queanbeyan city council po box 90 - · pdf file27.04.2017 · queanbeyan city...
TRANSCRIPT
Queanbeyan City Council
PO BOX 90
QUEANBEYAN NSW 2620 Job No. CO377
Attn: Ms Eli Ramsland
1 July 2015
Re: Flooding Investigation for Proposed Crossing of the Queanbeyan River as part of
the Ellerton Drive Extension Project
Dear Madam,
This letter sets out the findings of an investigation which was undertaken on behalf of
Queanbeyan City Council (QCC) into the flood related impacts of the proposed bridge crossing of
the Queanbeyan River (Proposed Bridge) as part of the Ellerton Drive Extension Project (EDEP).
Figure 1 attached shows the extent of the EDEP and the location of the Queanbeyan River
Bridge.
The objectives of the investigation were to:
assess the impact of the Queanbeyan River Bridge on present day flood conditions during
a flood with an average recurrence interval (ARI) of 100 years;
undertake a bridge scour assessment for floods with ARI’s of 100 and 2000 years; and
provide a summary of hydraulic inputs for the design of the Queanbeyan River Bridge.
The followings sections of this letter provide background to the development of the hydraulic
model which was relied upon for the purpose of the current investigation, as well as the key
outcomes of the investigation.
1. Background to the Development and Updating of the Molonglo and Queanbeyan
Rivers Hydraulic Model
A one-dimensional unsteady flow hydraulic model of the Molonglo and Queanbeyan Rivers at
Queanbeyan was developed as part of the draft Queanbeyan Floodplain Risk Management Study
and Plan (L&A, 2008). The model was developed using the HEC-RAS software and was used to
define flooding behaviour along the two rivers for floods with ARI’s ranging between 5 and 500
years, together with an Extreme Flood Event (assumed to have a peak flow three times greater
than the 100 year ARI event). The existing hydraulic model has been denoted herein as the MQR
HEC-RAS Model.
The model was updated as part of the present investigation by inserting additional cross sections
in the vicinity of the Proposed Bridge. The additional cross sections were defined using detailed
ground survey along the proposed EDEP corridor. The updated model has been denoted the
pre-EDEP HEC-RAS Model. Figure 2 shows the layout of the pre-EDEP HEC-RAS model. For
the purpose of the present investigation the pre-EDEP HEC-RAS Model was run in steady state
mode.
Page 2
The proposed bridge arrangement was then added to the model to reflect post-EDEP conditions.
Details of the proposed bridge arrangement were based on 15% bridge design drawings prepared
by Opus on behalf of QCC. The updated model has been denoted the post-EDEP HEC-RAS
Model.
Discharge hydrographs used as input to the MQR HEC-RAS Model were generated by a RAFTS
model that was also developed as part of L&A, 2008 (MQR RAFTS Model). The MQR RAFTS
Model was updated as part of the present investigation to include design rainfall intensities for the
2000 year ARI event, procedures for which are set out in Section 3 of Book 6 of Australian
Rainfall and Runoff (IEAust, 1998). Figure 2 shows the discharge hydrographs which were
generated by the MQR RAFTS Model for the Queanbeyan River at Queanbeyan for the 100 and
2000 year ARI flood events.
2. Present Day Flood Behaviour
Figure 3 shows the extent of flooding in the vicinity of the Proposed Bridge, while Figure 4 shows
design water surface profiles extending from a location 490 m downstream of the Proposed
Bridge to the upstream boundary of the pre-EDE HEC-RAS Model for floods with ARI’s of 100 and
2000 years.
The key features of flooding behaviour in the vicinity of the Queanbeyan River Bridge at the
100 year ARI level of flooding are as follows:
i. Flooding along the river occurs to a maximum depth of about 11 m and a maximum width
of about 120 m.
ii. Floodwater is generally confined to undeveloped land along the river corridor. However,
it is shown to extend a short distance into a residential property which is located
immediately upstream of the Proposed Bridge on the southern bank of the river.
iii. The flood slope in the river is relatively flat in the vicinity of the Proposed Bridge, with a
computed slope of about 0.1 per cent.
iv. The average flow velocity in the river is about 2.4 m/s.
