Division / Business Unit: Corporate Services & Safety Function: Engineering Document Type: Procedure © Australian Rail Track Corporation Limited (ARTC) Disclaimer This document has been prepared by ARTC for internal use and may not be relied on by any other party without ARTC’s prior wri tten consent. Use of this document shall be subject to the terms of the relevant contract with ARTC. ARTC and its employees shall have no liability to unauthorised users of the information for any loss, damage, cost or expense incurred or arising by reason of an unauthorised user using or relying upon the information in this document, whether caused by error, negligence, omission or misrepresentation in this document. This document is uncontrolled when printed. Authorised users of this document should visit ARTC’s intranet or extranet (www.artc.com.au) to access the latest version of this document. CONFIDENTIAL Page 1 of 27 Rail Network Configuration Management EGP-03-01 Applicability ARTC Network Wide SMS Publication Requirement Internal / External Primary Source Document Status Version # Date Reviewed Prepared by Reviewed by Endorsed Approved 2.0 18 Apr 19 Configuration Management Administrator Configuration Manager Manager Standards General Manager Technical Standards 29/04/2019 Amendment Record Amendment Version # Date Reviewed Clause Description of Amendment 2.0 18 Apr 19 Appendix 2 NAN example updated to include new mandatory stakeholder of Train Control Systems Manager

Upload: others

Post on 15-Nov-2019

62 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Division / Business Unit: Corporate Services & Safety

Function: Engineering

Document Type: Procedure

© Australian Rail Track Corporation Limited (ARTC)

Disclaimer

This document has been prepared by ARTC for internal use and may not be relied on by any other party without ARTC’s prior wri tten consent. Use of this document shall be subject

to the terms of the relevant contract with ARTC.

ARTC and its employees shall have no liability to unauthorised users of the information for any loss, damage, cost or expense incurred or arising by reason of an unauthorised user

using or relying upon the information in this document, whether caused by error, negligence, omission or misrepresentation in this document.

This document is uncontrolled when printed.

Authorised users of this document should visit ARTC’s intranet or extranet (www.artc.com.au) to access the latest version of this document.

CONFIDENTIAL Page 1 of 27

Rail Network Configuration

Management

EGP-03-01

Applicability

ARTC Network Wide

SMS

Publication Requirement

Internal / External

Primary Source

Document Status

Version # Date Reviewed Prepared by Reviewed by Endorsed Approved

2.0 18 Apr 19 Configuration

Management

Administrator

Configuration

Manager

Manager

Standards

General Manager

Technical Standards

29/04/2019

Amendment Record

Amendment

Version #

Date Reviewed Clause Description of Amendment

2.0 18 Apr 19 Appendix 2 NAN example updated to include new mandatory stakeholder of

Train Control Systems Manager

Page 2: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Table of Contents

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 2 of 27

Table of Contents

Table of Contents ............................................................................................................................................. 2

1 Introduction ............................................................................................................................................. 4

1.1 Purpose .......................................................................................................................................... 4

1.2 Scope ............................................................................................................................................. 4

1.3 Configuration Management Manual ............................................................................................... 5

1.4 Configuration Management Standard ............................................................................................ 5

1.5 Procedure Owner ........................................................................................................................... 5

1.6 Responsibilities .............................................................................................................................. 5

1.7 Reference Documents ................................................................................................................... 5

1.8 Definitions ....................................................................................................................................... 6

2 Configuration Management ................................................................................................................... 8

2.1 Introduction ..................................................................................................................................... 8

2.2 Pre-Approval Activities ................................................................................................................... 8

2.3 Configuration Change Management .............................................................................................. 9

2.4 New Configuration Management Baseline ..................................................................................... 9

2.4.1 The Contract Baseline .................................................................................................................... 9

2.4.2 The Functional Baseline ............................................................................................................... 10

2.4.3 The Design Baseline..................................................................................................................... 10

2.4.4 The Commissioned Baseline ........................................................................................................ 10

2.5 The Product Baseline ................................................................................................................... 10

2.6 Configuration Assessment ........................................................................................................... 10

3 Network Alteration Notice (NAN) ........................................................................................................ 12

3.1 Introduction ................................................................................................................................... 12

3.2 Purpose ........................................................................................................................................ 13

3.3 Responsible Officer ...................................................................................................................... 13

3.4 Process ........................................................................................................................................ 13

3.5 Generate the NAN ........................................................................................................................ 13

3.6 Approval and Signoff .................................................................................................................... 16

3.7 Issue of Notification to Affected Parties ....................................................................................... 17

