risk managament by vilas mahajan
TRANSCRIPT
1
Risk Management
By – Vilas Mahajan
The Risk
• Exposure to the possibility of loss, injury ,or other adverse or unwelcome circumstance ; a
chance or situation involving such a possibility ……Oxford Dictionary • ‘Effect of uncertainty on objectives’
~ Uncertainties include events (which may or not happen) and uncertainties caused by a
lack of information or ambiguity …..ISO Guide -73
The Risk
• Future problems that can be avoided or mitigated, rather than current ones that must be immediately addressed.
• Risk can be seen as relating to the Probability of uncertain future events.
• The probable frequency and probable magnitude of future loss.
• Risk is …..the product of ( probability of a hazard resulting in an adverse event) * ( severity of event)…… -
OHSAS
The Risk
• Risk versus Uncertainty :
~ Uncertainty is immeasurable ,not possible to calculate ,while risk is measurable.
~ One may have uncertainty without risk but not risk without uncertainty.
~ Uncertainty is the absence of information about future events
Risk Management
What is Risk Management ?
~ Process steps that enable improvement in decision making
~ A logical and systematic approach
~ Identifying opportunities
~ Avoiding or minimising losses
Risk Management
What is Risk Management ? ~ Risk Management is the name given to a logical and
systematic method of identifying, analyzing, treating and monitoring the risks involved in any activity or process.
~ Risk Management in Project is about proactively working with project stakeholders to minimise the risk and maximise the opportunities associated with project decisions.
Risk Management
• The aim is not to avoid risk but to make more informed decisions to ensure that project objectives are achieved and , ideally, exceeded.
• The Challenge is not to avoid risk , but to take calculated risks, by recognising and managing effectively
• Risk Management is a proactive process of looking forward and is fundamentally different from Crisis
Management. ~ Crisis Management is reactive and backward
looking.
Risk Management
What is Risk Management ? ~ Risk Management is a methodology that
help managers make best use of their available resources.
Risk Management
Who uses Risk Management ?• Risk Management practices are widely used in public and the
private sectors, covering a wide range of activities or operations.
These include: ~ Finance and Investment ~ Insurance
~ Health Care
~ Public Institutions
~ Governments
Risk Management
How is Risk Management used?
~ The Risk Management process steps are a generic guide for any organization,
regardless of the type of business, activity or function.
Risk Management
• The basic process steps are: ~ Establish the context
~ Identify the risks ~ Analyze the risk ~ Evaluate the risk ~ Treat the risk
Risk Management
• Risk is dynamic and subject to constant change, so the process includes continuing:
~ Monitoring and review
~ Communication & consultation
Risk Management• The Risk Management process: ~ Establish the context : - The strategic and organizational context in
which risk management will take place
- For example, the nature of business, the risks inherent in the business and the
business priorities.
Risk Management
• The Risk Management process: ~ Identify the risks : - Defining types of risk, for instance, ‘Strategic’ risks to
the goals and objectives of the organization. - Identifying the stakeholders, (i.e., who is involved or
affected).
- Past events, future developments.
~ Monitor and review ~ Communicate & consult
Risk Management
• The Risk Management process: ~ Analyze the risks - How likely is the risk event to happen? (Probability and
frequency?)
- What would be the impact, cost or consequences of that event occurring? (Economic, political, social?)
~ Monitor and review ~ Communicate & consult
Risk Management
• The Risk Management process: ~ Evaluate the risks
- Rank the risks according to management priorities, by risk category and rated by likelihood and possible cost or consequence.
- Determine inherent levels of risk.
Risk Management
• The Risk Management process: ~ Treat the risks : - Develop and implement a plan with specific
counter-measures to address the identified risks.
~ Consider: - Priorities (Strategic and operational)
- Resources (human, financial and technical)
- Risk acceptance, (i.e., low risks)
Risk Management
• The Risk Management process: ~ Treat the risks : - Document your risk management plan and describe the reasons behind selecting the risk and for the treatment chosen.