The key features of flooding behaviour in the vicinity of the Queanbeyan River Bridge at the
2000 year ARI level of flooding are as follows:
v. Flooding along the river occurs to a maximum depth of about 14 m and a maximum width
of about 180 m.
vi. Floodwater extends across a section of Barracks Flat Drive east of River Drive.
vii. The average flow velocity in the river is about 3.0 m/s.
3. Proposed Bridge Arrangement
As mentioned, the detailed design of the Proposed Bridge is currently being prepared by Opus on
behalf of QCC. Table 1 over the page gives details of the Proposed Bridge arrangement which
were taken from the 15% design drawings. Attachment A of this letter contains a copy of a
select number of the bridge drawings prepared by Opus.
Page 3
TABLE 1
DETAILS OF PROPOSED BRIDGE ARRANGEMENT
ITEM DIMENSION
No. of Spans 6
Length of Spans (m) 25 (Spans 1, 2 & 4), 38 (Spans 3 & 6), 33 (Span 5)
Total Length of Deck (m) 184
Pier Type 2 off 1500 mm diameter bored concrete piles aligned normal to
carriageway
Pier Skew to Direction of Flow 15 degrees
Abutment Type Spill-Through
Abutment Batter Slope 1V:1.5H
Elevation of Bridge Deck (m AHD) 591.8
Elevation of Bridge Soffit (m AHD) 589.6
Elevation of River Bed (m AHD) 567.8
4. Impact of Proposed Bridge on Flood Behaviour
Figures 3 and 4 show the impact the Proposed Bridge will have on the extent of flooding and
water surface elevations in the Queanbeyan River respectively for floods with ARI’s of 100 and
2000 years. Table 2 over the page sets out the difference in peak 100 year ARI flood levels at
the location of the HEC-RAS model cross sections under pre- and post-EDEP conditions (referred
to as “afflux”).
The increase in peak 100 year ARI flood levels upstream of the Proposed Bridge is attributed to
the hydraulic losses associated with flow around the bridge piers. Hydraulic losses due to the
bridge piers were modelled in the post-EDEP HEC-RAS Model using the Momentum Balance
Method, which was found to produce a head loss that was 0.22 m and 0.25 m higher than the
Energy and Yarnell equations, respectively (i.e. the Energy and Yarnell equations gave an afflux
immediately upstream of the Proposed Bridge of 0.07 m and 0.04 m, respectively compared to
0.29 m for the Momentum Balance Method). These results indicate that the computed increases
in peak flood levels attributable to the Proposed Bridge are sensitive to the method which is
adopted for computing pier losses. Further discussion on this issue is contained in Section 6 of
this letter.
Figure 4 shows that the impact of the Proposed Bridge on peak flood levels extends a significant
distance upstream of the road crossing, only reducing to 0.15 m at a location corresponding to the
upstream boundary of the hydraulic model. It is noted that the nearest development adjacent to
the Queanbeyan River is located a further 1.1 km upstream of the model limit.
While the length of river over which the Proposed Bridge will impact flood levels can be attributed
to the flat flood gradient, it is also a function of the higher hydraulic losses which have been
derived using the Momentum Balance Method.
It is also noted that the Proposed Bridge has the potential to increase peak flood levels by up to
0.29 m in the existing residential development which is located on the southern bank of the river
immediately upstream of the road crossing.
Page 4
TABLE 2
PEAK FLOOD LEVELS IN THE VICINITY OF QUEANBEYAN RIVER BRIDGE
100 YEAR ARI
River Station Location
Peak Flood Levels (m AHD)
Afflux (m) Pre-EDEP
Conditions
Post-EDEP
Conditions
7375 Upstream limit of post-EDE
HEC-RAS model 580.37 580.52 0.15
7167 580.01 580.19 0.18
6660 579.53 579.77 0.24
6424 579.29 579.55 0.26
6323 Upstream residential
property 579.17 579.45 0.28
6303 579.11 579.39 0.28
6294 Immediately upstream of
Queanbeyan River Bridge 579.09 579.38 0.29
6264 Immediately downstream of
Queanbeyan River Bridge 579.06 579.06 0
6255 579.06 579.06 0
6204 578.79 578.79 0
5772 490 m downstream of
Queanbeyan River Bridge 578.09 578.09 0
5. Bridge Scour Assessment
Damage to bridge approaches due to rare flood events can usually be repaired relatively quickly.