3.7.1 Train Notices ................................................................................................................................ 17

3.7.2 SAFE Notices ............................................................................................................................... 17

3.7.3 Train Operating Conditions (TOC) Amendment/Waiver................................................................ 17

Page 3: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Table of Contents

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 3 of 27

3.7.4 Route Access Condition (RAC) Notice ......................................................................................... 17

3.8 Changes to Planned Works ......................................................................................................... 17

3.9 Response to Incidents .................................................................................................................. 18

3.10 Close out of NAN ......................................................................................................................... 18

3.11 Independent Review of the CCL .................................................................................................. 18

3.12 NAN and CCL Auditing ................................................................................................................ 18

4 Design Change Management .............................................................................................................. 19

4.1 Inspection and Test ...................................................................................................................... 19

4.2 Verification of Design Integrity ..................................................................................................... 19

Appendix 1 – NAN Process Flowchart ................................................................................................... 22

Appendix 2 - Network Alteration Notice.................................................................................................. 23

Page 4: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Introduction

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 4 of 27

1 Introduction

1.1 Purpose

The purpose of this procedure is to

1. define rail network configuration management in ARTC;

2. provide tools for management and implementation of Configuration Management; and

3. provide guidance on Configuration Change and Network Alteration Notices including

documentation and approvals

1.2 Scope

This procedure covers all rail network items managed by ARTC, and the documentation that

describes these items. Rail network items include all assets, systems and related documentation

and software required to operate and maintain the ARTC rail network.

This procedure does not cover the assessment of new rail network equipment and systems from

a suitability perspective.

Specific detail on change management for infrastructure documents, operations documents and

for drawings is detailed in Table 1-1.

The following table clarifies what procedures are applicable:

Topic Procedures

to use

Procedure Title

Risk considerations for change

management

Regulatory Notification

RSK-PR-001

ARTC SMS

Risk considerations for change management

Regulatory Notification in accordance with the

ARTC Safety Management System (Manage

Accreditation – Variation and Change)

Changes to infrastructure

documents

EGP-01-01 Engineering Document Control

Changes to operations

documents

ARTC SMS ARTC SMS (Document Control)

New rail network equipment

and systems approval

EGP-21-01 New Equipment and Systems Approvals

New rail network drawings and

drawing updates

EGP-04-01

EGP-04-02

Engineering Drawings & Documentation

Drawing Management System (DMS)

Configuration management of

rail network items

EGP-03-01 Rail Network Configuration Management

Equipment data updating EGP-03-02

EGP-10-01

Equipment Register Updating & Maintenance

Asset Management System

Table 1-1 Applicable Procedures for Change Management

Page 5: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Introduction

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 5 of 27

1.3 Configuration Management Manual

This procedure refers to and must be read in conjunction with the Configuration Management

Manual EGN-03-01 for greater detail to deal with more complex projects and for training

purposes.

1.4 Configuration Management Standard

This configuration management procedure is based upon AS/ NZ 10007- 2003 Guidelines for

Configuration Management.

1.5 Procedure Owner

The Configuration Manager is the Procedure Owner and is the initial point of contact for all

queries relating to this procedure.

1.6 Responsibilities

The General Managers Asset are responsible for implementation of configuration management

within their area of responsibility in accordance with this procedure. General Manager(s) may

delegate their responsibility for defined scope of work to Project Managers or other staff. These

delegations can be for specific periods of time or for specific projects and shall be recorded for

audit purposes.

The General Managers Asset are also responsible for ensuring that an appropriate level of risk

assessment is performed per RSK-PR-001 for Major Periodic Maintenance and Capital Works

Projects identified in the Annual Work Program undertaken per PP-151.

The Configuration Manager is responsible for the provision of training in configuration

management, and for ensuring that configuration management auditing is taking place and that

audit findings are being responded to by responsible staff.

The General Manager Technical Standards is responsible for ensuring that an appropriate level

of risk assessment is performed per RSK-PR-001 for new equipment and systems introduced into

the ARTC Network per EGP-21-01.

