report of the auditor general on the financial statements ... · report of the auditor general on...
TRANSCRIPT
THE REPUBLIC OF UGANDA
REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS
OF KAMPALA CAPITAL CITY AUTHORITY
FOR THE FINANCIAL YEAR ENDED 30TH JUNE 2016
OFFICE OF THE AUDITOR GENERAL
UGANDA
ii
TABLE OF CONTENTS
LIST OF ACRONYMS .................................................................................................. iii
REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF KAMPALA
CAPITAL CITY AUTHORITY FOR THE YEAR ENDED 30TH JUNE, 2016 ............................. iv
1.0 INTRODUCTION ............................................................................................. 8
2.0 BACKGROUND INFORMATION .......................................................................... 8
3.0 ENTITY FINANCING ........................................................................................ 8
4.0 MANDATE AND 0BJECTIVES OF KCCA ............................................................... 9
5.0 AUDIT OBJECTIVES ........................................................................................ 9
6.0 AUDIT PROCEDURES PERFORMED ................................................................. 10
7.0 CATEGORIZATION AND SUMMARY OF FINDINGS ............................................ 11
7.1 Categorization of findings .............................................................................. 11
7.2 Summary of Findings ..................................................................................... 11
8.0 DETAILED FINDINGS..................................................................................... 12
8.1 Receivables .................................................................................................. 12
8.2 Legal costs ................................................................................................... 12
8.3 Revenue Shortfall .......................................................................................... 13
8.4 Property - Land titles ..................................................................................... 14
8.5 Payables....................................................................................................... 15
8.6 Youth Livelihood Programme .......................................................................... 17
8.7 Human Resource Management ....................................................................... 18
8.8 Budget performance ...................................................................................... 19
8.9 Field Inspections ........................................................................................... 24
iii
LIST OF ACRONYMS
Acronym Meaning
BLB Buganda Land Board
CDD Community Driven Development
DLB District Land Board
DPP Directorate Of Physical Planning
EFT Electronic Funds Transfer
IGG Inspectorate of Government
KCC Kampala City Council
KCCA Kampala Capital City Authority
KDLB Kampala District Land Board
MDA Ministries, Departments and Agencies
MOU Memorandum of Understanding
NSSF National Social Security Fund
NTR Non-Tax Revenue
PPDA Public Procurement and Disposal of Assets Authority
YIG Youth Interest Group
YLP Youth Livelihood Programme
PFMA Public Finance Management Act, 2015
TAIs Treasury Accounting Instructions
iv
REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF
KAMPALA CAPITAL CITY AUTHORITY
FOR THE YEAR ENDED 30TH JUNE, 2016
THE RT. HON. SPEAKER OF PARLIAMENT
I have audited the Financial Statements of Kampala Capital City Authority (KCCA) for the
year ended 30th June 2016. These financial statements comprise of the statement of
financial position, the statement of financial performance, statement of changes in equity
and cash flow statement together with other accompanying statements, notes and
accounting policies.
Management Responsibility
Under Article 164 of the Constitution of the Republic of Uganda, 1995 (as amended) and
Section 45 of the Public Finance Management Act, 2015, the Accounting Officer is
accountable to Parliament for the funds and resources of Kampala Capital City Authority.
The Accounting Officer is also responsible for the preparation of financial statements in
accordance with the requirements of the KCCA Act 2010, and the International Public
Sector Accounting Standards (IPSAS) on Accrual basis of accounting and for such internal
controls as management determines is necessary to enable the preparation of financial
statements that are free from material misstatement, whether due to fraud or error.
Auditor’s Responsibility
My responsibility as required by Article 163 of the Constitution of the Republic of Uganda,
1995 (as amended) and Sections 13 and 19 of the National Audit Act, 2008 is to audit
and express an opinion on these statements based on my audit. I conducted the audit in
accordance with International Standards on Auditing. Those standards require that I
comply with the ethical requirements and plan and perform the audit to obtain
reasonable assurance whether the financial statements are free from material
misstatement.
An audit involves performing audit procedures to obtain evidence about the amounts and
disclosures in the financial statements as well as evidence supporting compliance with
relevant laws and regulations. The procedures selected depend on the Auditor’s judgment
including the assessment of risks of material misstatement of financial statements
whether due to fraud or error. In making those risk assessments, the Auditor considers
v
internal control relevant to the entity’s preparation and fair presentation of financial
statements in order to design audit procedures that are appropriate in the circumstances
but not for purposes of expressing an opinion on the effectiveness of the entity’s internal
control. An audit also includes evaluating the appropriateness of accounting policies used
and the reasonableness of accounting estimates made by management as well as
evaluating the overall presentation of the financial statements. I believe that the audit
evidence I have obtained is sufficient and appropriate to provide a basis for my audit
opinion.
