renewable energy integration: driving the distribution...
TRANSCRIPT
Renewable Energy Integration: Driving the distribution grid modernization
Froilan J. Savet, MSEE, PEE
I IEE Senior Member
Network P lanning & Pro j ect Management
MANILA ELECTRIC COMPANY
42nd IIEE Annual National Convention
November 17 – 19, 2017, SMX Convention Center, Philippines
Meralco Distribution System
Largest DU among 140 DUs/ECs
3% of Philippine land area, 27% of total population
6,973 MW demand, 12,425 MVA substation capacity
Bulk power from centralized generation
8 230kV delivery-point substations
109 115kV, 34.5kV distribution substations
117 sub-transmission circuits, loop, 920 ckt-km
777 distribution circuits, radial, 17,093 ckt-km
97% overhead (17,557 ckt-km)
3% underground (456 ckt-km)
20 typhoons (average) annually
225 minutes SAIDI
2.18 times SAIFI
DU system But concepts are much the same has evolved
Has evolved over the years but needs to modernize for future-proofing
Data as of December 2015
Delivery substation
Meralco Power System
Backbone looped Lines
Distribution radial lines
Distribution substation
Delivery substation
Transformative changes in the power industry Drivers to modernize the system into integrated, optimized and intelligent grid
Proliferation of Disruptive Technologies such as Renewables and Energy Storage
Continuous Improvement in Reliability and System Loss Levels
Asset Optimization Increasing Customer Expectations
amidst worsening weather disturbances
amidst changing regulatory environment
• Reliability performance targets Drive to improve performance and strive grid resiliency amidst worsening weather conditions.
• Asset optimization Optimize asset utilization
• Evolving customer engagement and expectations
Customers today are using more electronic appliances for comfort and entertainment causing a rise in demand; more customers are becoming prosumers.
• Increasing penetration of renewables Falling cost of renewables especially, solar PVs; the DOE has released the Renewables Energy Act of 2008 (9513): An act promoting the exploration, development, utilization and commercialization of renewables; policy incentives like FIT, Net Metering, Renewable Portfolio Standards and Green Option.
1
2
3
4
A generating facility consisting of one or more
generating units, where electric energy is produced from
a source that is renewable, cannot be stored by the
facility owner or operator and has inherent variability
that is beyond the control of the facility owner or
operator. This refers to Wind Farms and Photovoltaic
(SOLAR) generation systems.
Variable Renewable Energy (VRE) Clean Electric Energy
Thermal Loading The current carrying
capacity of the
equipment. Loading an
equipment beyond its
thermal rating may lead
to permanent damage.
Voltage Regulation Embedded generation can
be used for voltage
support, in some cases,
but often makes voltage
control more complex in
the distribution system.
Power Quality The high DER penetration
may affect adversely
power quality, raising
issues such as voltage
fluctuations, flicker, and
harmonics.
Fault level Every point in a
distribution network has a
particular fault level,
which is a measure of the
maximum fault current
expected at that point.
Control/Safety Island forms when a
generator continues to
supply the load in a part
of the network
disconnected from the
upstream grid
RENEWABLE
ENERGY
(RE)
As of September 2017
Solar Plants (34, 43.34 MW)
Biomass/Biogas Plants (3 EGs, 20.47 MW)
Hydro Plant (1 EG, 1.15 MW)
Geothermal Plant (1 EG, 20 MW)
Embedded RE Capacity: 138.96 MW (13 exporting RE; 27 own-use RE)
NM Capacity: 6.94 MW (1,009 energized facilities)
Total RE Capacity: 145.90 MW
Embedded RE Plants Meralco franchise
Wind Plant (1 EG, 54 MW)
Philippine Distribution Code (PDC): establishes the basic rules, procedures, requirements, and standards that govern the operation, maintenance, and development of the electric Distribution Systems in the Philippines
Philippine Electrical Code (PEC): used nationally as the basis for safeguarding persons, buildings and its contents from hazards that may arise from the use of electricity
ANSI IEEE 1547 – Standard for Interconnecting Distributed Resources with Electric Power Systems: provides a set of criteria and requirements for interconnection of distributed generation resources into the power grid
Distribution Services and Open Access Rules (DSOAR): sets the terms and conditions related to the provision of connection assets and services, service to the captive market, supplier of last resort (SOLR) service and unbundled distribution wheeling service provided to the contestable market, and redistributor’s service to sub-meter users
International Electrotechnical Commission (IEC) Standards: international standards and conformity assessment for all electrical, electronic and related technologies
Connection and Operational Requirements Applicable Standards used in the Philippines
Energization
Apply for
Interconnection
Conduct Distribution
Impact Study
Conduct Distribution
Asset Study; FABD
Construct Connection Assets and
Execute Connection Agreements
Perform Testing and
Secure Regulatory Approval
S
T
E
P
S
T
E
P
S
T
E
P
S
T
E
P
S
T
E
P
S
T
E
P
RE Interconnection Process
Other Requirements Installation of synchro-check relay, delta-wye interface transformer, installation of line switches, and
metering facilities (w/ import & export billing), etc.
