VH-OJH INCIDENT
23 SEPTEMBER 1999PETER THOMASOJH PROJECT COORDINATOR
![Page 2: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/2.jpg)
THE FIRST DAY
• VH-OJH left the end of RWY 21L at BKK INTERNATIONAL AIRPORT on the night of 23 SEPTEMBER 1999. The A/C travelled a further 200 metres across the RWY run-off area.
• On its way the A/C collided with the RWY 03R Localiser Antenna before coming to rest in a RWL position.
![Page 3: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/3.jpg)
pth13:
Localiser Antenna
![Page 4: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/4.jpg)
pth13:
“The Day After”
![Page 5: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/5.jpg)
![Page 6: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/6.jpg)
![Page 7: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/7.jpg)
pth13:
No.3 Pylon
pth13:
Note failure of Diagonal Brace “end fitting”
![Page 8: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/8.jpg)
pth13:
Golf Course Road
![Page 9: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/9.jpg)
THE RECOVERY
• The importance of keeping the “Station Aircraft Recovery List” updated, including checking Emergency Contacts and Equipment Suppliers phone numbers.
• An assistant is required to keep notes during the initial Recovery planning period.
![Page 10: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/10.jpg)
![Page 11: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/11.jpg)
pth13:
Construction of a road to return to RWY 21L.
![Page 12: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/12.jpg)
pth13:
Road constructed to allow unloading of aft cargo and parking of crane.
![Page 13: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/13.jpg)
pth13:
Stabilising R/H wing to prevent A/C movement.
![Page 14: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/14.jpg)
pth13:
Fuselage damage due to ingress of NLG Assy.
![Page 15: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/15.jpg)
pth13:
“Classic” failure of R/H WLG.
![Page 16: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/16.jpg)
ARRIVAL OF PARTS
• To ensure swift delivery of Parts, Materials and Tooling a Custom’s Agent must be engaged who has contacts at the HIGHEST LEVELS”. Arranging a “Custom’s Carnet” is of utmost importance to overcome “heavy” Customs Duties.
• To ensure these deliveries are completed with the utmost promptness, cooperation with all levels of the Airport Authority is required.
![Page 17: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/17.jpg)
![Page 18: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/18.jpg)
![Page 19: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/19.jpg)
INCIDENT SITE SCRAP
• All scrap had to be collected for documentation.
• To conform to “Customs” regulations all parts and raw materials movements had to be thoroughly documented and presented to the Authorities for approval so as not to incur large Customs duties. This procedure was also required for all scrap material.
![Page 20: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/20.jpg)
![Page 21: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/21.jpg)
JANUARY 23 2000REPAIR BEGINS
• The Boeing Team begins the repair by first stabilising and “jigging” the Aircraft to prevent fuselage movement during the removal of the lower sections of Sections41 and 42.
![Page 22: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/22.jpg)
pth13:
A/C was “tied” to the tail jack and the jack was cabled to the ground. Jack point was “drilled” to allow fitment of a rod between the jack adaptor and the jack point.
![Page 23: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/23.jpg)
pth13:
Installation of “Tower Jacks”
![Page 24: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/24.jpg)
pth13:
Fuselage “stabilisation” complete.
![Page 25: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/25.jpg)
AIRCRAFT REPAIR BEGINS
• Removal of Section 41 and 42 begins.• Replacement of the damaged “window-
belt” has to be done before removal of the lower Section 41. This is to ensure the alignment of the Aircraft is maintained.
![Page 26: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/26.jpg)
pth13:
“Window belt” repair.
![Page 27: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/27.jpg)
pth13:
No.3 Pylon repair.
![Page 28: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/28.jpg)
pth13:
“Wiring pull-back”
![Page 29: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/29.jpg)
pth13:
“Wiring pull-back” completed.
![Page 30: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/30.jpg)
pth13:
Sections 41/42 removed.
![Page 31: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/31.jpg)
pth13:
“Aligning Sect.41.
![Page 32: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/32.jpg)
pth13:
Installation of Sect.42 “plug”.
![Page 33: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/33.jpg)
pth13:
“Final Alignment”
![Page 34: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/34.jpg)
![Page 35: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/35.jpg)
pth13:
Skin “finish” after repair.
![Page 36: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/36.jpg)
STORES PERSONNEL
• A team of Stores Personnel was required to acquit all the Parts demands and to administer a Parts store to ensure a “smooth” production flow is maintained.
• Boeing were ordering “hundreds” of parts daily from Seattle and expecting 2 days delivery at the site.
![Page 37: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/37.jpg)
pth13:
Mick Gledhill
![Page 38: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/38.jpg)
DOCUMENTING AND CERTIFICATION
• To lessen the impact of the “cost” of the repair to QANTAS a lot of rotable parts were supplied by QANTAS. The Insurance Company will only pay “Market Price” for these parts.
• A Team of LAME’s were needed to document and certify these parts as a lot of the Parts were delivered straight from the Vendor. This included all the Landing Gear assembly’s.
![Page 39: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/39.jpg)
pth13:
Mark Coffey
![Page 40: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/40.jpg)
pth13:
First Engine installed by QANTAS LAME’s
![Page 41: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/41.jpg)
pth13:
Zones 1 & 2 rework by QANTAS.
![Page 42: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/42.jpg)
pth13:
A “few” of the 300+ F/G repairs to the L/E.
![Page 43: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/43.jpg)
![Page 44: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/44.jpg)
HI - BLOW TEST
• “Seats” all the rivets and frame joints.• Exposes any fuselage skin joints leakage.• Fuselage blown to 12.5 psid.
![Page 45: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/45.jpg)
![Page 46: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/46.jpg)
pth13:
“Hi-Blow” relief vlv.
![Page 47: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/47.jpg)
ROLL-OUT AFTER REPAIR
• Rollout from Hangar after approx. 6 months.
• Due to publicity sensitivity the A/C had to be similar in appearance to other B744’s prior to “rollout”.
• The repaint of the repaired areas was achieved by “paint rollers”.
![Page 48: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/48.jpg)
![Page 49: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/49.jpg)
![Page 50: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/50.jpg)
![Page 51: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/51.jpg)
pth13:
Thorough wash before “functional checks begin”.
![Page 52: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/52.jpg)
![Page 53: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/53.jpg)
![Page 54: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/54.jpg)
pth13:
Second Test Flt. Return.
![Page 55: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/55.jpg)
pth13:
Taxi-In after 2nd Test Flt.return.
![Page 56: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/56.jpg)
![Page 57: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/57.jpg)
AFTER A/C DEPARTURE
• A/C Departs for Paint Facility in Xiamen.• Final Clean-up underway.
![Page 58: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/58.jpg)
pth13:
Signing of “Certificate of Completion”.
![Page 59: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/59.jpg)
pth13:
Departure for repaint at Xiamen, China.
![Page 60: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/60.jpg)
pth13:
All scrap had to be disposed of so as to not arouse “Media” interest.
![Page 61: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/61.jpg)
pth13:
Last shipment of scrap is loaded before returning the Hangar to Thai Airways.
![Page 62: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/62.jpg)
pth13:
The crash site 6 months later. Note: the addition of landing lights.
![Page 63: Repairs b 747 vh-ojh qantas](https://reader036.vdocuments.site/reader036/viewer/2022062306/54be13964a7959d76a8b46bc/html5/thumbnails/63.jpg)
THE END
VH-OJH RETURNED TO SERVICE AFTER REPAIR AND REPAINT
ON 8 APRIL 2000.