REINFORCED EARTH
STRUCTURES
P . Suresh B .Tech.,
![Page 2: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/2.jpg)
The soils which have little tensile strength can be strengthened by the inclusion of materials with high tensile strength . The principle is same as adopted in reinforced concrete.
This mobilization of tensile strength is obtained by surface interaction between the soil and the reinforcement elements through friction and adhesion.
The reinforced earth technique is useful in urban locations where availability of land is minimum and construction is required with min disturbance to traffic.
If the soil is cohesion less like sand the resistance will be friction and if the soil is cohesive the bond stress will be adhesive.
BASIC CONCEPT OF REINFORCED EARTH
![Page 3: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/3.jpg)
It is very important to note that the total horizontal earth pressure is resisted by the frictional force between the soil and reinforcing element and the design will be made with required no. of layers vertically at adequate spacing
Hence there will not be any horizontal thrust on facia panels/blocks and these elements are non structural and are provided only to prevent erosion, loss of material at the face of re wall. The foundation provided for facia panels is only to take the self weight of panels, kerb over wall etc., but not for resisting the horizontal thrust.
The facia wall facilitates to keep the reinforcing elements at desired level and to retain fill material.
Compaction of fill material is not compulsory for walls without any vertical loads like gardens etc. For roads the compaction of fill shall be done as usual. But care must be taken that the compaction equipment like rollers etc should go not closer than 2m to wall facing
![Page 4: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/4.jpg)
Generally the size of square panels shall be 1500 x 1500mm. The thickness of panels shall be 180 mm and concrete grade of M35 shall be adopted. Nominal reinforcement consisting of 8mm Hysd bars shall be provided both ways at center
A leveling pad with m15 grade concrete shall be casted to provide a firm, level, and flat surface on which the facing units can be erected to the correct line, level. The width of footing is generally 600mm, and depth of 200mm. The leveling pad shall be cured for 24 hours prior to commencement of placing of panels.
![Page 5: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/5.jpg)
No plant or equipment with a weight of more than 1500 kg shall be allowed to operate within a distance of 1.50m from the facing
A light weight less than 1500kg vibratory roller or vibratory plate compactor may be used in this zone
Beyond a distance of 1.50m from the facing a static or vibratory roller of 8- 10 t may be used for compaction.
![Page 6: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/6.jpg)
CONCEPT OF REINFORCED EARTH
![Page 7: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/7.jpg)
SKETCH SHOWING ACTIVE AND RESISTANT ZONES
STABLE SLOPE STEEP SLOPE
EMBANKMENT
EXISTING G.L.
SOIL FORMATION
![Page 8: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/8.jpg)
COMPONENTS OF REINFORCED EARTH STRUCTURE
1) REINFORCING ELEMENT
2) SOIL BACK FILL
3) FACING ELEMENT
![Page 9: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/9.jpg)
TYPES OF REINFORCING ELEMENTS
Strips with metals like steel, aluminum, copper, polymers, glass fibre reinforced plastic etc.
Grids with steel, galvanized weld mesh, polymers (geo grids)
Sheet reinforcement with steel, fabric (geotextile)
Planks with timber, reinforced concrete, pre stressed concrete.
![Page 10: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/10.jpg)
SKETCH SHOWING COMPONENTS OF RE WALL
![Page 11: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/11.jpg)
![Page 12: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/12.jpg)
The fill material for reinforced earth structures shall be
preferably cohesion less and it should have angle of
interface friction between the compacted fill and
reinforcing element not less than 30.