Part “A” of this report sets out my opinion on the financial statements. Part “B” which
forms an integral part of this report presents in detail all the significant audit findings
made during the audit which have been brought to the attention of management and
form part of my Annual Report to Parliament.
PART ‘‘A’’
Opinion
In my opinion, the financial statements present fairly, in all material respects the financial
position of Kampala Capital City Authority as at 30th June, 2016 and its financial
performance and cash flows for the year then ended in accordance with the International
Public Sector Accounting Standards (IPSAs) and the KCCA Act 2010.
Report on other legal requirements
As required by the Kampala Capital City Authority Act, 2010 and the National Audit Act,
2008:
i. I have obtained all the information and explanations, which to the best of my
knowledge and belief were necessary for the purpose of my audit.
ii. In my opinion, proper books of account have been kept by the Authority, so far as
appears from my examination of those books; and
iii. The statement of financial position and statement of financial performance are in
agreement with the books of account.
Emphasis of Matter
Without qualifying my opinion, attention is drawn to the following matters that are
described in Note 4, Note 12 and Schedule L1 in the financial statements and also in
paragraph 8.1 and 8.2 of my report:
vi
Outstanding receivables
The trade and other receivables amounted to UGX.53,014,155,403 as at the close of the
financial year. The uncollected outstanding receivables may eventually necessitate writing
off the debts thus causing financial loss to the Authority. This would impact on the cash
flows of the Authority.
Legal costs
Management recognized a provision for legal liabilities amounting to UGX.26,719,950,359
and also disclosed contingent legal liabilities amounting to UGX.100,789,450,678 as at
30th June 2016. These legal costs relate to various civil cases filed against the Authority,
and currently pending before the courts of law. There is a possibility that these costs
may severely constrain the implementation of the Authority’s planned activities, should
the liabilities crystallize.
John F.S. Muwanga
AUDITOR GENERAL
KAMPALA
22nd December, 2016
7
REPORT OF THE AUDITOR GENERAL AND
SUPPLEMENTARY INFORMATION
8
“PART B”
DETAILED REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS
OF KAMPALA CAPITAL CITY AUTHORITY FOR THE YEAR ENDED 30TH JUNE, 2016
This Section outlines the detailed audit findings, management responses, and my
recommendations in respect thereof.
1.0 INTRODUCTION
Article 163 (3) of the Constitution of the Republic of Uganda, 1995 (as amended)
requires me to audit and report on the public accounts of Uganda and all public
offices including the courts, the central and local government administrations,
universities, and public institutions of the like nature and any public corporation or
other bodies or organizations established by an Act of Parliament. Accordingly, I
carried out the audit of Kampala Capital City Authority (KCCA) to enable me report to
Parliament.
2.0 BACKGROUND INFORMATION
Kampala Capital City Authority was enacted by Kampala Capital City Act 2010. The
Authority is a body corporate with perpetual succession and may sue and be sued in
its corporate name. It is located at city hall on Plot 1-3 Sir Apollo Kaggwa road,
Kampala Capital City. The Authority’s vision is’’ to be a vibrant and sustainable City’’
while the Mission is ‘’to deliver Quality service to the City “
3.0 ENTITY FINANCING
The Authority was financed by grants from Central Government, donor funds and
locally generated revenue. Grants totaling to UGX.207,778,350,016 from Central
Government were received while, UGX.111,951,019,783 was received as funding
from development partners (including KIIP2 project UGX.85,461,894,928 and
Uganda Road Fund UGX.14,738,725,987, among others). Cash collections from Non-
tax revenue amounted to UGX. 84,927,640,611 and UGX.76,734,694 was collected
from Miscellaneous revenue. Out of the total funding received of UGX.
404,733,745,104, the Authority spent UGX.286,971,524,720 and this constituted
70% of the revenue received.
9
4.0 MANDATE AND 0BJECTIVES OF KCCA
The core mandate is enshrined in section 7 (1-4) of the Kampala Capital City
Authority Act, 2010 and are;
(i) To provide for Administration of Kampala by the Central Government;
(ii) To provide for the Territorial Boundary of Kampala;
(iii) To Provide for the Development of Kampala Capital City;
(iv) To Establish a Kampala Capital City Authority as the Governing Body of the
city;
(v) To Provide for the composition and Election of Members of the Authority;
(vi) To Provide for the removal of members from the Authority;
(vii) To provide for the Functions and Powers of the Authority;
(viii) To provide for the election and removal of the Lord Mayor and Deputy Lord
Mayor;
(ix) To Provide for the Appointment, Powers and Functions of an Executive Director
and Deputy Executive Director of the Authority;
(x) To provide for Lower urban councils under the Authority;
(xi) To provide devolution by the Authority of Functions and Services;
(xii) To provide for a metropolitan Physical Planning Authority for Kampala and
adjacent Districts;
(xii) To provide for the power of the Minister to veto decisions of the Authority in
certain circumstances and for related matters.”