1.7 Reference Documents

The following documents are referred to in this procedure:

• AS/ NZ 10007 – 2003 Guidelines for Configuration Management

• AS4292.1-2006 Clauses 6.3 and 6.4,

• AS4292.4-2006 Clauses 3.4, 4.3 and 7

• EGN-03-01 Configuration Management Manual

• EGP0301F-01 Network Alteration Notice

• EGP-03-02 Equipment Register Updating and Maintenance

• Network Information Books and diagrams

• PP-115 Asset Identification

• EGP-04-01 Engineering Drawings and Documentation

Page 6: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Introduction

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 6 of 27

• EGP-04-02 Drawing Management System [DMS]

• EGP-21-01 New Equipment and System Approvals

• Route Access Standard

• PP-130 Control of Software Configuration for Signalling & Communications Systems

• PP-151 Annual Work Program

• EGP-20-01 Project Management

• EGP-10-01 Asset Management System

• RSK-PR-001 Risk Management Procedure

• ARTC SMS – Safety Audit

• ARTC SMS – Manage Accreditation – Variation and Change

• OGP-30-01 Route Access Condition Notice

• OPE-PR-001 Preparation and Distribution of Operational Notices

1.8 Definitions

The following terms and acronyms are used within this document:

Term or acronym Description

Approved Alternative

Item

An item that has been type approved in accordance with EGP-21-01 and that

fulfils the function of the original item that it replaces.

ARTC Fixed Asset

Register (AFAR)

A register used for financials of all items of equipment within the ARTC Network.

Change Initiator The person initiating the change. This may be, for example, the ARTC Project

Manager, Major Works Alliance Partner, Area Manager, Project Delivery

Manager, Corridor Manager, or Maintenance Alliance Partner.

Configuration ▪ The Functional and Physical characteristics of an existing or planned product, or a combination of products.

▪ One of a series of sequentially created variations of a product.

Configuration Audit An audit of the functional and physical status of an item and the documents

which fully describe it (specifications, design reports, drawings, test reports,

commissioning reports, user manuals etc)

Configuration

Baseline

Configuration of a product and the documents which fully describe it, formally

established at a specific point in time, which serves as reference for further

activities.

Configuration Change

List (CCL)

A list of configuration items and the changes required to be made to them.

Configuration Item A non-specific term used to denote any product, including systems, materials,

parts, software, subassemblies, sets, accessories, etc.

Configuration

Management

Technical and Organisational activities comprising of configuration identification,

configuration control, configuration status accounting and configuration auditing

and provides the necessary management controls that enable:

▪ The orderly establishment, recording, and maintenance of a product’s

performance, functional and physical characteristics.

Page 7: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Introduction

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 7 of 27

▪ Orderly management and control of changes to the product’s

characteristics.

Configuration

Management Plan

A Configuration Management Plan describes how Configuration Management is

accomplished and how consistency between the product’s definition, its

configuration, and the configuration management records is achieved and

maintained throughout the applicable phases of the product’s life. Guidance is

provided in EGN-03-01 Configuration Management Manual

Equipment Register

(Ellipse)

A register of all items of Network equipment and data within the Network. Refer

EGP-03-02 Equipment Register Updating & Maintenance for more information.

General Managers

Asset

General Manager Asset Management – Interstate Business Unit

General Manager Asset Delivery – Hunter Valley Business Unit

Network Information

Books and Diagrams

Network Information Books and associated line diagrams can be found on the

ARTC website at https://www.artc.com.au/customers/operations/nib/

MST Maintenance Schedule Tasks - an instruction to perform a specific maintenance

inspection.

Network Any defined infrastructure or operational system, on / off track maintenance /

measuring equipment that is required for the purpose of creating or supporting

ARTC deliverables.

Network Alteration

Notice (NAN)

The form used to coordinate the notification and authorisation of a configuration

change.

Product Something that is used or produced to satisfy a need or is as a result of a

process (e.g., documents, facilities, firmware, hardware, materials, processes,

services, software, systems,).

Project Management

Procedure

EGP-20-01 Project Management is the primary document for reference and

further guidance is provided in the supporting work instructions and templates

depending on whether a project is deemed to be simple or complex

Route Access

Condition (RAC)

Notice

Document used to approve changes to the Route Access Standard (RAS)

Manual between versions of the RAS Manual

SAFE Notice Document used in NSW to advise temporary and permanent changes to

Safeworking Rules and Procedures. Also used to advise changes to

infrastructure as detailed in Network Information Books (NIBs)

TOC

Amendment/Waiver

Document used in NSW to advise temporary and permanent changes to the

Train Operating Conditions Manual (TOC Manual).

TMP Technical Maintenance Plan

Train Notice Document used in SA, Vic and WA to advise permanent changes to the Code of

Practice for Operations and Safeworking (TA02 and TA20). Also used to advise

temporary changes to operating conditions.

Page 8: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Configuration Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 8 of 27

2 Configuration Management

2.1 Introduction

Configuration Management (CM) in ARTC is a risk control and change management process that

is applied over the life cycle of the network or a product to provide visibility and control of its

functional and physical characteristics. This is usually due to maintenance or approved project

activity.

