rapid risk assessment studyenvironmentclearance.nic.in/writereaddata/online/... · the rapid risk...

51
RAPID RISK ASSESSMENT STUDY FOR RE-ROUTING OF OIL PRODUCT PIPELINES IN CHENNAI RRA - PIPELINE PROJECT Submitted to: Indian Oil Corporation Limited Chennai Submitted by: Vimta Labs Ltd. 142 IDA, Phase-II, Cherlapally Hyderabad500 051 [email protected], www.vimta.com (NABET & QCI Accredited, NABL Accredited and ISO 17025 Certified Laboratory, Recognized by MoEF, New Delhi) May 2015

Upload: others

Post on 31-Jan-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

  • RAPID RISK ASSESSMENT STUDY

    FOR RE-ROUTING OF OIL PRODUCT PIPELINES IN CHENNAI

    RRA - PIPELINE PROJECT

    Submitted to:

    Indian Oil Corporation Limited Chennai

    Submitted by:

    Vimta Labs Ltd.

    142 IDA, Phase-II, Cherlapally Hyderabad–500 051

    [email protected], www.vimta.com (NABET & QCI Accredited, NABL Accredited and ISO 17025 Certified Laboratory, Recognized

    by MoEF, New Delhi)

    May 2015

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    1.0 INTRODUCTION

    1.1 Background

    Indian Oil Corporation Limited (IOCL) propose to lay three underground pipelines about 5.45 km long between IOC Korukkupet and Foreshore Terminals in North Chennai to replace the existing lines which pass through densely populated areas and are difficult to maintain.

    These lines are used for both export from CPCL, import and coastal positioning of HSD

    during shortfall in CPCL production to meet the demand of Tamil Nadu, Pondicherry UT and

    parts of adjoining states. The Fuel Oil line is used for positioning product at FST from CPCL

    for bunkering as well as for export from Chennai port. Similarly the Lube line is used for

    export from CPCL and import of base oils as well as extracts. Thus these dock lines play a

    vital role in evacuation of CPCL production and also receive through coastal movement to

    meet local demand during shortfall in production/shut down period. Besides meeting the

    public demand for MS/HSD, these lines also cater to requirement of PDS, all thethree wings

    of Defence, Coast Guard, Para military, Civil Aviation, Bunkering requirements for merchant

    navy ships, major customers like power plants, Railways, State Transport sectors, Fertilizer

    plants etc.

    Taking into consideration the vital requirement of these lines on the one hand and the challenge of maintaining the lines passing through densely populated areas on the other hand, it is proposed to re-route the lines between IOC Korukkupet and IOC Foreshore Terminal in North Chennai.

    In a PIL case filed in National Green Tribunal Chennai (NGT), Chennai after the incident of contamination of water in the bore well/wells near underground oil pipelines, Ministry of Petroleum & Natural Gas (MOP&NG) as one of the respondents made commitment on behalf of Oil Manufacturing Companies as per which, IOC would be required to take action for re-routing of the underground portion of the dock lines in the Railway corridor.

    1.2 RRA Study

    IOCL being an organization with commitment to high standards of process safety management wish to identify the hazards associated with the re-routing of oil pipelines in

    North Chennai and implement all necessary measures to ensure that the risk due to the pipelines are kept as low as reasonably practicable. With this objective, IOCL have engaged

    the services of Vimta Labs, Hyderabad, for carrying out a Rapid Risk Assessment (RRA) study for the re-routing of pipelines in North Chennai.

    Vimta Labs have wide experience in conducting environmental impact assessment (EIA) study and risk analysis for a large number of oil & gas facilities, petroleum installations, chemical/ fertilizer plants, power plants, mines & mineral installations etc.

    This report contains the Rapid Risk assessment (RRA) for the IOCL pipelines re-routing project in North Chennai.

    VIMTA Labs Limited, Hyderabad 2

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    2.0 FACILITY DESCRIPTION

    2.1 Replacement & Rerouting of IOCL Pipelines in North Chennai

    The pipelines will be routed in a corridor 4 m wide along the Railway tracks between

    Korukkupet and Chennai Port entry, where IOCL already have 1.6 m width. As per OISD guidelines, in 4 m width, maximum 3 pipelines can be accommodated. In compliance with the OISD norms, against the presently existing 4 lines, it is proposed to lay the following 3 pipelines to meet the requirements.

    1) 20” diameter line for White Oil products MS, HSD, ATF, Naptha, SKO as a multiproduct line

    2) 14” diameter line for Black Oil (Fuel Oil)

    3) 12” diameter line for Lube Oils

    The pipelnes cater to the following throughputs:

    White Oil products Black Oil products Lube Oil products

    : 1.1 MMTPA : 0.7 MMTPA : 0.3 MMTPA

    All the pipelines will be piggable to facilitate smooth operation and maintenance.

    As per the pipeline operations, maximum operating pressure shall not exceed 7 kg/sq.cm. However for the calculation purpose 12 kg/sq.cm. maximum operating pressure is considered.

