rigging requirements part l “cranes” and part f-1 “not cranes” construction safety standard...

27
Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane Safety Supervisor

Upload: deirdre-howard

Post on 24-Dec-2015

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Rigging RequirementsPart L “Cranes” and Part F-1

“NOT CRANES”Construction Safety Standard

WAC 296-155

Brad SolheimDepartment of Labor & IndustriesCrane Safety Supervisor

Page 2: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Rigging for Cranes & Rigging other than Cranes 296-155 Parts L “Cranes” and F-1

–Scope and Application–Rigger Qualifications–Rigging Requirements–Choosing the Right Part–296-155-53401 Duties Assigned

personnel

Page 3: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Scope WAC 296-155 PART L Cranes, Rigging, and Personnel

Lifting This part applies to power-operated cranes and

derricks used in construction that can hoist, lower and horizontally move a suspended load…….

Equipment includes, Articulating boom cranes; crawler cranes; mobile cranes, rough-terrain, all-terrain, commercial truck-mounted, boom truck cranes; tower cranes; and other variations.

Page 4: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Part L “CRANES”

Rigging Requirements

Rigger Qualifications

Page 5: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part L) “CRANES”

A qualified rigger is required whenever employees in the fall zone and are hooking, unhooking, or guiding a load

During crane assembly and disassembly hoisting activities

This activity requires at least one qualified rigger

Page 6: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part L) “CRANES”

The rigger must meet the qualification requirements of 296-155-53306

When hoisting with a Crane or Derrick, the Qualified Rigger Requirements of Part L apply and must be followed

Page 7: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part L) “CRANES”

Understands sling and rigging hardware application and limitations.

Sling selection and application.Rigging gear removal criteria.Load weight estimation, center of gravity, and basic hand signals, as applicable.

Page 8: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Riggers (cont’d) “CRANES” Qualification Requirements:

– Know and understand the requirements of applicable ASME standards: B30.7-2006 Base-Mounted Drum Hoists, B30.9-2010 Slings, B30.10-2009 Hooks, B30.16-2007 Overhead Hoists (Underhung), B30.20 2010 Below the Hook Lifting Devices, B30.21 2005 Manually operated Hoists, B30.26 2004 Rigging Hardware.

8

Page 9: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part L) “CRANES”

Qualification Documents:– Written and Practical test – Documentation from qualified

evaluator must be on site• A Third Party Qualified Evaluator

• An Employer Qualified Evaluator

– Employer's qualification is not portable

– Documentation effective February 1, 2013

Page 10: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part L) “CRANES”

Assessment by a Qualified Evaluator• Qualified Evaluator is a person who has

demonstrated that they are competent in accurately assessing whether individuals meet the rigger qualification requirements of Part L

• Qualified Evaluator (Third Party) means an independent entity

• Qualified Evaluator (not a third party) is a person employed by the signal person’s or the rigger’s employer

Page 11: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part L) “CRANES”

Qualification

Options

Documentation

Required Portable

Expiration

Date

3rd Party Qualified Evaluator

Yes Yes5 Yrs

maximum

Employer Qualified Evaluator

Yes No

5 Yrs

maximum

11

Page 12: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Site Supervisor’s duties (a-l). “CRANES”– ( c) ensuring that a qualified person is designated

as the lift director.– ( i) Allowing crane operation near electric power

lines only when requirements of WAC 296-155-53408 have been met.

– (k) Ensuring that work performed by the rigging crew is supervised by a qualified rigger. See WAC 296-155-53406

12

Page 13: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

LIFT DIRECTOR DUTIES (a-o) “CRANES” (g) Assigning qualified signal person(s) and

conveying that information to the crane operator. (i) Allowing crane operation near electric power

lines only when the requirements of WAC 296-155-53408 and any additional requirements determined by the site supervisor have been met.

13

Page 14: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Lift Director duties continued:– (l) Informing the crane operator of the weight of

loads to be lifted, as well as the lifting, moving, and placing locations for these loads.

– (m) Obtaining the crane operator’s verification that this weight does not exceed the crane’s rated capacity;

– (n) Ensuring that the load is properly rigged and balanced before it is lifted more than a few inches.

14

Page 15: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Part F-1 “NOT CRANE”

Rigging Requirements

Rigger Qualifications

Page 16: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Scope “NOT CRANES”

WAC 296-155 Part F-1 Rigging Requirements for Material Handling

This part applies to material/load handling activities when using slings, rigging hardware, below-the hook-lifting devices when performing construction activities. ASME B30.9-2010 Slings, B30.10 2009 Hooks, B30.20 2010 Below the hook devices, B30.26 2010 Hardware.

Page 17: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part F-1) “NOT CRANES”

Part F-1 All rigging activities must be conducted: By a qualified rigger or Under the direction of a qualified rigger

Riggers must be a qualified person who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, successfully demonstrated the ability to solve/resolve problems relating to the subject matter, the work, or the project.

Page 18: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part F-1) “NOT CRANES”

Qualification Requirements:• Know and understand:

o Requirements for slings, rigging hardware, and below the hook lifting devices as applicable

o Rigging limitations, associated hazards, rigging practices, and inspection requirements

Page 19: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part F-1) “NOT CRANES”

Qualification Requirements: Know and understand rigging related

conditions, such as load weight estimation, center of gravity, effect of angles on rigging components and basic hand signals, as applicable.

Sling Hitch application Rigging gear removal criteria

Page 20: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Qualified Rigger (Part F-1) “NOT CRANES”

Written and Practical examinations are not required

Page 21: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Part L “CRANES” Part F-1 “Not Cranes”Rigging with Cranes Material Handling w/o crane

Qualified Rigger required when workers are in the fall zone

All rigging/material handling activities require a Qualified Rigger or supervision by a Qualified Rigger

Written and Practical tests documented & on site

Documentation not required

Third Party or Employer Qualified Evaluator

Not addressed

Page 22: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Rigging Requirements, Parts L & F-1 A Qualified Person must inspect the rigging equipment

before each day or shift.

A Qualified Person must ensure the equipment’s use and application is safe.

A Qualified Person must ensure that defective equipment is removed from service that would create a hazard if used or meets any of the removal criteria.

Page 23: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Rigging Inspections, Parts L & F-1

** DailyInspections

** PeriodicInspections

Chain Slings Visual * Documentation

Wire Rope Visual * Documentation

Synthetic Web & Round

Visual * Documentation

** Qualified Person * Written record of the most recent Periodic inspection

Page 24: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Forklifts and Construction Powered Industrial Truck (forklift) configured to hoist

and lower (by means of a winch or hook) and can horizontally move a suspended load, some elements of Part L must be followed, including:

• Rigger Qualifications• Power line clearance distances

Not included • Forklift (crane) certification• Operator Certification

Page 25: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

A telescopic boom Powered Industrial Trucks configured with a winch or hook DOES fall under the scope of Part L.

Manufacturer’s written approval is required before using attachments

Page 26: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Forklifts and Construction A vertical mast Powered

Industrial Truck when configured with a hook would not fall under the scope of Part L.

Rigging (Part F-1) Operation (Chpt 863-

20010) Manufacturer’s written

approval is required before using attachments

Page 27: Rigging Requirements Part L “Cranes” and Part F-1 “NOT CRANES” Construction Safety Standard WAC 296-155 Brad Solheim Department of Labor & Industries Crane

Questions?

Brad [email protected]