    RECORDS, ACIEVEMENTS & AWARDS

    • In the History of TSTPP there is never

    loss of power generation due toshortage of coal.

    • CHP is consistently maintaining higher

    availability than target due to

    Preventive, Condition based

    maintenance & Predictive maintenance.

    CHP team got the meritorious awardon 15th

      August 2000 for designing &

    implementing the on line spillage coal

    washing tray under conveyor 2A/2B.

    This has brought down down-time of

    conveyors 2A/2B during monsoon.

    • CHP team got the meritorious award

    on 26-01-2003 for modification in VGF,resulting in better grizzly action of

    VGF by fixing screens on grizzly bed.

    • CHP team got the First prize for best

    House Keeping on 26-01-2003.

    • CHP team got awards in 2002 & 2001

    for presentation of tableaus onRepublic Day.

    • CHP team got meritorious award on

    for modification of water sprinkler

    system in stackyard. The modified

  • 8/17/2019 Records&Achievements

    2/2

    system is very easy to operate &

    maintain. Earlier it was getting

    submerged in coal.

    • Maximum coal handled from TrackHopper in a shift, 9000MT on 31-10-

    2002.

    • Maximum coal handled from Track

    Hopper in a day, 24,200 MT on 29-12-

    2002.

    Record coal of 28,400 MT handled(bunkered) in a day on 14/04/2003.

    • Record coal of 30,100 MT handled

    (bunkered) in a day on 27/06/2003.