Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 1
Table of Contents
Executive Summary ........................................................................................................................................................................ 2 4th Quarter Highlights with a Look Ahead to Next Quarters: ...................................................................................................... 3
Active Construction Contracts Summary ..................................................................................................................................... 5 44th St. Vent Plant & 245 Park Ave. Entrance (CM004) .............................................................................................................. 8 Manhattan South Structures (CM005) ....................................................................................................................................... 10 50th St. Ventilation Facility (CM013) ........................................................................................................................................ 12 55th St. Ventilation Facility (CM013A) ..................................................................................................................................... 14 GCT Concourse & Facilities Fit-Out Early Work (CM014A) ................................................................................................... 16 Early Work for GCT and Facilities Fit Out (CM014MP) .......................................................................................................... 18 Vertical Circulation - Escalators & Elevators (VM014) ........................................................................................................... 20 Manhattan – MNR F/A Support (FMM19) ................................................................................................................................ 21 Queens Bored Tunnels and Structures (CQ031) ........................................................................................................................ 23 Plaza Substation and Queens Structures (CQ032) .................................................................................................................... 25 Harold Structure Part 1 and GO2 Substation (CH053) ............................................................................................................. 27 Harold Structures – Part 2A (CH054A)..................................................................................................................................... 29 Harold Stage 1 – Amtrak Force Account (FHA01) .................................................................................................................... 31 Harold Stage 2 – Amtrak Force Account (FHA02) .................................................................................................................... 33 Harold Stage 1 – LIRR Force Account (FHL01) ....................................................................................................................... 35 Harold Stage 2 – LIRR Force Account (FHL02) ....................................................................................................................... 37 Procure Harold Materials – Stage 2 (VHA/L02) ....................................................................................................................... 39 Harold and Point CILs – (VH051 Part 1) .................................................................................................................................. 40 Harold Tower Supervisory Control System (VH051 Part 2) ...................................................................................................... 42
Summary of Completed Contracts .............................................................................................................................................. 44 Contract Packaging Plan – Rev.9.6 ........................................................................................................................................... 47 Budget ........................................................................................................................................................................................ 50 Project Funding Status (As of December 31, 2013) ($ in Millions) ........................................................................................... 51 Status of Project Contingency .................................................................................................................................................... 52 Construction Safety .................................................................................................................................................................... 53 System Safety and Security ........................................................................................................................................................ 53 Quality Assurance ...................................................................................................................................................................... 53 Grand Central Terminal ............................................................................................................................................................ 54 Railroad Systems ....................................................................................................................................................................... 55 Operational Readiness/LIRR Start Up ....................................................................................................................................... 55 Public Outreach ......................................................................................................................................................................... 56 Real Estate ................................................................................................................................................................................. 57 Historic and Preservation Issues ............................................................................................................................................... 58
Federal Railroad Administration High Speed Rail and Harold Interlocking – NEC Congestion Relief Project .................. 59
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 2
Executive Summary
Construction Only $ 6,268.4 $ 4,001.2 64 % $ 3,484.8 56 % $ 3,389.7
Note: The budget and schedule reflect the June 2012. The budget excludes Rolling Stock reserve of $463M.
Contingency Summary (millions)
Contract Status Award Value (millions)
No. of Active 22 $ 1,943.6
No. of Completed 30 $ 1,797.0
Note: Excludes Access and Protection contracts
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 3
4th Quarter Highlights with a Look Ahead to Next Quarters:
Construction Safety:
Safety statistics reported for the project leveled during the 4th quarter (October to
December), averaging at 2.23 incidents per 200,000 work-hours. In 2013, the overall
project rate continued to improve with the lowest values reported during the third and
fourth quarters. The overall project rate continues to trend closer to the national industry
rate of 2.00.
The following key milestones were reached in the 4th quarter:
- Metro North Railroad (MNR) took over beneficial occupancy and opened the 245
Park Avenue Entrance on October 21, 2013. The new entrance to Grand Central
Terminal (GCT) was completed under the 44th St. Demolition & Construct Fan
Plant Structure & 245 Park Ave. Entrance (CM004) contract.
- Final completion was reached on November 30, 2013 for the 280 Park Avenue
work done under the 50th Street Ventilation Facility (CM013) contract. Substantial
completion for this contract is projected for the 1st quarter of 2014.
- Substantial completion was reached on December 23, 2013 for MTA’s first Small
Business Federal Mentor Program contract, Early Work for GCT and Facilities
Fit-Out (CM014MP), with final completion forecasted in the 1st quarter of 2014
Manhattan Construction:
Work began on the Manhattan South Structures (CM005) contract in the 4th quarter. The
contractor is progressing with concrete, shotcrete and waterproofing operations in the
GCT eastbound and westbound caverns and tail tracks.
Production blasting and rock excavation including the shaft will be completed in the 1st
quarter at the 55th Street Ventilation Facility (CM013A). Shotcrete operations in the
plenum have begun.
The Plaza Substations & Queens Structures (CQ032) contractor began environmental
work and concrete repairs in the existing 63rd Street eastbound tunnel and also started
concrete work for the Yard Lead tunnel invert. Concrete and steel work continues in the
open cut area. In preparation for the follow-on Systems contract, the B10 Substation and
other existing structure fit-outs (except at 23rd Street) are on target for completion in the
1st quarter of 2014. Waterproofing and steel erection continue at the C06 Substation.
Harold Construction and Amtrak/LIRR Coordination:
The Harold Structures – Part 3 Westbound Bypass (CH057A) contract received limited
Notice to Proceed on December 2, 2013. The contract includes construction of the
westbound bypass structure, a 630-ft long tunnel with east and west end approach
structures. The scope also includes the installation of catenary foundations, poles, and
signal bridges to support rail road systems. It is the first major construction contract
funded by the Federal Railroad Administration’s High Speed Intercity Passenger Rail
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 4
Program. The contractor has started to mobilize and prepare the required submittals in
preparation of starting construction in the next quarter.
LIRR completed the Phase 1 signal cutover and removed the wires from existing Tower
36 in the 4th quarter. This allowed the Harold Structure Part 1 and GO2 Substation
(CH053) contractor to proceed with the erection of steel for the bridge structures at 43rd
and 48th Streets.
Construction continues on the 12kV ductbank and storm sewer under the Harold
Structures Part 2A (CH054A) contract
Procurement:
Award of the Manhattan North Structures (CM006), Systems Package 1 – Facilities
Systems (CS179) and Systems Package 3 – Signal Equipment Procurement (VS086)
contracts is pending MTA’s approval at the January board meeting
Advertisement of the GCT Concourse and Facilities Fit-Out (CM014B) and Systems
Package 4 – Traction Power Systems (CS084) contracts is planned for 1st quarter 2014
A Request for Expression of Interest (RFEI) for the work in the GCT Caverns (CM007)
was released in November. Contract documents have been provided to the firms
responding to the request and are expected in February.
Costs
Contract modifications totaling $39,267,737 were executed in the 4th quarter. Major
changes include Mod #32 for the rehabilitation of the eastbound 63rd Street tunnel for
$25,600,000 (Plaza Substation and Queens Structure (CQ032)), Mod #19 early works
scope transfer for $4,275,000 from GCT Concourse and Facilities Fit-Out (CM014B) to
GCT Concourse and Facilities Fit-Out Early Work (CM014A), and Mod #74 part 1D
motor generator set-civil work for $5,700,000.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 5
Active Construction Contracts Summary
Forecast Orig Revised
MANHATTAN / BRONX CM004 – 44th St. Demolition and Construct Fan Plan Structure and 245 Park Ave. Entrance
Yonkers Contracting Company, Inc. (YCC)
NO 42.8 40.8 55.3 4.0 59.3 55.9 99.1 92.2 51.5 09/16/09 09/11 12/13 04/14 Concurrent critical paths go through the building completion and the street utility work.
CM005 - Manhattan South Structures Michels Corporation NO 220.7 200.6 200.6 20.1 220.7 225.3 5.5% 8.4% 16.8 09/09/13 02/16 02/16 02/16
Completed cutting/patching rock bolts and shotcrete operation in the eastbound cavern as scheduled.
CM013 – 50th St. Vent Facility
CCA Civil-Halmar International (CCA) NO 99.1 94.4 96.1 4.4 100.5 96.5 96.9% 95.3% 92.7 01/04/10 06/12 12/13 02/14
Completed acoustical insulation spraying from damper level to upper roof level.
CM013A – 55th Street Vent Facility
SCC-JPP, JV (Schiavone and Picone, JV) NO 58.8 56.0 56.4 2.4 58.8 59.2 23.2% 27.1% 15.3 09/04/12 04/15 04/15 04/15
The contractor continued blasting operations in the shaft.
