robustness of steel framed buildings with pre-cast

203
THE UNIVERSITY OF MANCHESTER ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST CONCRETE FLOOR SLABS A thesis submitted to the University of Manchester for the degree of Doctor of Philosophy in the Faculty of Engineering and Physical Sciences 2014 Seyed Mansoor Miratashiyazdi School of Mechanical, Aerospace and Civil Engineering

Upload: others

Post on 19-Feb-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

THE UNIVERSITY OF MANCHESTER

ROBUSTNESS OF STEEL FRAMED

BUILDINGS WITH PRE-CAST

CONCRETE FLOOR SLABS

A thesis submitted to the University of Manchester for the degree of

Doctor of Philosophy

in the Faculty of Engineering and Physical Sciences

2014

Seyed Mansoor Miratashiyazdi

School of Mechanical, Aerospace and Civil Engineering

Page 2: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

2

Table of Contents

List of Figures .............................................................................................................. 7

List of Tables.............................................................................................................. 11

Abstract ...................................................................................................................... 12

Declaration ................................................................................................................. 13

Copyright ................................................................................................................... 14

Acknowledgements .................................................................................................... 15

Chapter 1. Research Background........................................................................... 16

1.1 Structural Robustness .................................................................................. 16

1.2 Research Originality .................................................................................... 18

1.3 Research Objectives .................................................................................... 19

1.4 Research Methodology ................................................................................ 20

1.5 Thesis Structure ........................................................................................... 20

Chapter 2. Literature Review ................................................................................. 22

2.1 Major Accidents of Progressive Collapse ................................................... 22

2.1.1 Ronan Point Building ........................................................................... 22

2.1.2 Alfred P. Murrah Federal Building ...................................................... 26

2.2 Building Codes and Regulations on Robustness of Structures ................... 28

2.2.1 Implementation of the robustness requirements .................................. 32

2.2.1.1 Application of the Tying Force Method to Precast Reinforced

Concrete Structures ......................................................................................... 35

2.3 Research on Structural Tying System of PCFS ........................................... 36

2.3.1 Bending Tests on Tie Connections ...................................................... 37

2.3.2 Formulation of Tie Behaviour in Bending ........................................... 39

2.4 Construction Technology of PCFS .............................................................. 42

2.4.1 Design of PCFS .................................................................................... 43

2.4.1.1 Flexural capacity .............................................................................. 43

2.4.1.1.1 Serviceability limit state (SLS) ................................................... 43

Page 3: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

3

2.4.1.1.2 Ultimate limit state of flexure ..................................................... 44

2.4.1.2 Shear capacity of PCFS .................................................................... 45

2.4.2 PCFS Manufacturing ............................................................................ 46

2.5 Providing Tying Resistance in Precast Concrete Floor Slabs ..................... 49

2.5.1 Precast Concrete Floor Slabs ............................................................... 49

2.5.1.1 Hollowcore floor units ...................................................................... 49

2.5.1.2 Solid precast floor units .................................................................... 50

2.5.2 Connections of precast concrete floor slabs ......................................... 50

2.6 Bond-Slip ..................................................................................................... 51

2.7 Summary and Objectives of Research ......................................................... 55

Chapter 3. Validation of Numerical Modelling ..................................................... 57

3.1 Choosing DIANA FE Package .................................................................... 57

3.2 Modelling concrete in DIANA .................................................................... 58

3.2.1 Compressive Behaviour ....................................................................... 59

3.2.1.1 Tresca ............................................................................................... 59

3.2.1.2 Von-Mises ........................................................................................ 59

3.2.1.3 Mohr-Coulomb ................................................................................. 60

3.2.1.4 Drucker-Prager ................................................................................. 60

3.2.2 Tensile Behaviour ................................................................................ 61

3.2.2.1 Brittle Cracking ................................................................................ 61

3.2.2.2 Linear Tension Softening ................................................................. 62

3.2.2.3 Moelands Tension Softening ............................................................ 63

3.2.2.4 Hordijk Tension Softening ............................................................... 63

3.2.3 Bond-Slip ............................................................................................. 65

3.2.4 Concrete Elastic Material Properties .................................................... 66

3.2.4.1 Tensile Strength ................................................................................ 66

3.2.4.2 Elastic Modulus ................................................................................ 67

3.3 Axially Restrained Beams (Su et al., 2009) ................................................ 67

3.3.1 Test Subassemblies & Setup ................................................................ 68

3.3.2 Typical Beam Behaviour to Reach Catenary Action ........................... 71

Page 4: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

4

3.3.3 Finite Element Model ........................................................................... 72

3.3.4 Comparison between Simulation and Test Results .............................. 74

3.4 Verification of Bond-Slip Modelling .......................................................... 78

3.4.1 Test Specimens and Variables ............................................................. 78

3.4.2 Finite Element Model ........................................................................... 80

3.4.3 Comparison between Simulation and Test Results .............................. 82

3.5 Summary ..................................................................................................... 85

Chapter 4. Parametric study of 2D Restrained Slab .............................................. 86

4.1 Illustrative behaviour ................................................................................... 87

4.1.1 Slab with total axial restraint................................................................ 87

4.1.2 Slabs with Elastic Axial Restraint ........................................................ 94

4.1.3 Slabs with Partial Tie Bar .................................................................... 98

4.2 Accidental Load Calculation ..................................................................... 101

4.3 Parametric Study ....................................................................................... 102

4.3.1 Height of the Slab............................................................................... 103

4.3.2 Slab Span ............................................................................................ 107

4.3.3 Tie Bar Length ................................................................................... 107

4.3.4 Tie Bar Height .................................................................................... 110

4.3.5 Tie Bar Diameter ................................................................................ 112

4.3.6 Tie Bar Yield Stress ........................................................................... 114

4.3.7 Grouting Concrete Strength ............................................................... 115

4.3.8 Ultimate Strain of the Steel Tie Bar ................................................... 116

4.3.9 Summary ............................................................................................ 117

Chapter 5. 2D Slab Analytical Load-Displacement Relationship ....................... 119

5.1 Development of the Analytical Relationship ............................................ 119

5.1.1 Axially Restrained Slabs .................................................................... 119

5.1.2 Elastic Axially Restrained Slabs ........................................................ 121

Page 5: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

5

5.2 Maximum Slab Displacement ................................................................... 123

5.2.1 Slab Height ......................................................................................... 126

5.2.2 Tie Bar Diameter ................................................................................ 127

5.2.3 Tie Bar Position ................................................................................. 128

5.2.4 Ultimate Strain of the Steel Tie Bar ................................................... 130

5.3 Validation of the Analytical Prediction for the Maximum Catenary Action

Resistance ............................................................................................................. 131

5.3.1 Comparison of FE and Analytical Results ......................................... 133

5.4 Summary ................................................................................................... 135

Chapter 6. Three-dimensional behaviour of PCFS with column removal ........... 137

6.1 Finite Element Model ................................................................................ 138

6.2 Effects of Loss of an Edge Column ........................................................... 140

6.2.1 Slab Height ......................................................................................... 141

6.2.2 Tie Bar Diameter ................................................................................ 146

6.2.3 Tie Bar Ultimate Tensile Strain ......................................................... 148

6.2.4 Transverse Tie Bars............................................................................ 149

6.2.5 Procedure of Improving Robustness of Precast Floor Systems ......... 153

6.3 Loss of a Centre Column ........................................................................... 153

6.3.1 Slab Height ......................................................................................... 154

6.3.2 Tie Bar Diameter ................................................................................ 157

6.3.3 Tie Bar Ultimate Strain ...................................................................... 159

6.3.4 Transverse Tie Bars............................................................................ 159

6.4 Loss of Corner Column ............................................................................. 160

6.5 Conclusions ............................................................................................... 161

Chapter 7. Conclusion and Further Studies ......................................................... 163

7.1 Literature Review ...................................................................................... 163

7.2 Finite Element Model & Validation .......................................................... 164

Page 6: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

6

7.3 Two-Dimensional Analysis of Slabs ......................................................... 165

7.4 Predictive Analytical Relationship of the 2D Model ................................ 166

7.5 Three-Dimensional Simulation of the Floor System ................................. 167

7.6 Limitations of the Current Study ............................................................... 168

7.7 Future Studies ............................................................................................ 168

Bibliography ............................................................................................................. 170

Appendix 1: Assessment of tie bars designed according to British Standard

regulations ................................................................................................................ 176

Appendix 2: Evaluation of Analytical Relation ....................................................... 186

Page 7: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

7

List of Figures

Figure ‎1-1: Effects of Losing an External Column to a Blast Loading: a) alternate

load path design: no progressive collapse; b) conventional design: progressive

collapse (Baldridge and Humay, 2003) ...................................................................... 17

Figure ‎1-2: Precast Floor Unit Connection Layout (FIB-Bulletin-43, 2008) ............ 18

Figure ‎2-1, Ronan Point Building after collapse (MacLeod, 2005) ........................... 24

Figure ‎2-2: Estimation of tie force in catenary action................................................ 25

Figure ‎2-3, Alfred P. Murrah Building, before the attack (Suni, 2005) ..................... 26

Figure ‎2-4, Alfred P. Murrah Building, after the attack (Chernoff, 2009) ................ 27

Figure ‎2-5: Floor ties in a concrete structure (Brooker, 2008) .................................. 33

Figure ‎2-6: Area of the structure susceptible to collapse (Approved Document A) .. 34

Figure ‎2-7: Vertical and Horizontal tying in a structure (NIST, 2007) ..................... 35

Figure ‎2-8: Lifting tests on the connection between PCFSs (Engström, 1992) ......... 39

Figure ‎2-9: Pure suspension mode of action in a precast floor after loss of an interior

column (Engström, 1992)........................................................................................... 40

Figure ‎2-10: Resistance mechanism of tie connection between PCFS in the case of

lost column ................................................................................................................. 42

Figure ‎2-11: Installed Casting Beds (Spiroll, 2014) .................................................. 46

Figure ‎2-12: Extruder Components (Elematic, 2014) ................................................ 47

Figure ‎2-13: Different types of cut on PCFS (Spiroll, 2014) ..................................... 48

Figure ‎2-14: Slab lifting from its side grooves (Ultra-Span, 2012) ........................... 48

Figure ‎2-15: Hollowcore unit profile on steel structure (Hanson, 2014) ................... 49

Figure ‎2-16: Placement of tie bar in hollowcores (CCIP-030) .................................. 50

Figure ‎2-17: Placement of tie bar in between units (CCIP-030) ................................ 51

Figure ‎2-18: Generic bond-slip relationships (CEB-FIP 2010) ................................. 53

Figure ‎3-1: Tresca and Mohr-Coulomb yield criteria (TNO-DIANA, 2010) ............ 59

Figure ‎3-2: Mohr-Coulomb and Drucker-Prager yield criteria (TNO-DIANA, 2010)

.................................................................................................................................... 61

Figure ‎3-3: Brittle Cracking Behaviour (TNO-DIANA, 2010) ................................. 61

Figure ‎3-4: Linear tension softening (TNO-DIANA, 2010) ...................................... 62

Figure ‎3-5: Moelands Tension Softening (TNO-DIANA, 2010)............................... 63

Page 8: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

8

Figure ‎3-6: Hordijk tension softening (TNO-DIANA, 2010) .................................... 64

Figure ‎3-7: Comparison of tension softening models ................................................ 64

Figure ‎3-8: Cubic function of Dörr model (TNO-DIANA, 2010) ............................. 65

Figure ‎3-9: Power Law of Noakowski (TNO-DIANA, 2010) ................................... 65

Figure ‎3-10: Test Subassembly and Reinforcement Layout (Su et al 2009) ............. 68

Figure ‎3-11: Test Specimen and Schematic Illustration of Test Setup (Su et al, 2009)

.................................................................................................................................... 70

Figure ‎3-12: Behaviour of Stages of model A3 ......................................................... 72

Figure ‎3-13: Results of mesh sensitivity study .......................................................... 73

Figure ‎3-14: Finite element model ............................................................................. 74

Figure ‎3-15: Comparison of experiment and FE results for A-series ........................ 75

Figure ‎3-16: Comparison of experiment and FE results B-series .............................. 77

Figure ‎3-17: Test specimens of type I and II (Engström et al., 1998) ....................... 79

Figure ‎3-18: Concrete block FE model for simulation of bond-slip tests .................. 81

Figure ‎3-19: Comparison of experiments with FE results ......................................... 83

Figure ‎3-20: Comparison of experiment and FE results, Type II .............................. 84

Figure ‎3-21: Bond-Slip specimens deformed mesh, Types I and II .......................... 84

Figure ‎4-1: Two-dimensional representation of the slabs with pinned BC ............... 86

Figure ‎4-2: Mesh view of half of the model (left slab) .............................................. 88

Figure ‎4-3: FE Results for the 2D slab Model ........................................................... 90

Figure ‎4-4: Axial tie bar stress in the connection ...................................................... 92

Figure ‎4-5: Axial Stress and Crack Pattern of Slabs' Connection .............................. 93

Figure ‎4-6: Schematic 2D Slabs with Elastic Axial Restraints .................................. 94

Figure ‎4-7: Columns acting as fixed beams ............................................................... 95

Figure ‎4-8: Calculation of stiffness for a fixed beam under a point load .................. 95

Figure ‎4-9: Effect of Horizontal Displacement on Vertical Deflection ..................... 96

Figure ‎4-10: Behaviour of slabs with elastic axial restraint ....................................... 97

Figure ‎4-11: Partial Tie Bar, development of Catenary Action ................................. 98

Figure ‎4-12: Crack Pattern, Partial Tie Bar ............................................................... 99

Figure ‎4-13: Crack Pattern, Partial Tie Bar, showing concrete cracking in the

unreinforced zone of grouting .................................................................................... 99

Figure ‎4-14: Partial Tie Bar, large tie bar size resulting in total crack of concrete

grouting in the unreinforced zone ............................................................................ 100

Page 9: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

9

Figure ‎4-15: Axial Stress in Unreinforced Region, a) no crack through in the

unreinforced region (small tie bar); b) Crack through in the unreinforced region

(large tie bar) ............................................................................................................ 100

Figure ‎4-16: Slab's reference case dimensions ........................................................ 103

Figure ‎4-17: Hollowcore Sections (Bison, 2012) .................................................... 104

Figure ‎4-18: Effects of varying Slab Height on Vertical Load and Axial Reaction

Force ......................................................................................................................... 105

Figure ‎4-19: Force diagram ...................................................................................... 106

Figure ‎4-20: Variation of slab span affecting the connection response ................... 107

Figure ‎4-21: Variation of Tie Bar Length on the development of catenary action .. 109

Figure ‎4-22: Placing the Tie Bar between Hollowcore Units (CCIP-030) .............. 110

Figure ‎4-23: Effects of tie bar height (measured from bottom of slab) on catenary

action development .................................................................................................. 112

Figure ‎4-24: Effects of changing tie bar diameter ................................................... 113

Figure ‎4-25: Effects of changing tie bar yield stress................................................ 114

Figure ‎4-26: Effect of concrete strength on load-displacement of slabs' connection

(stresses in MPa) ...................................................................................................... 115

Figure ‎4-27: Effects of changing Tie Bar Ultimate Strain ....................................... 116

Figure ‎5-1: Free body diagram of one slab .............................................................. 120

Figure ‎5-2: Comparison of FE model with analytical relationship, slab height 265

mm, width 1200 mm, span 5 m, tie bar height 45mm, diameter 16 mm, steel yield

stress 500 MPa ......................................................................................................... 121

Figure ‎5-3: Slab deflection with axial displacement ................................................ 122

Figure ‎5-4: Comparison of the FE model with elastic BC with the analytical

relationship, slab span: 7 m ...................................................................................... 123

Figure ‎5-5: Strain distribution at the connection between PCFS ............................. 124

Figure ‎5-6: Strain distribution along the tie bar in the FE model ............................ 124

Figure ‎5-7: Variation of tie bar strain distribution with slab height ........................ 126

Figure ‎5-8: Effect of tie bar diameter on strain distribution length ......................... 128

Figure ‎5-9: Variation of strain distribution with tie bar position ............................. 129

Figure ‎5-10: Effect of tie bar ultimate strain on connection behaviour ................... 130

Figure ‎5-11: Comparison of FE base case with the analytical calculation .............. 132

Figure ‎6-1: Plan of a floor system ............................................................................ 137

Figure ‎6-2: Modelled slab resting on steel structure ................................................ 138

Page 10: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

10

Figure ‎6-3: Floor arrangement and three dimensional finite element model

representation ........................................................................................................... 139

Figure ‎6-4: Possible structural behaviour after loss of an edge column, (Baldridge

and Humay, 2003) .................................................................................................... 141

Figure ‎6-5: Slab Height effect on the connection behaviour ................................... 142

Figure ‎6-6: Plate structure with 3 fixed and 1 free edges (Moody, 1990) ............... 144

Figure ‎6-7: Effect of tie bar diameter on floor behaviour ........................................ 147

Figure ‎6-8: Effect of changing tie bar ultimate tensile strain................................... 149

Figure ‎6-9: Arrangement of transverse ties .............................................................. 150

Figure ‎6-10: Effects of introducing transverse tie bars ............................................ 151

Figure ‎6-11: Strain in main longitudinal tie (b) and two of the transverse ties (c) .. 152

Figure ‎6-12: Loss of centre column in a floor system ............................................. 154

Figure ‎6-13: effect of slab height when central column is lost ................................ 155

Figure ‎6-14: Plate structure with point load at centre (Timoshenko, 1959) ............ 156

Figure ‎6-15: Effect of tie bar diameter when central column is lost ........................ 158

Figure ‎6-16: effect of tie bar strain when central column is lost ............................. 159

Figure ‎6-17: Transverse tie bars in loss of a centre column .................................... 159

Figure ‎6-18: Deformed shape of the model with loss of a corner column ............... 160

Figure ‎6-19: Load-displacement and tie bar strain diagram under corner column loss

.................................................................................................................................. 161

Figure A1-1: comparison between simulation load-deflection curves and accidental

load, with BS tie bar ................................................................................................. 180

Figure A1-2:‎Comparison‎of‎simulations’‎load-deflection curve with accidental load,

with recommended tie bar ........................................................................................ 184

Page 11: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

11

List of Tables

Table ‎2-1: Building classes (Approved Document A) ............................................... 30

Table ‎2-2: Differences in building classification in BS and EN ................................ 32

Table ‎2-3: Load/Span Table (Bison, 2012) ................................................................ 46

Table ‎2-4: Type I (tie bar pull-out) bond-slip relationship parameters (CEB-FIP

2010) .......................................................................................................................... 53

Table ‎2-5: Parameters for Type II (tie bar yield) bond-slip relationship ................... 54

Table ‎3-1: Crack band width calculation (TNO-DIANA, 2010) ............................... 62

Table ‎3-2: Specimen Properties ................................................................................. 69

Table ‎3-3: FE models divisions along 3D axis for mesh sensitivity study ................ 73

Table ‎3-4: Characteristics of the test specimen (Engström et al., 1998) .................... 80

Table ‎3-5: Calculated concrete material properties (based on CEB-FIP Model Code

2010) .......................................................................................................................... 80

Table ‎4-1: Material Properties used in FE Model ...................................................... 88

Table ‎5-1: Calculation of strain distribution for the base case................................. 131

Table ‎5-2: Comparison of FE and analytical results, Tie Bar height ....................... 133

Table ‎5-3: Comparison of FE and analytical results, Tie Bar Ult. Tensile Strain ... 134

Table ‎5-4: Comparison of FE and analytical results, Slab Height ........................... 134

Table ‎5-5: Comparison of FE and analytical results, Tie Bar Diameter .................. 135

Table ‎6-1: Material property of concrete and steel used in the FE model ............... 140

Table ‎6-2: Accidental load based on the ultimate bending resistance of the slabs .. 145

Table ‎6-3: Position (from bottom of the section) and lengths of the transverse tie bars

.................................................................................................................................. 151

Table ‎6-4: Equivalent of accidental point load on the connection ........................... 157

Table A1-1: Simulations based on Bison (2012) load-span table ............................ 177

Table ‎A1-2: Models with recommended tie diameters ............................................ 181

Table A1-3: Comparison of tie forces of the BS and recommended ties ………....185

Table A2-1: Models with tie bar of diameter 10 mm .............................................. 187

Table A2-2: Models with tie bar of diameter 20 mm .............................................. 188

Page 12: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

12

University of Manchester

Seyed Mansoor Miratashiyazdi

Doctor of Philosophy

Robustness of steel framed buildings with precast concrete floor slabs

2014

Abstract

Following some incidents in high-rise buildings, such as Ronan Point London 1968,

in which collapse of a limited number of structural elements progressed to a failure

disproportionate to the initial cause, consideration of robustness was introduced in

British Standard. The main method of preventing progressive collapse for providing

robustness to steel framed buildings with precast concrete floor slabs focuses on the

allowable tying forces that the reinforcement in between the slabs and in hollowcores

should carry. However there are uncertainties about the basis of the practical rules

associated with this method. This thesis presents the results of numerical and

analytical studies of tie connection behaviour between precast concrete floor slabs

(PCFS). It is shown that under current design regulations the tie connection is not

able to resist the accidental load limit applied on the damaged floor slabs.

By establishing the capability of a finite element model to depict and predict the

behaviour of concrete members in situations such as arching and catenary action

against several experimental tests, an extensive set of parametric studies was

conducted in order to identify the effective parameters in enhancing the resistance of

the tie connection between PCFSs. These parameters include: tie bar diameter,

position,‎ length,‎ yield‎ stress‎ and‎ ultimate‎ strain;‎ the‎ slab’s‎ height,‎ length;‎ and‎ the‎

compressive strength of the grouting concrete in between the slabs that encases the

tie bar. Recommendations are made based on the findings of this parametric study in

order to increase the resistance of the tie connection. Based on the identified

effective parameters in the parametric study a predictive analytical relationship is

derived which is capable of determining the maximum vertical displacement and

load that the tie connection is able to undergo. This relationship can be used to

enable the connection to capture the accidental limit load on a damaged slab.

The identified parameters are examined in a three dimensional finite element model

to assess their effect when columns of the structure are lost in different locations

such as an edge, corner or internal column. Based on the findings of this study

methods for improving the connections performance are presented. Also the effect of

alternative transverse tying method is evaluated and it is concluded that although this

kind of tie increases the load carrying capacity of the connection, its effect on the

catenary action is not significant.

Page 13: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

13

Declaration

No portion of the work referred to in this thesis has been submitted in support of an

application for another degree or qualification of this or any other university or other

institute of learning.

Page 14: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

14

Copyright

The author of this thesis (including any appendices and/or schedules to this thesis)

owns‎certain‎copyright‎or‎related‎rights‎in‎it‎(the‎“Copyright”)‎and‎he‎has‎given‎The‎

University of Manchester certain rights to use such Copyright, including for

administrative purposes.

Copies of this thesis, either in full or in extracts and whether in hard or electronic

copy, may be made only in accordance with the Copyright, Designs and Patents Act

1988 (as amended) and regulations issued under it or, where appropriate, in

accordance with licensing agreements which the University has from time to time.

This page must form part of any such copies made.

The ownership of certain Copyright, patents, designs, trademarks and other

intellectual‎property‎(the‎“Intellectual‎Property”)‎and‎any‎reproductions‎of‎copyright‎

works in the thesis, for example graphs and tables (“Reproductions”),‎which‎may‎be‎

described in this thesis, may not be owned by the author and may be owned by third

parties. Such Intellectual Property and Reproductions cannot and must not be made

available for use without the prior written permission of the owner(s) of the relevant

Intellectual Property and/or Reproductions.

Further information on the conditions under which disclosure, publication and

commercialisation of this thesis, the Copyright and any Intellectual Property and/or

Reproductions described in it may take place is available in the University IP Policy

(see http://documents.manchester.ac.uk/DocuInfo.aspx?DocID=487), in any relevant

Thesis restriction declarations deposited in the University Library, The University

Library’s‎regulations‎(see‎http://www.manchester.ac.uk/library/aboutus/‎regulations)‎

and‎in‎The‎University’s‎policy‎on‎Presentation‎of‎Theses.

Page 15: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

15

Acknowledgements

I would like to express my sincere gratitude to my supervisor Professor Yong Wang.

It was with the help of his knowledge, experience, and affection of work that writing

this thesis became possible and his continuous guidance that always inspired new

ways of thinking for me. What I learnt from him in terms of problem tackling and

engineering judgement, was far more important than things about precast concrete

floor slabs.

Also I would like to thank Dr Parthasarathi Mandal, for his kindness and patience

that were of great help for me in difficult situations. It would not been possible to go

over the obstacles in this research without his aid.

And last but not the least I want to thank my father Dr Sam Miratashi, for his support

and encouragement throughout these years.

Page 16: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

16

Chapter 1. Research Background

1.1 Structural Robustness

When subjected to any unpredicted and accidental loading, the ability of a structure

not to suffer collapse disproportionate to the original cause is called robustness.

Upon achieving robustness in a structure, accidental actions which are beyond the

engineering design values should not cause damage to the structure which is not

proportionate to the direct initial and local damage caused by the accidental actions

(Menzies, 2005). In the literature the meaning of disproportionate collapse is not

usually distinct from the meaning of progressive collapse, though the result of a

progressive collapse usually leads to a disproportionate collapse, but their concepts

are different. A progressive collapse happens when localised damage in a part of a

structure, due to weakness in joints and linking elements, leads to further damage

and progresses to other parts of the structure. Since the result of the first damage has

widened its effect in other parts of the structure (i.e. progressed) and so is not

proportionate to the initial damage, it is also a disproportionate collapse (Hai, 2009).

The concept of progressive collapse has been considered in codes and building

regulations since the partial collapse of the Ronan Point Building in East London in

1968 (Moore, 2002), where a gas explosion on the 18th

floor caused the collapse of

the whole corner of a 22 storey building. In this incident 4 people were killed. The

explosion threw a wall panel out; consequently, without support, the upper floor

structural elements fell down on the lower floors and this phenomenon made

progress throughout the height of the building. As a result, in the early 1970s the

concept of robustness was introduced to the building codes and regulations in the

UK and later on the European and American codes (Pearson and Delatte, 2005).

Figure ‎1-1 shows a schematic example of an accidental action and the possible

scenarios that may happen afterwards. If the connections between the structural

components are able to withstand the extra applied load (accidental load), in this case

by bridging over the lost column, the floors above the lost column retain their

integrity and the structure remains robust (Figure ‎1-1-a), otherwise progressive

collapse occurs (Figure ‎1-1-b).