    API 5L X46 grade pipes have been chosen. Accordingly the thickness required and maximum allowable operating pressure for the pipelines are as follows:

    Thickness Thickness required

    Actual Maximum

    Pipeline operating allowable of pipeline for maximum

    diameter pressure operating considered operating pressure

    (inch) considered pressure (inch) (inch)

    (kg/sq.cm.) (kg/sq.cm.)

    20 0.281 0.07419 12 45.45

    14 0.281 0.05193 12 64.93

    12.75 0.281 0.04729 12 71.29

    Thus pipes are of higher wall thickness and MAOP much higher than the required. Further corrosion mitigation measures are implemented.

    The terrain along the pipeline route is mostly flat and plain. At 3 locations it crosses the

    railway track. There are also 3 road crossings. At rail crossings, where casing pipe would be

    provided, the pipe wall thickness would remain same as that for the main pipeline as per the standards. For Horizontal Directional Drilling (HDD) technique at road crossings, higher wall

    thickness pipes are considered. There is no crossing of water course. Entire relaying/re-

    routing is planned to be laid underground with effective cover of minimum 1.2 M below the

    ground level.

  • VIMTA Labs Limited, Hyderabad 3

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    The route map of re-routed pipelines are provided in Annexure – I.

    The proposed pipelines will be hooked up to the existing pipeline system at Korukkupet exchange pit. Scraper facilities shall be provided at Foreshore and Korukkupet Terminals. Necessary surge relief system and thermal relief valves are provided for safety with underground storage for the released oil.

    Suitable Mass Flow Meters (MFMs) shall be provided at Korukkupet and Foreshore Terminals to measure the incoming and outgoing flow.

    FST and Korukkupet would be provided with hot standby PLC based station control system to perform local control functioning and to monitor and control

    The field instrumentation at FST & Korukkupet stations would comprise pressure transmitters, pressure switches, pressure gauges, mass flow meters, temperature gauge, temperature transmitter, scraper detector, emergency shut down switches etc.

    Station Control Centre (SCC) would have workstations as operator interface to the station instrumentation and control system, on dual local area network (LAN) in client server mode.

    230 V UPS system with dual battery back up would be provided at Korukkupet and Foreshore Terminal.

    Optical fibre cable shall be laid along with the main line which will be connected through a Ethernet cum land switch at both the ends. The same shall be used for data transfer between the 2 stations.

    Through Optical Fibre network the PLC system for automation shall be hooked up through LAN network. A separate server shall be integrated with the automation system. The requisite information for the purpose of control and monitoring of the pipeline shall be

    acquired with suitable application software installed in the server. Leak detection software also shall be installed in the server which will collect the data from the system and work on a real time basis.

    Fire detection & alarm system: For the Control building, smoke detectors and rate of rise (RoR) heat detectors along with Fire Alarm Panel and SIL-2 rated PLC with HMI have been considered for all attended stations.

    Fire Suppression system: Besides portable Fire extinguishers, CO2 flooding would be

    provided in cable trenches, hydrants. Water monitors would be provided suitably in the piping area. The numbers and type of extinguisher would be in line with OISD 214.

    Hydrants and Water monitors would be provided suitably in the piping area. Firewater network (with required number of Water monitors and hydrants with double landing valves) would be provided. Medium Velocity Water Sprinkler system considered for piping and metering and scrapper barrel area.

    VIMTA Labs Limited, Hyderabad 4

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    3.0 SCOPE, OBJECTIVE & METHODOLOGY

    3.1. Scope

    The scope of this RRA study covers the three underground pipelines (20”, 14” and 12.75”) for white oil, black oil and lube oil to be installed adjacent to the railway track between Korukkupet and Foreshore Terminals in North Chennai.

    3.2 Objective

    The objectives of this study are as follows:

    Identify major accident scenarios associated with the storage and handling of hydrocarbons in the pipeline system

    Carry out consequence analysis for the significant accident scenarios

    Carry out Rapid Risk assessment (RRA), and

    Identify measures for risk reduction wherever warranted.

    3.3 Methodology

    Risk arises from hazards. Risk is defined as the product of severity of consequence and likelihood of occurrence. Risk may be to people, environment, assets or business reputation. This study is specifically concerned with risk of serious injury or fatality to people.

    The following steps are involved in Rapid Risk Assessment (RRA):

    Study of the plant facilities and systems.

    Identification of the hazards.

    Enumeration of the failure incidents.

    Estimation of the consequences for the selected failure incidents. Risk analysis taking into account the failure frequency, extent of consequences and

    exposure of people to the hazards. Risk assessment to compare the calculated risk level with risk tolerability criteria and

    review of the risk management system to ensure that the risk is “As Low As Reasonably Practicable” (ALARP)

    The process of Rapid Risk Assessment (RRA) is shown in the following block diagram in Figure 3.1.

