Redwood Heights Stage 2 Update

Citizen’s Advisory Committee June 28, 2016

Page 2: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Outline • Engineering Servicing • Transportation Study • ALC Inclusion/Exclusion Application • Potential Land Use Changes • Outstanding Items • Timeline

Page 3: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Engineering Servicing Update

• Stage 1 Complete October 2013 • Prepare ToR for Stage 2 July 2014 • Consultant Retained for Stage 2 March 2015 • Draft Servicing Report Submitted April 2016 • Revised Draft Servicing Report July 2016

Page 4: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Water Servicing • Limited water infrastructure exists in the

NCP area. • Water supply is from the Grandview

pump station and reservoir on 24 Ave / 168 St.

• To service the NCP area, new feeder mains, distribution mains and pressure zone boundaries are required.

Page 5: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

• New feeder mains are required along 24 Ave for the 142m and 110m pressure zones.

• 142m Zone is supplied by Grandview Pump

Station and Grandview Reservoir.

• 110m Zone is supplied by the Grandview Reservoir.

• 90m Zone is supplied by the 110m Zone via PRVs.

Water Servicing

Page 6: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

• No existing sanitary sewer infrastructure in the NCP area.

• To service the NCP area, a network of gravity sewers, a pump station, a force main and an interceptor are required.

• Based on topography, the pump station will also service areas outside the NCP (shown in grey)

Sanitary Sewer Servicing

Page 7: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

• The NCP area is currently serviced by open ditches and culverts, typical of rural and agricultural areas.

• The existing system conveys stormwater to the Nicomekl River lowlands, to the north.

• A servicing plan has been developed to: – Protect downstream lands from prolonged flooding – Protect receiving watercourses from erosion – Maintain base flows in creeks – Maintain water quality in creeks, ditches and storm systems – Safely convey runoff to large river systems – Protect the natural environment adjacent to watercourses

Stormwater Management

Page 8: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Stormwater Management • 5 stormwater catchments • 4 stormwater catchments require detention ponds • To mitigate the increase in impervious surface

runoff, infiltration measures are required, such as: – pervious pavement – absorbent lawns – vegetated buffer strips – road infiltration trenches

• To help maintain water quality, the follow BMPs are recommended:

― inlet sumps ― oil-water separators ― water quality swales

Page 9: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Draft Cost Estimate

Servicing Type

Stage 1 Cost Estimate

(2013)

Stage 2 Draft Cost Estimate

(2016) Change in Cost

Stormwater $36,240,000 $36,660,000 $420,000

Sanitary Sewer $22,260,000 $17,330,000 -$4,930,000

Water $13,770,000 $10,580,000 -$3,190,000

Total $72,270,000 $64,570,000 -$7,700,000

Page 10: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Engineering Servicing - Next Steps

Finalize servicing strategies for water, sanitary sewer and stormwater.

Update cost estimates, based on any changes to the servicing strategies.

Identify any interim scenarios, if development may occur in advance of any infrastructure improvements.

Identify any DCC shortfalls attributed to servicing the NCP area and consider funding mechanisms to address the shortfalls.

Page 11: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

TRANSPORTATION STUDY: Traffic Modelling Additional traffic modelling initiated in May

of 2016, for additional consultant services that will extend beyond the Redwood Heights NCP area;

Traffic model will forecast the fully developed scenario and expand the study area to identify traffic impacts the developed area will have on the City and Provincial road networks;

Results of the additional work will delay the completion of the NCP, but will allow staff to complete the Stage 2 component of the Redwood Heights NCP.

Page 12: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Potential Land Use Changes Land Use amendments may be required surrounding Highway 15 Corridor depending on Transportation study Outcome and Ministry of Transportation input? Key areas of possible changes may include:

Area surrounding 24 Ave and Highway 15;

Areas surrounding Highway 15;

Areas near proposed Intersections along Highway 15

Page 13: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

ALC Inclusion/Exclusion: App # 15-0093 Excluded ALR

Included ALR

-Potential for future NCP Boundary Adjustment -Potential Changes to NCP Land Use Concept Plan -Potential for Servicing Strategy Amendments -Potential OCP Amendment -Potential for RGS Amendment of Urban Containment Boundary

Page 14: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

STAGE 2 – Other Outstanding Issues Determine cost of “Greenspace Levy” and financing

strategy;

Prepare “Design Guidelines” for the various land uses and features such as: greenways, walkways, selected streets, neighbourhood gateways, entrance points, gathering places and buffers;

Establish list of “NCP Amenity Contributions needed to serve area including: park development, fire, police and library needs.

Establish per unit “Application Surcharge Fee” to recover NCP ‘consultant’ preparation cost.

Prepare an “Implementation Strategy” to guide the

development in keeping with the NCP's Vision, Principles and land Use Concept Plan.

Greenspace Levy

Design Guidelines

NCP Amenity Contributions

NCP Surcharge Levy

Implementation Strategy

Page 15: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

STAGE 2- Consultation Timeline Stage 2 - Update CAC Meeting

(Initial Servicing & Transport Study Update)

Stage 2 - Additional CAC Meetings (Servicing Strategies)

Stage 2 - City Committee Meetings

Interagency and Stakeholder Group Meeting(s)

Final Stage 2 Public Open House

*We are Here

Estimate: Spring 2017?

Page 16: Redwood Height Presentation CAC 2016-06-28 Rev1 - Surrey · 2019. 12. 11. · Greenspace Levy . Design Guidelines NCP Amenity Contributions NCP Surcharge Levy . Implementation Strategy

Discussion / Comments