  to  the  satellite  TV outlet  in  rooms  indicated  in table 7‐1 [k9]for satellite receiver programming. 

Horizontal data cabling shall include but not limited to: 

Provide required horizontal data cables (Category 6, 4‐ pair UTP plenum cable 23 AWG cables) from  Communications  room/closet  data  distribution  cabinets  to  every  desk  location  and workstation computer, and as  indicated  in table 7‐1[k10].   The horizontal data cables shall be terminated on RJ‐45  jacks, along with horizontal  telephone  cables  (indicated  in  Section 14 Communication  Requirements)  in  a  single  outlet.  The  data  jacks  shall  be  in  color  of  Blue. Refer  to  Section  13  Electrical  Requirements  for  details  regarding  dedicated  duplex  outlet (125VAC/20A,  1  PH,  IG)  at  each workstation  outlet  location.  Provide  electrical  outlets  fed from  a  UPS  backed  panel  for  computer workstations  in  every  office,  including  all  offices directed by Amtrak. 

Provide “KRONOS” data cabling for the Employee Timekeeping System (two Category 6 cables in 3/4  inch  conduit)  from Communications  room/closet data distribution  cabinets  to areas indicated  in table 7‐1[k11]. Each Category 6 cable shall be terminated  in a male RJ‐45  jack, to permit connection to "KRONOS" timekeeping unit supplied by the Authority.  The outlet box 

Page 201: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐196 

Part 3 Project RequirementsJuly 18, 2013

 

 

shall be  installed 51  inch above  the  finished  floor and next  to  the punch clock  indicated  in Section 7.9[k12].   Refer  to Section 13 Electrical Requirements  for details  regarding dedicated duplex outlet (125VAC/20 A, 1 PH, IG) in each "KRONOS" location indicated above from a UPS backed up electrical panel. 

Typically  at every desk or  computer workstation  location,  install  telephone  jacks  and data jacks in the same outlet box with a four‐port faceplate.   Unused port shall be provided with blank inserts.  

Provide  200  pair  vertical  backbone  telephone  cable  to  interconnect  the  main Communications room and each communications closet and 100 pair cables to  interconnect main Communications and Satellite communications rooms to Telco room. 

Provide  vertical  backbone  cables  (36‐strand  and  12‐strand multimode  plenum  Fiber Optic cable  50  Micron  50/125um)  to  interconnect  data  cabinets  inside  the  main/satellite Communications room and data cabinets inside each Communications closet. Also provide 25 pair copper cable to interconnect the data cabinets and telephone terminal boards inside the main Communications room and the satellite communications room. 

Provide  redundant connection  (1‐12 strand multimode plenum Fiber Optic cable 50 Micron 50/125um) from each communications closet, in the facility, to the building core, in the main communications room. 

Provide  four  Cat  6  4  pair  twisted  cables  from  each wireless  antenna  in  the  facility  to  the nearest communications closet. Locations of wireless antennas, shown on the drawings, are approximate. The final locations shall be determined in the field, after an approved wireless access points antenna survey. 

Provide data communication system as follows: 

The Design‐Builder shall  furnish and  install the cable  infrastructure work  for the data/voice system.  It  shall  consist  of,  but  not  be  limited  to:  data/voice  patch  panel,  data  equipment cabinets,  power  strips,  fiber  optic  cable  distribution  panels,  copper  cable  (CAT  6)  patch panels, connecting blocks, vertical/horizontal cable management system, cable  ladder/tray, empty shelves, data/phone jacks and computer workstation outlets.    

AMTRAK’s Network Operations Group shall furnish, install and configure all LAN and wireless switches, DSU’s, routers etc.    

Spacing  of  equipment  and  patch  panels  in  the  cabinet  shall  allow  for  proper  cable management.   Horizontal cable management shall be provided below every patch panel  in the cabinet.  

In  general,  every  computer  workstation  outlet  shall  be  terminated  with  data  horizontal cables from the data cabinet patch panels  located  inside each Communications room/closet 

Page 202: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐197 

Part 3 Project RequirementsJuly 18, 2013

 

 

throughout the facility.  If required by design, furnish and install a wall mounted data cabinet (E2‐WM‐SC‐362424‐RH‐PD‐BL by  the Copper B‐Line)  in an environmentally controlled office for  feeding computer workstation outlets exceeding  the 300  feet  limit  to  its corresponding data cabinet.   A 12‐strand multimode plenum  fiber optic backbone cable shall be provided and configured from the data cabinet to the main Communications room.   The remote data cabinet shall be provided with integral fan/filter, power strip, fiber patch panel, CAT 6 patch panel, horizontal cable management as required by the number of outlets to be fed) and all required mounting hardware.    

Provide communications system for Elevators.  The system shall consist of the following: 

Sound power telephones in elevator cab and Machinery room to provide communications for elevator maintenance force.  Sound power telephone jacks shall be installed in elevator cab, top of cab, pit and elevator machine room. 

Provide  an  ADA  compliant  recessed  speakerphone  inside  elevator  for  communication between elevator and the two 24 hour manned property protection and dispatcher offices for emergency passenger assistance.  Coordinate with the elevator cab manufacturer. 