5.0 AUDIT OBJECTIVES
The audit was carried out in accordance with International Standards on Auditing
and accordingly included a review of the accounting records and agreed procedures
as was considered necessary. In conducting my reviews, special attention was paid
to establish whether:-
a. The financial statements have been prepared in accordance with consistently
applied Accounting Policies and fairly present the revenues and expenditures
for the period and of the financial position as at the end of the period.
b. All funds were utilized with due attention to economy and efficiency and only
for the purposes for which the funds were provided.
10
c. Goods and services financed have been procured in accordance with the
Government of Uganda procurement regulations.
d. To evaluate and obtain a sufficient understanding of the internal control
structure of the organization, assess control risk and identify reportable
conditions, including material internal control weaknesses.
e. The Management was in compliance with the Government of Uganda
financial regulations.
f. All necessary supporting documents, records and accounts have been kept
in respect of all activities, and are in agreement with the financial statements
presented.
6.0 AUDIT PROCEDURES PERFORMED
The following audit procedures were undertaken:-
(a) Revenue
Obtained schedules of all revenues collected and reconciled the amounts to the
cashbooks and bank statements.
(b) Expenditure
The Authority payments vouchers were examined for proper authorization,
eligibility and budgetary provision, accountability and support documentation.
(c) Internal Control System
Reviewed the internal control system and its operations to establish whether
sound controls were applied throughout the period audited.
(d) Procurement
Reviewed the procurement of goods and services by the Authority during the
period under review and reconciled with the approved procurement plan.
(e) Fixed Assets Management
Reviewed the use and management of the assets of the Authority during the
period audited.
11
(f) Authority’s Financial Statements
Examined, on a test basis, evidence supporting the amounts and disclosures in
the financial statements; assessed the accounting principles used and
significant estimates made by management; as well as evaluating the overall
financial statement presentation.
7.0 CATEGORIZATION AND SUMMARY OF FINDINGS
7.1 Categorization of findings
The following system of profiling of the audit findings is used to better prioritize the
implementation of audit recommendations:
No Category Description
1 High significance Has a significant/material impact, has a high likelihood of
reoccurrence, and in the opinion of the Auditor General, it
requires urgent remedial action. It is a matter of high risk or
high stakeholder interest.
2 Moderate significance Has a moderate impact, has a likelihood of reoccurrence,
and in the opinion of the Auditor General, it requires
remedial action. It is a matter of medium risk or moderate
stakeholder interest.
3 Low significance Has a low impact, has a remote likelihood of reoccurrence,
and in the opinion of the Auditor General, may not require
much attention, though its remediation may add value to the
entity. It is a matter of low risk or low stakeholder interest.
7.2 Summary of Findings
No Finding Significance
8.1 Receivables High
8.2 Legal costs High
8.3 Revenue Shortfall High
8.4 Property - Land titles High
8.5 Payables High
8.6 Youth Livelihood Programme (YLP) High
8.7 Human Resource Management High
8.8 Budget performance Moderate
8.9 Field inspections Moderate
12
8.0 DETAILED FINDINGS
8.1 Receivables
Outstanding trade and other receivables
The trade and other receivables presented in the statement of financial position
decreased from UGX.77,007,788,342 to UGX.53,014,155,403 (representing 31%
decrease from the previous year’s balance). Out of the receivables amount it was
noted that property rates decreased from UGX.66,396,029,910 to
UGX.42,043,077,310 while ground rent decreased from UGX.13,993,742,152 to
UGX.13,469,029,766. The uncollected outstanding receivables may eventually
necessitate writing off the debts thus causing financial loss to the Authority.
Management explained that the Authority has instituted debt recovery initiatives like
reorganizing ground rent lease records, intensifying issuance of tax invoices,
issuance of demand letters, verifying of property records, updating the tax legers
and intensifying sensitization and engagement of tax payers.
I await a further decrease of the receivable positon given the initiatives of the
Accounting Officers in collecting the outstanding receivables.
