risk-based oversight

Upload: rob-de-la-espriella

Post on 03-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Risk-Based Oversight

    1/17

    Fall 2005Nuclear Oversight Conference

    Strategies forImplementing

    Risk-Based Oversight

  • 8/12/2019 Risk-Based Oversight

    2/17

    Fall 2005Nuclear Oversight Conference2

    In This Presentation:

    Excerpts from the St. Lucie Nuclear

    Assurance Business Plan: Department Areas of Emphasis Administrative Letter 17, Risk Based

    Oversight Daily process used for assigning oversight Results

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    3/17

    Fall 2005Nuclear Oversight Conference3

    St. Lucie Nuclear Assurance Organization

    Kathi ButlerStaff Technician

    Ed ArmandoSRO (PWR, BWR)

    Bruce ParksSRO (PWR)

    Lead AuditorQC Inspector (Mech II)

    John HaugerSRO (PWR)

    Bob EavensonChem Tech

    QC Inspector (Mech I)

    VACANCYRadiation Protection

    Mike SnyderAudit Supervisor

    Areas = Operations,RP / CHM

    Kathy GettyISI/IST, ENG

    QC Inspector (Mech I)Lead Auditor

    John LuchkaChem, Ops

    QC Inspector (Mech II)Lead Auditor

    Jim McNeySecurity

    QC Inspector (Mech I)Lead Auditor

    Doug MelodyQC Level III Elec/IC

    QC Inspector (Mech II)Lead Auditor

    Bob CarrollEngineer

    Dom FucaTechnical Reviews and Assessements Supv.

    Areas = Engineering,Fire Protection

    George IngramQC Level III Mech

    QC Inspector (Elec/IC II)Lead Auditor

    Mike MeileyQC Level III Civil

    QC Inspector (Mech I)

    Jim NormanQC Inspector (Mech II)

    QC Inspector (Elec/IC I)QC Inspector (Coatings II)

    Lou PanessaQC Inspector (Elec/IC II)QC Inspector (Mech II)QC Inspector (Civil II)

    VACANCYQC Inspector

    Greg PustoverQuality Control Supervisor

    Areas = Maintenance,Work Management

    Rob De La EspriellaSite Quality Manager

  • 8/12/2019 Risk-Based Oversight

    4/17

    Fall 2005Nuclear Oversight Conference4

    Areas of Emphasis*:

    Nuclear Safety

    Plant Reliability

    Risk Significant ctivities

    *Established in 2000

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    5/17

    Fall 2005Nuclear Oversight Conference5

    Areas of Emphasis:

    Nuclear Safety

    RCS Pressure Boundary SSCs required to mitigate theconsequences of an accident

    SSCs required to shutdown and maintainthe plant in a safe condition

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    6/17

    Fall 2005Nuclear Oversight Conference6

    Areas of Emphasis:Plant Reliability

    Processes and Procedures that supportequipment reliability System Health Reports Plant Health Committee Maintenance Rule Work Management Process Outage Management PM Optimization

    Critical Spare Parts Program

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    7/17

    Fall 2005Nuclear Oversight Conference7

    Areas of Emphasis:Risk Significant ctivities

    Risk = Probability + Consequences(Error Rate) (Defense in Depth)

    Risk -B ased Overs ig h t

    Error Rate: Work Preparation Work Performance Work Feedback

    KEY: Focus on CRITICAL TASKS

    Defense-in-Depth: ENGd Controls

    ADMIN Controls Oversight Controls

  • 8/12/2019 Risk-Based Oversight

    8/17

    Fall 2005Nuclear Oversight Conference8

    Administrative Letter 17,Risk Based Oversight

    SCOPE:

    Risk-management is a fundamental component ofmaintaining safety at operating nuclear power plants. The guidance in this AL defines how theQuality Department evaluates the risk associatedwith plant activities on a daily basis, and howQuality Department Supervisors will establish theappropriate oversight plan based on relative risk,department priorities and available resources.

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    9/17

    Fall 2005Nuclear Oversight Conference9

    Administrative Letter 17Risk Based Oversight

    INPUTS: St. Lucie Nuclear Plant Daily Status Reports for

    both units (including operational focus items andunplanned control room annunciators)

    Configuration Risk Management ProgramImplementation (ADM-17.16)

    Daily Configuration Risk Management Program(CRMP) calculations (Modes 1, 2, 3) CRMP / Shutdown Safety Assessments (Modes

    4,5,6, defueled) Operations control room logs for both units

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    10/17

    Fall 2005Nuclear Oversight Conference10

    Administrative Letter 17Risk Based Oversight

    INPUTS:

    The Top Ten Equipment Issues list for the station The list of Operator Work-Arounds and Burdens The list of control room deficiencies for both units The list of Red and Yellow PWOs being worked for

    the week The list of Maintenance Rule systems in a(1)

    status The list of System Health Reports with RED

    systems

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    11/17

    Fall 2005Nuclear Oversight Conference11

    Administrative Letter 17Risk Based Oversight

    Nuclear Safety Elements1. Operations

    Conservative Decision Making Culture Use of OLRM/Shutdown Safety Assessments Involvement in Work Management & Equipment

