Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes in North America: DEMON and ANITA Mox Andrea Nifong, World Water Works (formerly HRSD) Stephanie Klaus, VT & HRSD

Upload: others

Post on 20-Jan-2021

13 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Recommendations and Lessons Learned from the Startup of the First Two Full-Scale

Sidestream Deammonification Processes in North America: DEMON and ANITA Mox

Andrea Nifong, World Water Works (formerly HRSD)

Stephanie Klaus, VT & HRSD

Page 2: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Key Points

• Training is key but only 2 “champions” need in depth training

• Control strategy for long term operation is stable and hands off

• AOB are the most sensitive bacteria in the process, AOB are limiting not anammox

• 25°C is a reasonable minimum temperature

• Long term shutdowns are possible

2

Page 3: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Sidestream Deammonification

Influent Primary Clarifier

Aerobic Secondary Clarifier Tertiary

Anaerobic Digestor DewateringDeammonification

Primary Clarifier

Secondary Clarifier Tertiary

Anaerobic Digestor Dewatering

Centrate

• ~1% of Total Plant Influent Flow• ~20-40% of the Total Plant TN load• NH4 Concentration between 900 – 1,500 mg/L• Alkalinity/NH4 ratio ≅ 3.5-4.0• Temperature 30 - 38C• Alkalinity insufficient for complete nitrification• Insufficient carbon for denitrification

3

Page 4: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Conventional Nitrification-Denitrification

NITRIFICATION

1 mol Ammonia

(NH3/ NH4 +)

1 mol Nitrite(NO2

- )

1 mol Nitrate(NO3

- )

75% O2 (energy)~100% Alkalinity

Autotrophic Bacteria

Aerobic Environment

1 mol Nitrite(NO2

- )

½ mol Nitrogen Gas(N2 )

25% O2 (energy)

40% Carbon (BOD)

60% Carbon (BOD)

Heterotrophic BacteriaAnoxic Environment

DENITRIFICATION

Nitritation

Nitratation

Denitritation

Denitratation

4

Page 5: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Partial Nitritation + Anammox = Deammonification

1 mol Ammonia

(NH3/ NH4 +)

0.5 mol Nitrite(NO2

- )

37% O2 (energy)~57% Alkalinity

Autotrophic BacteriaAerobic Environment

½ mol Nitrogen Gas (N2 ) + 0.11 mol Nitrate (NO3-)

Autotrophic Anoxic Environment

NH4+ + 1.32 NO2

- + 0.066 HCO3- + 0.13 H+

0.26 NO3- + 1.02N2 + 0.066 CH2O0.5N0.15 + 2.03 H2O

Advantages: • 63% reduction in oxygen demand (energy) • Nearly 100% reduction in carbon demand • 80% reduction in biomass production • No additional alkalinity required

5

Page 6: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

One-Step Sidestream Deammonification(with full-scale applications)

• Upflow Granular Sludge– Paques ANAMMOX®

• SBR– DEMON®

• MBBR – ANITA™Mox

– Deammon®

6

Page 7: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Operation Objectives

Target is 90% NH4 Removal

(80% TIN Removal)

• Typical Guidelines:o Residual alkalinity 150 -250 mg/L as CaCO3

o Residual NH4 of 50-100 mg/Lo Nitrite concentration below 20-40 mg/L

Target is 10-15% NO3 Production

7

Page 8: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

DEMON at York River

DEMON

DENITE FILTERS

HEADWORKS

AERATIONBASINS

ANAEROBIC DIGESTION

THICKENING

DEWATERING

Page 9: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Demon® York River WWTP

9

Page 10: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

1010

Seed Sludge Aeration System

Instruments & Controls

Tank

Blowers Decanter Mixer Cyclone

DEMON® Process Components

Page 11: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

DEMON® – Control Strategy• SBR configuration – typically 6 or 8 hour cycle time• Last hour of cycle - settle and decant• During React Period – multiple mini-cycles (10-30 mins):

• Aerate• Mix/fill• Mix

• Aeration:• DO ~0.2-0.5 mg/L (PID control or constant airflow)• pH based aeration control

11

Page 12: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

DEMON® Control Strategy - Anammox Enrichment

• Continual enrichment of anammox

– Large excess of activity

– Provides stability

• Ability to Washout NOB if proliferation occurs

Anammox returned to Process

AOB/NOB/OHO/debris

12

Page 13: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Seed Sludge

13

Confidential; Copyright 2013, World Water Works, Inc. All rights reserved.