CM014A - GCT Concourse and Facilities Fit-Out Early Work
Yonkers Contracting Company, Inc. NO 46.5 43.5 48.8 3.0 51.8 54.7 80.9 55.4 27.0 11/07/11 04/13 07/13 06/14
Critical path is being driven by the SCADA change order issue.
CM014MP - Early Work for GCT and Facilities Fit-Out The Urban Group, Ltd.
NO 2.0 1.9 2.0 0.0 2.0 2.0 100.0% 92.2% 2.0 03/27/13 10/13 10/13 12/13 Substantial completion was achieved on December 23, 2013.
VM014 - Vertical Circulation
(Escalators and Elevators)**
Schindler Elevator Corp. NO 51.4 24.2 24.4 25.9 50.3 47.3 2.0% 2.0% 4.0 09/27/10 09/18 09/18 09/18 Continue the Phase II Fabrication activities.
FMM19 - Manhattan Force Account Support MNR
NO 33.1 31.8 31.1 11.5 42.6 TBD N/A 94.3% 28.2 04/01/08 03/12 07/13 04/14 Force Account support for Manhattan construction. Schedule tracks with third party construction.
QUEENS CQ031 - Queens Bored Tunnels and Structures
Granite-Traylor-Frontier Joint Venture (GTF) NO 756.8 648.9 760.2 26.4 786.6 758.7 100.0% 98.7% 747.6 09/28/09 09/12 09/12 11/13
Completed all contract and change order work in November 2013. Continued punch list, clean up and demobilization. Substantial Completion to be retroactively declared as of 11/18/13.
CQ032 - Plaza Substation and Queens Structures
Tutor Perini NO 162.1 147.4 206.9 10.9 217.8 223.7 72.3% 44.4% 92.0 08/10/11 08/14 08/14 08/15
Continued work at Plaza Substation installing steel and concrete encasement at C06 Level. Continued installation of exterior and interior masonry and commenced installation of metal roof panels at B-10 Substation.
ESA program only *EAC’s do not include possible contract mods and future claims **Current approved contract does not include full scope
Status Critical Path (CP) Near Critical (NC) Not Critical (NO)
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 6
CURRENT VALUE
Forecast Orig Revised
HAROLD INTERLOCKING CH053 - Harold Structures Part 1 and GO2 Substation Perini Corp.
CP 144.1 137.3 233.5 42.4 275.9 252.0 100.0% 84.7% 199.7 01/01/08 05/10 01/12 12/14
Completed setting steel girders for 43rd St. WBY Bridge and 48th St ML2/4 Bridge. Continued excavation and lagging at Tunnel A Reception Pit.
CH054A - Harold Structures Part 2A
Perini Corp. NO 27.1 21.8 44.7 15.1 59.8 56.8 100.0% 66.7% 29.4 08/24/09 12/10 12/10 07/14
Completed installation of conduits in jacked shield 12KV tunnels Run 15 and Run 16. Installed two precast manholes and commenced construction of jacking pit for Microtunnel Run 13.
FHA01 - Harold Stage 1 –Amtrak Amtrak Force Account
CP 9.5 9.5 16.8 0.0 16.8 16.8 96.3% 94.2% 16.8 06/30/07 09/10 01/12 12/14
Completed wire transfers for B-911E removal. Surfacing 771 switch (FHA02) will be performed after the B-911E pole is removed (CH053). Continued working on signal and catenary wire relocations between Thomson Avenue and Substation 44.
FHA02 - Harold Early Stage 2 (Partial Budget Only) – Amtrak Amtrak Force Account
CP 27.3 9.7 38.6 1.4 40.0 41.7 79.1% 76.5% 35.0 12/15/08 09/13 08/14 04/15 F1-CIH is now in-service. Commenced removing signal apparatuses in existing F-CIH.
FHL01 - Harold Stage 1 – LIRR
LIRR Force Account NO 28.8 28.8 20.8 1.2 22.0 22.0 81.8% 77.3% 18.1 06/29/07 09/10 10/11 01/15
The signal power was cutover on November 6, 2013. Commenced removing retired cables from existing signal towers.
FHL02 - Harold Early Stage 2 (Partial Budget Only) – LIRR
LIRR Force Account NO 54.1 7.4 29.0 33.7 62.7 69.3 41.7% 31.2% 28.6 08/17/09 11/15 11/15 03/16
Continued testing and revisions for new Point CIL cutover (February 28, 2014). Continued cabling and testing for H4 CIL cutover.
VHA02 - Procure Harold Material Stage 2 – Amtrak
Amtrak Force Account NO 12.7 6.0 11.2 1.5 12.7 11.2 N/A 79.7% 6.2 01/09 01/12 05/12 08/14
Procurement of LIRR and Amtrak Force Account material in support of Stage 2 construction.
VHL02 - Procure Harold Material Stage 2 – LIRR
LIRR Procurement NO 25.0 6.0 20.8 4.2 25.0 24.0 N/A 87.7% 18.1 01/09 08/13 08/13 11/15
Procurement of LIRR and Amtrak Force Account material in support of Stage 2 construction.
VH051 (Part 1) - Harold and Point CILs
Ansaldo STS USA, Inc. (ASTS) NO 30.9 25.8 26.8 4.0 30.8 30.8 75.0% 72.0% 19.6 05/11/09 06/12 06/12 07/15
POINT, H4, H3, H5, H6 and LOC 30 CILs have been delivered; H2 & H1 to ship 1st Qtr. 2014. POINT, H4 and H5 CILs have been placed on-site.
VH051 (Part 2) - Harold Tower Supervisory Control System
ARINC, Inc. NO 7.1 5.4 7.2 0.9 8.1 8.0 100.0% 88.0% 6.7 02/03/09 08/10 08/10 07/15
GATE, F1, F2, existing POINT & existing Harold are currently operating on the FHACS. New POINT is scheduled for February 2014 cutover.
ESA program only *EAC’s do not include possible contract mods and future claims
Status Critical Path (CP) Near Critical (NC) Not Critical (NO)
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 7
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 8
44 th
St. Vent Plant & 245 Park Ave. Entrance (CM004) Oct, Nov, Dec ‘13
Contractor: Yonkers Contracting Company, Inc. (YCC)
Construction Manager: Bill Madden FTA Grant: NY-03-0344, ARRA Stimulus Funds NY-36-0002
C o
n s
tru c
tio n
existing building, perform soil and rock excavation. Construct shell of
new building. Frame and partially fit-out new building. 245 Park
Avenue Entrance: Conduct environmental abatement and demolition;
construct new foundations, walls and supports, furnish and install
escalator. Install architectural finishes, plumbing, fire protection,
HVAC, lighting, power, fire alarm, and communication systems.
Load Test of Gantry Crane.
CM004 Contract Status
April 1, 2014
Gantry Crane in service in December, one month later than
previously forecasted, due to Subcontractor issues
Shaft 1 punch-list work started December, 30 days behind schedule due to crane delays
AT-1 punch-list began in October as previously forecasted
Below grade steel completed in December
Above ground intumescent painting and building façade
installation complete. CMU installation is 90% complete,
expected completion January 2014, two months behind
schedule due to the gantry crane delay and Contractor
progress.
245 Park Avenue Entrance: Beneficial Use was achieved October
21, as planned. Punch list is ongoing and is expected to be completed on January 31, 2014.
2. Critical Issues:
Structural Steel – below grade steel installation completed
in December. It was delayed one month by the gantry crane
completion and contributed to the building completion delay.
Intumescent paint is approximately 85% complete, and the
subcontractor has not been on site since December 1 due to cold temperatures
3. Mitigation:
Weekly meetings are held to monitor progress and mitigate any slippages
The south side street utility work is being removed from the contract
Contractor will complete work in time to meet handover to CM005 as necessary
The balance of intumescent painting will not hold up
completion of the rest of work, and could be completed as
a punchlist item
4. 1st Quarter ’14 Look Ahead: 44th Street Vent Plant: Complete all work by April 1, a two month
loss since the last quarterly report. This is due to the gantry crane delay and slow Contractor progress.
Milestones CM004
N/A NTP 09/16/09 09/16/09 09/16/09 (A)
N/A Complete South End of Platform E
05/28/10 05/28/10 10/05/11 (A)
06/01/11 01/28/13 06/28/13 (A)
09/16/11 10/04/12 10/21/13 (A)
09/16/11 12/31/13 04/01/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete* 2.6 5.6 99.1 92.2
*Curve redesigned again based on Original Baseline, Current Baseline and Actuals
Contract Costs ($000) as of 12/31/13
CM004 FA Support* Total
Current Budget** 59,266 - 59,266
Original Award 40,765 - 40,765
Approved Changes 14,516 - 14,516
Invoiced Amount 51,468 - 51,468
*Force Account costs are reported on the FMM19 summary page.
