ram services limited health and safety method statement ... · ram services limited health and...
TRANSCRIPT
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 1 of 15
Contract South Manchester 132kV Substation
Contract No J-4225
Document ref 4225/MS01 Revision status [Rev]
Prepared by Name Signed Date
Paul Haworth 07/05/10
Checked by
N K Dymott 07/05/10
Communicated to
Contracts supervisor
Foreman
Revised by Date Issued to Details
Copied to Date Copied to Date
JAB Simon O’Keeffe 07/05/10
Related documentation (delete or amend as
needed)
Ram Services Safe Working Guidance Notes
COSHH Assessments
Site Safety Rules
Other (specify)
Ram Services Limited Holyoake House 240-244 Lowerhouse Lane Burnley Lancashire BB12 6NG
Tel 01282 452211 Fax 01282 452244 Email [email protected]
File Master Copy
Site Master Copy
Circulation Copy
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 2 of 15
1 Work to be undertaken
a. This method statement relates to Concrete Survey Works.
b. The main work activities to be carried out are as follows;
i. Visual inspection
ii. Hammer testing
iii. Removal of 100mm core samples
iv. Insitu carbonation depth testing
v. Testing off site of concrete core samples
2 Location(s) of Work to be carried out
a. South Manchester 132kV substation compound (restricted access)
b. Gate access off Fairy Lane, Wythenshawe Road, Sale M33 2JU
3 Responsibility
a. Overall responsibility for the implementation of this procedure rests with the Foreman
(named above) in charge on site
b. The foreman concerned should ensure that all team members, sub-contractors and other
relevant parties are fully briefed on the content of this and other related documentation.
Details of all such briefings should be recorded on the form provided with this document.
Substation M33 2JU
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 3 of 15
4 Contact details
Ram Services Limited
Head Office Tel 01282 452211
Fax 01282 452244
Email [email protected]
Contracts Supervisor Nick Dymott 07802 554571
Site Foreman As above As above
UUE
Dave Oultram Mobile 07795 375006
JAB Design
Simon O’Keeffe Tel 01925 732200
Mobile 07768 975093
5 Supervision
a. Work will be supervised on site by the UUE nominated safety representative who shall be
present for the full duration of all work
6 Programme
a. One days work on 12 May 2010
7 First Aid
a. Nominated first aiders are as follows
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 4 of 15
8 Risk Assessment
Ref Hazard Persons at
risk
P S R Control measure P S R Link
1 Unfamiliar working environment Operatives 3 3 9 All operatives working on site shall receive site
induction training administered by UUE SAP
All operatives will be briefed upon, read and
understand the contents of this Risk Assessment
and Method Statement before any work is
undertaken. Ensure you have signed the record
sheet to the back of this document.
1 3 3
2 Construction operations Operatives 3 3 9 All Ram Services operatives shall wear as standard
the following personal protective equipment hard
hat, reflective vests and safety boots. Other types
of safety equipment will be worn as deemed
necessary by COSHH assessment and for
individual work activities, which will be
undertaken. Arc resistant overalls will be worn at
all times.
1 3 3
3 Contamination by fuel spillage Operatives
Environment
3 3 9 Use drip tray under all generators. Use funnel
when filling tanks and take care to avoid spillage
1 3 3
4 Working with vibrating tools Operatives 3 3 9 Breakers provide for other concrete repair works
will be Makita HMO81OT, which are rated at
10m/s and allow a trigger time of 1hour per eight-
hour day. Drills provided for drilling are rated at
7.5 m/s and allow a trigger time of 1 hour 18 mins
per day. Angle grinders used for cutting concrete
have a rating of 6.5 m/s and allow a trigger time 1-
1 3 3
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 5 of 15
hour 39 mins per day to be reviewed by operatives
and foreman.
Before using grinders or any vibrating equipment
ensure hands are warm and wear gloves at all times
to minimise impact on hands.
When using breakers, drills or other vibrating
equipment, share the works between operatives to
reduce the risk of hand arm vibration injury. Swap
tasks between breaking out, clearing debris and
filling back to reduce the risks further.
5 Use of construction chemicals Operatives 2 3 6 Comply with material supplier guidance sheets and
COSHH assessments, for correct handling and
storage.
1 3 3
6 Manual handling Operatives 2 2 4 Care should be taken when carrying heavy
materials, especially over uneven ground. Only
handle what you feel comfortable doing so.
In particular care should be taken when lifting
equipment or materials from the van, use two
people and employ good lifting techniques.
Task – The task to be undertaken involves lifting
and carrying materials from the van to the work
area. Materials on site, which may require lifting
will be, bagged materials in 25kg units and small
tools and a small generator.
