road project
TRANSCRIPT
![Page 1: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/1.jpg)
Page 1 of 23
NORTH DAKOTA STATE UNIVERSITY
COLLEGE OF ENGINEERING AND ARCHITECTURE
DEPARTMENT OF CONSTRUCTION MANAGEMENT &
ENGINEERING
CME 701: CONSTRUCTION TECHNOLOGY AND
EQUIPMENT
Final Course Project: Planning and estimating one mile
highway project
By Moh’d Jawad Albakri
Submitted to
Instructor: Joseph Memba
![Page 2: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/2.jpg)
Page 2 of 23
Introduction:
This report describes the process for planning one mile interstate highway between
Fargo and Grand Forks in the State of North Dakota. The road has two lanes in each
direction with a median between them.
Process outline:
The first step is stripping material and cleaning the site along with determining
the equipment, time, quantity and cost for this step. Then we need to haul the
material and fill them on the road for building the sub grade course and
determine the equipment, cost, quantity and time for this step. Afterwards we
need to haul the material and fill them on the road for building the sub base
course and determine the equipment, cost, quantity and time for this step. The
fourth step is to haul the material and fill them on the road for building the base
course and determine the equipment, cost, quantity and time for this step. Then
we need to pave the asphalt on the road according to best practices to build the
pavement layer along with determining the equipment, cost, quantity and time for
this step
Stripping and clearing the site:
Stripping and clearing the site will be applied to the whole road including the
median and the shoulders. This will include removing the overburden material for
![Page 3: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/3.jpg)
Page 3 of 23
the whole site and removing clay for the whole site except in the median. Clay
will be beneficial for median landscaping. The overburden materials and clay are
hauled to the plant that is 10 miles away from the site. The first step is to choose
the right truck for hauling the overburden and clay materials. We should put into
consideration that the project is relatively small, so it is wise when hauling the
clay and overburden material to the plant, to take into consideration filling up the
truck with filling materials for the subgrade, sub base, base layers on the way
back. For this purpose we need hauling equipment that can haul the filling and
cutting material. Another factor will be that the slope is 2% and the tractor will be
operating off road, but it is in very good condition. Taking into consideration
that the truck needs to travel, 10 miles, the materials going to be free flow
materials and clay, and we need high capacity then Rigid Frame trucks will be
most suitable for this. The ADT has low capacity and speed, and the bottom
dump is not efficient for clay so the Rigid Frame is the most suitable choice. The
trucks will be filled to reach its heaped capacity. Heaped capacity saves a lot
when hauling. The weight of the material should be calculated to assure that the
truck can carry the weight. The project has to be done in seven to eight months.
We will assume that the project has to be done within 220 days and keep the rest
as contingency.
![Page 4: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/4.jpg)
Page 4 of 23
Along with the truck we will need an equipment to strip the land and load the
material to the truck. Scrapers are economical to distance up to 5,000 feet
according to table 3.2 from the text which is almost a mile. Dozers are efficient to
distance up to 300 feet. The third option is to use excavators for cutting the
materials and filling the trucks. We will compare the time for the scraper to cut
the materials and hauling them next to the truck and excavator + the time
needed for the excavator to move the materials to the truck to the time needed
for the excavators to cut the materials and moving them to the trucks.
Dozer:
First we will start with a dozer. The dozer will travel a maximum distance of 300
feet. It needs trucks and loaders to load the material to the truck. We will test the
efficiency of the dozer for the overburden materials and compare it to the scraper
with the loaders and trucks and loaders with trucks alone. The first step is to find
the production of one dozer based on the project conditions.
For the dozer we will use big dozer because of the large amount of hauling. We
will use D10 N as it has high capacity.