**EAC does not include possible contract mods and future claims.
245 Park Avenue Entrance: Punchlist to finish by January 31.
Cost: As of 12/31/13, 76 modifications were executed for a total of
$14,516,646.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 9
Coordination Required
Real Estate: 47 E. 44th St. acquired and vacated. NYC Planning
Commission approved 245 Park Ave. change of use in Plaza area.
Railroad Agencies: MNR and LIRR.
Permits: Contractor acquired all demolition, construction, sidewalk and
MPT (lane closing-DOT) permits.
Progress (CM004)
minimize safety issues and correct any issues immediately
Management walkthrough’s conducted on weekly basis, to assure that
CM’s office and Contractor’s management get together and address any
and all concerns with the project
Performed quarterly safety assessments
Project Contract BLS** (’13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
0%
20%
40%
60%
80%
100%
0
10
20
30
40
50
Sep-09 Jan-10 May-10 Sep-10 Jan-11 May-11 Sep-11 Jan-12 May-12 Sep-12 Jan-13 May-13 Sep-13 Jan-14
M il
li o
n s
245 Park Ave. Entrance
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 10
Manhattan South Structures (CM005) Oct, Nov, Dec ‘13
Contractor: Michels Corporation
Description: The Manhattan South Structures work provides the fabrication and construction of permanent structural concrete lining, interior
structures, and fit-out for caverns and tunnels previously excavated by others beneath the existing Grand Central Terminal located in
Manhattan.
Progress, Schedule and Cost
shotcrete operation in the EB cavern as scheduled. The east
wall is 95% complete as planned and 85% complete in
west wall, the pit waterproofing is 16% complete. Current
expected completion date for all waterproofing is February
1, 2014, which is 24 days behind the baseline planned
completion. This delay will not impact the overall contract
completion.
Commenced shotcrete operation as planned.
GCT 1&2 EB/WB – Began setting shotcrete guide pins
and drilling holes for trench layout in EB. Began
mobilization for cutting bolts and drilling holes in invert
for drainage work in WB.
Tail Tunnel L402 – Completed installation of screed rails
for invert pour. Shotcrete placement and installation of
waterproofing for invert was completed. The work in this
location is ahead of the Baseline schedule.
2. Critical Issues: MTA is concerned about the slow progress of
waterproofing in the walls and pits of EB Cavern
3. Mitigation: MTA provided Michels with written notification of the
availability of the Access Restraint based on coordination
with the adjacent contractor
Michels to start 2nd shift for waterproofing in EB & WB
Cavern as needed
4. Planned Work:
Begin concrete work in pits in EB Cavern
Continue invert drainage and commence rebar and
concrete installation in L402 Tunnel
Milestones CM005
1 Escalator / Cavern Connections 09/09/14 09/09/14 09/09/14
2 North End of East Cavern 07/06/14 07/06/14 07/06/14
3 North End of West Cavern 01/12/15 01/12/15 01/12/15
4 Substantial Completion 02/06/16 02/06/16 01/29/16
5 Final Completion 05/06/16 05/06/16 05/06/16
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete 5.0 6.2 5.5 8.4
Contract Costs ($000) as of 12/31/13
CM005 F/A Support Total
Current Budget* 220,663 - 220,663
Original Award 200,602 - 200,602
Invoiced Amount 16,831 - 16,831
*The current budget does not include pending scope transfers.
**EAC does not include possible contract mods and future claims.
Cost: As of 12/31/13, zero modifications have been executed.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 11
Coordination Required
Real Estate: All properties and easements are secured for tunnel
construction. MTA sent mailings to owners regarding contract NTP,
zones of influence, pre-construction survey, instrumentation, and
monitoring.
provided by MNR.
Construction Permit: Permit Rev1 received (Under Review)
Water Discharge Permit – NYCDEP: Permit to be received
DOT Lane Closure Permits – NYCDOT: Permits to be received
Tunnel Permits – NYCDEP: Permit received
Progress (CM005)
Safety
The CM will conduct weekly safety walks which Michels will attend to
address all on-site safety related issues
The FDNY will conduct bi-weekly tours
Safety audits will be conducted on a quarterly basis
New hire drug and alcohol testing will be administered by Medcor
RWP training will be required when working near Metro North property
Safety Statistics* (Cumulative Incidents per 200,000 work-hours)
Project Contract BLS** (’13)
hours only
Site Map
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
Sep-13 Nov-13 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Jul-15 Sep-15 Nov-15 Jan-16 Mar-16 May-16
M ill
io ns
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 12
50th St. Ventilation Facility (CM013) Oct, Nov, Dec ‘13
Contractor: CCA Civil-Halmar International
Construction Manager: Vincent Monaco
structure and vertical utility shaft.
Metal Cladding Installation at Vent Building.
Installing Granite Cladding at Public Open Space West Wall.
Progress, Schedule and Cost
Roofing at second floor vent building is 80% complete. Panels
and louvers at the vent building is 70% complete. Store front
glass fabrication is pending completion of framing. Framing
installation is expected to be completed by January 2014.
Vent Shaft work resumed on December 12, 2013. Completed
acoustical insulation spraying from damper level to upper roof
level. Completed planters light installation and started light
wiring in public open space. Granite panel installation is 30%
complete. MEP work is ongoing.
2. Critical Issues: The current schedule is behind the revised baseline
schedule. Contractor missed the Substantial Completion date which
was projected for December 31, 2013 due to work added under CPR
38, installation of framing and cladding.
3. Mitigation: MTA is reviewing CPR 38 with the CM to address LDs
on Substantial Completion. Current forecast Substantial Completion
is March 3, 2014.
Vent Building: Continue installing panels and louvers; painting
CMU walls and installing railings. Continue roof installation.
Continue installation of roof and roll-up doors in loading dock
Public Open Space: Install wiring and irrigation lines. Install
granite curbs; ceramic tiles at fountain location; fountain
structure and store front glass.
Cost: As of 12/31/13, 29 modifications for a total of $1,793,254 have
been executed.
Milestones CM013
N/A NTP 01/04/10 01/04/10 01/04/10 (A)
2 Installation of Street Decking 11/17/10 11/19/10 11/06/10 (A)
1 300 Park Independent Wall & Site Access
12/15/10 02/06/11 04/29/11 (A)
08/27/12 08/27/12 08/01/13 (A)
3 Substantial Completion 06/01/12 12/31/13 03/03/14
4 Final Completion 09/04/12 03/01/14 04/01/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan* Actual Plan* Actual
Percent Complete** 9.4 8.2 96.9 95.3
*Global modification executed. The Plan % is based on revised forecast which is under review.
**Curve redesigned based on revised forecast and actual
Contract Costs ($000) as of 12/31/13
CM013 CMR13
F/A Support
Current Budget* 100,472 28,000 - 128,472
Original Award 94,355 24,000 - 118,355
Approved Changes 1,793 0 - 1,793
Current Contract Value 96,148 28,000 - 124,148
Invoiced Amount 92,689 26,077 - 118,766
Estimate at Completion** 97,026 28,000 - 125,026
*Force Account costs are reported on the FMM19 summary sheet.
**EAC does not include possible contract mods and future claims.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 13
Coordination Required
awaiting a tax lot merger
Railroad Agencies: MNR
Permits: The contractor has secured all of the required permits for
the project.
Park MOU executed, NYCDEP / MNR executed.
Progress (CM013)
Safety
Continued to maintain emphasis on safety with contractor and their trades
through daily walkthrough’s and developing daily hazard logs
Continued to hold contractor management responsible for safety as well
as the workers
Safety Statistics* (Cumulative Incidents per 200,000 work-hours)
Project Contract BLS** (’13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
60
70
80
90
100
Jan-10 Mar-10 May-10 Jul-10 Sep-10 Nov-10 Jan-11 Mar-11 May-11 Jul-11 Sep-11 Nov-11 Jan-12 Mar-12 May-12 Jul-12 Sep-12 Nov-12 Jan-13 Mar-13 May-13 Jul-13 Sep-13 Nov-13 Jan-14 Mar-14
M il
li o
n s
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 14
55th St. Ventilation Facility (CM013A) Oct, Nov, Dec ‘13
Contractor: SCC-JPP, JV (Schiavone and Picone, JV)
Construction Manager: Caroline Purcell
C o
n s
tru c
tio n
Description: Work includes excavation from the street level to an existing cavern below. Upon completion of excavation, a subsurface
concrete vent building is erected from the cavern invert to the sidewalk elevation.
Installation of Rock Support Against Shaft Wall.
Placement of Concrete for Plenum Invert Mud Slab.