13

Page 14: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

NH4 and TIN Removal Percentages

0

10

20

30

40

50

60

70

80

90

100

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

8-Oct-12 28-Oct-12 17-Nov-12 7-Dec-12 27-Dec-12 16-Jan-13 5-Feb-13 25-Feb-13

NO

2-N

Co

nce

ntr

atio

n (

mg

/L);

Tem

pe

ratu

re (◦C

)

% N

H4

-N R

em

ova

l ; %

NO

3-N

Pro

du

ctio

n

NH4-N Removal NO3-N Production

NO2-N Cencentration Temperature

removal efficiency loss

due to low temperatures

14

Page 15: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

NH4 Loading and Removal Rates

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0.40

0.45

0.50

NH

4-N

kgN

/m3

/day

)

NH4-N Influent Load (kgN/m3/day)

NH4-N Load Removed (kgN/m3/day)

System Shut- down

15

Page 16: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

HRSD James River Treatment Plant

16

Page 17: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

ANITA Mox Process Components

Aeration System Instrumentation Centrate Feed

Mixers and Heaters K5 Media Media Retention17

Page 18: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Supplemental Heating

• DEMON

– Temp maintained above 25°C after supplemental heating was supplied

– Lesson Learned: Insulate or provide heating during startup

• ANITA Mox

– Temp maintained above 30°C during startup and 25°C long term

18

Page 19: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Anitamox Process Control

• Centrate Feed Control

• Aeration Control

– Continuous and Intermittent

– Three Different Modes

1. Airflow setpoint (scfm)

2. Fixed DO setpoint

3. pH-based DO or airflow

• Mixer Control

19

Page 20: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Seeding and Startup

20

Page 21: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Biofilm Growth

Seed media

2/26/14

New media

4/10/14

Seed media

4/10/14

New media

2/26/14New media

7/15/14

Seed media

7/15/14

Seed media

12/12/13

New media

12/12/13

21

Page 22: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

12/3/13 1/2/14 2/1/14 3/3/14 4/2/14 5/2/14 6/1/14 7/1/14

%, m

g/L

, C°

TIN Removal %

NH4 Removal %

NO2 out (mg/L)

Temperature

NO3 Production Ratio

StartupComplete

NH4 and TIN Removal Percentages

22

Page 23: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

NH4 Loading and Removal Rates

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

12/3/13 1/2/14 2/1/14 3/3/14 4/2/14 5/2/14 6/1/14 7/1/14

kg/m

3/d

ay

NH4 Load (kg/m3/day)

NH4 Removed (kg/m3/day)

IntermittentAeration

ContinuousAeration

Startup Complete

23

Page 24: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

pH-based Aeration Control

24

Page 25: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

DEMON pH-Based Aeration Control– Aeration time is based on a low pH setpoint

– Anoxic/Feed time based on a timer or high pH setpoint

25

Page 26: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Option 1: ANITA Mox Fixed DO or Airflow Setpoint

26

Time (min)

0 200 400 600 800 1000 1200 1400

pH

6.4

6.5

6.6

6.7

6.8

6.9

7.0

DO

(m

g/L

), C

en

tra

te F

low

(m

3/h

r)

0

2

4

6

8

10

12

14

pH

DO

Centrate Flow

DO setpoint

Page 27: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Option 2: ANITA Mox pH-Based Aeration Control

27

Day

420 430 440 450 460 470 480

DO

(m

g/L

), C

en

tra

te F

low

(m

3/h

r),

pH

0

5

10

15

20

NO

3 P

rodu

ctio

n %

, N

H4

Rem

ova

l %

0

20

40

60

80

100pH Feedback

Centrate Flow

pH Setpoint

DO Setpoint

NO3 Production %

NH4 Removal %

Page 28: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

DEMON and ANITA Mox – Both use a form pH-Based Aeration Control

• Control modes:• DEMON – pH affects aeration time at controlled DO• ANITA Mox – pH affects DO concentration

• pH Probe – minimal maintenance/calibration• Use handheld/lab probe to verify

• Consistent ammonia load & removal = constant OUR• 1 or 2 Lead Operators trained on pH Based aeration control

28

Page 29: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Alarms and Fail Safes• Low pH = air shut off

• High DO = air and centrate feed shut off

• Low Level = air and centrate feed shut off

• Centrate Feed Pump Low Flow/Fail = air shut off

• High Level = centrate feed shutoff

• High/Low Temperature = alarm

• Cyclone Pump Low Pressure= shut off

• Manual Mode Alarm = alarm

29

Page 30: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Training

• Entire plant staff trained on basic understanding of process theory, process components, analysis requirements and controls

• Daily meetings during startup, tapering to weekly meeting. Participants included: Plant staff, R&D team, and vendor.