Page 17: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

17

(a) (b)

Figure ‎1-1: Effects of Losing an External Column to a Blast Loading: a) alternate load path

design: no progressive collapse; b) conventional design: progressive collapse (Baldridge and

Humay, 2003)

Different types of structures have different rules for supplying robustness to the

structure. Among them, due to their intrinsic discrete nature, structures constructed

using precast concrete floor slabs (PCFS) are one of the most vulnerable to

disproportionate collapse. The scope of this study will be to examine methods of

providing integrity of precast concrete floor slabs in steel framed buildings.

The highest risk of progressive collapse occurs when a supporting element in the

structure, most commonly a column, is lost due to an accidental action. In this

situation the beams that were supported by the removed column may act like a

hanging chain (catenary action), but the exact reaction of the connections of the

beams and the column above, and the connections between the precast concrete

elements that form the floor of which the column is lost, are most influential in

determining the behaviour of the remaining structural elements (Liu, 2010). To

prevent progressive collapse, the PCFSs should be connected to each other and to the

supporting frame, in such a way that the integrity and continuity of the floor remains

Page 18: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

18

in an acceptable degree so that the first link of the progressive collapse chain does

not form.

For steel structures with precast concrete floor system, the required integrity of the

connection between precast units is provided by the steel tie bars which are placed

both in the hollowcore units and in between them in the longitudinal joints

(Figure ‎1-2).

Figure ‎1-2: Precast Floor Unit Connection Layout (FIB-Bulletin-43, 2008)

However, although the tying method is commonly used in construction as a means of

providing structural robustness, there are uncertainties about the basis of the practical

rules associated with this method. Understanding and improving the effectiveness of

these practical methods are the main aims of this research.

1.2 Research Originality

The present regulations for providing robustness to steel framed buildings with

precast concrete floor slabs focus on the allowable tying forces that the

PCFS

Longitudinal Tie

Transverse Tie

Tie in the Hollowcore

Page 19: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

19

reinforcement in between the slabs and in hollowcores should carry. This

information is based on investigations on collapsed buildings such as Ronan Point,

London (see section ‎2.1.1 for further details). The derivation of tying force

relationship was based on equilibrium of catenary action force in the beam/slab and

the applied load and assuming a vertical displacement of

(L being the beam/slab

span for a span of 5m) and typical loading condition. This derivation did not

consider whether the structure has sufficient deformation capacity. Neither did it

consider whether the surrounding structure would be able to provide the necessary

axial restraint that is required to activate catenary action.

In the lack of research on performance of ties connecting the PCFS, the present study

attempts to develop a thorough understanding of the response of steel framed

structures with precast floor slabs on column removal and the fundamental

mechanisms of catenary action in precast floor slabs. Through such a study, better

methods of providing robustness to this type of structure will be recommended.

1.3 Research Objectives

The objectives of this study can be summarised as:

Establish the foundation of a reliable FE model to examine the factors

affecting the behaviour of the tie connection between two Precast Concrete

Floor Slabs (PCFS) until fracture;

Identifying the influential parameters that affect PCFS tie connections

behaviour;

Developing a predictive analytical method to predict PCFS tie connection

behaviour, validated by the parametric study results;

Assessing the effectiveness of current building code regulations and practical

construction methods for providing robustness of PCFS in steel framed

buildings;

Suggesting methods for improving robustness of precast concrete floors in

steel frame buildings;

Studying the mechanisms of collapse, due to the loss of a column in different

locations, in a representative steel framed building with PCFS.

Page 20: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

20

1.4 Research Methodology

Due to resource limits, this research will be conducted through numerical

simulations using the finite element method (FEM). In this study the commercial

FEM package TNO DIANA has been utilised owing to its powerful material models

for concrete. The numerical modelling will be validated by comparison with

available experiments on concrete structural elements that undergo arching and

catenary actions which are similar to the expected behaviour of PCFS slabs under

accidental loading.

The validated modelling method will then be used to conduct extensive parametric

studies, one set for precast concrete slabs for thorough understanding of the catenary

action mechanism, and one set for steel framed structures with precast concrete slabs

for understanding of realistic whole structural behaviour. These parametric study

results are then used to formulate an analytical predictive method which may be used

in practical design. The parametric study results are also used to assess effectiveness

of the current construction methods and to identify methods that can improve

robustness of this type of construction.

1.5 Thesis Structure

Chapter 2 covers a review of literature in the field of robustness with special focus

on precast concrete floor slabs in steel frame buildings, and explains the different

approaches in building code regulations regarding the robustness concept and

critically assesses the shortcomings of these methods, leading to justification for the

current research.

In chapter 3 tests, reported in literature, on concrete structural elements that undergo

a very similar behaviour to the interest of the present study, are simulated. Using the

validated numerical model, an extensive parametric study is carried out and the

results are reported in chapter 4. Variables examined in the parametric study include:

precast‎ concrete‎ slab’s‎ height‎ and‎ length;‎ connecting‎ tie‎ bar’s‎ position,‎ length,

diameter, yield stress, and ultimate strain; and‎ grouting‎ concrete’s‎ compressive‎

strength.

Page 21: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

21

Based on the influential parameters identified in chapter 4, a mathematical

relationship is formulated in chapter 5 to analytically predict the precast concrete

slab load-deflection behaviour under catenary action until failure which is

characterised by reinforcement fracture.

Chapters 3-5 deal with catenary action in precast concrete slab elements in the

direction of the span. In realistic structures, the slabs interact in directions

perpendicular to their span and also with the surrounding structural elements.

Chapter 6 reports the results of a numerical parametric study examining how this

type of structure behaves with the removal of a supporting column in different

locations. Comparisons will be made between structures using the existing practical

construction details with the alternative details that have been shown in chapter 4 to

provide improved robustness.

Chapter 7 summarises the results of this study and presents topics for further

investigation in this field.

Page 22: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

22

Chapter 2. Literature Review

This chapter presents a detailed introduction to background information related to

current UK rules governing the design and construction of precast floor systems

(PCFS) to meet the requirements of structural robustness. Further details related to

technical investigations, including testing, numerical simulation and analytical

calculation methods, will be presented in relevant chapters.

First this chapter reviews major incidents that led to changes in the UK building

regulations concerning robustness of structures. This is then followed by a summary

of building rules and regulations that are intended to control disproportionate

collapse of building structures. Among these, providing sufficient tying between the

primary components of a structure is the main mean by which the regulations on

structural robustness are achieved.

This chapter will review the ties connecting PCFS and explain why the current tie

force regulations may not be effective. To help this review, this chapter will first

provide a brief review of the design and construction technology of this type of

structural units including placement of ties.

Since the most important parameter affecting behaviour of the ties between the PCFS

components is the bond between the steel reinforcement with the surrounding

concrete, this chapter provides a review of research on this phenomenon as well.

2.1 Major Accidents of Progressive Collapse

2.1.1 Ronan Point Building

All of the current rules and regulations, governing the design and construction of

buildings to control disproportionate collapse in the UK and elsewhere, can trace

their origin to the Ronan Point accident. On May 16 1968, there was a gas explosion

in an apartment on the 18th

floor of 22-storey Ronan Point building in east London,

which commenced the partial collapse of the whole corner of the structure. The

Page 23: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

23

pressure from the explosion blew out the walls of the apartment, which were the sole

support for the walls directly above. The unsupported walls of the 19th

floor and the

three other floors above fell down to the 18th

floor, and this sudden impact loading

was much greater than its resistance. The corner of the 18th

floor collapsed and sent

debris cascading down the corner of the building, causing damage to each of the

floors below (Figure ‎2-1). Later, in investigations carried out on this building, it was

found that there had been many flaws in both design and construction quality (Choi

and Chang, 2009). However, it was the progressive and disproportionate manner in

which the corner of the building completely failed that caused all those concerns

(including public authorities, engineers, and academics) about the building

regulations of the time.

These investigations found that the pressure required for displacing the internal walls

in the Ronan Point building was 1.7 kPa and the pressure which could displace the

exterior walls was only 21 kPa (Griffiths, 1968). This showed the extremely poor

workmanship applied to this structure, and also the weakness of the building codes

used at that time, which were dated back to 1952. Later on it was also discovered

that the load applied by winds to this structure could cause a progressive collapse,

since the building code that the Ronan Point was designed according to, had not

considered structures with that height (Pearson and Delatte, 2005).

Continuing concerns over the structural integrity of the Ronan Point Building

eventuated in its demolition in May of 1986. In order to study the joints of this

structure carefully, Ronan Point was not demolished in the traditional fashion, it was

dismantled floor by floor. During these investigations the extensive scale of the poor

quality of the connections was evident throughout the building (Wearne, 2000).

There were some connections where it was found that the necessary force to break

them was as low as 15.6 kN (Hendry, 1979).

After this incident, and considering the fact that the Ronan Point building was

designed to comply with statutory building regulations of the time, the government

investigations concluded that the codes did not provide secure and robust structures

capable of resisting accidental actions. According to (Hendry, 1979), “new‎

regulations‎ …‎ require that under specified loading conditions a structure must

remain stable with a reduced safety factor in the event of a defined structural

Page 24: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

24

member or portion thereof being removed. Limits of damage are laid down and if

these would be exceeded by the removal of a particular member, that member must

be designed to resist a pressure of 34 kN/m2 (5 lb/in

2) from any direction. Of special

importance in relation to load bearing wall structures is that these conditions should

be met in the event of a wall or section of a wall being removed, subject to a

maximum length of 2.25 times the storey‎height”‎(Hendry, 1979).

Figure ‎2-1: Ronan Point Building after collapse (MacLeod, 2005)

The values that appeared in the robustness regulations (tying force of 60 kN/m for

concrete structures, and the pressure of 34 kPa to be applied on the key element)

have their origins in investigations of the Ronan Point incident. The value of 34 kPa

was related to a severe gas explosion and is considered by some authors as overly

conservative (Burnett, 1975).

Page 25: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

25

By considering the weak connections between the precast concrete members of the

Ronan Point building, it was assumed that if the structural elements were tied

together in a better fashion, the extent of the damage would have been far more

limited. The tying force resistance was calculated based on the typical loading in

concrete buildings with following assumptions:

gk and qk: permanent and variable load of 3.8 kN/m2 (Burnett, 1975 assumes 3.6

kN/m2)

L: beam span before loss of a column: 5m

Δ: Allowable deflection of the span in catenary action: L/5

Accidental loading condition: gk +

The moment equilibrium of the tie connection in the middle of the span in catenary

action would dictate (Figure ‎2-2):

Figure ‎2-2: Estimation of tie force in catenary action

Δ

Ft

Ft

gk + (qk/3)

L L

Page 26: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

26

Equation ‎2-1

By substituting the various assumed values, Equation ‎2-1 yields the tie force (Ft) of

60 kN/m.

2.1.2 Alfred P. Murrah Federal Building

On April 19, 1995 in Oklahoma City a truck containing approximately 5000lbs of

explosives was parked near the north side of the Alfred P. Murrah building

(Figure ‎2-3), close to the middle point, where it was detonated. Roughly 30% of the

building was destroyed by the explosion, over 300 buildings nearby were destroyed

or damaged, and 168 lives were lost (Piotrowski and Perdue, 1995). The explosion

caused the destruction of the three columns adjacent to the blast on the ground floor,

and some other floor slabs and walls in the vicinity of the blast. But the final

destruction (Figure ‎2-4), being disproportionate to the initial incident, was due to a

progressive collapse (Corley, 1998).

Figure ‎2-3: Alfred P. Murrah Building, before the attack (Suni, 2005)

Page 27: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

27

Figure ‎2-4: Alfred P. Murrah Building, after the attack (Chernoff, 2009)

The structure of the Alfred P. Murrah building was an ordinary concrete frame

designed in accordance with the ACI 318-71 code. The construction of the building

was of high quality and very well detailed. However, it was not designed to resist

any abnormal loading such as earthquake or explosion similar to many other federal

and office buildings of the time in that region (Corley, 1998).

Investigations carried out following the incident pointed out some design and

construction methods that could mitigate the effects of unpredicted accidental

loading (Corley, 1998):

a) If the building had been designed as a special moment frame or dual system

with special moment frame, among the three destroyed columns adjacent to

the blast loading, only the one which was the closest would have collapsed

due to brisance, and the other two could have survived. The presence of more

reinforcement in the concrete members of a special moment frame would

have facilitated higher energy dissipation. This shows the key role of the steel

bars in concrete members for prevention of progressive collapse which is the

subject of the present study.

b) Increased redundancy, in general, would have increased the chances of

preventing a bad situation getting worse (progressive collapse). “There

should be no single critical element whose failure would start a chain reaction

of successive failures that would take down a building. Each critical element

Page 28: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

28

should have one or more redundant counterparts that can take over the critical

load in case the first should fail.”‎

c) Compartmentalized construction: this type of construction has proved to be

able to resist progressive collapse to a good level. But the inflexible and

rather small spaces that emerge by construction of this type, limits its

application to office buildings.

d) Dual systems (with special moment frame): the investigations concluded that

if the A. P. Murrah building had been designed for a seismic area, its level of

destruction could have been reduced by up to 85%. Utilizing more

reinforcement and different types of connection in the dual systems with

special moment frames would have given the building the capacity of

absorbing more energy.

Other investigations (Osteraas, 2006) have pointed out some general

recommendations to enhance robustness of structures:

a) To‎avoid‎irregularities‎in‎the‎structure’s‎plan‎and‎to have a three dimensional

space frame.

b) To avoid anti-redundant features (such as transfer girders) and to provide the

structure with enough redundancy to form alternate load paths.

c) To provide the structural frame with mechanical fuses which allows the walls

and slabs to collapse without affecting other parts of the structural frame.

d) To provide the structural frame with enough ductility for energy absorption

(such as design of structures in highly seismic areas).

2.2 Building Codes and Regulations on Robustness of

Structures

The risk of progressive structural collapse due to damages caused by accidental

loading is different depending on the nature, the size and occupancy of the building.

It is therefore important to strike an appropriate balance between the cost of

providing a robust structure and the benefit of reduced risk of progressive collapse.

In many parts of the world, this is done by dividing buildings into a number of

classes and specifying different requirements for different classes. For example, in

Page 29: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

29

the British Standard Approved Document A, buildings are divided into the following

three classes (Table ‎2-1):

Page 30: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

30

Table ‎2-1: Building classes (Approved Document A)

Class Building type and occupancy

1 •‎Houses‎not‎exceeding‎four‎storeys.

•‎Agricultural buildings.

•‎Buildings‎into‎which‎people‎rarely‎go,‎provided‎no‎part‎of‎the‎building‎is‎

closer to another building, or area where people do go, than a distance of 1.5

times the building height.

2A •‎5‎storey‎single‎occupancy‎houses.

•‎Hotels‎not‎exceeding 4 storeys.

•‎Flats,‎apartments‎and‎other‎residential‎buildings‎not‎exceeding‎4‎storeys.

•‎Offices‎not‎exceeding‎4‎storeys.

•‎Industrial‎buildings‎not‎exceeding‎3‎storeys.

•‎Retailing‎premises‎not‎exceeding‎3‎storeys‎of‎less‎than‎2000‎m2 floor area

in each storey.

•‎Single‎storey‎Educational‎buildings.

•‎All‎buildings‎not‎exceeding‎2‎storeys‎to‎which‎members‎of‎the‎public‎are‎

admitted and which contain floor areas not exceeding 2000 m2 at each

storey.

2B •‎ Hotels,‎ flats, apartments and other residential buildings greater than 4

storeys but not exceeding 15 storeys.

•‎Educational‎buildings‎greater‎than‎1‎storey‎but‎not‎exceeding‎15‎storeys.

•‎Retailing‎premises‎greater‎than‎3‎storeys‎but‎not‎exceeding‎15‎storeys.

•‎Hospitals‎not‎exceeding‎3‎storeys.

•‎Offices‎greater‎than‎4‎storeys‎but‎not‎exceeding‎15‎storeys.

•‎ All‎ buildings‎ to‎ which‎ members‎ of‎ the‎ public‎ are‎ admitted‎ and‎ which‎

contain floor areas exceeding 2000 m2 for the notional but less than 5000 m

2

at each storey.

3 •‎All‎buildings‎defined‎above as Class 2A and 2B that exceed the limits on

area and/or number of storeys.

•‎All‎buildings‎containing‎hazardous‎substances‎and/or‎processes.

•‎Grandstands‎accommodating‎more‎than‎5000‎spectators.

Page 31: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

31

For building class 1, provided that they are designed and constructed based on other

buildings codes and construction regulations there is no need for any action to assure

their robustness. For class 2A buildings it is said that effective horizontal ties or

effective anchorage of suspended floors to walls for framed and load bearing walls

should be provided according to BS 8110-1:1997 and BS 8110-2:1985 for concrete

structures, BS 5628-1:1992 for unreinforced masonry structures and BS 5950-1:2000

for steel structures. For class 2B buildings there should be effective vertical ties for

all supporting columns and walls and horizontal ties for frame and load bearing

walls. For class 3 buildings a systematic risk assessment should be undertaken while

considering all the normal predictable and unpredictable hazards and all the

structural elements should be designed based on the aforementioned building codes

and regulations.

The European code EN 1991-1-7:2006 takes a similar approach. Table ‎2-2 compares

the regulations between the British Standard and EuroCode for building

classification and precast concrete structures.

Page 32: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

32

Table ‎2-2: Differences in building classification in BS and EN

Bld. Class Type Approved

Document A- A3

EuroCode 1991-1-7

1 Houses not

exceeding four

storeys

Single Occupancy

houses not exceeding

four storeys

2A Retailing premises:

less than 2000 m2

Retailing premises: less

than 1000 m2

2B Admissible damaged

area: 15% or 70 m2

whichever smaller

Admissible damaged

area 15% or 100 m2

whichever smaller

3 Bld. Containing

hazardous

substances

N/A

The value of 70 m2

for the admissible damage area is an estimation based on two 6 m

× 6 m structural bays that at the time of drafting the British Standard was a typical

bay size. But as the modern structural systems came into practice this size was

augmented to 7.5 m × 7.5 m which is almost the 100 m2 recommended by the

EuroCode considering two adjacent floor bays close to the lost column (CPNI,

2011).

2.2.1 Implementation of the robustness requirements

The British standards were the first building code to recommend regulations for

avoiding the progressive collapse of buildings, of which the catastrophic accident of

Ronan Point Building in 1968 was the main motivation. In a number of publications

of the British Standard such as those for steel, concrete, masonry and composite

Page 33: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

33

structures, also steel and concrete bridges, the concept of robustness and

recommendations for achieving it are given.

The main methods proposed in the British Standards to ensure that the structure will

not suffer from an accidental action in an amount which is not proportional to the

cause, can briefly be described as follows (Moore, 2002):

The tying method: vertical and horizontal ties should be provided between

the primary structural components (Figure ‎2-5). The assumption is that the

provision of ties creates a structure with a degree of redundancy that

increases the structural continuity, and thus provides the building with

alternative load paths if part of the structure is removed by an accidental

action. In general the ties are steel members or rebar, also the beam to

column joint is considered to carry the tying force. The minimum value for

tying force resistance is 75 kN is steel structures and 60 kN in concrete.

Figure ‎2-5: Floor ties in a concrete structure (Brooker, 2008)

The bridging method: wherever tying is not feasible, the structure should be

designed to be able to bridge over the loss of a member which has not been

tied and the area of collapse should be limited and localised. To do so, each

time an untied member is notionally removed (including vertical load bearing

members and beams connected to one or more columns) and the area of the

Page 34: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

34

affected zone in the immediate adjacent storeys, is checked so that the area at

risk of collapse should be limited to the smaller of these values: 15% of the

area of the considered storey, or 70 m2 (Figure ‎2-6).

Figure ‎2-6: Area of the structure susceptible to collapse (Approved Document A)

The key element method: if bridging over a missing member is not possible;

such a member should be designed as a key element which is capable of

resisting a pressure of 34 kN/m2 from any direction. The value of 34 kN/m

2

(5 lb/in2) was chosen based on the observational evidence on an estimation

that exterior wall panel would fail at Ronan Point (Hai, 2009). Such

accidental design loading is supposed to act simultaneously with one third of

all normal characteristic loading.

Following the above recommendations in BS is considered to produce robust

structures that can resist disproportionate collapse due to various accidental causes,

such as impact and gas explosions (Demonceau, 2008).

Page 35: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

35

2.2.1.1 Application of the Tying Force Method to Precast Reinforced

Concrete Structures

Design codes for different types of structure provide detailed recommendations on

how to apply the tying force method. Among the three methods presented in the last

section, specific guidance is often necessary on application of the tying method. This

section presents an overview of the tying method application to precast reinforced

concrete structures.

Figure ‎2-7: Vertical and Horizontal tying in a structure (NIST, 2007)

Figure ‎2-7 shows a scheme of providing ties. Internal ties should be available at each

floor and roof level approximately at right angles and they should be continuous, and

at each end they should be anchored to peripheral ties. In the British Standard BS

8110-1:1997, the internal ties should be capable of resisting a tensile force equal to

the greater value of the two following relationships (in kN/m width):

Page 36: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

36

Equation ‎2-2

Equation ‎2-3

Whichever is larger.

Where:

is dead load on floor (in kN/m2)

is the imposed (live load) on floor (in kN/m2)

is the greater of the distances between centres of columns, frames or walls

supporting any two adjacent floor spans in the direction of the considered tie

is the lesser of these two values: (20 + 4n0) or 60 kN/m; where n0 is the number of

storeys in the structure.

The value of 60 kN was chosen based on an estimation of the equilibrium state that a

tie connecting two horizontal members on top of the lost column should be able to

provide with regard to the floor area applying load to the tie.

But as will be seen in this study (‎Chapter 4), for precast concrete floor slabs, this

value is subject to many other local factors at the connection zone. Also it will be

shown (in ‎Chapter 4) that solely specifying the tie force does not necessarily

guarantee robustness of the structure, because in the case of the connection between

PCFSs it is mainly the elongating capacity of the tie bar that provides this

characteristic for the structure in catenary action.

2.3 Research on Structural Tying System of PCFS

There have been many experimental and numerical investigations regarding the

robustness of steel and concrete frames. But most of the research in the field of

progressive collapse focuses on the connections between the main structural

elements i.e. columns and beams and they usually consider the flooring system as an

integrated structural element which does not fall apart (Shi et al., 2010), (Zolghadr

Page 37: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

37

Jahromi et al., 2013), (Vlassis et al., 2008), (Izzuddin et al., 2008), (Sasani, 2008).

This assumption not only dismisses the intrinsic segmental nature of the precast

concrete flooring system but also neglects the effect of the debris from such floors on

the lower levels which itself causes extra loading on the remaining structure. This

phenomenon has more importance as it has not been considered in the current

building regulations (Izzuddin et al., 2008).

Despite questioning the effectiveness of tying resistance for PCFS against

progressive collapse (CPNI, 2011), there is a scarcity of experimental and numerical

(finite element) research on connections between precast concrete floor units and

how they contribute to the robustness of this type of structure. Most of the research

on PCFS in steel frame concentrate on the composite behaviour of the PCFS on the

steel beam, considering the shear stud (Lam et al., 1999), (Lam et al., 2000), (Lam

and Nip, 2002), (Fu and Lam, 2006), (Hegger et al., 2009) and not the ties

connecting the floor slabs especially in the case of loss of a column. The only major

study on the tying system connecting the PCFS with special attention to the bond-

slip phenomenon of the rebar inside concrete was conducted by Engström (1992).

2.3.1 Bending Tests on Tie Connections

Bending tests on the connection of PCFS have been conducted by Engström (1992),

Rosenthal (1978), and Gustavsson (1974). The scope of these studies has been to

obtain the adequate floor integrity by means of connection between the concrete

floor slabs, deformation capacity and anchorage capacity of the tie connection

respectively. In all of the mentioned experiments the PCFS units rested on three

beams and the middle one (under the connection) was raised in order to apply

bending‎to‎the‎slabs’‎connection‎(Figure ‎2-8). Although the boundary conditions of

these experiments were not a faithful representation of the real PCFS flooring system

(because there was no consideration of axial restraint), their results shed some light

on the behaviour of tie connections between PCFS, including:

Smooth tie bars may enable more elongation in the connections, but the bond

stress provided by them did not give sufficient anchorage between concrete

and steel bars, in comparison to ribbed bars.

Page 38: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

38

Increasing the tie bar dimension increased the bending resistance of the

connection, although a balance should be struck between concrete and steel

tensile strength.

Due to pure bending action in these tests, under sagging moments, the tie bar

served better if placed at the bottom of the section and under hogging

moment at the top. Placing the tie bar at mid-height of the section would

provide some resistance under bending in both directions.

Slabs were always separated first at one of the transverse joint interfaces.

Once the transverse joint was cracked, the tensile strength was carried by the

tie bar only.

The contribution of the tie bar in the transverse joint was negligible.

If the tie bar was sufficiently long (usually defined as 75ϕ) the end hooks

were not strained.

Smooth tie bars, even with end hooks, did not provide sufficient bond with

concrete.

However the lack of consideration of axial restraints and the different boundary

condition of the other far ends of the slabs from the real structure condition in the

aforementioned experiments, neglected the effect of arching action prior to the

catenary stage. Also as the slabs can move freely on both far ends (from the

connection, in the lack of axial restraint) the catenary action behaviour of these tests

may not illustrate behaviour close to what may happen in real floor slabs; as

adequate tension was not applied on the tie connecting the slab units.

Page 39: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

39

Figure ‎2-8: Lifting tests on the connection between PCFSs (Engström, 1992)

In the bending tests of Engström (1992) the type, dimension and position of the tie

bars were studied. The present study will broaden the scope of investigation by

including the following additional parameters: grouting concrete strength, span and

depth of the slabs, and tie bar length. Also the effect of yield stress and ultimate

strain of the tie bars will be individually studied.

2.3.2 Formulation of Tie Behaviour in Bending

Engström (1992) seems to be the only one to have made an attempt to formulate the

requirement on tie connection between PCFS in the case of column loss. It was

assumed that after column loss, slabs are suspended by ties from both ends and that

the elongations (w) of all of the ties were the same at all times (Figure ‎2-9).

Page 40: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

40

Figure ‎2-9: Pure suspension mode of action in a precast floor after loss of an interior column

(Engström, 1992)

For this formulation, the following parameters were defined:

Q: total load of each floor element applied at the centre of the element;

N: tensile force of the tie bar;

a: maximum vertical displacement of the connection

aqz: vertical displacement of the driving force (Q),

w: elongation (displacement) of the tie bar

l: length of the slab

For one slab, the deformed geometry yields:

(

)

Equation ‎2-4

Neglecting the quadratic terms of w, the vertical displacement of the driving force

can be written as:

Equation ‎2-5

Page 41: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

41

The equilibrium of moments gives:

Equation ‎2-6

The ultimate strength and elongation of the ties are Nmax and wmax respectively.