Provide a telephone terminal box and 12 pair cable in 1‐inch conduit from elevator machine room to telephone terminal board  in Communications room. Make all required connections to  provide  communications  for  elevator  speakerphone  with  telephone  in  both  property protection booths. 

Design,  furnish  and  install  paging  speakers  and  structured  cabling  to  support  a  telephone accessible and central amplified  (70V) zone paging system.   The system shall consist of  the following: 

Provide  overhead  paging  speakers  throughout  the  facility  and  the  roof  area  (indoor  and outdoor  versions  as  required)  to  generate  at  least 15 dBA  signal output over  the  ambient noise.   Provide all  required speaker brackets, and hardware  for mounting speakers. Mount paging speakers on the lighting poles, in the car parking area.  

Ceiling paging speakers shall be provided with wall mounted volume control unit in the office areas, supervisors’ rooms, lunch rooms and conference rooms. Provide all required brackets, back boxes and hardware for mounting speakers. 

Speakers shall be grouped in zones and cabling to zone speakers shall be distributed from the terminal board inside the main Communications room (see Section 7.2.2).  Furnish and install two pair cable to each zone speakers and terminal blocks to terminate zone speaker wiring.  Each zone speaker cable shall be  tagged  to  identify  the zone and phasing on  the cable and terminal block. Speaker wiring/zoning shall be as follow: TBD 

Zone  speakers wiring  to  the parking  areas  shall be provided with  a wall mounted  volume control unit mounted on the paging terminal board inside the Communications room. 

Page 203: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐198 

Part 3 Project RequirementsJuly 18, 2013

 

 

Determine and tap the wattage level at speakers as per the listening area coverage, ambient noise level in the listening area and speaker spacing. Provide design calculation documenting speaker  wattage  tap,  speaker  quantity  and  power  amplifier  requirement  for  each  zone coverage.  

Paging shall be done using dedicated paging microphones and /or telephones.     

AMTRAK’s  Telecommunications  Services  shall  furnish  and  install  zone  paging  controller, telephone  access  paging  module,  paging  amplifiers,  and  telephone  switch.  AMTRAK’s Telecommunications  Services will program paging  zones as described    in  Section 7.6.3 and zone groups as follows: TBD 

Provide a manual and automatic,  zone coded and non‐zone  coded  supervised, addressable fire  alarm  and  detection  system  for  the  entire  building.  The  system  shall  have  alarm verification,  self‐checking  features,  voice  announcement,  and  equipment  for  future expandability  and  central  office  connection/equipment  for  alarm  transmission  to  the  Fire Department. The fire alarm system shall be coded. The system shall be designed and installed in accordance with the latest National Fire Protection Agency (N.F.P.A.) codes, the New York State Building code and any other applicable agencies having  jurisdiction,  including but not limited to the AMTRAK Office of System Safety and the Federal Transit Administration. The complete fire detection and alarm system shall include but not be limited to the following:  

Addressable Fire Alarm Control Panel(s) of the multiplex type system with the capability of sounding fire alarms through indicating devices and displaying alpha‐numeric alarm through a liquid  crystal display,  shutting down  equipment  and  sufficient  alarm points  to  individually annunciate  the  activation of  smoke detectors, duct detectors, heat detectors, manual pull stations,  sprinkler water  flow/valve  tamper  switches,  and  other  initiation  and  supervisory devices. The main fire control panel shall be wall mounted in the Main Lobby, near the main entrance of the facility where accessible by the Fire Department.  

Remote annunciator panels shall be installed in 24 hours manned locations: TBD, to provide information on fire alarms. 

An  eight  inch  bell  and  three  illuminated  signs with  3  inch  letter  imprinted  ("Fire”)  to  be installed at the top of main control panels and remote annunciator panels to indicate alarms. Fire alarm sign shall be lit steady on fire alarm. The bell shall be activated for fire alarms.  

Provide addressable double action type manual pull stations.  These units shall be installed by every exit/entry door and hallways as  recommended by  the NFPA 72 guidelines. Each pull station shall be provided with protective cover, tamper‐proof clear polycarbonate shield and frame with horn.  

Provide  addressable  smoke/heat  detectors  of  the  photoelectric  type/  135oF  fixed temperature type respectively. These units shall be installed for area fire detection. However final  placing  of  these  units  shall  be  based  on  the  type  of  ceiling,  air movement,  physical 

Page 204: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐199 

Part 3 Project RequirementsJuly 18, 2013

 

 

obstacles, etc and the NFPA 72E guidelines. Provide addressable smoke detectors in Electrical Distribution Rooms/Closets, Emergency Generator Rooms, Communications Rooms/Closets, Computer Rooms, Mechanical Equipment Rooms, Elevator Machine Rooms/Shafts/Lobbies, Battery Charging Rooms and Haz‐Mat Storage Building. Provide addressable heat detectors in areas where substances can rapidly burn and reach high temperatures. 