In comparison, major structural damage to a bridge can create safety hazards to motorists and
high social and economic costs to repair. For this reason, Waterway Design – A Guide to the
Hydraulic Design of Bridges, Culverts and Floodways (Austroads, 1994) recommends a greater
assurance that scour will not endanger the foundation of a bridge than is warranted for the design
of its approaches.
In accordance with Austroads, 1994 the following design floods have been adopted in the bridge
scour assessment:
100 year ARI for the design of protection works to the fill around bridge abutments and
bridge approaches; and
2000 year ARI flood event for the design of the bridge foundations under Ultimate Limit
State (ULS) load conditions assuming all stream bed material above the total scour line
has been removed and is not available for bearing or lateral support.
The bridge scour assessment was carried out using the post-EDE HEC-RAS model and the
in-built bridge scour function within the HEC-RAS software. Table 3 over the page provides a
summary of the bridge hydraulic results used in the scour depth assessment.
Page 5
TABLE 3
BRIDGE HYDRAULIC SUMMMARY
Hydraulic Characteristic
Design Flood Event
100 year ARI 2000 year ARI
Design Flow Rate (m3/s) 1440 2850
Peak Flood Level (m AHD) 579.4 582.5
Flow Depth
(m)
Northern
Abutment - 0.1
Southern
Abutment - 2.7
Pier 1 0.7 3.8
Pier 2 9.1 12.2
Pier 3 8.3 11.4
Pier 4 3.1 6.3
Pier 5 - 2.7
Flow Velocity(1)
(m/s)
Northern
Abutment - 1.5
Southern
Abutment - 1.5
Pier 1 0.9 1.6
Pier 2 2.4 3.0
Pier 3 2.4 3.0
Pier 4 1.0 1.5
Pier 5 - 1.5
1. Flow velocity is based on an average section velocity within the main channel and overbank areas.
Total scour depths were calculated by adding general contraction scour and local scour at each
pier and abutment. General contraction scour was calculated using the live -bed scour equation.
Local pier scour was calculated using the Colorado State University (CSU) equation, with project
pier widths adjusted to account for the greater of pier skew and debris accumulation. Project pier
widths for debris accumulation were calculated using the procedures set out in Hydraulic
Engineering Circular 18 - Evaluating Scour at Bridges, 5th
Edition (US FHWA, 2012). Local
abutment scour was calculated using the Froehlich’s Abutment Scour Equation.
Parameter assumptions adopted for the bridge scour assessment were based on the proposed
bridge arrangements summarised in Section 3 of this letter and geotechnical information
presented in the report entitled “Ellerton Drive Extension Geotechnical Investigation Report”
(Coffey, 2014). Attachment B of this letter contains a plan and long section of geotechnical
profiles which were extracted from Coffey, 2014.
The available borehole logs show the presence of shale and limestone rock at 2.5 to 3.2 m depth.
The rock is overlain with fill, colluvium and alluvium comprising sand, gravel and clays.
Page 6
Table 4 over the page summarises the estimated scour depths at the bridge abutments and piers
floods with ARI’s of 100 and 2000 years. Approximate depths to rock based at each pier and
abutment are also provided in Table 4.
The key features of the 100 year ARI bridge scour results are as follows:
i. The northern and southern bridge abutments are located outside the extent of flooding.
As a result, no scour protection measures are required around the bridge abutments to
protect against scour caused by flooding.
ii. Depth to rock is less than the scour depths computed by the HEC-RAS model. The depth
of the rock layer is therefore the limiting factor in the scour depth assessment.
iii. No scour will occur at the base of Pier 5 as it is located outside the extent of flooding.
iv. Due to the depth and velocity of flow experienced at Piers 1 to 4, rock riprap protection is
recommended to inhibit erosion and reduce maintenance. However, it cannot be relied
upon as a permanent scour counter measure in the design of the bridge piers. The
recommended arrangement is as follows:
o The riprap layer should extend a minimum distance of 3 m out from the base of
each pier.
o At Piers 1 and 4 the riprap layer should comprise a d50 rock size of 400 mm and
have a minimum thickness of 0.8 m, while at Piers 2 and 3 the riprap layer should
have a d50 rock size of 700 mm and a minimum thickness of 1.4 m.
o The riprap shall be graded in accordance with Table 6.2 or Austroads, 1994 and
be hard, dense, durable, resistant to weathering and free of overburden, spoil or
organic matter.