Dozers
![Page 5: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/5.jpg)
Page 5 of 23
Ideal production 680 lcy/hr
Material weight correction 2800
Weight Constant 27
Soil density to loos cy 2240 lb/lcy
Standard weight 2300 lb/lcy
Weight correction 1.026786
Average skill operator 0.6
Material-type correction factor 1.2
Operating-technique correction factor 1
Visibility correction factor 1
Efficiency 0.75
Machine transmission 1
Blade adjustment factor 1
Grade correction 1
Product of correction factors 0.554464
Production 377.0357 bcy/hr
Convert to bcy 301.6286 bcy/hr
Weight in bank state
pcf
Swell 0.25
C.of mass distance 300 ft
Downhill grade 0.02
![Page 6: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/6.jpg)
Page 6 of 23
O&O 95 $/hr
Operator Wage 15 $/hr
Operator Benefits Percentage 0.35
Total Operator Wage 20.25 $/hr
Cost Per Cubic Yard 0.382092 $ per cubic yard
Amount Required 18773.31 bcy
Work Shift 8 hrs per day
Hours needed to finish the job 62.23984 Hours
Days needed to finish the job 8 days
Total Operating Cost 7173.142 $
From the analysis above it takes 8 days to haul the overburden materials 300 feet
with operating cost of almost 7,000$. We need to take into consideration that
when moving the material 300 feet the truck and the loader have to move as well
which will increase the cost.
![Page 7: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/7.jpg)
Page 7 of 23
Scrapers:
Type Auger Elevating Push Pull
Use For rocks and hard
materials
For small quantities For large
quantities
We will make calculations for each equipment to determine the best combination. For
this project we will use Push Pull scrapers. We will choose the Cat 657G scraper as it is a
push pull and has a high capacity. Scrapers are economical for distance up to 3,000 feet
but can reach till 5,000 for larger equipment. We will have trucks and loaders in the
middle and at the end of the site so the average hauling distance will be 2600 feet,
because it will take for the first trip 5200 but for the second it will be less and less till it
reaches next to the trucks and the loaders. Other trucks and loaders will be at the end of
the site. The rolling resistance for road will be estimated as 60 lb/ton as the it is in
excellent condition but not compacted which equal 60/20 = 3% . We will haul the
material in the slope that is going downward so the grade will be – 2% then the total
resistance will be 1%. According to the performance chart the speed will be at 35 mph
for 1% total resistance in both loaded and unloaded, this is taken from the Cat manual. It
is found that it takes 5.4 days to finish the whole work in comparison with the dozer that
requires 8 working days. This is big difference. Add to that, the trucks and the loaders
![Page 8: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/8.jpg)
Page 8 of 23
don’t need to travel every three hundred feet to catch up with the dozer. The trucks and
the loaders should be at the end of the road and they will be loading the trucks which will
make the loading time a lot faster and more efficient.
Swell factor 0.75
Scraper type
Distance 5280 ft
Condition Normal
Avg haul speed 35 mph
Avg return speed 35 mph
Efficiency 0.83333333
Avg speed for acce. And deacce. 4 mph
Average distance 2600 ft
EVW 150761 lb
Load size 44 lcy
Load size 33 bcy
Unit weight 2800 lb/bcy
Load Weight 92400
Gross Weight 243161 lb
Loading time 1 min
Haul time 0.84415584 min
![Page 9: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/9.jpg)
Page 9 of 23
Return time 0.84415584 min
Dump time 0.6 min
turn time fill 0.21 min
turn time cut 0.3 min
Efficiency 0.83333333
Total cycle time 3.79831169 min
Operator 11 $/hr
O&O 89 $/hr
Total Cost 100 $/hr
Production per hour 434.403529 bcy/hr
Total required quantity 18773.3146
Hours required to whole quantity 43.2163031 Hrs
Days 5.40203789 Days
Total Cost 4321.63031 For Job
Cost per cubic yard 0.23020071 $/bcy
Based on the above comparison we will use a scraper for this kind of job. We will now
analyze removing the clay from all areas except from the median. The rolling resistance
for clay is different than for topsoil. This step is when the top soil is already removed.