Therefore, the maximum vertical resistance (Qmax) for the connection is defined as:

Equation ‎2-7

The above procedure suffers from the following drawbacks:

While the slabs are assumed to be completely suspended, the expected

behaviour from the side tie bars would be dowel action rather than catenary

(capturing the tensile force).

Even if the two sides of the slabs were provided with vertical restraint so that

the ties would only carry tensile forces, the assumption that all three would

have equal elongations should have been substantiated.

The above arrangement of ties neglects slab connections with walls and

beams e.g. at the edge of the structure.

In the case of loss of a column, as long as the slabs have adequate axial, vertical, and

rotational restraint at both far ends from the lost column, the connection between the

PCFSs can undergo a large vertical displacement (h in Figure ‎2-10). Hence it is the

tie‎ bar’s‎ elongation (e) localized to the connection zone that may provide the

required integrity of the floor slabs, provided that there is enough bond between the

tie bar and surrounding concrete.

Page 42: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

42

Figure ‎2-10: Resistance mechanism of tie connection between PCFS in the case of lost column

The current tie connection regulation recommends a tie force derived based on

equilibrium of slab forces in the catenary action stage (as shown in section ‎2.1.1);

however, it neglects the fact that it is the ductility of the tie bar which dictates the

extent of the catenary action development (Figure ‎2-10). The present study will

demonstrate that a tie connection designed based on current regulations may fail.

Importantly, this study will show how to achieve robustness of PCFS system.

Based on the conducted literature survey presented above, the necessity of an

investigation on effectiveness of the tie connection is apparent. Such investigation

should particularly concentrate on parameters that affect the behaviour of the tie

connection in the catenary action stage because it is considered the dominant

mechanism under the column loss scenario (Elliot, 2002).

2.4 Construction Technology of PCFS

To understand the behaviour of the PCFS better, it is necessary to examine the

different components of this structural element. This can be achieved by considering

the design and manufacturing process of precast concrete members.

Tie Bar

PCFS Axial and Vertical Restraints

h

L

Page 43: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

43

2.4.1 Design of PCFS

PCFSs are designed mostly as simply supported, one-way spanning units. The main

failure modes for PCFSs are (Elliot, 2002):

Flexural capacity

Shear capacity

Other design considerations are:

Deflections limit

Bearing capacity

Handling restrictions (usually imposed by manufacturer)

2.4.1.1 Flexural capacity

The flexural capacity of a PCFS is checked in serviceability limit state (SLS) and

ultimate limit state (ULS) designs. When using design factors of 1.35 for permanent

and 1.5 for variable load, the SLS design check is usually the critical loading

condition (Elliot, 2002).

2.4.1.1.1 Serviceability limit state (SLS)

The serviceability limit state of flexure is calculated based on lesser of the following

two relationships (Equation ‎2-8 and Equation ‎2-9):

( √ )

Equation ‎2-8

Equation ‎2-9

Where: Zb and Zt are the section modulus to the bottom and top fibre respectively. fcu

is the cube compressive strength of concrete. And fbc and ftc are the maximum fibre

stress in the bottom and top of the section respectively, and defined as:

Page 44: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

44

(

)

Equation ‎2-10

(

)

Equation ‎2-11

in which

The final prestressing force (Pf) is the product of the effective prestress in the tendon

after all losses (fpe) and the cross sectional area of the prestressing strands (Aps):

e: eccentricity of the prestressing strand

and A is the total cross sectional area of the precast member

2.4.1.1.2 Ultimate limit state of flexure

The ULS flexure resistance can be calculated based on the following relationship

(Elliot, 2002):

Equation ‎2-12

in which:

Mur: is the slab ultimate bending moment resistance

fpb: is the design tensile stress in the tendons

Aps: is the total cross sectional area of the tendons per unit area of slab

d: is the effective depth of the precast concrete cross section

and X is the depth of concrete in compression calculated by equating the tensile force

in the tendons to compressive force of the concrete block

Page 45: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

45

2.4.1.2 Shear capacity of PCFS

Unlike the bending resistance, shear capacity is only considered at the ultimate state.

The shear capacity is calculated for a cracked (Vco) and uncracked (Vco) section

separately. Obviously the shear capacity of the uncracked section is more than that of

cracked, as the whole section contributes to resisting the shear forces.

The shear capacity of uncracked PCFS is given by the following relationship:

Equation ‎2-13

where

fcp is the compressive stress at centre axis resulting from prestress after all losses

y’ :is the distance from section centroid to total area (A) centroid

bv :is the web width

The shear capacity in the cracked region of concrete is given by:

(

)

Equation ‎2-14

in which vc is a factor obtained from BS8110, Part 1, Table 3.9

and fpu is the ultimate strength of the prestressing strands.

Most PCFSs are manufactured with predefined standard specifications, and their

load carrying capacities are reported by the manufacturing companies, giving load-

span tables. An example is shown in Table ‎2-3.

Page 46: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

46

Table ‎2-3: Load/Span Table (Bison, 2012)

Overall

structural

depth

Spans indicated below allow for characteristic service load (live load)

plus self-weight plus 1.5 kN/m2 for finishes

Characteristic service loads (kN/m2)

0.75 1.5 2 2.5 3 4 5 10 15

Effective span (m)

150 7.5 7.5 7.5 7.3 6.8 6.4 5.6 5 3.2

200 8.25 8.25 8.1 7.9 7.7 7.4 6.9 5.8 4.6

250 10.4 9.9 9.7 9.4 9.2 8.8 8.1 6.9 5.3

300 11.7 11.2 10.9 10.6 10.4 9.9 9.5 7.8 6.8

350 14.5 14 13.7 13.5 13.2 12.7 12.3 10.7 8.8

400 16 15.5 15.2 14.9 14.6 14.1 13.7 11.9 10

450 17.1 16.5 16.2 15.9 15.6 15.1 14.6 12.7 10.7

2.4.2 PCFS Manufacturing

The manufacturing process starts with cleaning the casting bed (Figure ‎2-11). The

casting bed should have a smooth surface which is oiled to provide detachable

surface with concrete. For concrete curing purposes there are heating pipes under the

metal surface of the casting bed which itself lies on a concrete base and insulation

material. The length of the casting bed depends on several parameters such as

utilisation of the casting bed, production flexibility, available space in the factory,

and strand patterns. The common length for the beds is 120m (Spiroll, 2014).

Figure ‎2-11: Installed Casting Beds (Spiroll, 2014)

The next step is positioning and pulling of the prestressing strands. This process is

done, by some manufacturers, with the same machine that cleans the bed. The

Page 47: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

47

strands are tensioned to the desirable stress and anchored at the other end of the

casting bed.

The main stage of the manufacturing process is performed with a machine called

“extruder”.‎Extruders‎have‎different‎characteristics‎ in‎ terms‎of‎speed,‎height‎of‎ the‎

slab they produce, number of hollow cores, slab width, and concrete compaction

technology.‎ The‎ concrete‎mix‎ is‎ usually‎ fed‎ into‎ the‎machine‎ from‎ the‎ “concrete‎

hopper”‎ and‎ transferred‎ to‎ the‎ nozzles‎ that‎move the extruder forward with their

injection force (Figure ‎2-12).

Figure ‎2-12: Extruder Components (Elematic, 2014)

Most manufacturers use a concrete mixture with a rather low water to cement ratio.

This dry mixture with intense concrete compaction allows the concrete mixture to

plasticise during a short time and form and mould while the extruder passes on the

casting bed. After the concrete is cured, slabs are ready to be sawed into the required

lengths.

Machines designed for sawing the PCFS use diamond blades with different

diameters depending on the height of the slab. Based on the type of the cut required,

machines with suitable angle of saw are chosen. Cuts may be longitudinal or

transverse and each requires the corresponding saw. There are also saws that can be

adjusted to any angle between 0 to 90 degrees (Figure ‎2-13).

Page 48: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

48

Figure ‎2-13: Different types of cut on PCFS (Spiroll, 2014)

Most of the transverse cuts are performed while the slab is on the casting bed,

providing slabs segments which can be moved to the storage area. This allows the

casting beds to have a faster turnaround. Slabs are lifted usually from their side

grooves (Figure ‎2-14). At the stock yard (storage area) other type of saws may be

used to give the slabs the required shape and size.

Figure ‎2-14: Slab lifting from its side grooves (Ultra-Span, 2012)

Longitudinal Cut

Transverse Cut

Inclined Cut

Page 49: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

49

2.5 Providing Tying Resistance in Precast Concrete Floor

Slabs

This research focuses on the behaviour of precast concrete floor slabs supported by a

steel frame. It is necessary to understand details of the structural components and

connections that are used to achieve sufficient tying resistance required for structural

robustness according to current construction methods.

2.5.1 Precast Concrete Floor Slabs

Precast concrete floor slabs are prestressed units and are constructed in two main

categories: 1) solid elements (planks) or 2) with longitudinal hollow cores (HC). The

units usually have 1200 mm width and can be up to 10 m long, with different depths

(Way et al., 2007).

2.5.1.1 Hollowcore floor units

The majority of the manufacturers produce units with depths ranging from 150 to

450 mm and a nominal width of 1200 mm. High tensile prestressing strands or wires

are used as the reinforcement in hollowcore floor slabs, and there is no shear

reinforcement in them.

Figure ‎2-15: Hollowcore unit profile on steel structure (Hanson, 2014)

PCFS

Tie Bar

Grouting

Shear Key

Page 50: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

50

The edges of the hollowcore units are profiled (shear key) such that it is possible to

grout the joint between two adjacent units to provide enough shear resistance

between them. The reinforcement for providing the tying resistance is located in this

grouted or concreted joint between the floor slabs (Figure ‎2-15).

2.5.1.2 Solid precast floor units

This kind of floor slab is used usually with structural in-situ concrete topping, and

their depth ranges from 75 mm to 100 mm. The prestressing reinforcement of solid

precast floor units is the same as for the hollowcore units. As there are no

hollowcores in this type of units their thickness is usually less than that of those with

hollowcores.

2.5.2 Connections of precast concrete floor slabs

Apart from the tie force that was discussed in section ‎2.2.1.1, other regulations

observe the placement of the tie bar in between the slabs for those types of structures

that require tying. Tie bars are normally placed in between the units and in the

hollowcores. For the latter, the top flange of the PCFS is removed and the core is

filled with in situ concrete (Figure ‎2-16).

Figure ‎2-16: Placement of tie bar in hollowcores (CCIP-030)

Placement of tie bars between units depends on the position of the grouting keys on

side of the PCFS, as shown in Figure ‎2-17. Other arrangements of tie bar are

Page 51: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

51

possible for connection of PCFS to supporting walls and beams, but they are out of

the scope of the present study.

(a) (b)

Figure ‎2-17: Placement of tie bar in between units (CCIP-030)

2.6 Bond-Slip

As explained in the preceding section, in precast concrete floor systems, tying

resistance is provided by the reinforcement between the floor units. It is therefore

important that this means of resistance is reliably quantified.

The tying resistance critically depends on the bond-slip behaviour between the

reinforcement and the concrete. This behaviour is complex due to the nature of

concrete and other factors such as: randomness of the size, shape and texture of the

aggregates, and chemical and physical adhesion between the reinforcement and

concrete. Many research studies have been devoted to this subject; examples

including (Naaman and Najm, 1991), (Lahnert et al., 1986), (Edwards and

Yannopoulos, 1979), (Huang et al., 1996), (Engström et al., 1998), (Mazzarolo et

al., 2012).

Depending on the length of the reinforcement, there are two generic modes of bond-

slip behaviour: tie bar pull-out (anchorage failure) in the case of short tie bar and tie

bar yield in the case of long tie bar. There have been pull-out tests conducted on the

Page 52: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

52

tie bar embedded in the grouting between the PCFSs (Regan, 1975), (Holmgren,

1975). The findings of these experiments can be helpful in the sense that when the tie

bar is embedded in the concrete and then tensioned, its strain is localised to the

section of the bar protruding from the concrete face, unlike the free steel bar along

which strain can be distributed more. To have more elongation of the tie bar

embedded in concrete, the use of smooth steel bars is suggested, but on the other

hand this type of bar would not provide enough bond with the surrounding concrete.

Hence in the present study the bond condition between steel and concrete is derived

with the assumption that grooved bars are embedded in concrete.

Similar tests by Engström et al. (1998) and Salo et al. (1984) focus on embedment

length in order to prevent anchorage failure of the tie bar in the connection between

PCFSs. Engström suggests that when the tie bar is grouted in the cores of the PCFS,

the embedment length should be between 0.5 m to 1 m. And (Salo et al., 1984)

suggest anchorage length of less than 60ϕ (where ϕ is the diameter of the tie bar) is

susceptible to failure. Later CCIP-030 regulated the anchorage length to be 75ϕ

(Whittle and Taylor, 2009). These recommendations will be checked in this study

through comparison with FE simulations (section ‎3.2.3) and it will be shown that the

BS regulations regarding tie bar length satisfy the required bond conditions between

reinforcement and surrounding concrete.

The two types of bond-slip behaviour are summarised in the CEB-FIP Model Code

2010 (CEB-FIP 2010) and are shown in Figure ‎2-18. For type I bond-slip

relationship the following relationships are provided:

Equation ‎2-15

Equation ‎2-16

Equation ‎2-17

Equation ‎2-18

Where:

Page 53: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

53

τ‎is‎the‎bond‎stress

: is the bond strength (dependent on concrete strength)

: is the residual bond stress (dependent on concrete strength)

s: the slip of steel bar in concrete in millimetres

α,‎ : are the coefficients that can be found based on the concrete and bond

conditions in the tables below:

Table ‎2-4: Type I (tie bar pull-out) bond-slip relationship parameters (CEB-FIP 2010)

1 mm

3 mm

Clear rib spacing

3

α 0.4

Figure ‎2-18: Generic bond-slip relationships (CEB-FIP 2010)

For type II bond-slip relationship, the parameters in Table ‎2-5 are used.

Page 54: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

54

Table ‎2-5: Parameters for Type II (tie bar yield) bond-slip relationship

1 mm

3 mm

Clear rib spacing

2

where fcm is the concrete cylindrical compressive strength.

It is assumed that the shear bond stresses over the area made up of the perimeter of

the tie bar multiplied by its length, should at least be equal to the product of steel

yield stress and its cross sectional area. By this method the minimum length that

provides the necessary bond stress which results in the yielding of the tie bar can be

determined (Mazzarolo et al., 2012):

Where:

fy: steel reinforcement yield stress

As: rebar cross sectional area

p: the perimeter of the steel reinforcement

lmin: is the length that if the reinforcement is less than, it does not yield

To apply and evaluate the bond-slip relationship in the connection between PCFSs

the tests conducted on long embedment of reinforcement in concrete are studied in

more detail in ‎Chapter 3.

Page 55: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

55

2.7 Summary and Objectives of Research

This chapter presented a brief review on robustness regulations in British Standard

and the background from which these rules have originated. It was shown that, in

particular, the tying method regulations are derived from the assumption that ties

connecting the slabs are able to develop catenary action. Then at catenary stage

where all the structural members are supposed to be in equilibrium, force values

required in ties to balance typical structural loads are recommended to be sufficient

to provide adequate robustness. The present study examines the initial assumption of

the British Standard about deformation capacity of ties, and casts doubt on available

tie ductility with current rules since they focus merely on the tie force.

It was seen that although the capability of current tying regulations has been

questioned (CPNI, 2011) yet the literature lacks substantial study into the behaviour

of ties and design parameters that may affect that. The only study concentrating on

PCFS and tie connection has been conducted by Engström (1992). It was seen that

since the tests were conducted without axial restraint, ties were not fully tensioned

and consequently the results could not represent precise tie behaviour of a real

structure. The assumptions made in derivation of an analytical relationship by

Engström (1992) for predicting the tie connection behaviour, also weaken the

resemblance of the analysed model compared to real connection behaviour. Hence

the necessity of research into the ductility of tie bars and the parameters affecting

that behaviour was established. This leads to the main objectives of this research as:

- To understand the load carrying mechanism for robust precast concrete floor

construction.

- Assessment of the adequacy, or lack thereof, of the current structural

robustness specification in achieving robust precast concrete floor

construction.

- To investigate methods of changing tie bar properties for enhancing

robustness of precast concrete floor construction.

For the tie bar to be able to facilitate its elongation to the fullest extent, it is

necessary to have enough bond with the concrete in which it is embedded. This

Page 56: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

56

research will include some investigation on how to provide sufficient bond to allow

the tie bar to achieve its full tying force and elongation capacity.

Page 57: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

57

Chapter 3. Validation of Numerical Modelling

The results reported in this thesis have been obtained by numerical simulations using

the finite element program DIANA (TNO-DIANA, 2010). This software package

was chosen for its ability to handle complex concrete behaviour. This chapter

presents examples of validating the numerical model. In analysis of robustness of

precast concrete floor slabs, the two important requirements for accurate modelling

are large deflection behaviour and bond slip relationship for the tie bar. This chapter

will present validation examples for these two situations: the experiments of Su et

al. (2009) numerical models for dealing with large deflection behaviour, including

both arching and catenary action in reinforced concrete members. And for

validating modelling of bond slip behaviour, some experiments by Engström et al.

(1998) were modelled.

3.1 Choosing DIANA FE Package

Initially in the present study, the commercial FE package ABAQUS was used to

model concrete structural elements in large deflections. However, as concrete has

proved to be a very sensitive material to be modelled in geometric nonlinearity

problems, the author was not able to obtain results that agreed with the experimental

results, especially for concrete members in catenary action stage. This deficiency has

also been observed by other researchers (Lee, 2009), (Garden, 1997). Hence the

general finite element software DIANA was used instead.

The main shortcomings of ABAQUS include:

1) Concrete‎ is‎modelled‎ in‎ABAQUS‎ either‎ by‎ “smeared‎ cracking‎model”‎ or‎

“damaged‎plasticity‎model”.‎The‎latter assumes that concrete is an isotropic

material even after cracking (cracks happening in orthogonal directions with

respect to each other) which is far from the reality of concrete behaviour.

However, if using the smeared cracking model, ABAQUS would not allow

the‎use‎of‎smeared‎cracking‎model‎in‎“ABAQUS‎Explicit”‎which‎would‎be‎

Page 58: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

58

necessary for numerical simulation stability. DIANA, on the other hand,

provides more suitable options as explained in sections ‎3.2.1 and ‎3.2.2.

2) The suitable modelling method for reinforcement in ABAQUS for the

present‎study‎would‎be‎the‎“embedded”‎option‎since‎the‎steel‎bar‎should‎be‎

modelled as an explicit material from concrete (the other option only assumes

higher stiffness for the concrete element which has the rebar). This option

assumes full bonding of reinforcement and the surrounding concrete. This

assumption would not be appropriate because it is necessary in the present

study to consider bond-slip phenomenon between the steel bar and concrete.

In contrast, DIANA allows the bond-slip function for reinforcement to be

modelled explicitly in concrete.

3.2 Modelling concrete in DIANA

There are two main material modelling methods available in DIANA: a) smeared

cracking and b) discrete cracking. In the smeared cracking approach, when the

tensile strength of concrete is breached in an integration point, it is assumed that

concrete is cracked and can carry no more tension at that point. On the other hand, to

model the cracks discretely specific interface elements are used which dictated the

knowledge of exact crack location in advance. The discrete cracking approach may

represent the discontinuity in the material better, but invokes some numerical

difficulties when used with other interface elements (TNO-DIANA, 2010). As in the

present simulation the effect of bond-slip needs to be taken into account, which is

modelled with interface elements available in the software for this purpose, the

smeared cracking approach is chosen.

The chosen smeared cracking approach (Multi-directional fixed crack model)

introduces several nonlinear plasticity models for both compressive and tensile

regimes of concrete. The compressive plasticity models include:

Tresca & Von-Mises

Mohr-Coulomb

Drucker-Prager

Page 59: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

59

And the tensile regime modelling consists of:

Brittle cracking

Linear tension softening

Multi-Linear tension softening

Moelands tension softening

Hordijk tension softening

3.2.1 Compressive Behaviour

3.2.1.1 Tresca

Tresca yield criterion is based on maximum shear stress. In principal stress space

(σ1>σ2>σ3), shear stress is defined as the difference between maximum and

minimum stresses:

| | | | | | Equation ‎3-1

Where σ1, σ2, σ3 are the principal stresses in a multi-axial stress state, and σy is the

yield strength.

3.2.1.2 Von-Mises

The Von-Mises criterion is a smoother approximation of the Tresca yield function

(Figure ‎3-1).

√ [

] Equation ‎3-2

Both Tresca and Von-Mises are usually used for ductile material such as steel.

Figure ‎3-1: Tresca and Mohr-Coulomb yield criteria (TNO-DIANA, 2010)

Page 60: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

60

3.2.1.3 Mohr-Coulomb

Mohr-Coulomb criterion is an extension of Tresca, but the yield function is mostly

dependent on the pressure. In a multi-axial principal stress state its function is

expressed as:

Equation ‎3-3

Where:

φ: is the internal frictional angle (usually ≈ 30o for concrete (TNO-DIANA, 2010))

c: is the cohesion:

Mohr-Coulomb yield function is usually used for concrete and other brittle materials.

This yield criterion shows more compatibility with test results over other

compressive behaviour options.

3.2.1.4 Drucker-Prager

Drucker-Prager is a smooth approximation of the Mohr-Coulomb (Figure ‎3-2). This

criterion in terms of principal stresses reads:

Equation ‎3-4

Where:

In the Drucker-Prager criterion the internal frictional angle is recommended to be

taken as 10o (TNO-DIANA, 2010).

This model is used mostly for modelling the plasticity of soil and masonry materials.

Page 61: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

61

Figure ‎3-2: Mohr-Coulomb and Drucker-Prager yield criteria (TNO-DIANA, 2010)

3.2.2 Tensile Behaviour

3.2.2.1 Brittle Cracking

In this cracking criterion after the tensile stress in a point reaches the tensile strength

of the concrete it is assumed that the stress suddenly drops to zero and the element

carries no more tension at that point (Figure ‎3-3).

Figure ‎3-3: Brittle Cracking Behaviour (TNO-DIANA, 2010)

This model does not reveal compatible results with the experimental results in

catenary action of the concrete structural members, as it sometimes causes

discontinuity, and also does not capture the tension stiffening effect of reinforced

concrete.

Page 62: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

62

3.2.2.2 Linear Tension Softening

This model assumes the tensile stress in a cracked element decreases in a linear

fashion (Figure ‎3-4).

Figure ‎3-4: Linear tension softening (TNO-DIANA, 2010)

The line of tension softening is defined by the fracture energy of the concrete (Gf).

The fracture energy is defined as the energy required to form a tensile crack of unit

area, and was calculated based on the CEB-FIP Model Code 2010 regulations. This

tension model showed acceptable results when compared to experimental results of

(Engström, 1992) and (Su et al., 2009) and was used as the tension softening model

in the simulations presented in this chapter.

Parameter h is the crack band width calculated by DIANA, which depends on the

element size (Table ‎3-1):

Table ‎3-1: Crack band width calculation (TNO-DIANA, 2010)

Element Type Crack band width (h)

Linear 2D √

Quadratic 2D √

3D √

Where A and V are the element area and volume respectively.

By assuming gradual decrease in tensile strength after the concrete has cracked, the

linear tension softening model, unlike the brittle cracking softening model, enables

tension stiffening of reinforced concrete to be modelled in a numerically stable

manner. Since it is the reinforcement that carries tensile forces during the catenary

action stage which is the main concern of this research, it will be shown that

Page 63: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

63

assuming linear stiffening of concrete yields numerical simulation results in good

agreement with the test results (section ‎3.3.4).

3.2.2.3 Moelands Tension Softening

The Moelands tension softening relationship is a modification of the linear tension

softening and it is advised to be used in cases if the linear tension softening causes

convergence problems (Figure ‎3-5).

Figure ‎3-5: Moelands Tension Softening (TNO-DIANA, 2010)

The normalized relationship for the Moelands curve is defined as:

{

(

)

Equation ‎3-5

3.2.2.4 Hordijk Tension Softening

Hordijk tension softening model is defined by the following relationship

(Figure ‎3-6):

{

( (

)

) (

)

Equation ‎3-6

Page 64: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

64

Figure ‎3-6: Hordijk tension softening (TNO-DIANA, 2010)

As with the linear tension stiffening model, the Hordijk and Moelands tension

softening models also give gradual reduction of tensile strength of concrete in a

cracked element, which helps with numerical stability. However, with a given

fracture energy, the linear tension softening model assumes a steeper reduction in

concrete tensile strength immediately after cracking. Hence, it gives concrete a lower

ultimate cracking strain ( ).‎This‎affects‎the‎“fracture‎energy/band‎width”‎ratio‎

(

area under the curve of tension softening models).

Figure ‎3-7: Comparison of tension softening models

As shown in Figure ‎3-7 a higher ultimate cracking strain, resulting from nonlinear

tension softening models (Moelands and Hordijk), leads to a higher tension

stiffening effect and consequently failure of the structure occurs at a higher vertical

displacement.

-500

-400

-300

-200

-100

0

100

200

300

0 0.05 0.1 0.15 0.2 0.25 0.3

Ho

rizo

nta

l R

eact

ion

V

erti

cal

Lo

ad

(kN

)

Vertical Displacement (m)

Test A1

Linear A1

Moelands A1

Hordijk A1

Page 65: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

65

3.2.3 Bond-Slip

There are interface elements available in the material model bank of DIANA for

modelling the bond-slip behaviour of reinforcement in concrete. These include:

Dörr Model (Figure ‎3-8):

Figure ‎3-8: Cubic function of Dörr model (TNO-DIANA, 2010)

This function is defined by:

{ ( (

) (

)

(

)

)

Equation ‎3-7

Noakowski Model (Figure ‎3-9):

Figure ‎3-9: Power Law of Noakowski (TNO-DIANA, 2010)

Page 66: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

66

Which is defined by:

{

Equation ‎3-8

Multi-linear Model

As it can be seen in Figure ‎3-8 and Figure ‎3-9, the two predefined relationships for

bond-slip behaviour are for modelling local bond-slip effect and do not consider the

“pull-out”‎or‎“yield‎and‎pull-out”‎failure‎modes‎of‎the‎this‎phenomenon.‎Hence‎the‎

bond-slip relationship used for modelling the tests in this study is the Multi-linear

Model which allows the user to define the relationship between the bonds stress and

slip. As mentioned in the literature review chapter this relationship is calculated

based on the CEB-FIP Model Code 2010.