This process comprises of six integrated process elements; Management Responsibility,

Planning, Configuration Identification, Configuration Control, Configuration Status Accounting and

Configuration Auditing, as shown in Figure 1.1.

Figure 1.1 Configuration Management Model

In broad terms it can be split into the following areas:

1. Pre–Approval activities

2. Configuration Change Management

3. New Configuration Management Baseline

2.2 Pre-Approval Activities

During this period assessments are undertaken to determine the changes required to the

configuration of particular items to meet requirements. During this stage there are no changes to

the configuration of the current items or the documents that fully describe them. Activities in this

period include:

1. Identify rail network items and where relevant identify the Asset Category or Type from

the Asset Register;

2. Describe the Scope of Works which is judged to be reportable per ; ARTC SMS –

Manage Accreditation – Variation and Change

3. Conduct a Risk Assessment per RSK-PR-001 on the defined changes of the activity;

CONFIGURATION MANAGEMENT PROCESS

MANAGEMENT RESPONSIBILITY

AUDITS STATUS ACCOUNTING

CONTROL IDENTIFICATION PLANNING

ORGANISATION

RESPONSIBILITIES

TRAINING

CONTRACT

REVIEW

CM PLAN

CM TOOLS

ITEM

IDENTIFICATION

BASELINES

ENGINEERING RELEASE

CONFIGURATION IDENTIFIERS

FORMAL CHANGE PROCESS

DATA RECORDING

MANAGEMENT REPORTS PHYSICAL

CONFIGURATION VERIFICATION

FUNCTIONAL CONFIGURATION

VERIFICATION

Page 9: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Configuration Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 9 of 27

4. Prepare the Network Alteration Notice (NAN) including the Configuration Change List

(CCL) as required; and

5. Plan the implementation of the configuration change.

2.3 Configuration Change Management

The commencement of this stage is when the formal approval is granted for a project (or other

configuration change) to proceed. This is linked with the Project Plan approval for the work to

proceed and the fulfilment of all applicable regulatory requirements per ARTC SMS – Manage

Accreditation – Variation and Change.

During this stage the configuration of the item is modified or changed in accordance with the

approved project scope. During change implementation, variation from the approved

specifications may be required. The variance is recorded and authorised by the responsible

manager in accordance with their delegation of authority. Variances are to be managed using the

Network Alteration Notice to approve and communicate the change. Approved variances are

recorded in the documentation of the as built configuration of the affected items. Refer to Section

4 for Design Change Management.

For complex projects the management of this change is by an approved Configuration

Management Plan that is prepared under the guidance of the Project Management Procedure

and Project Management Plan template EGW2001T-01. The template for the Configuration

Management Plan is provided as EGN0301T-01. Change notification is achieved using the

Network Alteration Notice (NAN) detailed in Section 3. The NAN/CCL is a live document and

may change during the course of the project.

For simple projects consideration of Configuration Management issues is to be included in the

Project Management Plan. Notification of change management is achieved using the NAN.

Detailed guidance on change management and development of configuration baselines for

complex projects is provided at Section 4.5.1 of EGN-03-01 Configuration Management Manual.

For configuration changes arising during maintenance, changes cannot commence until the NAN

is approved.

2.4 New Configuration Management Baseline

For complex network changes, there will be several configuration baselines between specification

and final commissioning. These can include the functional, design and allocated baselines per

EGN-03-01 Section 4.5.

Configuration baselines should be established whenever it is necessary to define a reference

configuration during the product life cycle, which serves as a starting point for further activities.

The level of detail to which a product is defined in the configuration baseline is dependent on the

degree of control required.

2.4.1 The Contract Baseline

The Contract and any Functional and Performance Specifications shall be placed under

configuration control at the commencement of the contracted activity (Contract Effective Date or

as soon as possible after). These documents form the contract baseline. These documents shall

be released on a controlled circulation through the CM process under the authority of the Project

Manager and recorded on the Document Management System.

Page 10: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Configuration Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 10 of 27

2.4.2 The Functional Baseline

The Functional Configuration Baseline consists of the functional configuration documentation,

which describes the systems functional performance, interoperability, interface requirements, and

the verifications required to demonstrate the achievement of those specified requirements. The

proposed Functional Configuration Documentation (e.g. Customer Requirements or Design Brief)

shall be released prior to the Preliminary Design Review, for review and agreement at the

Preliminary Design Review. The Functional Baseline is established following Functional

Configuration Documentation approval and Preliminary Design Review close out.

