rampion 150kv onshore cable connection suppliers’ day 11 th february 2015

13
Rampion 150kV Onshore Cable Connection Suppliers’ Day 11 th February 2015

Upload: lauren-higgins

Post on 19-Dec-2015

221 views

Category:

Documents


1 download

TRANSCRIPT

Rampion 150kV Onshore Cable Connection Suppliers’ Day

11th February 2015

Overview of Carillion

2

The UK’s leading provider of integrated solutions for buildings, infrastructure and services

Carillion plc is listed on the FTSE and is within the Top 150 companies by Market Capitalization

Turnover of over c£4.0 billion in 2014 with 40,000 employees worldwide.

Business Segments – Construction Services, Support Services, Public Private Partnerships and Middle East

Operations in UK, Middle East, North Africa, Canada & Caribbean

Specific HSE actions and strategies

Carillion fully embrace the challenging Health and Safety Targets established for the Rampion Project, notably:

• Zero Harm• SIF (Serious Incident Frequency) 0.4• TRIF (Total Recorded Incident Frequency) 2.5• FOF (Falling Object Frequency) 0.5

Carillion will promote the current drivers used in our internal Behaving Safely campaign, striving towards our common goal of Target Zero. We are conscious that the engagement of everyone on the Team is key to this successful delivery, encouraging the right behaviours, empowering people to speak up and challenge others, and to look after one another. These common objectives are formally encouraged through our Safety Systems:

• Predict and Prevent• Don’t Walk By (DWB)• Leadership Plan including Engagement and Safety Action Groups

3

Key strategy/experiences

• Good communication is vitaloEngender culture of “no surprises”oProactive engagement with key stakeholders including

landowners and local communityo Interfacing contractors

• Alternative delivery techniques to minimise the Project build phase, reducing overall cost, minimising programme risk and mitigating disruption to the community:

o Trenching machines installing ducto MDPE pipe as opposed to traditional uPVCo Bespoke jointing tents

4

5

Previous Offshore Windfarm Experience

• Currently engaged on Dudgeon connection• Sherringham Shoal Windfarm Interconnector Cables• Ormonde Offshore Windfarm Interconnector Cables• London Array Offshore Windfarm Connection• Greater Gabbard Offshore Windfarm Connection• Lynne and Inner Dowsing Interconnector Cables• Thanet Offshore Windfarm Interconnector Cables

Scope of Work

• Design, supply, installation, testing and commissioning of onshore cable

• Cable system will be twin circuit 150kV cable installed in ducts.

• Key Project Metrics

• Cable corridor length 27km

• 162km of cable and duct to be installed

• 23 double circuit joint-bays

• HDDs installed as separate package

• Road crossings

6

7

Programme Highlights

• Mobilise the Project Office Late May

• 2 ‘Satellite’ Compounds follow Mid June

• Landowner liaison throughout project

• PE pipe deliveries to compounds starting June

• Hedge cutting & topsoil stripping from June

• Duct Installation July to October

• Cable installation and Jointing April to July ‘16

• Completion of Cable installation contract November ‘16

8

Trenching Machine

9

Wrapping Machine

10

Wrapping Machine

11

Principal Subcontract Packages

• Soil strip & Accommodation works

• Surveys - Condition, Ecological & Lidar

• Security

• Specialist Crossings

• Pre & Post Land Drainage

• PE Duct Fusion & Cable Jointing

• Traffic Management

• Testing

‘My Register’

• The first stage in our compliance requirements under the CDM regulations (regardless of if a project is CDM reportable or not)

• Suppliers able to manage their own details and updates on line

• Allows the capture and viewing of all Suppliers details on line

• Allows the performance of suppliers to be captured reviewed and managed

• Every supplier offered an order will need to be registered on this system.

12

Carillion plc. On-line accreditation

13

Thank you for your time today

Any questions?