rigging and lifting procedure

Upload: ghazi-kallel

Post on 28-Feb-2018

417 views

Category:

Documents


4 download

TRANSCRIPT

  • 7/25/2019 Rigging and Lifting Procedure

    1/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 1/16

    RIGGING AND LIFTING PROCEDURE

    1. PURPOSE

    This procedure defines the standard work process for preplanning and executing

    work operations related to construction rigging and lifting activities.

    2. SCOPE

    This procedure applies at LPG Refrigerated Storage Project. It encompasses all

    rigging and lifting work operations performed ! project personnel including

    sucontractor and"or third part! emplo!ees.

    #.$. This procedure also provides the minimum standards for rigging and lifting

    work activities performed ! sucontractors on all P%&'()& &onsortiumprojects.

    #.#. *n! deviation from this procedure shall e documented and sumitted in

    advance to the P%&'()& &onsortium+ who will otain approval from the

    appropriate authorities.

    3. DEFINITIOSNS

    3.1 LIFTING

    The process of lifting or positioning e,uipment+ components+ or materials with

    a machine.

    3.2 LIFTING DEVICE

    *n! machine or device used to lift a load from its supporting surface. Such

    devices include+ ut are not limited to the following- crane+ hoist+ hoisting

    s!stem+ jack+ jacking s!stem+ gin pole+ derrick+ monorail hoist+ gantr! crane+

    levers+ pulle! s!stem+ air ag jack+ strand lift s!stem+ etc.

    3.3 RIGGING

    The process of relocating or moving heav! e,uipment+ components+ or

    materials which re,uire a crane to load / unload0 a considerale distance

    using a haul trailer+ rollers+ or similar devices.3.4 PAYLOAD WEIGHT

    The weight of the item to e lifted. Pa!load weight includes the actual item

    weight+ plus the weight of attachments+ saddles+ temporar! supports+ etc.

    Pa!load weight does not include rigging weight.

    3.5 TON

    The word 1ton2+ as used herein+ refers to a mass of $333kg. $333kg e,uals $

    Tone0

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    2/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 2/16

    RIGGING AND LIFTING PROCEDURE

    3.6 LIGHT LIFT

    *n! lift where the pa!load weight is $3 tons or less.

    3.7 MEDIUM LIFT

    *n! lift where the pa!load weight is over $3 tons ut less than 43 tons.

    3.8 HEAVY LIFT

    *n! lift where the pa!load weight is 43 tons or greater.

    3.9 WHAT IS RIGGING

    Rigging is work involving the use of mechanical load shifting e,uipment and

    associated gear to move+ place or secure a load including plant+ e,uipment or

    memers of a uilding or structure and to ensure the stailit! of those

    memers and the setting 5 up and dismantling of crane and hoists.

    There are three competencies levels involved in rigging-

    6asic Rigger

    Intermediate Rigger

    *dvanced Rigger

    The following outlines the competenc! 5 ased skills needed to carr! out

    asic+ rigging safel!.

    3.10 BASIC RIGGING

    Those ,ualified in asic rigging must know how to carr! out work associated

    with-

    7ovement of plant and e,uipment.

    Steel erection.

    6asic scaffolding particular hoists not self climing or with jis.

    Placement of pre'cast concrete.

    6asic scaffolding safet! nets and static lines.

    7ast climers.Perimeter safet! screens and shutters.

    &antilevered crane'loading platforms.

    3.11 INTERMEDIATE RIGGING

    Those ,ualified in intermediate rigging must know how to carr! out work

    associated with all asic rigging competencies and-

    8se of load e,uali9ing gear.

    The rigging of cranes+ conve!ors+ dredges and excavators.

    *ll hoists.

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    3/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 3/16

    RIGGING AND LIFTING PROCEDURE

    Tilt slas.

    (emolition.

    (ual lifts.

    3.12 ADVANCED RIGGING

    Those ,ualified in advanced rigging must know how to carr! out work

    associated with all asic and intermediate rigging competencies and-

    The rigging of gin poles and shear legs fl!ing foxes and calewa!s.

    Gu!ed derricks and structures.

    Suspended scaffolds and faricated hung scaffolds.

    3.13 QUALIFIED RIGGER/S

    Rigger is a person that holds a certificate identif!ing that the individual has

    een trained and passed a rigging ,ualification. Plus the person is competent

    and ac,uired through a comination of ,ualifications+ training or experience

    the knowledge and skills to perform the task re,uired.

