Recent Construction Sites of Micropiles in Germany
Thomas F. Herbst
Wessling / Munich Germany
5th IWM 2003 Seattle – Session 2
1. Replacement of the 100 years old lock Lauenburg of the Elbe-Lübeck Channel
Cross section of the lock
Lock Lauenburg: Aerial view during construction 2003
View of the site with 3 floating drill rigs
Execution: Bauer
Micropile GEWI dia. 63,5 mm anchored in underwater concrete slab
Underwater installation from pontoon
Length: 23 to 27 m
2. Retrofitting of a bridge abutment in Bad Waldsee
Execution: Bilfinger&Berger
Micropile GEWI dia. 50mm in sections, borehole dia. 150 mm
Free head room: max. 2 m
Soil: Gravel and silt
Rotary drilling with external cementitious flushing
Group testing with 3 GEWI piles at Bad Waldstadt site
Single and group testing of each micropile up to 1,25 service load
Service Load:
300 kN per micropile
3. Retrofitting of settled drainage tunnel of the waste disposal Kahlenberg
Cross section
Pump shaft
Settlements up to 24cm
Ore rib
Drainage tunnel
Auffüllung
Erzliegendes
Auffüllung
Erzliegendes
Grouted micropile and micropile with inflatable bulb
Auffüllung
Erzliegendes
fill
substratum
Micropile with inflatable bulb (system Bauer)
groundmicropile shaft with bearing element
A) Design for preloadable micropile head:
Solutions by Bauer
structural element
B) Preloading of the micropile and lifting of the structure
micropile shaft with bearing
element
structural element
ground
s
micropile shaft with bearing
element ground
structural element
grouted gap
C) Lifted structural element after preloading of the micropile, tightening the lock nut and grouting
D) Micropile head for preloading in case of an existing structure
sexisting structural
element
groundmicropile shaft with bearing element
Bauer - Klemm drill rig for low head room
116 micropiles in total
• 96 grouted micropiles
• 20 micropiles with inflatable bulb
Total amount of micropiles for the drainage tunnel of the waste disposal Kahlenbach installed by Bauer :
Ore rib