8.2 Legal costs
During the year under review, the Authority budgeted UGX.6,099,000,000 for legal
costs. However, a review of payments revealed that the Authority spent funds
totaling UGX.11,799,768,822 thus exceeding the budgeted expenditure by
UGX.5,700,768,822 (93%).
A review of the statement of financial position revealed that management disclosed a
sum of UGX.26,719,950,359 as provision for legal costs for the period under review.
This represents a decline of provisions on legal costs by UGX.1,428,482,773 (5%)
from the prior year. It was also noted that taxes and interest costs on a number of
these cases were yet to be determined by court. There is a possibility for further
increases in the legal costs payable.
Furthermore Management disclosed possible/contingent liabilities amounting to
UGX.100,789,450,678 in the financial statements an indication that there is a
possibility that the legal costs may severely constrain the activities of the Authority
in the near future. Delays by the Authority to offset interest bearing judgments in a
13
timely manner may lead to incurring more penalties in terms of interests arising from
delayed payments.
Management explained that the excess expenditure on legal costs during the year
was due to Garnishee Orders placed on the revenue collection accounts and the
delay to settle interest bearing judgments in a timely manner, majorly due to
inadequate funding provisions.
I advised Management to prioritize payments for legal costs which have high interest
clauses with a view of avoiding nugatory expenditure.
8.3 Revenue Shortfall
8.3.1 Under-collections of revenue
The Uganda Government Financial regulations, 2003 section 2.15.1 (i) requires the
Accounting officer to ensure that there are efficient and effective arrangements for
revenue collection from the public. It was observed that the Authority planned to
collect Revenue of UGX.111,080,000,000 during the year under review. However, it
was noted that only UGX.84,927,640,611 was collected representing a revenue
shortfall of UGX.26,152,359,390 (24%). Refer to the table below. Under-collection of
revenue affects the entity ability to perform its intended activities.
REVENUE
SOURCE
ACTUAL 2015/16 TARGET 2015/16 PERFORMANCE%
Business License 13,539,641,854 20,041,872,874 68
Property rates 20,265,048,851 23,433,322,361 86
Rent and Rates 4,483,346,408 7,445,091,185 60
Road User Fees 18,660,261,822 28,120,749,498 66
Advertising 1,407,997,150 3,008,400,220 47
Markets 2,187,439,687 2,537,875,380 86
Land fees 3,927,280,805 7,698,058,949 51
Building fees 2,482,902,972 3,498,866,276 71
Local service Tax 11,442,020,609 11,371,928,618 101
Local Hotel Tax 2,329,522,115 2,362,609,457 99
Other Revenue
Sources
3,103,249,585 1,561,225,183 199
Value Added Tax
(VAT)
1,098,928,753
Gross total
collections
84,927,640,611 111,080,000,000 76
14
Management explained that the budgeted forecasts included revenue from various
Ministries, Departments and Agencies of Government. However, the PS/ST under
the budget call circular dated 26th January 2016 waived all arrears MDAs owed to
Local Government to a tune of UGX.21billion. Going forward, KCCA has instituted
mechanisms to meet budget forecasts like collecting data for property valuation,
engaging political leaders to enhance revenue mobilization, creating of new grades
for trading licenses to cater for businesses which previously were not paying,
automating of the revenue database to enhance billing efficiency and recruiting of
staff to conduct door to door revenue registration.
I await the outcome of Management’s efforts to enhance revenue performance.
8.3.2 Shortfall in Government Grant
It was observed that the Authority estimated to receive UGX.160,548,184,124 grants
from the Central Government during the year under review. However, only
UGX.126,515,323,029 was received creating a short fall of UGX.34,032,861,095.
Failure by Government to release all budgeted funds to the Authority stalled
implementation of some programs thereby denying services to the beneficiary
communities.
Management explained that the short fall in release of budgeted funds by
Government affected implementation of planned activities for the year especially
construction works. Management has continuously engaged Government to release
all budgeted funds in order to fully implement the approved Work Plans and a
response from PS/ST is awaited.
I advised Management to continuously engage Ministry of Finance, Planning and
Economic Development for the deficit and ensure that planned activities are fully
funded.
8.4 Property - Land titles
A review of the entity property inventory as at 30th June, 2016 revealed that some
titles were not yet in possession of the Authority. This was attributed to some titles
pending mutation and there were delays in getting land title from Uganda Land
Commission, Kampala District Land Board and Buganda Land board while others
15
were caveated. Delays in acquiring land titles may result in to loss of property and
subsequent increases in litigation costs.