    VIMTA Labs Limited, Hyderabad 5

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    FIGURE-3.1 FLOW DIAGRAM OF RAPID RISK ASSESSMENT (RRA)

    3.3.1 Consequence Analysis

    Consequence analysis for the selected failure scenarios is carried out using DNV Phast software which provides results for selected failure scenarios such as the following:

    Dispersion of toxic clouds to defined concentrations

    Heat radiation intensity due to pool fire and jet fire

    Explosion overpressure

    Phast stands for ‘Process Hazard Analysis Software Tool’. It uses Unified Dispersion Modeling (UDM) to calculate the results of the release of material into the atmosphere.

    Phast has extensive material database and provides for definition of mixtures. Phast software is well validated and extensively used internationally for consequence and risk analysis.

    VIMTA Labs Limited, Hyderabad 6

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    3.3.2 Rapid Risk Analysis (RRA)

    The Rapid Risk Analysis (RRA) is carried out using the renowned DNV software Phast Risk Micro (previously known as SAFETI Micro) version 6.7.

    The following input data are required for the risk calculation:

    Process data for release scenarios (material, inventory, pressure, temperature, type of release, leak size, location, etc.)

    Estimated frequency of each failure case

    Distribution of wind speed and direction (wind rose data). Distribution of personnel/ population in the plant/ adjoining area during the day and

    night time. Ignition sources

    Failure frequencies are estimated using generic failure databases published by organizations such as UK Onshore Operator’s Association (UKOPA).

    UK Onshore Operator’s Association (UKOPA) 1962-2012. It presents collaborative

    pipeline and product loss incident data from onshore Major Accident Hazard Pipelines (MAHPs)

    operated by National Grid, Scotia Gas Network, Wales & West Utilities, Shell UK, BP,

    Huntsman and E-ON UK, covering operating experience up to the end of 2012. The overall

    failure frequency over the period 1962 to 2012 is 0.227 incidents per 1000 Km/year. (Ref.

    UKOPA Report No UKOPA/13/0047 issued December 2013).

    The failure frequency over the last 20 years is 0.080 incidents per 1000 km. year. For the last 5 years the failure frequency is 0.122 incidents per 1000 km. year, whilst in the previous report this figure was 0.108 incidents per 1000 km. year (covering the 5 year period up to the end of 2011).

    Selection of Failure Frequency Database

    UKOPA database is selected for this QRA study. It has by far the greatest detail, and enables great flexibility of analysis because of failure distribution with reference to causes. It gives the details in a format readily used in QRA.

    The database is designed to reflect the ways in which the UKOPA operators design, build,

    operate, inspect and maintain their pipeline systems. Although the pipeline and failure data

    are extensive, there are pipeline groups (e.g. large diameter, recently constructed

    pipelines) on which no failures have occurred; however, it is unreasonable to assume that

    the failure frequency for these pipelines is zero. Similarly, further pipeline groups exist for which the historical failure data are not statistically significant.

    UKOPA database contains extensive data on pipeline failures and on part-wall damage, allowing prediction of failure frequencies for pipelines for which inadequate failure data exist.

    For these reasons, it was chosen as the main source of failure information for this study

    VIMTA Labs Limited, Hyderabad 7

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Failure Data Analysis

    The total length of Major Accident Hazard Pipelines, above ground, below ground and elevated, in operation at the end of 2012 for all participating companies (National Grid, Scotia Gas Network, Northern Gas Network, Wales and West Utilities, BP, Shell UK, Huntsman and E-ON UK) is 22,113 km. The total exposure in the period 1952 to the end of 2012 is about 8, 32,775 km.yr.

    Transported Products

    The lengths of pipeline in operation at the end of 2012, by transported product, are shown in Table below.

    Table : Transported Products in Pipelines (km)

    Natural Gas (Dry) 20,344 Propylene 38.0

    Ethylene 1,140 Condensate 24.0

    Natural Gas Liquids 251 Propane 20.0

    Crude Oil (Spiked) 224 Butane 20.0

    Ethane 38

    Hydrogen 14 TOTAL 22,113

    Ignition

    There were 9 out of 189 (~5%) product loss incidents that resulted in ignition. Table below provides more detail:

    Table: Incidents that resulted in Ignition

    Affected Cause Of Fault Hole Diameter Class

    Component

    Pipe Seam Weld Defect 0-6 mm

    Pipe Ground Movement Full Bore and Above

    (18” Diameter Pipe)

    Pipe Girth Weld Defect 6-20 mm

    Pipe Unknown 6-20 mm

    Pipe Pipe Defect 0 – 6 mm

    Pipe Unknown 40 – 110 mm

    Pipe Lightning Strike 0-6 mm

    Bend Internal Corrosion 0-6 mm

    Bend Pipe Defect 6-20 mm

    The overall ignition probability in the present analysis has therefore been taken as 0.05.

