quarterly stormwater update · 9/26/2017 · quarterly stormwater update flood control projects...
TRANSCRIPT
QUARTERLY STORMWATER UPDATEFLOOD CONTROL PROJECTS
TONI ALGER, P.E. – CITY ENGINEER’S OFFICE/STORMWATER ENGINEERING CENTERSEPTEMBER 26, 2017
Aragona Drainage Improvements
Ashville Park Drainage Improvements
Central Resort District Drainage Improvements
Eastern Shore Drive Drainage
Lake Chubb/Bradford Lake
Sherwood Lakes Drainage Improvements
Stormwater Master Planning, Analysis and Inventory
Windsor Woods, Princess Anne Plaza, and The Lakes
DASHBOARD
2
FLOOD CONTROL PROJECTS IN THE FY 2018-2023 CIPCIP Number Project Name FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023 Total
Programmed
7400000 Aragona Drainage Improvements $ 1,400,000 $ - $ - $ - $ - $ - $ 1,400,000
7047000 Ashville Park Drainage Improvements $ 2,000,000 $ 3,000,000 $ 4,000,000 $ - $ - $ - $ 9,000,000
7041000 Central Resort District Drainage Improvements $ - $ - $ - $ - $ - $ - $ -
7151000 Eastern Shore Drive Drainage Phase I $ 1,000,000 $ 4,200,000 $ 6,200,000 $ 8,600,000 $ 7,000,000 $ 8,000,000 $ 35,000,000
7053000 Lake Chubb/Bradford Lake $ 1,084,100 $ 1,084,100 $ 1,084,100 $ 1,084,100 $ 1,084,100 $ 1,084,100 $ 6,504,600
7048000 Sherwood Lakes Drainage Improvements $ 1,000,000 $ 2,000,000 $ - $ - $ - $ - $ 3,000,000
7027000 SWM Master Planning, Analysis, and Inventory $ 2,700,000 $ 1,700,000 $ 800,000 $ 800,000 $ 800,000 $ 800,000 $ 7,600,000
7050000 Princess Anne Plaza Drainage Area $ 2,000,000 $ 3,000,000 $ 4,000,000 $ 4,000,000 $ 2,000,000 $ 5,000,000 $ 20,000,000
7051000 The Lakes Drainage Improvements $ 2,000,000 $ - $ - $ - $ - $ - $ 2,000,000
7028000 Windsor Woods Drainage $ 2,000,000 $ 1,500,000 $ 1,000,000 $ 5,000,000 $ 5,000,000 $ 2,000,000 $ 16,500,000
$ 15,184,100 $ 16,484,100 $ 17,084,100 $ 19,484,100 $ 15,884,100 $ 16,884,100 $101,004,600 $101,004,600
3
ASHVILLE PARK DRAINAGE IMPROVEMENTS, 7-047 Storm drain improvements
to address severe roadway and property flooding
Stormwater Pump Station Gated Control Structure at
Existing Outfall (Flanagans Lane)
Additional Stormwater Ponds
Temporary pumping in advance of significant rainfall events
Phase I Estimated Project Cost – $8.2M
4
ASHVILLE PARK DRAINAGE IMPROVEMENTS FIRST QUARTER ACTIVITIES▪ Pump down lakes in advance of forecasted significant rainfall
▪ Preliminary design underway – due December 2017
▪ Created a project web page: https://www.vbgov.com/government/departments/public-works/storm-water/Pages/ashville-park-sw.aspx
▪ Met with Developer to discuss cost participation agreement
▪ Gated control structure is under design; 100% design plans are due in October 2017
5
ASHVILLE PARK DRAINAGE IMPROVEMENTS FIRST QUARTER ACTIVITIES▪ Met with Fish & Wildlife to discuss project