Provide  photoelectric  type  addressable  duct  smoke  detectors  for  HVAC  and  HRU  system.  Duct smoke detectors are required in the supply side of supply air system greater than 2000 cfm, and both supply and return sides of re‐circulating air handler system greater than 15,000 cfm.   Duct smoke detectors shall be  interlocked to shutdown the associated HVAC and HRU equipment. 

Provide Water  flow  switches of  the vane  type and pressure  type  for  the  sprinkler and  fire pump  systems  (water  flow  alarms  and  high/low  pressure  indications).    Provide  tamper switches where required. 

Provide horns/strobes and  strobes of  the wall or  ceiling mounted  type  in  compliance with NFPA 72 guidelines. The horn/strobe units shall incorporate circuitry for synchronized strobe flash. The strobes shall be clear unfiltered or clear filtered white light. The horns shall be field programmable in order to provide multiple distinctive tone patterns (Code3 Temporal for fire alarms). 

Provide  all  required  control  relay  modules  to  interlock  re‐circulating  air  handler  system equipment  rated  15,000  cfm  or  greater,  supply  air  system  equipment  rated  2,000  cfm  or greater,  exhaust  fans,  smoke  hatches  at  the  top  of  the  shaft,  roll‐up  doors,  elevators, escalators, other systems as required by applicable codes. Coordinate with  Instrumentation and Controls for interlocking/shutdown.  

Provide monitor modules to make non‐addressable devices function as addressable devices, so that each field device and its protection zone are properly identified at the main fire alarm control  panel.    The main  fire  alarm  control  panel  shall  have  the  capability  to  receive  and annunciate the following equipment/sub system panels indication signals:  

Fire pump controller system panel indication signals (power on, pump running, phase failure, phase reversal, fire pump on back up power) 

All  stand‐alone  fire  suppression  system  panels  indication  signals  (alarm,  trouble  and supervisory) 

Refer to Section 13 Electrical Requirements for details regarding fuse cut out box in Electrical room for fire alarm control panel.   The power shall be fed from a dedicated circuit from the ATS power system.   Fire alarm control panel shall monitor  indication of ATS power  failure. Coordinate with Electrical. 

Page 205: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐200 

Part 3 Project RequirementsJuly 18, 2013

 

 

Provide  battery  back  up  for  the  complete  fire  alarm  system.  The  battery  back‐up  power supply shall be capable of operating the system under normal  load for a period of 24 hours followed immediately by a period of five minutes in alarm condition. 

Furnish  and  install  portable  fire  extinguishers  throughout  the  building  as  per  NFPA  10 guidelines and UL standards. 

Provide 20 pounds multi‐purpose dry chemical portable fire extinguisher (rated 20A: 120BC), 15  pounds  carbon  dioxide  portable  fire  extinguisher  (rated  10B:C)  and  125  pounds multi‐purpose dry chemical wheeled fire extinguishers (rated 40A: 240BC) as required.  

20  pounds multi‐purpose  dry  chemical  portable  fire  extinguisher  shall  be  placed  for  each 1,250 sq. ft. of office space or fraction thereof and as many as needed throughout the facility to insure that a traveling distance not to exceed 75 feet between units.   

15 pounds carbon dioxide portable fire extinguisher shall be placed  in electrical distribution rooms,  instrumentation/control  rooms,  communications  rooms/closets,  computer  rooms, mechanical equipment rooms. 

Provide all  required mounting and  fastening materials.   Portable  fire extinguishers  shall be mounted so that the bottom of the extinguisher is at least 4 inches above finished floor and the top of the extinguisher is not more than 4 1/2 feet above finished floor.   

Portable  fire extinguishers  in office areas and corridors shall be  installed  in recessed break‐glass type cabinets. 

Provide  a  complete  synchronous  time  clock  system  throughout  the  facility, which  shall be synchronized  with  the  Universal  Time  Signal,  transmitted  by  the  National  Institute  of Standards  and  Technology  (WWV/WWVH  radio  broadcasting  system)  from  Colorado.  The system shall include but not be limited to the following: 

Clock  antenna  shall  be  installed  on  roof  parapet.  Antenna  coaxial  cable  (RG‐58)  shall  be installed in steel conduit from roof to master clock receiver. Antenna and coaxial cable shall be grounded as per NEC codes (Articles 250, 810 & 820). 

Master clock receiver shall be wall mounted inside the main communications room. 

Time control center unit shall be wall mounted inside the main communications room next to the master clock receiver.  Time control center unit shall include all required interface circuits boards, WWV  interface  board,  CPU  and  power  boards,  coded  and  impulse  boards.    Time control  center  unit  shall  synchronize  the  secondary  time  clocks  and  activate  the  audible signaling of all brakes at all shifts and other daily scheduled events. 

Synchronous secondary time clocks shall be wall mounted in locations as indicated in Table 7‐1[k13]. 

Page 206: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐201 

Part 3 Project RequirementsJuly 18, 2013

 

 

Time attendance recorders (punch clocks) shall be wall mounted outside of the TBD office. 