    VIMTA Labs Limited, Hyderabad 8

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    The overall incident frequency by hole size over the period 1962 - 2012 is shown in Table below

    Table: Failure Frequency distribution by hole size

    Hole Size Class Number of Frequency [Incidents

    Incidents per 1000 km.yr]

    Full Bore* and Above 7 0.008

    110mm – Full Bore* 3 0.004

    40mm – 110mm 7 0.008

    20mm – 40mm 23 0.028

    6mm – 20mm 31 0.037

    0 – 6mm 116 0.139

    Unknown 2 0.002

    Total 189 0.227

    VIMTA Labs Limited, Hyderabad 9

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Incident Frequency by cause Table: Products loss Incidents by Cause

    Product Loss Cause No. of Incidents

    Girth Weld Defect 34

    External Interference 41

    Internal Corrosion 2

    External Corrosion 41

    Unknown 7

    Other 41

    Pipe Defect 13

    Ground Movement 7

    Seam Weld Defect 3

    Total 189

    Figure: Products Loss Incidents by Cause - Historical

    VIMTA Labs Limited, Hyderabad 10

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    An overview of the product loss incident frequency by cause and size of leak in the period 1962 to 2012 is shown in Figure below.

    Figure: Products Loss Incidents by Cause & Leak Size

    * Full Bore = diameter of pipeline # Equivalent hole diameter is the circular hole diameter in mm with an area equivalent to the observed (usually non-circular) hole size

    VIMTA Labs Limited, Hyderabad 11

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External Interference

    External Interference by Diameter Class

    Figure below shows the product loss incident frequencies associated with external interference by diameter class and by hole size.

    Figure: Products Loss Incidents by External Interference – Diameter Class

    Table: Exposure by Diameter Class

    Diameter Exposure Incidents Frequency/1000km.yr

    inches km.yr

    0-4 41098 5 0.122

    5-10 170268 20 0.117

    12-16 138055 9 0.065

    18-22 121019 3 0.025

    24-28 134607 3 0.022

    30-34 39945 1 0.025

    36-48 186783 0 0.000

    Total 832775 41 0.049 VIMTA Labs Limited, Hyderabad 12

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External Interference by Measured Wall Thickness Class The relationship between product loss incidents caused by third party interference and wall thickness is shown in Figure below.

    Figure: Products Loss Incidents by External Interference - Wall Thickness Class

    Table: Exposure by Wall Thickness Class

    Wall

    Exposure

    Frequency Thickness Incidents

    km.yr /1000 km.yr mm

    15 66818 0 0.000

    Total 832775 41 0.049

    VIMTA Labs Limited, Hyderabad 13

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External Interference by Area Classification Figure: Products Loss Incidents by External Interference – Area Classification

    Table: Exposure by Area Classification in km. yr.

    Area Exposure Incidents Frequency /1000 Classification km.yr km.yr

    Rural 754858 30 0.040

    Suburban 76847 11 0.143

    Urban 1069 0 0.000

    Total 832775 41 0.049

    VIMTA Labs Limited, Hyderabad 14

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External Corrosion by Wall Thickness Class

    Figure: Products Loss Incidents by External Corrosion - Wall Thickness Class

    Table: Exposure by Wall Thickness Class

    Wall Thickness Exposure km. yr Incidents

    Frequency/

    mm 1000 km. yr

    15 66818 0 0.000

    Total 811923 40 0.048

    VIMTA Labs Limited, Hyderabad 15

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External Corrosion by External Coating Type

    Figure: Products Loss Incidents by External Corrosion – Coating Type

    Table: Exposure by External Coating Type

    External Exposure Incidents

    Frequency /

    Coating km.yr 1000 km.yr

    Bitumen 30798 3 0.097

    Coal Tar 597009 26 0.044

    Polyethylene 79704 4 0.050

    FBE 84111 0 0.000

    Other/Unknown 41153 8 0.194

    Total 832775 41 0.049

    VIMTA Labs Limited, Hyderabad 16

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External Corrosion by Type of Backfill Figure: Products Loss Incidents by External Corrosion – Backfill Type

    VIMTA Labs Limited, Hyderabad 17

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Estimating IOCL Pipeline Failure Frequency

    The overall failure frequency reported in UKOPA database is 0.227 incidents per 1000 km. year over the period 1962 to 2011, and 0.122 incidents per 1000 km.year the last 5 years.

    The failure frequency for IOCL Pipeline is estimated by applying suitable adjustment factors to UKOPA data as shown in Tables.