REQUIREMENT OF SELECTED FILL
Plasticity index should be less than 6
The size of fill material should not exceed 125 mm
The soil should be coarse grained, and not more than
10% of particles shall pass 75 micron sieve
The earth reinforcement coefficient of friction should
be higher than 0.40
![Page 13: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/13.jpg)
COEFFICIENT OF INTERACTION BETWEEN SOIL AND GEO GRID
S.NO TYPE OF SOIL COEFFICIENT Ǿ VALUE
1) CRUSHED ROCK,GRAVEL 0.90 TO 1.0 40 TO 50
2) SANDS 0.85 TO 0.95 28 TO 40
3) PULVERISED FUEL ASH 0.80 TO 0.85 --
4) CLAY 0.60 TO 0.70 < 12
![Page 14: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/14.jpg)
COMPONENTS OF RE WALS
![Page 15: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/15.jpg)
![Page 16: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/16.jpg)
SKETCH SHOWING RE WALL DETAILS, DRAINAGE LAYER
![Page 17: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/17.jpg)
SKETCH SHOWING RE WALL SYSTEM
![Page 18: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/18.jpg)
MINIMUM LENGTH OF REINFORCEMENT
TYPE OF STRUCTURE MIN. REINFORCEMENT LENGTH
1)RETAINING WALLS 0.70 H (OR) MIN 3.0M
2)BRIDGE ABUTMENTS (0.60H+2) OR MIN 7.0 M
![Page 19: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/19.jpg)
SECTION SHOWING RE WALLS REINFORCEMENT
![Page 20: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/20.jpg)
SKETCH SHOWING WRAP AROUND GEOTEXTILE RE WALLS
![Page 21: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/21.jpg)
SKETCH SHOWING DIFFERENT TYPES OF RE WALLS
![Page 22: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/22.jpg)
![Page 23: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/23.jpg)
![Page 24: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/24.jpg)
TYPES OF FACING ELEMENTS
1)REINFORCED CONCRETE PRECAST
PANELS
2)PRECAST HOLLOW BLOCKS OR SOLID
BLOCKS
3) MILD STEEL SHEET
4) RUBBLE FACIA WITH WIRE MESH
![Page 25: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/25.jpg)
TYPICAL SKETCH SHOWING ONE TYPE OF FACIA PANELS
![Page 26: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/26.jpg)
SKETCH SHOWING TIE IN FACIA WALLS
![Page 27: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/27.jpg)
SKETCH SHOWING REINFORCEMENT CONNECTION WITH TIE
![Page 28: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/28.jpg)
PHOTO SHOWING CONNECTION OF REINFORCEMENT WITH TIE
![Page 29: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/29.jpg)
P.C.C. BED UNDER REINFORCED EARTH WALL
![Page 30: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/30.jpg)
INSIDE (EARTH FACE ) FACE OF RE WALL WITH FIRST ROW OF FACIA PANELS.
![Page 31: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/31.jpg)
PHOTO SHOWING FOUNDATION OF FACIA PANELS
![Page 32: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/32.jpg)
SKETCH SHOWING PLACEMENT OF FIRST ROW OF PANELS
![Page 33: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/33.jpg)
PHOTO SHOWING SCAFFOLDING FOR FIRST LAYER OF PANELS
![Page 34: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/34.jpg)
![Page 35: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/35.jpg)
RAISING OF FACIA WALL WITH PRECAST PANELS
![Page 36: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/36.jpg)
SKETCH SHOWING JOINTING OF PANELS
![Page 37: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/37.jpg)
THE PANELS MAY BE GIVEN SLIGHT TILT TOWARDS SELECTED FILL TO ALLOW OUTWARD MOVEMENT SO
THAT IT WILL BE TRULY VERTICAL AFTER LOADING
![Page 38: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/38.jpg)
![Page 39: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/39.jpg)
PHOTO SHOWING FURTHER LAYERS OF R.C.C. FACIA PANELS
![Page 40: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/40.jpg)
SKETCH SHOWING PLACEMENT OF R.C.C. FACIA PANELS
![Page 41: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/41.jpg)
SKETCH SHOWING IN SIDE OF FACIA PANELS DURING ERECTION
![Page 42: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/42.jpg)
PHOTO SHOWING CENTERING FOR CHECKING SPACING ,PLUMB
![Page 43: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/43.jpg)
STEEL REINFORCEMENT WITH STONE DUST FILL WITH R.C.C. FACIA PANELS
![Page 44: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/44.jpg)
STEEL FACIA PANELS WITH STEEL STRIPS AND FILL
