7/30/2019 Quarterly Report - Oct 2012 to Dec 2012 http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 1/259 National Cyclone Risk Mitigation Project (NCRMP) Revenue (DM) Department Government of Andhra Pradesh National Cyclone Risk Mitigation Project (NCRMP) Revenue (DM) Department Government of Andhra Pradesh

Upload: henrique-xavi-inesta

Post on 04-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 1/259

National Cyclone Risk Mitigation Project

(NCRMP)Revenue (DM) Department

Government of Andhra Pradesh

National Cyclone Risk Mitigation Project

(NCRMP)Revenue (DM) Department

Government of Andhra Pradesh

Page 2: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 2/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

INDEX 

1.0 Project Background 2

1.1 Third Party Quality Audit Consultant 3

1.2 Mobilization of Team 4

1.3 Setting up offices and logistics for the consultant teams 8

2.0 Review Meetings and Other Activities 9

3.0 Status of TPQA Visits 10

4.0 Progress of NCRMP works 11

5.0 District wise status of tests conducted by TPQA 39

6 0 Details of Quality Control Audit Reports Submitted During this 3 Months 40

Page 3: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 3/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.0 Project Background

 Andhra Pradesh (AP) state has one of the longest coastal belts in India. Out of 67,362 Km of road network in the state,

the nine coastal districts cover 26,000 km of road length. Every year during the period of April-May and September-

December, cyclonic situations set in to the Bay of Bengal. With the recent changes in climatic conditions, the catastrophic

events are increasing resulting in very devastating cyclones like Laila, Jal etc where the loss is enormous. In the 97 years

ranging from 1892 to 1989, there were as many as 67 cyclones within the State.

It is essential to provide safe residential accommodation to the vulnerable population during any eventuality or disaster

due to natural calamities such as cyclones and associated tidal waves and storm surges. The project is formulated based

on experiences of Government of Andhra Pradesh in mitigating such disasters during the past and also keeping in view the

existing facilities available in the project area in Andhra Pradesh.

The Government of India has applied for a credit of US$ 255 Million equivalent from the International Development

 Association (IDA) toward the cost of National Cyclone Risk Mitigation Project (NCRMP), and it intends to apply the

proceeds to payments for goods, works, related services and consulting services under this Project.

National Cyclone Risk Mitigation Project (NCRMP) – Project Implementation Unit (PIU), Andhra Pradesh, headquartered at

Hyderabad has invited the consultants to submit proposals for providing the consultancy services for Third Party Quality

 Audit for 9 coastal districts namely Srikakulam, Vijayanagaram, Visakhapatnam, East Godavari, West Godavari, Krishna,

Guntur, Prakasam and Nellore. The project “Construction of Multipurpose Cyclone Shelters, Roads to Cyclone

Shelters, and Roads to habitations and Roads & Bridges under NCRMP” is funded by International Development

 Association and received through Government of India. This consultancy is envisaged to audit the quality of works being

implemented by various line departments working under PIU. The number of works under progress / for which

agreements are concluded in each district is shown in the table below

Page 4: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 4/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.1 Third Party Quality Audit Consultant.

To provide Consulting Services of Third Party Quality Auditor for Construction of Multipurpose Cyclone

Shelters, Roads to Cyclone Shelters, Roads to habitations, and Roads and Bridges under NCRMP in 9 coastal

districts The Commissioner for Disaster Management & Project Director Project Implementation Unit (PIU)

Page 5: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 5/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.2 Mobilization of Team

In accordance with the Contract for Consultant Services, executed on 31st

May’2011, by The Commissioner 

for Disaster Management & Project Director, Project Implementation Unit (PIU) NCRMP and the Egis India,

professional services were authorized to commence work. The detail of team mobilization and organization

chart is shown below.

Sr.No. Name Designation

Date Of Joining

Last Day

of Working

NCRMP Project Office, Hyderabad

1 Bhavanna Rao Project Manager 01.06.2011

2 Dr. Surjit Singh Deepak Environmental Management Expert 09.06.2011

3 Dr. Sudesh Kaul Social Management Expert 01.06.2011

4 Mrityunjay Kumar MIS Expert 01.06.2011

5 V.Ravi Kumar Electrical 06.06.2011

6

Ch.Giridhar Electrical 02.06.2011 13.12.2012

Page 6: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 6/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

13 B.Srinivasulu Reddy Site Engineer 06.06.2011 22.09.2012

14 H.Venugopal Site Engineer 06.06.2011

15

Siva Kishore Vedula Site Engineer 09.06.2011 04.01.2012

Sivaji Raju Site Engineer 13.02.2012

16

Srinivas.Y Site Engineer 27.06.2011 06.01.2012

Venkateshwara Prasad Site Engineer 13.02.2012

17

Babu.G Office Manager 01.06.2011 19.06.2012

KNVS.Malleswara Swamy Office Manager 20.06.2011 14.11.2012

N.Ramakrishana Office Manager 17.11.2012

ELURU

18

M. Manohar DPM / Eluru 27.06.2011

R. Sathi Babu Randhi Deputy Project Manager 02.06.2011

Page 7: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 7/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

26  Arun Kumar DPM / Ongole 22.02.2012

27

P.Ramesh Reddy Site Engineer 06.06.2011 13.03.2012

T.SreeVishnu Site Engineer 14.03.2012

28

Shaik Zaheer Ahamad Gori Site Engineer 02.06.2011 31.08.2012

S.Narendar Site Engineer 10.09.2012

29 K. Rama Rao Site Engineer 22.06.2011

30 Suresh Babu.P Site Engineer 06.06.2011

31 R.Balakrishna Reddy Site Engineer 02.06.2011

32

Mallikarjuna Rao Site Engineer 02.06.2011 01.03.2012

Ravinder Reddy Site Engineer 15.07.2011

33 Neelakantan Office Manager 01.06.2011

Page 8: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 8/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Organization Chart of TPQA, NCRMP

Page 9: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 9/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1.3 Setting up offices and logistics for the consultant teams

We have established a Main office at Hyderabad, where all the necessary expertise that is required for this project. There

is a core team of national experts to monitor the project activities and discipline specialist will appropriately support this

core team. These experts will again be supported from the respective home office. Other than the experts, support staff is

also be stationed in this office. This office will be the base office during the project period of consultants.

The details of our site offices are given in table below. These offices are provided with required communication equipment,

transportation facilities and necessary infrastructure. The offices are also equipped with computers with basic software

programs, printers, and other electronic gadgets like telephone, fax machines, etc. as felt needed. Apart from the abovePM and DPM offices, we have established site offices in all other districts

PM Office – Hyderabad

9-1-77/3, No.31, Third Floor 

S.D. Road, Secundrabad – 500 003

Fax:=91-04-40179496

E- mail: [email protected]

DPM Office – Vishakhapatnam

Pavan Residency, Dr. No. 31-7-2/73,

Flat NO 503Kurmannapalem,

Opp to Bus Depot,

Vishakhapatnam - 530046

DPM Office – Eluru

Flat No. 504, Fourth Floor,

Yemireddy Residency Apartment,

Shekar Street, Gandhinagar,

Eluru, West Godavari Dist. A.P.

DPM – Ongole Office

H. No. 6-277, 2nd

lane

Beside computer Centre

Maruthi Nagar 

Ongole - 523002

Page 10: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 10/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2.0 Review Meetings and Other Activities

S.No. Place Date Activity

1 Hyderabad 10-10-2012 Attended ENC (PR) office and attendeddiscussion with PD SPIU in ENC (PR) chambers.

2 Hyderabad 15-10-2012

 Attended NCRMP office for Review meeting by

PM SPIU on TPQA Performance.

3 Hyderabad 17-10-2012 Attended NCRMP office for Review meeting byPM SPIU.

4 Hyderabad 19-10-2012 Attended NCRMP Review meeting in chambers of Commissioner DMA at 5th floor ‘L’ block APSecretariat.

5 Hyderabad 29-10-2012 Attended NCRMP Review meeting in Chief Secretary Peshi in ‘C’ block AP Secretariat.

6 Srikakulam 21.11.2012 Attended Review meeting at Srikakulam withWorld Bank ISR mission

7 Vi kh t 22 11 2012 Att d d R i ti t Vi kh t ith

Page 11: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 11/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3.0 Status of TPQA Visits:

The following table shows the details of TPQA visits to sites in respective districts.

DistrictTotal Number of Visits

TotalOct.'2012 Nov.'2012 Dec.'2012

Srikakulam 28 28 36 92Vizianagaram 5 05 01 11

Vishakhapatnam 19 11 23 53

East Godavari 16 32 22 70

West Godavari 10 13 26 49

Krishna 10 14 38 62

Guntur  23 21 32 76

Prakasam 27 17 23 67

Nellore 9 13 16 38

No. of Visits by TPQA

Page 12: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 12/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4.0 Progress of NCRMP works:

The district wise progress of works is shown below. The works in the West Godavari are not started and the works in

Krishna District has just started. At many places the first milestone is completed but works are not started. The line

departments are to analyze the reasons for the slow progress and if necessary penalty for the slow progress as per the

agreement conditions should be imposed.

Third Party Quality Audit by Egis – India consulting services

Summary of Activities

S.No. District

Agreements for PackagesCommunicated

Status of works

PR R&B Progress Not Started

1 Srikakulam 6 5 21 0

2 Vizianagaram - 3 3 0

3 Visakhapatnam 13 0 21 0

4 East Godavari 7 0 12 1

Page 13: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 13/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

TPQA STATUS REPORT FOR NCRMP WORKS TO THE END OF DECEMBER 2012

S.No.

District

Packages /

Worksentrusted

Status of Works No. of  Visits of 

TPQA

Total No.

of QCtestsdone

NCRs  AuditReportsIssued

Environmental

& SocialReportsIssuedPR R&B Started

NotStarted

Issued closed Pending

1 Srikakulam 16 5 21 0 452 1475 54 54 0 77 57

2 Vizianagaram - 3 3 0 72 461 3 1 2 11 9

3 Visakhapatnam 21 - 21 0 361 2237 25 25 0 71 41

4 East Godavari 13 - 12 1 612 1128 28 28 0 58 31

5 West Godavari 10 - 10 0 436 349 20 20 0 52 37

6 Krishna 8 - 8 0 299 85 3 3 0 35 21

7 Guntur 15 2 17 0 373 606 14 13 1 60 32

8 Prakasam 23 1 24 0 407 1905 36 30 6 116 50

9 Nellore 26 - 26 0 323 1174 32 28 4 109 48

Total 132 11 142 1 3335 9420 215 202 13 589 326

Page 14: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 14/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Status of works in Srikakulam District up to 31.12.2012

CategoryPackages allottedunder Phase - 1

Names of works undereach package

 AgreementNo. / Date

Milestone Completion Dates Progress w.r.t.milestone upto 31.12.2012

Remarks

First Second Third

RHB

NCRMP/B-W/AP/RHB/ PRED/01/Santhabommali/003

Road from DPN R&B road toUddandapalem

 /2010-11, Dt.30.04.2011

31.08.11 31.12.11 30.04.12complete Entire

work completed

Road from K. Umilada Junctionto Koduru (Link Road)

 /2010-11, Dt.30.04.2011

31.08.11 31.12.11 30.04.12complete Entire

work completed

Road from Borubhadra,Malagam to Kollipadu via

Seepuram, Gantapeta

 /2010-11, Dt.30.04.2011

31.08.11 31.12.11 30.04.12complete Entire

work completed

NCRMP/B-W/AP/RHB/PRED/01 /Polaki/006

Road from R&B road Mobagamto Duubakavanipeta via

Gajapathinagaram

 /2010-11, Dt.30.04.2011

30.08.11 31.12.11 30.04.12First Milestonei.e Earthwork & Cd works &GSB

300 mts CCroad

completed,GSB laying isin progress,

roadformationwidth vary

from 6.00mtsto 7.50mts

Road from Talasamudram to

Dola Regulator

 /2010-11, Dt.