Management explained that the delay in acquiring land titles was partly due to
shortfall in Non-Tax Revenue collections to enable settling land fees and titling
charges of UGX.881,000,000. Arrangements have been made to have this settled in
3rd quarter of this financial year (2016/17). Management further explained that the
rest of the titles are pending at the Ministry of Lands which the KCCA Land
Management Unit will follow up with the office of the Commissioner Land
Registration to secure the issuance of the titles.
I wait the outcome of Management’s efforts over the matter.
8.5 Payables
8.5.1 Trade creditors
A review of the payables schedule Note 10(a) revealed that payables decreased from
UGX.36,070,594,330 in the previous year to UGX.26,022,099,966 as at 30th June
2016. Further analysis revealed the following:
UGX.19,071,029,856 out of the trade payables of UGX.22,681,902,519 had not
been paid at the time of the audit (5 months after the year-end) which indicates
a slack in debt management. The outstanding trade payables included cleaning
services for health centers, air tickets and legal costs.
Out of the opening balance of severance package of UGX.359,012,330, the
Authority only paid UGX.11,780,268 leaving a balance of UGX.347,232,062 as at
30th June 2016.
Failure to pay off suppliers and severance package beneficiaries may result in to
litigation costs.
8.5.2 Outstanding Statutory obligations
A review of the other payables ledgers in Note 10(b) of the financial statement
revealed that the Authority had not remitted statutory deductions like PAYE, VAT and
NSSF as detailed below;
16
i. Non remittance of National Social Security contribution
Section 11 of the National Social Security Fund Act states that every contributing
employer shall, for every month during which he or she pays wages to an eligible
employee, pay to the Fund, within fifteen days next following the last day of the
month for which the relevant wages are paid, a standard contribution of 15%
calculated on the total wages paid during that month to that employee.
A review of the financial statements revealed that out of UGX.1,470,398,113 of
NSSF payable as at 30th June 2016, only UGX.1,271,717,003 was paid leaving an
outstanding amounting of UGX.198,681,110 (14%) 5 months after the year end.
Delayed remittances deny the employees the right to earn interest on contributions
for the months. Furthermore, delayed remittances can lead to penalties from the
statutory agency.
ii. Non-remittance of PAYE and VAT
Section 124(1) of the Income Tax Act requires a withholding agent to pay to the
Commissioner any tax that has been withheld or that should have been withheld
under this section within fifteen days after the end of the month in which the
payment subject to withholding tax was made by the withholding agent.
I noted that out of URA payables of UGX.9,227,431,839 as at 30th June, 2016 only
UGX.6,337,972,440 had been paid at the time of audit (5 months after the year-end)
leaving an outstanding balance of UGX.2,889,459,399 (31%). Violation of the
Income Tax laws attracts fines and penalties thus reducing funding for planned
activities.
Management explained that the delay to settle outstanding creditors was due to
shortfall in funding from Government, Non Tax Revenue Collections and Garnishee
Orders however arrangements were being made to settle the pending obligations in
3rd quarter of the financial year 2016/17.
I advised management to liaise with PS/ST on funding of the budget of the entity,
among other initiatives being pursued. I await the outcome of these efforts to clear
the outstanding payables.
17
8.6 Youth Livelihood Programme
The youth livelihood Programme (YLP) is a rolling government of Uganda
Programme, targeting the poor and un-employment in all the districts in Uganda.
The programme is being implemented under the Ministry of Gender, Labour and
Social Development. The funds for the programme are advances to the Youth
Interest Group (YIG) in form of a revolving fund in order to increase outreach and
enhance sustainability of the programme. A review of project reports and
accountability revealed the following issues;
8.6.1 Low absorption
During the year under review, KCCA received a sum of UGX.500,898,870 for
subsequent disbursement to the youth groups. It was however observed that at the
end of the year only 34 groups out of the expected 47 had benefited from the total
disbursements of UGX.182,039,949 which represents 36.34% of the total actual
release thus leaving a balance of UGX.308,145,036 on the account at end of the
year. There is a risk that the program is not achieving its objectives.
Management explained that the low absorption of funds was majorly due to the fact
that KCCA received funds three months to end of the financial year and the process
of identifying beneficiary groups up to the level of disbursement is quite lengthy.
Management further explained that most youth groups delayed to open bank
accounts; some groups submitted unsatisfactory accountabilities while others
withdrew from the project due to disagreements within the groups and as such funds
were automatically recovered.
I advised the Accounting Officer continue sensitizing the youth in order to boost
funds absorption by the beneficiary communities.
8.6.2 Low recovery and management of funds
The review of the project reports indicated that funds were advanced to the youth in
form of a revolving funds and recovery is supposed to be effected within one year
after which a service fee of 5% is charged on the outstanding loan after one year.