• 1-2 of the plant staff understand in depth theory, troubleshooting, and process control

30

Page 31: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Sampling/Analysis

Sampling• Frequency: Daily during startup

tapering down to weekly• Parameters:

-On site: HACH test kit NH3, NO2, NO3

-Lab data: Alk, sCOD, TSS, OP• Training: 2 Lab Technicians

Convenient Sample Ports

31

Page 32: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Sensor ManagementInstrument Calibration

FrequencyMaintenance Function

pH Quarterly Max WeeklyCleaning

Control

DO Annual Weekly Cleaning/Air Blast

Control

Conductivity Annual No issue Monitoring

Ammonia/Nitrate As needed compared to lab values

Air Blast Monitoring

32

Page 33: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Specific Conductivity• Specific conductivity represents the measure of all

relevant ions

• For deammonification the most important are NH4

+, NO2-, NO3

-, HCO3-

• Great monitoring tool

33

Page 34: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Specific Conductivity- ANITA Mox

34

Day

420 430 440 450 460 470

pH

5.4

5.6

5.8

6.0

6.2

6.4

6.6

6.8

7.0

7.2

Sp

ecific

Co

ndu

ctivity,

NH

4

60

80

100

120

140

160

180

200

220

240

pH

NH4

Specific Conductivity

Page 35: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Centrate Quality• Automate centrate diversion valves

• Eliminate sources of dilution water

• Sufficient EQ size and settling

• Temperature control if necessary

35

Page 36: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Micronutrient Addition

Source: Grady, C., Daigger, G., Love, N., Filipe, C. (2011). Biological Wastewater Treatment, IWA Publishing. 36

Page 37: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Micronutrient Deficiency - DEMON®

0

5

10

15

20

25

30

35

40

45

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

26-Jan-13 15-Feb-13 7-Mar-13 27-Mar-13 16-Apr-13 6-May-13 26-May-13 15-Jun-13 5-Jul-13

NO

2-N

Co

nce

ntr

atio

n (

mg

/L);

Te

mp

era

ture

(◦

C)

% N

H4

-N R

em

ova

l ; %

NO

3-N

Pro

du

ctio

n

NH4-N Removal NO3-N Production NO2-N Cencentration Temperature

Micronutrient Addition

37

Page 38: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

ANITA Mox Micronutrient Deficiency

38

0

2

4

6

8

10

12

14

0

10

20

30

40

50

60

70

80

90

100

9/26/2014 10/26/2014 11/25/2014 12/25/2014 1/24/2015

pH

Pe

rce

nt

%

NH4 Removal %

NO3 Production Ratio

pH

12% NO3 Production

Resume Micronutrient Addition

Page 39: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Shutdowns

• Shutdown for a week at a time with no significant change in operation strategy

• > 1 week requires a reduced load during startup

• AOB are the limiting factor

• Anammox are very robust (very slow decay rate)

• DEMON and ANITA Mox appear similar

– One month shutdown for DEMON = one month restart

39

Page 40: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

ANITA Mox Shutdown Test

FIN EFF FIN EFF FIN EFFTKN NOx T-N

4/5/2015 2.42 2.33 4.754/6/2015 3.72 2.8 6.524/7/2015 3.63 3.28 6.914/8/2015 2.87 3.3 6.174/9/2015

4/10/20154/11/20154/12/2015 4.36 3.13 7.494/13/2015 5.95 3.07 9.024/14/2015 5.82 3.5 9.324/15/2015 5.99 3.92 9.91

With sidestream treatment

Without sidestream treatment

40

James River Main Plant Performance with and without ANITA Mox

Page 41: Recommendations and Lessons Learned from the Startup of ......Recommendations and Lessons Learned from the Startup of the First Two Full-Scale Sidestream Deammonification Processes

Conclusions

• Complete ownership of the system starts with daily, then weekly performance discussions with two champions of the system

• Anammox are robust, all limiting issues have been caused by AOB

• pH control is simple and effective

• Sidestream deammonification is a proven technology

• Process is not plug & play, careful attention required during startup

• Thoughtful attention during normal operation; set point changes ~1-2X/week (assuming good EQ)

• Lessons learned from DEMON applied to ANITA Mox

41