Progress, Schedule and Cost Schedule:
1. Progress:
During this update period, SP commenced blasting
operations in the shaft for El. 320 to El. 302 (Stage 1) as
planned; 30% complete. The rock bolt installation Stage I
started as scheduled with anticipated 30 days delay due to
vibration concerns.
excavation at the west side which is still in progress;
continued installing rock bolts on South plenum walls; and
commenced and completed pouring the mud slab in the East
side of the plenum.
SP intends to install a work platform which will be
suspended from the temporary deck after shaft excavation is
complete
complete by the end of January 2014
The delay in design approval may impact the rock bolt
installation and shotcrete in the plug section
3. Mitigation: SP received comments and expects to resubmit the
platform design by January 2014. MTACC will expedite review
of this information. Based on the submitted draft schedule, the
shaft completion is planned for January 31, 2014.
4. Planned Work:
the shaft
section
Complete shotcrete operation in the plenum
Milestones CM013A
N/A NTP 09/04/12 09/04/12 09/04/12 (A)
N/A Access Restraint #1 02/21/14 02/21/14 02/21/14
1 Milestone #1 10/01/14 10/01/14 09/26/14
2 Substantial Completion 04/05/15 04/05/15 04/04/15
3 Final Completion 07/04/15 07/04/15 07/03/15
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete 3.6 7.0 23.2 27.1
Contract Costs ($000) as of 12/31/13
CM013A
Current Budget 58,846 - 58,846
Original Award 56,044 - 56,044
Approved Changes 340 - 340
Invoiced Amount 15,268 - 15,268
Estimate at Completion* 59,220 - 59,220 *EAC does not include possible contract mods and future claims. Overrun due to extended use of traffic enforcement agents.
Cost: As of 12/31/13, one modification for $340,000 has been executed.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 15
Coordination Required
Railroad Agencies: Flagging and access and protection are being provided
by MNR as needed
Blasting Permit – FDNY: Permit Obtained
Lane Closure Permits – NYCDOT: Permits Obtained
Storm Water Discharge Permit –Permit Obtained
DEP Tunneling Permit – Permit Obtained
Progress (CM013A)
Continued to maintain emphasis on safety and public protection around
the site with contractor and their workers
Conducted daily safety walks and documented each in daily hazard logs
Safety Statistics* (Cumulative Incidents per 200,000 work-hours)
Project Contract BLS**(’13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
Sep-12 Nov-12 Jan-13 Mar-13 May-13 Jul-13 Sep-13 Nov-13 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Jul-15
M il li
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 16
GCT Concourse & Facilities Fit-Out Early Work (CM014A) Oct, Nov, Dec ‘13
Contractor: Yonkers Contracting Company, Inc. (YCC)
Construction Manager: Bill Madden FTA Grant: NY-03-0344
C o
n s
tru c
tio n
Description: Fit-out of lower portion of new LIRR concourse located in
the lower level of GCT, construction of south sub-station facility, fit-out
of shaft #2, procurement of electrical equipment for north substation and
US-3/US-4 unit substations, construction and fit-out of Terminal
Management Center (TMC), and construction of certain rooms adjacent
to south substation and TMC.
CMU Wall Construction.
existing air tunnel, both currently over 95% complete but have
lost a month in the last quarter due to slow Contractor
performance. Continued subway roof closure work and
modifications to the existing air tunnel, both 95% complete
with 30 days behind schedule.
Slab on grade concrete placement is over 99% complete, with
only slight amounts of change order work to complete
Continued CMU wall, door frame and concrete header
construction. It is approximately 60% complete but lost two
months in the quarter due to slow Contractor performance.
Continued CMU wall, door frame and concrete header
construction. It is 60% complete and two months behind
schedule due to slow Contractor performance.
MV transformers and unit substation components were
installed this quarter, two months behind last quarter’s forecast
Air Handling units were installed in November, slightly ahead
of the forecast last quarter
2. Critical Issues:
SCADA delay costs are expected to be finalized in January
Switchgear delivery is expected in February but has lost a
month in the quarter. This and SCADA are driving the critical
path.
The Contractor issued a CPM with a Substantial Completion
date of February 27, 2014. This was followed by updates with
Substantial Completions of April 1 and then February 28th.
The schedules were rejected for contract non-compliance. The
CM feels that those dates cannot be met.
3. Mitigation: SCADA unilateral modification to capture time related portion
of SCADA delay has been issued to the Contractor, and caps
the impact due to SCADA at 308 calendar days
The CM is meeting weekly with the Contractor to address
critical issues
Complete subway roof closure and air tunnel modifications by
the end of January 2014, a loss of one month this quarter
Complete CMU work in mid-March, a loss of two months this
quarter
Continue HVAC and plumbing installation; it was delayed by
YCC until January, a loss of two months in the quarter
Milestones CM014A
N/A NTP 11/07/11 11/07/11 11/07/11(A)
1 Substantial Completion 04/24/13 07/08/13 06/01/14
2 Final Completion 07/23/13 10/08/13 09/01/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete* 15.4 10.8 80.9 55.4
*Curve redesigned based on Original Baseline, Current Baseline and Actual. Current contract value increased this month which decreased the cumulative %.
Contract Costs ($000) as of 12/31/13
CM014A
Current Budget 51,837 - 51,837
Original Award 43,502 - 43,502
Approved Changes 5,259 - 5,259
Invoiced Amount 26,998 - 26,998
*Force Account costs are reported on the FMM19 summary sheet.
**EAC does not include possible contract mods and future claims. The overrun is due to funding MNR/Stantec repair work.
Continue SCADA equipment fab; delivery forecast is March
2014
Initiate work in Shaft 2 by February 1, a loss of six weeks in the
quarter
Cost: As of 12/31/13, 17 modifications have been executed with a total
value of $5,259,272.
Because of Contractor delays and the SCADA issue, the CM is now
forecasting Substantial Completion at June 1, 2014. This is a loss of two
months this quarter.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 17
Coordination Required
Railroad Agencies: LIRR (MNR for work within 43rdSt. parking garage)
Permits: Construction, NYCDOT
OCIP walkthrough’s of the site
Continued to stress the importance of safety with field
management, foreman and superintendent. Addressed safety
issues and documented what was corrected through hazard logs.
Continued to have safety talks with the CM construction team on
a weekly basis
upcoming work
Project Contract BLS**(’13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 18
Early Work for GCT and Facilities Fit Out (CM014MP) Oct, Nov, Dec ‘13
Contractor: The Urban Group, Ltd.
Construction Manager: Nick Schiavone FTA Grant: N/A
C o
n s
tru c
tio n
Description: CM014MP is part of the federal mentor program that allows
small businesses an opportunity to bid on large federal/public projects.
The scope of work includes installation of duct bank and conduit between
the wellways located in Madison Yard. Also included is the installation
of 2 Con-Ed manholes and the excavation and installation of concrete air
plenum along “Ladder U”. Ladder U is located at the entrance to
Madison Yard at tracks 123 and 125, also alongside active MNR track
115. This work will require close work with MNR flagging.
Con-Edison Manhole Installation.
CM014MP Contract Status
Schedule:
1. Progress: The contractor has completed all work as of December
23, 2013. A Substantial Completion walkthrough is being scheduled
with the relevant parties.
2. Critical Issues: Awaiting NYCT final inspection and resolution of
outstanding issues (time extension request and final credit
modification (Mod #3).
3. Mitigation: Outstanding issues are currently under review.
4. 4th Quarter Look Ahead: Final Completion is scheduled for the 1st
quarter of 2014.
Cost: As of 12/31/13, two modifications have been executed for
$85,050.
N/A NTP N/A N/A 03/27/13 (A)
1 Substantial Completion 10/27/13 10/27/13 12/23/13 (A)
2 Final Completion 01/25/14 01/25/14 01/25/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete 40.0 44.0 100.0 92.2
Contract Costs ($000) as of 12/31/13
CM014MP
Current Budget 1,983 - 1,983
Original Award 1,889 - 1,889
Approved Changes 85 - 85
Invoiced Amount 1,950 - 1,950
*Force Account costs are reported on the FMM19 summary sheet.
**EAC does not include possible contract mods and future claims.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 19
Coordination Required
MOU: N/A
Progress (CM014MP)
Continue maintaining a safety culture with the contracts Safety Statistics* (Cumulative Incidents per 200,000 work-hours)
Project Contract BLS**(’13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
M il li o
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 20
Vertical Circulation - Escalators & Elevators (VM014) Oct, Nov, Dec ‘13
Contractor: Schindler Elevator Corporation
Construction Manager: Doug Tilden
C o
n s
tru c
tio n
and installation of 17 elevators and 45 escalators for the
Concourse, Caverns, 44th and 50th St. Ventilation
Facilities, and MNR facilities. Options exist for an
additional five elevators and two escalators.
