raw materials storage pre wet hall phase 1 hall bunkers filling hall emptying hall blocking hall...
TRANSCRIPT
Raw materials Raw materials storagestorage
Pre Wet Pre Wet HallHall
Phase 1 Phase 1 HallHall Phase 1 Phase 1
bunkersbunkers
Filling HallFilling Hall
Emptying Hall
Emptying Hall
Blocking Blocking HallHall
Phase 2/3 Phase 2/3 tunnelstunnels
StrawStraw
Elf Farm Supplies Pty LtdAbout Us
Phase II and III is serviced with chillers and cooling towerswhich supply 2700kW of cooling
capacity. Compost is initially levelled to a consistent temperature then
After bale wetting, the bales are transferred into the Prewet Shed.Bales are broken and mixed with other ingredients using
a Mobile Blender. Water is also added through this mixing process. The ricks are turned, blended and water added to further
promotethe composting process over the following days. Fresh air is supplied through air pipes underneath the
ricks tokeep the process aerobic. This method was first developed at the Elf Farm Supplies site and is now standard industry practice throughout the world.
The roof of the Prewet Shed is constructed of wood and fastenedwith stainless steel nails. This is due to the high ammonia
environment which corrodes metal but preserves wood.
Phase I As in the Prewet Shed, fresh air is supplied through
air pipesunderneath the bunkers to control compost temperatures and oxygen levels and keep the process aerobic.
The compost is blended a number of times and has water added
to adjust the moisture content. Exhaust air is passed through a Bioscrubber and
discharged upthe stack. Strict odour control practices are in place to meet our EPA licence conditions.
Phase II
heated for 8 hours to pasteurise the compost. Phase II is designed to kill unwanted pathogens and to create an ideal nutrient and bio- logical medium for mycelium development.
After pasteurisation, the compost is conditioned at 45 to 50 degrees Celsius for 3-4 days.
Phase III
Pre-Wet Bales are pre-wet and allowed to heat up to remove
the waxylayer from the straw and to initiate the composting process.
Phase II and III comprises 22 tunnels which are each 40 metreslong and 4 metres wide. A chamber located underneath the
concrete slat floor enables circulation of air up through the compost in each tunnel.
Phase I compost is loaded into the tunnels using a cassette filler
which is a system of conveyors that extend into the tunnels.
The compost is placed on top of a pulling net, which enables subsequent removal from the tunnel.
Each tunnel holds up to 200 tonnes of Phase 1 compost that will finally reduce to 150 tonnes of Phase 3 compost.
The Phase II process is computer controlled using fresh and recir- culated air to control compost temperatures and oxygen levels. Each tunnel has a dedicated air intake and fan
system. Air ispassed through a series of filters to remove particles down to 4 mi- crons absolute. Filtration is important to prevent the introduction of competitor species.
After Phase II is complete, the Phase III process commences
which involves the addition of spawn to the compost. This operation is undertaken following intensive
cleaning anddisinfecting. It is imperative that “sterile” conditions are created to prevent infection of the compost with unwanted pathogens that can impede mushroom growth.
Phase II material is removed from the tunnel using a pullingwinch, inoculated with spawn and returned to another
tunnel using a cassette filler.
The Phase III process is fully computer controlled to createenvironmental and biological conditions that maximise
mushroom mycelium development.
Phase III material is removed from the tunnels using a pulling
winch. Some Customers require the addition of a protein
supplementduring ship out. The supplement is added at nominated rates during the transfer from the tunnels to the trucks/blocking line. White Prince trailers with the capacity to carry 25
tonnes eachare used to transport compost to farms in bulk. Each trailer is fitted with a walking floor and a conveyor to transfer material to unloading conveyors located at the farms. Load time is only 12 mins.
Phase III Blocks Some of the Phase III compost is then
manufactured intoblocks.
The length of the process from commencement of Pre-wet toship out is approximately 6—7 weeks. Mushroom
harvesting com- mences a further two weeks after delivery to the farm.
Compost Production Process
Elf Farm Supplies Pty Ltd was established at it’s present site at Mulgrave in 1981. We are proud to be a wholly owned Australian Company.Since 1990, Elf Farm Supplies has expanded rapidly. With the environmental and economic pressures placed on the industry, new and innovative ways of producing mushroom compost have been tested and implemented.Today, Elf Farm Supplies is one of the leading compost producers in Australia. We are the largest agricultural enterprise in the Hawkesbury and the only supplier in the Sydney region. Our products are supplied throughout Australia and are integral to the success of the Australian Mushroom Industry.