reliability, availability, maintainability and safety (rams ... · keymile umux; network components...

44
2014 ARS, Europe: Paris, France Red Room, Session 5 Reliability, Availability, Maintainability and Safety (RAMS) - Application for Self-Contained Power Supply of Gotthard Base Railway Tunnel Dr. Andreas van Linn Amstein+Walthert Progress Andreasstrasse 11 8050 Zürich Begins at 3:30 PM, Wednesday, April 23rd

Upload: vuminh

Post on 12-Apr-2018

221 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

2014 ARS, Europe: Paris, FranceRed Room, Session 5

Reliability, Availability, Maintainability and Safety (RAMS) - Application for

Self-Contained Power Supply of Gotthard Base Railway Tunnel

Dr. Andreas van LinnAmstein+Walthert ProgressAndreasstrasse 118050 Zürich

Begins at 3:30 PM, Wednesday, April 23rd

Page 2: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

PRESENTATION SLIDESPRESENTATION SLIDESThe following presentation was delivered at the:

International Applied Reliability Symposium, EuropeApril 23 - 25, 2014: Paris, France

http://www.ARSymposium.org/europe/2014/

The International Applied Reliability Symposium (ARS) is intended to be a forum for reliability and maintainability practitioners within industry and government to discuss their success stories and lessons learned regarding

the application of reliability techniques to meet real world challenges. Each year, the ARS issues an open"Call for Presentations" at http://www.ARSymposium.org/europe/presenters/index.htm and the presentations

delivered at the Symposium are selected on the basis of the presentation proposals received.

Although the ARS may edit the presentation materials as needed to make them ready to print, the content of the presentation is solely the responsibility of the author. Publication of these presentation materials in the

ARS Proceedings does not imply that the information and methods described in the presentation have been verified or endorsed by the ARS and/or its organizers.

The publication of these materials in the ARS presentation format is Copyright © 2014 by the ARS, All Rights Reserved.

Page 3: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 2Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Agenda

Project - Introduction 5 min

Requirements 10 min

Reliability Prediction 20 min

RAMS - Life Cycle Management 10 min

Conclusion 5 min

Questions 10 min

Introduction Requirements Life Cycle ConclusionReliability

Page 4: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 3Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project - Introduction

Introduction Requirements Life Cycle ConclusionReliability

© AlpTransit Gotthard AG

Gotthard Base Tunnel

Page 5: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 4Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project - Introduction

Gotthard Base Tunnel North portal: Erstfeld

South portal: Bodio

2 x 57 km single-track tubes

Crossways all 325 m

Considering all connecting tunnels, the system length measures 152 km

Rock cover: 2300 m

2 x multifunctional sites (MFS)

with emergency stops

Introduction Requirements Life Cycle Conclusion

© AlpTransit Gotthard AG

Reliability

Page 6: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 5Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project - Introduction

Introduction Requirements Life Cycle ConclusionReliability

© AlpTransit Gotthard AG

The first flat trajectory railway through the Alps

Page 7: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 6Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project - Introduction

Introduction Requirements Life Cycle ConclusionReliability

Tunnel System of the Gotthard Base Tunnel

© AlpTransit Gotthard AG

Emergency stop

Emergency stop

Shaft Shaft

Multifunctional site (MFS)

Multifunctional site (MFS)

Access tunnel

Cable tunnel

Access tunnel

Intermediate excavationand shafts Sedrun

Crossway

Page 8: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 7Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project - Introduction

Organisation

Operator: SBB AG

Client: Alp Transit Gotthard AG

General contractor rail-engineering: Transtec Gotthard:

General partner:

Alpiq Alcatel-Lucent/Thales Renaissance Construction Balfour Beatty Rail

Introduction Requirements Life Cycle ConclusionReliability

Page 9: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 8Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project - Introduction

Maintenance Group / Lot

Introduction Requirements Life Cycle Conclusion

Sub-Contractor Area of Expertise

Sub-Arge BBR / RC

Rail track

Power supply 50 Hz and cables

Sub-Arge BBR / K+M

Rail power supply 16.7 Hz

Sub-Arge ALU / TRSS

Signalling, control andcommunication

Reliability

Page 10: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 9Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Project Partner