Provide one  (1)  electrical duplex  outlet  (125VAC/20A,  1 PH,  IG)  in  each  location  indicated above to power punch clock and "KRONOS" timekeeping units (as indicated in Table 7‐1[k14]) from an UPS backed Electrical panel.    "KRONOS"  timekeeping unit will be provided by  the Authority.  

Provide cards and card  racks  for all maintenance employees.   Time card  racks shall be wall mounted next to the time attendance recorders.   

Design,  furnish  and  install  structured  cabling  system  for  the  Direct  Broadcast  Satellite Television Distribution  System  at  a  TBD  location.  The  satellite  television  system  (dish  and receivers)  shall  be  installed  and  programmed  by  a  local  satellite  television  company  as arranged  by  the  Authority.  The  structured  television  cabling  and  equipment  used  in  the system  shall  support  satellite and  local broadcast TV  reception  (54 MHz  ‐ 2150 MHz),  shall provide acceptable signal  levels to every receiver  in the system and shall be  furnished with but not be limited to the following: 

Determine  a  location  to mount  the  antennas  on  the  roof  at  unobstructed  line‐of‐sight  to receive  the  best  signal  quality  of  Satellite  and  local  TV  broadcast.    Furnish  and  install  an outdoor TV antenna  (Terk, HDTV 60 or approved equal)  for  receiving  the off‐air broadcast VHF/UHF/HDTV local channels.   Provide mast and mast mounting hardware as required and fasten the antenna in a position that gives the best reception. The antenna shall be grounded as per NEC codes (Articles 250, 810 & 820).   

Provide  four  RG‐58  coaxial  cables  in  2  inch  conduit  up  to  roof  level  from  the  TBD Communication Closet and  terminate  conduit with a waterproof  junction box mounted on roof parapet, and seal all openings.   One RG‐58 coaxial cable shall be terminated directly to the clock antenna (indicated  in Section 7.9[k15]), one RG‐58 coaxial cable shall be terminated directly to the outdoor TV antenna and two RG‐58 coaxial cables shall have 10 feet coiled for future connection  to a dual output LNB  satellite dish.   Outdoor coaxial cables with ground wire shall be used between outdoor TV/Satellite antennas and multi‐switches, and shall be terminated with weatherproof male "F" type connectors (RCA #D905 or approved equal). 

All outdoor coaxial cables from the roof shall be grounded as per NEC codes (Articles 250, 810 & 820).  Provide required coax cable grounding blocks (RCA #D902 or approved equal) inside Communication Closet.  

Provide  four wall mounted dual  LNB/distribution multi‐switches  (RCA #D6530 or approved equal)  inside  the  TBD  Communication  Closet  to  serve  as  central  distribution  point.    Each multi‐switch  shall allow both Satellite and VHF/UHF  signals  to  travel down a  single  coaxial cable  up  to  four  satellite  receivers.    Furnish  and  install  three  4‐way  power  dividers  (RCA #D2471  or  approved  equal)  and  required  interconnect  coax  cables  connected  to  multi‐switches.  

Page 207: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐202 

Part 3 Project RequirementsJuly 18, 2013

 

 

Provide coaxial cables (RG‐58/U) home run from the central distribution point inside the TBD Communication  Closet  to  the  satellite  TV  receiver  locations  as  indicated  in  Table  7‐1[k16].  Every home run coaxial cable shall be terminated to a female‐female "F" type connector in a wall  outlet.  Furnish  and  install  a  diplexer  (RCA  #D926  or  approved  equal)  and  required interconnect coax cables connected between diplexer and wall outlet. 

Provide in‐line amplifiers (RCA #D903 or approved equal) at the beginning of each run of RG‐58  coaxial  cable  run  greater  than  100  feet  (between  outdoor  TV/Satellite  antennas  and central distribution point and between central distribution point and wall outlets).  

Install an electrical duplex outlet  (120 VAC, 20 A, 1 PH) next to satellite TV outlet  in rooms indicated  in  table  7.1  [k17]and  next  to  the  Central  Distribution  Point  in  the  TBD Communications  Closet  indicated  in  7.10.4  [k18]to  power  television/satellite  receiver equipment and multi‐switch distribution equipment.  

Install  a RJ‐45  telephone  outlet  next  to  satellite  TV  outlet  in  rooms  indicated  in  table  7.1 [k19]for satellite receiver programming. 

 14.2  General Requirements  

Provide all communications items of work required for the facility, including the following: 

Design,  furnish  and  install  various  communications  systems  as  listed  above  in  compliance with  all  applicable  state  and  national  electrical  codes,  current  industry  standards,  and electrical area classifications required under electrical description of work,  including but not limited to Underwriters Laboratories  Inc., National Fire Protection Association, NYS Building Code, NYS  Energy  Conservation  Construction  Code, American National  Standards  Institute, National Electrical Manufacturers Association, Federal  standards an Specifications, TIA/EIA‐568B and TIA/EIA‐607. The most stringent of the codes shall apply. 

Provide  all  necessary  work  for  integration  with  other  systems,  including  Mechanical, Instrumentation and Control, and Electrical. 

Provide all necessary wires and cables for complete and operational systems as required and recommended by the various manufacturers.  

