road without drain - a great disaster
TRANSCRIPT
-
7/30/2019 Road Without Drain - A Great Disaster
1/7
ROADWITHOUT DRAIN
A GREAT DISASTER-
A case Study
By
Er. Nandanandan Das
Ex. E.I.C cum Secretary, Works,
Govt. Of Odisha
1
-
7/30/2019 Road Without Drain - A Great Disaster
2/7
The good road net work system is the symbol of development of the
country. Good road creates easy transportation. Even if the road is
improved and made good motor able condition, can be damaged due
to inadequate provision of drainage system. .
The provision of drains use:-
To carry storm water, waste water.
Act as cut off, which protect to entry of outside ground water to inside
of road.
V-Type line (Fig-I) drains act as prevention of accidents while passing
through villages and towns.
Typical Section of V-Type Lined Drain
2
-
7/30/2019 Road Without Drain - A Great Disaster
3/7
-
7/30/2019 Road Without Drain - A Great Disaster
4/7
The drainage layer is provided to release the water inside the road to outside
but when the same was blocked, the function of drainage of water from inside
of road to outside was stopped. Rather outside water easily entered to drainag
layer making up ward pressure from bottom of GSB & WMM layer to top
during monsoon.
This created deterioration of surface of road due to vertical water pressure from
bottom and by running of traffic on top. The formation of the road was with 7m
carriage way. The typical cross section of road has been given in (Fig. -II).
Crosses Section details - thickness of G.S.B. - 275mm. W.M.M. -250mm, D.B.M
-100mm, B.C -40mm total 665 mm i.e. 0.665m. The depth of drain should b
665mm + depth of storm water flow in the drain i.e. about 400mm below G.S.B
layer. So total depth was 1065mm. i.e. 1.065m. Slope of road was 1:2, so th
horizon coverage was 2.13m. Total effective length from centre of road wa
6+2.13 m. I.e. 8.13m.
Fig-IITypical Cross Section of Sambalpur Rourkela (SH-10)
4
-
7/30/2019 Road Without Drain - A Great Disaster
5/7
Since earth work was completed on almost entire stretch of road and paymen
on earth work item was released, subsequent bill was held up for rectificatio
of defects and trimming the slope of embankment and providing V-typearthen drain where ever necessary (See Fig.III).
Contractor was unwilling to attend such defect, as the length of road was mor
than 100 km and complained that this would have been pointed out from th
starting of the work.
Fig-III
1M
5
-
7/30/2019 Road Without Drain - A Great Disaster
6/7
When the contractor understood that the maintenance for the road for one yea
was to be made at their cost and the road will be damaged gradually, if the ove
burden earth were not removed.
Contractor was given option to move J.C.B on both side of road at a distance 8.5m from the centre of the road for a depth of 1.m from the formation leve
with 0.75m width, which was suitable.
The option was accepted. The contractor could complete making drain on bot
side for a length 110 km from Jharsuguda to Rourkela covering two package
since Author was in charge of those two packages. The road was saved from
further deterioration. Vide Fig-IV
Fig-IV
Always Engineers should derive the solution on problem as per the si
condition for arriving qualitative and quantitative work.
6
-
7/30/2019 Road Without Drain - A Great Disaster
7/7
THE END
7