- Record allocated responsibilities, monitoring or evaluation processes, and assumptions on residual risk.
Risk Management
• The Risk Management process: ~ Monitor and review : - In identifying, prioritizing and treating risks,
organizations make assumptions and decisions based on situations that are subject to change,
(e.g., the business environment, trading patterns, or government policies).
- Risk Management policies and decisions must be regularly reviewed.
Risk Management• The Risk Management process: ~ Monitor and review : - Risk Managers must monitor activities and processes to determine the accuracy of planning assumptions and the effectiveness of the measures taken to treat the risk.
- Methods can include data evaluation, audit, compliance measurement.
~ Communicate & consult
Risk Management• Evaluate the risks - After identifying and analyzing
the risks, you can evaluate …….• What is the likelihood of the risk event occurring? - Almost certain - Likely - Moderate - Unlikely - Rare
Risk Management
• What is the consequence if the risk event occurs?
- Extreme - Very high - Moderate - Low - Negligible
Risk Management
• Evaluate the risks : - Describe or quantify exactly what is the ‘Likelihood’ and ‘Consequence’ terms mean to you.
- This helps in ensuring a consistent approach in future risk assessment and review and monitoring.
- It promotes a common understanding within the Administration.
Risk Management
• Evaluate the risks :
After establishing ‘Likelihood’ and ‘Consequence’, tabulate the workouts……..
Risk Management• Evaluate the risks : Extreme Very high Moderate Low Negligible
Almost certain Severe Severe High Major Moderate
Likely Severe High Major Significant Moderate
Moderate High Major Significant Moderate Low
Unlikely Major Significant Moderate Low Very low
Rare Significant Moderate Low Very low Very Low
Risk Management
• Treating the risks - Low and very low level risks can normally be accepted, subject to on-going monitoring.
- All other risks are included in the management plan.
- The plan catalogues the risks, the level of risk, and describes a treatment.
- The treatment is the action proposed, (and perhaps the resources allocated).
Risk Management
• Treating the risks : ~ Development of Risk Profiles
~ Industry audits
~ Random examinations
~ Targeted selections
~ Physical examination
~ Compliance improvement
28
Risk ManagementContract Risk Management
• Risks are the Chances or Probabilities of Damage or Loss.
• Risks are to be ..• Identified• Understood• Evaluated and..• Mitigated
• Risk Management is a subject of guesstimate of future.
29
Risk ManagementContract Risk Management
• Element Causing Risks..
• “Silence” on Certain Aspects• Inadequate Specifications
• “Openness” on Certain Aspects
• Unlimited Liabilities
30
Limitation on Liabilities Seller’s liabilities are specified under various
clauses for identified circumstances. These are : Termination of Contract - risk purchase Warranty / Guarantee - risk purchase Defects Liability Consequential & or indirect damages Indemnities Liquidated damages against delayed delivery
& shortfall in performance
31
Limitations on Liabilities
Seller’s liabilities vary as per the stipulations of individual clauses.
Put Cap on Overall Liabilities of the Seller arising out of All Clauses in the Contract.
Limitation of Liability
• Clause 17.6 :- FIDIC ~ Neither Party shall be liable to the other Party for loss of use of any Works ,loss of profit, loss of any
contract or for any indirect or consequential loss or damage which may be suffered by the other Party in connection with the Contract,
other than ….. (a) Under Sub-Clause16.4 (Payment on Termination)
and (b) Sub-Clause 17.1( Indemnities )
Limitation of Liability~ The total liability of the Contractor to the Employer , under
or in connection with the Contract , other than …… (a) under Sub – Clause 4.19 (Electricity, Water, and Gas), (b) Sub –Clause 4.20 ( Employer’s Equipment and Free-
Issue Material), (c) Sub – Clause 17.1( Indemnities) and (d) Sub-Clause 17.5 (Intellectual and Industrial Property
Rights), shall not exceed the sum stated in the Particular
Conditions or ( if a sum is not so stated ) the Contract Price stated in the Contract Agreement .