![Page 10: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/10.jpg)
Page 10 of 23
Rolling Resistance 170 lb/ton
Rolling Resistance 8.5 %
Grade Resistance 2 %
Total Resistance Return 6.5 %
Total Resistance Haul 10.5 %
Material Clay
Swell factor 0.75
Scraper type 657G
Total Distance 5280 ft
Condition Normal
Avg haul speed 22 mph
Avg return speed 17 mph
Efficiency 0.83333333
Avg speed for acce. And deacce. 4 mph
Average distance 2600 ft
EVW 150761 lb
Load size 44 lcy
Load size 33 bcy
Unit weight 2700 lb/bcy
Load Weight 89100
Gross Weight 239861 lb
![Page 11: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/11.jpg)
Page 11 of 23
Loading time 1 min
Haul time 1.34297521 min
Return time 1.73796791 min
Dump time 0.6 min
turn time fill 0.21 min
turn time cut 0.3 min
Efficiency 0.83333333
Total cycle time 5.19094312 min
Operator 11 $/hr
O&O 89 $/hr
Total Cost 100 $/hr
Production per hour 317.861314 bcy/hr
Total required quantity 21902.2003
Hours required to whole quantity 68.9048946 Hrs
Days 8.61311182 Days
Total Cost 6890.48946 For Job
Cost per cubic yard 0.31460261 $/bcy
According to the above calculations it will take 15 days to remove the topsoil and clay.
All the materials will be hauled where loaders and trucks are there to move them to the
plant. Trucks should not come back empty, they should get filled with the materials that
are required for the different layers for the road construction.
![Page 12: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/12.jpg)
Page 12 of 23
We will use two scrapers to remove the overburden materials and clay which equals 7
working days because we will divide the total days by two as two of them are working on
the same time.
Loaders:
First we need to choose the appropriate loader for the project. We will choose the loader
first to find the balanced number of trucks afterwards. All the needed information is
available to estimate the production. We need to check tipping and all other factors that
affect production, which is shown on the following table.
Loader
Model 990K
Material Overburden
Unit Weight 2240 lb/lcy
Swell Factor 0.8
Static weight table 9.8 150,000
Load weight 41070.4
Fill Factor 0.95
Efficiency 0.833333333
Bucket Capacity 19.3 lcyd
![Page 13: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/13.jpg)
Page 13 of 23
Bucket Capacity for the material 18.335 lcyd
Cycle time 0.666666667 min
Cycle time 0.011111111 hour
Static check 33929.6 OK
Materials required to move 18773 bcy
Materials required to move 23466.25 lcy
Production 1375.125 lcyd/hr
Production 1100.1 bcy/hr
Production 1540.14 ton/hr
Hours needed 17.06481229
Days needed 2.133101536 days
From the above, it takes just 17 hours to haul all the overburden materials to the trucks.
This also show that the loader can travel to materials that where hauled at 2300 feet and
at the end of the road by the scrapers. The loader needs to travel to six locations which
will add extra time so we will take that it takes 3 days to fill the trucks with all of the
overburden materials.
![Page 14: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/14.jpg)
Page 14 of 23
Loader
Model 990K
Material Clay
Unit Weight 2000 lb/lcy
Swell Factor 0.75
Static weight table 9.8 150,000
Load weight 36670
Fill Factor 0.95
Efficiency 0.833333333
Bucket Capacity 19.3 lcyd
Bucket Capacity for the material 18.335 lcyd
Cycle time 0.666666667 min
Cycle time 0.011111111 hour
Static check 38330 OK
Materials required to move 21902 bcy
Materials required to move 29202.66667 lcy
Production 1375.125 lcyd/hr
Production 1031.34375 bcy/hr
Production 1375.125 ton/hr
![Page 15: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/15.jpg)
Page 15 of 23
Hours needed 21.23637245
Days needed 2.654546556 days
Here it takes another 3 days (including traveling time between dumping locations) to fill
all the tractors. This shows that one loader is a good balance for two scrapers. The total
time that is estimated to fill all cut materials is 6 days. There will be one extra day that
makes a difference between loading all the trucks and the scraper work. This mean that
we can bring the loader one day after the scrapers start working if we are renting it to
save money. Here in the sketch it shows where are the dumping location should be
where scrapers can dump the materials and trucks can dump the materials that are hauled
from the plant that are needed for the road layers.