Individual Capabilities. – Everyone on this
contract appear to be fit and healthy and have not
reported any difficulties in lifting or handling.
Load – None of the materials, which are being
1 2 2
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 6 of 15
used, should present a danger of being too heavy to
lift.
Environment – The environment where the works
will be undertaken is generally good under foot,
but does require carrying materials over loose
stones.
7 Abrasive wheels. Flying debris, sparks
etc
Operatives 2 3 6 All operatives will be trained in the use of abrasive
wheels and be competent to use the equipment.
Ensure that the wheels used for work on concrete o
steel is the correct wheel for the task to be
undertaken, ensure that the spindle speed of the
machine does not exceed the RPM of the wheel
being used.
During work involving use of grinders or cut off
saws, operatives shall wear appropriate skin, eye
and respiratory protection.
Operatives not involved in the work shall wear
similar protection, or stay well clear until such
work is complete
1 3 3
8 Working at height There is no work at height on this contract.
9 Working with cementitious products Operatives
Environment
2 2 4 Working with cement or cement-based products
can cause burns and associated industrial illnesses.
Cement can also cause environmental damage.
When mixing grout or cement operatives will wear
minimum safety glasses, rubber gloves overalls
and dust mask. When placing concrete repair
materials operatives will wear minimum safety
glasses, rubber gloves overalls. Any splashes to
1 2 2
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 7 of 15
skin must be washed off with clean water
immediately; slashes to eyes must be washed out
using eye bath and medical attention sought.
A mixing station will be set up with visqueen
placed on the ground to avoid contamination.
When washing out equipment do not allow water
to contaminate any watercourse or surface water
drains.
10 Use of small electrical plant Operatives 2 3 6 All plant and equipment shall be suitable for
purpose, checked and maintained in accordance
with current good practise. All electrical small
tools shall operate at 110V CTE, and have current
PAT certification.
Plant shall only be operated by experienced
operatives who are competent to do so. No plant
should be left to operate unattended at any time
and should be placed away in the works stores or
van when the plant is no longer being used.
All fuelled plant will have drip trays placed
beneath them to catch any fuel drips or spillages.
1 3 3
11 Works in an operational sub station Operatives
Building
3 4 12 Security to the site will be maintained at all times
by the safety standby man who will keep the gate
locked at all times.
All operatives shall wear arc resistant overalls at
all times.
All personnel working on the site to have attended
a site-specific Electrical Safety Briefing prior to
commencement. SAP to brief safety standby man
1 4 4
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 8 of 15
of all electrical safety issues prior to
commencement. Safety standby man is to oversee
works and supervise any electrical safety issues on
the site.
SAP is to ensure safety standby is aware of safety
clearances and put in place all necessary danger
notices, barriers and screens to create a safe
working zone.
All electrical equipment in close proximity to the
works is to be made dead prior to any work
activities commencing.
Work within marked safety zones only including
designated access routes from mess room.
Any items of plant exceeding 1.5m in length to be
carried by two persons, horizontally below waist
level under direct supervision by UU safety staff
All equipment located in the sub station is live and
therefore presents significant danger of electric
shock.
Do not interfere with any equipment.
Do not move or disturb anything without first
seeking permission from UU Safety Standby Man.
12 High Noise levels Operatives 2 3 6 Drilling works which will be undertaken create
high levels of noise, which is above 80db all
operatives within the work area will wear hearing
protection at all times.
1 3 3
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 9 of 15
13 Housekeeping Operatives
Other trades
2 2 4 Bad housekeeping resulting in an untidy work area
not only looks unprofessional but also can cause
injury to yourselves and others around you.
Clear materials and plant away when not in use.
Clear all debris arising from your works into
appropriate skips or bag up in rubble sacks and
stacked neatly in a safe place.
All cables and hoses will be routed as to not cause
trip hazards.
1 2 2
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 10 of 15
Explanatory notes on risk classification
Risk is the likelihood of potential harm from a hazard being realised. The extent of risk will depend on;
The likelihood/probability of that harm occurring
The potential severity of that harm ie of any resultant injury or adverse health effect
The population which might be affected by the hazard ie the number of people who might be exposed
The risk assessment should be reviewed if there is reason to suspect that they are no longer valid or there has been significant change in the matters to which they relate.