    3.14 RIGGING SUPERVISOR

    The Rigging Supervisor is an individual with demonstrated technical skills

    who is assigned responsiilit! for planning and supervising heav! haul+ heav!

    lift+ and"or general rigging work operations on a project.

    The Rigging Supervisor is responsile for developing safe work methods and

    plans for rigging operations and for supervising the performance of the work.

    The Rigging )ngineer assists the Rigging Supervisor ! providing the design

    support needed for the rigging plan development.

    The Rigging Supervisor shall e nominated ! Sucontractor and reviewed !

    P%&'()& &onsortium.

    3.15 RIGGING ENGINEER

    * Rigging )ngineer is an individual with demonstrated technical skills

    assigned responsiilit! for anal!9ing rigging operations and designing the

    temporar! structural s!stems re,uired to support heav! lift rigging or heav!haul work operations.

    * Rigging )ngineer is responsile for preparing all necessar! rigging plans

    and calculations under the direction of Rigging Supervisor as re,uired ! this

    procedure. The Rigging )ngineer also monitors general project rigging

    operations to ensure that all lifts are performed in accordance with normal safe

    rigging operations.

    The Rigging )ngineer shall e nominated ! Sucontractor and reviewed !

    P%&'()& &onsortium.

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    4/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 4/16

    RIGGING AND LIFTING PROCEDURE

    4. INSTRUCTIONS

    4.1 LIFT CATEGORIES

    Light Lifts

    $3 tons and less0

    Planned and )xecuted using good

    rigging practices.

    Rigging operation is under supervisor

    direction+ using ,ualified crane operators

    and ,ualified riggers.

    Medium Lifts

    more than $3

    less than 43 ton0

    Rigging plans are re,uired

    P%&'()& &onsortium is re,uired to

    review.

    Heavy haul,

    Citi!al " Heavy

    Lifts

    43 tons or more+ or

    per section :0.

    Rigging plans are re,uired

    P%&'()& &onsortium is re,uired to

    review.

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    5/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 5/16

    RIGGING AND LIFTING PROCEDURE

    ;.$.$Light lifts do not require a formal rigging plan or calculations. However,

    light lifts shall be performed under the direction of a superintendent, aqualified crane operator, and a qualified rigger using safe rigging work

    practices.

    ;.$.# Sub-conctractor shall prepare a detailed rigging plan for each medium

    lift. These plans shall be reviewed and approved by !"-#$"

    "onsortium.

    ;.$.:% written rigging plan and supporting calculations shall be prepared for

    heavy haul operations, heavy lifts, and critical lifts. This plan should be

    prepared by the ro&ect 'igging $ngineer. %ll heavy lift, critical lift, and

    heavy haul plans must be reviewed by !"-#$" "onsortium. The plansshould be reviewed by !"-#$" "onsortium (echanical (anager,

    )ield Superintendent, and HS$ representative.

    ;.$.;%ny lifts occurring at warehousing facilities, lay down areas, mechanics

    shops, or at off-site locations *&etty rail sidings, ports, etc+ are to be

    identified by the supervisor or manager of that areafacility, categoried,

    then planned and approved according to category.

    ;.$.4Lifts occurring during the assembly of large cranes must be categoried,

    planned, and approved according to category.

    4.2 RIGGING APPROACH

    ;.#.$ "ategoriation of lifts shall be an ongoing activity for the duration of the

    pro&ect. "ategoriation is required so that the lift can be planned in

    accordance to the specific requirements of its category.

    ;.#.# The 'igging lan should also indicate the travel route within the site and

    the orientation of site heavy lift equipment. The 'igging lan should be

    developed early and should be given to the pro&ect design engineering

    group to ensure that they are aware of the erection sequence and the

    access that will be required.

    ;.#.:n some cases, it may be necessary to coordinate with equipment

    suppliers prior to fabrication to ensure that the pro&ect equipment

    installation approach is acceptable to the manufacturer and that

    manufacturer/s lifting procedures are consistent with pro&ect needs.

    ;.#.;%ll calculations, drawings, sketches, and related documents developed to

    support heavy haul and heavy lift rigging operations shall be controlled.

    4.3 PLANNING RIGGING AND LIFTING ACTIVITIES

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    6/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 6/16

    RIGGING AND LIFTING PROCEDURE

    ;.:.$ "onstruction rigging and lifting operations are classified into the

    general categories of light, medium, heavy, and critical lifts. $veryrigging and lifting operation, regardless of category or sie, shall be

    planned to ensure a safe lift. #ue to the comple0ity and added risks

    associated with heavy or critical lifts, their planning requirements are

    more comprehensive.

