reliability and renewables: two case studies using the superopf tim mount department of applied...

28
RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University [email protected] DoE Visualization and Controls Peer Review 1

Upload: beverly-gibson

Post on 28-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

RELIABILITY and RENEWABLES:Two Case Studies Using the SuperOPF

Tim Mount

Department of Applied Economics and ManagementCornell University [email protected]

DoE Visualization and Controls Peer Review

1

Page 2: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

OBJECTIVE AND OUTLINE OBJECTIVE

– To demonstrate how the analytical capabilities of the SuperOPF can provide new insight into system planning:• The objective criterion is consistent for evaluating both Operating Reliability and System Adequacy on an AC network,• Equipment failures (contingencies) are considered explicitly, and reliability problems (e.g. shedding load) typically occur first in these

contingencies,• Levels of reserve generating capacity are determined endogenously and change as system conditions change.

OUTLINE– Case Study on Reliability:

• Increase peak load holding system capacity constant until reliability standards fail,

– Case Study on Renewables:• Add new wind capacity to replace existing coal capacity keeping load constant,

– Next Steps for Research:• Evaluate the implications of electrifying more energy services (e.g. transportation)

2

Page 3: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Contributors to the Case Studies

Lindsay Anderson Judy Cardell Alberto Lamadrid Surin Maneevitjit Tim Mount Robert Thomas Ray Zimmerman

3

Page 4: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

CASE STUDY #1: RELIABILTY

Increase Peak System Load Holding Network Capacity Constant on the 30-Bus Test Network

4

Page 5: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

30-BUS NETWORK

Area 1- Urban- High Load- High Cost- VOLL = $10,000/MWh

Area 3- Rural- Low Load- Low Cost- VOLL = $5,000/MWh

Area 2- Rural- Low Load- Low Cost- VOLL = $5,000/MWh

5

Page 6: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Contingencies Considered

Number Probability 0 = base case 95% 1 = line 1 : 1-2 (between gens 1 and 2, within area 1) 0.2% 2 = line 2 : 1-3 (from gen 1, within area 1) 0.2% 3 = line 3 : 2-4 (from gen 2, within area 1) 0.2% 4 = line 5 : 2-5 (from gen 2, within area 1) 0.2% 5 = line 6 : 2-6 (from gen 2, within area 1) 0.2% 6 = line 36 : 27-28 (main tie from area 3 to area 1) 0.2% 7 = line 15 : 4-12 (main tie from area 2 to area 1) 0.2% 8 = line 12 : 6-10 (other tie from area 3 to area 1) 0.2% 9 = line 14 : 9-10 (other tie from area 3 to area 1) 0.2% 10 = gen 1 0.2% 11 = gen 2 0.2% 12 = gen 3 0.2% 13 = gen 4 0.2% 14 = gen 5 0.2% 15 = gen 6 0.2% 16 = 10% increase in load 1.0% 17 = 10% decrease in load 1.0%

6

Page 7: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

The Underlying Rationale for Doing this Case Study

Area 1 represents an urban load pocket with high load, high cost generation, and high VOLL.

Areas 2 and 3 represent rural areas with low load, low cost generation, and low VOLL.

Transmission capacity into Area 1 from Areas 2 and 3 is relatively limited.

An economic dispatch would use generation in Areas 2 and 3 as much as possible and use generating capacity in Area 1 for reserves to maintain operating reliability (e.g. guard against failure of the tie lines into Area 1).

In this Case Study, operating costs remain constant, offers equal the true marginal costs, and all loads in Area 1 are increased in increments until things start to go wrong (i.e. load shedding occurs at one or more nodes in one or more of the contingencies).

7

Page 8: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Nodal Prices for GeneratorsPrice Differences are Caused by Congestion

Expected Nodal Prices (Generators)

20

30

40

50

60

70

80

90

0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50 1.60

Scale Factor for Load

$/MWhr

G1G2G3G4G5G6

$90/MWh

$20/MWh

Higher Load in the Load Pocket (Region 1) ->

8

Page 9: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Nodal Prices for LoadsHigh Prices in Area 1 (blue) are Caused by Load Shedding

--- A Very Localized Effect at a Single Node

$10,000/MWh

$10/MWh

Higher Load in the Load Pocket (Region 1) ->

9

Page 10: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

The Expected Cost of Lost Load(Weighted by the Probability of Each Contingency Occurring)

Higher Load in the Load Pocket (Area 1) ->

Problems show up first in contingencies as system load increases.The capacity of Line 10 in Area 1 is the binding constraint.

Con

tinge

ncy

$4,500/MWh

$0/MWh

10

Page 11: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

The Question for Planners: Will it Pay to Increase the Capacity of Line 10 over a Year?

