PERHITUNGAN VOLUME
I PEKERJAAN PERSIAPAN
No. JENIS PEKERJAAN PERHITUNGAN VOLUMEpanjang lebar tinggi/tebal berat jumlah volume satuan
1 Mobilisasi & demobilisasi
II PEKERJAAN ABUTMENT
No. JENIS PEKERJAAN PERHITUNGAN VOLUMEpanjang lebar tinggi/tebal berat jumlah volume satuan
1 Beton abutment bagian I dan II (K-350) 12 m 0.75 m 0.2 m 2 3.6012 m 1.5 m 2.1 m 2 75.6012 m 2.5 m 1 m 2 60.0012 m 1.5 m 0.4 m 2 7.212 m 0.5 m 0.4 m 2 2.4
148.802 Beton abutment bagian III (K-350) 12 m 2 m 8 m 2 384.00
12 m 2.5 m 0.4 m 2 1212 m 2.5 m 0.4 m 2 1212 m 7 m 1.5 m 2 252
660.003 Beton wing abutment (K-350) 1 m 2 m 0.2 m 4 1.6
1 m 2 m 8.5 m 4 681 m 2 m 3 m 4 12
81.604 Tulangan D 25 - 100 12.08 m 3.980 kg/m 202 9711.84 kg5 Tulangan D 19 - 100 9.80 m 2.250 kg/m 84 1852.20 kg6 Tulangan D 22 - 200 28.22 m 3.040 kg/m 102 8750.46 kg7 Tulangan D 22 - 200 9.80 m 3.040 kg/m 92 2740.86 kg8 Tulangan D 38 - 200 16.28 m 8.950 kg/m 102 14862.01 kg9 Tulangan D 25 - 200 9.80 m 3.980 kg/m 208 8112.832 kg10 Tulangan Ǿ 8 - 200 29.5 m 0.3942 kg/m 202 2348.84 kg
66.6 m 0.3942 kg/m 102 2677.65 kg53.22 m 0.3942 kg/m 102 2139.71 kg
7166.20 kg
III PEKERJAAN RANGKA JEMBATAN
No. JENIS PEKERJAAN PERHITUNGAN VOLUMEpanjang lebar tinggi/tebal berat jumlah volume satuan
1 Besi profil WF 400.200.8.13 30 m 66 kg/m 5 9900 kg2 Besi profil WF 600.300.12.20 10 m 151 kg/m 7 10570.00 kg3 Besi profil WF 200.200.12.12 375.97 m 56.2 kg/m 1 21129.51 kg4 Besi profil WF 400.300.10.16 266 m 107 kg/m 1 28462.00 kg5 Plat sambungan rangka t = 22 mm 0.90 m 1 m 0.22 m 7850 26 40411.80 kg6 Baut rangka Ǿ 3/4" 380 380 bh7 Baut melintang Ǿ 1/2" 84 84 bh8 Baut memanjang Ǿ 1/2" 140 140 bh9 Plat sambungan ikatan angin t = 10 mm 0.72 m 0.54 m 0.1 m 7850 26 7935.41 kg10 Baut ikatan angin Ǿ 1/2" 104 104 bh11 Elastomer 0.6 m 0.3 m 0.042 m 4 0.0312 Plat elastomer 0.59 m 0.29 m 0.004 m 7850 12 64.47 kg
IV PEKERJAAN PELAT LANTAI
No. JENIS PEKERJAAN PERHITUNGAN VOLUMEpanjang lebar tinggi/tebal berat jumlah volume satuan
1 Beton pelat lantai jembatan (K-275) 10 m 30 m 0.2 m 1 602 Lapisan aspal 8 m 30 m 1 2403 Tulangan tarik lapangan D 19 - 120 8 m 2.2242 kg/m 248.6667 4424.61 kg4 Tulangan bagi lapangan D 13 - 100 30 m 1.0417 kg/m 102 3187.50 kg5 Tulangan tarik tumpuan D 19 - 120 8 m 2.2242 kg/m 248.6667 4424.61 kg6 Tulangan bagi tumpuan D 13 - 100 30 m 1.0417 kg/m 102 3187.50 kg
V PEKERJAAN TROTOAR, SANDARAN DAN KERB
No. JENIS PEKERJAAN PERHITUNGAN VOLUMEpanjang lebar tinggi/tebal berat jumlah volume satuan