    ;.:.# The 'igging $ngineer, 'igging Supervisor shall review the requirements

    of each medium, critical, and heavy lift plan with the field engineers,

    superintendents, equipment operators, the rigging crew, signalman,

    truck drivers and other personnel associated with performing the lift

    prior to the start of the work. These lifts shall be monitored by the'igging $ngineer and superintendents to ensure strict adherence to the

    rigging work sequence plan.

    ;.:.:n developing lift plans the following considerations should be

    addressed1

    a0 Soil conditions and site terrain to verif! access for lifting e,uipment

    and to ensure stailit! along the haul path and at location of the lift.

    0 8nderground utilities along the haul path or at the lift location to

    avoid damage to existing utilities and to ensure ade,uate ground

    support.c0 The location of overhead power lines to ensure re,uired clearances are

    maintained during oth heav! haul and lifting operations.

    d0 Lift e,uipment and rigging hardware re,uirements including the

    method of removal following execution of the lift. Including

    verification of ,ualit! of lifting e,uipment to e used and all

    e,uipment must e certified and certificates availale for verification.

    e0 *ccess of haul and lift e,uipment into and out of the lift area. In some

    cases+ asseml! and disasseml! of cranes or other e,uipment must e

    included in the planning process.

    f0

  • 7/25/2019 Rigging and Lifting Procedure

    7/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 7/16

    RIGGING AND LIFTING PROCEDURE

    4.4 RIGGING PLAN PREPARATION

    ;.;.$ !endor drawings and associated data shall be reviewed by the 'igging

    $ngineer for information applicable to the preparation of equipment liftplans. %pplicable information includes equipment weight, location of

    center of gravity, recommended or specified lifting points, and special

    handling requirements. This information should be verified and double-

    checked using sources such as fabricator drawings, checked

    calculations, similar units previously handled, and actual shipping

    weights. 2henever possible, the actual scale weight information should

    be obtained before units arrive at the site.

    ;.;.# The rigging plan for each haul or lift shall include the followingelements as a minimum1

    a0 * list of the crane or hoisting e,uipment to e used in the work

    operation.

    0 * sketch showing the position and travel path of haul e,uipment+

    hoisting e,uipment+ lift crane+ tailing crane+ initial location of the item

    to e lifted+ and the final 1set2 position of the lifted item.

    c0 * la!out of the work area+ including the locations of all ostacles and

    potential interferences.

    d0 =aul and lift path minimum clearances+ turning radius+ and clearancere,uirements from existing facilities+ utilities+ and overhead power

    lines.

    e0 (efinition of the item to e lifted including verified weight and

    authori9ed attachment or lift points.

    f0 ),uipment manufacturer drawings showing component weight+

    shipping skid weight+ designated rigging attachment points+ and center

    of gravit! should e attached to the rigging plan.

    >ote- )lements h. / i. that follow are especiall! important for an!

    =eav! =aul activities. The successful completion of a heav! haulactivit! depends greatl! upon the preparation of the haul route itself.

    g0 (efinition of special soil preparation and crane mat re,uirements.

    h0 * sketch showing the locations of underground utilities that could

    affect the haul route and"or rigging work operation or that re,uire

    special clearances or criing to perform the work.

    i0 Rigging e,uipment to e used for the rigging operation+ includingslings+ spreader eams+ shackles+ hooks+ and other components in the

    load chain. Shall e checked and verified for ,ualit! all lifting

    e,uipment must e certified and certificates availale for verification.

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    8/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 8/16

    RIGGING AND LIFTING PROCEDURE

    j0 &alculations used to determine the forces applied to each rigging

    component must e provided for all heav! lifts. Standard riggingreference charts ma! e used to determine si9e and t!pe of the

    components re,uired.

    k0 Load capacit! charts and notes for cranes or other e,uipment used to

    perform the lift. These shall e posted in the crane and referenced in

    the rigging plan. It is important that the actual configuration of the

    crane+ including line parting and si9e+ oom and ji length+

    counterweight si9e+ and load lock si9e are factored into the

    parameters used to determine lifting capacit!.

    l0 * description of the communication method to e used ! e,uipmentoperators and rigging crews during completion of the lift.

    m0 * list of the names and ,ualification of the riggers that will e

    carr!ing out the rigging activit!.

    n0 Special considerations+ such as the effects of wind on the ailit! of

    crews to safel! complete the lift.

    o) *n! special precautions that the work crew must e aware of prior to

    making the lift for example+ removal of temporar! shipping skids

    prior to lifting0.