I noted that the Authority made cumulative disbursements of UGX.1,222,349,899 to
139 groups appraised from the inception of the project up to 30th June 2016.
18
However, only UGX.186,359,751 was recovered which represents only 12.1%
recovery rate. Failure to recover funds disbursed to groups denies other potential
beneficiaries of funds to improve their livelihoods.
Management explained that the set guidelines had issues specifically related to
recovery but pledged to liaise with Ministry of Gender and Social development to
improve on the Youth Livelihood Programme guidelines.
I await the outcome of Management’s efforts to enhance the benefits of the Youth
livelihood Programme in Kampala.
8.7 Human Resource Management
8.7.1 Unapproved Human Resource Manual
Section 45(2) of the Public Finance and Management Act 2015 requires an
accounting officer to put in place effective systems of risk management and internal
controls in respect of all resources and transactions.
It was observed that the Human Resource policy was still in draft form pending
approval. Operating without approved human resource policy may result in irregular
recruitments and selective application of human resource standards may not apply to
all staff thus hindering achievement of the Authority’s strategic objectives.
Management stated that the proposed KCCA Human Resource Manual was submitted
to the Ministry of Public Service for compliance assurance with the applicable
laws, regulations and approval as per the mandate given to the Ministry under KCC
Act 2010 section 25 (4). Management is continuously engaging with the Ministry to
ensure that the Human resource Manual is approved.
I await the outcome of Management’s efforts to have the Human resource Manual
approved.
8.7.2 Staffing
I noted that the KCCA appointed overstaff on temporary basis to perform duties in
various departments whose contracts were renewable every three to four months.
Some of the officers were in senior positions.
19
Having temporary staff in senior positions may demotivate them and they may pay
less attention to risk control since they are not certain of their future.
Management explained that the main reason for appointment of staff on temporary
appointment was the cap on recruitment that arose from the failure by the Ministry
of Finance to confirm funds to facilitate the appointment of staff on permanent
terms. Going forward, plans are underway to start filling vacant positions in January
2017 upon confirmation of availability of funds.
I advised management to liaise with MOFPED for the required funding to ensure the
filling of its structure for purposes of meetings its mandate. I await further action by
Management.
8.8 Budget performance
Section 45 (3) of the Public Finance Management Act 2015 states that an Accounting
Officer shall enter into an annual budget performance contract with the Secretary to
the Treasury which shall bind the Accounting Officer to deliver on the activities in the
work plan of the vote for a financial year, submitted under section 13 (15). Budget
estimates are based on outputs to be achieved for the financial year and during
implementation, effort is required to be made to achieve the agreed objectives or
targets of the entity within the availed resources.
The budget performance for the year under review revealed that some targets were
partially or not achieved despite release of funds to the vote functions as indicated
below:
20
Vote
function output
Item
description
Planned
outputs/Quantity
Amount (UGX)
budgeted
Amount
released (UGX)
Actual output/
Quantity
Remarks
Vote Function:
0105 Urban Commercial
and Production
Services
Output: 010503
Market Access for Urban
Agriculture
1,188 Number of small
scale urban farmers
introduced to new technologies
1,188 Number of
farmers supported with inputs and knowledge
2,359,000,000 1,289,0000,000 A total of 566
individuals received
training on various aspects of vegetable
production
A total of 1,277
farmers were
introduced to new technologies
Whereas the number of
farmers introduced new technologies Less than half
of the planned activities(566) was performed
Output: 010580 Urban Market
Construction
Purchase land to
construct more markets(Kasubi market)
7,500,000,000 5,384,959,355 Part payment of USAFI
market made Registration of USAFI
Market vendors: The
activity was not
carried out due to an urgent need to
register street vendors working along Allen
Road. Registration will
be done in Quarter 1 of the new financial
year 2016/17)
A partial payment to
USAFI market was done because government
released for that purpose.
The Purchase of Kasubi
Market was not done due
to shortfalls in NTR collections.
Vote Function:
0204 Urban Planning,
Security and Land Use
Programme 09
Physical Planning
Output: 020403
Slum Development
and Improvement
Carrying out a slums
improvement needs
assessment. Preparing project
Proposal for slums
improvement. Identifying partners to
work with in slums
342,000,000 204,000,000 Activities related to
slum development
were in the current year were kick started.
The activities included profiling, needs
assessments among
others
I noted that this activity
requires significant
funding (USD 12m) but because of limitation in
funding partial implementation of activity
was done.
21
improvement Management should
prioritize slum
development activities in order to attain the much
needed slum
improvement in the city.