30.04.201130.08.11 31.12.11 30.04.12

First Milestonei.e Earthwork & Cd works &GSB

completed

NCRMP/B-W/AP/RHB/PRED/01 /Polaki/005

Road from R&B roadEdulavalasa - Killam to Jonnam

via Talasamudram

 /2011-12, Dt.30.04.2011

31.07.11 31.10.11 31.01.12First Milestonei.e Earthwork & Cd works &GSB

BT layercompletedfrom Km

5/670 to Km7/270, andWBM Gr- III

metalcollection is

Page 15: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 15/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

in progressfrom Km

5/000 to Km5/670

Bridges

NCRMP/B-W/ AP/Br/R&B/01/Patnavanipeta/001

Construction of bridge at Km11/6-8 of NH-5 toPatnavanipeta ConnectingSundarapalem

46/2011, Dt.17.12.2010

17.08.11 17.01.12 17.06.12Completion of entire work 

Slab A2-piercompletedand Slab A1-pier sis inprogress,Approach roade/w,GSB,WMM,SDBCcompleted.CD,R/W workscompleted.

NCRMP/B-W/AP/Br/R&B/01/Surampeta/003

Construction of Minor Bridge atKm 12/2-4 of NH-5 to

Surampeta Road via Naruva,mentada

45/2010-2011,

Dt17.12.201017.05.11 17.10.11 17.03.12

Completion of entire work 

Deck slabsweiring coat& hand railscompleted,A 

pproacheroad work completed.

NCRMP/B-W/AP/Br/R&B/01/Bendigedda/004

Construction of High levelbridge across Bendi gedda at

KM 4/10 of Pundi-Parlakimidiroad in Srikakulam Dt, A.P.

1/2010,Dt.11.11.201

011.08.11 11.01.12 11.06.12

Completion of 

entire work 

Bridge work completed, Approach

roadcompletedupto WMMlayers, And

SDBCpending.

RoadsNCRMP/B-W/AP/RD/R&B/01/Nowpada/006)

Improvesments Naupada- Venkatapuram road from0/0to15/0km

43/2010-11,17.12.2010 17.05.11 17.10.11 17.03.12

Completion of 

entire work 

work 

completed

Roads tocyclonic

NCRMP/B-W/AP/RCS/PRED/01

Road from NP road toURKpuram

G.o rt No 451dt

29.01.12 29.05.12 29.09.12WBM GR-II &III

completework 

completed

Page 16: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 16/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

shelters  /V.KOTTURU/002 06.04.2010

Road from Deppuru,Bahadapalli road to onkuluru & to cyclone shelter

G.o rt No 451dt

06.04.201129.01.12 29.05.12 29.09.12

WBM GR-II &IIIcomplete

work completed

Road from R&B road toDevunthalada

G.o rt No 451dt

06.04.201229.01.12 29.05.12 29.09.12

WBM GR-II &IIIcomplete

work completed

Road from pollada toKomarthalada & to cycloneshelter

G.o rt No 451dt

06.04.201329.01.12 29.05.12 29.09.12

WBM GR-II &IIIcomplete

work completed

NCRMP/B-W/AP/RCS/PRED/01

 /ETCHERLA/005

Road from Koyyam R&B Roadto Moosavanipeta

G.o rt No 451dt

06.04.201007.11.11 07.02.12 07.06.12

Completion of entire work 

work completed

Road from Mentada toDovupeta

G.o rt No 451dt

06.04.2010

07.11.11 07.02.12 07.06.12Completion of entire work 

work completed

Road from Kotcherela road toKollibhemavaram & cycloneshelter

G.o rt No 451dt

06.04.201007.11.11 07.02.12 07.06.12

Completion of entire work 

work completed

Road from Kotcherla road toPathasundarapalem

G.o rt No 451dt

06.04.201007.11.11 07.02.12 07.06.12

Completion of entire work 

work completed

MPCS

NCRMP/B_W/AP/MP

CS/PRED/01/Santhabommalli/005

Construction of Cyclone shelterat Kollipadu

G.o rt No 451dt

06.04.201007.03.12 07.08.12 07.01.13

Completion of stilt floor & first

floor

Silt floor levelslab

completed.

Construction of CycloneShelter at Runku

G.o rt No 451dt

06.04.201007.03.12 07.08.12 07.01.13

Completion of stilt floor & first

floor

Upto plinthbeam

completed,and columnsabove plinthbeam is inprogress

Page 17: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 17/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN VIZIANAGARAM DISTRICT UP TO 31.12.2012

CategoryPackages

allotted underPhase – 1

Names of works under eachpackage

 AgreementNo./ Date

Milestone Completion Dates Progress w.r.t.milestone upto 31.12.2012

RemarksFirst Second Third

Bridges

NCRMP/B-W/ AP/Br/ R&B/

02/Puligadda/ 007

Construction of Minor Bridge atKm. 7/2 near Puligedda of 

Konada – Ramatheertham R&BRoad to Konathalapalem via

 Yerukonda, Pasupam,Kollayavalsa (Z.P. Road)

31/2010-2011Dt. 01.12.2010

30.06.11 31.01.12 31.05.12100% of work 

completed

 As against of 100 % in the 3rd

Milestone

NCRMP/B-W/ AP/Br/ R&B/ 02/Chakaligadda

 /008

Construction of Minor Bridge atKm 15/2 near Chakaligadda of Konada Ramatheertham R&Broad to Konathalapalem (via)

 Yerukonda, Pasupam,Kollayavalsa (ZP Road)

34/2010-2011Dt. 08.12.2010

07.07.11 07.02.12 07.06.1290% of work completed

Minor deviationapproval is

awaited. It takes15 days’ time to

complete thework afterdeviationapproval

Road

NCRMP/B-

W/AP/RD/R&B/02/ Konada/009

Improvements to Road fromKonada Ramatheertham (R&B)Road to Konathalapalem (Via)

Pasupam, Yerukonda,Kollayavalsa from Km 12/0 to16/5 (Km 0/0 to 4/0 i.e. up to

NH-5 crossing)

33/2010-2011

Dt. 08.12.2010 07.06.11 07.12.11 07.03.12

100% of work 

completed -

Page 18: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 18/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF TOTAL WORKS IN VISAKHAPATNAM DISTRICT UP TO DECEMBER-31.12.2012

Categor y

Packagesallotted underPhase – 1

Names of worksunder each package

 AgreementNo. / Date

Milestone Completion DatesProgress w.r.t.milestone up to

30.12.2012Remarks

First Second Third

MPCS

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/

003

Construction of cycloneshelter at

Gajapathinagaram

 /2011-12, Dt.03.10.2011

05.06.12 05.10.12 05.02.13

Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOAT submittedon 24.08.12

likely to becompleted

beforeMarch.201

3

Construction of cycloneshelter at Ratnayampeta

 /2011-12, Dt.03.10.2011

02.02.12 02.06.12 02.10.12

 All Slabs are completed.Inside and outside wallplastering work completed.White cement applications,wood joinery and Electricalworks are to be progress.

likely to becompleted

before15.02.2013

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cycloneshelter at Patimeeda

 /2011-12, Dt.03.10.2011

02.03.12 02.08.12 02.01.13

Plinth beam & Staircase,Stilt floor slab, First floorslab, ramp slabs arecompleted. EOATsubmitted on 24.08.12

likely to becompleted

beforeMarch.201

3

Construction of cycloneshelter at Mullaparra

 /2011-12, Dt.03.10.2011

02.03.12 02.08.12 02.01.13

Stilt Slab & stilt floor, Firstfloor and head room slabsare completed. Ceilingplastering work and firstfloor brick work are inprogress.

likely to becompleted

beforeMarch.201

3

Page 19: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 19/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Construction of cycloneshelter at Bangarampeta

 /2011-12, Dt.03.10.2011

02.03.12 02.08.12 02.01.13

Stilt floor, First floor,second floor, Head roomslabs are completed. Istfloor and second floor brick 

masonry work is inprogress.

likely to becompleted

before

March.2013

NCRMP/B-W/AP/MPCS/PRED/

03/Rambilli/004

Construction of cycloneshelter at

 Venkayyapalem

 /2011-12, Dt.03.10.2011

02.01.12 02.04.12 02.07.12

Plinth beam completed andfilling under floor is inprogress. EOAT proposalssubmitted on 29.06.12.

likely to becompleted

beforeJune.2013

NCRMP/B-W/AP/MPCS/PRED/03/Parawada/001

Construction of cycloneshelter at

Thikkavanipalem

 /2011-12, Dt.07.10.2011

06.01.12 06.04.12 06.07.12Work not started due tosite problem

Progressis Slow

NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/00

1

Road from NH-5 toRamarayadupalem

 /2011-12, Dt.15.09.2011

14.12.11 14.03.12 14.06.12Road Furniture & B.T is

completed.completed

NCRMP/B-W/AP/RCS/PRED/0

3/Rambilli/002

Road from R & B road toRajakoduru

 /2011-12, Dt.15.09.2011

14.01.12 14.05.12 14.09.12CD works are completed & 

B.T work is Completedcompleted

Road from R & B road toKattubolu to Marripalem

 /2011-12, Dt.15.09.2011

14.01.12 14.05.12 14.09.12CD works are completed & 

B.T work is Completedcompleted

Road from R & B road toKrishnampalem

 /2011-12, Dt.15.09.2011

14.01.12 14.05.12 14.09.12 CD Work is completed & B.T work is completed

completed

NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003

Road from R&B road toPedatheernala toChinatheernala

 /2011-12, Dt.15.09.2011

14.12.11 14.03.12 14.06.12B.T & C.C road works are

Completed.completed

Page 20: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 20/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from UpmakaRajayyapeta R&B road

to Janakayyapeta

 /2011-12, Dt.15.09.2011

14.12.11 14.03.12 14.06.12CD works are Completed & 

B.T work is completedcompleted

NCRMP/B-W/AP/RHB/PRED/03/Nakkapalli/001

Road from Vempudi toPatimeeda

 /2010-11, Dt.11.01.2011

10.05.11 10.09.11 10.01.12 Work is completed -

Road from R&B road toMullaparra up to Beach

end

 /2010-11, Dt.27.01.2011

26.04.11 26.07.11 26.10.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/00

3

Road from R&B B.PKallalu to

Matchvanipalem

 /2010-11, Dt.10.03.2011

09.06.11 09.09.11 09.12.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/0

3/Paravada/004

Road from R & B road to

Pothurajanapalem

 /2010-11, Dt.