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    9/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 9/16

    RIGGING AND LIFTING PROCEDURE

    4.5 DETAILED RIGGING CALCULATIONS AND DRAWINGS

    The lift plan shall convey the work operation plan to the field personnel who will

    e0ecute the lift. The information provided shall ensure that the crane is set upin the correct configuration and at the proper location. The rigging plan shall

    also include all pertinent crane and lift data that the planner used in

    developing the rigging plan. Lift and crane data should be compiled in

    summary form. 'eference %ttachments % and 3.

    4.6 CRANE SETUPS AND RIGGING APPURTENANCES

    ;.?.$%ll cranes shall be set up for lifting on firm, level ground. %ny deviations

    shall be reviewed by !"-#$" "onsortium.;.?.#%ll lift beams and spreader bars used in the heavy rigging category must

    be designed and fabricated in accordance with &urisdictional rules,

    regulations, and applicable local code.

    ;.?.:Lifting lugs and attachment points provided and installed by the

    equipment supplier shall be inspected for visual defects or discrepancies

    prior to lifting the equipment from the delivery vehicle.

    ;.?.;Lifted components shall be inspected prior to lifting from delivery

    vehicles to ensure that the lifting configuration matches that included in

    the lift plan. )or e0ample, if the lift plan is based on lifting the emptyweight of a tank with shipping skids removed, the tank shall be inspected

    prior to lifting to ensure that the tank is actually empty and that the

    shipping skids are removed.

    4.7 PRE-LIFT CHECKS

    ;.@.$)or all lifts, the following pre-lift safety checks shall be performed1

    a0 The Aperator has completed the dail! crane check and all e,uipment

    and s!stems are in a satisfactor! condition to perform the lift.

    0 The operator has completed his dail! log ook and signed of

    inspection and items checkedc0 Rigging crew and e,uipment operatorss0 shall verif! rigging and

    lifting e,uipment is set up per the rigging plan.

    d0 Rigging )ngineer"Rigging Supervisor shall inspect and verif!

    e,uipment supplier specified lift points.

    e0 Rigging engineer"rigging supervisor shall keep a rigging register

    identif!ing rigging e,uipment+ inspection dates and name of

    competent person that completed the inspections.

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    10/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 10/16

    RIGGING AND LIFTING PROCEDURE

    f0 Rigging )ngineer"Rigging Supervisor shall inspect e,uipment for

    factors that ma! add to the total weight of the lift+ such as ice orexcess moisture.

    g0 Rigging Supervisor shall inspect rigging and lifting e,uipment.

    h0 Bor medium+ critical+ and heav! lifts+ a pre'lift riefing shall e

    conducted ! the Rigging Supervisor+ rigging crew+ and e,uipment

    operators. &lear communications etween the Aperator and the

    Rigging crew shall e emphasi9ed .

    i0 Bor light lifts+ a pre'lift discussion shall take place etween the rigging

    crew and e,uipment operators0 prior to making the lift. &lear

    communications etween the Aperator and the Rigging crew shall eemphasi9ed.

    j0 The Rigging Supervisor shall evaluate weather conditions to ensure

    the lift can e made safel!.

    k0 The rigging crew and e,uipment operators0 shall inspect attachmentsand rigging e,uipment including lugs+ slings+ shackles+ and spreader

    eams.

    l0 The rigging crew shall ensure that tag lines are attached to the load.

    m0 The rigging crew shall ensure that temporar! arricades are placed

    around the work area and that adjacent work crews are notified of therigging work operation.

    ;.@.##uring-Lift "hecks1

    a0 *fter all pre'lift inspections and checks are completed+ the lift ma!

    proceed.

    0 (uring the execution of the lift-

    Rigging Supervisor shall ensure that critical aspects of the lift are

    monitored.

    The rigging crew and e,uipment operators0 shall pa! close

    attention to critical weights+ ph!sical clearances particularl! near

    overhead power lines0+ and oserve for unforeseen events.

    ;.@.:ost lift1

    a0 Ance the lift has een safel! completed and the load has een secured

    in its final position-

    The rigging crew shall remove all tag lines+ rigging+ and temporar!

    arriers

    ),uipment operators0 shall remove all rigging and lifting

    e,uipment from the area if no longer needed0

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    11/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 11/16

    RIGGING AND LIFTING PROCEDURE

    The responsile superintendent shall restore the work area for

    future construction work.

    0 The Rigging Supervisor shall ensure that rigging and lifting

    e,uipment that is no longer re,uired for the project is safel!

    disassemled+ loaded onto transport e,uipment+ and removed from theconstruction site.