Rendering of New Escalators.
Progress, Schedule and Cost
The contractor is engaged in the Phase II – Fabrication work
which includes the submittal of shop drawings
The contractor is preparing a change proposal for increased
labor and material costs resulting from the adjustments to the
GCT Concourse and Facilities Fit-Out (CM014B) schedule as
initially set forth in the VM014 contract awarded in September
2010
2. Critical Issues: Finalizing all interface design issues at each
escalator and elevator to be installed as part of the GCT Concourse
and Facilities Fit-Out (CM014B) contract in preparation for the bid
advertisement of that contract.
3. Mitigation: N/A
4. 1st Quarter ’14 Look Ahead: Negotiate the change order to the
VM014 contract recognizing the increased labor and material costs
necessitated by the updated schedule for the GCT Concourse and
Facilities Fit-Out (CM014B) contract.
Cost: As of 12/31/13, four modifications have been executed; three with
no dollar value and one with a value of $205,000.
Milestones VM014
N/A Notice of Award 09/23/10 09/23/10 09/23/10 (A)
N/A NTP 09/27/10 09/27/10 09/27/10 (A)
N/A Substantial Completion 09/20/18 09/20/18 08/29/19
N/A Final Completion 12/20/18 12/20/18 11/29/19
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete
Phase IV – Interim Maint. 0% 0% N/A N/A
Contract Costs ($000) as of 12/31/13
VM014 Regional
Investment** F/A
Support Total
Current Budget 50,292 2,589 - 52,881
Original Award* 24,170 246 - 24,416
Approved Changes 205 - - 205
Invoiced Amount 4,000 - - 4,000
Estimate at Completion*** 47,333 2,589 - 49,922
*Original Award is for Phase I (Engineering and Design Services) and Phase II (Fabrication of escalators and elevators) only
**Not included as part of the FFGA Budget. The 45th St. CPW elevator is funded by Freedom Grant. Work must be progressed concurrently with ESA construction.
***EAC does not include possible contract mods and future claims.
Coordination Required
Permits: N/A
MOU: N/A
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 21
Manhattan – MNR F/A Support (FMM19) Oct, Nov, Dec ‘13
Contractor: Metro-North Railroad
C o
n s
tru c
tio n
Description: MNR Railroad resources in support of the Manhattan contracts CM009, CM019, CM004, FM216, CM013, CM014A,
CM014MP, and CM002. These resources include both direct and indirect labor, flagging, project management, work train support,
load inspection, rail cars inspection and repair, and track outages.
Power Wash UA Wall.
Progress, Schedule and Cost
Madison Yard envelope during the day and night shifts
MNR is providing 24 hour flagging support to Early
Work for GCT and Facilities Fit-Out (CM014MP) to
complete Ladder N track work
MNR continued to provide occasional flagman support
and track outages to Yonkers Contracting on Tracks #11
and #13 during the daytime to complete punch list work
2. Critical Issues: None
Continue to provide flagman support and track outages to
Yonkers Contracting on Tracks #11 and #13 during the
daytime and occasionally during the night time shifts
Continue to provide flagman protection outside of
Madison Yard envelope during the day and night shifts
Continue support of GCT Concourse & Facilities Fit-Out
Early Work (CM014A) and Early Work for GCT and
Facilities Fit-Out (CM014MP) and General Condition’s
contracts
Contract Costs ($000) as of 12/31/13
FMM19 F/A Support Total
Current Budget 42,570 - 42,570
Original Award 31,819 - 31,819
Invoiced Amount 28,225 - 28,225
*EAC does not include possible contract mods and future claims.
Quarterly Review Report – 3rd Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 22
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 23
Queens Bored Tunnels and Structures (CQ031) Oct, Nov, Dec ‘13
Contractor: Granite-Traylor-Frontier Joint Venture
Construction Manager: Frank Perrone
0002
Description: Construct three revenue tunnels and one non-revenue tunnel beneath Sunnyside Yard and Harold Interlocking. Construction
includes: complete main open-cut excavation (from CQ028), procure and assemble two pressurized face tunnel-boring machines and
ancillary equipment, excavate tunnels, install a one-pass pre-cast concrete tunnel liner, install ground treatment along the alignment to
support tunnel construction, underpin bridge piers and LIRR mainline structures, construct an Amtrak access road, and construct
exit/ventilation structures (below-ground) and TBM reception pit, environmental monitoring, water quality sampling and elevation.
Preparing Anchor Bolt Assembly for Tower Foundation 29E.
Rebar Cage and Beam Installed for Guy Anchor 29E.
Progress, Schedule and Cost
will be transferred to future contracts.
Performed clean up and restoration at Tunnel A Approach
Structure
Separation towers 29D and 29E (includes tower foundation and
guy anchor)
2. Critical Issues: None
4. 1st Quarter ’14 Look Ahead: Complete punch list and
demobilization and final contract closeout.
Cost: As of 12/31/13, 91 modifications for a total of $113,244,586
including $4,349,392 in Regional Investment have been executed.
Milestones CQ031
1 Temporary TBM Substation 09/27/10 09/27/10 09/26/10 (A)
N/A Begin Yard Lead Mining 02/24/11 02/24/11 05/18/11 (A)
4 Complete Tunnels 03/04/12 03/04/12 07/28/12 (A)
N/A YL Tunnel Cross-Passage 02/15/12 02/15/12 01/18/13 (A)
7 Substantial Completion 09/26/12 09/26/12 11/18/13 (A)
8 Final Completion 01/24/13 01/24/13 01/08/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete* 0.0 0.2 100.0 98.2
*Curve redesigned based on Original Baseline, Current Baseline and Actual
Contract Costs ($000) as of 12/31/13
CQ031 ESA
Only Regional
Investment* F/A
Support Total
Approved Changes**
Estimate at Completion***
758,715 15,034 32,800 806,549
*Not included as part of the FFGA Budget. Work must be built concurrently with ESA construction pursuant to an agreement with Amtrak.
**ESA Approved Changes include a $2,400,000 settlement.
***EAC does not include possible contract mods and future claims.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 24
Coordination Required Real Estate: All Real Estate has been acquired and tenants are
being relocated.
Railroad Agencies: Amtrak, LIRR, NYAR.
Permits: A FDNY blasting permit was and the water discharge permit were obtained. Long Island Well Permit has been obtained
MOU: Amtrak Project Initiative and Permit to Enter obtained.
Progress Curve (CQ031)
daily hazard logs
Weekly OCIP walks continue
Project Contract BLS**(‘13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
B13 Power Substation
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 25
Plaza Substation and Queens Structures (CQ032) Oct, Nov, Dec ‘13
Contractor: Tutor Perini
C o
n s
tru c
tio n
St. Tunnel. Construction of Plaza Interlocking below grade facilities for Mainline Traction Power
Substation C06, Facility Power Substation B11,
ventilation, signal, emergency power, mechanical and communication rooms. Construction of Mid-Day
Storage Yard Traction Power Substation.
Construction of above grade Plaza Bulk Facility Power Substation (B10) and Yard Lead Service
Building. Installation of ConEd Manholes and
conduits for permanence power services. Construction of miscellaneous site work in
preparation for Mid-Day Storage Yard.
Cleaning Out Dowel Hose Couplers at Face
of Launch Block (Tunnel D).
Removing Level 3 Strut 19 at Plaza.
Progress, Schedule and Cost Schedule:
1. Progress:
turnover (punch list items)
turnover (punch list items)
and design criteria
The final completion of the facility is also pending a
revision to interior signage and key re-design.
Bulk Power Substation (B10) - Commenced installation of
interior and exterior masonry
Area 1A
Commenced the work per the modification issued in
August. Removed existing track and began repairs inside the
tunnel.
electrical lines
The work at the Early Access Chamber has been designed
and the drawings have been let
CPR(s) need to be negotiated for starting the field activity
for January/February 2014
EAC Area is on the secondary critical path
3. Mitigation: A re-baseline schedule accounting for the access
restraint delays by adjacent contractors and changes in the scope
of work will need to be reviewed by both parties. The Contractor
mentioned in a prior meeting that he intends to work some tasks
in parallel to mitigate some of the delays. The magnitude of the
delays will be reported upon review and acceptance of the
proposed re-baseline schedule.
Continued Yard Lead Trench and Revenue Track Invert
work
*EAC does not include possible contract mods and future claims. Overrun due to early access chamber, bracing redesign, and surface substrate for the walls.
Continued Sump Pit Concrete walls and Roof work
Continue rehabilitation of Existing 63rd Street Tunnel (Scope
Transfer)
Bulk Power Station (B10) to be completed 1st Quarter 2014
Cost: As of 12/31/13, 34 modifications for a total of $59,511,933 have
been executed.