1 Beton trotoar (K-275) 1 m 30 m 0.25 m 2 152 Tulangan atas D 13 - 175 2.5 m 1.0417 kg/m 634 1649.95 kg3 Tulangan bagi Ø8 – 120 30 m 0.6158 kg/m 15 273.43 kg4 Pipa sandaran Ǿ 3" 30 m 6 180 m'5 Tulangan utama D 13 - 175 30 m 1.0417 kg/m 8 250.00 kg
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
kg/m3
kg/m3
m3
kg/m3
m3
m2
m3
6 Tulangan sengkang Ø8 – 120 0.6 m 0.6158 kg/m 345 127.42 kg
RENCANA ANGGARAN BIAYA
NO. JENIS PEKERJAAN VOLUME SATUAN
I PEKERJAAN PERSIAPAN1 Mobilisasi & demobilisasi 1 Ls 62,000,000 62,000,000
SUB TOTAL 62,000,000 II PEKERJAAN ABUTMENT1 Beton abutment bagian I dan II (K-350) 148.80 840,699 125,096,011 2 Beton abutment bagian III (K-350) 660.00 840,699 554,861,340 3 Beton wing abutment (K-350) 81.60 840,699 68,601,038 4 Tulangan D 25 - 100 9711.84 kg 8,650 84,006,758 5 Tulangan D 19 - 100 1852.20 kg 8,655 16,030,656 6 Tulangan D 22 - 200 8750.46 kg 8,662 75,793,290 7 Tulangan D 22 - 200 2740.86 kg 8,662 23,740,370 8 Tulangan D 38 - 200 14862.01 kg 8,576 127,452,785 9 Tulangan D 25 - 200 8112.83 kg 8,650 70,175,470
10 Tulangan Ǿ 8 - 200 7166.20 kg 8,647 61,965,681 SUB TOTAL 1,207,723,400
III PEKERJAAN STRUKTUR GELAGAR1 Besi profil WF 400.200.8.13 9900 kg 11,000 108,900,000 2 Besi profil WF 600.300.12.20 10570.00 kg 11,000 116,270,000 3 Besi profil WF 200.200.12.12 21129.51 kg 11,000 232,424,654 4 Besi profil WF 400.300.10.16 28462.00 kg 11,000 313,082,000 5 Plat sambungan rangka t = 22 mm 40411.80 kg 9,000 363,706,200 6 Baut rangka Ǿ 3/4" 380 bh 250 95,000 7 Baut melintang Ǿ 1/2" 84 bh 250 21,000 8 Baut memanjang Ǿ 1/2" 140 bh 250 35,000 9 Plat sambungan ikatan angin t = 10 mm 7935.408 kg 9,000 71,418,672
10 Baut ikatan angin Ǿ 1/2" 104 bh 250 26,000 11 Elastomer 0.03 m3 76,817,558.30 2,322,963 12 Plat elastomer 64.47 kg 9,000 580,234
SUB TOTAL 1,208,881,723 IV PEKERJAAN PELAT LANTAI1 Beton pelat lantai jembatan (K-275) 60.00 840,699 50,441,940 2 Lapisan aspal 240.00 94,000 22,560,000 3 Tulangan tarik lapangan D 19 - 120 4424.61 kg 8,655 38,294,667 4 Tulangan bagi lapangan D 13 - 100 3187.50 kg 8,640 27,540,000 5 Tulangan tarik tumpuan D 19 - 120 4424.61 kg 8,655 38,294,667 6 Tulangan bagi tumpuan D 13 - 100 3187.50 kg 8,640 27,540,000
SUB TOTAL 204,671,273 V PEKERJAAN TROTOAR, SANDARAN DAN KERB1 Beton trotoar (K-275) 15 840,699 12,610,485 2 Tulangan atas D 13 - 175 1649.95 kg 8,640 14,255,526 3 Tulangan bagi Ø8 – 120 273.43 kg 8,647 2,364,300 4 Pipa sandaran Ǿ 3" 180 m' 164,133 29,544,000 5 Tulangan utama D 13 - 175 250.00 kg 8,640 2,160,000 6 Tulangan sengkang Ø8 – 120 127.42 kg 8,647 1,101,819
SUB TOTAL 62,036,130 TOTAL 2,745,312,527
HARGA SATUAN (Rp.)