    Pipeline size : 14 inches

    Operating Pressure : 7 bar

    Area Classification : Rural

    Table: Failure Frequency Adjustment Factors for 14” IOCL Oil Pipeline

    Adjustment Factors for Pipeline Failure Frequency

    S. Parameter Actual Ratio: Actual Adjustment

    No. Value value/ Database factor

    Value

    1.0 External

    Interference

    1.1 Diameter class 14 inches 0.065 / 0.049 1.326

    1.2 Wall thickness class 7.1 mm 0.061 / 0.049 1.244

    1.3 Area classification Rural 0.040 / 0.049 0.816

    Avg. factor for 1.128

    external

    interference

    2.0 External

    Corrosion

    2.1 Wall thickness class 7.1 mm 0.041 / 0.048 0.854

    2.2 Coating type 3 LPE 0.050/0.049 1.020

    2.3 Backfill type 1.000

    2.4 Year of Construction 1.000

    Avg. factor for 0.968

    external corrosion

    3.0 Internal corrosion 1.0

    4.0 Pipe defect 1.0

    5.0 Girth weld defect 1.0

    6.0 Seam weld defect 1.0

    7.0 Ground 1.0

    movement

    VIMTA Labs Limited, Hyderabad 18

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Table: Adjusted Failure Frequency for 14” IOCL Oil Pipeline

    Adjusted Pipeline Failure Frequency for Pipeline S. Cause Incidents in UKOPA Data Adjustment Adjusted

    No. base (Ref: Table 6) factor for Factor for

    No. of Fraction 14” IOCL 14” IOCL

    Incidents Oil Pipeline Oil Pipeline

    1. External 41 0.217 1.128 0.244

    interference 2. External corrosion 41 0.217 0.968 0.210

    3. Internal corrosion 2 0.011 1 0.011

    4. Pipe defect 13 0.069 1 0.069

    5. Girth weld defect 34 0.180 1 0.180

    6. Seam weld defect 3 0.016 1 0.016

    7. Others 41 0.217 1 0.217

    8. Unknown 7 0.037 1 0.037

    9 Ground Movement 7 0.037 1 0.037

    Total Incidents 189 1.000 1.021

    Base failure 0.122 per 1000 km.yr

    frequency (UKOPA

    – last 5 yrs.)

    Adjusted failure 0.122 x 1.021

    frequency for 14” = 0.125 per 1000 km.yr (1.25 x 10-4

    per km.yr) IOCL Oil Pipeline

    VIMTA Labs Limited, Hyderabad 19

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Pipeline size :20 inches

    Operating Pressure : 7 bar

    Area Classification : Rural

    Table: Failure Frequency Adjustment Factors for 20” IOCL Oil Pipeline

    Adjustment Factors for Pipeline Failure Frequency

    S. Parameter Actual Ratio: Actual Adjustment

    No. Value value/ Database factor

    Value

    1.0 External

    Interference

    1.1 Diameter class 14 inches 0.065 / 0.049 0.510

    1.2 Wall thickness class 7.1 mm 0.061 / 0.049 1.244

    1.3 Area classification Rural 0.040 / 0.049 0.816

    Avg. factor for 0.856

    external

    interference

    2.0 External

    Corrosion

    2.1 Wall thickness class 7.1 mm 0.041 / 0.048 0.854

    2.2 Coating type 3 LPE 0.050/0.049 1.020

    2.3 Backfill type 1.000

    2.4 Year of Construction 1.000

    Avg. factor for 0.968

    external corrosion

    3.0 Internal corrosion 1.0

    4.0 Pipe defect 1.0

    5.0 Girth weld defect 1.0

    6.0 Seam weld defect 1.0

    7.0 Ground 1.0

    movement

    VIMTA Labs Limited, Hyderabad 20

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Table: Adjusted Failure Frequency for 20” IOCL Oil Pipeline

    Adjusted Pipeline Failure Frequency for Pipeline S. Cause Incidents in UKOPA Data Adjustment Adjusted

    No. base (Ref: Table 6) factor for Factor for

    No. of Fraction 20” IOCL 20” IOCL

    Incidents Oil Pipeline Oil Pipeline

    1. External

    41 0.217 0.856 0.185 interference

    2. External corrosion 41 0.217 0.968 0.210

    3. Internal corrosion 2 0.011 1 0.011

    4. Pipe defect 13 0.069 1 0.069

    5. Girth weld defect 34 0.180 1 0.180

    6. Seam weld defect 3 0.016 1 0.016

    7. Others 41 0.217 1 0.217

    8. Unknown 7 0.037 1 0.037

    9 Ground Movement 7 0.037 1 0.037

    Total Incidents 189 1.000 0.962

    Base failure 0.122 per 1000 km.yr

    frequency (UKOPA

    – last 5 yrs.)

    Adjusted failure 0.122 x 0.962

    frequency for 20” = 0.118 per 1000 km.yr (1.18 x 10-4

    per km.yr) IOCL Oil Pipeline

    VIMTA Labs Limited, Hyderabad 21

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    RISK ANALYSIS

    The results of Rapid Risk Analysis are commonly represented by the following parameters:

    Individual Risk

    Societal Risk

    Individual risk is the risk that an individual remaining at a particular spot would face from the plant facility. The calculation of individual risk at a geographical location in and around a plant assumes that the contributions of all incident outcome cases are additive. Thus, the total individual risk at each point is equal to the sum of the individual risks, at that point, of all incident outcome cases associated with the plant.