Project 1253 Kampala Road
Rehabilitation
Output: 040675 Purchase of
Motor Vehicles
and Other Transport
Equipment
Transport equipment
purchased including; pick-up for drainage
works and motor
cycles.
150,000,000 37,500,000 Motorcycles were
procured to support on maintenances
Surveillance.
Pick up was not
procured.
I observed that due to
shortfall in NTR collections the
surveillance pick up was
not bought. Only Motorcycles were
procured.
Vote Function:
1005 Gender, Community
and Economic Development
Project 0115 LGMSD
(former LGDP)
Output:
080780 Health Infrastructure
Construction
Renovation of Kawaala
HCIV and expansion of
Maternity Ward and chain-link fencing at
Kawaala Health Centre IV.
Renovation of Kitebi HC
III, OPD block. Repair of wall and
ceiling of Pediatric
Ward at Komamboga
HC. Repair of roof, drainage
and face lifting of
Kisuggu Health Centre. Renovation of KCCA
Kisenyi Health Centre
IV Perimeter Wall and
Entrance Gate and Installation Step Up
100KVA Transformer at Kisenyi Health Centre
Expansion of OPD at
4,380,862,270 3,436,142,271 Upgrading and
Renovation of KCCA
Health Facilities Construction works
and upgrade of
Kawempe and Kiruddu Health centres to 170
bed hospitals is almost complete with works
at 98%.
Kisenyi HC IV;
Installation of the main gate completed
and Supplied 100KVA transformer by
UMEME. Small fittings
on leaking roofs clutters are also
completed. Kawaala HC III
Remodeling of
maternity ward commenced and is still
I observed that
Construction of Bukoto
H/C, Kiswa HC , Repair and drainage of Kisuggu
health centre was not done due to shortfall in
collections.
There is need to urgently
fund these projects in
order to improve the health services in the city
22
Kiswa HC III and
expansion of infrastructure at Bukoto
HC II for upgrade to HC
IV.
ongoing.
Output: 100551
Small scale business
promotion
200 Small scale
enterprises and CBOs
groups provided with CDD grant
1,376,416,260 768,659,319 150 groups were
supported with CDD
funds worth UGX.734,430,000. The
beneficiaries were
trained in pre award workshops, financial
management, project planning &
management,
leadership and group dynamics while 28
parish model networks were formed due to
limited budget releases. Pre-
disbursement training
held for all 150 groups.
50 groups were not given
funds due to lack of
funds.
24
Service delivery is hampered and the appropriating Authority’s objectives will not be
met.
Management explained that some planned activities were not implemented due to
revenue shortfall and Garnishee orders.
I advised Management to continue engaging MoFPED to fund the whole budget and
internally they should improve revenue collection efforts in order to achieve the
planned outputs.
8.9 Field Inspections
Field inspection of some KCCA primary schools and Health centres was conducted for
purposes of verifying the Authority’s undertakings in relation to its core objectives of
effective service delivery in the city.
8.9.1 Inspection of Health Centres
Inspection carried out at some of KCCA Health Centres revealed the following;
Land encroachment
Land not fenced
National Medical Stores supplying drugs which are about to expire.
Limited drug storage capacity
The health centre IIIs have meager budget of only UGX.45,426,300 per year for
medical supplies.
Detailed observations are in the table below:
Site Remarks Status
Komamboga
Health Centre
III
Land was encroached on by a
resident as it was not fenced
There is limited space in drug
stores hence boxes are piled up to
the ceiling which may affect the
durability of the drugs.
The health centre lacks staff
quarters/accommodation which
leads to delays by the medical
personnel to work on patients in
cases of emergencies.
I noted that National Medical
Stores supplied drugs that were
25
about to expire to the health
centres.
The health centre often
experienced drug stock outs due
to the limited annual budget of
UGX. 45,426,300 for drug supplies.
The children’s ward had developed
a crack. Due to safety concerns,
the ward is not used.
Kiswa Health
Centre III
The Health centre land was
encroached on by the residents.
The health centre lacked a
maternity ward.
There is limited space in drug
stores hence boxes are piled up to
the ceiling which may affect the
durability of the drugs.
National Medical Stores supplied
drugs which were about to expire
for example the HIV testing Kits
which were supplied in October
2016 were set to expire in
November 2016.
Expired drugs have not been
disposed of since 2014
The health centre often
experienced drug stock outs due
to the meager annual budget of
UGX 45,426,300 for drug supplies
yet the patient load is 600-750 per
day.
The picture shows the poor drug
storage on rusty shelves and piled
up boxes.