Impact Study Asset Study
Thermal Loading
Voltage Regulation
Power Quality
Fault Level
Control/Safety
Other Requirements
Network Reinforcement through the construction and/or reconductoring of
subtransmission/distribution lines
Network Reinforcement, Installation of AVR (Automatic Voltage Regulators) and
capacitors, Resetting of On-load tap changers (OLTC)
Installation of PQ compensating equipment (e.g. static var compensators, harmonic
filters, etc.)
Uprating of power circuit breakers, installation of fault current limiting fuses (CFL) on
DTs, resetting of protective relays.
Installation of Direct Transfer Trip (DTT) schemes, Installation of SCADA,
teleprotection equipment, and comm. links for status monitoring and control
Installation of synchro-check relay, delta-wye interface transformer, installation of line
switches, and metering facilities (w/ import & export billing), etc.
The conduct of Distribution Asset Study (DAS) is to determine all distribution assets and costs necessary to accommodate a
proposed interconnection.
Distribution Impact/Asset Studies DIS/DAS
The Distribution Utility has to perform a Distribution Impact Study (DIS) to assess the ability of the Distribution System to
safely and reliably accommodate a proposed Connection Agreement and any upgrades that may be required.
Reference:
Philippine Distribution Code Revised Edition
Connection and Operational Requirements Definition and Classification of Embedded Generating Plant
Embedded Generating Plant A Generating Plant that is connected to a Distribution System or the System of any User and has no direct connection to the Grid.
Embedded Generating Unit A Generating Unit within an Embedded Generating Plant
Embedded Generation Company A person or entity that generates electricity using an Embedded Generating Unit
RE Class Capacity Generator Output Active Power
Control
Reactive Power
Capability
Frequency
Withstand Voltage Ride
Through
Large 10 MW and more Rated capacity within +/-
0.3hz
Should be equipped with
Active Power Control
0.95 leading/lagging power
factor Disconnection
allowed within pre-set
values of frequency
and time
Required
Medium 1 MW < RE < 10MW Rated capacity within +/-
0.3hz
Should be equipped with
Active Power Control
0.98 leading/lagging power
factor Required
Intermediate 100 kW < RE <= 1 MW Rated capacity within +/-
0.3hz
Should be equipped with
Active Power Control
0.98 leading/lagging power
factor Required
Small 10 kW < RE <= 100 kW Rated capacity within +/-
0.3hz
Not required 0.98 leading/lagging power
factor Disconnection
allowed frequency
outside 58.2-61.8 Hz
Required
Micro RE < =10 kW Rated capacity within +/-
0.3hz
Not required 0.98 leading/lagging power
factor Not required
DESCRIPTION:
PV System – 5,856 units of solar photovoltaic (PV) panels, each rated 255 W peak, connected to 61 units of SMA STP 20000 TLEE-10 inverters, each rated 20 kWp.