    . ATTACHMENTS

    4.$ %ttachment % 4 Lift #ata Sheet 4 Single "rane ick and Set

    4.# %ttachment 3 4 Lift #ata Sheet 4 Two "rane ick and Set

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    12/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 12/16

    RIGGING AND LIFTING PROCEDURE

    #$$#CHM%&$ #

    '(C)*%C

    C+&+-$/ML$ *#$# H%%$ &L% C-#&% 'C #&* %$

    -%C+-* &/M%- *#$%

    '-+%C$ C+&$-#C$+-

    L$%* '%C% *%C-'$+&

    Reference (ocument >umer Revision

    >umer

    Remarks

    C-#&% C+&/-#$+&

    &rane T!pe 6lock Si9e

    6oom Length Line Parts

    6oom T!pe Ci T!pe

    Tip T!pe Ci Length

    &ounterweights Ci Affset

    C-#&% %* %H$ '%C% %H$

    7ain 6lock Piece

  • 7/25/2019 Rigging and Lifting Procedure

    13/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 13/16

    RIGGING AND LIFTING PROCEDURE

    '(C)*%CC+&+-$/M

    L$ *#$# H%%$ &L% C-#&% 'C #&* %$

    -%C+-* &/M%- *#$%

    'C C#'#C$; %$ C#'#C$;

    *ctual Pick Radius *ctual Set Radius

    &hart Radius &hart Radius

    &hart &apacit! &hart &apacit!

    Percent &apacit! D Percent &apacit!- D

    CL%#-#&C%

    7inimum &learance from 6oom to Astruction-

    7inimum &learance from 6oom to Lifted Piece or Spreader-

    -& %=/'M%&$

    Rigging e,uipment inspected and deemed safe and correct for lifting activities to e

    completed

    Ees F >o F f : lift is t >e sus?e:ded.

    C+MM%&$

    '-%'#-%* ; *#$%

    -%(%%* ; *#$%

    PVC-DEC CONSORTIUM

  • 7/25/2019 Rigging and Lifting Procedure

    14/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 14/16

    RIGGING AND LIFTING PROCEDURE

    #$$#CHM%&$

    '(C)*%C

    C+&+-$/ML$ *#$# H%%$ $+ C-#&% 'C #&* %$

    -%C+-* &/M%- *#$%

    '-+%C$ C+&$-#C$+-

    L$%* '%C% *%C-'$+&

    Reference (ocument >umer Revision

    >umer

    Remarks

    C-#&% 1 C+&/-#$+& C-#&% 2 C+&/-#$+&&rane T!pe- &rane T!pe-

    6oom Length- 6oom Length-

    6oom T!pe- 6oom T!pe-

    Tip T!pe- Tip T!pe-

    &ounterweights- &ounterweights-

    6lock Si9e- 6lock Si9e-

    Line Parts- Line Parts-

    Ci T!pe- Ci T!pe-Ci Length- Ci Length-

    Ci Affset- Ci Affset-

    C-#&% 1 %* %H$ C-#&% 2 %* %H$

    7ain 6lock 7ain 6lock

  • 7/25/2019 Rigging and Lifting Procedure

    15/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 15/16

    RIGGING AND LIFTING PROCEDURE

    '(C)*%CC+&+-$/M

    L$ *#$# H%%$ $+ C-#&% 'C #&* %$

    -%C+-* &/M%- *#$%

    '-+%C$ C+&$-#C$+-

    *uxiliar! 6oom Sheaves

    deduct0

    *uxiliar! 6oom Sheaves

    deduct0

    Ci deduct0 Ci deduct0

    Ca:e 1 -iggi:g eight Ca:e 2 -iggi:g eight

    Spreader Spreader

    Slings Slings

    Shackles Shackles

    Ather Ather

    $tal Ca:e 1 i

  • 7/25/2019 Rigging and Lifting Procedure

    16/16

    LPG REFRIGERATED STORAGE PROJECT DOCU. NO.:

    094315-HS-PRO-013

    REV. NO. : A

    PAGE : 16/16

    RIGGING AND LIFTING PROCEDURE

    #$$#CHM%&$

    '(C)*%C

    C+&+-$/ML$ *#$# H%%$ $+ C-#&% 'C #&* %$

    -%C+-* &/M%- *#$%

    '-+%C$ C+&$-#C$+-

    C-#&% 1 L$ %H$ /MM#-; C-#&% 2 L$ %H$

    Total Bixed