28.03.2011

27.06.11 27.09.11 27.12.11 Work is completed -

Road from R & B road toJalaripeta

 /2010-11, Dt.28.03.2011

27.06.11 27.09.11 27.12.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/0

3/Rambilli/006

Road from R & B road to Venkayyapalem

 /2010-11, Dt.11.01.2011

10.04.11 10.07.11 10.10.11 Work is completed -

NCRMP/B-W/AP/RHB/PRED/03/Atchutapuram/0

07

Road from R&B road to

 Ava- Somavaram

 /2011-12, Dt.

27.04.2011 26.07.11 26.10.11 26.01.12 Work is completed -

Road from R&B Road to Avarajam

 /2011-12, Dt.27.04.2011

26.07.11 26.10.11 26.01.12 Work is completed -

Page 21: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 21/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF TOTAL WORKS IN EAST GODAVARI DISTRICT UP TO DECEMBER-31.12.2012.

Category Packages allotted underPhase - 1 Names of worksunder each package  Agreement No./ Date

Milestone Completion Dates

Progress

w.r.t.

milestoneup to

31.07.2012

Remarks

First Second Third

RCS

NCRMP/B-W /RCS/PRED/04/Karapa/001

 Approach Road tocyclone Shelter at Adivipudi

32/2011-12Dt:20.05.2011

30-11-2011 31-10-2011 31-01-2012 100% Completed.

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto P.Chodipallipeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012

100% Completed.

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto K.Chodipallipeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012

100% Completed

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto Hukumpeta CS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012

100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003

Road from R&B Roadto ChinaraghavulapetaCyclone Shelter

74/2011-12Dt: 23.09.2011

3 months22.11.2011

3 months22.06.2011

----------- 100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto Gaddipeta CS

73 /2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012

100% Completed

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto Danavaipeta CS

73 /2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012

100% Completed

Page 22: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 22/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RCS/PRED/04/Thondangi/004

Road from R&B Roadto G.MusalayyapetaCS

73/2011-12Dt:07.09.2011

3 months06.12.2011

3 months06.03.2012

3 months06.06.2012

NilNot yetStarted

RHB

NCRMP/B-W/AP/RHB/PRED/04/Karapa/001

Road fromGurjanapalli toBandulavaripalem

24/2011-12Dt:27.04.2011

30-09-2011 31-10-2011 31-01-2012 100% Completed

NCRMP/B-W/AP/RHB/PRED/04/Katrenikona/003

Road from PR roadsto Dasarivanipeta andto Cyclone Shelter

18/2011-12Dt:27.04.2011

30-11-2011 30-11-2011 20-01-2012 100% Completed.

MPCS

NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Construction of Cyclone Shelter atPedaraghavulapeta of Uppalaguptam Mandal

E.G.Dt.

78/2011-12Dt:17.10.2011

3 months16.01.2012

3 months16.04.2012

3 months16.07.2012

30%

Likely to becompleted byJune 2013

NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter atLakshmanudipeta inThondangi

77/2011-12Dt:07.09.2011

4 months16.02.2012

4 months16.06.2012

4 months16.10.2012

75%

Likely to becompleted byMarch 2013

NCRMP/B-W /AP/MPCS/PRED/04/Thondangi/001

Construction of Cyclone Shelter at Avulamanda

77/2011-12Dt:07.09.2011

4 months16.02.2012

4 months16.06.2012

4 months16.10.2012

75%

Likely to becompleted byMarch 2013

Page 23: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 23/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN WEST GODAVARI DISTRICT UP TO 30.11.2012

Category

Packagesallotted under

Phase – 1

Names of works under eachpackage

 AgreementNo. / Date

Milestone Completion Dates Progress w.r.t.milestone up

to 30.11.2012

RemarksFirst Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/001

Road from NH 214 A at Ranga Statuecenter to Harijanawada of Kalipatnam

(E) (Mogalthuru Mandal

16 /2011-12Dt.27.04.2011

27/4/2011to

22/9/2011

23/9/2011to

24/2/2012

25/2/2012to

26/7/2012

100% Completed

R&B road at Panchayat Office toPulaparthivarithota via Badava(Mogalthuru Mandal W.G.Dist.)

100% Completed

Mogalthuru Vempa R&B Road atUchintha Kalava Bridge to Gogulamma

Harijanapeta (Mogalthuru Mandal)100% Completed

From Narsapur Mogalthuru R&B road toDayadaldaspeta via VenkateshwaraSwamy temple (Mogalthuru Mandal )

100% Completed

Road from NH 214 A road toHarijanapeta of Kothota

27/4/2011to

22/9/2011

23/9/2011to

24/2/2012

25/2/2012to

26/7/2012100% Completed

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

R&B road to Indira Nagar (via)Pochamma temple (Narsapur Mandal)

21 /2011-12Dt.09.05.2011

09/05/2011to

04/09/2011

05/09/2011to

06/01/2012

07/01/2011to

08/5/2012

100% Completed

Road from R&B road to Pedalanka(Narsapur Mandal W.G.Dist.)

100% Completed

Road from LB Cheria CC road to

Chillapalem of LB Cheria.

100% Completed

NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road toSatyanarayanapuram (Kalla Mandal)

25 /2011-12Dt.26.05.2011

26/5/2011To

20/8/2011

20/8/2011to

21/11/2011

22/11/2011To

23/2/2012

100% Completed

From A-U R&B Road to Mekaladibba(Kalla Mandal W.G.Dist.)

100% Completed

Page 24: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 24/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN KRISHNA DISTRICT UP TO 31.12.2012

Category

Packages allottedunder Phase - 1

Names of works undereach package

 Agreement No. /Date

Milestone Completion Dates Remarks

First Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/06/Ma

chilipatnam/001

Road connecting R&B roadthrough Gantlammapalem

8/2011-12/27.04.2011

26.07.2011 26.10.2011 26.01.2012 Completed

NCRMP/B-W/AP/RHB/PRED/06/Ma

chilipatnam/002

Road from R & B Road toB.V Thota

7/2011-12/27.04.2011

26.07.2011 26.10.2011 26.01.2012 Completed

Road from Potalapalem Z.P

road to Chikativanipalem

7/2011-

12/27.04.2011 26.07.2011 26.10.2011 26.01.2012 Completed

NCRMP/B-W/AP/RHB/PRED/06/Kr

uthivennu/003

Road from Intheru R&BRoad to Rangaraopet

9/2011-12/27.04.2011

26.07.2011 26.10.2011 26.01.2012 Completed

Road from R&B road toCyclone Shelter atChandala

9/2011-12/27.04.2011

26.07.2011 26.10.2011 26.01.2012 Completed

RCSNCRMP/B-W

 /AP/RCS/PRED/06/Machilipatnam/001

Road from BhogireddypalliR&B Road toRamakhandam

32/2011-12/Dt.02.09.2011

01.12.2011 01.03.2012 01.06.2012CD works, GSB, Gr-II,

Gr-III, BT,CCcompleted

Road from R&B RoadChinnapuram toGundupalem

32/2011-12/27.04.2011

01.12.2011 01.03.2012 01.06.2012CD works, GSB, Gr-II,Gr-III,BT completed

Road from Potalapalem Z.Proad to Pothepalli.

32/2011-12/Dt.02.09.2011

01.12.2011 01.03.2012 01.06.2012GSB, Gr-II, Gr-III,CC,BT completed

Page 25: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 25/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN GUNTUR DISTRICT UP TO 31.12.2012

Category

Packages allottedunder Phase - 1

Names of works undereach package

 Agreement No./Date

Milestone completion datesProgress

w.r.t.milestone

up to31.11.2012

RemarksFirst Second Third

RHB

NCRMP/B-W/AP/RHB/PRED/07/KA 

RLAPALEM/001

R/f Ganapavaram R&BRoad to Kesavapuri ST colony

7/2011-2012

27.04.2011

26.7.2011 26.10.2011 26.01.2012 - Completed.

NCRMP/B-W/AP/PRED/07/Nagara

m/002

R/f R&B Road to Mohammad Alipalem 8/2011-

201227.04.2011

26.8.2011 26.12.2011 26.4.2012 - Completed.

R/f R&B Road toKaturivaripalem.

- Completed.

Bridges

NCRMP/B-W/AP/Br/R&B/07/Bapatl

a/010

Reconstruction of High-levelBridge @Km5/2 of Bapatla-Suryalanka Road across peralidrain in Guntur Dt.

79/2010-2011

1.12.2010

31.5.2011 30.11.2011 31.5.2012

90%

Likely to becompletedby end of Jan 2013

NCRMP/B-W/AP/Br/R&B/07/Bapatl

a/011

Reconstruction of High-levelBridge @Km2/4 of Bapatla-Pandurangapuram Road acrossperali drain in Guntur Dt.

78/2010-2011

1.12.2010

31.5.2011 30.11.2011 31.5.2012

90%

Likely to becompleted

beforeMarch 2013

RCS

NCRMP/B-

W/AP/RCS/PRED/07/PVPalem/001

Road from R&B road toMandevaripalem

2011-2012

1.11.2011

31.01.2012 30.04.2012 31.07.2012- Completed.

Road from R&B Road Alluru to Yadavapalem

31.01.2012 30.04.2012 31.07.2012

45%

Likely to be

completedbefore Feb

2013

NCRMP/B-W/AP/RCS/PRED/07/Karl

apalem/002

Road from Ganapavaram R&BRoad to Pedamarpuvaripalem

2011-20121.11.2011

29.02.2012 30.06.2012 31.10.2012

20%

Likely to becompletedbefore Jan

2013

Road from R&B Road toChinapuluguvaripalem

29.02.2012 30.06.2012 31.10.201225%

Likely to becompletedbefore Jan

Page 26: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 26/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2013

From R&B roadtoYaramvaripalem

29.02.2012 30.06.2012 31.10.201295% Completed.

Road from R&B Road toPedagollapalem CycloneShelter

29.02.2012 30.06.2012 31.10.201298% Completed.

Pedagollapalem P.R road toBonthagoralapalem

29.02.2012 30.06.2012 31.10.201295%

Shouldersare in

progress.

NCRMP/B-W/AP/RCS/PRED/07/Niz

ampatnam/003

Road from R&B Road toGurunadhanagar

2011-201217.10.2011

16.01.2012 16.04.2012 16.07.201299% Completed.

Road from R & B Road to Adavala H/O Bavaji Palem

16.01.2012 16.04.2012 16.07.201299% Completed.

Road from R & B Road to Atlavaripalem 16.01.2012 16.04.2012 16.07.2012 99% Completed.

NCRMP/B-W/AP/RCS/PRED/07/Bap

atla/004

Road from R & B Road toHanumathanagar

2011-201227.10.2011

26.01.2012 26.04.2012 26.07.201299% Completed.

Road from R & B Road to Adarsh nagar

26.01.2012 26.04.2012 26.07.201299% Completed.

