resource reconciliation automation project_final
TRANSCRIPT
-
8/3/2019 Resource Reconciliation Automation Project_Final
1/18
Copyright 2009 Accenture All Rights Reserved. Accenture, its logo, and High Performance Delivered are trademarks of Accenture.
Resource Reconciliation AutomationProject
-
8/3/2019 Resource Reconciliation Automation Project_Final
2/18
Copyright 2008 Accenture All Rights Reserved.
Contents
22
Roles and Responsibilities
Project Charter
Flow Chart (As Is)
Data collection
5 Why Analysis
Solutions Identification
Implementation Plan
Process Map (To Be)
Control Plan
Key learning's from this Project
Benefits
Sign off
-
8/3/2019 Resource Reconciliation Automation Project_Final
3/18
-
8/3/2019 Resource Reconciliation Automation Project_Final
4/18
Copyright 2008 Accenture All Rights Reserved. 4
Project Charter
Problem Definition:
Resource Reconciliation report is a highly manual report which involves extracting and pooling source data from severalfeeder reports into the Reconciliation template, performing reconciliation and highlighting action points. The entireactivity consumes approximately 3 hours per week if done manually and is prone to human error.
To reduce the amount of time spent in preparing the report by atleast 50% (i.e. to 1.5 hours from the existing 3 hours) bySept. 2011
Improvement Goal:
Current Baseline:
3 hours per week
Project Scope :
AstraZeneca PMO Team
Solution implemented can also be used for otherprojects wherever reconciliation is required
Define Measure Analyze Improve Control
Business Case:Resource Reconciliation is a weekly reconciliation report generated to ensure that only Active resources have access toAstraZeneca systems and resources. The report highlights inaccuracies in the management control resource list andverifies who has rolled on/off and needs adding/taking off the:
Project server (PWA) Distribution lists
SharePoint Organization charts WBC Codes
Each tab uses the resource list to check against access to the above mentioned.
-
8/3/2019 Resource Reconciliation Automation Project_Final
5/18
Copyright 2008 Accenture All Rights Reserved.
Process Map (As Is)
5
Extract Feeder Reports
Define Measure Analyze Improve Control
Prepare ReconciliationTemplate
Load Current WeeksData
Perform Reconciliation
IdentifyAction Points
Start
Stop
-
8/3/2019 Resource Reconciliation Automation Project_Final
6/18
Copyright 2008 Accenture All Rights Reserved.
Detailed Flow Chart (As Is) Contd.
6
Define Measure Analyze Improve Control Resourceconciliation As-Is
-
8/3/2019 Resource Reconciliation Automation Project_Final
7/18
Copyright 2008 Accenture All Rights Reserved.
Data collection
7
Define Measure Analyze Improve Control
S. No Measure Name Units
1. Time consumed in report
preparation
Hours:Minutes:Seconds
-
8/3/2019 Resource Reconciliation Automation Project_Final
8/18
5 Why Analysis
5-Why AnalysisToo much time consumed in
report generation
Highly manual drivenWhy ?
Why ?
Root Cause Identified
Define Measure Analyze Improve Control
Report involves pooling data from multipleresources into the template followed by
Reconciliation
Highly Manual intensive Report involves pooling datafrom multiple resources into the template followed by
Reconciliation per certain specific rules.
-
8/3/2019 Resource Reconciliation Automation Project_Final
9/18
Copyright 2008 Accenture All Rights Reserved.
Solutions Identification
9
SL No Issues Solution Identified Solution Implemented Remarks
Quality check of the report
by peer/supervisor
Introduction of QC
mechanisms into the manual
report
Complete Report automation
follow ed by QC by peer /
supervisor
3
Highly cumbersome as it
involves incorporating data
from several feeder reports
into the f inal template
Automatic uploading of data
from the feeder reports into
the final reconciliation
template
Automatic uploading of data
from the feeder reports into
the final reconciliation
template
Issue Resolved
through
automation
Improve ef ficiency through
practice over a period oftime.
Perform a step by step
study to ascertain the best
sequence of events in
report generation w hich
w ould produce the report in
minimum amount of time
Complete Report automation
follow ed by QC by peer /
supervisor
Issue Resolved
through
automation
Increased chance of errors
as the report is produced
manually
Complete Report automation
follow ed by QC by peer /
supervisor
Issue Resolved
through
automation
Highly time consuming -
approximately 3 hours per
w eek spent in report
generation.
Complete Report automation
follow ed by QC by peer /
supervisor
Issue Resolved
through
automation
1
2
4
Highly Manual process
Complete Report automation
follow ed by QC by peer /
supervisor
Complete Report automation
follow ed by QC by peer /
supervisor
Define Measure Analyze Improve Control
-
8/3/2019 Resource Reconciliation Automation Project_Final
10/18
Copyright 2008 Accenture All Rights Reserved.
Implementation Plan
1010
SL
NoIssues
Solution
IdentifiedDetailed Activity Intended Outcome Owner
Date of
Completion
Insert
ArtifactsRemarks
1 Highly Manual process
Automation
Achieved - Issue has
been resolved
Raminder
Singh
Chadha
Aug 29th, 2011 Resolved
2
Increased chance of
errors as the report is
produced manually
Automation
Achieved - Issue has
been resolved
Raminder
Singh
Chadha
Aug 29th, 2011 Resolved
3
Highly cumbersome as
it involves
incorporating data
from several feeder
reports into the final
template
Automation
Achieved - Issue has
been resolved
Raminder
Singh
Chadha
Aug 29th, 2011 Resolved
4
Highly time consuming -
approximately 3 hours
per week spent in
report generation.