Introduction Requirements Life Cycle Conclusion

Company Area of Expertise Service Package (LP)Andrew Radio communicaton LP70

Avesco No Break LP22; LP40

Ascom Service communication (BKA) LP61

Hirschmann Access; telecommunication LP61

Keymile UMUX; network components LP80; LP81; LP82; LP83

ABB Secheron Medium-high voltage LP40

Siemens Control system; IT LP60

Swisscom Solutions Cisco; network components LP61

Leoni-Studer Cable systems LP22; LP40; LP41; LP42; LP43; LP44

Swibox Electrical connection cabinets LP45

Pöyry Planning-coordination, management support LP10

Grunder Ingenieure Survey and mapping LP30; LP31; LP32; LP33

ABB Schweiz Transformer LP40

Planning, RAMS, PQM,… LP40; LP41; LP42; LP43; LP44; LP45; LP46; LP47

Scheuchzer Realisation LP30; LP31

Alpha Plan Planning LP40; LP41; LP42; LP43; LP44; LP45; LP46; LP47

Hefti, Hess, Martignoni Planning; consulting LP40; LP41; LP42; LP43; LP44; LP45; LP46; LP47; LP22

Reliability

Page 11: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 10Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Requirements According To Reliability

Introduction Requirements Life Cycle ConclusionReliability

Based on EN 50126:

Railway applications –

The specification and demonstration of

Reliability, Availability, Maintainability and

Safety (RAMS)

Page 12: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 11Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Requirements According To Reliability

Introduction Requirements Life Cycle Conclusion

Rail Track 50Hz and Cables

Rail Power Supply 16,7Hz

TC-Fixed Network

TC-Radiocom.

Safety Devices

Complete System – Railway Technology

Disturbance rate per year

Disturbance Class (SK)

SK 1 SK 2 SK 3 SK 4

40 20 5 0.4

Rail System

Switch Points

Switchgear panels

Cable systems

El. Lighting

El. Cabinets

Signs

Handrail

Overhead contact lines and cables

Switching Stations

Control and comm. sytem

El. grounding

Protective section north

Tunnel controlsystem

Data network

Service comm.

TC- Radiocomm. Railway controlsystem

ETCS Level 2

Train control andcomm. system

Reliability

Page 13: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 12Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Disturbance Classes (SK)

Definition of disturbance classes 1-4

Factors

Influence on train’s schedule

Elimination with/without intervention on trail

Blocking of route sections

Introduction Requirements Life Cycle ConclusionReliability

© AlpTransit Gotthard AG

Page 14: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 13Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Disturbance Classes

Introduction Requirements Life Cycle Conclusion

Class Influence On Railway System Example

1 No longer than 1h influence on timetable stability. The sum of delays of directly affected trains is less than 10 minutes.

• Emergency braking of a train because of system failure.

• Local outage of GSM-R for one minute.

2 More than 1h influence on timetablestability. The sum of delays of directly affected trains is more than 10 minutes.

• Disturbance of wheel-countingapparatus driving on sight.

3 Immediate blocking of one track sectionas result of failure or for fault repair.

• Switch points not in final position and impassable.

• Railbreakage (ultrasonic failure).• Enduring outage of overhead

contact line.

4 Immediate blocking of more than one track sections (one track) or total blocking (both tracks).

• Total failure of signalling / safetydevices

• Total outage of GSM-RReliability

Page 15: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 14Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Requirements for 50Hz and Cable

Introduction Requirements Life Cycle Conclusion

Subsystem Availability1: Standard power supply centre Sedrun

(medium voltage) 99.941 %

2: Standard power supply centre Sedrun(low voltage)

99.936 %

3: Standby power supply centre Sedrun(low voltage)

99.937 %

4: Standard power supply transverse tunnel(low voltage)

99.852 %

5: Standby power supply transverse tunnel(low voltage)

99.976 %

Reliability

Page 16: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 15Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

ReliabilityIntroduction Requirements Life Cycle Conclusion

Example: Subsystem 3

Circuit Breaker

Transformer

Static Transfer System (STS)

FuseConsumer Load

No Break Diesel:Uninterruptible Power Supply (UPS)

Cables

Page 17: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 16Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Requirements

Additional requirements on Maintainability

o Based on maintainability concepts of SBB

Safetyo Based on Quantitative Risk Analyses (QRA) from SBB

Introduction Requirements Reliability Life Cycle Conclusion

Page 18: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 17Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Reliability Prediction