1. Load Shedding and Congestion Payments to an ISO (i.e. High Prices) may only occur for a Few Hours each year.

2. Some of the time (30%), Loads pay the True Marginal Cost of Energy.

3. Net Revenues for Generators may be a substantial part of the total cost for Loads

11

Page 12: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Conclusions: Case Study 1 on Reliability

The analytical framework of the SuperOPF can be used to evaluate PLANNING (System Adequacy) and REAL-TIME DISPATCH (Operating Reliability).

Using the SuperOPF, it is possible to identify the LOCATION of weaknesses on the network and to determine the net economic benefit of upgrading the network.

A large part of the economic benefit of adding new capacity to a network may be to AVOID SHEDDING LOAD when credible contingencies occur (e.g. N-1 contingencies).

Weaknesses in System Adequacy tend to occur first in contingencies when the system load is high, and for most of the time over a year, reliability standards are not violated.

The economic effects (i.e. high nodal prices) of failing to meet reliability standards are often spatially limited to specific loads rather than affecting nodal prices throughout the network.

12

Page 13: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

CASE STUDY #2: RENEWABLES

Replacing Coal Capacity with Wind Capacity on the 30-Bus Test Network

13

Page 14: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

30-BUS NETWORK

Area 1- Urban- High Load- High Cost- VOLL = $10,000/MWh

Area 3- Rural- Low Load- Low Cost- VOLL = $5,000/MWh

Area 2- Rural- Low Load- Low Cost- VOLL = $5,000/MWh

Wind Farm

Improved Tie Line

14

Page 15: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

The Underlying Rationale for Doing this Case Study

Area 1 represents an urban load pocket with high load, high cost generation, and high VOLL.

Areas 2 and 3 represent rural areas with low load, low cost generation, and low VOLL.

Transmission capacity into Area 1 from Areas 2 and 3 is relatively limited.

Replace 35MW of coal capacity by 105MW of wind capacity at Generator 6 (Area 2) in increments.– Case 1: Initial network capacity– Case 2: Upgrade tie line from Area 2 to Area 1

15

Page 16: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Wind Scenarios Considered

Forecasted

Wind Speed

Probability of Forecast

Output(% of MW Installed)

Output Probability(Conditional on Forecast)

LOW

(0-5 m/s)

11%

0% 66%

7% 26%

33% 5%

73% 3%

MEDIUM

(5-13 m/s)

46%

6% 24%

38% 20%

62% 18%

93% 38%

HIGH

(13+ m/s)

43%

0% 14%

66% 4%

94% 3%

100% 79%

16

Page 17: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Contingencies Considered

97%

3%

All Equipment Failures are Specified at the Lowest Realization of Wind

17

Page 18: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Total Non-Wind Reserves (in different cases)

Case 1: Base Case Case 2: Tie Line L15 upgraded(Tie line between Area 1 and Area 2)

More Wind Capacity More Wind Capacity Optimum Levels of Up and Down Generating Reserves are Determined Endogenously and Increase when Additional Wind Capacity is Installed

18

Page 19: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Production Costs per MW of Load Served (in different cases)

Case 1: Base Case Case 2: Tie Line L15 upgraded(Tie line between Area 1 and Area 2)

More Wind Capacity More Wind Capacity Savings in Fuels Costs are Larger than the Increase in Costs for Reserves when Additional Wind Capacity is Installed

19

Page 20: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Annual Values (0% wind)(High Ranked System Load Low)

Expected Annual Value Case 1 ( 0% Wind penatration)

-$5,000

$195,000

$395,000

$595,000

$795,000

$995,000

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100

$

GenCost (0%) c1 GenNET (0%) c1 WindNET (0%) c1 Conges (0%) c1

Expected Annual Value Case 2 ( 0% Wind penatration)

-$5,000

$195,000

$395,000

$595,000

$795,000

$995,000

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100

$

GenCost (0%) c2 GenNET (0%) c2 WindNET (0%) c2 Conges (0%) c2

20

Page 21: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Annual Vales (100% wind)(High Ranked System Load Low)

Expected Annual Value Case 1 (100% Wind penatration)

-$5,000

$195,000

$395,000

$595,000

$795,000

$995,000

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100

$

GenCost (100%) c1 GenNET (100%) c1 WindNET(100%) c1 Conges (100%) c1

Expected Annual Value Case 2 ( 100% Wind penatration)

-$5,000

$195,000

$395,000

$595,000

$795,000

$995,000

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100

$

GenCost (100%) c2 GenNET (100%) c2 WindNET(100%) c2 Conges (100%) c2

21

Page 22: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Maximum capacities dispatched at the peak system load

Case1 ---->

Case2 ---->

0%wind 100%wind 0%wind 100%wind

Gen1 36.37% 43.83% 44.09% 42.71%

Gen2 50.39% 77.89% 45.79% 78.46%

Gen3 99.75% 100.00% 100.00% 100.00%

Gen4 84.36% 89.37% 77.95% 82.98%

Gen5 100.00% 100.00% 100.00% 100.00%

Gen6 96.50% 100.00% 100.00% 100.00%

Wind 0.00% 73.42% 0.00% 91.76%

For most Non-Wind Generators, MORE capacity (energy + up reserves) is needed to meet the peak system load

when more wind capacity is installed (RED is an INCREASE or the same as 0% wind)

