TOPIC OBJECTIVES
Business Process Procedure OverviewBackgroundA pipeline material is a material that flows directly into the production process from a pipeline (for example, oil), from a pipe (for example, tap water), or from another similar source (for example, electricity). A material from the pipeline is always available; i.e. it can be withdrawn from the pipeline at any time and in any quantity. The pipeline withdrawal has no effect on the existing warehouse stock or on the availability of the material.Only when you do this do you incur a liability toward the vendor. Payment is due at certain set intervals, for example, monthly.ScenarioSABIC have pipeline materials as part of their Bill of Material. They do not expect an invoice from the vendor for goods withdrawals from the pipeline. Instead, they will settle posted withdrawals and return deliveries weekly, and send the vendor a statement of the settlement. This settlement periodically will be set up as a background batch job. PrerequisitesPipeline handling is mandatory for materials with material type PIPE; i.e. only withdrawals from the pipeline can be posted for these materials.These materials have the following characteristics: They are neither procured nor planned. They can be withdrawn from the pipeline at any time and in any quantity. They are not stored or kept in stock. No physical inventory is taken. Pipeline movements are mandatory in all valuation areas; i.e. no other goods movements may be posted.
PROCEDURAL STEPS
Menu Path Logistics Materials Management Logistics Invoice Verification Automatic Settlement MRKO – Pipeline Settlement
Transaction Code MRKO
Last changed on: 04/08/23 Version: Final
SAP 4.6CWork Instruction
Page: 1 of 5
Invoice Verification
Perform the following steps of how to Perform Pipeline Settlement using the information below:
Menu path: Logistics Materials Management Logistics Invoice Verification Automatic Settlement MRKO – Pipeline Settlement
SAP Easy Access
1. Double Click on MRKO – Consignment and Pipeline Settlement.
Last changed on: 04/08/23 Version: Final
SAP 4.6CWork Instruction
Page: 2 of 5
Invoice Verification
Consignment and Pipeline Settlement
2. Update the following required and optional fields:
Field Name Description Values
Company code Enter the required company code here
Example: 1200
Vendor Code identifying the vendor account
Example: 100096
Plant Code identifying the operational unit of the company where the material is manufactured and stored
Example: 1200
Material Code identifying a product or component
Example: 23000000
3. Click <radio button> Settle to perform pipeline settlement.
4. Click Execute Button .Last changed on: 04/08/23 Version: Final
SAP 4.6CWork Instruction
Page: 3 of 5
Invoice Verification
Consignment and Pipeline Settlement
The system had performed postings according to your criteria and generated the report that shows the posted documents. You can display the document details.
5. To display a document, double click on one of the line items. For example, double click on 1200 - 100096 - 4900003284 - 2002 - 1 - 01.12.2002 - 1200 - 23000000 - 10 - TO - 5,000.00 - SAR - 51 in list box.
Last changed on: 04/08/23 Version: Final
SAP 4.6CWork Instruction
Page: 4 of 5
Invoice Verification
Display Document: Overview