Milestones CQ032
1 Complete B10 Substation 06/20/13 06/20/13 03/31/14
2 Turnover YL Track 06/10/13 06/10/13 08/13/14
3 Complete C06 Substation area
09/08/13 09/08/13 05/15/15
6 Substantial Completion 08/14/14 08/14/14 08/07/15
7 Final Completion 11/12/14 11/12/14 11/05/15
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete 10.5 10.7 72.3 44.4
Contract Costs ($000) as of 12/31/13
CQ032 F/A Support Total
Current Budget 217,848 569 218,417
Original Award 147,377 - 147,377
Approved Changes 59,511 - 59,511
Invoiced Amount 91,962 33 91,995
Estimate at Completion* 223,686 571 224,257
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 26
Progress Curve (CQ032)
Safety
Continued daily safety walkthrough’s of the site with contractor safety
and MTACC safety, and weekly safety walks with the CM team and
OCIP
Continued to emphasize safety and that they are accountable for their
actions as well as the actions of the workers, to the contractor’s
management
Project Contract BLS**(‘13)
*The project performance statistics are based on construction hours
only
Site Map
CQ032 – Plaza Substations and Queens Structures
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 27
Harold Structure Part 1 and GO2 Substation (CH053) Oct, Nov, Dec ‘13
Contractor: Perini Corp.
LIRR Amtrak Right of Way for the
future TBM tunnels and Mainline
track diversions including the design,
and installation of a pre-fabricated
substation and installation of new
signal towers and catenary structures
by replacing the existing structures.
43rd St. WBY Bridge Lathers Laying Out Rebar
for Concrete Bridge Deck.
Abutment and Center Pier.
Progress, Schedule and Cost
construct the control arm, knife switch and T2 ductbank for
the C3 breaker
for B-917EE structure
Bridge west abutment.
48th St. Bridge: Completed construction of 48th St. ML2&4
Bridge east and west abutments
Tunnel A Reception Pit: Completed drilling and installing 28
soldier piles in the last quarter of 2013; completed 31 out of
45 piles to date.
various different activities in CH053 and adjacent contracts.
12KV ductbank drives the completion of Micro Tunnel Runs
1-4 which is currently the critical path of CH053 and also
Tunnel A Reception Pit and Approach Structure.
DC Negative Return Feed: Construction of the reception pit
for Micro Tunnel Run 1 is impacted by an existing DC
negative return ductbank
pads, ductbanks and signal towers specified in CPR-109E
drive the cutover of MG Signal Power Separation, which in
turn drives cutover of LIRR H4 CIL and H3 CIL scheduled
for March and June 2014, respectively
3. Mitigation:
A change order will be issued during the first week of January
2014 for the additional work required by Amtrak for 12KV
cutover. Identification and development of the scope has been
a joint effort between ESA, Amtrak, GEC and the contractor.
A change order to relocate the DC negative return was issued
to the contractor and will be resolved towards the end of
January 2014, followed by commencement of work.
Resolution of the change order was delayed because of issues
regarding division of labor between Amtrak and the
contractor.
Catenary Structures: Erect Structure B-917EE
48th St. Bridge: Commence construction of concrete bridge
deck
1
12/16/08 01/01/11 11/18/13 (A)
08/14/09 04/15/11 12/23/14
Schedule Progress 4th Quarter Cumulative*
Cost Expenditure Plan Actual Plan Actual
Percent Complete 0.0 4.6 100.0 84.7
*Current contract value increased this month which decreased the cumulative % complete.
Contract Costs ($000) as of 12/31/13
CH053 LIRR Costs RI
Original Award 137,280 2,000 - 27,560 166,840
Approved Changes
Invoiced Amount 199,714 - 336 42,112 242,162
Estimate at Completion*
247,569 0 576 47,647 295,792
*EAC does not include possible contract mods and future claims. LIRR EAC reduced to $0 due to a decision to delete microtunnnel runs 10 and 11 from CH053 scope.
12KV Ductbank: Complete splicing and megger testing of
C1 and C2 feeders
48-S1
Runs 1, 3 and 4
Cost: As of 12/31/13, 130 modifications for a total of $96,539,045
including $336,000 in Regional Investment have been executed.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 28
Coordination Required
secured.
perform required support work.
Con Ed: Provide inspection services.
Permits: Pre-award reviews and approvals have been obtained from NYCDOT and NYCDEP.
Relevant permit have been obtained by the contractor. Amtrak Entry Permit was approved.
MOU: Amtrak labor clearance was obtained. LIRR and Amtrak force account agreements were
signed. Project Initiative (PI) with Amtrak signed.
Progress Curve (CH053)
Continued ongoing weekly safety walkthrough’s of the site with
management and documentation in daily hazard logs
Coordination with the railroads, “toning” of the ground, and hand
digging procedures are still being followed to prevent buried utility
“strikes” at excavation sites
Continue safety tool box talks for CM staff
Safety Statistics* (Cumulative Incidents per 200,000 work-hours)
Project Contract BLS**(‘13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 29
Harold Structures – Part 2A (CH054A) Oct, Nov, Dec ‘13
Contractor: Perini Corp.
C o
n s
tru c
tio n
Right-of-Way for the future TBM tunnels and Main-line track diversions including: 1) the construction of retaining walls 2) Track
D TBM reception pit 3) AC traction power duct bank 4) access road work 5) demolition of existing Catenary Foundations 6) procurement of two signal bridges and 7) other utility relocations and adjustments.
Installing Bore Spacers and PVC Conduits for Run 15.
Setting Precast Manhole EMH-28-A and B.
Progress, Schedule and Cost Schedule:
1. Progress:
of open cut concrete ductbank
Snow Melter Units: Commenced procurement of
three Snow Melter Units for LIRR
B Type Power Cases: Delivered B-Type power cases
to be installed by LIRR at Point Interlocking (100%)
C Type Power Cases: Delivered four C-Type power
cases (100%) to be installed by LIRR at H4 CIL and
H3 CIL
to be installed by LIRR
2. Critical Issues: To recover the impact of the Storm Sewer work on
the 12KV ductbank construction between Thompson
Ave and Queens Blvd, a design of a microtunnel
option to construct the remaining sections of sewer
was started and has been completed. A change order
has been issued to the contractor which is expected to
be resolved in January 2014. Work on the
microtunnel storm sewer is expected to commence in
February.
expected to be delivered in February and March,
2014.
locations simultaneously for the 12KV ductbank. In order
to further mitigate the schedule, work which follows the
cutover of 12KV ductbank such as construction of the
Access Road AR4 and Loop 1A Track Bed will be
advanced to commence in March 2014, in areas which are
not impacted by the 12KV ductbank. Work on the Storm
Sewer microtunnel is scheduled to commence in February
2014. ESA and the contractor are currently working on
pricing which is expected to be completed by end of
January 2014.
Milestones CH054A
Milestones Original
Approved (Approved
N/A NTP 08/24/09 08/24/09 08/24/09 (A)
2 Retaining Wall THOM S1/S2 05/26/10 05/26/10 12/21/10 (A) N/A Complete 12KV Relocation 12/07/10 12/07/10 05/08/14
3 Substantial Completion 12/21/10 12/21/10 07/05/14 4 Final Completion 03/21/11 03/21/11 10/02/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete 0.0 11.3 100.0 66.7
Contract Costs ($000) as of 12/31/13
CH054A F/A Support Total
Current Budget 59,754 6,748 66,502
Original Award 21,778 2,978 24,756
Approved Changes 22,901 - 22,901
Invoiced Amount 29,402 6,087 35,489
Estimate at Completion* 56,432 6,748 63,180 *EAC does not include possible contract mods and future claims.
4. 1st Quarter ’14 Look Ahead:
12KV Ductbank: Complete construction of open cut sections
of 12KV ductbank. Approximately 400 LF remains.
Access Road AR4 & Loop 1A Track Bed: Commence
construction of Access Road AR4 and Loop 1A Track Bed
Cost: As of 12/31/13, 36 modifications for a total of $22,901,259 have
been executed.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 30
Coordination Required
city streets.
Permits: NYCDOT permits needed. Water discharge permit (DEP) needed.
MOU: Obtained Project Initiative and Permit to Enter from Amtrak.