Provide  all  necessary  cables  raceway  systems,  (rigid  conduit, messenger, metal  raceways, cable  ladders, cable  trays, etc.,) along  the horizontal and perpendicular  line of  the building and  at  a  height  so  as  not  to  obstruct  any  portion  of  a  window,  doorway,  stairway  or passageway  and  not  to  interfere with  operation  or  access  to  any mechanical  or  electrical equipment. Each system (Telephone/Data, Clock, Paging, CCTV, Security, and Fire Alarm) shall have  its  own  raceway  system.      120  volts  AC  power wires/cables  shall  be  installed  in  a separate conduit system.  Test all wires and cables installed. Tag all wires and cables. 

Page 208: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐203 

Part 3 Project RequirementsJuly 18, 2013

 

 

Provide a complete cable ladder system in Communications Rooms/Closets, Telco Room and Computer  Rooms  for  running  cables  within  these  enclosures.    Install  all  cables/wires  in concealed conduits/steel race ways in office areas. 

All conduits shall be hot dip galvanized steel, except as described in Section 7.11.7 [k20]below.  Conduit size smaller than 3/4 inch shall not be used and size smaller than 1 inch shall not be concealed.   

For  all  hazardous  (classified)  areas  use  threaded  rigid  galvanized  steel  conduits,  sealing fittings, sealing compound, explosion proof fittings and enclosures for all  installation within the classified area above finished floor and 18 inches below the ceiling as required for Class 1, Division  1,  NEMA  7,  Group  D  in  accordance with  the  National  Electrical  Code  (NFPA  70) specifically Article 510.   The explosion proof  requirements will not apply  for non essential Communications system equipment (paging and clock).  

For  all wet  areas,  all  threaded  rigid  galvanized  steel  conduits,  boxes  and  fittings  shall  be coated with polyurethane (Rob Roy). 

For  the  office  areas  with  hung  ceiling,  electrical metallic  tubing  (EMT)  with  compression fittings and stamped steel boxes shall be used in plenum area. 

Follow  the  electrical  classified  areas  requirements  specified  in  Section  13  Electrical Requirements. 

Provide readily visible signs for fire alarm devices hidden above hung ceiling for maintenance purposes. 

Perform all tests on the installed systems to verify their proper operation and the integrity of each of their elements and their compliance with applicable codes. 

Install all equipment in a readily accessible location for maintenance. 

All equipment provided shall have 50 percent spare inputs available for future expansion. 

Provide As‐Built drawings, manuals, programming and training on the installed systems. 

There shall be no gas piping, water piping, sprinkler piping, drainage piping or drains  in the main  Communications  room,  the  Communications  closets,  the  Computer  room,  and  Telco room. 

SECTION 15   INSTRUMENTATION AND CONTROLS REQUIREMENTS 

Page 209: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐204 

Part 3 Project RequirementsJuly 18, 2013

 

 

15.1  Building Management System (BMS) (DfE) 

A. The  system  shall  incorporate Direct Digital Controllers  (DDC),  centralized monitoring  and control  functions and  shall also  interface with  the  facility  fire alarm  system.   The  system shall consist of the following elements: 

1. Microprocessor based controllers,  interfacing directly with  local sensors and actuators for  the  control and monitoring of HVAC and  Lighting  Systems  throughout  the  facility. The BMS  shall also monitor  the  systems as outlined  in  the BMS Monitoring Overview section below. The BMS shall also have Energy Management capabilities.   

2. All  controllers  shall  be  networked  providing  bi‐directional  communication  with  the Building Management System Workstation (BMS‐WS).  

3. The BMS shall include a remote alarm monitoring display. Locally detected alarms shall be displayed and printed on the local monitor and retransmitted to the remote display.  

B. BMS Monitoring Overview  

1. Electric Distribution System 

2. Emergency Generator System 

3. Fire Alarm System 

4. Elevator System 

5. Escalator System 

6. Compressed Air System 

7. Facility Air Curtains 

8. Heat Recovery Units (HRU’s) 

C. Heating Ventilating Air Conditioning (HVAC) Units 

1. All HVAC Units shall be provided with “Hand‐Off‐Auto” selector switches mounted on  the  unit.   With  the  switch  in  the  “Auto”  position,  the  unit will  automatically function to produce the requested air discharge temperature.  This temperature set point will be selected from the BMS by the system operator and be transmitted to the locally mounted HVAC controller via the BMS network. 

2. A low temperature safety thermostat shall be provided to stop the operation of the supply fan and close all dampers, whenever a temperature of 40 degrees Fahrenheit or below is sensed downstream of the furnace. 

3. Each  HVAC  unit  shall  be  automatically  shutdown  due  to  high  or  low  supply  air temperature or a high smoke condition.  Addressable smoke detectors shall be used for smoke detection. These conditions shall also be annunciated through the BMS‐WS  display.  A  differential  pressure  switch  shall  be  provided  for  each  system  to monitor air filter condition.  A high‐pressure differential shall be annunciated on the BMS‐WS display.  