    The individual risk value is a frequency of fatality, usually chances per million per year, and it is displayed as a two-dimensional plot over a locality plan as contours of equal risk in the form of iso-risk contours as shown in the following Figure 3.7.

    FIGURE-3.7 ISO-RISK CONTOURS ON SITE PLAN (TYPICAL)

    3.3.3 Risk Tolerability Criteria

    For the purpose of effective risk assessment, it is necessary to have established criteria for tolerable risk. The risk tolerability criteria defined by UK Health & Safety Executive (UK-HSE) are normally used for risk assessment in the absence of specific guidelines by Indian authorities.

    UK-HSE has, in the publications “Reducing Risk and Protecting People” and “Guidance on ALARP decisions in control of major accident hazards (COMAH)” enunciated the tolerability criteria for individual risk.

    VIMTA Labs Limited, Hyderabad 22

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Indian Standard IS 15656:2006 provides guidelines for hazard identification and risk analysis.

    The risk tolerability criteria are as follows-

    An individual risk of death of one in a million (1 x 10-6

    ) per annum for both workers and

    the public corresponds to a very low level of risk and should be used as a guideline for the boundary between the broadly acceptable and tolerable regions.

    An individual risk of death of one in a thousand (1 x 10-3

    ) per annum should on its own

    represent the dividing line between what could be just tolerable for any substantial category of workers for any large part of a working life, and what is unacceptable.

    For members of the public who have a risk imposed on them ‘in the widerinterest of society’ this limit is judged to be an order of magnitude lower, at 1 in 10,000 (1

    x 10-4

    ) per annum.

    The upper limit of tolerable risk to public, 1 x 10-4

    per year, is in the range of risk due to

    transport accidents. The upper limit of broadly acceptable risk, 1 x 10-6

    per year, is in the range of risk due to natural hazard such as lightning. The tolerability criteria for individual risk are shown in Figure 3.8.

    Risk

    to Risk to

    Personnel Publi

    c

    Intolerable Risk

    10

    -3 per year

    10-4

    per year

    Risk Tolerable

    If ALARP

    10

    -6 per year 10

    -6 per year

    Broadly

    Acceptable

    FIGURE-3.8 INDIVIDUAL RISK CRITERIA

  • VIMTA Labs Limited, Hyderabad 23

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    3.3.4 Societal Risk (or Group Risk) Criteria

    Societal Risk parameter considers the number of people who might be affected by hazardous incidents. Societal risk is represented as an F-N (frequency-number) curve, which is a logarithmic plot of cumulative frequency (F) at which events with N or more fatalities may occur, against N.

    Societal risk criteria indicate reduced tolerance to events involving multiple fatalities. For example a hazard may have an acceptable level of risk for one fatality, but may be at an unacceptable level for 10 fatalities. The tolerability criteria for societal risk as defined by UK-HSE are shown in the following Figure 3.9.

    Figure 3.9: Societal Risk Criteria

    3.3.5 Risk Assessment

    Based on the results of RRA, necessary measures to reduce the risk to ALARP are to be formulated. For this purpose the information regarding top risk contributors provided by Phast Risk software is useful.

    VIMTA Labs Limited, Hyderabad 24

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    4.0 RAPID RISK ANALYSIS

    4.1 Input Data

    The failure scenarios and the relevant input data for RRA of IOCL Pipelines in North Chennai

    TABLE-4.1

    FAILURE SCENARIOS AND THE RELEVANT INPUT DATA

    Item Failure Scenario Fraction Total Failure

    Description of Total Rate

    Failure (per km.year)

    White Oil Small leak: 5 mm dia 60% 1.18 E-04

    Pipeline Medium leak: 25 mm dia 25%

    (20”) Large leak: 100 mm dia 10%

    Full bore leak 5%

    Black Oil Small leak: 5 mm dia 60% 1.25 E-04

    Pipeline Medium leak: 25 mm dia 25%

    (14”) Large leak: 100 mm dia 10%

    Full bore leak 5%

    4.2 Population Data

    The population across pipeline route is as shown in Table 4.2.

    TABLE 4.2 Population Data – IOCL North Chennai Pipeline Route

    Area Population

    0 – 3 km 8.50 lakhs

    3 – 7 km 14.24 lakhs

    7 – 10 km 9.81 lakhs

    4.3 Ignition Source Data

    The following ignition sources are considered along the pipeline route. - Railway line - Roads

    Appropriate data for traffic density and speed are used for input to Phast software.

    VIMTA Labs Limited, Hyderabad 25

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    4.3 Weather Data

    The weather data for the site required for dispersion analysis and RRA are provided in Table 4.3.