Progress Curve (CH054A)
Continued ongoing weekly walkthrough of site with management and
daily safety site visits which are documented in the daily hazard logs
Coordination with the railroads, “toning” of the ground, and hand
digging procedures are still being followed to prevent buried utility
“strikes” at excavation sites
Continued to have safety talks with the CM construction team on a
weekly basis
Safety Statistics* (Cumulative Incidents per 200,000 work-hours)
Project Contract BLS** (‘13)
*The project performance statistics are based on construction hours only
**Bureau of Labor Statistics/National Industry Average
Site Map
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 31
Harold Stage 1 – Amtrak Force Account (FHA01) Oct, Nov, Dec ‘13
Contractor: Amtrak
Description: Install one track crossover (723), relocate catenary and signal power at several locations, perform modifications and removal of
poles, third-rail installation, signal infrastructure installation, cable pulls, tie-ins, testing and cut-over of the 723 crossover incorporating
changes to “F” Interlocking and software and hardware modification for the Penn Station Central Control (PSCC). Clear debris and other
incidentals from the Amtrak Maintenance-of-Way Yard, electrical traction relocations in support of the CH053, CH054A and CQ031 civil work.
Catenary Wire Transfer on Line 1 at B-910E.
Performing Catenary Transfer on Line 1 at Pole B-910E.
Progress, Schedule and Cost Schedule:
1. Progress:
B-907AE, B-908E, B-909E, and B-912ES
Catenary wire transfers on B-910E and B-910EA; remove
the old wires on B-910E (North)
Replaced old hangers and clips; transferred catenary wire
on Line 1 at B-909E.
Replaced old hangers and clips; transferred catenary wire
on Line 3 between B-906E to B-910EA
Relocated ground wire at B-925MS
Removed guy wires and the ground wire from the old
pole B-950C
side of Line 4
2. Critical Issues: The track and signal power outages are
required in order to complete signal power and feeder
relocations on schedule.
3. Mitigation: ESA continued to work with Amtrak and LIRR to
lockdown track and power outages which are required for
signal power relocation on the south and north sides.
4. 1st Quarter ’14 Look Ahead:
Continue hardware installation, catenary wire transfer,
signal power (#124 and #123), and feeder (#4301 and
#4303) relocations between Thomson Avenue and
Substation 44 (84 % completed)
Catenary wires for 821 and 823 Switches over Line 4,
Line 2, WWD LI Pass, and WWD LI FRT tracks
Cost: As of 12/31/13, one modification has been executed for
$1,500,000.
Forecast # Description
N/A 100% Design 11/19/07 11/19/07 11/19/07 (A) N/A Commence Stage 1 06/30/07 06/30/07 06/30/07 (A) N/A Cutover Switch O1/O2 04/13/08 08/10/08 10/05/08 (A) N/A Compl. 68 Spur Track 09/15/09 05/01/10 09/06/10 (A) N/A Compl. Signal Power Cable 04/15/09 09/20/10 04/23/12 (A) N/A Substantial Completion 09/30/10 01/03/12 12/23/14
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete* 1.9 1.5 96.3 94.2
*Curve redesigned based on Original Baseline, Current Re-plan Baseline and Actual.
Contract Costs ($000) as of 12/31/13
Stage 1 Total
Current Budget* 16,824 16,824
Original Award 9,500 9,500
Approved Changes 1,500 1,500
Invoiced Amount 16,753 16,753
Estimate at Completion** 16,824 16,824
*Note: Budget has been adjusted based on estimate and P.I. value.
**EAC does not include possible contract mods and future claims.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 32
Coordination Required
Permits: None required.
Progress Curve (FHA01)
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 33
Harold Stage 2 – Amtrak Force Account (FHA02) Oct, Nov, Dec ‘13
Contractor: Amtrak
Description: Install seven switches and LP1A Track (app. 2,400lf). Relocate catenary and signal power at several locations, perform
modifications and removal of poles. Third-rail installation, signal infrastructure installation, cable pulls, tie-ins, testing and cut-over of F1
CIH, F2 CIH and FHACS (“F” Interlocking and Harold Interlocking Alternate Control System).
Prepping Cable Termination at Q Tower.
Removing Old Racks and Wires at Existing F CIH.
Progress, Schedule and Cost Schedule:
1. Progress: Completed pre-testing and performed cutover F1-CIH. Now
that F1-CIH is in service, the signals on the north side (from
E35 Bridge to Portal Tunnel Line 2 and 4) are being
controlled from F1-CIH
F1 and F2 Interlocking
signals at E34 Bridge
cutover
Completed fiber cables from F2, F1, Q Tower, and Harold
Communication Hut
and F1 to Harold Communication Hut (85% completed)
Continued removing existing relays and equipment at F-CIH
and old track circuits
2. Critical Issues: None
Complete communication cables on redundant route from F1
and F2-CIHs to Harold Communication Hut
Erect Signal Bridge E34 (Line 1 Track)
Complete remaining signal work at E35 location (F1GW and
F1GE) for H3-CIL cutover
Cost: As of 12/31/13, zero modifications have been executed. The EAC
is trending over budget due to several additional work items such as
communications work, retaining walls, signal infrastructure, track, ET
catenary and additional supporting resources. The budget will be
adjusted as part of the overall Harold re-planning efforts.
Milestones FHA02
N/A FHACS Cutover 07/15/12 07/15/12 07/16/13 (A)
N/A F2 – CIH Cutover 11/17/12 11/17/12 05/18/13 (A)
N/A F1 – CIH Cutover 03/02/12 03/02/12 11/02/13 (A)
N/A Complete Stage 2 09/30/13 08/30/14 04/24/15
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete* 9.8 7.0 79.1 76.5
*Curve is revised based on the current plan
Contract Costs ($000) as of 12/31/13
Stage 2 Total
Current Budget 39,985 39,985
Original Award 9,706 9,706
Approved Changes 0 0
Invoiced Amount 34,962 34,962
*EAC does not include possible contract mods and future claims.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 34
Progress Curve (FHA02)
Permits: None required.
Site Map
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 35
Harold Stage 1 – LIRR Force Account (FHL01) Oct, Nov, Dec ‘13
Contractor: LIRR
C o
n s
tru c
tio n
Description: Install eight track switches into the existing signal system and remove two switches. Install signal infrastructure in
preparation of Stage 2 (Harold and Point CILs). Reroute signal power cables. Install third rail for new switches and track. Pull traction
power cables from G02 Substation final manholes to Harold Main Line tracks. Energize and commission the relocated G02 Substation
installed by CH053. Install and relocate signal and communications cables. Cut and throw Main Line 4 and relocated Main Line 2 upon CH053 expanding the South ROW East of 43rd Street.
Installing Signs for Transformer Cases at Tower 34 and 40.
Remove Existing Cable between Old Tower 33 and New Tower 34.
Progress, Schedule and Cost Schedule:
1. Progress:
at Tower 34 and Tower 40
Installed pullboxes, conduits and cables from Tower 34
and Tower 40 pads to H Location and 23 Location
Completed wiring and terminating power cable for
134/135 circuits for signal power separation from Tower
32 to Tower 51
Tower 51)
spans remaining)
2. Critical Issues: The Substantial Completion date is driven by
the new G02 Substation construction that is impacted by the
delay of Microtunneling construction (CH053).
3. Mitigation: Working with Perini and LIRR to re-schedule the
construction plan of the new G02 Substation.
4. 1st Quarter ’14 Look Ahead:
Complete removing cables from existing Towers
Complete communication works at the new G02
Substation
# Description
N/A 100% Design 06/07 06/07 07/07 (A) N/A Begin Stage 1 06/29/07 06/29/07 06/29/07 (A) N/A Install 823 Switches 01/25/08 03/20/10 08/21/10 (A) N/A Cutover 865 Switch 03/01/09 10/16/10 10/16/10 (A) N/A Compl. Signal Power Cable 07/15/09 09/20/10 11/06/13 (A)
N/A Operate 821 & 823 Switches 02/15/10 03/05/11 05/10/14
N/A Substantial Completion 09/30/10 10/10/11 01/30/15
Schedule Progress 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete* 5.6 1.9 81.8 77.3
*Curve redesigned based on Original Baseline, Current Re-plan Baseline and Actual
Contract Costs ($000) as of 12/31/13
Stage 1 Total
Current Budget 21,972 21,972
Original Award 28,781 28,781
Approved Changes 0 0
Invoiced Amount 18,115 18,115
*EAC does not include possible contract mods and future claims.
Cost: As of 12/31/13, zero modifications have been executed.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 36
Progress Curve (FHL01)
MOU: Amtrak Force Account Agreement signed. LIRR Force
Account Agreement signed.
Permits: None required.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 37
Harold Stage 2 – LIRR Force Account (FHL02) Oct, Nov, Dec ‘13
Contractor: LIRR
C o
n s
tru c
tio n
Description: Install 15 track switches, new Mainline 4 tracks (app. 2,800lf) and remove two switches; Install signal infrastructure,
cable, testing and circuit revision for Harold (6 CILs) Loc 30, Point CILs and HTSCS; Install third rail for new switches & track.