Interface Transformer – 400 Volts 3phase line-to-line inverter output to 34.5 kV using 1.5 MVA transformer
Connection – Interconnection to 34.5 kV feeder Balintawak 47E by constructing 30 meters of new 34.5 kV 3-phase line using 1-AWG 3/0 ACSR per phase
Solar Rooftop Project at Quezon City
Vicinity Map of Solar PH
NAME: 1.22 MW SM North EDSA Solar Project
APPLICANT: Solar Philippines Commercial Rooftop Projects Inc. (Solar PH)
LOCATION: Carpark Building Rooftop of SM City North EDSA, 2.5 circuit km away from Balintawak Substation
Case Studies VRE Interconnection
NAME: 54 MW AWOC Wind Farm Project
APPLICANT: Alternergy Wind One Corporation (AWOC)
LOCATION: Sitio Mahapang Sapa, Brgy. Halahayin, Pililia, Rizal
DESCRIPTION:
System – Composed of twenty-seven (27) wind turbine generators with a capacity of 2 MW each
Interface Transformer – 0.69 kV wind turbine generator output to 22 kV and aggregated before finally stepped-up to 115 kV through two (2) 40 MVA power transformers
Connection – Interconnection to Malaya-Teresa Subtransmission 115 kV line
Wind Farm at Pililia, Rizal
Case Studies VRE Interconnection
A key imperative for Meralco in the face of transformative changes in the power industry
Grid Modernization
• SmartGrid – long-term technology roadmap envisioned in 2011
• Smart devices and systems over the distribution network
• Core pillars: ANA and AMI
• Objective: Monitor and manage network operations and assets in real-time to address changing loads, generation, and outage events
Deployment of smart devices and systems over the distribution network
Objective: Real-time monitoring and management of network
operations and assets to address changing loads, generation, and failure
conditions of the distribution system.
Advanced Network Automation (ANA)
Integrated system of smart meters, communications infrastructure,
and back-end systems
Objective: Enable two-way communication between utilities and
customers
Advanced Metering Infrastructure (AMI)
Advanced Network Automation (ANA) Smart Grid Initiatives to support RE integration
Fault Location,
Isolation and Service
Restoration (FLISR) Designed to decrease the
duration of outages and
number of customers affected
Integrated Volt-Var
Optimization
(IVVO) Aims to minimize technical
losses and manage voltage
within acceptable limits
Advanced Distribution Management System Integrated system combining outage and distribution
management system
1
*Future Projects
Intelligent Asset
Management Use of asset condition
sensors and advanced
analytics to optimize asset
utilization
Mobility Use of mobile devices to
accomplish business tasks
2 3
Control Center
Modernization Upgrade of existing system control
center and operations dispatch centers
Substation Automation Upgrade of existing substations in
compliance with latest industry-
standard IEC 61850
4
Power Tech Philippines’ first innovation, research and
development, and technical training facility
featuring a smart grid setup
5
Distributed Energy
Resources (DER)
Integration* Enable effective integration of variable
RE generators and other customer-cited
energy resources
Demand Response (DR)* Programs that encourage change in
customers’ consumption behavior to
reduce peak demand
6
Future Distribution Network
• Similar in major design but manage two
flows of power
• More facilities underground, hardened infra
• More automation, communication between
equipment
• Smarter switches and controllers
• Can integrate widespread distributed
generation and battery energy storage
• Can charge electric vehicle and take power
from it as well
• Advanced demand response
of http://www.ecoissues.ca/Managing_a_complex_energy_system:Smart_Grid
Integrated, optimized, smarter and cleaner
Thank you.
The objective of the distribution system is not only to provide adequate, reliable,
safe and efficient electric service but to deliver clean power as well.
Cautionary statements
This presentation is prepared for the participants of the 42nd IIEE Annual National Convention in Pasay City, Philippines on
November 17 - 19, 2017. This presentation has consequential limitations and the discussion is limited to renewable integration.
The same materials are restricted to the participants and may only be used in conjunction with the presentation held on such
date.
The information contained herein should not be quoted in whole or in part without prior consent of the author. No responsibility
to any third party is accepted as the presentation has not been prepared for and is not intended for any other purpose.
Accordingly, the author makes no representation or assurance that any projected results based on the use of these information
will be realized. Participants should not place undue reliance on these information, though presumed correct at the time of the
presentation.
These information are exposed to various risks and competitive uncertainties and contingencies which are beyond the author’s
control.