The key features of the 2000 year ARI bridge scour results are as follows:
i. The northern bridge abutment will be inundated to a depth of only 0.1 m during a 2000
year ARI flood, indicating significant scour of the spill-through abutment will not occur
during a flood of this return period.
ii. Depth to rock at the southern abutment, as well as at Piers 1 to 5 is less than the
scour depths computed by the HEC-RAS model. The depth of the rock layer is
therefore the limiting factor in the scour depth assessment.
6. Potential for the EDEP to Exacerbate Flooding Conditions in Existing Development
The present investigation found that depending on which method is used to compute the hydraulic
losses which will be imposed by the bridge piers, peak 100 year ARI flood levels could be
increased by as much as 0.29 m in existing residential development. While this increase is
considered to be an overestimate of the impact the bridge will have on peak flood levels upstream
of the bridge site, it does highlight the potential for the project to exacerbate flooding conditions in
several properties. Because of this, it is recommended that the two-dimensional (in plan)
hydraulic model which we have developed as part of the Kings Highway Upgrade project be
extended upstream to the bridge site to allow a check to be undertaken of the HEC-RAS model
results. It is also recommended that additional ground and floor level survey be commissioned
within the residential properties which are located immediately upstream of the Proposed Bridge
site. The survey would allow the nature of flooding in these properties to be more accurately
defined and for any flood mitigation measures to be scoped.
Page 7
TABLE 4
ESTIMATED SCOUR DEPTHS
Location Borehole
Approximate
Depth to
Rock(1)
Design Flood Event
100 year ARI 2000 year ARI
Contraction
Scour
Local Scour
(Abutment or
Pier)
Total Scour
Depth
Contraction
Scour
Local Scour
(Abutment or
Pier)
Total Scour
Depth
Northern Abutment TP46 / B-BH01 1.2 - - - - - -
Southern Abutment B-BH04 / B-BH05 3.2 - - - 1.1 6.9 8.0
Pier 1 B-BH01 0.0 1.0 2.6 3.6 1.7 4.5 6.2
Pier 2 B-BH02 2.8 0.8 6.1 6.9 1.1 6.9 8.0
Pier 3 B-BH02 / B-BH03 2.9 0.8 6.0 6.8 1.1 6.9 8.0
Pier 4 B-BH03 2.9 0.5 4.9 5.4 1.1 5.6 6.7
Pier 5 B-BH04 2.5 - - -(3) 1.1 4.2 5.3
(1) Approximate depth to rock is based on review of geotechnical information presented in Coffey, 2014.
Page 8
We trust that the findings presented in this letter will assist QCC in its understanding of the flood
related impacts of the Proposed Bridge and also Opus in progressing the bridge design. If we can
be of any further assistance in this matter, please do not hesitate the undersigned.
Yours faithfully
Lyall & Associates
Scott Button
Principal
FIGURES
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
TIME (hrs)
0
500
1000
1500
2000
2500
3000
3500
4000
DIS
CH
AR
GE
(m
3/s
)
LEGEND
2000 year ARI
100 year ARI
PROPOSED BRIDGE OVER QUEANBEYAN RIVERFLOODING INVESTIGATION
Figure 2
DESIGN DISCHARGE HYDROGRAPHSQUEANBEYAN RIVER AT QUEANBEYAN
PROPOSED BRIDGE OVER QUEANBEYAN RIVERFLOODING INVESTIGATION
SPA
CE
SPAC
Figure 4
WATER SURFACE PROFILES
5000 5500 6000 6500
570
575
580
585
590
Main Channel Distance (m)
Ele
vatio
n(m
)
Legend
2000 year ARI - Present Day
100 year ARI - Post Upgrade
Invert of River Bed
2000 year ARI - Post Upgrade
100 year ARI - Present Day
5772
5988
6204
6230
6255
6279
6303
6323
6424
6660
7167
7375
Queanbeyan River Upstream of CBD
TOE OF NORTHERN ABUTMENT
TOE OF SOUTHERN ABUTMENT
BRIDGE DECK
ATTACHMENT 1
ATTACHMENT 2