Page 27: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 27/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN PRAKASAM DISTRICT UP TO 31.12.2012

Category

Packages allottedunder Phase - 1

Names of works undereach package

 Agreement No. /Date

Milestone completion dates Progress of work for the

month -December

Remarks

First Second Third

BRIDGES

NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012

Construction of High levelBridge at Km 16/10 of Naguluppapadu – Kanaparthyroad

76/2010-11Dated1/12/2010

5/31/2011Completionup to silllevel

12/31/2011Completionup to belowdeck slab

5/31/2012Completion of entirework includingapproach

es

Bridge work iscompleted.

completed

RHBNCRMP/B-W/AP/RHB/PRED/08/S.K onda/001

Road from Pakala ZP Road to Aulavaripalem Cyclone shelter

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001Dated25.04.2011

8/24/2011Earth work,CD work,

GSB

12/24/2011WBM,

Grade II & 

III

4/24/2012BT,

Shoulders& road

furniture

CC Road & Shoulderswork isCompleted.

completed

Road from R&B Road toSomarajupalli

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001

Dated25.04.2011

BT, CC road & culverts arecompletedfrom KM 0/0 to

2/146.

completed

Road from R&B road toNarravaripalem

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/001Dated25.04.2011

BT, & culvertsare Completedfrom KM 0/0 to0/900. work iscompleted

completed

Page 28: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 28/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/08/S.K onda/002

Road from NH5 toMulaguntapadu

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

dated10/02/2011

6/9/2011Earth work,CD work,

GSB

10/9/2011WBM,

Grade II & III

2/9/2012BT,

Shoulders& road

furniture

WBM-Grade-III LayerCompleted.OGPC + Seal

Coat To betaken up

80%

Road from R&B road toChalivendradibba

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002dated -10/02/2011

WBM-Grade-III LayerCompleted.OGPC + SealCoat To betaken up

80%

NCRMP/B-W/AP/RHB/PRED/08/S.K onda/002

Road from Pakala R&B road to

Mosanaladinne

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002dated10/02/2011

6/9/2011Earth work,CD work,

GSB

10/9/2011WBM,

Grade II & III

2/9/2012BT,

Shoulders& road

furniture

WBM-Grade-III materiallaying work isin progress

75%

Road from R&B road toBinginapalli HarijanawadaCyclone Shelter

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002dated10/02/2011

CC road work is completedfrom KM 0/0 toKM 0/220.Shoulderswork is to betaken up.

98%

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

Road from R&B Road Allur toM T Raju colony

NCRMP/B-

W/AP/RHB/PRED/08/K othapatnam /003 Dated27/04/2011

8/26/2011Earth work,CD work,GSB

12/26/2011WBM,Grade II & III

4/26/2012

BT,Shoulders& roadfurniture

BT, CC road,shoulders & 

culverts arecompletedfrom km 0/0 tokm 3/8.work iscompleted

completed

NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

Road from KEM R&B Road toSankuvarigunta

NCRMP/B-W/AP/RHB/PRED/08/K othapatnam

9/26/2011Earth work,CD work,

GSB

2/26/2012WBM,

Grade II & III

7/26/2012BT,

Shoulders& road

BTcompleted.CDwork completed.CC

completed

Page 29: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 29/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

 /004 Dated27/04/2011

furniture road work completedfrom km 0/0 tokm 1/430 and

CC dip work iscompleted

Road from KEM R & B Road toPullareddypalem

NCRMP/B-W/AP/RHB/PRED/08/K othapatnam /004 Dated27/04/2011

BTcompleted.CDwork completed.CCroad andshoulders work completedfrom km 0/0 tokm 3/900.

completed

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07

Road from MC Road toSubbarayudu Satram

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/07dated27/04/2011

8/26/2011Earth work,CD work,GSB

12/26/2011WBM,Grade II & III

4/26/2012BT,Shoulders& roadfurniture

BTcompleted.CDwork completed andshoulders work completedfrom km 0/0 tokm 3/4. work is completed

completed

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08

Road from R&B road Tettu toRamayapatnam

NCRMP/B-W/AP/RHB/PRED/08/Ulavapadu/08dated27/04/2011

8/26/2011Earth work,CD work,GSB

12/26/2011WBM,Grade II & III

4/26/2012BT,Shoulders& roadfurniture

BTcompleted.CDwork 

completed.CCroad andshoulders work completedfrom km 0/0 tokm 5/086.work iscompleted

completed

Page 30: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 30/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-

W/AP/RHB/PRED/08/Tangutur/09

Road from R&B road Pellur to Vasepallipadu

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09dated16/03/2011

7/15/2011Earth work,CD work,GSB

11/15/2011WBM,Grade II & III

3/15/2012BT,

Shoulders& roadfurniture

BT completed.CD work completed.CCroad and

shoulders work completedfrom km 0/0 tokm 4/5. work is completed

completed

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10

Road from R&B road toKesupalem

NCRMP/B-W/AP/RHB/PRED/08/Tangutur/10dated19/04/2011

7/18/2011Earth work,CD work,GSB

10/18/2011WBM,Grade II & II

1/18/2012BT,Shoulders& road

furniture

BT completed.CD work completed.CCroad andshoulders work completedfrom km 0/0 tokm 2/103.work iscompleted

completed

RCSNCRMP/B-W/AP/RCS/PRED/08/Vetapalem/001

Road from R&B road to Vijayanagar colony cycloneshelter

NCRMP/B-W/AP/RCS/PRED/08/V

etapalem/001 dated2011/12dated30.09.2011

1/29/2012Earth work,GSB

5/29/2012shoulders,Gr-III

9/29/2012BT, CCpavementand roadfurniture

cc roadcompleted, BTroadcompleted& shoulderscompleted.Road from km0/0 to km

0/525. work iscompleted

completed

Road from NH road toChallareddypalem

cc roadcompleted, BTroadcompleted& shoulderscompleted.Road from km0/0 to km

completed

Page 31: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 31/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1/735. work iscompleted

Road from R&B road to jeevaraksh nagar colonycyclone shelter

C.C.road andShoulders arecompletedRoad from km0/0 to km0/500.

completed

Road from R&B road toRamnagar colony cycloneshelter

C.C.completedRoad from km0/0 to km0/475.Shoulders to be taken

up.

completed

Road from R&B road tocyclone shelter atMankenavaripalem

CC roadcompleted.Shoulderswork is to betaken up.

completed

NCRMP/B-W/AP/RCS/PRED/08/Chirala/002

Road from R&B Road toKeerthivaripalem cycloneshelter NCRMP/B-

W/AP/RCS/

PRED/08/Chirala/002dated27.08.2011

C.C road andShoulders arecompletedfrom km 0/0 tokm 0/265.work is

completed

completed

Road from R&B Road toDevinuthula cyclone shelter of Chirala Mandal

C.C road andShoulders arecompletedfrom km 0/0 tokm 0/800.work iscompleted

completed

Page 32: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 32/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

MPCSNCRMP/B-W/APMPCS/PRED/08/Ulavapadu/001

Chakicharla cyclone shelter inUlavapadu Mandal

NCRMP/B-W/AP/MPCS /PRED/08/Ulavapadu/001

24.11.2011 All items upto stilt floorslabincludingramp, staircasefoundations

, columns,beams, pccflooringetc.,

24.02.2012 All items upto secondfloor slabincludingfirst floor,and in 2ndfloor

includingstair case,columnsetc.,

24.05.2012 Headroom,plastering

, flooring,watersupplyarrangements,sanitaryfitting,electricalitems,compound wall, ccpavement. Earthenmounds(raisedportion),waterharvesting, septictank,slump andsoak pit.etc.,

Stilt floor, G.F ,& Terracefloor- roof slabcompleted.Brick work completed,Plasteringwork completed,Cattle platformcompletedrevetmentwork completed,

flooring work is completed,compound wall120 meterslengthcompleted,Electrical work is completed.work iscompleted

completed

Page 33: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 33/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/APMPCS/PRED/08/NGPadu/003

Kanaparthy cyclone shelter inNaguluppapadu Mandalprakasam district

NCRMP/B-W/AP/MPCS /PRED/08/NGPadu/003

23.11.2011 All items upto stilt floorslabincludingramp, staircasefoundations, columns,

beams, pccflooringetc.,

23.02.2012 All items upto first floorslab andhead roomslb in 2 ndfloorincluding

stair case,columnsetc.,

23.05.2012plastering, flooring,

watersupplyarrangements,sanitaryfitting,electricalitems,compound wall, ccpavement. Earthen

mounds(raisedportion),waterharvesting, septictank,slump andsoak pit.etc.,

Internal & ExternalPlasteringcompleted.Flooring Work Completed.CompoundWall PaintingCompleted. CCRoadCompleted.Shoulder work in Completed.Painting work in Completed.

ElectricalFittings inprogress. Tilesin bathroomswork inCompleted.Water harvest& Soak pitwork incompleted.

completed

Page 34: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 34/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATUS OF WORKS IN SPSR NELLORE DISTRICT UP TO 31.12.2012

Name of package Name of work  date of 

agreement

mile stone -I mile stone -IImile stone -

III

Present

Statues of work 

Remark 

s

RHB

NCRMP/B-W/AP/RHB/PRED/09/BOGOLO/RHB/

001

1. Road from NH5 toSambasiva Puram

1/19/20115Months: Earth

Work, PipeCulverts, GSB

10 Months:WBM Gr-II,Gr-II andShoulders

15 Months:BT and Road

Furniture

OGPC+ SCcompleted

completed

Road from 9/6 of JuvvaladinneR&B Road to 11/0 of 

Juvvaladinne R&B Road Via Venkateshpalem

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/002

Road from 1/6 of ZuvvaladinneR&B Road to Tellagunta KM to

2/72007.02.2011

6.5,2011 3Months:Earth Work, Pipe

Culverts, GSB

6.8.2011 6Months: WBMGr-II, Gr-II

and Shoulders

6.11.20119Months: BTand RoadFurniture

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/CHITTAMURU/

003

Road from R&B Road toMuttambeka Via Pittuvanipalla

18.01.201117.6.2011

5Months: EarthWork, Pipe

Culverts, GSB

17.11.2011 10Months: WBMGr-II, Gr-II

and Shoulders

17.4.2012 15Months: BTand RoadFurniture

OGPC+ SCcompleted

completed

Road from R&B Chittamur toSoma Samudram

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI/0

04

Road from5/8 of Chennayapalem Road to

Gummadi bandla

17.01.2011

16.6.20115Months: Earthwork, CD

Works, ccpavement and

GSB

16.11.2011 10Months: WBMGr-II, Gr-Ii I

and Shoulders

16.4.201215 Months:

BT and RoadFurniture

OGPC+ SCcompleted

completed

Road from pedattapupalemR&B road to Chennayapalem

H.wada

OGPC+ SCcompleted

completed

Road from K.T R&B Road to Alliguntapalem

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/

005

1)Road from KT R&B road to Alaganipadu to Vavilla

27.04.2011

26.9.20115Months: Earth

Work, PipeCulverts, GSB

26.2.201210Months: WBMGr-II, Gr-II

and Shoulders

26.7.2012 15Months: BTand RoadFurniture

OGPC+SCcompleted

completed

Road from R&B roadKancharapalem HW to

 Alaganipadu.

WBM Gr-II isin progress & 

CD Workscompleted.

