Renewable Energy Development Plan
Presented in Japan-Indonesia Business Forum for Energy Efficiency, Conservation and Renewable Energy Hotel Indonesia Kempinski
Jakarta, 14th November 2018
Directorate of Corporate Planning
PT PLN (Persero)
www.pln.co.id |
Content
Electricity Demand Forecast 2
Power Development Plan 3
Fuel Mix Projection 4
Renewable Energy Development Plan 5
Current Renewable Energy Development 1
Renewable Energy Procurement 6
Renewable Energy Investment 7
PLN Company Profile Up to Jan-
55.876
19.065
122.706
49.234
114.631
21.632
14.453
924
6.255
8,50
68.374
Installed Capacity MW 57.469 55.926 54.665 50.859 49.591
Sales GWh 133.440 223.134 21.600 202.846 198.602
Installation
Power Contracted MVA 126.610 122.018 114.266 106.582 100.031
Transmission Lenght kms 50.613 48.901 46.266 41.683 39.910
Substation Capacity MVA 122.370 113.790 108.479 92.651 86.472
Production 151.987 254.403 248.611 233.982 228.553
Own Production GWh 101.856 167.977 166.457 156.631 152.853
Rent GWh 6.339 13.447 17.352 19.841 22.443
Purchase GWh 43.793 72.979 64.802 57.510 53.257
Quality
Network Losses Percentage 9,55 8,76 9,48 9,77 9,71
Number of Customers Thousand
customers 70.019 68.068 64.282 61.157 57.493
www.pln.co.id
| 3
Description Unit Up to Jul
2018 2017 2016 2015 2014
www.pln.co.id |
PLN Electrification Ratio – July 2018
4 Indonesia : 93,3%
www.pln.co.id |
Electrification Ratio
Gorontalo
Information
Electrification Ratio (%)
Realization 2017
www.pln.co.id |
Target of Electrification Ratio in RUPTL (1/2)
No. Provinsi 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
1 Aceh 97,4 99,3 99,9 100,0 100,0 100,0 100,0 100,0 100,0 100,0
2 Sumut 98,9 99,4 99,7 100,0 100,0 100,0 100,0 100,0 100,0 100,0
3 Sumbar 93,5 96,3 99,1 100,0 100,0 100,0 100,0 100,0 100,0 100,0
4 Riau 95,3 97,5 99,8 100,0 100,0 100,0 100,0 100,0 100,0 100,0
5 Kepri 85,1 94,5 98,2 99,9 99,9 100,0 100,0 100,0 100,0 100,0
6 Jambi 88,9 92,2 96,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
7 Bengkulu 96,9 97,9 99,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
8 Sumsel 93,0 96,0 99,1 100,0 100,0 100,0 100,0 100,0 100,0 100,0
9 Babel 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
10 Lampung 94,0 99,2 99,8 100,0 100,0 100,0 100,0 100,0 100,0 100,0
11 Jabar 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
12 DKI 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
13 Banten 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
14 Jateng 98,9 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
15 DIY 94,9 97,9 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
16 Jatim 95,5 98,2 99,8 100,0 100,0 100,0 100,0 100,0 100,0 100,0
17 Bali 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
www.pln.co.id |
Target of Electrification Ratio in RUPTL (2/2)
No. Provinsi 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
18 NTB 93,5 97,5 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
19 NTT 70,0 77,0 84,3 90,1 96,0 99,9 100,0 100,0 100,0 100,0
20 Kalbar 93,3 96,1 99,1 100,0 100,0 100,0 100,0 100,0 100,0 100,0
21 Kalsel 95,0 97,3 99,6 100,0 100,0 100,0 100,0 100,0 100,0 100,0
22 Kalteng 70,4 81,1 85,7 89,9 93,9 97,8 100,0 100,0 100,0 100,0
23 Kaltim 99,4 99,6 99,7 100,0 100,0 100,0 100,0 100,0 100,0 100,0
24 Kaltara 86,3 90,5 95,2 100,0 100,0 100,0 100,0 100,0 100,0 100,0
25 Sulut 97,5 99,0 99,8 99,9 100,0 100,0 100,0 100,0 100,0 100,0
26 Sulteng 91,5 94,9 98,4 99,9 100,0 100,0 100,0 100,0 100,0 100,0
27 Gorontalo 97,4 98,4 99,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
28 Sulsel 99,8 99,9 100,0 100,0 100,0 100,0 100,0 100,0 100,0 100,0
29 Sultra 87,7 90,2 92,6 95,1 97,5 100,0 100,0 100,0 100,0 100,0
30 Sulbar 87,3 89,4 91,6 93,7 95,8 97,9 100,0 100,0 100,0 100,0
31 Maluku 92,6 94,8 96,4 98,2 100,0 100,0 100,0 100,0 100,0 100,0
32 Malut 98,9 99,2 99,6 99,9 100,0 100,0 100,0 100,0 100,0 100,0
33 Papua 65,0 77,7 82,7 87,7 92,7 97,7 100,0 100,0 100,0 100,0
34 Pabar 90,4 93,6 96,8 98,1 98,1 98,2 100,0 100,0 100,0 100,0
Indonesia 96,2 98,0 99,1 99,6 99,8 99,9 100,0 100,0 100,0 100,0
www.pln.co.id | 8
Strategies for Increasing Electrification Ratio
• Developing and monitoring electricity infrastructures projects stated in RUPTL.