2.4.3 The Design Baseline

The Design Configuration Baseline consists of the approved design configuration documentation,

which is the combined performance and design documentation utilised for the production and

procurement of a product, it may include documentation on tooling and production processes.

The proposed Design Configuration Documentation shall be released prior to the Design Review,

for review and agreement at the Design Review. The Design Baseline is established following

Design Review close out.

2.4.4 The Commissioned Baseline

The Commissioned Configuration Baseline consists of the “marked up” approved design

configuration documentation. This documentation is established after close out of the Functional

and Physical configuration audits and prior to the commencement of operation. The

documentation shall be released prior to the Product Configuration “As Built” Baseline.

2.5 The Product Baseline

The Product Baseline consists of the approved product configuration documentation, which is the

“As Built” documentation. The Product Baseline is established after the commissioned baseline

has been formally drafted and then released.

This new baseline is typically, but not exclusively, described by the following:

▪ Specifications, design reports, drawings, user and maintenance manuals, spares lists,

test reports, updates to related documents and systems (eg. Ellipse), and commissioning

reports.

It is a requirement that all technical documentation relevant to the as-built configuration, per the

list above, be stored electronically in the applicable record management systems for ready future

access e.g. Drawings and Engineering Reports in the Drawing Management System (DMS),

Structures Documents in Ellipse and general Engineering Documents in Sharepoint.

2.6 Configuration Assessment

Configuration assessment is used to ensure that a configuration change complies with its

contracted or specified requirements and to ensure that a configuration change is accurately

reflected in the configuration data. At least two types of assessments shall be performed during

commissioning:

▪ Functional Configuration Assessment (FCA) which verifies whether the configuration item

meets the functional performance requirements specified.

Page 11: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Configuration Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 11 of 27

▪ Physical Configuration Assessment (PCA) which verifies whether the configuration item

meets the physical characteristics specified in the approved design documentation

(including any approved changes).

General audits will also be carried out for configuration compliance against project or

maintenance requirements per the standard audit program, as required by the Configuration

Manager from time to time.

Further details on configuration auditing may be found in Section 3.16, EGN-03-01 Configuration

Management Manual Section 7 and ARTC SMS – Safety Audit.

Page 12: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 12 of 27

3 Network Alteration Notice (NAN)

3.1 Introduction

The process of managing the configuration change of ARTC items; informing stakeholders and

obtaining approvals is undertaken though a Network Alteration Notice (NAN) as part of the

approval process during all project management or maintenance activities as shown in Figure 3-

1.

Figure 3-1 NAN and CCL flowchart for maintenance and project configuration changes

Page 13: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 13 of 27

3.2 Purpose

The NAN covers the requirement for the advice, approval and notification of Network alterations

which alter the operational capability, configuration, documentation or safe working requirements

of the ARTC Network and the maintenance of ARTC operational systems.

A Network alteration can be any software component, release, tool, documentation or hardware

unit required for the purpose of creating or supporting ARTC Network deliverables.

All Network alterations undertaken by ARTC, Alliance Partners and / or (sub) Contractors are

required to conform to this procedure.

3.3 Responsible Officer

The ARTC staff responsible for approving alterations to the Network are the relevant Corridor

Manager/Manager Maintenance (where titles vary, the manager shall be a direct report to the

relevant General Manager) or delegated officer and the relevant General Manager or delegated

officer.

3.4 Process

For complex projects, the NAN is written in the Project Assessment Phase, and is part of the

Project Approval. The NAN shall also be raised on commencement of a simple project, or when

maintenance action leads to a necessary configuration change. The aim is to report, record and

update system information that comes through the major / minor or periodic maintenance work

schedules, using the NAN as the approval form covering updated MST’s. There may be minor or

major changes to the NAN content during Detailed Design or Project Implementation. In the case

of minor changes to the NAN that do not alter the project objectives the project proceeds as

planned, and the NAN is updated with all such minor changes prior to commissioning. However in

the case of major changes that impact on project objectives, the amended NAN shall be re-

approved by the responsible manager. For complex projects, a revision to the Configuration

Management Plan shall be developed and approved.

During maintenance, changing an item with one of exactly the same manufacturer and part

number is not a configuration change.

Replacing an item with an approved alternative item is a configuration change and a NAN is

required. Approval of the NAN is not required when replacing an item with an approved

alternative item that does not result in any changes to the operational capability, configuration or

safe-working requirements of the ARTC Network; however distribution of the change information

on the unapproved NAN is required so that records can be updated.

3.5 Generate the NAN

The NAN is prepared and managed by the Change Initiator. The initiator can be an ARTC

employee or service providers and will be able to obtain a number from the system.