77%

NCRMP/B-W/AP/PRED/09/MUTHUKUR/RHB/0

Road from R&B road toPatuvari Kandriga

25.4.1124.7.2011

3Months: EarthWork, Pipe

24.10.2011 6Months: WBMGr-II, Gr-II,

24.1.2012 9Months: BTand Road

OGPC+ SCcompleted

96%

Page 35: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 35/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

06 Culverts, GSB CC Pavementand Shoulders

Furniture

NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB

 /007

Road from Survepalli-Pudiparthi

road to Srikanth Colony27.04.2011

26.8.20114Months: EarthWork, Pipe

Culverts, GSB

26.12.2011 8Months: WBMGr-II, Gr-II

and Shoulders

26.4.2012 12Months: BTand RoadFurniture

OGPC+ SC

completed

comple

tedproviding BT Surface to the

road from R&B road to EdagaliKandriga

OGPC+ SCcompleted

97%

NCRMP/B-W/AP/RHB/PRED/

09/Allur/009

Road from R&B road Alluru toGalidibbalu (via) Chukavani

dibba24.01.2011

23.6.20115Months: Earth

Work, PipeCulverts, GSB

23.11.2011 10Months: WBMGr-II, Gr-II

and Shoulders

23.4.2012 15Months: BTand RoadFurniture

OGPC+ SCcompleted

99%

NCRMP/B-W/AP/RHB/PRED/009/T.P.GUDUR/0

12

Ring Road to TP Gudur-Salipeta R & B Road via CS

Puram and Mandapam Village 19.05.2011

18.8.20113Months: Earth

Work, Pipe

Culverts, GSB

18.11.2011 6Months: WBMGr-II, Gr-II,

CC Pavementand Shoulders

18.2.2012 9Months: BTand Road

Furniture

OGPC+ SCcompleted

96%

Road from R & B Road C SPuram to Sivaramapuram OGPC+ SCcompleted 98%

RCS

NCRMP/B-W/AP/PRED/09/k ota/RCS /001

Road from R&B road to A.SPURAM

10.05.20119.8.2011 3Months:Earth Work, Pipe

Culverts, GSB

9.11.11 6Months: WBMGr-II, Gr-II

and Shoulders

9.2.2012 9Months: BT,CC Pavement

and RoadFurniture

OGPC+ SCcompleted

98%

NCRMP/B-W/AP/PRED/09/k ota/RCS /001

Road from GD Road to VavillaPalem

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/PRED/09/MUTHUKUR/RCS/00

2

Road from R&B Roadkappaladoruvu to bandla Palem

H.wada

21.04.2011

20.7.20113Months: Earth

Work, Pipe

Culverts, GSB

20.10.2011 6Months: WBMGr-II, Gr-II,CC

Pavement andShoulders

20.1.2012 9Months: BTCC road and

RoadFurniture

OGPC+ SCcompleted

98%

NCRMP/B-W/AP/PRED/09/Chillakur/RCS/004

Road from Kakuvaripalem R&Broad to Vellapalem

23.05.2011

22.8.20113Months: Earth

Work, CD Works,GSB

22.11.2011 6Months: WBMGr-II, Gr-II

and Shoulders

22.2.2012 9Months: BT,CC Pavement

and RoadFurniture

OGPC+ SCcompleted

completed

NCRMP/B-W/AP/RCS/PRED/09/T.P.GUDUR/00

Road from7/2 M.C Road to Venkannapalem Pattuapalem

17.05.201116.8.20113Months: EarthWork, Pipe

16.11.2011 6Months: WBMGr-II, Gr-II

16.2.2012 9Months: BT,CC Pavement

OGPC+ SCcompleted

completed

Page 36: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 36/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5 Culverts, GSB Shoulders andCC Pavement

and RoadFurniture

NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

Road Connecting R&B Roadthrough Voturu Village in SPSR 

Nellore District.21.09.2011

20.1.2012 4Months: Earth

Work, PipeCulverts,

GSB

20.5.2012 4Months: WBMGr-II, Gr-II ,

Shoulders andCC Pavement

20.9.2012 4Months: BT,CC Pavement

and RoadFurniture

GSB. From

0.00 to5.320(Bits),WBM Gr-II,Gr-III from0.00 to 5.320and OGPC+SC0/6 to 5/1 iscompleted

completed

NCRMP/B-W/AP/RCS/PRED/

09/KAVALI/007

Road from Kotha satram R&Bto Indrsanagar (via)

Thumalapenta palam,Patharavadu palam, Ramudupalam, Karaduvari palam & 

Sreeramapuram

29.08.2011

28.12.20114Months: Earth

Work, PipeCulverts, GSB

28.4.2012 4Months: WBM

GrII,GrII ,

Shoulders andCC Pavement

28.8.2012 4Months: BT,CC Pavement

and RoadFurniture

OGPC+ SCcompleted

99%

NCRMP/B-W/AP/PRED/09/D. V.SATRAM/RCS/0

08

Road from R&B road toSullurpeta Mallam to

Berijengalapalli cyclone shelter09.05.2011

8.8.2011 3Months:Earth Work, PipeCulverts, GSB

8.11.2011 6Months: WBMGrII, GrIIShoulders andCC Pavement

8.2.2012 9Months: BT,CC Pavementand RoadFurniture

OGPC+ SCcompleted

98%

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT road toPedapannamgadu in Tada

Mandal

14.09.2012

14.02.2013(5Months) EarthWork, PipeCulverts, GSB & 

CC road

13.06.2013 (4Months): WBMGrII, GrII

Shoulders

13.09.2013Months) BTand Road

Furniture

GSB work is inprogress

59%

Road from @ 56/8 to C.K roadto Periyavettu kuppam cycloneshelter

14.02.2013(5Months) EarthWork, PipeCulverts, GSB & CC road

13.06.2013 (4Months): WBMGrII, GrIIShoulders

13.09.2012Months) BTand RoadFurniture

work is notstarted

5.88%

Page 37: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 37/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

LIST OF NCR'S PENDING FOR NCRMP WORKS TO THE END OF DECEMBER 2012

Sl.No

Distric

t

sl.no

Date of Inspecti

on

Name of Work/Package No. Observation Remarks Status

1

     V     I     Z     I     N     A     G     A     R     A     M

1

06.04.12

Construction of Minor Bridge at Km15/2 near Chakaligadda of KonadaRamatheertham R&B road toKonathalapalem (via) Yerukonda,Pasupam, Kollayavalsa (ZP Road)NCRMP/B-W/AP/Br/R&B/02/Chakaligadda/008

Revetment, Apron stone samples arecollected and verified for size andweight. Some samples are notsatisfying the requirements of MORT& H Clause 2504.Required minimumweight is 40 kgs and minimum size is300 MM minimum.

NCR-2 Issued to takesuitable remedialaction beforeproceeding withfurther layers.

The Contractor toldthat the under sizestones will be removedand repacked withsuitable stones as peragreement. NCR Pending.

2 2

25.07.12

Construction of Minor Bridge at Km.7/2 near Puligedda of Konada –Ramatheertham R&B Road toKonathalapalem via Yerukonda,Pasupam, Kollayavalsa (Z.P. Road)NCRMP/B-W/AP/Br/R&B/02/Puligedda/007

Rain cuts and gullies are formed inshoulder portion. Shoulders aredisturbed at some places. The sameshall be rectified.

NCR-3 Issued to takesuitable remedialaction beforeproceeding withfurther work.

The Contractorintimated that thegullies will be rectifiedby filling, compactingand sectioning theslopes after thecompletion of Raineyseason. NCR Pending.

3

     G     U     N     T     U     R

1 30.10.12 Reconstruction of HLB @ km5/2 of Bapatla - Suryalanka road acrossperali drain in Guntur DtPackage No.: NCRMP/B-W/AP/Br/R&B/07/Bapatla/010.

Revetment thickness is varying from220 mm to 275 mm as against thespecified thickness 300 mm. rectifythe same before tacking up thegrouting.

NCR-13 Issued, R&BDepartment officers isrequest to takesuitable remedialaction beforepreceding the furtherwork.

NCR Pending

4

     P     R     A     K     A     S     A     M

1

01.09.12

Road from R&B road Pellur to Vasepallipadu. NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09

The sign boards which are providedin site are not semi reflective. Semireflective sign boards are to beprovided as per agreement.

NCR-27 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding withfurther work.

NCR Pending

Page 38: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 38/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5 2

11.10.12

Construction Thoupula Kanaparthycyclone shelter in Nagulappapadumandal Prakasam districtNCRMP/B-W/APMPCS/PRED/08/NG

Padu/003

1. Street light fittings are not of approved brand specified in theagreement.2. Exhaust fans (2no's) of 225mm

size are provided whereas theagreement specifies 300mm size.3. For ceiling fans & tube lightsceiling roses are not provided.

NCR-32 Issued, PR Department officersinform that suitableremedial action will be

taken beforeproceeding withfurther work.

NCR Pending

6 3

19.10.12

Construction of High level Bridge atKm 16/10 of Naguluppalapadu –Kanaparthi road in PrakasamDistrict NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012

Rain cuts & dip gullies are formed inthe bridge approaches. Shoulders aredisturbed at many places. The sameshall be rectified immediately.

NCR-33 Issued, R & BDepartment officersinform that suitableremedial action will betaken beforeproceeding withfurther work.

NCR Pending

7 4

21.11.12

Construction of High level Bridge atKm 16/10 of Naguluppalapadu –Kanaparthi road in PrakasamDistrict NCRMP/B-W/AP/Br/R&B/08/Kanaparthi/012

Grouted rough stone revetment work for quadrants is damaged, deepgullies are formed in the bridgeapproaches and shoulders aredisturbed at many places (NCR no-33). These damages shall be rectifiedimmediately and compliance reportfurnished.

NCR-34 Issued R & BDepartment officers isinform to take suitableremedial action beforeproceeding withfurther work.

NCR Pending

8 5

28.11.12

Road from Pakala R&B road toMosanaladinneNCRMP/BW/AP/RHB/PRED/08/S.Konda/002

WBM Grade-III layer is badlydisturbed in the stretch km 0/000 tokm 0/450 which is to be rectifiedimmediately and compliance

furnished.

NCR-35 Issued, P R Department officers isinforming to takesuitable remedial

action beforeproceeding withfurther work.

NCR Pending

9 6

28.11.12

Road from NH5 to MulaguntapaduNCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

WBM Grade-III layer is badly disturbedin the stretches from km 0/000 to km0/310 and from km 0/400 to km 0/600.The disturbed stretches are to berectified immediately and compliancefurnished.

NCR-36 Issued, P R Department officers isrequested to takesuitable remedial actionbefore proceeding withfurther work.

NCR Pending

Page 39: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 39/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

10

     N     E     L     L     O     R     E

1 18.07.12 Road from 1/6 of Zuvvaladinne R&BRoad to Tellagunta NCRMP/B-W/AP/RHB/PRED/ 09/BOGOLU/001

1. Non Reflective type sign boards areprovided. As per agreementspecifications all the sign boards shallbe semi reflective in nature. Suitableremedial action is to be taken up2. in KM 1/6, big hole is left inbetween road and sluice head wall. it isvery dangerous to the public.Immediate protective action she betaken to prevent accidents.

NCR-14 Issued, PR Department officersinform that suitableremedial action will be

taken beforeproceeding withfurther work.

NCR Pending

11 2 17.07.12 Road from R&B road to PatuvariKandriga NCRMP/B-W/AP/RHB/PRED/09/MUTHUKUR/006

Sump is constructed in the formationwidth of the road near slab culvertlocation in km 0/200. Proper safetymeasures shall be taken to avoidaccidents

NCR-28 Issued, PR Department officersinform that suitableremedial action will betaken before proceedingwith further work.