Probability that harm will occur * Potential severity of harm *
0 Almost impossible Probability close to zero 0 No harm No injury, damage, sickness or other
loss
1 Extremely unlikely Highly improbable, never known
to occur 1 Minor harm
Minor injury with short term effect,
minor damage or loss
2 Unlikely Improbable, remote chance 2 Moderate harm Lost time injury or illness, moderate damage or loss
3 Likely Possible, has happened occasionally
3 Serious harm Over 3 day injury or illness, substantial damage or loss
4 Extremely likely Probable, commonly occurs 4 Major harm Major injury, major damage or loss
5 Almost certain Inevitable, definite, continually occurs
5 Catastrophic harm Fatality (inc to public) or disabling illness, catastrophic damage or loss
Risk classification and required action;
Probability (P) * Severity (S) *
0 1 2 3 4 5
No harm Minor harm Moderate harm
Serious harm Major harm Catastrophic harm
0 Almost impossible - - - - - -
1 Extremely unlikely - 1 2 3 4 5
2 Unlikely - 2 4 6 8 10
3 Likely - 3 6 9 12 15
4 Extremely likely - 4 8 12 16 20
5 Almost certain24 - 5 10 15 20 25
Risk rating/classification
0 – 1 Low No action required
5 – 6 Low Maintain control measures to ensure as reasonably practicable the control of residual risk
8 – 16 Medium Apply control measures to reduce risk rating to a level as low as reasonably practicable
20 – 25 High activity not permitted – hazard to be avoided or risk considerably reduced
9 Resources
a. Labour - 1 No operative + 1 No engineer
b. Materials - Flexcrete Monomix or Fastfill
c. Plant - Generator and core drilling kit
d. Sub-contractors – None
Linked information to be considered in conjunction with this document
D Drawing / sketch M Method statement P Safe Working Procedure
G Published guidance F Health and Safety Plan O Other
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 11 of 15
10 Method Statements
a. Method 1
i. Attend site electrical safety briefing by SAP or Safety Standby Man and familiarise
ones self with the site and the safe routes to the work area. Ensure all switching is
complete and the work area is safe.
ii. Site generator on drip tray and route cables to work area through the safe zone.
iii. Working only from ground level, undertake visual inspection of all single post bus
bar support base slabs under consideration. Document findings
iv. Take photographs of all relevant features
v. At locations as directed by Ram Services technical staff, remove dust samples from
base of concrete posts using 12mm dia drill bits. Bag dust for testing off site
vi. Break out small areas of concrete or drill additional holes (12mm dia for insitu
testing for carbonation
b. Method 2
i. Determine locations for core samples
ii. Check surface of concrete with cover meter and mark out positions of reinforcement
bars
iii. Clearly mark position and size of core holes required
iv. At marked locations, drill concrete 100mm diameter x 200mm deep for core
sample. Break out core sample, rinse clean, tag and bag for subsequent testing
v. Flush holes clean with water and infill hole with cementitious repair mortar
11 Third Party Considerations
a. None
12 Interface with others
a. Liaise with JAB re structures to be investigated
b. Liaise with UUE SAP and standby man during works to ensure electrical safety is
maintained at all times
13 Monitoring requirements
a. Compliance with this method statement and general health and safety requirements will be
monitored through site safety audits carried out routinely by Ram Services management or
their appointed health and safety representatives
b. Issues raised by such checks will be discussed with the site foreman and any corrective
action implemented accordingly
c. Safety audit check findings should be recorded on the form provided for subsequent review
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 12 of 15
14 Emergency Procedures
a. Comply with instructions issued by UUE Safety Representative present
b. Summon emergency services (999) stating nature of emergency, working environment (eg,
high voltage substation compound etc) number and details of casualties and location
c. Site is at
United Utilities Electricity 132kV Substation
Fairy Lane, off B5397 Wythenshawe Road, Sale
d. Nearest hospital is at:
Trafford General Hospital
Moorside Road, Urmston, Manchester, Greater Manchester, M41 5SL
A&E onsite
http://www.nhs.uk/servicedirectories/Pages/ServiceSearch.aspx
15 Additional information required by employees/others
a.
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 13 of 15
Work Completion and Quality Handover Certificate
Contract Name and Job No
Client
Site Location
Location Works undertaken Completed
OK
Date
Site cleared and left clean and tidy on completion
Outstanding issues to be addressed (snagging)
This is to certify that all work covered by this method statement document has been completed in accordance with the
requirements detailed therein and to the clients satisfaction.
Job completed by (foreman)
Signed (foreman) Date
Job accepted by (client rep)
Signed (client rep) Date
Job completion reviewed by (Ram manager)
Signed (Ram manager) Date
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 14 of 15
Site Briefing Record
Contract Subject Site induction
Tool box talk
Contract No Documentation Ref Method statement/risk assessment
COSHH assessment
Start date Other (specify)
Date Name Signature Briefing by
Ram Services Limited Health and Safety Method Statement and Risk Assessment Documentation
L:\Completed contracts\J4201 - J4300\J-4222 JAB South Manchester 132kV Sub\4225 MS01.doc Page 15 of 15
CSCS Operative Skills Cards