Page 210: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐205 

Part 3 Project RequirementsJuly 18, 2013

 

 

D. Ventilation Fans (VF) 

1. Ventilation Fans shall be controlled by the BMS. Each ventilation fan starter shall be provided with a Hand‐OFF‐Auto selector switch and a speed selector switch.  In the “Auto” position,  the  fans shall be controlled by  the BMS, and  the “Hand” position shall be used for local operation.  The “manual” speed selector switch shall function only  in  the  “Hand”  position.    In  the  “Auto”  position,  the  BMS  shall  control  the starting, stopping, and the speed of that fan. 

2. Each  starter  shall  be  equipped  to  provide  status  (ON/OFF)  and  speed  (High/Low) indications to the BMS.  The BMS shall turn on the associated Ventilation Fan when a Heat Recovery Unit (HRU) turns on, and shall select the speed of the Ventilation Fan (High/Low) to match the fan speed of the HRU. 

E. Exhaust Fans (EF) 

1. Each EF shall be provided with “Hand‐Off‐Auto” selector switch located at the motor starter.    With  the  switch  in  the  “Auto”  position,  the  EF  shall  be  operated  in accordance with the facility’s normal operating procedure. 

2. The local controllers for the EF shall be networked to the BMS. 

F. Safety Interlocks ‐ Provide electrical safety interlocks to interface with the fire alarm system to  shut down heating, ventilation and air  conditioning  systems and associated motorized dampers. Battery chargers shall also be electrically interlocked, preventing operation when the battery charging area ventilation system  is not  functioning. Each safety  interlock shall include  all  enclosures,  relays  and  associated  components  necessary  provide  a  fully integrated system. 

G.A. Air‐Curtain  Monitoring  ‐  Facility  Air‐Curtains  shall  be  monitored  by  the  BMS  for associated hand‐off‐auto (H‐O‐A) control switch position as well as on/off and failure status. All  alarm  conditions  and  statuses  shall  be  generated  at  the  BMS‐WS.  Sensors  shall  be provided to monitor fan airflow, motor current and Air‐Curtain discharge air temperature. 

SECTION 15.  SECURITY REQUIREMENTS 

15.1  Facility Requirements 

The Design Builder (DB) must adhere to the following criteria encompassing the work required to design, furnish, install and test/commission the following systems; 

• Video Surveillance Systems  • Physical Accesss Control System 

The work  required under  this  section  is applicable  to  the Temporary Station Trailers and  the final Station configuration for Phase I and II. 

Before  commencing  on  the  design  and  installation  of  any  work  in  this  section,  the  DB Contractor shall meet with the proper agency  (Fire Department, Amtrak  IT, Amtrak Police) to 

Page 211: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐206 

Part 3 Project RequirementsJuly 18, 2013

 

 

coordinate  the  location  of  devices  and  infrastructure  and  ensure  compliance  to  referenced Amtrak standards. 

15.2   Standards and Codes 

Amtrak Premise Distribution System Standards V1.0 

Amtrak Police Department ‐ Corporate Security Standard Design Practice 2011 

Amtrak Engineering Stations Standard Design Practices (SDP) June 2012 

ANSI TIA/EIA‐568 

NFPA 70 – National Electrical Code 2011 

NFPA 72 – National Fire Alarm and Signaling Code 

15.3  Video Surveillance System 

A. Design,  furnish  and  install  security  components  in  accordance  with  Amtrak  Police Department  ‐  Corporate  Security  Standard  Design  Practice  and  as  coordinated with  the Amtrak Police Department.  

B. The  Video  Surveillance  System  design  portrayed  on  the  Contract  Documents  provides  a representation of expected  layouts and  topology of  security  systems. DB Contractor  shall coordinate specific  requirements,  location of devices and  final configuration of all  system with Amtrak and Trailways.  

C. All camera locations shall provide unobstructed view of expected scenes. The DB Contractor shall coordinate locations of cameras with Amtrak Police.   

D. Camera Location Survey:   

1. The DB Contractor shall be responsible to ensure that the selected camera locations will provide the optimum display of viewing area.  

 2. The DB Contractor shall submit for review a template form of the expected site survey 

indicating location, types of equipment used and views.  3. The  DB  Contractor  is  to  conduct  a  site  survey  in  the  presense  of  the  Engineer  and 

Amtrak Police after substantial completion of construction of designated areas using a portable  camera with  lenses  to  replicate  specified  camera  and  lenses.  The  specified lighting  and  signage  for  area  being  monitored  shall  be  installed  when  survey  is performed. 

  

Page 212: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐207 

Part 3 Project RequirementsJuly 18, 2013

 

 

4. The views for the survey shall be single views for fixed cameras and four (4) views at 0, 90,  180,  270  degree  increments  on  the  aiming  angle  specified  during  the  survey  by Amtrak Police for pan‐tilt‐zoom cameras. 

 5. Where  site cameras are  to be pole mounted,  the DB Contractor  shall utilize a bucket 

truck to provide the required height of the specified pole mounted camera.  