Page 23: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Annual Capacity Factors

Case1 ---->

Case2 ---->

0%wind 100%wind 0%wind 100%wind

Gen1 0.01% 0.02% 0.01% 0.02%

Gen2 0.04% 0.27% 0.03% 0.24%

Gen3 59.62% 36.04% 59.73% 40.61%

Gen4 57.00% 44.62% 56.60% 29.80%

Gen5 39.65% 24.20% 39.45% 24.59%

Gen6 63.94% 34.46% 64.34% 36.74%

Wind - 56.18% - 60.31%

For Non-Wind Generators in Areas 2 and 3, the capacity factors areLOWER when more wind capacity is installed (RED shows a

DECREASE), and the capacity factors for Gen1 and Gen2 in Area 1 are always very low.

Page 24: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Expected Annual Net Benefits(Changes from the Initial Conditions)

CASE 1 CASE 1 CASE 2 CASE 2

0% wind 100% wind 0% wind 100% wind

Level Change from Case 1 with 0% wind

Total Operating Costs $8,224,612 -$4,157,884 -$31,095 -$4,557,138

Gen Net Rev (14) $14,172,181 -$9,337,862 $256,922

-$10,513

,825

Wind Net Rev (15) $0 $706,233 $0 $2,559,206

Congestion (16) $711,575 $2,088,313 -$652,893 -$1,092,187

Consumer Surplus (17) DD – Load Paid* $10,701,201 $427,066 $13,603,945

Total Surplus(14)+(15)+(16)+

(17) $4,157,886 $31,095 $4,557,139

*DD = Sum (Loads Served x VOLL)

Page 25: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Conclusions:Case Study 2 on Renewables

The analysis of the peak system load for different levels of wind penetration show that total production costs decrease as wind capacity increases, particularly if the tie line is upgraded.

The annual net benefit for the system (total annual surplus) increases with more wind capacity and with the tie line upgrade (the change in this value should be greater than the annualized cost of an investment for it to be economically viable).

Adding more wind capacity displaces a high proportion of the conventional generation when system loads are low and also reduces average market prices substantially.

The net earnings of conventional generators fall substantially with more wind capacity, particularly if the tie line is upgraded, and it is likely that additional sources of revenue would be needed to keep them financially viable (e.g. to pay for reserve generating capacity).

Upgrading the tie line eliminates congestion payments to the System Operator, and additional sources of revenue would be needed to pay for transmission.

Customers and wind generators benefit a lot from more wind capacity and the tie line upgrade but there will be other bills to pay for transmission etc.

25

Page 26: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Next Steps for Research

Renewables, Distributed Energy Resources, Electric Vehicles and Storage

26

Page 27: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Likely Implications for the Transmission Grid in the Transition to a Low-Carbon Economy

Electricity will displace Fossil Fuels for Delivering Energy Services (e.g. PHEVs and Ground-Source Heat Pumps).

Wind and Solar (+ Nuclear and Carbon Capture and Sequestration) will be Major Sources of Energy for Generating Electricity.

Storage Devices, including Batteries in PHEVs and Thermal Storage, will be needed to compensate for the Intermittent Supply from Renewable Sources.

Distributed Energy Resources and Controllable Loads will be More Important Components of the Electric Delivery System and Require SmartGrid Capabilities on MicroGrids.

Aggregators will act as Single Customers on the Bulk Power Grid at the Substation/MicroGrid Level.

27

Page 28: RELIABILITY and RENEWABLES: Two Case Studies Using the SuperOPF Tim Mount Department of Applied Economics and Management Cornell University tdm2@cornell.edu

Goals for Research Next Year

Primary Goals• To determine how renewable sources of energy such as wind and solar power

can be integrated into a transmission network effectively using portfolios of controllable load and storage.

• To develop an analytical framework that can evaluate the system and financial implications of establishing a more decentralized electric delivery system based on a bulk power network supporting microgrids.

Approach• Two problems emerged in the current case study of adding wind capacity that

need to be addressed by designing appropriate economic incentives:• 1) Paying for reliability (i.e. making conventional generators financially viable).• 2) Paying for transmission upgrades when congestion payments to the System Operator are reduced.

• Compare coupling wind capacity with local storage and the use of controllable loads, storage, PHEVs and other distributed resources to complement generation from renewable resources (use typical weeks rather than typical hours).

• Demonstrate how transmission and distributed energy resources can both improve reliability and lower system operating costs (reduce the system peak).

• These objectives are compatible with the capabilities of an enhanced SuperOPF.

28