AE3S75 Project Management Distance Learning 2009-10 Quiz 01 (One) Answer the following questions by putting a cross (X) or tick () mark in the appropriate box. Sl. No. The question A B C 1 There are a min imu m of how man y bas ic characteristics of a project Two Three Four  2 Pro jec ts are “te mpo rary”, mea nin g a definite start and a definite end Yes No Something different 3 Pro jec ts are “te mpo rar y”, mea nin g a “…” period of time Short Long Finite 4 Ongo ing business effor ts are proje cts, not operational work. Yes No May be both 5 Dev elo pin g a new pro duc t is a pro jec t, not operational work Yes No May be both 6 Org ani sin g an awa ren ess pro gra mme against smoking in your locality is a project, not an operational work. Yes No May be both 7 Pro jec ts are rep etit ive in nat ure , whi le operational works are unique. Yes No May be both 8 Projects are temporary and unique Yes No Either one 9 Pro jec ts are oft en uti lis ed as a mea ns of attaining an organisation’s strategic plan Yes No The opposite 10 Proje ct manag ement refers to deal with initiating and Planning & executing Monitoring & controlling All of these 11 Proje ct manag ement is a proce ss, not a methodology Yes No Both 12 Pro jec t management and gen eral management use the same knowledge and skills Yes No Plus inter- personal skills 13 Interp erson al skills includ e leadership and motivation Yes No Only one of  the two 14 Proje ct manag ement mainly deals with routine works, whereas general management concerned with innovation Yes No The opposite AE3S75 Project Management, Quiz One: Page 1 of 3

Upload: ibraheem-sadiq

Post on 08-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Quizz 01 - Questions

8/7/2019 Quizz 01 - Questions

http://slidepdf.com/reader/full/quizz-01-questions 1/3

Page 2: Quizz 01 - Questions

8/7/2019 Quizz 01 - Questions

http://slidepdf.com/reader/full/quizz-01-questions 2/3

15 Widely known project management body of knowledge refers to that by

APM PMI Both

16 The term ‘knowledge area’ is used by APM PMI Both

17 Projects are usually parts of a programme Yes No The opposite

18 In large organisations, portfolios aremanaged by project management office

Yes No Not sure

19 Organisations manage their portfolios inorder to achieve specific goals

Yes No Not sure

20 According to BS 6079-1: 2002, the number of phases common to all projects in their life cycle is

Four Five Six

21 Project phases are usually sequential Yes No Notnecessarily

22 Project life cycle and product lie cycle arethe same

Yes No Notnecessarily

23 The completion & approval of one or moredeliverables characterises a project phase.

Yes No Notnecessarily

24 The main purpose of the inception phase isto document the user needs

Yes No Notnecessarily

25 The purpose of the feasibility phase is toestablish “…” viability.

Technical Financial andcommercial

All of these

26 The outcome o the feasibility phase isusually a written document, which contains:

Areas of difficulties& solutions

Initial estimatesof cost, time &

resources

All of these

27 Implementation phase is usually the largestphase of project life cycle and may need tobe died into several stages

Yes No Notnecessarily

28 The termination phase can itself be a project Yes No Never  29 Project stakeholders are Various

individualsVarious

organisationsBoth

30 Stakeholders cannot influence the project’sobjectives and outcomes

Yes No Never  

31 Who plays the central role in a project Projectsponsor 

Projectmanager 

Project team

32 Project stakeholders often have very

different or conflicting objectives

Yes No Never  

AE3S75 Project Management, Quiz One: Page 2 of 3