NCR Pending

12 3

17.08.12

Road from R&B Chittamur to SomaSamudram NCRMP/B-W/AP/RHB/PRED/09/CHITTAMURU/003

l)At Km 1.380(RHs),collection chamberhas to be covered with suitablemeasures to avoid accident.2.At Km 1.250(LHS)a deep ditch existat the BT edge where a water Bump islocated. It is hazardous to the roaduser and it shall be protected bysuitable arrangements

NCR-29 Issued, PR Department officersinform that suitableremedial action will betaken beforeproceeding withfurther work.

NCR Pending

13 4

17.08.12

Providing BT Surface to the Road tothe Road from R&B Road to EdagaliKandriga NCRMP/B-W/AP/RHB/PRED/09/Chalam/007

 At Km 0,010(RHs), uncovered waterpump chamber is located on theshoulder of the road. It has to becovered immediately

NCR-30 Issued, PR Department officersinform that suitableremedial action will betaken before proceedingwith further work.

NCR Pending

14 5

08.10.12

Road Connecting R&B Roadthrough Voturu Village in SPSR Nellore District. NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006

Road is badly damaged in somestretches from km 1/8 to km 2/6.Thorough rectification is to be done

NCR-31 Issued, PR Department officersinform that suitableremedial action will betaken before proceedingwith further work.

NCR Pending

Page 40: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 40/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

5.0 District wise status of tests conducted by TPQA:

 Apart from monitoring the tests being conducted by the implementation team (contractors & Line department) at various

stages, the Third party Quality Audit team also conducted tests to confirm its compliance with the standards. These tests are

carried out in the site itself and in some cases samples are collected and testing done in outside laboratories. The details of 

tests conducted in the field till end of December 2012 are presented.

Summary of QC Tests - Up to 31.12.2012

S.No. District

No. TestsConductedduring the

Month

Total no. of TestsCumulativeTests Done

Total no. of Tests

Passed Failed Passed Failed

1 Srikakulam 82 82 0 1475 1469 6

2 Vizianagaram 4 4 0 461 461 0

3 Visakhapatnam 106 106 0 2237 2191 46

4 East Godavari 54 54 0 1128 1128 0

5 West Godavari 0 0 0 349 349 0

6 Krishna 3 3 0 85 85 0

7 Guntur   23 23 0 606 595 11

8 Prakasam 6 6 0 1905 1901 4

Page 41: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 41/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.0 Details of Quality Control Audit Reports Submitted during this 3 months:

6.1 Details of Quality Control Audit Reports Submitted During this Month of October-2012:

Package Number Name of Work District

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter atBangarampeta in Nakkapalli Mandal

 Vishakhapatnam

NCRMP/B-W/AP/RCS/PRED/

07/Nizampatnam/003

Road from R&B Road to

GurunadhanagarGuntur

NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

From R&B Road to Yaramavaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/09/Kavali/006

Road Connecting R&B Road through Voturu Village in SPSR Nellore District

from km 0.00 to km 5.320Nellore

NCRMP/B-W/AP/MPCS/PRED/

03/Payakaraopeta/003

Construction of cyclone shelter at

Gajapathinagaram in Payakaraopeta

 Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter atRatnayampeta in Payakaraopeta

 Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002

Construction of cyclone shelter atMullaparra in Nakkapalli Mandal

 Vishakhapatnam

NCRMP/B-W/AP/MPCS/PRED/ Construction of cyclone shelter at Vishakhapatnam

Page 42: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 42/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.2 Details of Quality Control Audit Reports Submitted During this Month of November-2012:

Package Number Name of Work District

NCRMP/B-W/AP/MPCS/PRED/08/NGPadu/003

Construction of Cyclone shelter atThopupalem kanaparthy in

Nagulapapadu MandalPrakasam

NCRMP/B-W/AP/RHB/PRED/

08/S.Konda/002

Road from NH5 to Mulaguntapadu

village in Singarayakonda Mandal

Prakasam

NCRMP/B-W/AP/Br/R&B/07/Bapatla/011/2010

Reconstruction of HLB @ km 2/4 of Bapatla-Pandurangapuram road

across Perali drainGuntur

NCRMP/B-W/AP/RCS/PRED/06/Machilipatnam/001

Road from Bhogireddypalli R&B roadto Ramakhandam

Krishna

NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002

Road from R&B Road toChalivendradibba in Singarayakonda

mandalPrakasam

NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu/003

Road from R&B road to Cycloneshelter at Chandala

Krishna

NCRMP/B-W/AP/Br/R&B/Reconstruction of HLB @ km 5/2 of 

Page 43: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 43/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/B-W/AP/RHB/PRED/

05/MOGALTHURU/001

Road from NH 214 A road to

Harijanawada of kothota of Mogalthuru Mandal West Godavari

NCRMP/B-W/AP/RHB/PRED/05/MOGALTHURU/001

From Narsapur Mogaltur R&B road toDayadalspeta via Venkateshwara

Swamy Temple of Mogalthuru MandalWest Godavari

NCRMP/B-W/AP/RCS/PRED/

07/Nizampatnam/003

Road from R&B Road to

Gurunadhanagar Guntur

NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003

Road from R&B Road to Atlavaripalem in Nizampatnam Mandal

Guntur

NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.

Road from Ganapavaram R&B road toPedamarpuvaripalem

Guntur

NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002

Road from LB Cherla CC road toChillapalem of LB Cherla of Narsapur

MandalWest Godavari

NCRMP/B-W/AP/RHB/PRED/05/Narasapur/002

Road from R&B road to Pedalanka of Narsapur Mandal

West Godavari

Page 44: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 44/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6.3Details of Quality Control Audit Reports Submitted During this Month of October-2012:

Package Number Name of Work District

NCRMP/BW/AP/RHB/PRED/01/Polaki/005

Road from R&B road Edulavalasa -Killam roadto Jonnam via Talasamudram in Polaki

Mandal.Srikakulam

NCRMP/B-W/AP/RCS/PRED/09/TADA/009

Providing BT road to Peda Pannam Gadu inTada Mandal.

SPSR Nellore

NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.

Road from R&B Road toChinapuluguvaripalem.

Guntur

NCRMP/BW/AP/RCS/PRED/07/Karlapalem/002.

Road from Ganapavaram R&B road toPedamarpuvaripalem.

Guntur

NCRMP/BW/AP/RHD/PRED/01/Polaki/005

Road from R&B road Edulavalasa -Killam roadto Jonnam via Talasamudram in Polaki

Mandal.Srikakulam

NCRMP/BW/AP/RHB/PRED/09/Vidavalur/005

Road from R&B road Kancharapalem HW to Alaganipadu.

SPSR Nellore

NCRMP/B-W/AP/RCS/PRED/04/THONDANGI/004

Road from R&B Road to Danavaipeta. East Godavari

NCRMP/B-W/AP/RCS/PRED/04/THONDANGI/004

Road from R&B Road to Gaddipeta of Thondangi Mandal.

East Godavari

Page 45: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 45/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

NCRMP/BW/AP/RHB/PRED/01/Polaki/005

Road from R&B road Edulavalasa - Killam roadto Jonnam via Talasamudram in Polaki Mandal

Srikakulam

NCRMP/BW/AP/RHB/PRED/01/Polaki/005

Road from Talasamudram to Dola regulator of Polaki Mandal

Srikakulam

NCRMP/B-W/AP/RCS/PRED/08/VETAPALEM/001

Road from R&B Road to Vijayanagar colonycyclone shelter In Prakasam District

Prakasam

NCRMP/BW/AP/BR/R&B/01/Patnavanipeta/001

Construction of HLB Act KM 11/6-8 of NH-5 to

Patnavanipeta Road Via Tamada connectingSundarapalem in Srikakulam District.

Srikakulam

NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Construction of Cyclone Shelter atPedaraghavulapeta in Uppalaguptam Mandal,

E.G.Dt.East Godavari

NCRMP/BW/AP/RCS/PRED/

07/Karlapalem/002.

Road from R&B Road to Chinapuluguvaripalem

in Guntur DT.

Guntur

NCRMP/B-W/AP/RCS/PRED/04/Uppalaguptam/003.

Road from R & B road to ChinaraghavulapetaCyclone Shelter in East Godavari District.

East Godavari

NCRMP/B-W/AP/MPCS/PRED/03/Rambilli/004

Construction of cyclone shelter at Venkayyapalem in Rambilli

 Visakhapatnam

Page 46: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 46/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.0 Details of Environmental and Social Reports Submitted During this 3 Months:

7.1 Details of Environmental and Social Reports Submitted During this Month of October 2012:

Package Number Name of Work District

NCRMP/B-W/AP/Br/R&B/PRED/O7/Bapatla/010

Reconstruction of HLB @ Km.5/2 of Bapatla-Suryalanka road across

Guntur

NCRMP/B-W/AP/Br/R&B/PRED/O7/Bapatla/011

Reconstruction of HLB @ Km.2/4 of Bapatla-Pandurangapuram road

across Perali DrainGuntur

NCRMP/B-W/AP/RCS/PRED/O7/Bapatla/004

Road from R&B Road to Adarsh nagar Guntur

NCRMP/B-W/AP/RCS/PRED/

O7/Bapatla/004

Road from R&B Road to

HanumathanagarGuntur

NCRMP/B-W/AP/RCS/PRED/O7/Nizampatnam/003

Road from R&B Road to Atlavaripalem Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Nizampatnam/003

Road from R&B Road toGurunadhanagar

Guntur

Page 47: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 47/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.2 Details of Environmental and Social Reports Submitted During this Month of November 2012:

Package Number Name of Work District

NCRMP/B-W/AP/Br/R&B/PRED/O7/Bapatla/010

Reconstruction of HLB @ Km.5/2 of Bapatla-Suryalanka road across Perali Drain

Guntur

NCRMP/B-W/AP/Br/R&B/PRED/O7/Bapatla/011

Reconstruction of HLB @ Km.2/4 of Bapatla-Pandurangapuram road across Perali Drain

Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

Road from R&B Road to Pedagollapalem Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

Road from Pedagollapalem P.R. Road toBonthagoralapalem

Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Nizampatnam/003

Road from R&B Road to Gurunadhanagar Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

Road from Ganapavaram R&B Road to Kesavapuri STColony

Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

Road from Ganapavaram R&B Road toPedamarpuvaripalem

Guntur

NCRMP/B-W/AP/RCS/PRED/O7/Karlapalem/002

Road from R&B Road to Chinapuluguvaripalem Guntur

Page 48: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 48/259

QUARTERLY SUMMARY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7.3 Details of Environmental and Social Reports Submitted During this Month of December 2012:

Package Number Name of Work District

NCRMP/B-W/AP/RHB/PRED/01/Polaki/005

Road from R&B Road Edulavalasa Killam toJonnam via Talasamudram

Srikakulam

NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

Road from R&B Road Mobagam toDubbakavanipeta via Gajapathinagaram

Srikakulam

NCRMP/B-W/AP/RHB/PRED/01/Polaki/006

Road from Talasamudram to Dola Regulator Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone Shelter at Kollipadu Srikakulam

NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone Shelter at Runku Srikakulam

NCRMP/B-W/AP/MPCS/PRED/04/Uppalaguptam/002

Construction of Cyclone Shelter atPedaraghavulapeta

EastGodavari

QUARTERLY REPORT

Page 49: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 49/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.0 Consolidated E&S Reports during this 3 Months:

8.1 Consolidated E&S Report for Guntur District in the Month of October 2012:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Guntur in October,2012)

S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

COMPLICEDNOT

APPLICABLETOTAL

1Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement the

provisions laid out in the EMP

7 7

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

· Consent for establishment and operation of plant (for concretework) from SPCB.