3.2.4 Concrete Elastic Material Properties

3.2.4.1 Tensile Strength

The CEB-FIP Model Code introduces a relationship for calculating the tensile

strength based on compressive strength:

(

)

Equation ‎3-9

Where:

fctm: mean axial tensile strength

fcrko,m= 1.40 MPa

fck: Compressive strength

fcko=10 MPa

Page 67: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

67

3.2.4.2 Elastic Modulus

The elastic modulus of concrete in the CEB-FIP Model Code 2010 can be calculated

using the following relationship:

Equation ‎3-10

Where:

Eci: is the concrete elastic modulus

Ec0 = 2.15 ×104

fck: Compressive strength

Δf = 8 MPa

3.3 Axially Restrained Beams (Su et al., 2009)

Although the subject matter of this thesis is reinforced concrete slabs, the main focus

of this research is development of catenary action of axially restrained member. For

this behaviour, the experimental work of Su et al. (2009) is the most relevant for the

purpose of validation, even though the subject matter of their research is reinforced

concrete beam. In particular, the work of Su et al. (2009) was in the context of

structural robustness under column removal scenarios, which is closely related to the

present research.

Su et al. (2009) referred to some axially restrained slab tests by Guice and Rhomberg

(1988). However, this study was mainly focused on slab capacity under compressive

membrane action, which is not suitable for the purpose of progressive collapse

investigation where the slab deflection is rather high. Therefore, the tests of Guice

and Rhomberg (1988) were not used in the validation study of this research.

Page 68: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

68

3.3.1 Test Subassemblies & Setup

As shown in Figure ‎3-10 each test subassembly consisted of two doubly reinforced

concrete beams connected with a central column stub and two short columns at the

two far ends. The centre column represented the lost column and had a 250 mm

square base for all the specimens, but the edge columns were with enlarged sizes for

ease of being anchored into the test setup.

Figure ‎3-10: Test Subassembly and Reinforcement Layout (Su et al 2009)

The test specimens constructed were varied in their reinforcement (A-series), beam

geometry (B-series), and the loading speed (C-series). The A-series specimens varied

in flexural reinforcement ratio (from 2ϕ12 to 3ϕ14), with the cross section

dimensions being the same (150 mm wide (b), 300 mm deep (h), span length (ln)

1225 mm (span to depth ratio of 4.08). In the B-series, the cross sections of all the

specimens were the same as for the A-series, but their span to depth ratio (ln/h) was

variable, with the range being from 6.58 to 9.08. The C-series tests examined the

effects of loading rate. This series of tests was chosen to examine the influence of

dynamic loading caused by rapid column removal. Since in this study, it was

assumed that loading acts in a static manner, only the A and B-series of the tests

were modelled.

The concrete cube strength fcu for the specimens in this experiment varied from 23.3

to 39 MPa. The yield strength for the steel reinforcement varied from 290 to 340

Page 69: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

69

MPa, and the reinforcement diameter varied between 12 and 14 mm. Table ‎3-2 lists

the main parameters of the tests simulated in this research.

Table ‎3-2: Specimen Properties

Test

b × h

(mm)

ln

(mm)

fcu

(MPa)

Longitudinal

Reinforcement

Ties fctm

(MPa)

Ec

MPa

Top Bottom

A1 150 x

300

1225 32.3 2ϕ12 2ϕ12 ϕ8

@100

3.05 34214.23

A2 150 x

300

1225 35.3 3ϕ12 3ϕ12 ϕ8

@80

3.24 35042.98

A3 150 x

300

1225 39.0 3ϕ14 3ϕ14 ϕ8

@80

3.46 36013.98

B1 150 x

300

1975 23.3 3ϕ14 3ϕ14 ϕ8

@100

2.45 31449.95

B2 150 x

300

2725 24.1 3ϕ14 3ϕ14 ϕ8

@120

2.51 31715.64

B3 150 x

300

2725 26.9 3ϕ14 2ϕ14 ϕ8

@120

2.67 32455.72

The load was applied through the centre column. During the test, the vertical

displacement and load at the centre column stub were measured by a built-in load

cell and a displacement transducer. The horizontal and the vertical reaction forces at

the beam ends were measured at the support columns; however the exact locations of

measurement was not specified in the test report (Su et al., 2009). Figure ‎3-11 shows

the test setup. For the A- and B- test series, the load was applied with displacement

control at a constant rate of 5 mm/min, except for initial state and during the pauses

for inspection. In the C test series, the displacement rate was 0.2, 2, and 20 mm/s.

Page 70: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

70

Figure ‎3-11: Test Specimen and Schematic Illustration of Test Setup (Su et al, 2009)

The two end columns were restrained axially, vertically and rotationally to simulate

the possible restraints applied to the concrete beam ends by the rest of the structure

in real building. To obtain the horizontal and rotational stiffness of the beam ends,

the corresponding displacement of the side columns were measured, but the exact

locations of measurements were not given in the original publication (Su et al 2009).

The reported values for horizontal and rotational stiffness of the connection between

the end column and the steel socket are 1000’000 kN/m and 17,500 kN-m/rad

respectively.

Using these reported stiffness values caused the FE model to predict higher

compressive arching action, and correspondingly higher axial reaction forces than

the test results; meaning that the used stiffness values were higher than what have

been applied on the test specimens. Through a correspondence between the author

and the researchers of the experiments (Miratashi, 2011), it was established that the

actual boundary stiffness may vary from what was reported. The researchers

suggested values of 1/10th

of the reported ones, stating that such values were

obtained from more precise measurements of their similar ongoing tests using the

same apparatus. Applying the modified values again overestimated the arching

action and corresponding axial reaction force at the beam ends. Hence to find the

Page 71: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

71

appropriate restraint stiffness values, the author had to conduct an extensive set of

numerical simulations until one set of restraint stiffness values gave simulation

results consistently being in good agreement with the experimental results for all the

tests. These values were 1500 kN/m and 75 kN-m/rad for the axial and rotational

stiffness respectively.

3.3.2 Typical Beam Behaviour to Reach Catenary Action

Model A3 is used to show different stages of behaviour of the beams. Figure ‎3-12

shows the applied load on this beam and the horizontal reaction force in the supports.

Initially, steel acted in an elastic manner (up to Point B), and because the beam

deflection was very small, there was very little axial reaction force in the beam (up to

Point A). At larger deflections, the lower edge of the concrete beam at the supports

bore against the supports, thus developing compressive arching action.

The development of compressive arching action continued until the maximum at C

and D. Afterwards, the maximum compressive stress in concrete was reached and the

compressive membrane action force decreased. This was accompanied by a

reduction in the applied load that can be resisted by the beam (from C to E in

Figure ‎3-12). When the beam deflection was about ½ of the beam depth,

compressive arching action diminished and the beam quickly underwent large

deflections and activated catenary action (point E). Catenary action was stable and

the applied load on the beam increased until failure of the beam due to reinforcement

fracture (point F).

Page 72: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

72

Figure ‎3-12: Behaviour of Stages of model A3

3.3.3 Finite Element Model

Due to the symmetry in both the test specimen geometry and loading, the finite

element model simulated only a quarter of the beam. For the sake of simplicity and

computational efficiency, the side columns were not included in the model; instead,

their effects were represented by a rotational stiffness of 75 kN-m/rad and an axial

stiffness of 1.5E3 kN/m. The downward displacement in the tests was modelled as a

prescribed displacement on the model beam end (corresponding to the actual beam

centre column stub). The test beam was doubly reinforced with stirrups spaced at

distances of 80-120 mm along the beam.

For the concrete beam, twenty noded solid brick quadratic elements (CHX60) were

used. This element type is consistent with the selected method of modelling the

reinforcement in DIANA. Both the longitudinal and transverse reinforcements were

modelled by the embedded reinforcement option available in DIANA.

-400

-300

-200

-100

0

100

200

300

0 0.05 0.1 0.15 0.2 0.25

Ho

rizo

nta

l R

eact

ion

V

erti

cal

Lo

ad

(kN

)

Vertical Displacement (m)

Test A3

A

BC

D

E F

Page 73: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

73

Table ‎3-3: FE models divisions along 3D axis for mesh sensitivity study

Model Division Along

x-axis

Division Along

y-axis

Division Along

z-axis

A 1 1 8

B 1 2 16

C 1 2 24

D 2 4 32

E 3 8 32

F 3 8 48

G 4 10 56

H 4 10 64

The mesh size chosen for the model was based on the results of a mesh sensitivity

study using eight different element sizes (Table ‎3-3). Figure ‎3-13 shows the results

of mesh sensitivity study. Based on this result, mesh E can be used.

Figure ‎3-13: Results of mesh sensitivity study

0

50

100

150

200

250

A B C D E F G H

Ver

tica

l L

oa

d (

kN

)

Models

Page 74: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

74

Figure ‎3-14: Finite element model

The prescribed displacement was applied on a node in the middle of the beam, and

the mentioned node was constrained vertically with adjacent nodes within a distance

of 125 mm to represent the middle column stub of the actual test set up. The far end

surface of the model is restrained totally in the vertical (y) direction and rotational

and axial stiffness have been provided by spring elements attached to the nodes of

this surface. Figure ‎3-14 shows a typical finite element model. The solution method

chosen for this model was the tangential regular Newton method which revealed

better results than the other solution methods.

3.3.4 Comparison between Simulation and Test Results

Figure ‎3-15 and Figure ‎3-16 show comparison between the simulation and test

results for the A and B-series of tests respectively, showing the applied load- and

axial reaction-vertical displacement relationships. In all cases, the observed arching

action and catenary action stages were closely followed by the numerical simulation

results.‎Furthermore‎the‎tests’‎failure‎was‎defined‎based‎on‎the‎rupture‎of‎the‎tensile‎

reinforcement in the bottom of the section in the beams close to the centre column

stub. This is shown with the terminating points of the diagrams.

Prescribed

displacement

Page 75: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

75

(a)

(b)

(c)

Figure ‎3-15: Comparison of experiment and FE results for A-series

Due to lower span to depth ratio of the A-series specimens, the development of

arching action was more than the B-series. This resulted in higher applied load to the

structure and less vertical displacement. In models A3 and B1, as the tensile

-500

-400

-300

-200

-100

0

100

200

300

0 0.05 0.1 0.15 0.2 0.25

Ho

riz

on

tal R

ea

cti

on

Verti

ca

l L

oa

d

(kN

)

Vertical Displacement (m)

Test A1

FE A1

-400

-300

-200

-100

0

100

200

300

0 0.05 0.1 0.15 0.2 0.25

Ho

riz

on

tal R

ea

cti

on

Verti

ca

l L

oa

d

(kN

)

Vertical Displacement (m)

TestA2

FE A2

-400

-300

-200

-100

0

100

200

300

0 0.05 0.1 0.15 0.2 0.25

Ho

riz

on

tal R

ea

cti

on

Verti

ca

l L

oa

d

(kN

)

Vertical Displacement (m)

Test A3

FE A3

Page 76: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

76

reinforcement in the bottom of the section had a higher cross sectional area, concrete

reached its compressive strength and there was a sudden drop of the applied load.

In B-series models due to higher span/depth ratio the tensile reinforcement enabled

the models to develop more into the catenary stage and hence in them the final

applied load was higher than the load due to arching action. The axial reaction force

of all the models depict that after arching action (where the maximum axial force

occurred) the decrease in the axial force is a representation of onset of the catenary

action.

Page 77: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

77

(a)

(b)

(c)

Figure ‎3-16: Comparison of experiment and FE results B-series

The presented results manifest the capability of the finite element modelling for

capturing the concrete cracking, crushing and its interaction with the reinforcement

inside. It is shown that by proper plasticity model of concrete and its cracking, the

FE model is able to predict the behaviour of the specimens in catenary action stage.

-300

-250

-200

-150

-100

-50

0

50

100

150

200

0 0.1 0.2 0.3 0.4 0.5

Ho

riz

on

tal R

ea

cti

on

Verti

ca

l L

oa

d

(kN

)

Vertical Displacement (m)

FE B1

Test B1

-250

-200

-150

-100

-50

0

50

100

150

200

0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4

Ho

riz

on

tal R

ea

cti

on

Verti

ca

l L

oa

d

(kN

)

Vertical Displacement (m)

Test B2

FE B2

-250

-200

-150

-100

-50

0

50

100

150

0 0.1 0.2 0.3 0.4 0.5

Ho

rizo

nta

l R

eact

ion

V

erti

cal

Lo

ad

(kN

)

Vertical Displacement (m)

Test B3

FE B3

Page 78: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

78

Also the plasticity model used for reinforcement was able to simulate the rupture of

the reinforcement close to the test results.

3.4 Verification of Bond-Slip Modelling

In the tests of Su et al. (2009), the longitudinal reinforcement was throughout the

length of the beam. Therefore, there was no reinforcement pull-out. However,

reinforcement pull-out may occur when using tie bar if the tie bar length is not

sufficiently long. It is important that the tie-bar bond-slip behaviour is accurately

modelled. For this purpose, the experiments conducted by Engström et al., 1998

were used. These experiments focused on the global bond-slip behaviour of the steel

tie-bar. Some of the test results used here, related to same series of experiments, are

reported in (Huang et al., 1996).

3.4.1 Test Specimens and Variables

Two types of specimens (shown in Figure ‎3-17) were modelled: I) concrete cubes

(400mm) with the steel rebar being placed in the centroid; II) concrete cuboids of

cross section 400 × 400 mm and the length of 400 or 500 mm with the steel rebar

being placed in the middle of the side to check the effect of the concrete cover on the

bond-slip behaviour. This type of specimen was provided with an extended nose-like

part to help the support of specimen in the testing machine and to balance the

eccentricity of the applied load. Both high strength and normal strength concretes

were considered for both specimen types.

Page 79: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

79

Series-I Series-II

Figure ‎3-17: Test specimens of type I and II (Engström et al., 1998)

The embedment length of the steel rebar in concrete varied between 90 to 250 mm

for specimens made with high strength concrete, and between 150 to 500 mm for

normal‎strength‎concrete.‎The‎steel‎ rebar’s‎nominal‎yield‎stress‎was‎reported‎ to‎be‎

500 MPa but the actual value from the tensile test was recorded as 569 MPa. The

steel rebar diameter was 16 mm in all specimens.

The concrete cover to the reinforcement in specimens of type (I) was 192 mm

(=12ϕ). The concrete cylindrical compressive strength was reported to be about 30

MPa for normal strength type and 110 MPa for high strength concrete. The fracture

energy for normal concrete ranged from 110 N/m to 165 N/m for the high strength

type. The tests were carried out after 40 days of concrete casting. Table ‎3-4 lists the

test‎specimens’‎characteristics.

Page 80: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

80

Table ‎3-4: Characteristics of the test specimen (Engström et al., 1998)

Test Types of

specimen

Bar

Location

Concrete

compressive

Strength

(MPa)

Concrete

Cover

(mm)

Embedment

Length

(mm)

N290 I centroid 30.6 192 290

N500 I centroid 26.8 192 500

H170 I centroid 101.5 192 170

N290m-16 II Mid-edge 28.6 16 290

H170m-16 II Mid-edge 110.9 16 170

The loading was applied by at the rate 0.1 mm/min at the end of the rebar protruding

out of the concrete block (the active end of the rebar). Slip was measured at the end

of the steel rebar relative to the nearest concrete.

3.4.2 Finite Element Model

For modelling bond-slip, DIANA introduces the reinforcement by interface elements

which have normal and tangential stiffness defined by user. The behaviour of the

interface element in the normal direction is assumed to be linear, but the behaviour

in the tangential direction (between shear stress and strain) can be considered as

nonlinear. There are two predefined material models for the relationship between

shear stress and strain and the user is provided with an option to define this

relationship. The relationship in CEB-FIP Model Code 2010 (section ‎2.6) was used

herein.

Table ‎3-5: Calculated concrete material properties (based on CEB-FIP Model Code 2010)

Model fc

(MPa)

ft

(MPa)

Ec

(MPa)

τmax

(MPa)

τy

(MPa)

τf

(MPa)

τy,f

(MPa)

lmin

(mm)

H170 101.5 6.21 46550.8 45.67 34.25 18.27 9.13 49.83

N290 30.6 2.41 31213.73 13.77 10.32 5.5 2.75 165.28

N500 26.8 2.13 29864.14 12.06 9.04 4.82 2.41 188.72

N290m-16 28.6 2.26 30518.3 12.87 9.6525 5.148 2.574 176.84

H170m-16 110.9 6.62 47945.6 49.90 37.42 19.96 9.981 45.60

The tensile strength and elastic modulus of concrete were calculated using

Equation ‎3-9 and Equation ‎3-10. However, for the elastic modulus, the CEB-FIP

Model Code advises that when the actual compressive strength of concrete at the age

of 28 days is known, the term Δf must be dropped from the relationship which is the

Page 81: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

81

case for this experiment; and in the tensile strength relationship Δf must be deducted

from fcm (CEB-FIP, 2010). Since the steel rebar used in all of the test specimens is

the same, the slip values for the bond-slip diagram are constant (as slip is related to

the rib spacing of rebar). The calculated values for bond stress based on CEB-FIP

Model Code 2010 are shown in Table ‎3-5.

Figure ‎3-18: Concrete block FE model for simulation of bond-slip tests

Specimen Type I

Specimen Type II

Load

Rebar

Page 82: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

82

The concrete model used in the finite element model to simulate these tests is

smeared cracking with Mohr-Coulomb plasticity and linear tension softening

behaviour. For better results and time efficiency, the 8-noded solid elements

(HX24L)‎were‎used‎for‎the‎concrete‎and‎the‎interface‎elements‎(“bar‎in‎solid”‎type,‎

HX30IF) were chosen to simulate the bond-slip interface between the concrete and

steel rebar. The reinforcement was modelled using the 2-noded truss element

(L6TRU) compatible with the solid element of concrete and bond-slip interface

element. The element size was 50 mm.

As reported in the experiment, the concrete block was supported in the axial

direction (in the same direction as loading) on the loading face by steel plates

covering 10 cm of the concrete surface on each side of the reinforcement in type I. In

the finite element model the other end of the specimen was constrained in the four

corner points to avoid any trivial movement. For type II, the nose-shape part of the

concrete block is restrained in all directions and the bottom of the concrete block

close to the reinforcement is restrained in the parallel direction to the reinforcement (

Figure ‎3-18).

3.4.3 Comparison between Simulation and Test Results

Figure ‎3-19 compares the load-slip curves. The simulation results are very close to

the test results. For test specimen type I, in the load-slip diagram after the maximum

load is reached, there is a plateau which marks yielding of the steel rebar, and this is

accurately captured in the numerical simulation. Afterwards, the applied load

decreases, reflecting pull-out failure or rupture of the reinforcement; again the

numerical simulation results follow the test results closely.

Page 83: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

83

(a)

(b)

(c)

Figure ‎3-19: Comparison of experiments with FE results

For specimens type II, since the concrete cover is not enough to provide the

reinforcement with adequate bond, the reinforcement is not yielded before being

pulled-out (Figure ‎3-20). Here after the maximum load is reached, the bond stress

declines which marks the failure of the model.

0

20

40

60

80

100

120

140

0 2 4 6 8 10 12 14 16

Axia

l L

oa

d (

kN

)

Slip (mm)

FE

N290b

0

20

40

60

80

100

120

140

0 5 10 15 20

Axia

l L

oa

d (

kN

)

Slip (mm)

Experiment N500

FE

0

20

40

60

80

100

120

140

0 2 4 6 8 10 12 14 16

Axia

l L

oa

d (

kN

)

Slip (mm)

FE

Experiment H170

Page 84: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

84

(a)

(b)

Figure ‎3-20: Comparison of experiment and FE results, Type II

Figure ‎3-21 shows‎the‎deformed‎shape‎of‎the‎model’s‎mesh:

Figure ‎3-21: Bond-Slip specimens deformed mesh, Types I and II

0

20

40

60

80

100

120

0 2 4 6 8 10 12 14 16

Axia

l L

oa

d (

kN

)

Slip (mm)

Experiment N290m-16

FE

0

20

40

60

80

100

120

140

0 2 4 6 8 10 12 14 16

Axia

l L

oa

d (

kN

)

Slip (mm)

FE

H170m-16

Page 85: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

85

3.5 Summary

In this chapter the capability of the commercial finite element software DIANA was

evaluated against analysis of concrete in large deformation in order to capture the

arching and catenary action behaviour of reinforced concrete structural members. It

was shown that the most suitable material model for concrete was the Mohr-

Coulomb plasticity in compression regime along with the tension softening in

tension. The reinforcement was modelled as embedded rebar in concrete with Von-

Mises perfect plastic behaviour. The suitable mesh for concrete was determined in a

sensitivity study. The FE model was able to predict the failure of the Su, et al. (2009)

experiments with good agreement. The model was able to depict catenary and

arching actions.

The material models of concrete and steel, and the bond-slip interface of DIANA

proved to be a powerful tool in predicting the pull-out tests of Engström et al.,

(1998). The bond-slip relationship was calculated based on the relationships

provided by CEB-FIP Model Code 2010.

Page 86: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

86

Chapter 4. Parametric study of 2D Restrained

Slab

This chapter presents the results of an extensive parametric study of design

parameters on the behaviour and load carrying capacity of 2-D concrete floor slabs.

The objectives of this parametric study are:

(1) To investigate the effects of different design parameters with a view of how to

improve slab resistance;

(2) To provide a comprehensive database of results for the development and

validation of an analytical method that may be used as a design tool.

Figure ‎4-1 shows the simulated structure. It represents the accidental loading

condition of losing the centre column/beam support of a two-span precast panel

structure. The parameters considered here that affect the behaviour and load carrying

capacity‎of‎the‎slab‎are‎taken‎from‎the‎‎connections‎and‎the‎slab,‎including‎:‎tie‎bar’s‎

length,‎ diameter,‎ position,‎ yield‎ stress;‎ slabs’‎ height‎ and‎ length;‎ concrete‎ grouting‎

compressive strength; and the stiffness of the constraint by which the slabs are

connected to the rest of the structure.

Figure ‎4-1: Two-dimensional representation of the slabs with pinned BC

Precast Concrete Slabs

Steel Tie Bar

Lost Column

Page 87: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

87

The results will provide insight into whether or not the tying mechanism is able to

provide sufficient load carrying capacity under the accidental loading condition.

Suggestions will be made based on the condition of the connection between the two

slabs in order to enhance its performance in the case of an accidental action.

4.1 Illustrative behaviour

4.1.1 Slab with total axial restraint

To illustrate the complete range of the behaviour of the structural system, this section

presents the simulation results of two precast concrete floor slabs which have lost

their supporting column at the centre, shown in

Figure ‎4-1. A point load (as a prescribed displacement) was applied at the centre of

the two slabs to simulate the applied floor loads. Herein it was assumed that the

connection to the slabs at their far ends was capable of providing enough rotational

capacity and that they will not rupture.

For this model, the slabs are typical of those used in residential floor system with the

following dimensions: length 5 m, depth 265 mm and width 1.2 m. The

reinforcement diameter is 16 mm to provide the required tying resistance according

to British Standard (BS8110-1, 2007). The concrete is modelled using smeared

cracking with Mohr-Coulomb plasticity and Linear Tension Softening, and the tie

bar in the slabs is modelled using Von-Mises plasticity. Table ‎4-1 lists the material

properties used in this model:

Page 88: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

88

Table ‎4-1: Material Properties used in FE Model

Concrete

Ec 33842.32 MPa

ν 0.2

fc 39 MPa

ft 2.97 MPa

Gf 0.0778 N.mm/mm2

Steel (Tie Bar)

Es 210000 MPa

ν 0.3

fy 500 MPa

As explained in ‎Chapter 3, the general finite element software DIANA was adopted

in this study and concrete was modelled in two dimensions using the 8-noded

quadrilateral plane stress elements (CQ16M) which were able to predict concrete

cracks and the following catenary action properly. To model the bond-slip behaviour

between the tie bar and the surrounding concrete, the 2-noded line interface elements

of L8IF and for the tie bar the 3-noded truss elements of CL6TR were used.

The element sizes were chosen based on a sensitivity study, as explained in ‎Chapter

3. Figure ‎4-2 shows the finite element mesh of the half of the structure with the

applied boundary condition. The mesh around the tie bar in the connection zone,

between the slabs, has been chosen to be finer than the other parts of the structure.

Figure ‎4-2: Mesh view of half of the model (left slab)

Concrete Slab

Steel Tie Bar

Page 89: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

89

Figure ‎4-3-a shows the load-deflection results of the structure of the node on the top

of the connection. The structural behaviour goes through a number of stages before

failure due to the fracture of the tie bar. At the start of loading on the structure, the

behaviour is linear elastic while concrete is contributing to tensile resistance. This

stage terminates when the concrete at the bottom of the connection between the two

slabs reaches its tensile strength. This can be confirmed by the plot of the axial stress

in the bottom of the section (Figure ‎4-3-b). After the concrete has reached its tensile

strength and has developed tensile cracks, the applied load drops before increasing

again due to arching action in concrete.

Page 90: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

90

(a)

(b)

(c)

(d)

Figure ‎4-3: FE Results for the 2D slab Model

-15

-10

-5

0

5

10

15

20

25

30

35

0 100 200 300 400 500

Load

(kN

)

Vertical Displacement (mm)

Accidental Action Load

FE Pinned BC

-0.5

0

0.5

1

1.5

2

2.5

3

3.5

0 100 200 300 400 500Axi

al S

tre

ss in

Mid

dle

Bo

tto

m E

lem

en

t (M

Pa)

Vertical Displacement (mm)

-35

-30

-25

-20

-15

-10

-5

0

5

0 100 200 300 400 500

Axi

al S

tre

ss in

Mid

dle

To

p E

lem

en

t (M

Pa)

Vertical Displacement (mm)

-1200

-1000

-800

-600

-400

-200

0

200

400

0 100 200 300 400 500

Axi

al R

eac

tio

n F

orc

e (k

N)

Vertical Displacement (mm)

Tie Bar Strength

Tie Bar Axial Reaction Force

Page 91: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

91

In arching action mechanism, the axial stress in the middle top element of the

concrete develops a negative, compressive, value (Figure ‎4-3-c) and at the same time

the two pinned constraints at both far ends of the slabs are pushed away from each

other which causes the increase of negative axial reaction force of the end restraints

of the slabs, as shown in Figure ‎4-3-d.

This‎ behaviour‎ continues‎ until‎ the‎ vertical‎ displacement‎ of‎ the‎ slabs’‎ connection‎

reaches a point where the slab tips will cease pressing against each other and start to

move away from one another. As it can be seen in Figure ‎4-3-c and Figure ‎4-3-d, the

maximum negative values of these two diagrams happen at the same vertical

displacement, which shows by splitting the concrete slabs’‎tips‎the‎value‎of‎reaction‎

force starts to decrease too. After this stage, the compressive force is released and

the structure develops catenary action in order to sustain the applied load.