![Page 45: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/45.jpg)
STEEL REINFORCEMENT WITH STEEL FACIA AND GRAVEL FILL
![Page 46: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/46.jpg)
CLOSE UP VIEW OF STEEL STRIP REINFORCEMENT ,FACIA PANELS
![Page 47: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/47.jpg)
RE WALL WITH CRUSHED AGGREGATE FILL, FACIA PANMELS
![Page 48: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/48.jpg)
RE WALL WITH STEEL REINFORCEMENT
![Page 49: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/49.jpg)
PHOTO SHOWING STEEL REINFORCEMENT IN SOIL ,FACIA PANEL
![Page 50: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/50.jpg)
STEEL REINFORCEMENT WITH R.C.C. FACIA PANELS
![Page 51: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/51.jpg)
CLOSEUP VIEW OF STEEL REINFORCEMENT
![Page 52: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/52.jpg)
PHOTO SHOWING GEOGRID REINFORCEMENT WITH HOLLOW BLOCKS FACIA
![Page 53: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/53.jpg)
PHOTO SHOWING GEO SYNTHETIC REINFORCEMENT ,FACIA BLOCKS
![Page 54: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/54.jpg)
PHOTO SHOWING GEO GRID REINFORCEMENT, OVER LAP
![Page 55: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/55.jpg)
CLOSE UP VIEW OF GEO TEXTILE REINFORCEMENT
![Page 56: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/56.jpg)
GEO GRID REINFORCEMENT WITH PRECAST C.C.BLOCKS FACIA
![Page 57: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/57.jpg)
CLOSE UP VIEW OF GEOGRID REINFORCEMENT
![Page 58: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/58.jpg)
GEOGRID REINFORCEMENT WITH HOLLOW BLOCKS FACIA
![Page 59: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/59.jpg)
METAL REINFORCEMENT, STONE DUST FILL, HOLLOW BLOCKS FACIA
![Page 60: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/60.jpg)
DRAINAGE LAYER, SELECTED FILL, C.C. HOLLOW BLOCKS FACIA
![Page 61: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/61.jpg)
SPREADING OF GEO GRID
![Page 62: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/62.jpg)
SPREADING OF GEO GRID WITH FACIA BLOCKS
![Page 63: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/63.jpg)
SPREADING OF FILL MATERIAL (CRUSHED ROCK), GEOGRID
![Page 64: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/64.jpg)
STONE DUST FILL, R.C.C. FACIA PANELS
![Page 65: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/65.jpg)
PHOTO SHOWING COMPACTION OF FILL MATERIAL
![Page 66: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/66.jpg)
PHOTO SHOWING COMPACTION WITH PLATE COMPACTOR CLOSE TO FACIA WALLS
![Page 67: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/67.jpg)
PRECAST BLOCKS FACIA WITH STEEL REINFORCEMENT
![Page 68: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/68.jpg)
METAL REINFORCEMENT WITH PRECAST HOLLOW BLOCKS FACIA
![Page 69: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/69.jpg)
SPREADING OF SELECTED FILL STONE DUST
![Page 70: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/70.jpg)
GEOTEXTILE FIXED WITH FACIA WALLS AND ERECTION OF FACIA PANELS
![Page 71: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/71.jpg)
ERECTION OF FULL HIGHT FACIA WALLS
![Page 72: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/72.jpg)
ERECTION OF PRE-CAST FACIA PANELS
![Page 73: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/73.jpg)
ERECTION OF PRECAST FACIA PANELS WITH TIES
![Page 74: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/74.jpg)
ERECTION OF FULL HIGHT FACIA PANELS
![Page 75: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/75.jpg)
ERECTION OF FULL HIGHT FACIA PANEL
![Page 76: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/76.jpg)
COMPLETED RE WALL WITH FACIA PANELS
![Page 77: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/77.jpg)
PHOTO SHOWING TIMBER GRID RETAINING WALL
![Page 78: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/78.jpg)
COMPLETED BRIDGE ABUTMENT AS RE WALL
![Page 79: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/79.jpg)
COMPLETED BRIDGE ABUTMENT AS RE WALL WITH FULL HIGHT CONCRETE FACIA PANELS
![Page 80: RE Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022062301/577cceff1a28ab9e788e9bee/html5/thumbnails/80.jpg)
THANK YOU
P. SURESH. Deputy Executive Engineer