    TABLE 4.3 CLIMATOLOGICAL DATA, IMD CHENNAI (MINAMBAKKAM)

    Month Temperature (0C) Rainfall (mm)

    Max. Min. Monthly Total

    January 28.8 20.4 35.3

    February 30.5 21.1 13.0

    March 32.6 23.0 14.5

    April 34.7 25.8 15.9

    May 37.4 27.6 42.4

    June 37.3 27.4 53.9

    July 35.3 26.1 99.6

    August 34.5 25.5 129.9

    September 33.9 25.2 123.5

    October 31.8 24.2 284.6

    November 29.4 22.6 353.0

    December 28.4 21.2 146.3 Source: India Meteorological Department, Pune

    Wind rose diagrams for the site showing the distribution of wind direction and wind speed during a year are shown in the following figures.

    VIMTA Labs Limited, Hyderabad 26

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    FIGURE 4.1: ANNUAL WIND ROSE DIAGRAM – IMD, CHENNAI

    (MINAMBAKKAM)

    VIMTA Labs Limited, Hyderabad 27

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    4.5 Consequence Analysis Results

    In case of leaks from the IOCL Pipeline in North Chennai, the hazards are mainly pool fire and/or explosion due to accidental release of flammable liquids MS, HSD, ATF, Naptha, SKO and Fuel Oil.

    Pool fire heat radiation

    The effects of heat radiation from pool fire are shown in the following Table 4.4.

    TABLE 4.4

    EFFECTS OF HEAT RADIATION

    Heat Radiation Level Observed Effect (kW/m2)

    4 Sufficient to cause pain to personnel if unable to reach cover

    within 20 seconds; however blistering of the skin (second-degree burn) is likely; 0% lethality.

    12.5 Minimum energy required for piloted ignition of wood, melting

    of plastic tubing. 37.5 Sufficient to cause damage to process equipment.

    Vapour Cloud Explosion (VCE)

    When a large quantity of flammable vapour or gas is released, mixes with air to produce sufficient mass in the flammable range and is ignited, the result is a vapour cloud explosion (VCE).

    In case of large release of MS or Naphtha from pipeline there is potential for vapour cloud explosion (VCE). The damage effect of VCE is due to overpressure,

    The effects of overpressure due to VCE are shown in the following Table 4.5.

    TABLE-4.5

    EFFECTS OF OVERPRESSURE

    Over-pressure

    bar(g) psig Observed Effect

    0.021 0.3 “Safe distance” (no serious damage below this value);

    some damage to house ceilings; 10% of window glass broken.

    0.069 1 Repairable damage; partial demolition of houses, made

    uninhabitable; steel frame of clad building slightly distorted.

    0.138 2 Partial collapse of walls of houses.

    0.207 3 Heavy machines (3000 lb) in industrial buildings

    suffered little damage; steel frame building distorted and pulled away from foundations.

    VIMTA Labs Limited, Hyderabad 28

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Consequence analysis for leaks in the IOCL pipelines in North Chennai has been carried out for the following case:

    Leak from 25 mm diameter hole representing maximum credible scenario

    Results of consequence analysis by Phast software for the above scenarios are shown in the Table-4.6.

    TABLE-4.6

    CONSEQUENCE ANALYSIS RESULTS – MAX. CREDIBLE SCENARIOS

    Description Downwind Effect

    Distances (Metres)

    Wind speed & Atm. Stability class → 3 m/s; D

    Product: MS

    Leak Size: 25 mm

    Pool fire heat radiation intensity

    4 kW/m2

    41.3

    12.5 KW/m2

    20.6

    37.5 kW/m2

    8.4

    Vapour cloud explosion overpressure

    0.021 bar (0.3 psi) -

    0.069 bar (1 psi) -

    0.207 bar (3psi) -

    Product: HSD

    Leak Size: 25 mm

    Pool fire heat radiation intensity

    4 kW/m2

    40.5

    12.5 KW/m2

    20.2

    37.5 kW/m2

    8.2

    Vapour cloud explosion overpressure

    0.021 bar (0.3 psi) -

    0.069 bar (1 psi) -

    0.207 bar (3psi) -

    With respect to VCE scenario, it is to be noted that on the entire stretch lines are laid minimum 1.5 m below ground level and there is a on-time monitoring of flow characteristics and hence likelihood of accumulation of MS product on the surface is very remote.

    Graphical results of consequence analysis plotted on pipeline route map are provided in Annexure – II.

    VIMTA Labs Limited, Hyderabad 29

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    4.6 RRA Results

    4.6.1 Individual risk

    Iso-risk contours for individual risk along pipeline route near populated areas are shown in the following Figure 4.2. 4.3. 4.4 and 4.5.

    FIGURE-4.2 ISO-RISK CONTOURS FOR INDIVIDUAL RISK – OVERALL ROUTE

    1.0E-08 per year

    VIMTA Labs Limited, Hyderabad 30

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    FIGURE-4.3 ISO-RISK CONTOURS – ENLARGED VIEW FOR INITIAL SECTION

    1.0E-08 per year

    VIMTA Labs Limited, Hyderabad 31

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    FIGURE-4.4

    ISO-RISK CONTOURS – ENLARGED VIEW FOR MIDDLE SECTION 1.0E-07 per year

    1.0E-08 per year

    VIMTA Labs Limited, Hyderabad 32

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    FIGURE-4.5 ISO-RISK CONTOURS – ENLARGED VIEW FOR END SECTION

    1.0E-08 per year

    The maximum individual risk contour observed along the pipeline route is 1E-07 per year.

