rf systems commissioning o. brunner ab/rf on behalf of the rf group (ltc – march ’08) many...
TRANSCRIPT
RF Systems Commissioning
O. Brunner AB/RF
on behalf of the RF group
(LTC – March ’08)
Many thanks to L. Arnaudon, Ph. Baudrenghien, W. Hofle, D. Valuch, J. Molendijk, A. Butterworth, F. Dubouchet, Ed. Ciapala, U. Wehrle, T. Bohl, P. Maesen, V. Rossi, M.E. Angoletta, E. Montesinos for their help
1obrunner, LTC March'08
Summary
400 MHz superconducting cavities (ACS)
RF dampers (ADT)
Pick ups & RF instrumentation
RF synchro & beam control
2obrunner, LTC March'08
ACS – LHC accelerating system
100kV- 40A power converter
HV switch
mod 1 mod 2 mod 3 mod 4 thyratron 4uF capacitor
kly
circ
control systems:-interlocks-specialists applications-supervision
made up of: 4 4MW power converters 16 RF power stations (HV equipment, 330kW klystrons, circulators, RF loads, WG) 16 superconducting cavities (4 cryostats)
kly
circ
kly
circ
kly
circ
cavities
3obrunner, LTC March'08
Low level RF system
warm commissioning (WG short-circuited)1. High voltage commissioning: switch on tests (AB/PO) control interlocks operation: 10kV services cooling (air, water) control interlocks DCCTklystron (focus,...) crowbar (spark gap)
Still to be done (in March) test with all 4 power converters full power in parallel
test&calibrate TS/EL equipment optimize HV ripple (600Hz) test spare power converter test spare HV cables (surface to tunnel)
4obrunner, LTC March'08
operation: 58kV klystrons current control crowbar (ext. trigger @ 62kV) klystron heaters set up DC power calibrations thermal power calibration RF switch ON RF calibrations
2. RF commissioning: RF interlocksRF calibrationklystron protectionRF pre-amplifierCirculator temperature control unit300 kW RF power testsklystron saturation curveKlystron freq responsegroup delay meas.
Status: done on 15/16 RF power stations To be finished in March
cold commissioning – status of sector 4-5 Access & RAMSES systems tested & validated
2 modules (sect 4-5) successfully cooled down in November
Cryogenics system Excellent cryogenic regulations (level&pressure) in the modules Several cryo control system communication problems ( He lost through modules safety valves) So far no direct impact of magnet quenches on RF cavities
Low RF power tests of 8 cavities done Mechanical Tuner range of 8 cavities measured&Q measurements performed
Parallel conditioning of eight cavities up to: 1MV/cavity with main coupler position1 (QL = 20’000) 2MV/cavity with main coupler position 2 (QL = 60’000)
Radiation measurements: Peak value: few mSv/h close to the cavities (8 cavities running in //)
Might get higher radiation above 2MV No radiation measured nor in UX45 nor outside the RF zone
five weeks of “conditioning”
(~1 ½ wk per cavity)
Main issues: frequent stops due to accesses in RF zone, UX45 (w/o film badges..)
logging system (Timber) not fully operational
5obrunner, LTC March'08
Set up the Klystron drive limiter to prevent driving the klystron over the saturation limit during loop transients
Set up the Tuner Loop to keep the cavity on resonance
Set up the Klystron Polar Loop to compensate the variation of klystron power and phase shift (by e.g. caused by high voltage supply
ripple 600Hz).
Set up the RF feedback to keep the accelerating voltage at the desired value in the presence of transient beam loading later: 1 turn feedback
condition: cavities & main couplers must be fully conditioned successfully done on 3 cavities after training: 2-3 days of work/cavity
cold commissioning – low level RF set up
more results will be presented by Ph. Baudrenghien
Vcav Feedback Closed. 25 kHz span, 30 Hz BW
Phase Noise Vcav-Ref RF fdbk open ~4 dg pkpk, fdbk closed ~0.3 dg pkpk @1MV CW
Phase Noise Vcav-Ref RF all loops closed ~0.1 dg pkpk @1MV CW
6obrunner, LTC March'08
Low Level RF hardware equipment - status
System Item HardwareReady - Installed
Firmware Drivers FESA App.SW
Expected ready forstartup
ACS Automatic conditioning system Yes
Cavity Controller RF Modulator/Klystron polar loop Yes
Cavity Controller Switch/protection module Yes
Cavity Controller RF feedback Yes
Cavity Controller Setpoint module Yes
Cavity Controller Clock generation Yes
Cavity Controller Clock distribution Yes
Cavity Controller Analogue demodulator Yes (Passive, no control)
Cavity Controller 1 turn feedback Yes
Cavity Controller Conditioning DDS Yes
Cavity Controller Tuner RF Front end Yes
Cavity Controller Tuner Control Yes
ACS High-level Logic & Interface to LSA Yes
Not yet startedIn progressCompleted
7obrunner, LTC March'08
ACS system commissioning - status
cavities cold & ready for RF ~ mid-May
expected commissioning time: ~ 6-8 weeks
cavities cold & ready for RF ~ mid-June