![Page 16: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/16.jpg)
Page 16 of 23
Trucks:
The first and most important step is to balance the trucks numbers with the loader. We
need to do all the required calculations. We need to find the total cycle time which equals
dump, load, haul going and haul return for the truck. We need to take efficiency into
consideration. We will use the performance charts with the total resistance to determine
the speed. Though the truck can travel at maximum speed but 35 mph should be safe
enough. We then balance number of trucks to the loader to find the balanced number. All
the calculations were done on the following table for the overburden materials. We take
into consideration that the trucks will come back hauled with the filling materials, this
should save a lot of money. We can till from both calculations that the hourly production
for clay and overburden materials are almost the same, this should help us to determine
the quantity of material that the truck will have when coming back.
![Page 17: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/17.jpg)
Page 17 of 23
Material Overburden Swell 0.8
Truck Model 770G Truck Capacity Heaped 32.9 lcy
Balanced number of buckets 2 Dump time 1 min
Load time 1.333333333 min
Load weight 73696 lb
EVW 73254 lb
GVW 146950 lb
Grade Resistance 2 %
Rolling Resistance 3 %
Total Resistance going 5 %
Total Resistance coming 1 %
Going speed 35 Mph
Coming speed 35 Mph
Hauling Distance 10 miles
Hauling Time going 17.14285714 Min
Haul Time coming 17.14285714 Min
Total cycle time 36.61904762 Min
Truck production 45.82041612 lcy/hr
Balanced number of trucks 27.46428571 Trucks
Number of trucks 28 Trucks
Trucks cost 55 $/hr
Total trucks cost 1540 $/hr
Material to be hauled 18773 Bcy
Material to be hauled 23466.25 Lcy
Hours needed 18.29054443 Hours
Total cost 28167.43843 $
![Page 18: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/18.jpg)
Page 18 of 23
Material Clay Swell 0.75
Truck Model 770G Truck Capacity Heaped 32.9 Lcy
Balanced number of buckets 2 Dump time 1 Min
Load time 1.333333333 Min Load time (fill materials) at plant 1.333 Min
Load weight 65800 Lb
EVW 73254 Lb
GVW 139054 Lb
Grade Resistance 2 %
Rolling Resistance 3 %
Total Resistance going 5 %
Total Resistance coming 1 %
Going speed 35 mph
Coming speed 35 mph
Hauling Distance 10 miles
Hauling Time going 17.14285714 min
Haul Time coming 17.14285714 min
Total cycle time 37.95204762 min
Truck production 44.2110533 lcy/hr
Balanced number of trucks 28.46403571 Trucks
Number of trucks 28 Trucks
Trucks cost 55 $/hr
Total trucks cost 1540 $/hr
Material to be hauled 21902 bcy
![Page 19: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/19.jpg)
Page 19 of 23
Material to be hauled 29202.66667 lcy
Hours needed 23.59030838 Hours
Total cost 36329.0749 $
At this point all the overburden materials and clay materials are removed and similar
quantity of filling materials are brought to the site. As it is specified in the specifications
the ACC is 6’’. The subgrade materials are from mixed rocks and soil with unit weight
2950 lb/cy with 0.7 swell factor and 13.5 $ per ton. The subbase also from the rocks and
soil mixture that are obtained from the plant. Base course will be from course and fine
aggregate. We need first to determine the quantity that is needed for the subgrade layer
and subbase layer. For this we need to find the thickness. According to North Dakota
Asphalt conference for the subbase it is 16’’ and the subgrade it is 5’’ inches and 9’’
inches for the base course. The pavement is 6 inches from the project information. This
total is 36 inches which equal to the materials that have been removed from the site. The
total volume of materials to be hauled from the plant is 24640 cyd which means there are
no need for additional trips just to bring filling material and their cost and time are
included in hauling the cut materials.
We need now to spread the materials using the scrapers and rolling them to get the
subgrade, subbase and base courses then we can pave the highway with Asphalt. The
scrapers will load the materials. As all the materials are similar we will treat them as one
![Page 20: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/20.jpg)
Page 20 of 23
kind for saving time, as this project was supposed to be group project and it is done by
one student. With two scrapers it will take almost 6 days to spread all the materials on
the road.