E. Camera  Types:  Camera  types  shall  be  per  the  Amtrak  Police  Department  ‐  Corporate Security Standard Design Practice. The DB Contractor shall coordinate all locations for fixed, pan‐tilt‐zoom  (PTZ),  long  distance    and wide‐area/high  resolution  cameras with  Amtrak Police  

F. Camera Recording: Recoding of camera outputs shall be per the Amtrak Police Department ‐ Corporate Security Standard Design Practice. The DB Contractor shall provide calculations to support size of network storage media  

G. Integration with Physical Access Control System: Where required by Amtrak, cameras shall be interconnected to the locations secured by the Physical Access Control System to provide surveillance of secured doors and areas.  

H. Raceways:  All  Video  Surveillance  System wiring  shall  be  routed  in  rigid  galvanized  steel conduit. All junction boxes associated with the Video Surveillance System shall have tamper resistant hardware.  

I. Video Surveillance Power Supplies  

1. Power Over Ethernet (POE): For cameras utilizing power over ethernet (POE), head end ethernet  switch  shall  be  rack mounted  and  capable  of  providing  necessary  power  to cameras.  

2. Low‐Voltage  Power  Supply  (12V  or  24V):  For  cameras  utilizing  low‐voltage  power supplies (12V or 24V), the power supply shall be:  a. Rack mounted  

 b. 120V 60 Hertz input 

 c.  Minimum of sixteen (16) Class 2 PTC protected circuits with screw post terminals 

 

J. Submittals: The following is the minimum product data to be submitted: 

1. CCTV Site Survey form 

2. CCTV Site Survey results 

Page 213: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐208 

Part 3 Project RequirementsJuly 18, 2013

 

 

3. Cameras 

4. Mounts 

5. CCTV Cabling Riser Diagram  – Depicting  all  cameras with  video wiring  and power wiring defined. 

6. Digital Video Recorders 

7. Power Supply 

15.4    Physical Access Control System 

A. Design,  furnish  and  install  security  components  in  accordance  with  Amtrak  Police Department  ‐  Corporate  Security  Standard  Design  Practice  and  as  coordinated with  the Amtrak Police Department.  

B. The Physical Access Control System design portrayed on the Contract Documents provides a representation of expected  layouts and  topology of  security  systems. DB Contractor  shall coordinate specific  requirements,  location of devices and  final configuration of all  system with Amtrak and Trailways.  

C. The  integrated  access  control  and  alarm  monitoring  system  shall  make  access granted/denied  decisions  to  restricted  areas  and  building's  perimeter/roof  doors,  define time zones and access  levels/groups,  import/export Amtrak's employee data base, detect unauthorized  entries within  restricted  areas  and  building's  perimeter/roof  doors,  detect alarm points from motion detectors and dry contacts, generate reports of each alarm type, time and  location.   The  system  shall also  interface with CCTV  system  for alarm  recording and alarm  call‐up  features.   The  system  shall  include but not be  limited  to  the  following devices,  modules  and  equipment  as  prescribed  in  the  Amtrak  Police  Department  ‐ Corporate Security Standard Design Practice: 

 

1. Card readers  

2. Magnetic locks  

3. Door switches  

4. Push buttons 

5. Motion Detectors 

6. Intelligent System Controllers 

7. Dual Reader Controllers (DRIM) 

D. Refer to Amtrak Police Department ‐ Corporate Security Standard Design Practice for typical arrangement of electric door hardware  configurations  (#1  through #21). Where designed door configuration does not apply to typical arrangements, coordinate with Amtrak Police for proposed arrangement of devices. 

Page 214: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐209 

Part 3 Project RequirementsJuly 18, 2013

 

 

 E. The Intelligent System Controller (ISC), Dual Reader Controllers (DRIMs) and power supplies 

shall be  installed  in a  lockable  sheet  steel NEMA 1 enclosure within  the Communications Room. 

 F. Coordinate  with  Architectural  discipline  for  provision  of  an  electromechanical  panic 

hardware and a sign "AUTHORIZED AND EMERGENCY EXIT ONLY.  ALARM WILL SOUND FOR UNAUTHORIZED USE" on every stairwell’s exit door and every emergency exit door leading from building.  The panic hardware shall be integrated with the access control and security alarm system  for providing access  for authorized employees egress and  ingress  from card readers installed both outside and inside of the building as well as allow immediate egress in  an  emergency.   A  strobe  shall  be  installed  at  the  interior  of  emergency  exit  doors  to indicate  alarm  for unauthorized egress.    The unauthorized exit  alarm  signal  shall  also be remotely  transmitted  to  the alarm monitoring system  inside  the security booth and CCTV system indicated for alarm recording and alarm call‐up features.  

G. All wiring  associated with  the  Physical  Access  Control  System  shall  be  installed  in  rigid galvanized steel conduit. 

 H. Door  contacts  shall  be  provided  for  door  status  and  security  alarm  monitoring  on  all 

building's perimeter employee entry/exit doors, stairwell entry/exit doors, emergency exit doors, and all interior doors of rooms with high security profiles. Magnetic door contacts for all building’s perimeter roll‐up doors are not required.  