• Developing New and renewable energy for remote and isolated areas.
• Encouraging programs of rural electrification in order to achieve 100% rural areas electrified in
2019.
• Enhancing the role of PLN corporate social responsibility (CSR), especially for activities related to
rural electrification.
• Obtaining good corporate relationship with the government for pre-electrification program such as
LTSHE (efficient solar PV lamp) program.
• Working together with local governments in order to develop new and renewable energy projects
and free electricity installment for houses of poor families in all over Indonesia.
www.pln.co.id |
Installed Capacity (June 2018)
www.pln.co.id |
Progress of Renewable Energy Development (June 2018)
www.pln.co.id | 13
Electricity Demand Forecast 2018-2027
EASTERN INDONESIA
INDONESIA
9,1%
35 78
TWhTWh
SUMATERA
JAVA - BALI
6,1%
177 TWh
301 TWh
8,6%
26 TWh
54 TWh 433
TWh
239 TWh
6,86%
11,2%
35 92
TWh TWh
7,2%
174 TWh
326 TWh
10,8%
26 64
TWhTWh
480 TWh
234 TWh
2017 2026 2018 2027
8,3%
10,1% 8,5%
KALIMANTAN
9,9% 8,4%
NUSA TENGGARA
11,7% 8,6%
SULAWESI
12,1% 9,4%
MALUKU
10,5% 8,7%
PAPUA
Notes:
Blue
Red
: RUPTL 2017-2026
: RUPTL 2018-2027
(Bappenas High Scenario)
Comparison Between RUPTL 2017-2026 and RUPTL 2018-2027
www.pln.co.id | 15
TYPE RUPTL 2017-2026 RUPTL 2018-2027
CFPP 31.935 26.807
CC/GT/GE PP 24.389 14.305
HEPP 13.762 8.283
GeoPP 6.290 4.583
Other RE 1.224 2.046
TOTAL 77.873 56.024
The additional
capacity is lower
from previous
RUPTL due to lower
demand growth.
Decrease thermal
power plant,
especially coal fired
power plant.
Increase other
renewable energy
(wind, solar PV etc.)
www.pln.co.id | 16
Electricity Infrastructure Development
REGIONAL SUMATERA
Power Plant 15.990 MW
Transmission 20.947 kms
Substation 39.810 MVA
REGIONAL KALIMANTAN
Power Plant 4.599 MW
Transmission 10.430 kms
Substation 5.810 MVA
REGIONAL SULAWESI
Power Plant 4.849 MW
Transmission 8.269 kms
Substation 7.043 MVA
REGIONAL MALUKU & PAPUA
Power Plant 1.540 MW
Transmission 2.599 kms
Substation 1.920 MVA
REGIONAL JAWA, BALI & NT
Power Plant 29.046 MW
Transmission 21.610 kms
Substation 96.841 MVA
INDONESIA
Power Plant 56.024 MW
Transmission 63.855 kms
Substation 151.424 MVA
www.pln.co. id | 17
Power Plant Development Plan (MW)
www.pln.co.id | 19
Fuel Mix Projection
RE portion in 2018 : 12,4% RE portion in 2025 : 23,0%
Renewable Energy Criteria
www.pln.co.id | 21
1. Supply and Demand Balance
2. System Readiness
3. Financing Capability
4. Economic Feasibility
Renewable Energy Development Strategies
• The development of RE power plants shall consider the balance between supply-demand and the
readiness of the system as well as the cost efficiency.
• PLN will utilize the renewable energy resources from water energy resources, geothermal (which include
small scale/modular), biofuel, wind energy, solar energy, biomass and waste, etc., and will support any
effort to create RE-BID (renewable energy based on Industrial Development).
• Particularly for PV, PLN would develop centralized PV to electrify isolated areas that relatively far from
existing grids. These areas could be undeveloped areas, border areas and outermost islands. Hybrid
system (PV, other RE and Diesel PP) would also be developed for areas that still have less than 12
hours electricity, commonly in the eastern part of Indonesia.
