Rinconada Water Treatment PlantReliability Improvement Project
Saratoga City CouncilOctober 7, 2015
The purpose of this presentation is to inform you about the Rinconada Reliability Project• Provide Project Background• Describe the Phases of the Project• Explain how you can stay informed
Purpose
• Original Rinconada WTP finished in 1968• Sole District Water supply to West Valley
Service Area• Current Project Planning completed June 2012 Design completed January 2015 Construction started July 2015 Construction completion July 2020?
Project Background
• Replace facilities and components that are near the “end of their useful life”• Meet increasingly stringent water quality
standards• Comply with current seismic codes• Improve plant safety
Project is needed to
• Increase Water Production Capacity from• 80 MGD to 100 MGD• Provide new facilities• Raw Water Ozonation• Flocculation and Plate Settler
Clarification• Dual Media Filtration
Improvements
Jan 2018
July 2015
July 2020
Residuals
July 2017
July 2018
July 2019
July 2016
Jan 2016
Jan 2017
Jan 2019
Jan 2020
Ops Bldg Seismic
Quito Bridge
Rinconada Reliability Improvement Project Construction PhasesPhase
1 Phase 2 Phase 3 Phase 4 Phase 5
Coordinating Schedule with Other Activities
Stay Informed:• Visit the District’s website and blog at
www.RinconadaReliabilityProject.com • Contact District’s Public Affairs Representative
Tony Mercado Telephone number: 408-426-1039 E-mail address: [email protected]