During the catenary action stage, the only load carrying part of the model is the steel

tie bar and this makes the axial reaction force of the restraints to be equal to the yield

force of the tie bar (Figure ‎4-3-d), which at this stage has completely yielded. In fact,

as shown in Figure ‎4-4, the tie bar has yielded in bending, long before the

development of catenary action. Based on the input stress-strain curve, the tie bar

fractures when its maximum strain has reached 20% and rupture of the tie bar marks

the completion of the numerical model (Figure ‎4-4-a). Figure ‎4-4-b shows the tie bar

stress – structural deflection relationship.

Page 92: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

92

(a)

(b)

Figure ‎4-4: Axial tie bar stress in the connection

The horizontal reaction force on the pinned boundary condition depicts that, at the

very early stages of loading, while slabs’‎connection‎has‎a‎linear‎elastic‎behaviour;‎

there is no considerable amount of force exerted to the restraints (Figure ‎4-3-d). But

as the tensile strength of concrete is breached and by the onset of the arching action,

compressive forces are developed in the pinned restraints and this continues until the

arching action is transferred to the catenary action due to separation of the two

concrete slabs. From this point on, the value of the tying force is equal to the product

of the yield stress of the steel and the cross sectional area of the tie bar.

The variation of axial stress of the concrete element near the connection region

between the slabs is a good representation of the behaviour of the slabs, as it can

show the onset and termination of arching action, the occurrence of final crack, and

whether the concrete in the compressive region reaches its strength or is cracked

before that. This can be shown with the plots of the axial stress in the region of

connection between the two slabs with the crack propagation at the main stages of

the behaviour.

0

0.05

0.1

0.15

0.2

0.25

0 100 200 300 400 500

Stra

in

Vertical Displacement (mm)

0

100

200

300

400

500

600

0 100 200 300 400 500

Axi

al S

tre

ss M

idd

le T

ie B

ar E

lem

en

t (M

Pa)

Vertical Displacement (mm)

Page 93: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

93

a b

c d

Figure ‎4-5: Axial Stress and Crack Pattern of Slabs' Connection

Figure ‎4-5-a, shows the concrete stress and crack state just after the linear elastic

limit of the connection. As it can be seen at this stage the axial stresses on top and

bottom of the section are almost the same, however the top fibre of concrete has

Page 94: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

94

negative compressive values and the concrete in the bottom fibre has just passed the

tensile strength of the concrete.

After this stage because of the crack opening in the bottom of the section, the arching

action starts which leads to increased stress in the top fibre of the concrete in the

connection zone. Simultaneously with this phenomenon, the crack propagation

happens from the tensile zone in the bottom of the section (Figure ‎4-5-b). At the time

when the arching action has caused its maximum compressive effect in the concrete,

the vertical displacement of the connection reaches a value that the two slabs start

moving away from one another.

While the slabs move away from each other, cracks take over the whole height of the

connection, and as can be seen in Figure ‎4-5–c the top fibre of concrete in the

connection zone reaches its tensile strength and the final crack of the concrete

section occurs. From this point cracks have reached the top fibre of the connection

and concrete in this region does not carry any load, and it will be the tie bar that

provides the resistive load and helps to develop the catenary action (Figure ‎4-5-d).

4.1.2 Slabs with Elastic Axial Restraint

In realistic structures, the slabs will be connected to other structural members, such

as beams and walls. These components will provide flexible, rather than rigid,

support to the slabs. This section illustrates how the slab behaves if the axial

restraints are elastic. As shown in Figure ‎4-6, it is assumed that the two far ends of

the slabs are connected via a horizontal spring to fixed points and the slab ends are

vertically fixed.

Figure ‎4-6: Schematic 2D Slabs with Elastic Axial Restraints

The axial restraint stiffness to the slabs may be estimated as follows: The stiffness

comes from the remaining columns acting as one fix-ended beam of span 2L under a

point load at its centre (Figure ‎4-7, Figure ‎4-8).

Page 95: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

95

Figure ‎4-7: Columns acting as fixed beams

The stiffness of a beam under a point (Figure ‎4-8) is given in Equation ‎4-1:

Figure ‎4-8: Calculation of stiffness for a fixed beam under a point load

Equation ‎4-1

Using typical column sizes in steel structures with PCFS (Fu and Lam, 2006), (Fu et

al., 2008), a restraint stiffness value of about 50 kN/mm was obtained. Due to infill

walls, the real stiffness may be much higher (Sasani, 2008). In the case of assessing

robustness of one or two slabs of a floor losing their vertical supports, the axial

Lost Support

L

L

PCFS

Remaining Columns

F

F

2L

Page 96: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

96

restraint stiffness to these slabs can be orders of magnitude higher if the effect of in-

plane‎ stiffness‎ of‎ the‎ rest‎ of‎ the‎ floor‎ slabs‎ is‎ considered.‎ So‎ in‎ the‎ author’s‎

parametric study, the axial restraint value ranges from 100 to 10000 kN/m.

Comparing the load-deflection results in Figure ‎4-3 and Figure ‎4-10, it can be seen

that the slabs with rigid and flexible axial restraints undergo similar stages of

behaviour. However, during the initial stage, the development of compressive (arch)

membrane action is reduced as the supports become more flexible. Before full

development of catenary action, slabs with more flexible axial restraint (lower

Boundary Condition (BC) stiffness) experience less catenary force at the same slab

deflection, hence the slab resistance to the applied load is lower. Therefore, at the

same elongation of the tie bar (hence similar bar force and tensile stress in concrete),

the vertical displacement of the slab with lower BC stiffness is higher, as shown in

Figure ‎4-9, where L=L1=L2). This increased vertical deflection results in postponing

total concrete cracking, as shown in the load-deflection curves in Figure ‎4-10.

Figure ‎4-9: Effect of Horizontal Displacement on Vertical Deflection

Once the concrete slab has totally cracked through the thickness, the concrete stress

drops to zero (Figure ‎4-10-b) and the tension force is that of the tie bar (Figure ‎4-10-

c). Once the tie bar has reached its maximum resistance (yield force), the horizontal

displacement of the slab remains constant. At this stage, since the slab resistance

comes from the tie bar tensile force, acting on the slab vertical deflection, the load –

Δ

Δ

h2

h1 L1

L2

L

Page 97: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

97

vertical deflection relationship of the slabs coincide for all the different BC stiffness

values.

(a)

(b)

(c)

Figure ‎4-10: Behaviour of slabs with elastic axial restraint

As shown in Figure ‎4-10(a), in some of the models analysed, the maximum load

carrying capacity of structure before total cracking of concrete is higher than the

maximum resistance after total cracking when the tie bar provides all the tensile

-15000

-10000

-5000

0

5000

10000

15000

20000

25000

30000

35000

40000

0 100 200 300 400 500

Load

(N

)

Vertical Displacement (mm)

Accidental Action LoadBC Stiffness 50kN/mmBC Stiffness 100 kN/mmBC Stiffness 1000 kN/mmBC Stiffness 10 000 kN/mm

-30

-25

-20

-15

-10

-5

0

5

0 100 200 300 400 500

Axi

al S

tre

ss in

Co

ncr

ete

Mid

dle

To

p

Ele

me

nt

(MP

a)

Vertical Displacement (mm)

BC Stiffness 50 kN/mm

BC Stiffness 100 kN/mm

BC Stiffness 1000 kN/mm

BC Stiffness 10000 kN/mm

-1200

-1000

-800

-600

-400

-200

0

200

400

0 100 200 300 400 500

Axi

al R

eac

tio

n F

orc

e (k

N)

Vertical Displacement (mm)

BC Stiffness 50 kN/mm

BC Stiffness 100 kN/mm

BC Stiffness 1000 kN/mm

BC Stiffness 10000 kN/mm

Page 98: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

98

resistance. Since concrete cracking is brittle, using the strength of the slabs before

total cracking of the concrete for providing robustness of the system, is not

recommended.

4.1.3 Slabs with Partial Tie Bar

In the previous systems, the tie bars are through the entire length of the slabs. It is

possible for slabs with partial tie bars (tie bar length < total slab span) to develop

catenary action, provided the slab portions without tie bar are not cracked and the tie

bar length offers enough bond between the tie bar and the surrounding concrete for it

not to slip through.

The results of such a case are shown in Figure ‎4-11, with a tie bar length of 2.5 m in

each slab. It can be seen that even after the final cracking of the connection between

the slabs, the load-displacement diagram of the slabs shows the development of

catenary action. Figure ‎4-12 shows that in this case, the concrete in the unreinforced

region is not cracked in tension.

Figure ‎4-11: Partial Tie Bar, development of Catenary Action

Page 99: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

99

Figure ‎4-12: Crack Pattern, Partial Tie Bar

However, such a load carrying mechanism would be sensitive to the tie bar size. If

the tie bar size is large, total concrete cracking can happen in the unreinforced region

of the concrete grouting between the slabs or infill of the hollowcores, and the

structure model would not be able to carry any load (Figure ‎4-13).

Figure ‎4-13: Crack Pattern, Partial Tie Bar, showing concrete cracking in the unreinforced

zone of grouting

To demonstrate this effect, a model with tie bar diameter of 64mm (Figure ‎4-14) was

simulated. The slab possesses no strength due to negligible development of catenary

action.

Page 100: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

100

Figure ‎4-14: Partial Tie Bar, large tie bar size resulting in total crack of concrete grouting in the

unreinforced zone

To further confirm this, Figure ‎4-15 compares the tensile stress development in the

unreinforced region of the grouting between slabs in the above two cases. It can be

seen that in the case of the smaller tie bar, the tensile stress in concrete is lower than

the tensile strength. But for the slab with large tie bar diameter, the tensile stress

breaches the tensile strength and the concrete stress diminishes after cracking. In the

model with smaller tie bar, the force obtained by the product of the axial stress, if

added for all the elements in height of the slab, and multiplied by the cross sectional

area of the slab is the same as the force derived by the product of the steel cross

sectional area and its yield stress.

Figure ‎4-15: Axial Stress in Unreinforced Region, a) no crack through in the unreinforced

region (small tie bar); b) Crack through in the unreinforced region (large tie bar)

-20

-10

0

10

20

30

40

50

60

0 100 200 300 400 500

Load

(kN

)

Vertical Displacement (mm)

Page 101: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

101

Based on the above results, it can be concluded that it is possible for damaged slabs

(simulating internal support removal) to resist the accidental loads through the

development of catenary action. However, the provision of suitable tie bar is a key

factor. In the following section, an extensive set of parametric studies will be carried

out.

4.2 Accidental Load Calculation

The following calculations were performed to check whether or not the damaged

slabs can resist the accidental load in order to provide resistance against progressive

collapse:

gk = qk = 3.8 kN/m2

Length of each slab L = 5 m

The accidental load on the slabs with the above permanent and variable loads is:

Accidental Loading =

This uniformly distributed load (UDL) gives a total load of 61.2 kN on the two slabs

with a total length of 10 m and a width of 1.2 m. In the numerical model the total

load was applied as a point load at the centre of the two slabs. In order to give the

same maximum bending moment in the slabs, the applied point load should be

halved (30.6 kN).

Comparing the simulation result of ultimate load carrying capacity of 21 kN (in

catenary action) in Figure ‎4-3-a and Figure ‎4-10-a for the slabs with the required

accidental limit load, it appears that the slabs are not able to resist the accidental

load. Figure ‎4-3-a shows that the slabs can resist a force equal to the accidental load

under compressive arching action. However, it is not advisable to use compressive

arching action for structural robustness because compressive arching action is very

sensitive to axial restraint and has a brittle failure mode. Similarly Figure ‎4-10-a

shows that the model with the lowest BC stiffness provides a resistance just more

than the accidental load before final cracking of concrete.

Page 102: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

102

Appendix 1 presents further simulation results for slabs that have been designed

according to the current British Standard regulations (BS8110-1, 2007) and

presented in the manufacturer’s load-span table (Table ‎2-3) . The results again show

that with the current tying force requirement, it is not possible to provide resistance

against the design accidental loading on the structure in a reliable manner by

developing catenary action. The current tying force requirement neglects the

important factor of deformation capacity of the structure.

In the next section, a parametric study will be conducted to examine how different

design parameters may affect the development of catenary action in slabs, with the

principal aim to identify methods that can increase catenary action resistance.

4.3 Parametric Study

For determining the methods of enabling damaged precast concrete floor slabs

(simulating removal of the centre support) to resist progressive collapse, the effect of

each of the following parameters on tie bar elongation is investigated:

Precast concrete slab’s height

Precast concrete slab’s span

Tie bar length

Tie bar position

Tie bar diameter

Tie bar yield Stress

Grouting concrete strength

Ultimate strain of the steel tie bar

Figure ‎4-16 shows the basic geometric and material properties of the slabs. When

carrying out the parametric studies, the values of the parameter which is investigated

are changed while other values are kept constant. As changing each of the above

parameters may lead to a change in the concrete cracking trend, for each of the

parameters, a new mesh sensitivity study was conducted to prevent the convergence

problems inherent in the smeared cracking model of concrete. The presented results

are the outcome of about five thousand simulations.

Page 103: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

103

Figure ‎4-16: Slab's reference case dimensions

4.3.1 Height of the Slab

The range for the slabs height (150 mm- 450‎mm)‎ is‎ based‎on‎ the‎manufacturer’s‎

product listings (Bison, 2012). In all cases, the cover to the tie bar is 40 mm.

Figure ‎4-17 shows cross-sectional dimensions of the slabs.

Tie Bar Diameter = 16 mm

Tie Bar Height = 45 mm

5 m

265 mm

Page 104: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

104

Figure ‎4-17: Hollowcore Sections (Bison, 2012)

The variation of the maximum vertical load, vertical displacement and strain of the

tie bar in the connections are shown in Figure ‎4-18. With this tie bar diameter, slabs

with heights larger than 350 mm are not able to develop catenary action, and the tie

bar reaches its rupture strain before the cracks reach to the top of the concrete

section. In this situation the structure is relying on the compressive forces in the

concrete only. This could cause an abrupt failure under accidental loading, and hence

is not a reliable mechanism for enhancement against progressive collapse. On the

other hand, as the slab height decreases the tie bar in the connection has the

opportunity of providing the catenary action since the concrete of the connection is

cracked totally before the tie bar is ruptured.

Page 105: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

105

(a)

(b)

(c)

(d)

Figure ‎4-18: Effects of varying Slab Height on Vertical Load and Axial Reaction Force

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

sh150

sh200

sh250

sh300

sh350

-300

-200

-100

0

100

200

300

400

0 100 200 300 400 500 600

Axia

l R

eact

ion

Fo

rce

(kN

)

Vertical Displacement (mm)

150

200

250

300

350

-6

-5

-4

-3

-2

-1

0

1

2

3

4

0 100 200 300 400 500 600

Axia

l C

on

crete

Str

ess

(MP

a)

Vertical Displacement (mm)

150

200

250

300

350

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 100 200 300 400 500 600

Tie

Str

ain

Vertical Displacement (mm)

150

200

250

300

350

Page 106: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

106

As shown in Figure ‎4-19, the catenary action resistance is the catenary action force

multiplied by the distance between them (=slab vertical deflection h + distance from

the slab centre to the position of catenary action force d); therefore, increasing the

slab thickness increases the distance between the catenary action force and the centre

of the cross-section, thus increasing the vertical load when the vertical displacement

of the slabs is the same as shown in Figure ‎4-18-a. It is clear from Figure ‎4-18-c that

the concrete is totally cracked for all slab thicknesses so final failure of the slabs is

governed by reinforcement rupture. By increasing the slab thickness, the strain in the

tie bar also increases at the same vertical displacement of the slabs as shown in

Figure ‎4-18-d. This results in earlier rupture of the tie bar.

Figure ‎4-19: Force diagram

As a summary, as the applied loads in the case of thick slabs are likely to be higher,

but the catenary action resistance does not increase by the same proportion when the

slab thickness is increased. As the slab thickness increases, catenary action ceases to

become an effective means of preventing progressive collapse. Hence it is

L

h

F

𝑃

F d

Page 107: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

107

recommended that a balance should be struck between the compressive arching

action of concrete and tensile force exerted from steel tie bar.

4.3.2 Slab Span

Precast concrete floor slabs are able to cover structure spans of as long as about 10

m. In this study the effect of changing the slabs’‎span is investigated for the range of

spans from 3 to 10 m. As by changing the slab thickness, changing the slab span

changes the ultimate limit state resistance of the undamaged slabs and hence alters

the required accidental load.

Taking the slab span/depth ratio as the controlling parameter, then the effect of

increasing slab span is similar to that of reducing the slab depth. As shown in

Figure ‎4-20, as the slab span decreases, the vertical load in the slab increases.

However, the reinforcement fractures at lower slab deflections. Also, the ratio of the

slab catenary action resistance to the slab ULS resistance decreases to be much less

than that which is required to resist the accidental load, indicating that it is not

effective to use catenary action to control progressive collapse in short slabs.

Figure ‎4-20: Variation of slab span affecting the connection response

4.3.3 Tie Bar Length

Among the components present in the connection of the precast concrete floor slabs,

it is only the tie bar that provides reliable tensile resistance and ductility to enable the

damaged structure to undergo catenary action and hence the structure may be able to

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

3 m

4 m

5 m

6 m

7 m

8 m

9 m

Page 108: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

108

survive a local damage before failure. Since tie bars may not be provided over the

entire span of the slabs, it is important to understand how the tie bar length affects

development of catenary action.

The length of the tie bar affects not only the required elongation for catenary action,

but also the bond-slip behaviour of the tie bar in the surrounding concrete. As the tie

bar in the connection is always in tension in the catenary action, if the length is too

short it could be pulled out of the concrete while steel is still elastic; or it could reach

its yield stress and then be pulled out. In either of these cases the anchorage failure

causes the connection to have a brittle collapse.

The desirable failure mode is when the steel yields and then ruptures while it still has

enough bond with concrete that hinders the tie bar from slipping through. This is

satisfied if enough length of the tie bar is provided and if the bond between the

reinforcement and the concrete is in good condition. The good bond condition is

defined in CEB-FIP Model code 2010 and is assumed throughout this study.

Regulations, based on BS EN 1992-1-1, for the length of the bar tying the

hollowcore floor slabs state that if the yield load of the straight tie bars between units

is more than 30 kN, tie bars should use a minimum anchorage length of 100ϕ,

otherwise it can be taken as 75 ϕ.

Furthermore, as explained in section ‎4.1.3, the tie bar should be long enough so that

the unreinforced portion of the connections between the slabs or hollowcore infill

does not crack through after the slab has reached its catenary action resistance. In

this parametric study, the length of the tie bar is varied from the full length of the

slabs (5 m) to the minimum length that allows the tie bar to yield. This minimum

length is calculated based on the yield stress of the tie bar and the bond stress that it

develops with the surrounding concrete (Mazzarolo et al., 2012), which is about 100

mm for the present model. Tie bar lengths lower than this minimum will have either

the yield and pull-out failure, or just the pull-out failure mode.

The comparison of the load-displacement relationships of the different slabs with

different anchorage lengths in Figure ‎4-21-a shows that for long tie bar lengths

(those by which rupture of the tie bar can be achieved) up to a length of 290 mm, the

catenary action force is successfully developed and there is only a very small change

Page 109: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

109

of the maximum load and displacement in the catenary stage, The reduction being

about 3% when the tie bar length changes from the full slab length of 5 m to 290

mm. This fact shows that the strain on the tie bar is localized to the region near the

slabs’‎connection.

However, as shown in Figure ‎4-21-b, if the tie bar length is further shortened,

catenary action cannot be fully developed and the slab resistance is reduced. This is

because before final cracking of concrete in the connection between the slabs, the tie

bar has slipped and the bond is not enough to hold the tie bar to allow it to develop to

its ultimate stress and sufficient elongation.

(a)

(b)

Figure ‎4-21: Variation of Tie Bar Length on the development of catenary action

The trend of the load-displacement diagram of the models with short tie bar length

shows that as the tie bar length is decreased the amount of the applied load on the

structure is decreased too. This phenomenon can be explained by the amount of force

exerted to the connection by the tie bar. As the tie bar length is decreased the region

0

5

10

15

20

25

30

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

5000 mm

1000 mm

500 mm

290 mm

0

5

10

15

20

25

30

0 50 100 150 200 250 300 350

Lo

ad

(k

N)

Vertical Displacement (mm)

250 mm

200 mm

150 mm

100 mm

Page 110: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

110

in which the tie bar applies its load into the concrete is less and hence the reaction

force from the connection to each of the slabs will be less.

In summary, the length of the tie bar recommended in BS EN 1992-1-1 is enough to

enable full catenary action to develop.

4.3.4 Tie Bar Height

Results of the investigations in the previous sections show that catenary action can

develop in the damaged slabs, but the slab load carrying capacity during the catenary

action stage may not be sufficient to sustain the accidental loads by changing the

parameters investigated. Since catenary action is primarily dependent on the

reinforcement provided, this and the next two sub-sections investigate how tie bar

parameters may be changed to enable the slab to sustain the accidental load.

BS EN 1168 sets out regulations of the tie bar positioning with regard to the grouting

keys‎casted‎on‎the‎slabs’‎longitudinal profile. According to this code, if the slabs are

placed close to each other in such a way that their grouting keys are at the bottom of

the section, the tie bar should be placed in the space between half height of the

section and centre of the grouting key (Figure ‎4-22-a). This regulation holds for the

case when the tie bar in the hollowcore slabs too.

(a) (b)

Figure ‎4-22: Placing the Tie Bar between Hollowcore Units (CCIP-030)

On the other hand, if the grouting keys are on top of the section when placing the

hollowcore floor slabs adjacent to each other, the tie bar can be placed in a space

between the centre of the grouting keys and 40 mm from the bottom face of the

Page 111: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

111

connection (Figure ‎4-22-b). This is to provide enough concrete cover for the tie bar

so that the concrete is not crushed when the bar is in sagging moment.

The dimensions of the grouting keys are different in different concrete units but their

centre distance from the top or bottom faces of the concrete slab vary in a range of

30 to 50 mm. Hence the tie bar position range chosen for this study starts from 30

mm from bottom of the connection section and goes as high as 30 mm from the top

face of the slab.

Figure ‎4-23 compares the load-deflection relationships. There is some difference in

y-intercept of the load-deflection curve during the catenary action stage. However, it

can be seen that as the tie bar is moved up, the maximum deflection (hence the

maximum load that can be resisted by the slab) increases and then decreases. This

may be explained by how the tie bar is mobilising the surrounding concrete.

Considering the equilibrium of a slab, as the tie bar is moved up and the distance

between the centre line of the slab height and the tying force is decreased, it is

expected that the vertical applied load carried by the slab decreases. This is because

the distance between the centre line of the slab height and the tying force is

decreased, similar to the case where the height of the slabs was varied

(section ‎4.3.1). This explains the change in the trend of the load-deflection curves.

However, when the tie bar takes different positions in the height of the slab, different

concrete covers are achieved and hence the tie bar will possess different post-peak

bond-slip behaviours (Engström et al., 1998), (Torre-Casanova et al., 2013).

Furthermore, the additional factor of concrete cracking at the bottom of the slabs also

affects the effect of tie bar position as the cracked concrete gives different bond

behaviour to the tie bar than uncracked concrete.

When the tie bar is positioned at the top of the section, it does not contribute to the

tensile stresses of the section until the whole section is cracked. Therefore, catenary

action does not develop until complete separation of the slabs. However, at the same

time, since the tie bar experiences no tensile strain during bending of the slabs, it has

higher strain available during the catenary action stage to enable the slab to sustain

lateral deflections and high loads.

Page 112: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

112

Figure ‎4-23: Effects of tie bar height (measured from bottom of slab) on catenary action

development

Thus, moving the tie bar position has three effects on the slab performance: concrete

cover to tie bar for bond behaviour, change in distance between centre of slab and

position of tensile force and strain. As the tie bar moves up towards mid-height of

the slab, the beneficial effects of increased concrete cover and reduced tie bar strain

dominate and enable the slab to undergo large deflections and hence to sustain

higher loads. Afterwards, the detrimental effects of reduced concrete cover and

reduced distance between the tensile force in the tie bar and the slab centre take over

and the slab resistance decreases when the tie bar moves from the centre of the slab

towards the top. These effects are shown in Figure ‎4-23. To enable the slab to

achieve the highest load carrying capacity in catenary action, it is preferable to place

the tie bar in the centre of the slab.

4.3.5 Tie Bar Diameter

Figure ‎4-24 compares the effects of changing the tie bar diameter from 10 mm to 30

mm, showing the slab-deflection curves and the axial force (Figure ‎4-24-b) and tie

bar strain (Figure ‎4-24-c) results. In all cases, concrete was totally cracked through

-5

0

5

10

15

20

25

30

35

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Tie Height 30

Tie Height 70

Tie Height 90

Tie Height 130

Tie Height 170

Tie Height 210

Page 113: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

113

(as shown by the sharp reduction in tension load in Figure ‎4-24-b) and the ultimate

failure was due to tie bar fracture (Figure ‎4-24-c).

(a)

(b)

(c)

Figure ‎4-24: Effects of changing tie bar diameter

Increasing the tie bar size not only increases the tensile force during the catenary

action stage, it also increases the maximum slab deflection at failure. This increase in

-10

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Diameter 10 mm

Diameter 14 mm

Diameter 18 mm

Diameter 22 mm

Diameter 30 mm

-200

-100

0

100

200

300

400

500

0 100 200 300 400 500 600Axia

l R

eact

ion

Fo

rce

(kN

)

Vertical Displacement (mm)

D=10 mm

D=14 mm

D=18 mm

D=22 mm

D=30 mm

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 100 200 300 400 500 600

Str

ain

Vertical Displacement (mm)

D=10 mm

D=14 mm

D=18 mm

D=22 mm

D=30 mm

Page 114: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

114

displacement is a result of increased elongation of the tie bar since as the tie bar

diameter is increased; a longer length of the tie bar is activated as the bond surface is

increased. These two beneficial effects are exhibited as the higher load-deflection

slope and higher displacement in Figure ‎4-24-a as the tie bar diameter increases.

4.3.6 Tie Bar Yield Stress

Figure ‎4-25 compares slab load-displacement relationships for changing the tie bar

yield stress from 200 to 600 MPa. Increasing the tie bar yield stress has the clear

benefit of increasing the catenary action force and hence the slab resistance.

However, since the tie bar geometry is unchanged, the slab ultimate deflection does

not benefit from significant change.

Figure ‎4-25: Effects of changing tie bar yield stress

Hence it is recommended that to increase the load carrying capacity of a connection,

a tie bar with higher yield stress can be used, although the displacement of catenary

action is not changed.

0

5

10

15

20

25

30

35

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

200 MPa

300 MPa

400 MPa

500 MPa

600 MPa

Page 115: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

115

4.3.7 Grouting Concrete Strength

After aligning the precast concrete floor slabs on their supporting beams closely to

each other, and placing the tying reinforcements in the gaps between the floor units;

the space between the slabs is filled with grouting concrete. Tie bars are also placed

in the hollowcores of the slabs and again the length of the hollowcores encasing the

tie bar is filled with grout.