• PLN will develop Smart Grid system to increase penetration of intermiten RE and increase reability of
power system. PLN would also develop micro grid (usually using PV) for the areas where distribution
lines will not be developed in 2-3 years ahead.
• PLN will reduce the use of HSD and MFO and encourage the utilization of biofuel.
www.pln.co.id | 22
www.pln.co.id |
Renewable Energy Development Plan
www.pln.co.id |
Renewable Energy Development Plan per
Regional
Total Reg Sumatera : 5.533,6
MW
Total Reg JBB : 360,7
MW
Total Reg JBT : 4.387,6
MW
Total Reg JTBN : 2.352,3 MW Total Reg Kal : 370,1 MW Total Reg Sul : 1.726,5
MW
Total Reg MP : 180,4
MW
Renewable Energy Price and Cost of Production (BPP) 2017 (cent USD/kWh)
www.pln.co.id | 26 Source: Ditjen EBTKE
www.pln.co.id |
Renewable Energy Procurement
Direct Selection Direct Appointment
PLN HQ PLN Regional
Capacity
> 10 MW
1. PLTA
2. PLTBg
3. PLTBm
4. PLTA
LAUT
5. PLT
HYBRID
Capacity
≤ 10 MW
1. PLTA
2. PLTBg
3. PLTBm
4. PLTA LAUT
5. PLT
HYBRID
PLN HQ PLN Regional
> 1. PLTSa
10MW
2. PLTP
≤ 1. PLTSa
10MW
Capacity
Quota
(Intermittent)
1. PLTS
2. PLTB
Note: for Selected Providers (DPT)
PLN’s Renewable Energy Investment On Going Projects
www.pln.co.id | 30
No. Projects Location COD Lender
On Going Projects
1 Rehabilitation of PLTP Kamojang Unit 2-3 West Java 2020 KfW
2 1000 Islands Renewable Energy for Electrification Programme (REEP) phase I in NTT NTT 2021 KfW
3 PLTA Kumbih-3 (3 x 15 MW) Aceh - North Sumatera 2023 KfW
4 Updates of Feasibility Studies of Small Hydropower Plants in Eastern Indonesia AFD
5 Peusangan Hydroelectric Power Plant Construction Project Aceh 2020-2021 JICA
6 Asahan No. 3 Hidroelectric Power Plant Construction Project North Sumatera 2023-2024 JICA
7 Hululais Geothermal Power Plant Project (E/S) Bengkulu 2020-2021 JICA
8 Tulehu Geothermal Power Plant Project (E/S) Maluku 2020 JICA
9 FS and Preparation of Design and Bid Documents for Matenggeng Pumped Storage
Power Project and related Capaicty Building Central Java 2025 World Bank
PLN’s Renewable Energy Investment Pipeline Projects
www.pln.co.id | 31
* and many more renewable energy development with unallocated funding
No. Projects Location COD Lender
Pipeline Projects
1 PLTP Ulumbu 5 (1x10 MW) & Mataloko 2-3 (2x10 MW) Flores NTT 2021-2023 KfW
2 Sector Loan (PLTA Bakaru+REEP II) South Sulawesi 2019-2024 KfW
3 PLTA Sawangan (2X6 MW) North Sulawesi 2024 KfW
4 PLTM Nua (2X4,4 MW) Seram Maluku 2020 KfW
5 Masang II Hydro Power Plant Development West Sumatera 2023 AFD
6 Hululais Geothermal Power Plant 1 & 2 (2x55 MW) Bengkulu 2020-2021 JICA
7 Additional Loan for Peusangan 1 & 2 Hydroelectric Power (87 MW) Aceh 2020-2021 JICA
8 Matenggeng Pumped Storage Central Java 2025 World Bank
9 PLTA Poko (2x65 MW) South Sulawesi 2022 World Bank
New and Renewable Energy (NRE) Investment
www.pln.co.id | 32
1. Total investment for the new and renewable energy (NRE) in RUPTL 2018-2027 is
about USD 30 billion, accounted for 32% from the total power plant investment*.
2. PLN encourage private developers to develop NRE, with 77% of those investment
was IPP projects.
3. It’s expected that NRE investment will be cheaper in the future, to reduce electricity
production cost.
4. Government and Lending institutions will have more important roles to reduce the
financing cost to have cheaper investment of NRE.
5. PLN and private developers should have easy access to the cheaper Green Climate
Fund to support NRE development.
6. In the mean time, PLN will continue to strengthen the grid to give more opportunity
for the NRE in the electricity system.
*PLN+IPP investment