7 7

· PUC certification for all vehicles/equipment used for/duringconstruction.

7 7

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for materials like sand and earth.

7 7

· Permission for water extraction, if applicable in the local areacontext.

7 7

The Contractor shall abide by all conditions laid out in the saidclearances.

7 7

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents of landowners(individual/panchayat/govt. agency) for temporary use of landfor all construction related activities including:

QUARTERLY REPORT

Page 50: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 50/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

a) Setting-up and operation of construction camp including labour camps, stock yards etc.

7 7

b) borrow areas and 7 7

c) Disposal of debris and other waste material. 7 7

4 Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities of local inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

7 7

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

7 7

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

7 7

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space for cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

7 7

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

7 7

d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

7 7

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

7 7

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

7 7

b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

7 7

QUARTERLY REPORT

Page 51: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 51/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) The Contractor shall strip, store and preserve top soil from the site of construction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after theconstruction is over.

7 7

6Protection of Properties andResources

The Contractor shall take due care to protect and prevent damages to

the following resources during preparatory and construction work:a) Water supply lines 7 7

b) Irrigation canals 7 7

c) Cart, cattle and/or foot trail/tracks 7 7

d) Cultural properties and sites/structures of religious importance 7 7

e) Houses, Farmlands, Orchids and/or Trees. 7 7

f) School and other existing buildings adjacent to the site of construction.

7 7

In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

7 7

7QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

7

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor following the stipulations given below: The finalization of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractor shall enter into a formal agreement with landowner.

7 7

b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

7 7

c) Identification and Selection:

1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

7 7

2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

7 7

QUARTERLY REPORT

Page 52: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 52/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

7 7

4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centers.

7 7

5. No borrow area shall be opened with in 500mts. from a reserved or 

protected forest area, protected sites, wildlife movement zone andcultural heritage site.

7 7

6. No tree cutting shall be undertaken. 7 7

7. Borrow area near any surface water body will be at least 100mts.away.

7 7

d) Operation 7

1. Area up to which material will be extracted shall be cleareddemarcated on ground.

7 7

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 7 7

3. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level.

7 7

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

7 7

e) Rehabilitation of Borrow Areas:

1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

7 7

2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

7 7

9

Water Extraction

/Use

Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) the

individual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

7 1

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety of road users and local people, particularly in the internal village roadswhich will be used for transporting materials.

7 1

QUARTERLY REPORT

Page 53: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 53/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

7 1

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorized entry into the

construction.

7 1

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

7 1

b) All methods steps and measures are required for ensuring safety of workers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

7 1

c) Material safety data sheet record of fuel and other inflammable

chemicals shall be maintained at the site. 7 1

12 Air pollut ion a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and fine materialstorage stock yards

7 1

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

7 1

c) All plants and equipment shall comply with pollution control norms. 7 1

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

7 1

13 Water Pollution

a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to water bodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

7 1

b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

7 1

QUARTERLY REPORT

Page 54: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 54/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

1

b) Ear plugs shall be provided to the labour facing risk from high

noise pollution such as plant site and those working near generators,heavy equipment /machinery.

7 1

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimize noise during construction work and operationof camp.

7 1

15Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

7 1

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and water bodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protected

natural habitats.

7 1

16Restoration andRehabilitation of Sites

 All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

7 1

Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations used for material sourcing.

7 1

17 Liabilities

 Any liability arising out of Contractor’s agreement with landowners/ local

people/gram Panchayat (including those related to temporary use of land, water extraction and disposal of debris) shall be settled by theContractor.

7 1

QUARTERLY REPORT

Page 55: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 55/259

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.2 Consolidated E&S Report for East Godavari District in the Month of October 2012:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof East Godavari in October,2012)

S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

COMPLICEDNOT

APPLICABLETOTAL

1Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

4 4

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

· Consent for establishment and operation of plant (for concretework) from SPCB.

4 4

· PUC certification for all vehicles/equipment used for/duringconstruction.

4 4

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for materials like sand and earth.

4 4

· Permission for water extraction, if applicable in the local area

context.4 4

The Contractor shall abide by all conditions laid out in the saidclearances.

4 4

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents of landowners(individual/Panchayat/govt. agency) for temporary use of land for all construction related activities including:

a) Setting-up and operation of construction camp including labour camps, stock yards etc.

4 4

QUARTERLY REPORT

Page 56: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 56/259

Q

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) borrow areas and 4

c) Disposal of debris and other waste material. 4

4Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities of local inhabitants, particularly those of schools and health facilities.

Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

4 4

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

4 4

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

4 4

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of 

Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space for cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

4 4

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

4 4

d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

4 4

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

4 4

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

4 4

b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

4 4

c) The Contractor shall strip, store and preserve top soil from the site of construction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after the

4 4

QUARTERLY REPORT

Page 57: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 57/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

construction is over.

6Protection of Properties andResources

The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:

a) Water supply lines 4 4

b) Irrigation canals 1 3 4

c) Cart, cattle and/or foot trail/tracks 4 4

d) Cultural properties and sites/structures of religious importance 4 4

e) Houses, Farmlands, Orchids and/or Trees. 2 2 4

f) School and other existing buildings adjacent to the site of construction.

1 3 4

In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

4 4

7 QuarryOperations

The Contractor shall procure material from quarries that have been

approved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

4 4

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor following the stipulations given below: The finalization of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractor shall enter into a formal agreement with landowner.

4 4

b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

4 4

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

4 4

2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

4 4

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

4 4

QUARTERLY REPORT

Page 58: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 58/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centers.

4 4

5. No borrow area shall be opened with in 500mts. from a reserved or protected forest area, protected sites, wildlife movement zone andcultural heritage site.

4 4

6. No tree cutting shall be undertaken. 4 47. Borrow area near any surface water body will be at least 100mts.away.

4 4

d) Operation

1. Area up to which material will be extracted shall be cleareddemarcated on ground.

4 4

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 4 4

3. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level.

4 4

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

4

e) Rehabilitation of Borrow Areas:

1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

4 4

2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

4 4

9Water Extraction/Use

Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) theindividual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

4 4

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety of road users and local people, particularly in the internal village roadswhich will be used for transporting materials.

4 4

b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

4 4

QUARTERLY REPORT

Page 59: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 59/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorized entry into theconstruction.

4 4

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision andenforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

4 4

b) All methods steps and measures are required for ensuring safety of workers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

4 4

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site.

4 4

12 Air pollut ion a) Wind barriers or screens shall be provided in the downwind

direction at air pollution causing sources like plant sites and fine materialstorage stock yards

4 4

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

4 4

c) All plants and equipment shall comply with pollution control norms. 4 4

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

4 4

13 Water Pollution

a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to water 

bodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

4 4

b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

2 2 4

QUARTERLY REPORT

Page 60: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 60/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

4

b) Ear plugs shall be provided to the labour facing risk from high

noise pollution such as plant site and those working near generators,heavy equipment /machinery.

4 4

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimize noise during construction work and operationof camp.

4 4

15Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

4 4

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and water bodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protected

natural habitats.

4 4

16Restoration andRehabilitation of Sites

 All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

4 4

Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations used for material sourcing.

4 4

17 Liabilities

 Any liability arising out of Contractor’s agreement with landowners/ local

people/gram Panchayat (including those related to temporary use of land, water extraction and disposal of debris) shall be settled by theContractor.

4 4

QUARTERLY REPORT

Page 61: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 61/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.3 Consolidated E&S Report for Prakasam District in the Month of October 2012:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads toCyclone Shelters & Habitations, Bridges and Culverts under NCRMP (Detailsof Prakasam in October,2012)

S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

COMPLICEDNOT

APPLICABLETOTAL

1Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

1 1

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

· Consent for establishment and operation of plant (for concretework) from SPCB.

1 1

· PUC certification for all vehicles/equipment used for/duringconstruction.

1 1

· Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operations for materials like sand and earth.

1 1

· Permission for water extraction, if applicable in the local area

context.1 1

The Contractor shall abide by all conditions laid out in the saidclearances.

1 1

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents of landowners(individual/Panchayat/govt. agency) for temporary use of land for all construction related activities including:

a) Setting-up and operation of construction camp including labour camps, stock yards etc.

1 1

QUARTERLY REPORT

Page 62: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 62/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) borrow areas and 1 1

c) Disposal of debris and other waste material. 1 1

4Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities of local inhabitants, particularly those of schools and health facilities.

Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

1 1

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

1 1

c) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

1 1

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisions of 

Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional space for cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

1 1

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

1 1

d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

1 1

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

1 1

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are obtainedprior to cutting of such trees.

1 1

b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

1 1

c) The Contractor shall strip, store and preserve top soil from the site of construction work and in the stock yards prior to stacking of materials.The top soil shall be reinstated in the cyclone shelter compound after the

1 1

QUARTERLY REPORT

Page 63: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 63/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

construction is over.

6Protection of Properties andResources

The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:

a) Water supply lines 1 1

b) Irrigation canals 1 1

c) Cart, cattle and/or foot trail/tracks 1 1

d) Cultural properties and sites/structures of religious importance 1 1

e) Houses, Farmlands, Orchids and/or Trees. 1 1

f) School and other existing buildings adjacent to the site of construction.

1 1

In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

1 1

7QuarryOperations

The Contractor shall procure material from quarries that have been

approved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

1

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractor following the stipulations given below: The finalization of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verification tocross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractor shall enter into a formal agreement with landowner.

1 1

b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protected areas.

1 1

c) Identification and Selection:1. The borrow area should not be located in agriculture field’s/ unlessunavoidable i.e. barren land is not available. In case borrowing needs tobe done on an agricultural land, top-soil stripping, stacking andpreservation is must.

1 1

2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

1 1

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

1 1

QUARTERLY REPORT

Page 64: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 64/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centers.

1 1

5. No borrow area shall be opened with in 500mts. from a reserved or protected forest area, protected sites, wildlife movement zone andcultural heritage site.

1 1

6. No tree cutting shall be undertaken. 1 17. Borrow area near any surface water body will be at least 100mts.away.

1 1

d) Operation 1

1. Area up to which material will be extracted shall be cleareddemarcated on ground.

1 1

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 1 1

3. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level.

1 1

4. Slope at the edges will be maintained not steeper than 2:3 (Vertical: Horizontal)

1

e) Rehabilitation of Borrow Areas:

1. Rehabilitation shall be satisfactory undertaken immediately after theuse has ceased and at least three weeks prior to monsoon

1 1

2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

1 1

9Water Extraction/Use

Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) theindividual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

1 1

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning signage,speed breakers etc.) shall be made by the contractor to ensure safety of road users and local people, particularly in the internal village roadswhich will be used for transporting materials.

1 1

b) Material shall be covered during transportation to prevent spillage,accidents and pollution.