Figure ‎4-26: Effect of concrete strength on load-displacement of slabs' connection (stresses in

MPa)

Grouting concrete not only contributes to the bending capacity of the connection, but

also affects the bond-slip behaviour of the tie bar as bond stress relationships are

based on the compressive strength of the concrete (CEB-FIP Model Code 2010).

Stronger concrete provides more tensile strength in cracking which is expected to

provide higher load carrying capacity of the connection. However, once the slab is in

catenary action stage after the grout has completely cracked through, since the

tensile resistance comes from the tie bar reinforcement, the grout strength is not

expected to have any effect on the slab load-deflection behaviour. This is

demonstrated in Figure ‎4-26. This figure indicates that total crack through the grout

is delayed by using higher strength grout, but in the catenary action stage slab

behaviour is hardly changed. As a conclusion, using high strength grout is not

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Dispalcement (mm)

fc = 30

fc = 50

fc = 70

fc = 90

Page 116: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

116

effective in increasing the slab catenary action resistance for controlling progressive

collapse.

4.3.8 Ultimate Strain of the Steel Tie Bar

During the catenary action stage, the yield stress of the tie bar determines the slope

of the load-deflection curve while the maximum deflection of the slab is controlled

by the elongation of the tie bar. It is expected that increasing the tie bar ultimate

tensile strain would increase the slab maximum deflection and hence the slab load

carrying capacity. Figure ‎4-27 compares the slab load-deflection relationships for

different tie bar maximum strains from 5% to 40%.

The results confirm this expectation. The tie bars have developed complete yield

stress and their reaching the maximum tensile strains determines the failure of the

slabs. Since the yield stress of the tie bar is not changed, the slab load-deflection

behaviour before total concrete cracking is unchanged. Also since the tensile load in

the tie bar is the same, the different load-deflection curves coincide until tie bar

fracture.

Figure ‎4-27: Effects of changing Tie Bar Ultimate Strain

Comparing the effects of changing the tie bar ultimate strain with changing other

parameters, it is clear that using ductile tie bars with high elongation is the most

0

5

10

15

20

25

30

35

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Dispalcement (mm)

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

Page 117: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

117

effective method of increasing the catenary action resistance of damaged slabs for

controlling progressive collapse.

4.3.9 Summary

This chapter presented a two dimensional model of the slabs and the longitudinal

connection between them. It has been assumed that the supporting column in

between the two slabs and in the middle of the longitudinal tying connection has

been lost due to an accidental action on the structure, hence the behaviour of the

connection and the parameters that affect it have been identified.

Different stages of behaviour were identified and it was shown that due to the brittle

nature of concrete, in the case of a column loss, it was the catenary action provided

by the tie bar that delivered a reliable resisting mechanism against the progressive

collapse and not the arching action of concrete.

The accidental limit load was calculated for a typical residential building and it was

shown that the designed connection based on the current regulations was not able to

resist the load limit.

Different parameters in the connection zone were examined and their effect on the

catenary action was concluded as follows:

Slab height: as the slab height increases it was shown that the tie bar ruptures

sooner, hence the use of thinnest possible slab is recommended

Slab Span: although this parameter did not show any effect on the elongation

of the tie bar, it was shown that the slab span affects the equilibrium equation

of slabs under catenary action. The shorter the slab, the higher the load

carrying capacity, but at the same time the tie bar is strained in earlier stages

of loading and this decreases the vertical displacement

Tie bar length: as long as the length required for capturing enough bond

between concrete and tie bar is provided, the tie bar length does not affect the

resistance or displacement of the connection

Page 118: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

118

Tie bar height: it was shown that due to different factors such as concrete

cover, distance between the forces on the slab, and straining of tie bar, the

optimum location for the tie bar was the mid-height of slab

Tie bar diameter: increasing the tie bar diameter, boosted both resistance and

the elongation of the tie bar where the latter results in more vertical

displacement as well

Tensile ultimate strain of tie bar: directly affected the elongation and ductility

of tie bar in catenary action, resulting in both higher resistance and vertical

displacement

Tie bar yield stress: directly affecting the tying force, increase in tie bar yield

stress increases the load carrying capacity of the connection; but the

elongation of the tie bar is unchanged

Compressive strength of grouting concrete: increase in this parameter delays

the cracking of concrete, but does not affect the catenary action as the tie bar

is main load bearing unit in this stage

Based on the conducted parametric study, recommendation for each of the

parameters with the regard to their effect on the catenary action was made and the

effective parameters (tie bar diameter, height, ultimate tensile strain, and the slab

height) were identified in order to develop an analytical relationship to predict the

connection behaviour in catenary action in the next chapter.

Page 119: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

119

Chapter 5. 2D Slab Analytical Load-Displacement

Relationship

This chapter develops and assesses the accuracy of an analytical model to predict the

behaviour of 2D slabs. The assessment is made against the results of FE simulations

presented in the previous chapter. The analytical model should give the load carrying

capacity of the structure until fracture and should be able to deal with flexible end

restraints. The results of the previous chapter will be used to help make some

assumptions.

It was seen in ‎Chapter 4 that tie bars in thick slabs ruptured before the slabs

developed catenary action. Under the accidental loading that the thick slabs are

required to resist, relying on compressive arching action of the concrete slabs may

lead to a sudden failure of the structure. This is against the spirit of design rules that

require the structure to provide a ductile failure mode. Hence the derivation in this

chapter is focused on the catenary action.

5.1 Development of the Analytical Relationship

5.1.1 Axially Restrained Slabs

Figure ‎5-1 shows the free body diagram of half of the 2-D slab model. It is assumed

that the slab is in pure catenary action with no bending resistance. The catenary force

is F and the externally applied load is P. The catenary action force is provided by the

tying resistance of the steel tie bar.

Page 120: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

120

At catenary stage, the tie bar is yielded with a constant force equal to its yield

resistance (=steel yield stress multiplied by the cross sectional area of the tie bar).

Assuming that the far ends of the slabs are pinned, the equilibrium equation of the

forces applied on the slab can be written as (Equation ‎5-1):

)(2

dhFLP

Equation ‎5-1

Where:

P: the vertical force applied on the connection between the two slabs, representing

the accidental load, half of which is carried by each slab

L: length of each slab

F: tying force which is equal to fy,steel Asteel

h: vertical displacement of the slab

d: the distance of the tie bar to the centre of the slab

Initial Position of the Slab

Figure 5-1: Free body diagram of one slab

L

h

F 𝑃

F

L + e

d

𝑃

Initial Position of the Tie Bar

Page 121: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

121

From Equation ‎5-1 the vertical force applied on the slabs’‎ connection‎ (P as a

function of vertical displacement h) can be written in terms of the slab vertical

displacement (Equation ‎5-2):

Equation ‎5-2

Figure ‎5-2 compares the analytical equation (Equation ‎5-2) with the finite element

simulation. It is seen that the analytical solution provides close agreement with the

numerical result for the catenary action stage. Further comparisons are in Appendix

2.

Figure ‎5-2: Comparison of FE model with analytical relationship, slab height 265 mm, width

1200 mm, span 5 m, tie bar height 45mm, diameter 16 mm, steel yield stress 500 MPa

5.1.2 Elastic Axially Restrained Slabs

In chapter ‎Chapter 4, it was shown that the behaviour of support conditions did not

affect behaviour of the slabs during the catenary action stage. This section will

present the analytical derivations to prove this. Figure ‎5-3 shows the same structure

-15

-10

-5

0

5

10

15

20

25

30

35

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Analytical Relationship

FE Pinned BC

Page 122: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

122

as in Figure ‎5-1, except that the end of the slab has moved (Δ). This horizontal

displacement can be calculated by dividing the catenary action force (tying force) by

the axial stiffness of the support.

Figure ‎5-3: Slab deflection with axial displacement

Using the free body diagram shown in Figure ‎5-3, the equilibrium relationship can

be written as:

dhFLP

2

Equation ‎5-3

Giving:

L

dhFP

2

Equation ‎5-4

Where:

P: is the vertical force

F: tying force

h: vertical displacement of the connection between the slabs

Δ

h+d L+e

L

F

P/2 P/2

Page 123: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

123

d: vertical distance between the centre line of the slab height and tying force

L: slab length

And Δ: the horizontal movement of slab end due to flexibility of the support.

e: is the elongation of the tie bar.

As the support horizontal displacement (Δ) is negligible compared to the length of

the slab (L), the support stiffness has almost no effect on the equilibrium of the

system in catenary stage. Figure ‎5-4 shows typical comparison between Equation ‎5-4

with numerical simulation result for a case with elastic axial restraint. The agreement

is quite good. More comprehensive comparisons are provided in Appendix 2.

Figure ‎5-4: Comparison of the FE model with elastic BC with the analytical relationship, slab

span: 7 m

5.2 Maximum Slab Displacement

In order to obtain the maximum resistance of the slab in catenary action, it is

necessary to be able to estimate the maximum slab vertical displacement (h). It is

assumed that the maximum slab displacement is reached when the maximum strain

in the tie bar has reached its rupture strain (εult). At this stage, the strain in the tie bar

is distributed along a certain length of the tie bar (Lp). Figure ‎5-5 shows a schematic

distribution of strain at the connection between the slabs. As explained in

section ‎2.6, strain is localized to the connection zone.

0

5

10

15

20

25

0 100 200 300 400 500 600

Loa

d (

kN

)

Vertical Displacement (mm)

Analytical

Prediction

Elastic BC L=7 m

Page 124: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

124

Figure ‎5-5: Strain distribution at the connection between PCFS

Figure ‎5-6 shows the same tie bar as in Figure ‎5-5, but in a typical tie bar strain

diagram of an FE model. If the strain distribution (area under the strain curve: Sd),

and the strained length of the tie bar (Lp) are known, then the total tie bar elongation

(e in Figure ‎5-1 and Figure ‎5-3) can be calculated, from which the maximum

displacement h of the slab can be calculated.

Figure ‎5-6: Strain distribution along the tie bar in the FE model

The strain distribution (Sd) has been calculated based on the trapezium rule along the

tie bar (Figure ‎5-6). The region between each pair of the integration points along the

PCFS

Tie Bar

Strain Distribution

of Tie Bar at

Connection (Sd)

Lp

Sd εult

Lp

Page 125: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

125

tie bar is assumed as a trapezium, and the summation of these areas gave the strain

distribution of the FE models. For prediction of the strain distribution, it proved to be

a good estimation to consider the two parallel sides of the trapezium as εult and

.

Hence the strain distribution over the penetration length of strain (Lp) at the ultimate

strain of the tie bar (εult) can be written as:

Equation ‎5-5

On‎ the‎other‎hand‎ the‎ rupture‎ strain‎of‎ tie‎bar‎can‎be‎written‎ in‎ terms‎of‎ the‎bar’s‎

total elongation (e), and the strain penetration length (Lp), which with Equation ‎5-5

gives:

Equation ‎5-6

By referring to Figure ‎5-3 the following quadratic equation can be estimated for the

vertical‎displacement‎of‎the‎slab‎(neglecting‎the‎square‎of‎e,‎and‎Δ):

Equation ‎5-7

Having all the parameters calculated, Equation ‎5-7 is solved for the vertical

displacement h. Hence the maximum force applied on the connection is derived with

Equation ‎5-4, which is then compared with the required accidental limit force on the

connection between the slabs.

Among the parameters studied that affect the elongation of the tie bars, the following

parameters have noticeable effects: slab height, tie bar position and diameter, and

ultimate strain of the tie bar material.

Page 126: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

126

5.2.1 Slab Height

Figure ‎5-7 shows the strain distribution along the tie bar length with slab height

variation. A curve of best fit is also shown in the figure.

Figure ‎5-7: Variation of tie bar strain distribution with slab height

The relationship for strain distribution (Sd,S.H) and slab height (SH) can be written as:

Equation ‎5-8

The above trend can be explained as follows: Considering two models with different

slab heights at the same vertical displacement at a stage before plasticity of the tie

bar, and assuming the second model has a bigger height, it can be seen that

(Figure ‎5-1 and Equation ‎5-1) due to equilibrium of the forces applied to each slab,

the vertical force on the second model is bigger (P2 > P1); as the distance of the

influence line of the tie bar force from the centre line of the slab is more in this slab

(d2 > d1).

As the resisting force, provided by the tie bar, is the same in both cases, the

excessive force in the second model is carried by more straining of the tie bar, hence

ε2 > ε1. Expressing the tie bar strain in terms of the ratio of the elongation of the tie

bar (e) over the length of the tie bar elongated (Lp).

Sd = 3E-10(SH)4 - 5E-07(SH)3 + 0.0003(SH)2 - 0.0947(SH)

+ 25.327

0

2

4

6

8

10

12

14

16

18

20

0 100 200 300 400 500

Str

ain

Dis

trib

uti

on

(m

m)

Slab Height (mm)

Page 127: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

127

1

11

pL

e

And 2

22

pL

e

And noticing that the lengths and vertical displacements of the two slabs are the

same, it is apparent that the elongation of the two tie bars is equal and they can be

approximated by Pythagoras theorem (neglecting the quadratic term of e):

L

hee

2

2

21

This yields that:

1

1

2

212

pp L

e

L

e

Knowing that e1 = e2, gives: Lp1 > Lp2, hence the slab with lower height has higher

strain distribution along its tie bar length.

5.2.2 Tie Bar Diameter

Figure ‎5-8 shows that the tie bar strain distribution length increases with increasing

tie bar diameter. When the tie bar diameter increases, the tie force is also increased

according to the square of its radius. In the meantime, the bond force between the tie

bar and the concrete increases linearly (determined by the interface area). Therefore,

a longer tie bar strain distribution length is necessary to distribute the tie bar force.

Page 128: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

128

Figure ‎5-8: Effect of tie bar diameter on strain distribution length

The estimated linear relationship between strain distribution (Sd,T.D) and the tie bar

diameter (D) is:

Equation ‎5-9

5.2.3 Tie Bar Position

Figure ‎5-9 shows how the tie bar strain distribution changes with tie bar position.

Due to the number of factors affecting the strain distribution, when the tie bar

position changes in the height of the slab; the variation of this parameter cannot be

explained with the geometry relationships solely. Herein, the concrete cover to tie

bar, concrete cracking, and end rotation of the slab affect the strain distribution of the

tie bar.

Sd = 0.3988(D) + 7.9593

0

5

10

15

20

25

0 5 10 15 20 25 30 35

Str

ain

Dis

trib

uti

on

(m

m)

Tie Bar Diameter (mm)

Page 129: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

129

(a)

(b)

Figure ‎5-9: Variation of strain distribution with tie bar position

The quadratic relationship between the strain distribution (Sd,T.H) and the tie bar

height (TH) is written as:

Equation ‎5-10

If the tie bar is placed below the mid-height of the section, the effect of the tie bar

position is similar to that of increasing the slab height as explained in section ‎5.2.1.

Thus, when the tie bar moves up towards the mid-height, the effect is similar to

reducing the slab thickness in section ‎5.2.1, which leads to an increased tie bar strain

distribution length. Also as the tie bar moves up, the concrete cover is more, hence it

is able to deploy more bond stress with the surrounding concrete (Engström et al.,

1998), (Torre-Casanova et al., 2013).

Sd = 0.0035(TH)2 - 0.298(TH) + 19.468

0

5

10

15

20

25

30

35

40

45

0 20 40 60 80 100 120 140

Str

ain

Dis

trib

uti

on

(m

m)

Tie Bar Height (mm)

Sd = -0.1132(TH) + 50.645

0

5

10

15

20

25

30

35

40

45

0 50 100 150 200 250

Str

ain

Dis

trib

uti

on

(m

m)

Tie Bar Height (mm)

Page 130: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

130

When the tie bar moves above the mid-height, the strain distribution analogy for the

slab height holds but this time it starts to lose its concrete cover which leads to less

bond stress. Also when the tie bar is above the mid-height, the tie bar is in tension at

a later stage compared to the case when it is places below the mid-height due to later

concrete cracking under a sagging moment. Hence the tie bar has less opportunity of

developing‎tension‎along‎the‎tie‎bar’s‎length.

5.2.4 Ultimate Strain of the Steel Tie Bar

Figure ‎5-10 shows that the tie bar strain distribution length increases almost linearly

with increase in the ultimate strain of the tie bar. The increased tie bar ultimate strain

gives opportunity for the tie bar stress to be dissipated along a longer length of the

tie bar.

Figure ‎5-10: Effect of tie bar ultimate strain on connection behaviour

The linear relationship for strain distribution (Sd,ε) variation with respect to ultimate

strain of the tie bar is:

Equation ‎5-11

y = 76.42x + 0.5736

0

5

10

15

20

25

30

35

0 0.1 0.2 0.3 0.4 0.5

Str

ain

Dis

trib

uti

on

(m

m)

Ult. Strain of Tie Bar

Page 131: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

131

Figure ‎5-7 to Figure ‎5-10 give the best fitting equations to the various trends to

enable the tie bar strain distribution length to be calculated as functions of the

various design parameters. To obtain the overall value, the average of the four values

is taken.

5.3 Validation of the Analytical Prediction for the

Maximum Catenary Action Resistance

Using the approximate expressions between the tie bar strain distribution and the

various design parameters (slab thickness, tie bar diameter, tie bar position and tie

bar ultimate strain), the maximum tie bar elongation can be calculated. Equation ‎5-7

then gives the maximum slab displacement which can be used in Equation ‎5-4 to

give the ultimate resistance of the slab in catenary action. The analytical calculations

are presented here for the base case.

Table ‎5-1: Calculation of strain distribution for the base case

Design Parameter Value Sd

Tie Bar height 45 mm 13.14 (Equation ‎5-8)

Diameter 16 mm 14.34 (Equation ‎5-9)

Slab Height 265 mm 13.47 (Equation ‎5-10)

Ultimate Strain 0.2 15.85 (Equation ‎5-11)

Average Sd: ≈‎14

The vertical displacement can be written as (by Equation ‎5-6 and Equation ‎5-7):

√ √ (

)

And using the Equation ‎5-4 the resistance of the base case slab is shown in

Figure ‎5-11, where good agreement between the calculated vertical displacement and

slab resistance can be observed:

Page 132: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

132

Figure ‎5-11: Comparison of FE base case with the analytical calculation

For prediction of the resistive force (P) of other models, where more than one

parameter is changed, the strain distribution calculated (based on Equation ‎5-8 to

Equation ‎5-11) is normalised with respect to the average strain distribution of the

base case (Equation ‎5-12):

{ √ (

) }

Equation ‎5-12

Where:

Atie: is the cross sectional area of the tie bar

d: is the distance between the mid-height of slab to the tie bar position

Sd,S.H.: is obtained from the strain distribution relationship for slab height

(Equation ‎5-10)

Sd,T.D.: is obtained from the strain distribution relationship for tie diameter

(Equation ‎5-9)

0

5

10

15

20

25

30

0 100 200 300 400 500

Load

(kN

)

Vertical Displacement (mm)

Page 133: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

133

Sd,T.H.: is obtained from the strain distribution relationship for tie height (position,

Equation ‎5-8)

Sd,ε: is obtained from the strain distribution relationship for ultimate tie bar strain

(Equation ‎5-11)

The value obtained from the above equation can be checked against the accidental

load (Pacc) required on two damaged slabs to see if the connection between the slabs

has enough robustness to withstand this loading condition (Equation ‎5-13).

Equation ‎5-13

To obtain a suitable tie bar for a given accidental load, a trial and error procedure for

Atie should be followed until Equation ‎5-12 gives a force equal or greater than Pacc in

Equation ‎5-13.

5.3.1 Comparison of FE and Analytical Results

The results of the analytical calculations for all the numerical simulation models in

chapter ‎Chapter 4 are shown in Table ‎5-2 to Table ‎5-5. The overall agreement

between the analytical and numerical results is very good.

Table ‎5-2: Comparison of FE and analytical results, Tie Bar height

Parameter Displacement (mm) Load (N)

Tie Height

(mm)

Calc. FE Abs.

Difference

Calc. FE Abs.

Difference

30 440 416 24 21837 20400 1437

70 476 467 9 21528 21000 528

90 546 518 28 23659 23500 159

130 752 730 22 30351 31200 849

170 667 642 25 25336 24000 1336

210 617 610 7 21717 24700 2983

Page 134: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

134

Table ‎5-3: Comparison of FE and analytical results, Tie Bar Ult. Tensile Strain

Parameter Displacement (mm) Load (N)

Tie Ult.

Strain

Calc. FE Abs.

Difference

Calc. FE Abs.

Difference

5 227 167 60 12660 6350 6310

10 310 311 1 16018 22800 6782

15 376 369 7 18649 17400 1249

20 432 421 11 20885 19400 1485

25 481 472 9 22865 22000 865

30 525 519 6 24660 24700 40

35 567 569 2 26314 27700 1386

40 605 593 12 27857 29100 1243

Table ‎5-4: Comparison of FE and analytical results, Slab Height

Parameter Displacement (mm) Load (N)

Slab Height

(mm)

Calc. FE Abs.

Difference

Calc. FE Abs.

Difference

150 475 481 6 20330 19900 430

200 453 457 4 20455 19700 755

250 436 428 8 20768 20200 568

300 421 413 8 21180 20000 1180

350 407 385 22 21614 20300 1314

Page 135: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

135

Table ‎5-5: Comparison of FE and analytical results, Tie Bar Diameter

Parameter Displacement (mm) Load (N)

Tie

Diameter

(mm)

Calc. FE Abs.

Difference

Calc. FE Abs.

Difference

10 394 384 10 7565 8220 655

12 407 415 8 11187 11500 313

14 419 413 6 15614 15100 514

16 432 422 10 20885 19600 1285

18 443 449 6 27038 27000 38

20 455 462 7 34107 34700 593

22 466 480 14 42128 43700 1572

28 498 498 0 72230 63200 8630

30 509 515 6 84381 76700 7681

The absolute values of difference between FE and analytical displacement of all

models have average and standard deviation of 12 mm and 11.7 mm respectively.

And the absolute values of difference between the analytical and FE results of

resistance have the average and standard deviation of 1.8 kN and 2.3 kN

respectively.

5.4 Summary

This chapter has presented the derivation and validation of an analytical model to

calculate the load-displacement relationship of the slab in catenary action, based on

observations of the finite element simulation results presented in ‎Chapter 4. Under

catenary action, the slab is assumed to possess no bending resistance and deforms in

a straight line. The maximum slab displacement is related to the tie bar elongation,

which is based on a trapezium strain distribution along a tie bar strain distribution

length Lp. This strain distribution length has been found to be dependent on the slab

height, the tie bar diameter, position and ultimate tensile strain. Approximate

equations have been proposed to calculate the tie bar strain distribution length as

functions of these parameters. Using the proposed relationships, the maximum slab

displacement and slab resistance have been calculated for all the numerical models

in ‎Chapter 4. Good agreement was found between the analytical and numerical

Page 136: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

136

results. The proposed method may be used in design estimation of the potential of

the damaged slabs, after removal of the central support, to resist the accidental load.

Page 137: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

137

Chapter 6. Three-dimensional behaviour of PCFS

with column removal

This chapter presents the results of an extensive parametric study on a three

dimensional finite element model of the precast concrete floor slabs. This model

consists‎of‎eight‎PCFS’s‎segments‎tied together, representing a full span of a typical

flooring system. The results of the FE analysis are used to assess the current building

code‎ regulations‎ with‎ regard‎ to‎ the‎ effectiveness‎ of‎ tying‎ PCFS’s‎ to‎ achieve‎

robustness, and recommendations are made based on the presented parametric study.

Three case scenarios are considered herein (Figure ‎6-1):

1. Loss of an edge column

2. Loss of a centre column

3. Loss of a corner column

Figure ‎6-1: Plan of a floor system

The parametric study focuses on the parameters that were found effective in ‎Chapter

4. These include: the tie bar diameter and ultimate strain, and the slab height. Based

on the findings of the ‎Chapter 4 the tie bar is placed in the mid-height of the slab in

Corner Column

Edge Column

Centre Column

Longitudinal Tie

1.2 m

Transverse Tie

PCFS

Page 138: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

138

all 3D models as this was shown to be the optimum position. Also the effect of

transverse reinforcement on the performance of the connection between PCFS is

studied (Figure ‎6-1).

Figure ‎6-2: Modelled slab resting on steel structure

In steel framed structures, although the primary system for structural robustness is

through tying of the principal members at the beam-column joints, they have proved

to lack sufficient rotational capacity for development of catenary action (Byfield and

Paramasivam, 2007). This research will investigate whether ties connecting the

PCFS can resist the accidental loading without relying on the beam-column ties. In

these simulations, one steel member is assumed to have lost load carrying capacity

and other steel members are considered intact (Figure ‎6-2) so as to be able to provide

the PCFS with appropriate support condition.

6.1 Finite Element Model

The finite element model is depicted in Figure ‎6-3-a including the boundary

conditions. It is assumed that the surrounding structural elements do not fail to

provide the required vertical restraint to the slab segment in question. The same axial

restraint is applied to the 3-D model as discussed in ‎Chapter 4. Figure ‎6-3-c shows

the slab layout and positions of the tie-bars.

Stable Steel Beam

Stable Steel Column

PCFS

Lost Column

Beam-Column

Joint

Page 139: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

139

(a)

(b)

(c)

Figure ‎6-3: Floor arrangement and three dimensional finite element model representation

Due to symmetry, only half of the floor was simulated. Loading of the model is

applied via prescribed displacement. The nodes on the edge beam have been tied

together to have a displacement with linear proportionality so that they represent the

beam underneath the slabs on top of the lost column. The concrete material model is

the smeared cracking model with Mohr-Coulomb plasticity in compression and

Edge

1st Hollowcore Tie

4@1200 mm

5000 mm

Page 140: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

140

linear tension softening in tension, as used in ‎Chapter 3. The material model for

reinforcement is the Von-Mises plasticity model.

In order to model the grouted hollowcores which contain the tie bars, the middle

hollowcore of each model has been filled to the tie bar length which is necessary to

capture the cracking length of the slab as explained in ‎Chapter 4 (Figure ‎6-3-b). The

failure of the floor slab is marked with rupture of the 1st tie in the hollowcore

(Figure ‎6-3-c).

The base case of the parametric study is the same as the one for the 2D model

in ‎Chapter 4: slab height 265 mm, slab width 1200 mm, tie bar diameter 16 mm, and

span length 5 m.

Table ‎6-1 lists the material properties used in the numerical models.