26
Kisugu Health
Centre
National Medical Stores supplied
drugs which were about to expire.
The health centre often
experienced drug stock outs due
to the meager annual budget of
UGX.45,426,300 for drug supplies
yet the patient load is 700-800 per
day.
There are delays in collection of
expired drugs by National medical
stores.
Medical equipment in the stores
was not properly maintained.
Some of the expired drugs are
shown on the photos.
Kawaala HC
III
The health centre had high patient
load of 7,000-8,000 patients a
month with limited space, led to
congestion at the centre forced
Management to acquire cargo
containers and partitioned them
in to treatment rooms. However
the rooms lack enough ventilation,
for example setting up a TB unit
requires a more open environment.
The maternity ward had an
average of 450 deliveries per
month yet the ward has only 9
beds. Hence mothers at times are
discharged from the maternity
ward shortly after delivery before
full recovery to create space for
other expectant mothers.
Maternity ward above
27
There is no adequate space for
stores, thus some supplies were
stored in the patient’s waiting
rooms.
TB and ARVs drugs are well
stocked however the Health often
had stock outs for essential drugs
within two weeks after delivery due
to a meagre budget of UGX.
45,426,300 for drug suppliers.
Some Laboratory tests such as HB,
HCD and CDC for pregnant
mothers cannot be handled at the
center thus denying the community
quality service delivery.
The health centre also lacks vital
units such as X-ray, theater,
radiology and ultra-sound units.
The health centre lacks enough
toilets as the five stance toilets
were shared by all patients.
Container used as TB unit
Toilet shared by all patients
Kitebi HC III TB and ARVs drugs were well
stocked however the essential like
malaria drugs run out very fast. In
most cases they last about two
weeks after delivery.
The health centre lacks TB drugs
for the children.
The maternity unit had an
average of 260 mothers delivering
per month yet the unit had only 15
beds in the ward; this tends to
congestion and sometimes patients
have to sleep on the floor.
Mama kits were not enough to
cater for Maternity patients.
Patient load was 13,084 per month
and 156,071 annually.
28
The health centre lacks an
ambulance and Management often
assistance from Kawala HC III
whenever it had referral cases. The
annual budget for medical supplies
is UGX. 45,426,300 which is not
sufficient.
Failure to supply adequate drugs to health centres and poor storage of drugs denies
the beneficiary communities quality health services.
Management explained that the Authority was continuously engaging the Ministry of
Health to increase on the resource allocation to City Health centres in order to
support the ever increasing numbers of patients.
I await the outcome of Management’s efforts to have the resources allocation to
health centres increased.
8.9.2 Inspection of Schools
An inspection of a number of schools and the interviews carried out with Head
Teachers revealed the following;
Most schools did not have certificates of land titles
The School land was not fenced
There were staff shortfalls in some schools
Inadequate infrastructure such as staff quarters, classrooms and toilets
Details of the inspections are in the table below:
SCHOOL Remarks Status
Kalinabiri
Primary
School
The staff quarters
were dilapidated.
The dining hall is
incomplete.
In the last three years,
school achieved 112
first grades and 344
second grades out of a
total population of 477
candidates.
29
The school’s existence
is threatened as the
bonafide land lord
wants to dispose off
the land.
Ratios;
Teacher/Pupil 1:41
Classroom/Pupil 1:60
Toilet/Pupil 1:64
Luzira Church
of Uganda
Primary
School
The School enrollment
was 1312 pupils.
Classrooms and Seater
desks are not enough
because of the
overwhelming number
of pupils where by a
3-seater desk is
actually occupied by 6
pupils.
A number of seater
desks were broken.
Management installed
wire mashes instead
of glass windows
which may be
dangerous to the
pupils in case of an
emergency such as
fire outbreak in school.
Ratios;
Teacher/Pupil 1:64
Classroom/Pupil 1:103
Toilet/Pupil 1:84
30
Ntinda
Primary
School
The classroom block is
incomplete. Desks and
classrooms are not
enough for pupils as
school enrollment is
899.
Ratios;
Teacher/Pupil 1:46
Classroom/Pupil 1:67
Toilet/Pupil 1:41
Failure to improve the infrastructure for schools denies pupils and teachers a good
environment for learning.
Management stated that the Authority is committed to improving the school
infrastructure and secure titles within the approved budget. Management further
stated that Authority embarked on the process of rotating teachers in order to
improve the school’s teacher pupil ratio and consequently enhance their academic
performance.
I advised Management to prioritize funding to improve infrastructure in KCCA
schools.
31
APPENDIX 1
FINANCIAL STATEMENTS