JUMLAH HARGA (Rp.)
m3
m3
m3
m3
m2
m3
REKAPITULASI RENCANA ANGGARAN BIAYA
NO. JENIS PEKERJAAN
I PEKERJAAN PERSIAPAN 62,000,000 II PEKERJAAN ABUTMENT 1,207,723,400 III PEKERJAAN STRUKTUR GELAGAR 1,208,881,723 IV PEKERJAAN PELAT LANTAI 204,671,273 V PEKERJAAN TROTOAR, SANDARAN DAN KERB 62,036,130
TOTAL 2,745,312,527 PPN 10% 274,531,253 JUMLAH 3,019,843,779 DIBULATKAN 3,253,372,000
JUMLAH HARGA (Rp.)
Terbilang : Tiga Miliar Dua Ratus Lima Ratus Lima Puluh Tiga Juta Tiga Ratus Tujuh Puluh Dua Ribu Rupiah
ANALISA HARGA SATUANItem pekerjaan : Mobilisasi san DemobilisasiSatuan : Ls
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
I Mobilisasi1 Alat ukur Unit 2 500,000 1,000,000 2 Alat berat Unit 5 5,000,000 25,000,000 3 Alat bantu lainnya Ls 1 5,000,000 5,000,000
II Demobilitasi1 Alat ukur Unit 2 500,000 1,000,000 2 Alat berat Unit 5 5,000,000 25,000,000 3 Alat bantu lainnya Ls 1 5,000,000 5,000,000
JUMLAH 62,000,000
ANALISA HARGA SATUANItem pekerjaan : Beton Mutu K-275Satuan :
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
I Tenaga1 Pekerja Oh 1.65 50,000 82,500 2 Tukang Oh 0.275 70,000 19,250 3 Kepala tukang Oh 0.028 85,000 2,380 4 Mandor Oh 0.083 95,000 7,885
II Bahan1 Pc kg 384 1,260 483,840 2 Pasir beton 0.43 250,000 107,500 3 Koral beton (maks 30mm) 0.64 175,000 112,000
III Alat1 Concrete Mixer jam 0.44 33,800 14,872 2 Concrete Vibrator jam 0.44 23,800 10,472
JUMLAH 840,699
ANALISA HARGA SATUANItem pekerjaan : PembesianSatuan : kg
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
I Tenaga1 Pekerja Oh 0.007 50,000 350 2 Tukang Oh 0.007 60,000 420 3 Kepala tukang Oh 0.0007 75,000 53 4 Mandor Oh 0.0003 90,000 27
II Bahan1 Besi beton 1.05 9,000 9,450 2 Kawat bendrat kg 0.015 13,500 203
JUMLAH 10,502
HARGA SATUAN (Rp.)
JUMLAH HARGA (Rp.)
m3
HARGA SATUAN (Rp.)
JUMLAH HARGA (Rp.)
m3
m3
HARGA SATUAN (Rp.)
JUMLAH HARGA (Rp.)
m3
ANALISA HARGA SATUANItem pekerjaan : Pengadaan dan pemasangan Pipa Sandaran Ǿ 3"Satuan : m'
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
I Tenaga1 Pekerja Oh 0.108 50,000 5,400 2 Tukang Oh 0.18 60,000 10,800 3 Kepala tukang Oh 0.018 75,000 1,350 4 Mandor Oh 0.054 90,000 4,860
II Bahan1 Pipa sandaran Ǿ 3" m' 1 115,000 115,000 2 Perlengkapan Pipa 0.2 115,000 23,000
JUMLAH 160,410
ANALISA HARGA SATUANItem pekerjaan : Pengadaan dan pemasangan Besi baja profilSatuan : kg
NO. URAIAN PEKERJAAN SATUAN KUANTITAS
I Tenaga1 Pekerja jam 0.012 50,000 600 2 Tukang jam 0.003 60,000 180 3 Mandor Oh 0.006 90,000 540
II Bahan1 Besi baja profil kg 1 11,000 11,000 2 Kayu perancah 0.0002 3,500,000 700
III Alat1 Crane jam 0.44 33,800 14,872 2 Crane on track jam 0.44 23,800 10,472
JUMLAH 13,020
HARGA SATUAN (Rp.)
JUMLAH HARGA (Rp.)
HARGA SATUAN (Rp.)
JUMLAH HARGA (Rp.)
m3