Table ‎6-1: Material property of concrete and steel used in the FE model

Concrete

Ec 33842.32 MPa

ν 0.2

fc 39 MPa

ft 2.97 MPa

Gf 0.0778 N.mm/mm2

Steel (Tie Bar)

Es 210000 MPa

ν 0.3

fy 500 MPa

6.2 Effects of Loss of an Edge Column

If the structure suffers the loss of an edge column on the side of the structure, it may

be possible for the structure to provide an alternative load path, through the

development of catenary action (Figure ‎6-4).

Page 141: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

141

Figure ‎6-4: Possible structural behaviour after loss of an edge column, (Baldridge and Humay,

2003)

6.2.1 Slab Height

The slab heights in this study give the precast slab span/height ratio ranging from 33

– 14. Typically, the slab span/height ratio for PCFS is 30 (SpanRight, 2013). The

effect of slab height on load carrying capacity of the floor system is shown in

Figure ‎6-5-a. It can be seen that similar to the trend of the 2D case in ‎Chapter 4, as

the slab height increases, the load carried by the floor system increases, but this leads

to higher tie bar strain at the same vertical deflection. Figure ‎6-5-(b) and (c) show the

tie bar strain development in the connection at the first and the second tie bars. In all

cases, failure of the slab was due to tie bar fracture when the tie bar strain reached

the assumed tie bar fracture strain of 20%. Figure ‎6-5-d shows that the concrete in

the connection is thoroughly cracked and the force in the catenary action is only

provided by the tie bar.

Page 142: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

142

(a)

(b)

(c)

(d)

Figure ‎6-5: Slab Height effect on the connection behaviour

0

100

200

300

400

500

600

0 200 400 600 800 1000 1200 1400 1600

Lo

ad

(k

N)

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000

Ed

ge T

ie B

ar S

tra

in

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000 1200 1400 1600

1st

Ho

llo

wco

re T

ie S

tra

in

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

-14

-12

-10

-8

-6

-4

-2

0

2

4

0 200 400 600 800 1000 1200 1400 1600

Co

ncr

ete

Axia

l S

tress

(M

Pa

)

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

Page 143: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

143

As expected, when the slab height increases, the first peak load in the slab load-

deflection relationship (Figure ‎6-5-a) increases as a result of increased bending

moment capacity of the slabs. However, since the reason for using deep slabs is to

resist increased design loads, the residual load carrying capacity of the slab system

after column removal may not be sufficient to resist the accidental loading. Below a

procedure for estimation of required floor resistance for accidental loading is

proposed:

(1). The slab bending moment capacity per unit width can be calculated as follows

(Elliot, 2002):

Equation ‎6-1

In which:

Mur: is the slab bending moment resistance

fpb: is the design tensile stress in tendons

Aps: total cross sectional area of the tendons per unit area of slab

d: the effective depth of the precast concrete cross section

and X is the depth of neutral axis calculated by equating the tensile force in the

tendons to compressive force of the concrete block

Based on the manufacturers product listing (CFS, 2013) and (O'Reily, 2013), the

prestressing‎strands‎ in‎ the‎hollowcores‎ slabs‎ thinner‎ than‎300‎mm‎are‎10‎φ10‎mm‎

and‎for‎slabs‎thicker‎than‎300‎mm‎are‎10‎φ‎12.5‎mm.‎The‎ultimate‎tensile‎stress‎of‎

strands is taken as 1500 MPa and design stress is about 80% of that. It is usually

assumed that 70% of the design stress is lost due to construction deficiencies. Based

on this information, BS 8110 part1 table 4.4 provides the coefficients for calculation

of force provided by the prestressing strands and the location of the neutral axis (X).

(2). The ultimate limit state (ULS) load carrying capacity of the undamaged floor

system, under uniformly distributed loading, can be calculated as follows:

Page 144: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

144

Equation ‎6-2

Assuming a ratio of accidental load/ULS load of about 0.3, the accidental load (ALS)

is:

Equation ‎6-3

Based on which the maximum bending moment per unit slab width in the damaged

floor system is calculated. This is done by considering a plate with three fixed edges

and a free edge (as the edge column is lost in this case). (Moody, 1990) provides

relationships for calculation of the moment of different loading situations of plates

with different boundary conditions.

Figure ‎6-6: Plate structure with 3 fixed and 1 free edges (Moody, 1990)

As in this case the ratio a/b (Figure ‎6-6) is almost equal to one (a being the one slab

span, and b being four times of slab widths), the moment for concrete due to uniform

distributed loading at { is calculated by:

Page 145: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

145

Equation ‎6-4

Where:

P: is the uniform distributed load (ALS in here)

(3). The moment due to the uniformly distributed load calculated in the previous

stage, is equated to the moment that a point load in the middle of the edge of the

slabs (at { ) would produce. This is done due to limitation of displacement

control analysis when using DIANA.

Equation ‎6-5

Where p is the point load.

Table ‎6-2 shows the ULS undamaged slab resistance, the required equivalent point

load resistance for the damaged accidental situation, the slab first peak resistance,

and the slab final resistance under catenary action.

Table ‎6-2: Accidental load based on the ultimate bending resistance of the slabs

slab height

(mm) Mur (kN.m)

ULS

(kN/m2)

“1‎span”

w

Point

Load

(kN) “2‎

spans”

First

peak

resistance

(kN)

Max.

Load in

Catenary

(kN)

150 75.76 20.20 148.07 55 180

200 133.36 35.56 210.93 125 130

250 193.88 51.70 276.97 224 115

300 351.32 93.68 448.79 344 90

350 446.32 119.01 552.46 513 50

Page 146: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

146

The results in Table ‎6-2 suggest that only the thinnest slab (150mm) can develop

sufficient slab resistance in catenary action to resist the accidental load. For greater

slab heights, the required floor resistance under accidental loading is proportionally

increased as the slab height increases, but the floor resistance under catenary action

does not increase because this resistance is limited by the amount of reinforcement.

Although tie bars are useful to prevent accidental detachment of one precast unit

from others, the conclusion of this study casts doubt on the effectiveness of using tie

bars to develop an alternative load carrying mechanism to control progressive

collapse of the global structure.

6.2.2 Tie Bar Diameter

Figure ‎6-7 shows the slab load-deflection relationships for different tie bar

diameters. Because slab dimensions are unchanged, the bending resistance of the

floor system, as evidenced by the first peak, does not change. Increasing the tie bar

diameter increases the load carrying capacity of the floor system during the catenary

action stage. However, the results again suggest that the development of catenary

action would not be sufficient to resist the applied loads under accidental load

condition.

Page 147: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

147

(a)

(b)

(c)

Figure ‎6-7: Effect of tie bar diameter on floor behaviour

Nevertheless, the results in Figure ‎6-7(a) clearly show very useful increase in floor

resistance under catenary action when increasing the tie bar diameter. It is thus

possible to use increasing the tie bar diameter as a possible method of boosting floor

resistance under accidental loading. Figure ‎6-7(b) and Figure ‎6-7(c) again show that

0

50

100

150

200

250

300

0 200 400 600 800 1000 1200 1400

Lo

ad

(k

N)

Vertical Displacement (mm)

Tie Diameter 12

Tie Diameter 16

Tie Diameter 20

Tie Diameter 24

Tie Diameter 30

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000

Ed

ge T

ie B

ar S

tra

in

Vertical Displacement (mm)

Tie Diameter 12

Tie Diameter 16

Tie Diameter 20

Tie Diameter 24

Tie Diameter 30

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000 1200 1400

1st

Ho

llo

wco

re T

ie S

tra

in

Vertical Displacement (mm)

Tie Diameter 12

Tie Diameter 16

Tie Diameter 20

Tie Diameter 24

Tie Diameter 30

Page 148: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

148

failure of the slabs was caused by fracture of the tie bars which reached the fracture

strain of 20%.

6.2.3 Tie Bar Ultimate Tensile Strain

Catenary action develops as a result of large deflection of the floor system. In the

previous sections, floor failure was due to fracture of the tie bars. Therefore, it is

expected that if the tie bar deformation capacity (ultimate tensile strain) is changed,

it would have direct influence on the development of catenary action. Figure ‎6-8

shows results of changing the tie bar ultimate tension strain, ranging from 5%

(typical for reinforcement) to an artificially high value of 40%. Again, failure of the

floor system was due to the tie bars reaching their respective ultimate tensile strains.

However, the results in Figure ‎6-8(a) indicate that if the tie bar ultimate tensile strain

could be increased, it would be a very effective method of increasing the floor

resistance under catenary action. For comparison, the final floor resistance at 40% tie

bar ultimate tensile strain is more than double that at 20% tie bar ultimate tensile

strain. In contrast, the final floor resistance at 5% tie bar ultimate tensile strain is

about 60% of that at 20% strain. Whilst it may not be possible to increase the

ultimate tensile strain of tie bars, the results of this investigation clearly suggest that

for improved robustness of the floor system (which is the main aim of providing the

tie bars), tie bars with high ductility (hot rolled) instead of low ductility (high

strength, cold formed) should be used.

Page 149: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

149

(a)

(b)

(c)

Figure ‎6-8: Effect of changing tie bar ultimate tensile strain

6.2.4 Transverse Tie Bars

At present in the construction practice, according to the EuroCode, only longitudinal

ties are introduced in order to provide robustness between the PCFSs. This section

investigates whether it would be effective to enhance the floor resistance under

accidental loading by introducing transverse tie bars between the precast floor units.

0

50

100

150

200

250

300

0 500 1000 1500 2000

Lo

ad

(k

N)

Vertical Displacement (mm)

Tie Ult. Strain 0.05

Tie Ult. Strain 0.1

Tie Ult. Strain 0.15

Tie Ult. Strain 0.2

Tie Ult. Strain 0.25

Tie Ult. Strain 0.3

Tie Ult. Strain 0.35

Tie Ult. Strain 0.4

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

0 200 400 600 800 1000 1200

Ed

ge

Tie

Ba

r S

tra

in

Vertical Displacement (mm)

Tie Ult. Strain 0.05

Tie Ult. Strain 0.1

Tie Ult. Strain 0.15

Tie Ult. Strain 0.2

Tie Ult. Strain 0.25

Tie Ult. Strain 0.3

Tie Ult. Strain 0.35

Tie Ult. Strain 0.4

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

0 500 1000 1500 2000

1st

Ho

llo

wco

re T

ie S

tra

in

Vertical Displacement (mm)

Tie Ult. Strain 0.05

Tie Ult. Strain 0.1

Tie Ult. Strain 0.15

Tie Ult. Strain 0.2

Tie Ult. Strain 0.25

Tie Ult. Strain 0.3

Tie Ult. Strain 0.35

Tie Ult. Strain 0.4

Page 150: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

150

Figure ‎6-9 shows the arrangement of the transverse tie bar connecting the precast

units in the x-direction.

Tie bar in top of the section Tie bar in the middle hieght

Model 1 Model 2

Model 3 Model 4

Model 5 Model 6

Figure ‎6-9: Arrangement of transverse ties

Table ‎6-3 presents the characteristics of the transverse tie bars such as their length,

and height position. Tie bar diameters is the same as base case (16 mm).

Transverses Tie

Longitudinal Tie

Page 151: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

151

Table ‎6-3: Position (from bottom of the section) and lengths of the transverse tie bars

Model Position (mm) Length (mm)

1 132 600

2 220 600

3 132 600

4 220 600

5 132 4800

6 220 4800

The results in Figure ‎6-10 show that introducing transverse tie bars have some

beneficial effects increasing the load carrying capacity of the floor structure,

especially when the tie bars are placed above the mid-height of the slab section

(Models 1,3,5 compared to Models 2, 4, 6).

Figure ‎6-10: Effects of introducing transverse tie bars

However, since the added tie bars are not connected to any of the support structure,

their contribution to the floor resistance is through increased slab bending resistance,

rather than catenary action. This is confirmed by observing the maximum strains in

the longitudinal and transverse tie bars (Figure ‎6-11 (b) and (c)). While the

longitudinal tie bars have reached their ultimate tensile strain, the transverse tie bars

are at low levels of strain. What this investigation has demonstrated is the limited

0

50

100

150

200

250

300

0 200 400 600 800 1000 1200

Lo

ad

(k

N)

Vertical Displacement (mm)

Base Case

Model 1

Model 2

Model 3

Model 4

Model 5

Model 6

Page 152: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

152

effectiveness of introducing transverse tie bars if these tie bars are not anchored to

the edge supports.

(a)

(b)

(c)

Figure ‎6-11: Strain in main longitudinal tie (b) and two of the transverse ties (c)

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000 1200

Axia

l S

tra

in

Vertical Displacement (mm)

1st Hollowcore Tie

-0.001

0

0.001

0.002

0.003

0.004

0.005

0.006

0 200 400 600 800 1000 1200

Axia

l S

tra

in

Vertical Displacement (mm)

Trans. Tie A-1

Trans. Tie A-2

1st Hollowcore Tie

Trans. Tie A-1

Trans. Tie A-2

Page 153: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

153

Figure ‎6-11 shows that the strain progress in the transverse tie bars is much lower

compared to the longitudinal ties. This, in general, holds true for the other models

with different tie arrangements.

6.2.5 Procedure of Improving Robustness of Precast Floor Systems

Based on the results of this section, the following hierarchy (benefit from high to

low) of improving the robustness of precast floor system can be suggested:

- Use the thinnest slab depth;

- Use tie bars with the highest ductility;

- Increase tie bar diameter;

- Introduce transverse tie bar.

6.3 Loss of a Centre Column

In this section the loss of a central column is considered. Figure ‎6-12 shows the

simulation case and the finite element mesh with boundary condition applied on it.

The parameters studied here are the tie bar strain, and diameter and the slab height.

Also the effect of adding transverse ties of the slabs to the adjacent floor panel is

studied. This model has symmetry boundary conditions in the plane of the floor in

two perpendicular directions; hence a quarter of the model is simulated here.

Page 154: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

154

(a)

(b)

Figure ‎6-12: Loss of centre column in a floor system

6.3.1 Slab Height

Figure ‎6-13 shows the effect of the slab height on the behaviour of the connection

between PCSFs when a central column is lost.

Lost Centre Column Modelled Slab

Page 155: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

155

(a)

(b)

(c)

Figure ‎6-13: effect of slab height when central column is lost

It is seen that the load bearing capacity of the slabs is increased by the increase in

their height in the arching action stage, but as the catenary behaviour is mostly

dependent on the tie bar, this area of the connection behaviour is not affected

significantly.

0

500

1000

1500

2000

2500

3000

0 500 1000 1500 2000

Lo

ad

(k

N)

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 100 200 300 400 500 600 700 800

Ed

ge T

ie B

ar S

tra

in

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 500 1000 1500 2000

1st

Ho

llo

wco

re T

ie S

tra

in

Vertical Displacement (mm)

Slab Height 150

Slab Height 200

Slab Height 250

Slab Height 300

Slab Height 350

Page 156: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

156

Based on the calculated distributed accidental load in Table ‎6-2, and considering the

fact that the area of floor slabs in question is twice of the previous case the point load

which causes the same bending moment as the distributed load on the slabs is

calculated based on the relationships in (Timoshenko, 1959). Here a point load in a

centre of a slab with four fixed edges is considered:

Figure ‎6-14: Plate structure with point load at centre (Timoshenko, 1959)

The moment in the centre of the slab (at {

) due to uniform distributed load is

calculated by:

Equation ‎6-6

Where:

P: is the uniform distributed load

a: is the width of slabs

The equivalent point load is calculated by:

Equation ‎6-7

Page 157: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

157

Table ‎6-4 shows the equivalent point of the accidental actions:

Table ‎6-4: Equivalent of accidental point load on the connection

slab height

(mm)

Accidental

Load (kN/m2)

Point Load

(kN) “2‎spans”

150 7.95 291.51

200 11.33 415.27

250 14.88 545.30

(265) 15.95 584.33

300 24.12 883.56

350 29.69 1087.68

In the case of centre column loss, it can be seen that all the slabs are able to capture

the accidental limit load within the arching action. However the arching action in a

concrete floor leaves the slabs susceptible to sudden brittle crushing failure of

concrete. Hence relying on arching action is not recommended.

6.3.2 Tie Bar Diameter

As in previous cases an increase in the tie bar diameter allows the connection to

carry more load, and again it is seen that the force that the connection undergoes in

the arching action stage is more than the calculated accidental load that the structure

should be able to carry.

Page 158: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

158

(a)

(b)

(c)

Figure ‎6-15: Effect of tie bar diameter when central column is lost

0

200

400

600

800

1000

1200

1400

1600

0 200 400 600 800 1000 1200 1400 1600

Lo

ad

(k

N)

Vertical Displacement (mm)

Tie Diameter 10

Tie Diameter 14

Tie Diameter 18

Tie Diameter 24

Tie Diameter 30

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000

Ed

ge T

ie B

ar S

tra

in

Vertical Displacement (mm)

Tie Diameter 10

Tie Diameter 14

Tie Diameter 18

Tie Diameter 24

Tie Diameter 30

-0.05

0

0.05

0.1

0.15

0.2

0.25

0 200 400 600 800 1000 1200 1400 1600

1st

Ho

llo

wco

re T

ie S

tra

in

Vertical Displacement (mm)

Tie Diameter 10

Tie Diameter 14

Tie Diameter 18

Tie Diameter 24

Tie Diameter 30

Page 159: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

159

6.3.3 Tie Bar Ultimate Strain

Figure ‎6-16 shows the effect of tie bar ultimate tensile strain variation on the

connection behaviour in the case of central column lost. Similar to the previous cases

this parameter directly affects the catenary action of the connection.

Figure ‎6-16: effect of tie bar strain when central column is lost

6.3.4 Transverse Tie Bars

In the case of the central column removal, since the slabs in question can be

connected to adjacent slabs with tie bars in both horizontal directions; the failure

mode may change and depend on the failure of the last connecting tie in the

transverse direction.

Figure ‎6-17: Transverse tie bars in loss of a centre column

0

200

400

600

800

1000

1200

1400

0 500 1000 1500 2000 2500

Lo

ad

(k

N)

Vertical Displacement (mm)

Tie Ult. Strain 0.05

Tie Ult. Strain 0.1

Tie Ult. Strain 0.15

Tie Ult. Strain 0.2

Tie Ult. Strain 0.25

Tie Ult. Strain 0.3

Tie Ult. Strain 0.35

Tie Ult. Strain 0.4

0

200

400

600

800

1000

1200

1400

0 500 1000 1500 2000

Lo

ad

(k

N)

Vertical Displacement (mm)

Base Case

Model 1

Model 2

Model 3

Model 4

Model 5

Model 6

Page 160: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

160

The results in this section show similar structural behaviour of the floor system as in

the case of edge column loss, with the floor system being able to develop catenary

action. However, since the total applied load under accidental loading is much higher

than in the case of edge column loss (increased floor area) but the slab resistance

under catenary action is similar to that with edge column loss, the floor resistance

under catenary action is very low compared with the first peak load, indicating that

using catenary action would not be effective in resisting the floor load under

accidental loading condition.

6.4 Loss of Corner Column

Figure ‎6-18 shows a deformed shape of a model with the loss of a corner column.

Since there is no axial restraint available, it is not possible to develop catenary

action. Furthermore, since there is little slab bending resistance, the floor resistance

is very low, as shown by the load-displacement relationship in Figure ‎6-19-a.

Although this study is brief, it suggests that using the current construction practice,

precast floor system has little resistance to accidental loading in the event of corner

column loss. The method of providing tie bars is not effective. The only means of

providing resistance under corner column loss by improved bending resistance of the

corner bay slab through continuous construction.

Figure ‎6-18: Deformed shape of the model with loss of a corner column

Page 161: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

161

(a)

(b)

Figure ‎6-19: Load-displacement and tie bar strain diagram under corner column loss

6.5 Conclusions

This chapter has presented the results of an extensive set of parametric studies to

investigate the residual floor resistance after removal of an edge, an interior and a

corner column. The parameters investigated include those that were found to be able

to increase precast floor catenary action in ‎Chapter 4. The main conclusions are:

(1) In the case of corner column removal, the existing means of providing tie

bars is not effective. The structure will have very little resistance due to a

lack of horizontal restraints to help develop catenary action and a lack of

bending resistance. Continuous slab construction in the corner bays should be

considered.

(2) In the case of interior column removal, the floor resistance under catenary

action is very low and is unlikely to resist the accidental loading.

0

10

20

30

40

50

60

0 200 400 600 800 1000 1200

Lo

ad

(k

N)

Vertical Displacement (mm)

0

0.005

0.01

0.015

0.02

0.025

0.03

0.035

0.04

0.045

0 200 400 600 800 1000 1200 1400

Str

ain

Vertical Displacement (mm)

Page 162: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

162

(3) In the case of edge column loss, catenary action can develop in the tie bars to

provide some resistance to accidental loading. To further improve the

effectiveness of this method, the following (in order of decreasing benefit)

should be considered:

- Use the thinnest slab depth;

- Use tie bars with the highest ductility;

- Increase tie bar diameter;

- Introduce transverse tie bar.

Page 163: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

163

Chapter 7. Conclusion and Further Studies

This thesis presented the results of a numerical investigation into the resistance of tie

connection between Precast Concrete Floor Slabs (PCFS) against progressive

collapse and methods of improving this resistance. The objectives of the research

were:

A reliable FE model to examine the factors affecting the behaviour of the

connection between two Precast Concrete Floor Slabs (PCFS) until fracture

was established;

Parameters that affect PCFS tie connection behaviour in catenary action were

identified;

A predictive analytical method to foretell the behaviour of the PCFS tie

connection, validated by the parametric study results, was developed;

Effectiveness of current building code regulations and practical construction

methods for providing robustness of PCFS tie connection in steel framed

buildings, was assessed;

Methods for improving robustness of precast concrete floors in steel frame

buildings were suggested;

Mechanisms of collapse, due to loss of a column in different locations, in

representative steel framed buildings with PCFS were studied, and

suggestions for each case were made.

The main conclusions of this research were:

7.1 Literature Review

A brief review of the incidents leading the British Standard to consider the

robustness regulations was given. The background theory of robustness regulations

with special interest to tying regulations was presented and it was shown that the

current tying method is derived by only considering the equilibrium of forces in

catenary action. Neglecting the ductility of the tie bar, as the main parameter for

development of catenary action, can make the tying method susceptible to failure.

Page 164: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

164

It was shown that although the effectiveness of the tying method has already been

under scrutiny, there was a lack of suitable research on tying method and parameters

affecting the tie behaviour and ductility. The only major study (Engström, 1992) on

tying of PCFS was reviewed and it was shown that there were fundamental issues in

the‎ tests’‎ boundary‎ conditions‎ such as lack of axial restraint needed for inducing

proper tension in the tie bar. The assumptions made for development of an analytical

relationship by Engström (1992) suffered from some drawbacks such as:

Assumption of full tension in ties while slabs are totally suspended

Assumption of equal elongation in ties at both ends of slab and the tie

between slabs

The model could have benefitted from more realistic boundary conditions

By a brief review on the construction technology of PCFS, it was seen that due to

prestressing of tendons in the PCFS, prestressed slabs can cover a rather large span

and also can carry higher load in comparison to ordinary concrete slabs. This leads to

higher accidental load being applied to the PCFS tie connection, while the current

tying regulations do not take this extra loading into account.

7.2 Finite Element Model & Validation

The commercial package TNO-DIANA was chosen in this study as it was considered

to be an effective tool in modelling concrete owing to its many concrete modelling

options in different situations.

To establish the validity of DIANA models, a series of tests by Su et al. (2009) on

two axially restrained concrete beam assemblies with the middle support column

removed were simulated. The simulation results were close to the test results for the

vertical load-displacement relationship, the axial reaction force-displacement

relationship and the different stages of structural behaviour of the assembly.

Based on the validation results and the sensitivity study results, the following

simulation methodology was adopted:

The chosen material model for concrete was the Mohr-Coulomb plasticity for

compression and linear tension softening for tensile regime. The

Page 165: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

165

reinforcement was modelled with Von-Mises plasticity with perfect plastic

behaviour.

The element type chosen was the 20-noded solid brick quadratic element,

capable of capturing the bending of the model properly.

The mesh sensitivity study showed the element size of about 40 mm to yield

the best results along with the optimum analysis cost efficiency.

The boundary condition of the model should have appropriate axial restraint

in order to enable the model to depict arching and the following catenary

action.

The reinforcement was modelled using the embedded reinforcement option in

DIANA, which assumes a fully bonded condition of the steel rebar and

surrounding concrete.

7.3 Two-Dimensional Analysis of Slabs

To investigate whether the tie connection, designed according to current regulations,

between PCFS is able to resist the accidental loading after removal of the central

support, a two-dimensional model was developed. A series of simulations according

to manufacturer (Bison, 2012) load-span tables was performed. It was shown that the

connection’s‎tying‎resistance‎was‎not‎capable‎of‎developing‎enough‎catenary‎action‎

in order to resist the accidental load limit.

To suggest methods for improvement of connection resistance, a series of

parametrical studies were carried out to evaluate the effects of changing the

following design parameters: tie bar diameter, position, length, yield stress and

ultimate‎ strain;‎ the‎ slab’s‎ height,‎ length;‎ and‎ the‎ compressive‎ strength‎ of‎ the‎

grouting concrete in between the slabs which encases the tie bar. In this parametric

investigation, it was assumed the slabs were vertically supported and had various

degrees of axial restraint. Furthermore, it was shown that the axial restraint has only

a minor effect as long as the restraint has a capacity greater than the tensile strength

of the tie bars.

To improve the connection resistance to accidental loading, the following methods

may be used:

Page 166: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

166

Slab height: as the slab height increased it was shown that the tie bar ruptured

sooner; hence the use of thinnest possible slab is recommended.

Tie bar height: it was shown that due to different factors such as concrete

cover, distance between the forces on the slab, and straining of the tie bar, the

optimum location for the tie bar was at the mid-height of the slab.

Tie bar diameter: increasing the tie bar diameter boosted both resistance and

the elongation of the tie bar where the latter resulted in more vertical

displacement as well.

Tensile ultimate strain of the tie bar: directly affected the elongation and

ductility of the tie bar in catenary action, resulting in both higher resistance

and vertical displacement.

The tie bar yield stress: directly affected the tying force. Increase in the tie

bar yield stress increased the load carrying capacity of the connection, but the

elongation of the tie bar is unchanged.