Rolling Resistance 170 lb/ton
Rolling Resistance 3 %
Grade Resistance 2 %
Total Resistance Return 1 %
Total Resistance Haul 5 %
Material Fill materials
Swell factor 0.7 Scraper type 657G
Total Distance 5280 ft
Condition Normal Avg haul speed 35 mph
Avg return speed 35 mph
Efficiency 0.83333333 Avg speed for acce. And deacce. 4 mph
Average distance 5280 ft
EVW 150761 lb
Load size 44 lcy
Load size 30.8 bcy
Unit weight 2950 lb/bcy
Load Weight 90860 Gross Weight 241621 lb
Loading time 1 min
Haul time 1.71428571 min
Return time 1.71428571 min
Dump time 0.6 min
turn time fill 0.21 min
turn time cut 0.3 min
Efficiency 0.83333333 Total cycle time 5.53857143 min
Operator 11 $/hr
O&O 89 $/hr
Total Cost 100 $/hr
Production per hour 278.050039 bcy/hr
![Page 21: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/21.jpg)
Page 21 of 23
Total required quantity 24640 Hours required to whole quantity 88.6171429 Hrs
Days 5.53857143 Days
Total Cost 8861.71429 For Job
Cost per cubic yard 0.3596475 $/bcy
Number of scrapers 2
We need rollers to compact the layers behind the scrapers. As the production of the two
scrapers are not very high because of the traveling one roller would be enough roll all the
layers. From bellow even one roller can be enough for both scrapers. Roller is not on the
critical path so the time needed to finish the job is not critical. We will need the roller for
6 days to roll after both of the scrapers with daily operating cost of 400$ and then 2800$
for the six days.
Number of rollers
Compacted Width of Roller Pass 7 feet Speed 3 mph Compacted lift thickness 36 inches Number of passes req 16
Constant 16.3 Effecincy 0.833333 Compacted cubic yard per hr 641.8125 ccy/hr
1 bc = ccy 0.7 Bank cubic yard per hr for roller 916.875 Fill Rate in bank 278 cy/hr
Fraction 0.303204
Number of rollers 1
![Page 22: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/22.jpg)
Page 22 of 23
The final step is to pave the asphalt. First we need to apply a prime coat using an asphalt
distributer.
Asphalt distributer
residual application 0.035 gal/sy Length 5280 ft Width 56 ft Constant 9
emulsion rate 0.7 Amount of water 2
Liquid asphalt cement 1149.867 gal
Total gallons of emulsion 1642.667 gal Total gallons of diluted emulsion 1888848 gal Application rate of diluted emulsion 0.1 gal/sy
Paver
Model Ap600D Paving Width 24 feet
Paving speed 65 ft/min Road length 5280 ft Required time 1.353846 hrs Return speed 10 mph Number of lanes 4
Total hours 5.415385 hrs
![Page 23: Road Project](https://reader031.vdocuments.site/reader031/viewer/2022021918/58a3e8f01a28ab272e8b4fc7/html5/thumbnails/23.jpg)
Page 23 of 23
It takes 5.4 hours to pave the four lanes. The roller has to be driving after it as required in
the specifications.
Rent VS Buying
It is appropriate some times to rent instead of putting a lot of investment in projects that
don’t come often or when the company is just starting. Quotes were taken from a dealer
in North Dakota, Butler Machinery Company, though Oscar knew that it was a
university project but still provided me with renting rates. Here is an example from the
rates:
D9T with U dozer and rear ripper = $18,400/4 weeks with $96/hr. for excess hours
657G = $50,150/4 weeks with $214/hr. for excess hours
988K = $25,250/4 weeks with $108/hr. for excess hours
770G = $16,650/4 weeks with $71/hr. for excess hours
Based upon 160 hours of use per 4 weeks.
From the above rates it is practical to rent an equipment that we need for few days such
the paver instead of spending a lot of money on buying one. This is a one mile project so
most likely the company is fresh and would not want to invest a lot in machines. More in
depth analysis can be done but for time limitations this is what has be done for the one
mile project planning.