The Change Initiator assigns each NAN a number based on the NAN register. The Change

Initiator opens the NAN register, takes the next available number and fills in the Status, Date

Raised, who it was Raised By, the Jurisdiction of the change (eg North South, Hunter, East

West), the Location of the change, a short description of the change and the Project Number.

Page 14: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 14 of 27

The NAN register is available via the link shown on CONNECT under Our Network/Standards &

Procedures/Network Configuration. Each NAN number on the register is a link to a folder where

the configuration change documents are to be stored for use by the relevant stakeholders. Each

NAN folder contains the following sub-folders to help sort the information into clearly defined

sections:

01 NAN

02 CCL Confirmation

03 Ellipse Data

04 Drawings

05 Risk Assessment

06 Notices (SAFE, Train, Route Access Condition (RAC), Train Operating Condition (TOC)

07 Correspondence

When the NAN number is initially obtained, the Status column of the NAN register shall be filled in

with “Awaiting Approval”, or “Approval not required” in the case of approved alternative item

replacements. During the project or works, the status and other NAN details are to be updated to

reflect the progress of the configuration process.

Throughout the process, the NAN may have the following status:

• “Awaiting Approval” – before approval of the changes indicated on the NAN has been

gained.

• “Approved” – the changes proposed on the NAN have been approved.

• “On Hold” – the changes indicated on the NAN are put on hold.

• “Cancelled” – the changes indicated on the NAN have been cancelled.

• “Closed Out” – All changes indicated on the NAN have been completed and all required

Configuration systems updated, regulators informed where necessary (as per NAN Part 3

Item 11) and the completed Configuration Change List (CCL) has been signed off.

• “Approval not Required” - Network alterations that do not alter the operational capability,

configuration or safeworking requirements of the ARTC Network do not require approval

i.e. approved alternative item replacement.

The Date sent for Approval column shall have the date that the NAN was sent for approval

entered into it by the change initiator.

The Date Approved column shall have the date of approval of the NAN entered into it by the

change initiator.

The Date sent for Scope Change Approval column shall have the date that the NAN was sent for

approval entered into it by the change initiator.

The Date Scope Change Approved column shall have the date of approval of the NAN entered

into it by the change initiator.

The Project Start Date column shall have the date the project began entered into it by the change

initiator.

The Date of Practical Completion column shall have the date that the works being undertaken for

the project are completed entered into it by the change initiator.

Page 15: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 15 of 27

The date all items detailed in the CCL have been actioned shall be entered into the CCL Close

Out column by the change initiator.

The NAN Close Out date shall have the date that the NAN was closed out entered into it by the

change initiator.

EGP0301F-01 Network Alteration Notice (NAN) is available at:

https://extranet.artc.com.au/eng_all_form.html#configuration

The Change Initiator is required to complete the NAN (as per the following).

▪ Block 1: Enter the NAN Number and the details of the organisation responsible for the

configuration change.

▪ Block 2: Enter the Project details.

▪ Block 3: Enter details of the proposed change and works to implement the change.

▪ Block 4: Enter the location details of the proposed alteration.

▪ Block 5: Identify whether the project will affect network operations. To reach a decision,

the initiator may need to seek guidance from Network Controllers or Corridor Operations

Managers to determine how significant the effect would be. If the project is considered to

affect network operations, then the relevant Operations Manager must approve the

Network Alteration Notice. Details of the effect on operations are to be provided and a

Train / Safe Notice must be drafted as per Section 3.7.

▪ Block 6: Provide details of internal and external stakeholders who will be affected during

and after the alterations. Stakeholders identified in this section must also be included in

Part 3 to ensure that they receive notification during distribution of the NAN.

▪ Block 7: Provide a copy of the Risk Assessment for the project or maintenance works and

provide a schematic diagram showing the changes being made.

▪ Block 8: Approval of the NAN as discussed in Section 3.6

▪ Blocks 9 & 10: Should the scope of the work change significantly during the project or

activity, details of the scope change are to be provided in this section and approval of the

scope change is to be gained as per the instructions in Section 3.6. This change of scope

is to accompany financial approval documents.

▪ Block 11: Enter person and date of advice to inform regulators as per ARTC SMS –

Manage Accreditation – Variation and Change.

▪ Block 12: Identify Documents/Systems Requiring Update:

As part of the configuration management process, it is necessary to identify any systems and/or

documents which will require updating due to the changes resulting from the project,

maintenance or other activities identified in the NAN.