The basic principle of reliability prediction and integration of single results of one Subsystem into the complete tunnel system is described. This includes:

o Basic component data

o RAM-interfaces

o Reliability calculations

o Disruption protocol

The bottom up approach

The Causer principle

Introduction Requirements Reliability Life Cycle Conclusion

Page 19: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 18Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Reliability Prediction

Introduction Requirements Reliability Life Cycle Conclusion

1 Components 2 RAM-interfaces

3 Reliability calculation

singlefailures

single & multiple failures

additional failures

singlefailures

failures

4 Disruption protocol

singlefailures; SK

Bottom

Up

Page 20: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 19Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Bottom

Up

Components – Single Failure List

Introduction Requirements Reliability Life Cycle Conclusion

2 RAM-interfaces

3 Reliability calculation

singlefailures

single & multiple failures

additional failures

singlefailures

failures

4 Disruption protocol

singlefailures; SK

1 Components

Page 21: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 20Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Up

Bottom

Components – Single Failure List

Circuit Breaker

Transformer

Static Transfer System (STS)

Fuse

No Break Diesel:Uninterruptible Power Supply (UPS)

Describe Failure Mode, Cause, Effects

Certificate Producer Specifications

Benchmarks

Statistics

Basic Data MTBF (Mean Time Between Failure)

MTTR (Mean Time To Repair)

Introduction Requirements Reliability Life Cycle Conclusion

Page 22: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 21Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Up

Bottom

Components – Basic Data

No Break Diesel:Uninterruptible Power Supply (UPS)

Example 1:Certificate

Producer Specifications

Basic Data

MTBF [a] = 42.2

MTTR [h] = 8

Introduction Requirements Reliability Life Cycle Conclusion

Page 23: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 22Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Up

Bottom

Components – Basic Data

Example 2:Certificate

Producer Specifications

Basic Data

MTBF [h] = 2.5 10+6

MTTR [h] = 4

Introduction Requirements Reliability Life Cycle Conclusion

Static Transfer System (STS)

Page 24: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 23Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

RAM-Interfaces

Bottom

Up

1 Components

3 Reliability calculation

singlefailures

single & multiple failures

additional failures

singlefailures

failures

4 Disruption protocol

singlefailures; SK

2 RAM-interfaces

ReliabilityIntroduction Requirements Life Cycle Conclusion

Page 25: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 24Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

RAM-Interfaces - Matrix

Introduction Requirements Reliability Life Cycle Conclusion

• High complexity • Hundreds of technical interfaces

Page 26: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 25Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

RAM-Interfaces - Causer Principle

Introduction Requirements Reliability Life Cycle Conclusion

• Investigate each component failure and combinations (source) on the effect of each consumer (sink).

• Determine disruption class. • Protocol in RAM-interfaces lists.

Page 27: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 26Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

1 Components

RAM-Interfaces – Example

Introduction Requirements Reliability Life Cycle Conclusion

3 Reliability calculation

4 Disruption protocol

singlefailures

single & multiple failures

failures

additional failures

singlefailures; SKsingle

failures

2 RAM-interfaces

ID

Source

Sink

Single or combined failures

Location Failure mode

Cause

Effect

Criticality disruption class

(Failure mode, effects and criticality analysis) FMECA

Page 28: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 27Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Reliability Calculation

Bottom

Up

1 Components 2 RAM-interfaces

singlefailures

single & multiple failures

additional failures

singlefailures

failures

4 Disruption protocol

singlefailures; SK

3 Reliability calculation

Introduction Requirements Reliability Life Cycle Conclusion

Reliability Block Diagrams (RBA)

Page 29: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 28Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Bottom

Up

Reliability Calculation – Basic Formula

Reliability Availability

In Series

www.eventhelix.com

Introduction Requirements Reliability Life Cycle Conclusion

Page 30: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 29Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Bottom

Up

Reliability Calculation – Basic Formula

In Parallel

www.eventhelix.com

Introduction Requirements Reliability Life Cycle Conclusion

Page 31: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 30Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Up

Bottom

Reliability Calculation – Basic Formula

Considering Common Cause Failures in Parallel Systems

Determine β-factor according to (61508-6 © IEC:2010)

Introduction Requirements Reliability Life Cycle Conclusion

Page 32: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 31Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Bottom

Up

Reliability Calculation – Basic Formula

Considering Common Cause

Failures in Parallel Systems

β = 1 %

Example: R1=R2=R

Introduction Requirements Reliability Life Cycle Conclusion

Page 33: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 32Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Bottom