▪ Made the following presentations:o April 5, 2017 – Ashville Park Civic Leagueo June 1, 2017 – ITA Committee Meetingo June 22, 2017 – Mrs. Henley’s Citizen Forumo July 18, 2017 – City Council Briefingo August 2, 2017 – Mrs. Henley’s “Everything Stormwater in the Southern
Watershed” Presentationo August 7, 2017 – Ashville Park Civic League
6
SHERWOOD LAKES DRAINAGE IMPROVEMENTS, 7-048
Project to address severe roadway and property flooding
Improvements include a pump station with a pipe connection between 2 lakes
Temporary Pumping in advance of rain event
Estimated Project Cost –$5M
7
SHERWOOD LAKES DRAINAGE IMPROVEMENTSFIRST QUARTER ACTIVITIES▪ May 2017, engineering analysis of the hydrology and hydraulics of
the two lakes was completed
▪ Lakes pumped down in advance of forecasted significant rainfall
▪ Improvements were identified to lower and maintain the elevation of the lakes to 3.0-ft
▪ Pump station vault and discharge pipes design underway –100% Complete
▪ Permanent Pump design underway – 30% complete
8
SHERWOOD LAKES DRAINAGE IMPROVEMENTSFIRST QUARTER ACTIVITIES▪ Numerous meetings with the developer, HAV
▪ Created a project web page: https://www.vbgov.com/government/departments/public-works/storm-water/Pages/sherwood-lakes-07-17.aspx
9
WINDSOR WOODS, PRINCESS ANNE PLAZA & THE LAKES, 7-028, 7-050, & 7-051
Detailed Engineering Analyses to develop the specific program of flood control measures
Projects combined for initial analysis
Analyses will Identifyo Needed Improvementso Cost of the Improvementso Implementation and Phasing
Plano Environmental Permitting
Required
10
WINDSOR WOODS, PRINCESS ANNE PLAZA & THE LAKESFIRST QUARTER ACTIVITIES▪ May 9, 2017 – Budget Approved
▪ May 10, 2017 – RFP for A/E Services Posted
▪ May 19, 2017 – Notice to Proceed Northgate Ditch Project ($2M)
▪ June 22, 2017 – SOIQs received
▪ June 27, 2017 – Notice to Proceed Windsor Woods Canal Project ($2M)
▪ July 11, 2017 – Notice to Proceed Windsor Oaks West II Canal Project ($850K)
11
WINDSOR WOODS, PRINCESS ANNE PLAZA & THE LAKESFIRST QUARTER ACTIVITIES▪ July 20, 2017 – Michael Baker International teamed with CDM
Smith selected
▪ October 2017 – Windsor Oaks West I Canal Project to be Completed ($800K)
▪ Created a project web page: https://www.vbgov.com/government/departments/public-works/storm-water/Pages/plaza-drainage-12-15.aspx
12
WINDSOR WOODS, PRINCESS ANNE PLAZA & THE LAKESFIRST QUARTER ACTIVITIES▪ Made the following presentations:
o June 13, 2017 – Princess Anne Plaza Civic League Stormwater Presentationo September 5, 2017 – City Council Briefingo September 12, 2017 – Princess Anne Plaza Civic League Stormwater
Presentation
13
ARAGONA DRAINAGE IMPROVEMENTS, 7-400
Neighborhood developed in the mid 1950s
Storm drain improvements to address severe roadway flooding
Project limits include the area south of Haygood Road and west of Aragona Blvd.