    Reliability2. Configuration Management

    Design (e.g. TEDB, Drawings & Plant)

    Operational Margin (e.g. GL 91-18 evolutions) Regulatory Control ( e.g. Tech Specs)3. Equipment Reliability

    System Health Monitoring Maintenance Rule Program

    4. On-site / Offsite Safety Review Committees - Oversight

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    12/17

    Fall 2005Nuclear Oversight Conference12

    Administrative Letter 17Risk Based Oversight

    Plant Reliability Elements1. Work Management

    Daily Scheduling & Planning Outage Scheduling & Planning Metrics & Process Improvements

    2. Maintenance Corrective Elective On-line Maintenance (CMMs) Predictive Preventative Modifications

    3. Corrective Action Program Problem identification Problem resolution Self Assessments Significant Events/Root Cause

    4. Chemistry Controls Primary (SG tubes) Secondary (e.g. Secondary Pipe Walls)

    ODCM controls

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    13/17

    Fall 2005Nuclear Oversight Conference13

    Administrative Letter 17Risk Based Oversight

    Other Risk Significant Activities

    1. Personnel Safety Industrial (e.g. PPE, Fall Protection,

    Confined Space, Electrical Shock) Radiological Protection

    2. Emergency Preparedness3. Security4. Fire Protection5. Training (e.g. Qualifications & Safety Culture)

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    14/17

    Fall 2005Nuclear Oversight Conference14

    Administrative Letter 17Risk Based Oversight

    DAILY ASSIGNMENTS: Assessment of individual risk Assessment of aggregate risk Assignments based on skills available Tracking assignments to conclusion

    Risk -B ased Overs ig h t

  • 8/12/2019 Risk-Based Oversight

    15/17

    Fall 2005Nuclear Oversight Conference15

    Risk -B ased Overs ig h tRisk Based Oversight for Wednesday 9/1/04

    Protected Train: BC o n d i t i o no r A c t i v i t y

    R i s k A g g r e g a t eR i s k

    I s s u e s o r C o n c e r n s P l a n tS c h e d

    ule

    O v e r s i g h t Ta s k A s s i g n e e P r o d u c t s C N OD N ASQM

    ReactivityManagementoversightgroupmeetings

    Lack ofoversight =Potential forReactivityMgmt event

    Secondarysystems thatcan affectreactivity notbeing properlymaintained

    Is the ReactivityManagementOversight groupoperatingeffectively/adequately

    Access station'ssensitivity toReactivityManagement

    CR / DQS/ QR

    RCS LeakRate -30Day LCOstarted8/23/04

    Potential RCSpressureboundary leak

    Problems withRCS leakdetectionequipment incontainment

    Flange downstream ofV-1452 (top of Pzr)leaking

    1330meeting

    Leak repair activities

    QR - PanessaDeveloping V1452repair plan

    CR / DQS

    1A ICWPedestal

    SeismicIntegrity ofLevel 2Structures

    Backlog andLack of fundingfor level 2PWOs

    Continual long termdegradation with norepairs on correctiveactions

    Meeting@ 1000

    Surveillance ofStorm Action Plandevelopment

    DQS

    1A ECCS onlinemaintenance

    ORLMcontributor

    Critical MaintenanceManagement couldresult in exceedingLCO and a unitshutdown

    Preps & Executionof CMM (dependentof HurricaneFrances)

    DQS CNO

    Fire Sealsdo not matchdesign

    A fire couldspread andaffect systemsneeded forsafe (App R)shutdown

    Security Firewatches werefalsifying logs

    Fire seals do not meet10 CFR App R andlicensing basis

    10/31 Inspect Fire Seals -LER inspectioncommitment for QCfrom QA Finding

    DQS

    Hurricaneapproaching- SevereWeatherPreps

    EmergencyPreparedness maintainingthe ERO intact

    Low number ofqualified peoplein somepositions

    Hurricane FrancesHurricane Jeanne

    9/19/21

    Ensure storm prepsare adequatelyimplemented

    DQS

  • 8/12/2019 Risk-Based Oversight

    16/17

    Fall 2005Nuclear Oversight Conference16

    Risk -B as ed Overs ig h tResults:

    Area Issues Identified

    Boric Acid Corrosion

    Controls

    Significant weakness in process

    for addressing active leaksConfigurationManagement

    - Breakdowns in control of mods- Lack of control of EQ panels

    ReactivityManagement

    Lack of sensitivity to secondarysystems affecting reactivity

    Equipment Reliability Longstanding equipmentreliability issues linked toweaknesses in corporate long-range planning

  • 8/12/2019 Risk-Based Oversight

    17/17

    Fall 2005Nuclear Oversight Conference

    Questions orComments?