I. Provide a database server/client workstation computer  in the main communications room for the security alarms and access controls system. The database server/client workstation computers shall communicate with the AMTRAK’s employee database servers for database synchronization and alarm/diagnostics reporting.  

 J. DB Contractor to integrate Station security system to Amtrak WAN security system. 

 K. Provide required software for the security alarms and access controls system computers.   

 L. Provide security workstation computer. 

 M. Provide alarm printers and a report printer inside the main communications room. 

N. Submittals: The following is the minimum product data to be submitted: 

1. Card readers  

2. Magnetic locks  

3. Door switches  

4. Push buttons 

Page 215: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐210 

Part 3 Project RequirementsJuly 18, 2013

 

 

5. Motion Detectors 

6. Intelligent System Controllers 

7. Dual Reader Controllers (DRIM) 

8. Power Supply 

9. Riser Diagram indicating all doors, devices and wiring requirements. 

SECTION 156. FACILITY PARKING AND TRAFFIC REQUIREMENTS  

156.1  Parking 

The Design‐Builder shall provide short‐term parking for parcel and passenger drop‐off and pick‐up. Paid and  secure parking  lots  including accessible parking  shall be  constructed  in Phase  I, with a goal of 257 parking spaces at the conclusion of Phase II per Amtrak 30 year projections.   Phase I shall include the construction of a parking area that will become the future Phase II bus loop.  

Vehicular Parking  shall  consist of  standard nine  foot by nineteen  foot  stalls, oriented at 90°. Accessible  parking  spaces,  with  van  accessibility  shall  be  provided.    A minimum  of  fifteen employee  spaces  for  Amtrak  and  Trailways  shall  be  differentiated;  the  Design‐Builder  shall coordinate with  both  Amtrak  and  Trailways  for  final  employee  parking  counts.    Pedestrian walkways shall  link the parking  lot to station building,  including traffic calming speed tables at major crossing points.   

156.2  Pay Stations 

The Design‐Builder  shall  install accommodations  for  three parking pay  stations at  the  station building, visible from the street.   This  includes two standard pay stations, one ADA height pay station.   The pay  stations are  to be  located against an exterior wall, away  from  free  flowing pedestrian  traffic but  in  the  same general area.   Pay  stations  shall be  spaced  such  that each station can be opened for fee collection.   Amtrak and  its parking management company shall provide the pay station equipment, perform the connections to the pay station, and perform all testing.    The  Design‐Builder  is  responsible  for  providing  and  installing  the  infrastructure, including conduits and wiring, for the pay stations and coordinating the hookup arrangements. 

The  Design‐Builder  shall  also  provide  and  install  gate  arms  as  indicated  on  the  Preliminary Design plans, including: 

A. Conduit and pull string to the gate arm locations 

B. Loop detector and necessary conduit connections for future use with the gate arm 

No other equipment is necessary for initial construction. 

156.3  Bus Access 

Bus berths for five forty‐five foot long intercity buses with two spaces for additional berths for overnight bus parking are programmed  into the site.   The bus  loop shall have separate access 

Page 216: Rochester Station Project DB CONTRACT DOCUMENTS PART ... · Rochester Station Project Part 3‐2 Part 3 Project Requirements July 18, 2013 2.1 Scope An essential component of the

 

Rochester Station Project Part 3‐211 

Part 3 Project RequirementsJuly 18, 2013

 

 

from the street with a minimum driveway width of thirty feet and turning radii of at least forty‐two  feet.    Sufficient  space  is  required  beneath  the  canopy  for  five  buses.    Two  additional layover  spaces  shall  be  accommodated  within  the  bus  loop  for  waiting  and  overnight  bus parking.    Finally,  two on‐street parallel bus bays  shall be provided  for RGRTA buses  to  stop, board, and alight passengers without obstructing a travel  lane.   These bays shall be  located at North Clinton and Joseph Avenues and shall provide level and accessible boarding.  The Design‐Builder shall provide bus shelters at each bus stop location. 

156.4  Accommodations for Bicylists 

To  accommodate  bicycle  riders,  the  Design‐Builder  shall  reference  the  City  of  Rochester’s Bicycle Equipment Standards.   U‐shaped bike  racks with space  for a minimum of  twenty  (20) bicycles shall be installed beneath the bus boarding area canopy, as well as at the bus shelters adjacent to the RGRTA bus berths at North Clinton and Joseph Avenues, each with space for a minimum of ten (10) bicycles.   A minimum of ten (10) Bicycle bicycle  lockers shall be  installed beneath  the Phase  II bus canopy, as well as a  tamper‐resistant public bicycle work stand and separate public bicycle pump. 

SECTION 16. FRA TIGER Grant Submittal Requirements 

The  Design  Builder  shall  prepare  the  following  submittal  requirements  to  be  provided  by NYSDOT to the FRA: 

A. Final Staging Plan B. Station Building Final Design  C. Platform Final Design D. Tunnel Final Design E. Track Final Design 

The  Design  Builder  shall  work  cooperatively  with  NYSDOT  in  resolving  FRA  comments  on submittal requirements listed in Section 16.