Under Design –Approximately 30% complete
Estimated Project Cost –$3.7M
14
ARAGONA DRAINAGE IMPROVEMENTSFIRST QUARTER ACTIVITIES▪ Modeling the area south of Haygood Road and west of Aragona
Blvd. to determine cause of flooding that occurred during Fall of 2016
▪ Overman Avenue was added to the project limits after excessive spread was observed at the storm drain inlets
▪ Received the 30% design plans; Scheduled to advertise for construction in July 2018
15
CENTRAL RESORT DISTRICT DRAINAGE IMPROVEMENTS, 7-041
Multi-phase project to address severe roadway flooding
Improvements include storm drains, tide gate, pump station & ocean outfall
Interim Project: Redirect approx. 15 ac. from 21st St and Baltic Ave. to 16th St. Pump Station; estimated project cost ~ $15M
ATD: $300K, BTC: $112.7M
16
CENTRAL RESORT DISTRICT DRAINAGE IMPROVEMENTSFIRST QUARTER ACTIVITIES▪ Central Resort Area Drainage Study Report and supplemental Beach
Garden Park Pump Station Alternative Analysis Report Completed
▪ Analysis underway to evaluate a potential stormwater management pond at the Visitor Center
▪ No further project activities due to funding constraints
17
EASTERN SHORE DRIVE DRAINAGE PHASE I,7-151 Multi-phase project Flood control drainage
improvements Improvements include
stormwater collection systems, tide gates & pump stations
Detailed Engineering Analyses to develop the specific program of flood control measures
Identify Early Implementation projects
18
EASTERN SHORE DRIVE DRAINAGE PHASE IFIRST QUARTER ACTIVITIES▪ Cape Henry Ditch Sluice Gates Completed (3 gates)
o Project Cost – $1.3M
▪ Detailed Engineering Analyses completed▪ 30% Plans completed▪ Cape Henry Canal Drainage Improvements design underway
o Provides an improved drainage outfall for the Shore Drive Corridor Improvements – Phase III project (CIP 2-117)
o Deepen and Widen canal between Starfish Road and Beech Street o Begin construction in July 2018o Estimated Project Cost – $8M
19
CHUBB LAKE/ LAKE BRADFORD, 7-053
Multi-phase project Storm drain improvements
to alleviate roadway flooding
Additional stormwater culverts under roadways
Tide control devices such as mechanized sluice gates
Stormwater management pond improvements
Channel and ditch clearing
LAKECHUBB
BRADFORDLAKE
CHESAPEAKE BAY
20
CHUBB LAKE/ LAKE BRADFORDFIRST QUARTER ACTIVITIES▪ May 10, 2017 – RFP for A/E Services Posted▪ June 14, 2017 – SOIQs Received▪ July 27, 2017 – RK&K Selected▪ August 10, 2017 – Scoping Meeting Held▪ First Phase:
o Public Involvemento Preliminary Engineering Report▪ Identify Early Implementation Projects▪ Develop Project Schedule
21
CHUBB LAKE/ LAKE BRADFORDFIRST QUARTER ACTIVITIES▪ Public Works is coordinating with the Navy
o April 19, 2017 – Lake Bradford outfall ditch maintenance coordination meetingo July 15, 2017 – Coordinated with base regarding access to perform
maintenance (snag and drag) on ditch from Lake Bradford to Weir Gateo August 8, 2017 – Update related to ditch maintenance from weir gate to Boone
Clinico August 28, 2017 – Pre-storm coordination for Nor-Eastero September 9 , 2017 – Pre-storm coordination for tropical depressiono September 18, 2017 – Pre-storm coordination for Hurricane Joseo September 25, 2017 – Pre-storm coordination Hurricane Maria
22
SWM MASTER PLANNING, ANALYSIS, AND MODELING, 7-027 Updating the City’s 31
Stormwater Watershed Models
Includes Preliminary Drainage Analysis to identify future Capital Drainage Projects
Models will allow Stormwater Engineering Center to provide drainage design parameters such as downstream water surface levels to developers for projects
Models will be kept up to date and reside in the Stormwater Engineering Center
23
SWM MASTER PLANNING, ANALYSIS, AND MODELINGFIRST QUARTER ACTIVITIES▪ Lynnhaven River Watershed
o Watersheds 3, 5, & 8 are completeo Watersheds 7, 4, 30 & 6 to be completed by the end of the year
▪ Southern Rivers Watershedo Watersheds 9 and 10 to be complete by the end of the yearo Watersheds 12-15 to be complete by February 2019o Watersheds 11, 16, 23-28 to be complete by April 2020
24
SWM MASTER PLANNING, ANALYSIS, AND MODELINGFIRST QUARTER ACTIVITIES▪ Little Creek Watersheds
o Watershed 31 to be complete by March 2018o Watershed 1 to be complete by April 2018
▪ Atlantic Ocean Watershed o Watershed 29 to be complete by April 2019
▪ Elizabeth River Watershedso Watershed 2 to be complete by April 2018o Watersheds 17-22 to be complete by July 2019
25
DISCUSSION