A tool to assist in identifying the relevant documents or systems to be updated is available by

contacting [email protected]

The details of the documents/systems requiring change are to be included in the Configuration

Change List at the end of the Network Alteration Notice or by using the form available from the

Document and System List tool.

Page 16: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 16 of 27

During the configuration change, all configuration items identified in the Configuration Change

List shall be updated to reflect the final status of the items involved in the configuration change.

The change initiator is to liaise with the relevant stakeholder responsible for the document or

system update and, also provide all relevant information to ensure that the information is correct,

and in the required format to enable the document or system to be accurately updated. The

stakeholders can be directed to the relevant NAN folder and its individual subfolders to locate the

configuration change information to enable the document or system to be updated. Once this

information has been compiled, the parties identified in the CCL are required to perform the

action listed and then advise the change initiator of the completion of the task.

Note 1: Refer to procedure EGP-03-02 Equipment Register Updating and Maintenance for

instructions on updating changes to configuration items and associated maintenance

scheduled tasks.

Note 2: During construction, if assets are installed into the active network and to be

commissioned at a later date, then the Change Initiator, in conjunction with the Area

Manager and Asset Data Administrator, is to ensure that the relevant MST’s are

activated as appropriate when the asset is initially installed.

The completion date of the update shall be entered onto the electronic version of the CCL stored

on the server. Once all the updates have been completed, the CCL shall be printed off and

signed off by the Change Initiator. The signed and completed CCL shall then be scanned into the

NAN folder and the paper copy filed with all the other project records. All updates are expected

to be completed within 60 days of the commissioning of the configuration change and the updates

shall be coordinated to meet the demands of the FAR.

▪ Blocks 13/14/15: Identify stakeholders who will need to be advised of the activities

detailed in the NAN and provide advice at the appropriate phase of the project or work

that meets the stakeholder’s needs. Some guidance on this matter is included in Part 3 of

the NAN. Stakeholders may be included on the CCL if they are involved in an activity to

update a document or system or may receive advice of the NAN for information only

purposes to assist with the performance of their duties.

A detailed NAN process flowchart is provided in Appendix 1 and an example of a NAN template is

provided in Appendix 2 Network Alteration Notice.

3.6 Approval and Signoff

In the case of maintenance changes or simple projects, the NAN is raised as soon as a need for

change is identified and forwarded by the Change Initiator to the Corridor Manager/Manager

Maintenance (or delegate per Section 1.6) and relevant General Manager (or delegate per

Section 1.6) for approval and sign-off prior to the start of the configuration change.

In the case of complex projects, the NAN is initially raised in accordance with the Configuration

Management Plan (CMP) guidance before detailed design commences and forwarded to the

approval authority identified in the CMP.

The date that the NAN was sent for approval shall be entered into the Date Sent for Approval

column of the NAN and register by the Change Initiator.

A NAN may be amended prior to approval.

Page 17: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 17 of 27

The NAN will be rejected if it does not align with the ARTC Network strategy or does not meet

with infrastructure and operational requirements. The initiator will be informed of the decision and

this will be recorded.

If the NAN is rejected, “Not Approved” must be entered in the Status column of the NAN register.

If the NAN is approved per the delegations in Section 1.5, “Approved” must be entered in the

Status column of the NAN register, and the date of approval entered into the Date Approved

Column of the register by the change initiator.

Approval of the NAN shall be sought for any changes to the NAN in particular the CCL Section. If

multiple “Scope Change Approvals” are required an additional Approvals sheet shall be

produced.

A NAN shall be produced and distributed for all Network alterations, but approval is NOT required

for Network alterations that do not alter the operational capability, configuration or safeworking

requirements of the ARTC Network i.e. approved alternative item replacement.

3.7 Issue of Notification to Affected Parties

The Change Initiator is responsible to advise the relevant corridor operators as detailed.

Notification advices are to be prepared and sent to the relevant parties for issue, so that

notification can be made at least two weeks prior to the change coming into effect.

3.7.1 Train Notices

Train Notices shall be produced and distributed in accordance with OPE-PR-001 Preparation &

Distribution of Operational Notices.

3.7.2 SAFE Notices

SAFE Notices shall be produced and distributed in accordance with OPE-PR-001 Preparation &

Distribution of Operational Notices.

3.7.3 Train Operating Conditions (TOC) Amendment/Waiver

TOC Amendments/Waivers shall be produced and distributed in accordance with OWP-01-00

NSW TOC Waiver Preparation.

3.7.4 Route Access Condition (RAC) Notice

RAC notices shall be produced and distributed in accordance with OGP-30-01 Route Access

Condition Notice.