7.4 Predictive Analytical Relationship of the 2D Model

Based on the parametric study results, a predictive analytical relationship has been

developed for the catenary action stage of the PCFS tie connection. In this

development, it was assumed that the tie bars could develop their full tensile strength

and slab failure was due to the tie bar fracture. The slabs were assumed to be cracked

through at the slab-slab connection interface and each slab underwent rigid

movements. Vertical displacement of the PCFS was purely due to elongation of the

tie bar. In order to obtain the total tie bar elongation, strain distributions along the tie

bar, from the numerical simulation models, were used to develop a series of

regression equations to relate the tie bar elongation as a function of the four factors

as follows:

Strain distribution with slab height:

Equation ‎7-1

Strain distribution with tie bar diameter:

Page 167: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

167

Equation ‎7-2

Strain distribution and tie bar height:

Equation ‎7-3

Strain distribution and ultimate tensile strain:

Equation ‎7-4

The resulting load-vertical displacement of the PCFS is as follows:

{ √ (

) }

Equation ‎7-5

Based on comparison with all the models in the parametric study in ‎Chapter 5, the

analytical method was shown to produce reasonably close results with the simulation

results for the load-vertical displacement relationship, the maximum displacement

and the maximum resistance of the PCFS tie connection.

7.5 Three-Dimensional Simulation of the Floor System

To assess whether the conclusions of the 2D simulations were applicable to the

more realistic 3-D structure, and to investigate the feasibility of using transverse tie

bars to improve the PCFS resistance to accidental loading, a number of scenarios of

realistic 3-D arrangement were simulated. These scenarios included corner column

removal, edge column removal and interior column removal.

The simulation results suggest that the transverse ties were not effective in boosting

the resistance of the structure under catenary action.

Page 168: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

168

When a corner column of the structure was lost the development of catenary action

was not possible, due to a lack of axial restraint. The only method of resisting the

accidental loading in this case may be providing the slabs with enough bending

resistance.

In the case of an edge column removal, the connection had the chance to develop

catenary action, but it was shown that the current design regulations did not provide

the connection with enough resistance to withstand the accidental load limit. In the

case of an internal column removal, the connection developed catenary action; but

since the load bearing surface related to the connection was increased, it was less

likely for the catenary action resistance to capture the accidental loading.

7.6 Limitations of the Current Study

Due to difficulty of overcoming numerical divergence when using load control in

DIANA simulations, displacement control was employed in this study. This means

that only point loading was considered. Nevertheless, because the conclusions of this

research were based on relative performance of one PCFS tie connection under one

point load, it is considered that the conclusions of this research are generally valid

when the slabs are under other loading conditions.

7.7 Future Studies

For completion of understanding of the PCFS tie connection behaviour, the

following recommendation may be made:

Experiments on the PCFS connection with realistic boundary conditions are

required:

The current literature regarding the tying of PCFS would benefit from

experimental data that considers other structural elements in the floor.

Although it was shown that the‎axial‎stiffness‎of‎the‎slabs’‎restraints‎did not

affect the catenary action significantly; this cannot be true if no axial restraint

are considered for the slabs as in Engström (1992), since in this case, the

effect of arching and catenary actions are neglected.

Dynamic effect of column removal can be considered:

Page 169: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

169

In the current study the behaviour of the PCFS tie connection was studied

considering that the load on the connection was applied in a static fashion.

Although depending on the nature of the accidental action this may be the

case, the column removal may happen in an abrupt manner which could add

dynamic aspects to the situation.

The effect of connections of the transverse beams on supporting the slabs

may be taken into account:

The focus of the current study was on the tie bar between the PCFS, while

under any longitudinal tie connection lies a beam, which itself is connected to

other structural members at its far end. If this connection is designed to

capture bending moments, it could have some effect on supporting the slabs

in question.

Considering discrete cracking for the connection between the PCFSs may

enhance the accuracy of the FE analysis:

Experiments (Engström, 1992) have shown that in the case of a column loss

and large displacement of the connection between slabs, the interface

between the slabs and grouting concrete detaches and forms the first crack of

the connection. Although the adopted concrete material model was able to

predict the location of the cracks properly, applying the discrete crack

approach that depicts the actual discretisation of the mesh in concrete would

allow more realistic study of the strain distribution along the tie bar.

Modelling the discrete crack in the finite element software DIANA is via the

interface elements. In the current version of DIANA the combination of two

interface elements leads to numerical divergence and since the bond-slip

behaviour of the tie bar was modelled with interface elements as well, the

smeared cracking approach was chosen over the discrete cracking model.

Page 170: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

170

Bibliography

Approved Document A - Structure. In: MINISTER, O. O. D. P. (ed.). Building

Regulations 2000.

BALDRIDGE, S. & HUMAY, F. K. 2003. Preventing Progressive Collapse in

Concrete Buildings. Concrete International.

BISON. 2012. Products [Online]. London. Available: www.bison.co.uk [Accessed

21/06/2011 2011].

BROOKER, O. 2008. How to design concrete buildings to satisfy disproportionate

collapse requirements. Surrey, UK: The Concrete Centre.

BS8110-1 2007. BS 8110-1:1997 Structural use of concrete Part 1: Code of practice

for design and construction, London, British Standard Institution.

BURNETT, E. 1975. The Avoidance of Progressive Collapse: Regulatory

Approaches to the Problem. Washington D. C.: Centre for building

technology.

BYFIELD, M. & PARAMASIVAM, S. 2007. Catenary action in steel-framed

buildings. ice, 160, 11.

CEB-FIP 2010. CEB-FIP Model Code 2010, Lausanne, Thomas Telford.

CFS. 2013. Prestressed Hollowcore Floor Slabs [Online]. Concrete Flooring

Systems. 2013].

CHERNOFF. 2009. The Royia Grizzell Foundation for Victims of Violence [Online].

Indianapolis. [Accessed 05 September 2009].

CHOI, J. H. & CHANG, D. K. 2009. Prevention of progressive collapse for building

structures to member disappearance by accidental actions. Journal of Loss

Prevention in the Process Industries, 22, 1016-1019.

CORLEY, W. G., MLAKAR, P. F., SOZEN, M. A., THORTON, C. H. 1998. The

Oklahoma City Bombing: Summary and Recommendations for Multi-hazard

Mitigation. J. Perf. of Constr. Fac., ASCE, 12(3), 100-112.

CPNI 2011. Review of international research on structural robustness and

disproportionate collapse In: INFRASTRUCTURE, C. F. P. O. N. (ed.).

London: Department for Communities and Local Government.

Page 171: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

171

DEMONCEAU, J.-F. 2008. Steel and composite building frames: sway response

under conventional loading and development of membrane effects in beams

further to an exceptional action. PhD, Liège University.

EDWARDS, A. D. & YANNOPOULOS, P. J. 1979. Local Bond-Stress to Slip

Relationships for Hot Rolled Deformed Bars and Mild Steel Plain Bars. ACI,

76, 405-420.

ELEMATIC. 2014. Extruder El9000EW Product Description [Online]. Finland.

2014].

ELLIOT, K. S. 2002. Precast Concrete Structures, Oxford, Antony Rowe Ltd.

ENGSTRÖM, B. 1992. Ductility of Tie Connections in Precast Structures. PhD,

Chalmers University of Technology.

ENGSTRÖM, B., MAGNUSSON, J. & HUANG, Z. 1998. Pull-Out Bond

Behaviour of Ribbed Bars in Normal and High-Strength Concrete with

Various Confinements. ACI Structural Journal, 180, 28.

FIB-BULLETIN-43 2008. Structural connections for precast concrete buildings.

FU, F. & LAM, D. 2006. Experimental study on semi-rigid composite joints with

steel beams and precast hollowcore slabs. Journal of Constructional Steel

Research, 62, 771-782.

FU, F., LAM, D. & YE, J. 2008. Modelling semi-rigid composite joints with precast

hollowcore slabs in hogging moment region. Journal of Constructional Steel

Research, 64, 1408-1419.

GARDEN, H. N. 1997. The Strengthening of Reinforced Concrete Members Using

Externally Bonded Composite Materials. PhD, University of Surrey.

GRIFFITHS 1968. Report of the inquiry into the collapse of flats at Ronan Point,

Canning‎Town.‎London:‎Her‎Majesty’s‎Stationery‎Office,.

GUSTAVSSON, K. 1974. Anchorage of Reinforcement bars in joints between

concrete elements. Chalmers Tekniska Hogskola.

HAI, L. N. N. 2009. Structural Response of Steel and Composite Building Frames

further to an Impact Leading to the Loss of a Column. PhD, University de

Liege.

HANSON. 2014. Hollowcore Flooring [Online]. Heidelberg Cement Group.

Available: http://www.heidelbergcement.com [Accessed 25/03/2014 2014].

Page 172: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

172

HEGGER, J., ROGGENDORF, T. & KERKENI, N. 2009. Shear capacity of

prestressed hollow core slabs in slim floor constructions. Engineering

Structures, 31, 551-559.

HENDRY, A. W. 1979. Summary of Research and Design Philosophy for Bearing

Wall Structures. Journal of the American Concrete Institute, 76, 723-737.

HOLMGREN, J. 1975. Deformations of Embedded Reinforcement bars. Stockholm:

Meddelande - Institutinen för Byggnadsstatik.

HUANG, Z., ENGSTROM, B. & MAGNUSSON, J. 1996. Experimental and

Analytical Studies of the Bond Behaviour of Deformed Bars in High Strength

Concrete. 4th International Symposium on Utilization of High-Strength/High

Performance Concrete. Paris.

IZZUDDIN, B. A., VLASSIS, A. G., ELGHAZOULI, A. Y. & NETHERCOT, D.

A. 2008. Progressive collapse of multi-storey buildings due to sudden

column loss — Part I: Simplified assessment framework. Engineering

Structures, 30, 1308-1318.

LAHNERT, B. J., HOUDE, J. & GERSTLE, K. H. 1986. Direct Measurement of

Slip Between Steel and Concrete. Journal of the American Concrete Institute,

83, 974-982.

LAM, D., ELLIOTT, K. S. & NETHERCOT, D. A. 1999. Steel — Concrete

Composite Construction with Precast Concrete Hollow Core Floor. In:

CHAN, S. L. & TENG, J. G. (eds.) Advances in Steel Structures (ICASS '99).

Oxford: Elsevier.

LAM, D., ELLIOTT, K. S. & NETHERCOT, D. A. 2000. Parametric study on

composite steel beams with precast concrete hollow core floor slabs. Journal

of Constructional Steel Research, 54, 283-304.

LAM, D. & NIP, T. F. 2002. Effects of transverse reinforcement on composite beam

with precast hollow core slabs. In: CHAN, S. L., TENG, J. G., K.F.

CHUNGA2 - S.L. CHAN, J. G. T. & CHUNG, K. F. (eds.) Advances in Steel

Structures (ICASS '02). Oxford: Elsevier.

LEE, D. Y. C. 2009. The Behaviour of Unbonded Post-Tensioned Concrete Slabs at

Elevated Temperatures. PhD, The University of Manchester.

LIU, J. L. 2010. Preventing progressive collapse through strengthening beam-to-

column connection, Part 1: Theoretical analysis. Journal of Constructional

Steel Research, 66, 229-237.

Page 173: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

173

MACLEOD, I. 2005. Supplementary Information on Modelling [Online]. Available:

http://www.imacleod.com/msa/supllinfo.php [Accessed 06 March 2010].

MAZZAROLO, E., SCOTTA, R., BERTO, L. & SAETTA, A. 2012. Long

anchorage bond–slip formulation for modelling of R.C. elements and joints.

Engineering Structures, 34, 330-341.

MENZIES, J. Use of Robustness Concepts in Practice. 2005 Graston. JCSS &

IABSE, 6.

MIRATASHI, S. M. 2011. RE: More Details of a Published Paper in ACI. Type to

TIAN, Y.

MOODY, W. T. 1990. Moments and Reactions for Rectangular Plates, Water

Resources Technical Publications, United States Department of the Interior

Bureau of Reclamation.

MOORE, D. B., BRE. The UK and European Regulations for Accidental Actions.

Workshop on Prevention of Progressive Collapse Multihazard Mitigation,

10-12 July 2002 U.S.A. Council of National Institute of Building Sciences.

NAAMAN, A. E. & NAJM, H. 1991. Bond-Slip Mechanism of Steel Fibre in

Concrete. ACI Material Journal, 88, 135-145.

NIST 2007. Best practices for reducing the potential for progressive collapse in

buildings. Washington, DC: National Institute of Standards and Technology ,

Rep., U.S. Dept. of Commerce.

O'REILY. 2013. Precast Pre-stressed Hollowcore Floor Slabs - O'Reily Concrete

[Online]. 2013].

OSTERAAS, J. D. 2006. Murrah Building Bombing Revisited: A Qualitative

Assessment of Blast Damage and Collapse Patterns. Journal of Performance

of Constructed Facilities © ASCE, 20(4).

PEARSON, C. & DELATTE, N. 2005. Ronan point apartment tower collapse and its

effect on building codes. Journal of Performance of Constructed Facilities,

19, 172-177.

PIOTROWSKI, C. & PERDUE, B. 1995. Researching the Oklahoma City bombing.

Psychological Reports, 77, 1099-1102.

REGAN, P. 1975. Catenary Action in Damaged Concrete Structures. ACI, 48, 191-

224.

ROSENTHAL, I. 1978. Full scale test of continuous prestressed hollowcore slab.

PCI.

Page 174: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

174

SALO, I., KANERVA, P., HIRSI, H. & KARSTILA, K. 1984. Tests on the strength

of a variax hollow core slab floor under seismic loading. Helsinki: Helsinki

University of Technology, Department of Civil Engineering.

SASANI, M. 2008. Response of a reinforced concrete infilled-frame structure to

removal of two adjacent columns. Engineering Structures, 30, 2478-2491.

SHI, Y., LI, Z.-X. & HAO, H. 2010. A new method for progressive collapse analysis

of RC frames under blast loading. Engineering Structures, 32, 1691-1703.

SPANRIGHT. 2013. Load Span Tables [Online]. Swindon. Available:

www.spanwright.co.uk.

SPIROLL. 2014. Casting Beds [Online]. Derby, UK. [Accessed 04/05/2014 2014].

SU, Y., TIAN, Y. & SONG, X. 2009. Progressive Collapse Resistance of Axially-

Restrained Frame Beams. ACI Structural Journal, 106, 600-607.

SUNI, E. 2005. The urban public law school with a small liberal arts feel [Online].

Missouri. Available: http://www1.law.umkc.edu [Accessed 05 September

2009].

TIMOSHENKO, S. 1959. Theory of Plates and Shells, Singapore, McGraw-Hill,

Inc.

TNO-DIANA 2010. DIANA User Manual. In: MANIE, J. & KIKSTRA, W. P.

(eds.) User’s Manual. Delft: TNO DIANA bv.

TORRE-CASANOVA, A., JASON, L., DAVENNE, L. & PINELLI, X. 2013.

Confinement effects on the steel–concrete bond strength and pull-out failure.

Engineering Fracture Mechanics, 97, 92-104.

ULTRA-SPAN. 2012. Ultra-Span Technologies Inc. History [Online]. Available:

http://www.ultraspan.ca/ [Accessed 06/03/2014 2014].

VLASSIS, A. G., IZZUDDIN, B. A., ELGHAZOULI, A. Y. & NETHERCOT, D.

A. 2008. Progressive collapse of multi-storey buildings due to sudden

column loss—Part II: Application. Engineering Structures, 30, 1424-1438.

WAY, A. G. J., COSGROVE, T. C. & BRETTLE, M. E. 2007. Precast Concrete

Floors in Steel Framed Buildings (SCI-P351), Berkshire, The Steel

Construction Institute (SCI).

WEARNE, P. 2000. Collapse: When Buildings Fall Down. TV Books. New York.

WHITTLE, R. & TAYLOR, H. 2009. Design of Hybrid Concrete Buildings, Surrey,

The Concrete Centre.

Page 175: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

175

ZOLGHADR JAHROMI, H., VLASSIS, A. G. & IZZUDDIN, B. A. 2013.

Modelling approaches for robustness assessment of multi-storey steel-

composite buildings. Engineering Structures, 51, 278-294.

Page 176: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

176

Appendix 1: Assessment of tie bars designed

according to British Standard regulations

Slabs with recommended span and load from a manufacturer (Bison, 2012) are

modelled. Based on the permanent and variable load in the load-span table

(Table ‎2-3), the accidental loading and tie bar diameter are determined for a 5-storey

building. It is shown that, due to high bending resistance of PCFS, the tie bar is not

capable of providing robustness. Hence it is recommended that the tie bar be

designed considering the ductility of the tie bar (as addressed in section ‎5.3).

Since the variable load in Table ‎2-3 includes concrete topping and selfweight of the

PCFS, the imposed load is considered to be constant as in section ‎2.1.1. The tie force

is calculated according to Equation ‎2-2 (repeated below), and the tie bar diameter is

determined based on the required cross sectional area of two steel rebars at yield

stress in each slab of width 1.2 m. The accidental load as a point load is calculated as

explained in section ‎4.2.

Equation A1-1

Equation A1-2

Based on the calculation results using the two above equations, the following

simulations (Table A1-1) were performed.

Page 177: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

177

Table A1-1: Simulations based on Bison (2012) load-span table

Slab

Height

(mm)

Slab

Length

(m)

Variable

Load

(kN/m2)

Imposed

Load

(kN/m2)

Tying

Force

(kN/m)

Tie

Diameter

in 2D

(mm)

Accidental

Load (kN)

Model

Name

250

6.9 10 3.8 101.57 28 71.48

SH250-

SL6.9

8 5 3.8 75.1 24 66.88

SH250-

SL8

8.8 4 3.8 73.22 24 70.05

SH250-

SL8.8

9 3.5 3.8 70.08 24 69.84

SH250-

SL9

9.9 1.5 3.8 55.96 20 68.9

SH250-

SL9.9

10.4 0.75 3.8 50.47 20 69.26

SH250-

SL10.4

300

6.8 15 3.8 136.36 32 84.04

SH300-

SL6.8

7.8 10 3.8 114.81 28 80.8

SH300-

SL7.8

9 7 3.8 103.68 28 82.44

SH300-

SL9

9.9 4 3.8 82.36 24 78.8

SH300-

SL9.9

10.9 2 3.8 67.43 24 78.04

SH300-

SL10.9

11.7 0.75 3.8 56.78 20 77.92

SH300-

SL11.7

Figure A1-1 compares the simulations’ load-deflection curves with the accidental

loads.

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH250-SL6.9

Page 178: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

178

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH250-SL8

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH250-SL8.8

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH250-SL9

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH250-SL9.9

Page 179: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

179

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH250-SL10.4

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH300-SL6.8

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH300-SL7.8

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH300-SL9

Page 180: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

180

Figure A1-1: comparison between simulation load-deflection curves and accidental load, with

BS tie bar

The results in Figure A1-1 indicate that relying only on the tying force, as specified

in the current design method, is not able to provide robustness for PCFS.

Using Equation ‎5-12 and the procedure explained in section ‎5.3, improvement can be

made to the designs in Table A1-1 by changing the tie bar diameters. Table A1-2

shows required tie bar diameters for slabs of thickness 250mm and 300mm.

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH300-SL9.9

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH300-SL10.9

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

SH300-SL11.7

Page 181: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

181

Table A1-2: Models with recommended tie diameters

Slab Height

(mm)

Model Name Tie

Diameter

in 2D

(mm)

Slab Height

(mm)

Model Name Tie

Diameter

in 2D

(mm)

250

SH250-SL6.9 32

300

SH300-SL6.8 36

SH250-SL8 32 SH300-SL7.8 36

SH250-SL8.8 34 SH300-SL9 38

SH250-SL9 34 SH300-SL9.9 38

SH250-SL9.9 34 SH300-SL10.9 38

SH250-SL10.4 36 SH300-SL11.7 38

The new simulation results are shown in Figure A1-2. They all confirm that the new

tie bar diameters are able to provide the slabs with sufficient resistance against the

accidental loads.

0

10

20

30

40

50

60

70

80

90

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH250-SL6.9a

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH250-SL8

Page 182: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

182

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH250-SL8.8

0

10

20

30

40

50

60

70

80

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH250-SL9

0

10

20

30

40

50

60

70

80

0 200 400 600 800 1000

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH250-SL9.9

0

10

20

30

40

50

60

70

80

0 200 400 600 800 1000

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH250-SL10.4

Page 183: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

183

0

10

20

30

40

50

60

70

80

90

100

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH300-SL6.8

0

10

20

30

40

50

60

70

80

90

100

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH300-SL7.8

0

10

20

30

40

50

60

70

80

90

100

0 100 200 300 400 500 600 700 800

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH300-SL9

0

10

20

30

40

50

60

70

80

90

100

0 200 400 600 800 1000

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH300-SL9.9

Page 184: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

184

Figure A1-2: Comparison of simulations’ load-deflection curve with accidental load, with

recommended tie bar

It should be noted that other parameters (such as tie bar position and ultimate strain)

could have been changed in order to enhance the slab performance. Here, though,

only the tie bar diameter was changed to illustrate the practicality of the tie bar size

determined by this method.

Table A1-3 compares the tying forces for the simulated cases recommended by the

BS and tying force resulting from the tie bar diameter recommended in Table A1-2.

0

10

20

30

40

50

60

70

80

90

0 200 400 600 800 1000

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH300-SL10.9a

0

10

20

30

40

50

60

70

80

90

0 200 400 600 800 1000

Lo

ad

(k

N)

Vertical Displacement (mm)

Accidental Load

Rec-SH300-SL11.7

Page 185: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

185

Table A1-3: Comparison of tie forces of the BS and recommended ties

Slab Height

(mm)

Model Name BS Tie

Force

(kN/m)

Recommended

Tie Force

(kN/m)

Percentage more

(Recommended/BS)

250

SH250-SL6.9 101.57 334.93 69.67

SH250-SL8 75.1 334.93 77.57

SH250-SL8.8 73.22 378.11 80.63

SH250-SL9 70.08 378.11 81.46

SH250-SL9.9 55.96 378.11 85.19

SH250-SL10.4 50.47 423.9 88.09

300

SH300-SL6.8 136.36 334.93 67.83

SH300-SL7.8 114.81 334.93 72.91

SH300-SL9 103.68 378.11 78.04

SH300-SL9.9 82.36 378.11 82.56

SH300-SL10.9 67.43 378.11 85.72

SH300-SL11.7 56.78 423.9 87.97

This comparison shows that the recommended tie force is 60-80% more than the tie

force calculated according to BS regulations. However, it should be noted that the

results of this study shows relying merely on the tie force does not necessarily

provide the PCFS connection with adequate robustness under accidental loading, and

other design parameters should be taken into account.

Page 186: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

186

Appendix 2: Evaluation of Analytical Relation

To evaluate the relationship of the tying force of PCFS connection in catenary action

several models have been constructed in which the parameters in the tying force

relationship (Equation ‎5-4 presented in ‎Chapter 5) has changed. Also these models

are verified against the relationship for prediction of the maximum displacement and

tying force in the catenary action stage (Equation ‎5-12 in ‎Chapter 5). Table A2-1 and

Table A2-2 show the characteristics of the constructed models with their model

number which is used in the graphs below in order to specify the models.

Page 187: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

187

Table A2-1: Models with tie bar of diameter 10 mm

Tie Bar

Diameter

(mm)

fy.steel

(MPa)

Slab

Height

(mm)

Slab

Length

(m)

Model

10

400

200

5 10-1

6 10-2

7 10-3

250

5 10-4

6 10-5

7 10-6

300

5 10-7

6 10-8

7 10-9

500

200

5 10-10

6 10-11

7 10-12

250

5 10-13

6 10-14

7 10-15

300

5 10-16

6 10-17

7 10-18

600

200

5 10-19

6 10-20

7 10-21

250

5 10-22

6 10-23

7 10-24

300

5 10-25

6 10-26

7 10-27

Page 188: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

188

Table A2-2: Models with tie bar of diameter 20 mm

Tie Bar

Diameter

(mm)

fy.steel

(MPa)

Slab

Height

(mm)

Slab

Length

(m)

Model

20

400

200

5 20-1

6 20-2

7 20-3

250

5 20-4

6 20-5

7 20-6

300

5 20-7

6 20-8

7 20-9

500

200

5 20-10

6 20-11

7 20-12

250

5 20-13

6 20-14

7 20-15

300

5 20-16

6 20-17

7 20-18

600

200

5 20-19

6 20-20

7 20-21

250

5 20-22

6 20-23

7 20-24

300

5 20-25

6 20-26

7 20-27

Page 189: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

189

0

2

4

6

8

10

12

14

16

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-1

0

2

4

6

8

10

12

14

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-2

0

2

4

6

8

10

12

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-3

Page 190: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

190

-5

0

5

10

15

20

25

30

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-4

0

5

10

15

20

25

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-5

0

2

4

6

8

10

12

14

16

18

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-6

Page 191: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

191

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-7

-5

0

5

10

15

20

25

30

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-8

0

5

10

15

20

25

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-9

Page 192: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

192

0

2

4

6

8

10

12

14

16

18

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-10

0

2

4

6

8

10

12

14

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-11

0

2

4

6

8

10

12

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-12

0

5

10

15

20

25

30

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-13

Page 193: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

193

0

2

4

6

8

10

12

14

16

18

20

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-14

0

2

4

6

8

10

12

14

16

18

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-15

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-16

0

5

10

15

20

25

30

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-17

Page 194: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

194

0

5

10

15

20

25

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-18

0

2

4

6

8

10

12

14

16

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-19

0

2

4

6

8

10

12

14

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-20

0

2

4

6

8

10

12

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-21

Page 195: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

195

0

5

10

15

20

25

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-22

0

2

4

6

8

10

12

14

16

18

20

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-23

0

2

4

6

8

10

12

14

16

18

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-24

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-25

Page 196: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

196

0

5

10

15

20

25

30

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-26

0

5

10

15

20

25

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 10-27

Page 197: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

197

0

5

10

15

20

25

30

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-1

0

5

10

15

20

25

30

35

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-2

0

5

10

15

20

25

30

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-3

0

5

10

15

20

25

30

35

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-4

Page 198: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

198

0

5

10

15

20

25

30

0 100 200 300 400 500 600

Axis

Tit

le

Vertical Displacement (mm)

Model 20-5

0

5

10

15

20

25

30

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-6

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-7

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-8

Page 199: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

199

0

5

10

15

20

25

30

35

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-9

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-10

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-11

0

5

10

15

20

25

30

35

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-12

Page 200: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

200

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-13

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-14

0

5

10

15

20

25

30

35

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-15

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-16

Page 201: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

201

0

5

10

15

20

25

30

35

40

45

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-17

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-18

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-19

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600 700

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-21

Page 202: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

202

0

10

20

30

40

50

60

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-22

0

5

10

15

20

25

30

35

40

45

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-23

0

5

10

15

20

25

30

35

40

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-24

0

5

10

15

20

25

30

35

40

45

50

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-26

Page 203: ROBUSTNESS OF STEEL FRAMED BUILDINGS WITH PRE-CAST

203

0

5

10

15

20

25

30

35

40

45

0 100 200 300 400 500 600

Lo

ad

(k

N)

Vertical Displacement (mm)

Model 20-27