Limitation of Liability
~ This Sub – Clause shall not limit liability in any case of ……. fraud , deliberate default or reckless misconduct by the defaulting Party.
35
Risk ManagementContract Risk Management
Force Majeure
• Unforseeable Circumstances
• Beyond Party’s Normal Business Acumen.
• Caused By An Irresistible Force.
• Unavoidable Inspite Of The Reasonable Care
• Beyond Party’s Control.
36
Risk ManagementContract Risk Management
Force Majeure Events• Nature• Government• Wars• Public Actions
• Industrial Circumstances
• Shortage Of Inputs
Risk Management Force Majeure
~ Clause 19.1 :- FIDIC – Definition of Force Majeure
In this Clause, "Force Majeure” means an exceptional event or circumstance :
(a) which is beyond a Party’s control,
(b) which such Party could not reasonably have provided against before entering into the Contract.
Risk Management Force Majeure
(c) which ,having arisen, such Party could not
reasonably have avoided or overcome and,
(d) which is not substantially attributable to the other Party.
Risk Management Force Majeure
~ Force Majeure may include ,but is not limited to, exceptional events or circumstances of the kind listed below ,so long as conditions (a) to (d) above are satisfied :
(i) war ,hostilities (whether war be declared or not ), invasion act of foreign enemies,
(ii) rebellion ,terrorism, revolution ,insurrection ,military or usurped power, or civil war,
(iii) riot ,commotion, disorder, strike or lockout by person other than the Contractor’s Personnel and other
employees of the Contractor and Sub-contractors,
Risk Management Force Majeure
(iv) munitions of war, explosive materials, ionising
radiation or contamination by radio-activity, except as may be attributable to the Contractor’s use of such munitions ,explosives, radiation or radio- activity, and
(v) natural catastrophes ,such as earthquake, hurricane ,typhoon or volcanic activity.
Risk Management Force Majeure
~ Clause 19.2 :- Notice of Force Majeure If a Party is or will be prevented from performing any of
its obligations under the Contract by Force Majeure ,then it shall give notice to the other Party of the event or circumstances constituting the Force Majeure and shall specify the obligations, the performance of which is or will be prevented. The notice shall be given within 14 days after the Party became aware , or should have became aware, of the relevant event or circumstance constituting Force Majeure.
Risk Management Force Majeure
The Party shall having given notice, be excused performance of such obligations for so long as such Force Majeure prevents it from performing them.
Notwithstanding any other provision of this Clause, Force Majeure shall not apply to obligations of either Party to make payments to the Party under the Contract.
Risk Management Force Majeure
~ Clause 19.3 :- Duty to Minimise Delay Each Party shall at all times use all reasonable
endeavors to minimise any delay in the performance of the Contract as a result of Force Majeure.
A Party shall give notice to the other Party when it ceases to be affected by the Force Majeure.
Risk Management Force Majeure
~ Clause 19.4 :- Consequences of force Majeure If the Contractor is prevented from performing any of
his obligations under the Contract by Force Majeure of which notice has been given under Sub-Clause 19.2 [ Notice of force Majeure], and suffers delay and/or incurs Cost by reason of such Force Majeure the Contractor shall be entitled subject to Sub-Clause 20.1[Contractor’s Claims]to:
Risk Management Force Majeure
(a) an extension of time for any such delay, if Completion is or will be delayed under Sub-Clause 8.4 [Extension of Time for Completion], And
(b) if the event or circumstance is of the kind descried in sub –paragraphs(i) to (iv) of Sub –Clause 19.1[Definition of Force Majeure] and in the case of subparagraphs (ii) to (iv) ,occurs in the Country, payment of any such Cost.
After receiving this notice,theEmpolyer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters
Risk Management Force Majeure
~ Clause 19.5 :- Force Majeure Affecting Subcontractor
IF any Subcontractor is entitled under any contract or agreement relating to the Works to relief from force majeure on terms additional to or broader than those specified in this Clause ,such additional or broader force Majeure events or circumstances shall not excuse the Contractor’s non –performance or entitled him to relief under this Clause.