3.8 Changes to Planned Works

If changes are required to previously issued NAN's and Train/SAFE Notices regarding the

planned dates or extensions to agreed track closures then, notice shall be given to the operations

project representative and the Assistant Planner (or Train Transit Manager (TTM) outside of

normal business hours) as soon as possible. An amended Train/SAFE Notice shall be issued

identifying when the works will be completed and referencing the previous versions of the

Train/SAFE Notice.

Page 18: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Network Alteration Notice (NAN)

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 18 of 27

3.9 Response to Incidents

NAN’s are only required for items that will incur a permanent change. For incidents a NAN shall

be retrospectively issued if permanent changes to the infrastructure will result from any

restoration works.

3.10 Close out of NAN

The close out of the NAN is achieved by completing Part 4. The Change Initiator shall confirm

that the following conditions are met:

▪ All changes indicated on the NAN have been completed and all required Configuration

Systems updated,

▪ and the completed Configuration Change List (CCL) has been signed off.

The Change Initiator shall sign off and date the NAN. The completed NAN shall be electronically

stored in the NAN register folder and the original hardcopy shall be stored with the project file.

The change initiator is responsible to ensure that the NAN register is updated to indicate that the

NAN has “Closed Out” in the status column and the date that the NAN was closed out shall be

entered into the “Close Out Date” column.

3.11 Independent Review of the CCL

An independent review is to be performed to ensure completeness and accuracy of the CCL after

it has been signed off as completed by the change initiator.

3.12 NAN and CCL Auditing

The relevant General Manager shall ensure the audit of the progress and completion of NAN's

and CCL's.

Emphasis shall also be given to auditing that NAN’s are approved prior to the commencement of

configuration changes. Further audit details are provided at Section 2.6 and in EGN-03-01

Configuration Management Manual Section 7.

Page 19: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 19 of 27

4 Design Change Management

4.1 Inspection and Test

ARTC utilises independent agents for the verification and validation of design integrity.

Verification is achieved by inspection and assessment against a checklist of items, which may be

more extensive than that required for construction certification. For example; the verification

activity will include inspection and assessment of the infrastructure against ARTC and

Contractor/Alliance Partner documented monitoring and maintenance practices.

There are various types of inspection and testing activities that can be carried out for given

condition parameters. Each inspection type has specific conditions it is aimed at detecting.

Visual and other inspection types are generally carried out for one the following reasons:

▪ To detect unsafe conditions, which may be expected to occur in the infrastructure

between other more detailed inspections,

▪ To detect unsafe conditions that may occur in the infrastructure due to accelerated

deterioration; and

▪ To detect faults that cannot be measured by any other means.

Verification methods by inspection or test must take into account the following considerations:

▪ Clear definition of the defect conditions that may be found from each inspection method.

▪ The ability of the inspection and test process to reliably detect the defect condition to an

appropriate accuracy.

▪ Location, method, level of detail and frequency of inspection and testing; and

▪ Control, calibration and maintenance of equipment used for inspection and testing.

4.2 Verification of Design Integrity

ARTC accepts changes to the design or configuration of the infrastructure on the basis that the

changes conform to an approved design. The acceptance process must include the verification of

integrated engineering and operating systems in terms of requirements, standards and designs,

and validation against ‘as built’ documentation.

The various verification and validation tasks during modification of infrastructure are the same as

those for the concept and design, construction and implementation, and commissioning phases of

the asset life cycle. These verification and validation tasks are listed at table A1 of AS4292.4.

Internal verification procedures are to include inspection, testing and monitoring of design,

commissioning and maintenance of the infrastructure, and independent audits of the

infrastructure changes and processes.

Figure 2.1 illustrates the verification of design integrity.

Page 20: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 20 of 27

Figure 2.1 Verification of Design Integrity

Figure 2.2 illustrates the relationship between the configuration management documentation,

change control and project phases.

Page 21: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 21 of 27

Figure 2.2 Relationship of CM Documentation to Baselines, Change Control and Project Phase

Page 22: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 22 of 27

Appendix 1 – NAN Process Flowchart

Page 23: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 23 of 27

Appendix 2 - Network Alteration Notice

Page 24: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 24 of 27

Page 25: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 25 of 27

Page 26: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 26 of 27

Page 27: Rail Network Configuration Management - ARTC - Extranet · Rail Network Configuration Management EGP-03-01 Configuration Management This document is uncontrolled when printed. Version

Rail Network Configuration Management

EGP-03-01

Design Change Management

This document is uncontrolled when printed. Version Number: 2.0 Date Reviewed: 18 Apr 19 Page 27 of 27