Install new MG set for LIRR Signal Power Separation from Amtrak. Renovate Harold Tower. Install and remove signal bridges.
Pre-Testing Local Control Panel at Point Location.
Trenching and Installing Troughs at North of Line 4 for H3-CIL.
Progress, Schedule and Cost Schedule:
1. Progress:
Installed “B” power case at the new Point CIL location
and commenced wiring
Point CIL cutover (~77% Complete)
Performed Test 1 breakdown testing on H3-CIL at Bay
Crane Compound (~55% Complete)
Pulled signal cables from H4-CIL to the new Point CIL
(~7,000LF)
Pulled signal cables from 4B Case to 46ATR, 47ATR,
and 830T track circuits
47DT, 47DTA, 47DTR, and 47CT track circuits
2. Critical Issues: Signal Power Separation is required to begin
track circuit testing for new CIL’s except Point CIL. Point
CIL is being powered by the existing Amtrak power (91.6
Hz). Due to the delay of signal power separation, the current
H4 and H3 CIL cutovers could potentially slip.
3. Mitigation:
lock-down the cutover date of the MG set. The re-design
and coordinating schedule have been in process in order
to mitigate the schedule impact.
Track circuit testing for H4 CIL will begin with
Temporary Signal Power (91.6Hz) to mitigate the
schedule impact due to the delay of LIRR Signal Power
Separation.
various locations and perform testing at H4-CIL and new
Point CIL
and switches in Harold Interlocking
Complete communication work for Point, H4, and H3
cutovers
# Description
N/A EWD LI Passenger Track West 03/12/11 03/12/11 03/12/11 (A) N/A EWD LI Passenger Track East 09/24/11 09/24/11 09/24/11 (A) N/A PW2 Track Installation 12/03/11 12/03/11 12/03/11 (A) N/A Point CIL Installation 09/24/11 09/24/11 09/24/11 (A) N/A HTSCS Cutover 08/12/12 08/12/12 10/13/13 (A) N/A Point CIL Cutover 03/24/13 03/24/13 02/28/14 N/A Complete Stage 2 11/30/15 11/30/15 03/30/16
Schedule Progress* 4th Quarter Cumulative
Cost Expenditure Plan Actual Plan Actual
Percent Complete** 10.3 1.9 41.7 31.2
*To be updated after MOU (part 3) is approved, scheduled for 3rd quarter ’14.
**Curve redesigned based on Current Baseline and Actual
Contract Costs ($000) as of 12/31/13
Stage 2 Signal Training Total
Budget at Award 54,137 3,429 57,566
Current Budget 62,690 3,429 66,119
Original Award 7,351 3,429 10,780
Approved Changes - - -
Invoiced Amount* 28,587 2,730 31,317
Estimate at Completion** 69,296 3,429 72,725
*Note: MOU value under negotiation. Once MOU is signed off, the curve will be revised.
**EAC does not include possible contract mods and future claims.
Continue Point CIL and H4-CIL pre-testing
Deliver and install H3-CIL
Pull power cables between HP1 and HP2 poles for Signal
Power Separation
Cost: As of 12/31/13, zero modifications have been executed. The
EAC is trending over budget due to several additional work items
such as communications work, retaining walls, signal infrastructure,
track, power and additional supporting resources. The budget will be
adjusted as part of the overall Harold re-planning efforts.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 38
Progress Curve (FHL02)
MOU: Amtrak Force Account Agreement signed. LIRR Force
Account Agreement signed.
Permits: None required.
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 39
Procure Harold Materials – Stage 2 (VHA/L02) Oct, Nov, Dec ‘13
Contractor: Various
Construction Manager: Peter Malvese FTA Grant: ARRA Stimulus Funds NY-36-0002 (Only
VHL02)
t
Description: Procure LIRR and Amtrak Force Account material in support of Stage 2 construction. LIRR will manage and operate
the project warehouse with ESA oversight. Example of materials include: Track - switches, rail, concrete ties and ballast; Third-
Rail & Power – rail, cables, boards, brackets, wire, power connectors, bus bar; Signal Equipment – switch machines, cables,
signals, relays, motor generators, heaters, troughs, impedance bonds; and Structures – signal bridges, retaining walls etc.;
Communications – equipment, wire, cables, and poles.
Materials at Warehouse Storage Area.
Progress, Schedule and Cost
LIRR procured all 17 switches and they are to be
delivered from now until the spring of 2014 due to
changes with the installation schedule. Also
reviewing alternate locations with expanded
facilities for delivery, building and storage.
Bill of Materials (BOMs) for VHA/L02 is an
average of 83.7% procured. This percentage was
recalculated based on the average of Amtrak and
LIRR combined. Deliveries continue in coordination
with the construction schedule.
Cost: Table shows value of awards to date. An overall
VHL02 savings is expected due to large scale advance
procurement for Stage 2 materials. The budget of VHL02
was increased to purchase two motor generators for
Harold signal power separation. Meetings are being held
regarding contract purchase and award of the motor
generators.
have been sent to Procurement for requisition
processing
95% of procured DC traction miscellaneous material
has been delivered
been delivered
Critical Issues: None.
Material Budget
Percent Procurement Completed
Estimate at Completion
Third Rail/DCTrac. 923,247 777,277 92.0% 864,329
Communication 126,716 570,021 43.3% 1,159,168
Catenary 553,007 330,246 56.1% 608,660
Elec. Traction 2,106,948 417,056 89.1% 469,513
Total 12,719,087 8,517,020 79.7% 11,260,588
LIRR – VHL02 – Budget Summary (12/31/13)
Material Budget
Percent Procurement Completed
Estimate at Completion
Third Rail/DCTrac. 1,965,065 2,103,982 94.0% 2,247,866
High Tension 681,616 16.4% 904,708
Communication 2,850,950 498,328 13.0% 2,399,903
Subtotal 20,860,730 16,708,512 87.7% 19,796,953
Motor Generators 4,176,157 4,176,517 - 4,176,517
Total 25,036,887 20,885,029 87.7% 23,973,470
Quarterly Review Report – 4th Quarter ‘13
Quarterly Report (Oct, Nov, Dec ‘13) - East Side Access (PM 3.2.107595) 40
Harold and Point CILs – (VH051 Part 1) Oct, Nov, Dec ‘13
Contractor: Ansaldo STS USA, Inc. (ASTS)
Construction Manager: Chuck Miller FTA Grant: NY-03-0344
C o
n s
tru c
tio n
Description: This includes the procurement of seven Harold Interlocking Central Instrument Locations (CILs) and one Point Interlocking
CIL and the purchase of a fully operational Vital Microprocessor-Based Interlocking Control System for the referenced interlockings. This
system will operate the new Harold Interlocking configuration and eventually connect to the new GCT tunnels.
POINT Battery Hut Exterior.
Schedule:
1. Progress: Currently, six of the eight CILs have been delivered to
the project by Ansaldo. The POINT, H4 and H5 CILs have been
set on-site with final preparations being made to place H3 and H6
CILs. Submittals for the final two CIL locations, H1 and H2, have
been received and are under review.
2. Critical Issues:
Program Plan (RSPP) and the Informational Filing (IF) for the
Communications and Synchronization Printed Circuit Boards
remains the major critical issue. The LIRR will forward their
modified, conditionally approved, RSPP to the FRA and
continue its work responding to questions and comments from
the FRA on the IF. Per previous correspondence, the FRA
wrote that a Product Safety Plan (PSP) would be required. A
subsequent FRA clarification letter noted that the IF should be
adequate. No cutovers can take place without FRA acceptance
of both the RSPP and the IF.
Constant changes to the Harold footprint in order to mitigate/
improve construction sequencing and/or perceived operational
issues are resulting in additional cost and schedule impacts to
both the vital signal system and non-vital supervisory control
system. Scope changes are absorbing limited signal design
resources and increasing the probability of design errors.
3. Mitigation: Monitor FRA progress with periodic requests for updates on
the filing status, provide resources to assist the LIRR in
responding to the FRA’s comments on the IF
No additional changes to Harold Interlocking
4. 1st Quarter ’14 Look Ahead: Complete reviews, conduct witness testing and take delivery
of the H1 and H2 CILs
Cutover POINT and H4 CILs
Cost: As of 12/31/13, three modifications for a total of $999,995 have
been executed.
1 Compl. POINT CIL set 06/30/10 06/30/10 11/06/11 (A)
4 Compl. H4 CIL 04/26/11 04/26/11 07/27/12 (A)
5 Compl. H5 CIL 05/26/11 05/26/11 06/20/13 (A)
6 Compl. H6 CIL 07/26/11 07/26/11 10/31/13 (A)
7 Compl. 30 Loc Hut 07/26/11 07/26/11 10/3