Risk Management Force Majeure
~ Clause 19.6 :- FIIDC Optional Termination, Payment and Release If the execution of substantially all the Works in
progress is prevented for a continuous period of 84 days by reason of Force Majeure of which notice has been given under Sub-Clause 19.2 [Notice of Force Majeure],or for multiple periods which total more than 140 days due to the same notified Force Majeure ,then either Party may give to the other Party a notice of termination of the Contract.
Risk Management Force Majeure
In this event, the termination shall take effect 7 days after the notice is given, and the Contractor shall proceed in accordance with Sub-Clause 16.3[Cessation of Work and Removal of Contractor’s Equipment]Upon such termination, the Employer shall pay to the Contractor:(a) the amounts payable for any work carried out for which a price is stated in the Contract;
Risk Management Force Majeure
(b) the Cost of Plant and Materials ordered for the Works which have been delivered to the Contractor, or of which the Contractor is liable to accept delivery ;this Plant and Materials shall become the property of(and be at the risk of) the Employer when paid for by the Employer, and the Contractor shall place the same at the Employer’s disposal;
(c ) any other Cost or liability which in the circumstance was reasonably incurred by the Contract in the expectation of completing the Works;
Risk Management Force Majeure
(d) the Cost of removal of Temporary Works and Contractor’s Equipment from the Site and the return of these items to the Contractor’s work in his country (or to any other destination at no greater cost );and
(e) the Cost of repatriation of the Contractor’s staff and labour employed wholly in connection with the Works at the date of termination.
Risk Management Force Majeure
~ Clause 19.7 :- Release from Performance under the Law
Notwithstanding any other provision of this Clause ,if any event or circumstance outside the control of the Parties ( including ,but not limited to ,Force Majeure) arises which makes it impossible or unlawful for either or both Parties to fulfil its or their contractual obligations or which ,under the law governing the Contract, entitles the Parties to be released from further performance of the Contract, then upon notice by either Party to the other Party of such event or circumstance :
Risk Management Force Majeure
(a) the Parties shall be discharged from further performance, without prejudice to the rights
Of either Party in respect of any previous breach of the Contract, and
(b) the sum payable by the Employer to the Contractor shall be the same as would have been payable under Sub – Clause 19.6 [Optional Termination ,Payment and Release ]
if the Contract had been terminated under Sub- Clause 19.6.
Generic Formula for Variation Adjustment
= adjustment multiplier to be applied for the contract value.
a = fixed coefficient, non adjustable part of the contract value.
b, c, d….. = coefficients of percentage of each cost element.
Ln, En, Mn….. = current cost indices/ reference prices for the period ‘n’
L0, E0, M0….. = Base cost indices/ reference prices on the Base Date 53
.....
OOO
n
MMnd
EEnc
LLbaPn
Pn
54
i20.060.020.0 XSPECHECH
BPABPAXSPSP
O
N
O
NON
Price Variation Algorithm:
• SP = Sales Price; N = New ; O = Current; i=Initial• BPA = Index Price per MT of Bisphenol A (BPA)
• ECH =Index Price per MT of Epichlorohydrin (ECH)
Where,
VARIATIONS PERTAINING TO MATERIAL COST
55
VARIATIONS PERTAINING TO LABOUR COST
• Necessary when the supplies are labour intensive• Variation in basic wages of specified labour category • Variation in dearness allowance
Wv – WbWb
• Pv = Price variation payable; Pq = Quoted Price• Iv = Average consumer Price Index for Ind. Workers for Pune for later 2/3 rd period• Ib = Index for March (current year)• Wv =Average Minimum basic Wages of skilled worker in seller’s works for the month of completion of fabrication• Wb = Wages for March (current year)
+ 0.30 Pq xPv = 0.60 x Pq x Iv – IbIb
56
II शुभं भवतु II