    Risk transects at different points show the value of maximum individual risk as 1.1E-07 per year

    This is in the “Broadly Acceptable Region” as shown in Figure 4.6.

    VIMTA Labs Limited, Hyderabad 33

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    Risk to

    Risk to Intolerable Risk

    Public

    Personnel

    10-3

    per year

    10-4

    per year

    Risk Tolerable if ALARP

    Max. Individual Risk to Public: 1.1 x 10

    -7 per year

    10-6

    per year

    10-6

    per year

    Broadly Acceptable

    Risk

    FIGURE-4.6 INDIVIDUAL RISK ALONG IOCL CHENNAI PIPELINE

    VIMTA Labs Limited, Hyderabad 34

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    4.6.2 Societal Risk

    The FN Curves for societal risk for sections along pipeline route with some nearby population are shown in Figure 4.7.

    FIGURE-4.7 SOCIETAL RISK FOR IOCL PIPELINES

    It is seen that the societal risk for the IOCL pipelines in North Chennai is well within the Acceptable region.

    VIMTA Labs Limited, Hyderabad 35

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    5.0 CONCLUSIONS & RECOMMENDATIONS

    5.1 Conclusions

    The results of this RRA study for the re-routed white oil and fuel oil oil pipelines of IOCL between Korukkupet and Foreshore Terminals lead to the following conclusions.

    Te maximum individual risk to members of the public is 1.1 X 10-7

    per year

    which is less than 1 x 10-6

    per year and therefore in the Acceptable level.

    Societal risk is generally in the Acceptable region.

    Consequence analysis for leaks in the pipeline system indicates that significant effect distances for pool fire heat radiation intensity fall within 50 metres of the pipeline for 25 mm leak corresponding to maximum credible scenario.

    The pipelines are laid minimum 1.5 m below ground level along the entire stretch and there is a on-time monitoring of flow characteristics and hence likelihood of accumulation of MS product on the surface lading to VCE scenario is very remote.

    The above results indicate that the re-routed pipelines of IOCL conform well to the risk criteria. IOCL are expected to ensure the best practices for safety management system, engineering, construction, operation and maintenance for the pipeline.

    The lube oil line is excluded petroleum as flash point is in the range of 200 C.

    The installation design and construction conform to relevant codes & standards including OISD and PNGRB guidelines. In particular the following safety features are note-worthy:

    Routing of pipelines along the railway corridor.

    Selection of design pressure and pipe wall thickness much higher than normal requirement.

    100% radiography test for girth welds in the pipelines

    3-Layer polyethyelene coating on pipelines

    SCADA system and optic fibre cable (OFC) data communication link

    Real time leak detection system for pipeline

    Regular pigging for preventive maintenance which will help to identify the potential

    defects and take advance action

    VIMTA Labs Limited, Hyderabad 36

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    External interference, also termed third party damage, constitutes the main cause for leaks in

    pipelines. While necessary provisions such as routing the pipeline along the railway line and provision of 1.2 m cover for the underground pipe are in place to minimize the possibility of

    such leakage in these pipelines, continuous efforts are required to maintain the systems in

    effective condition. These include pipeline markers, frequent patrols, effective liaison with local communities, utility distribution companies etc.

    In case of any leakage in pipeline, it is necessary to isolate the supply with minimum delay. For this purpose effective communication system with emergency control centre is to be established.

    - - - - x - - - -

    VIMTA Labs Limited, Hyderabad 37

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    ANNEXURE – 1

    IOCL CHENNAI PIPELINE ROUTE MAP

    VIMTA Labs Limited, Hyderabad 38

  • Rapid Risk Assessment Study for Re-Routing of Oil Product Pipelines in Chennai

    ANNEXURE – II

    CONSEQUENCE ANALYSIS RESULTS

    VIMTA Labs Limited, Hyderabad 39

  • ANNEXURE – I

    IOCL CHENNAI PIPELINE ROUTE MAP

  • ANNEXURE – II

    CONSEQUENCE ANALYSIS

  • CONSEQUENCE ANALYSIS

    1. Pipeline containing HSD

    Leak size – 25 mm Weather – Wind speed 3 m/s; Stability D Intensity radii for Pool Fire

    Page | 2

  • CONSEQUENCE ANALYSIS Pool Fire on Map

    Page | 3

  • CONSEQUENCE ANALYSIS

    Page | 4

  • CONSEQUENCE ANALYSIS

    2. Pipeline containing MS

    Leak size – 25 mm Weather – Wind speed 3 m/s; Stability D Intensity radii for Pool Fire

    Page | 5

  • CONSEQUENCE ANALYSIS Pool Fire on Map

    Page | 6

  • CONSEQUENCE ANALYSIS

    Page | 7