Automation
Achieved - Issue has
been resolved
Raminder
Singh
Chadha
Aug 29th, 2011 Resolved
Complete
Report
automation
followed by QC
by peer /
supervisor
The Report involves extracting updated
information on currently active resources
in AstraZeneca from Project Server,
Sharepoint and Distribution Lists. These
are then pooled into the Main
Reconciliation spreadsheet and cross
checked with the last week's data onactive resources. If a new resource is
found, which is otherwise absent in last
week's list, these are searched in the New
Joiner Tracker and if found there, is
labelled as a New Joinee and added to
the respective systems (Project
Server/Sharepoint / Distribution Lists).
On the flip side, if a resource is found in
the last week's list, that is otherwise
absent on the current week's resource list,
it is searched in the Roll Off tracker for a
possible roll off. If this resource appearsin the Roll off Tracker, It is confirmed that
the resource has rolled off, its status and
roll off date is updated and removed from
the respective systems (Project Server /
Sharepoint / Distribution Lists). This
process continues till all the resources
have been checked and verified.
Define Measure Analyze Improve Control
-
8/3/2019 Resource Reconciliation Automation Project_Final
11/18
Copyright 2008 Accenture All Rights Reserved.
Process Map (To Be)
11
Define Measure Analyze Improve Control
Extract Feeder Reports
Prepare ReconciliationTemplate
Load Current WeeksData
Perform Reconciliation
IdentifyAction Points
Start
Stop Automated
Manual
Load Data Macro
PerformReconciliation Macro
-
8/3/2019 Resource Reconciliation Automation Project_Final
12/18
Copyright 2008 Accenture All Rights Reserved.
To-be Process Map Contd.
12
Define Measure Analyze Improve ControlResource
Automated Report
-
8/3/2019 Resource Reconciliation Automation Project_Final
13/18
Copyright 2008 Accenture All Rights Reserved.
Control Plan
Sl No Solution Control Measures Remarks
1 Report Automation
Macro (automation code) has been password protected to prevent
unauthorized change of code and thereby prevent accidental
damange to the automated template
Achieved
Cell Locking mechanisms have been implemented in cells
containing formulae (and wherever else necessary) to prevent
accidental modification of the code.
Achieved
Quality check practise by peer has been put in place to ensure
that the report produced by the macro is free of any discrepancies.Achieved
13
Define Measure Analyze Improve Control
-
8/3/2019 Resource Reconciliation Automation Project_Final
14/18
Copyright 2008 Accenture All Rights Reserved.
Key learning's from this Project
Technology Benefits
# Client
Business
Domain /Industry Engagement Project TeamSize Hardware Software
ProblemScenario /
OptimizationScenario /Improvement
Scenario
EffectivePractices Tangible Intangible
1 AstraZeneca
LifeSciences
AstraZenecaPMO
EERP 7NormalDesktopsystem
MS Office ,VBA,
ProjectServer,Sharepoint,DistributionLists server
Problem :Highly manualand timeconsumingprocess withsignificant riskof manual error
Solution:Implementationof automationto significantlysame time andhuman effortthereby alsoreducing therisk of humanerror.
1. Use ofpasswordprotection topreventaccidentalchange ofmacro code
2. Incorporationof cell lockingmechanismsfor cellscontainingformulae toprevent themfrom beingmodified by themacro /manually.
2.5 hourssaved on aweeklybasis.
1.Reductionin humaneffort2.Increasedaccuracy in
reportgeneration.3. The timesaved cannow beutilized inother value
addedactivitiesfor theproject
14
Define Measure Analyze Improve Control
-
8/3/2019 Resource Reconciliation Automation Project_Final
15/18
Copyright 2008 Accenture All Rights Reserved.
Benefits
1515
Define Measure Analyze Improve Control
-
8/3/2019 Resource Reconciliation Automation Project_Final
16/18
Copyright 2008 Accenture All Rights Reserved.
Benefits (Contd.)
1616
Define Measure Analyze Improve Control
Avg. Time Spent Per Week = 3:06:53
Before Improvement
After Improvement
Avg. Time Spent Per Week = 0:31:47
Avg. Time Savings Per Week = 2:35:06
Overall Efficiency Improvement = 83%
Resource
onciliation Time L
-
8/3/2019 Resource Reconciliation Automation Project_Final
17/18
Copyright 2008 Accenture All Rights Reserved.
Benefits (Contd.)
17
Tangible BenefitsTotal Hours saved per week = 2.5 hours (more than the initial estimated target of 1.5 hr)
Overall Efficiency Achieved = 83%
Annual Hourly Savings = 2.5 X 4 (weeks per month) X 12 (months) = 120 Hours
peryearAnnual Cost Savings = 120 Hours X $15 / hour (SSE LCR) = $1800
(or Rs. 84,294/ - considering an exchange rate of 46.83 per $)
Intangible Benefits (soft savings) Reduction in human effort
Increased accuracy in report generation Time saved can now be utilized in other value added activities for the project.
The solution implemented can be re-used for similar reconciliation requirements in otherprojects.
Note : Annual benefit can be derived out of saving opportunity costs (eg., reducing lead time, productivity savings etc., in addition to harddollar savingsCost should include salary cost, overhead cost, indirect cost , opportunity cost, etc.
17
Define Measure Analyze Improve Control
-
8/3/2019 Resource Reconciliation Automation Project_Final
18/18
Metrics for July, Aug & Sept00
Baseline
Project Owner : Raminder SinghChadha New Owner : Jagruthi Priya
I am aware of improvements brought about by the projectControl plan is completely Documented and Communicated
I understand the corrective action plan
I understand and take responsibility from here on
I will report Progress on this Process/ Sub Process regularly
23/11/2011
(date)
Raminder SinghChadha
Project Champion : Core Process Owner :
Signature & Date
Project Hand-off Sheet
BB Sign Off :
Sign off