expected commissioning time: ~ 4-5 weeks
8obrunner, LTC March'08
Sector 4-5 Sector 3-4
ADT (dampers) system
Damper essential to avoid increase of transverse emittance
pick-up 1
Kickers
Real time digital signal processing
pick-up 2
• feedback: curing transverse coupled bunch instabilities (becomes important with increasing intensity)
• excitation: of transverse oscillations for beam measurements & other applications (e.g. tune meas)
• damping: of transverse injection oscillations
Amplification
9obrunner, LTC March'08
ADT racks(driver amplifiers,PLC controls, fast interlocks)
ADT (4 modules)left of IP4+ space for 2 more modules (upgrade)
ADT (4 modules)right of IP4 + space for 2 more modules (upgrade)
Beam 1
Beam 2
SR4 (surface):Signal Processing electronics (VME crates)HV Power ConvertersPLC controls
8 Dedicated Pick-ups BPMC @ Q7L, Q7R, Q9L, Q9R
ADT system - layout
10obrunner, LTC March'08
ADT (dampers) commissioning - status
end of power commissioning: March
System Item Hardware Firmware Drivers FESA App. SW Expected ready for startup
ADT Power PLC controls Yes
ADT Low level Transverse feedback Yes (on the critical path)
ADT Low level ADT radial position acquisition Yes (on the critical path)
ADT High-level logic & interface to LSA Yes
11obrunner, LTC March'08
RF Beam Observation Status
APWL Pick-Ups 6 pick-ups in LHC tunnel (4 for RF Group, 2 for BI Group) all installed pick-up combiners not yet installed (soon)
Instrumentation instruments for RF Beam Observation all installed digital acquisition cards for RF Beam Observation, UX45 all installed digital acquisition cards for RF Beam Observation, SR4 not yet installed modules for peak detector (VME) under construction software for Mountain Range, low frequency signals (OASIS) under test software for bunch profile acquisition and analysis not yet implemented
System Item Hardware Firmware Drivers FESA App.SW Expected ready for startup
Beam Obs Signal distribution switching Yes
Beam Obs Detected signals (100MS/s) Yes, minimum functionality
Beam Obs Injection MR (8GS/s) Yes, minimum functionality
Beam Obs Bunch length measurement (8GS/s) Yes, minimum functionality
12obrunner, LTC March'08
RF synchro & beam control
beam control loopsmodules
beam phase modules (rigid and precise, for final use)
vector sum
ACS cavitieswide band pick-up
(APW)beam
radial strip line pu(Q10)
bu
nch
am
plit
ud
e
bu
nch
ph
ase
volt
ag
e s
een
by e
ach
bu
nch
beam
ph
ase
avera
ged
voltage seen by bunch
ph
ase
pu
sig
nal
frequency program
f RF re
ference
radial loop(for initial commissioning when ramp is not very reproducible)
stable phase
radial position
fiber optic link toCCC, CMS, AB/BT...
bunch freq
Frev
to longitudinal damper
10MHz (GPS)tempo
13obrunner, LTC March'08
Status:
Distribution of fast clocks to the experiments (Frev, 40 MHz) :Installation of Fiber Optic Transmitter and Receiver modules underway. Prototype link tested OK (S. baron, PH dept)
Distribution of Frev and kicker pulses to BI and BT: installation of TX/RX underway
Installation of the RF Synchro modules in SR4 to generate Frev and kicker pulses: starting end March
Link with the SPS: commissioning end March- begin April
Aim: all commissioned by mid April
RF synchro & beam controlSystem Item Hardware Firmware Drivers FESA App. SW Expected ready for
startup
All VME crates Crate Management Unit Needed - critical
RF Synchro Trigger unit Yes
RF Synchro Injection pulse generator Yes
RF Synchro Dual wideband switch Yes
RF Synchro Dual wideband demux Yes
RF Synchro 400 MHz phase shifter Yes, minimum functionality
RF Synchro Optical Tx analog Yes
RF Synchro Optical Rx analog Yes
RF Synchro Optical Tx digital Yes
RF Synchro Optical Rx digital Yes
RF Synchro Synchro Loop (Phase Synchro) Yes
Beam control Frequency Program DDS Yes
Beam control VCXO Yes, minimum functionality
Beam control Beam phase measurement Yes, minimum functionality
Beam control Beam position measurement Yes, minimum functionality
Beam control Low level loops DSP Yes
Beam control LL Loops Interface Yes
Beam control Beam parameters DSP No (Postponed 2009)
Beam control Longitudinal feedback No (Postponed 2009)
14obrunner, LTC March'08
Conclusions 400 MHz superconducting cavities (ACS)
High RF power stations commissioning comes to an end 8 cavities & main couplers conditioned LL RF setting up successful so far
Objective: get all LL RF modules + related SW ready&tested for next cool down Should be ready for beam on time (if not suffering from too many accesses in RF zone)
RF dampers (ADT) Power commissioning almost finished Critical: LL RF modules + related SW
Pick ups & RF instrumentation Good shape
RF synchro & beam control Well advanced Some LL RF modules + SW on the critical path
15obrunner, LTC March'08