Up

Disruption Protocol

1 Components 2 RAM-interfaces

3 Reliability calculation

singlefailures

single & multiple failures

additional failures

singlefailures

failures singlefailures; SK

4 Disruption protocol

Introduction Requirements Reliability Life Cycle Conclusion

Page 34: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 33Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Disruption Protocol

Introduction Requirements Reliability Life Cycle Conclusion

Description

Location

Source function

Interfaces

Source lot

ID

1 row for each source – sink –interface with disturbance class > SK0

Page 35: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 34Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Disruption Protocol

Introduction Requirements Reliability Life Cycle Conclusion

FMECA

Failure mode

Cause

Effect

Criticality disruption class

Detection

Interfaces sink

Page 36: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 35Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Disruption Protocol

Introduction Requirements Reliability Life Cycle Conclusion

Disruption Rate

Failure rate per Element/Subsystem

Quantity Total failure rate [1/h]

MTTR

Total failure rate [1/a]

Availability

∑ of all rowsbelonging to thesame disturbanceclass (SK1-4): Total

Disruption rate per SK forrailway technique

Page 37: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 36Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

RAMS - Life Cycle Management

It is not only the prediction of reliabilities but also the monitoring of the project from a RAMS point of view during the whole life cycle of the GBT.

The management comprises:

o Verification

o Validation

o Integration of RAMS-process into the general project management to practically use synergy

effects.

Introduction Requirements Life Cycle ConclusionReliability

Page 38: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 37Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

RAMS - Life Cycle Management

Introduction Requirements Life Cycle Conclusion

V-Modell

operation

1 Concept

2 System definition

3 Risk analysis

4 System requirements

5 Assignment

6 Construction 8 Installation

9 System validation

10 Approval; acceptance

11 Operation; maintenance 14 Suspension; disposal

7 Fabrication

12 Capture performance

13 Change; retrofiting

Reliability

Page 39: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 38Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Verification - Validation

Introduction Requirements Life Cycle Conclusion

V-ModellV-Modell

operationoperation

1 Concept

2 System definition

3 Risk analysis

4 System requirements

5 Assignment

6 Construction 8 Installation

9 System validation

10 Approval; acceptance

11 Operation; maintenance 14 Suspension; disposal

7 Fabrication

12 Capture performance

13 Change; retrofiting

Specification Validation

Verification

Implementation

Reliability

Page 40: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 39Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

RAMS - Other Management Systems

Introduction Requirements Life Cycle ConclusionReliability

RAMS

ServiceabilityOperating system

ValidationQualityProject specific

PQM

RAMSOperating system

Supporting Systems:• FRACAS (Failure Reporting, Analysis and Corrective Action System)

• MSMT(Maintenance Service Management Tool)

• Risk Management

Page 41: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 40Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Conclusion

Project still ongoing.

High complexity.

Different calculation methods (Fault Tree Analysis - FTA, ReliabilityBlock Diagram – RBD,…) for different subsystems / lots.

Not one calculation model for the whole system.

Quantities are implicitly resolved by the interfaces analysis and the Causer Principle.

Requirements for reliability (50Hz and cable system) met by direct RBD calculations.

RAMS is one management system in addition to others, but each with its own focus.

Use synergies with PQM, Validation,…

Introduction Requirements Life Cycle ConclusionReliability

Page 42: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 41Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Outlook

Application of the RAMS method is also interesting in fields other than railway engineering.

Data centers

Roads

Research

Introduction Requirements Life Cycle ConclusionReliability

Page 43: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 42Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Contact

Andreas van Linn

Dr.-Ing.

Senior Consultant, Risk Management

Amstein + Walthert Progress AG

Andreasstrasse 11, Postfach, CH-8050 Zürich

[email protected]

Introduction Requirements Life Cycle ConclusionReliability

Page 44: Reliability, Availability, Maintainability and Safety (RAMS ... · Keymile UMUX; network components LP80; LP81; LP82; LP83 ABB Secheron Medium-high voltage LP40 Siemens Control system;

Dr. Andreas van Linn, Amstein+Walthert Progress Slide Number: 43Session 5Red Room Ap

plie

d R

elia

bili

ty S

ymp

osi

um

, E

uro

pe

2014

Questions

Thank you for your attention.

Introduction Requirements Life Cycle ConclusionReliability

Do you have any questions