1 1

QUARTERLY REPORT

Page 65: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 65/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) All required measures to ensure safety of local residents includingchildren and other near-by residents shall be taken up by the Contractor.This shall include provisions to prevent un authorized entry into theconstruction.

1 1

11 Worker’s Safety

a) All measures required for ensuring safety and health of the workersshall be taken up by the Contractor. This includes provision and

enforcement of appropriate personal protective equipment; first aidfacility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

1 1

b) All methods steps and measures are required for ensuring safety of workers, particularly those needed while undertaking work in or aroundexcavations; workings at height; and; while handling inflammable, toxicand/or hazardous materials shall be ensured by the contractor.

1 1

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site.

1 1

12 Air pollut ion a) Wind barriers or screens shall be provided in the downwind

direction at air pollution causing sources like plant sites and fine materialstorage stock yards

1 1

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

1 1

c) All plants and equipment shall comply with pollution control norms. 1 1

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

1 1

13 Water Pollution

a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts to water 

bodies (such as ponds, streams, canals and rivers), water sources (suchas hand pumps and wells) and adjacent farmland shall be undertaken bythe Contractor.

1 1

b) Storage of materials like fuel, chemicals, and cement shall be donein a manner (with impervious layer on bottom and a covered shed ontop) that does not contaminate land and ground/surface water.

1 1

QUARTERLY REPORT

Page 66: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 66/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 Noise Pollution

a) All noise causing activities shall be stopped during night time (9.00PM to 6.00 AM). The Contractor shall schedule construction works inconsultation with local Panchayat Authority and School Principal toensure least disturbance to school children and other adjacent residents.

1

b) Ear plugs shall be provided to the labour facing risk from high

noise pollution such as plant site and those working near generators,heavy equipment /machinery. 1 1

c) Appropriate noise controlling devices including acoustic generatorsshall be used to minimize noise during construction work and operationof camp.

1 1

15Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

1 1

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and water bodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protected

natural habitats.

1 1

16Restoration andRehabilitation of Sites

 All work sites and areas under temporary use (including construction andlabour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

1 1

Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposal of debris/construction wastes at pre-approved locations and; restoration of borrow areas and other sites/ locations used for material sourcing.

1 1

17 Liabilities

 Any liability arising out of Contractor’s agreement with landowners/ local

people/gram Panchayat (including those related to temporary use of land, water extraction and disposal of debris) shall be settled by theContractor.

1 1

QUARTERLY REPORT

Page 67: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 67/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

8.4 Consolidated E&S Report for Prakasam District in the Month of October 2012:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of Guntur inOctober,2012)

S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

COMPLICEDNOT

 APPLICABLETOTAL

1Work Plan forEMP

implementation

The Contractor’s Project Manager shall be responsible forimplementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timeline

about specific actions that will be taken by him to implement theprovisions laid out in the EMP

12 12

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

· Consent for establishment and operation of plant (for concretework) from SPCB.

12 12

· PUC certification for all vehicles/equipment used for/duringconstruction.

12 12

· Permission/consent of the District Administration/Mining

Department/other agencies for quarrying and/or borrowing operationsfor materials like sand and earth.

12 12

· Permission for water extraction, if applicable in the local areacontext.

12 12

The Contractor shall abide by all conditions laid out in the saidclearances.

12 12

QUARTERLY REPORT

Page 68: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 68/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3Consultation andCommunityConsent

The Contractor shall consult and obtain written consents of landowners(individual/Panchayat/govt. agency) for temporary use of land for all construction related activities including:

a) Setting-up and operation of construction camp including labourcamps, stock yards etc.

12 12

b) borrow areas and 12 12c) Disposal of debris and other waste material. 12 12

4Construction/Labour Camp

a) Location: The camp and plant site/s location and establishmentshall be done in a manner that does not interfere or disturb theactivities of local inhabitants, particularly those of schools and healthfacilities. Written permission (no objection certificate) shall be takenfrom the Gramsabha and the land owner prior to location selection anda copy shall be submitted to the Engineer approval.

12 12

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

12 12

c) A distance of at least 500mts. Shall be maintained from

designated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

12 12

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisionsof Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional spacefor cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

12 12

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

12 12

d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

12 12

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

12 12

5 Site Clearancea) NO tree cutting is to carried out without the written instructionfrom the Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are

12 12

QUARTERLY REPORT

Page 69: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 69/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

obtained prior to cutting of such trees.

b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

12 12

c) The Contractor shall strip, store and preserve top soil from the siteof construction work and in the stock yards prior to stacking of materials. The top soil shall be reinstated in the cyclone sheltercompound after the construction is over.

12 12

6Protection of Properties andResources

The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:

a) Water supply lines 12 12

b) Irrigation canals 1 11 12

c) Cart, cattle and/or foot trail/tracks 12 12

d) Cultural properties and sites/structures of religious importance 12 12

e) Houses, Farmlands, Orchids and/or Trees. 11 1 12f) School and other existing buildings adjacent to the site of construction.

12 12

In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

12 12

7QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

12

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer on

technical and environmental grounds. This includes on-site verificationto cross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

12 12

b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protectedareas.

12 12

c) Identification and Selection:

QUARTERLY REPORT

Page 70: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 70/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

1. The borrow area should not be located in agriculture field’s/unless unavoidable i.e. barren land is not available. In case borrowingneeds to be done on an agricultural land, top-soil stripping, stackingand preservation is must.

12 12

2. Borrow pits shall not be located within a distance of 100mts.

From any NH, SH or other roads.

12 12

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

12 12

4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

12 12

5. No borrow area shall be opened with in 500mts. from a reservedor protected forest area, protected sites, wildlife movement zone andcultural heritage site.

12 12

6. No tree cutting shall be undertaken. 1 12

7. Borrow area near any surface water body will be at least 100mts.away.

1 12

d) Operation 121. Area up to which material will be extracted shall be cleareddemarcated on ground.

12 12

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 12 12

3. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level.

12 12

4. Slope at the edges will be maintained not steeper than 2:3(Vertical : Horizontal)

12

e) Rehabilitation of Borrow Areas:

1. Rehabilitation shall be satisfactory undertaken immediately after

the use has ceased and at least three weeks prior to monsoon

12 12

2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

12 12

QUARTERLY REPORT

Page 71: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 71/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9Water Extraction /Use

Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) theindividual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

12 12

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warningsignage, speed breakers etc.) shall be made by the contractor toensure safety of road users and local people, particularly in the internal

village roads which will be used for transporting materials.

12 12

b) Material shall be covered during transportation to preventspillage, accidents and pollution.

12 12

c) All required measures to ensure safety of local residentsincluding children and other near-by residents shall be taken up by theContractor. This shall include provisions to prevent un authorised entryinto the construction.

12 12

11 Worker’s Safety

a) All measures required for ensuring safety and health of the

workers shall be taken up by the Contractor. This includes provisionand enforcement of appropriate personal protective equipment; firstaid facility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

12 12

b) All methods steps and measures are required for ensuring safetyof workers, particularly those needed while undertaking work in oraround excavations; workings at height; and; while handlinginflammable, toxic and/or hazardous materials shall be ensured by thecontractor.

12 12

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 12 12

12 Air pollution a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and finematerial storage stock yards

12 12

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

12 12

QUARTERLY REPORT

Page 72: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 72/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) All plants and equipment shall comply with pollution controlnorms.

12 12

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

12 12

13 Water Pollution

a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts towater bodies (such as ponds, streams, canals and rivers), watersources (such as hand pumps and wells) and adjacent farmland shallbe undertaken by the Contractor.

12 12

b) Storage of materials like fuel, chemicals, and cement shall bedone in a manner (with impervious layer on bottom and a coveredshed on top) that does not contaminate land and ground/surfacewater.

12 12

14 Noise Pollution

a) All noise causing activities shall be stopped during night time(9.00 PM to 6.00 AM). The Contractor shall schedule constructionworks in consultation with local Panchayat Authority and School

Principal to ensure least disturbance to school children and otheradjacent residents.

12 12

b) Ear plugs shall be provided to the labour facing risk from highnoise pollution such as plant site and those working near generators,heavy equipment /machinery.

12 12

c) Appropriate noise controlling devices including acousticgenerators shall be used to minimise noise during construction work and operation of camp.

12 12

15 Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

12 12

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protectednatural habitats.

12 12

QUARTERLY REPORT

Page 73: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 73/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

16Restoration andRehabilitation of Sites

 All work sites and areas under temporary use (including constructionand labour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

12 12

Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposalof debris/construction wastes at pre-approved locations and;restoration of borrow areas and other sites/ locations used for materialsourcing.

12 12

17 Liabilities

 Any liability arising out of Contractor’s agreement with landowners/local people/gram Panchayat (including those related to temporary useof land, water extraction and disposal of debris) shall be settled by theContractor.

12 12

9.5 Consolidated E&S Report for Srikakulam & East Godavari Districts in the Month of December 2012:

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of Srikakulamin December,2012)

S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

COMPLICED

NOT

 APPLICABLE

TOTAL

1Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

5 5

QUARTERLY REPORT

Page 74: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 74/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

Consent for establishment and operation of plant (for concrete work)from SPCB.

5 5

PUC certification for all vehicles/equipment used for/duringconstruction.

5 5

Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operationsfor materials like sand and earth.

5 5

Permission for water extraction, if applicable in the local area context. 5 5

The Contractor shall abide by all conditions laid out in the saidclearances.

5 5

3Consultationand CommunityConsent

The Contractor shall consult and obtain written consents of landowners(individual/Panchayat/govt. agency) for temporary use of land for all construction related activities including:

a) Setting-up and operation of construction camp including labour camps, stock yards etc.

5 5

b) borrow areas and 5 5

c) Disposal of debris and other waste material. 5 5

4Construction/

Labour Camp

a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities of local inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

5 5

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds. 5 5

a) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

5 5

QUARTERLY REPORT

Page 75: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 75/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisionsof Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional spacefor cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

5 5

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

5 5

d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

5 5

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall beprovided by the contractor.

5 5

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) are

obtained prior to cutting of such trees.

5 5

b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

5 5

c) The Contractor shall strip, store and preserve top soil from the siteof construction work and in the stock yards prior to stacking of materials. The top soil shall be reinstated in the cyclone shelter compound after the construction is over.

5 5

6Protection of Properties andResources

The Contractor shall take due care to protect and prevent damages tothe following resources during preparatory and construction work:

a) Water supply lines 5 5

b) Irrigation canals 5 5

c) Cart, cattle and/or foot trail/tracks 5 5

d) Cultural properties and sites/structures of religious importance 5 5

e) Houses, Farmlands, Orchids and/or Trees. 5 5

f) School and other existing buildings adjacent to the site of construction.

5 5

In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

5 5

QUARTERLY REPORT

Page 76: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 76/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

7QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

5

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all such

locations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verificationto cross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

5 5

b) The Contractor shall not procure any kind of construction material(such as aggregates, sand and earth) from ecologically protectedareas.

5 5

c) Identification and Selection:

1. The borrow area should not be located in agriculture field’s/unless unavoidable i.e. barren land is not available. In case borrowingneeds to be done on an agricultural land, top-soil stripping, stackingand preservation is must.

5 5

2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

5 5

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

5 5

4. No borrow pits shall be located within 500mts. from schools,colleges, playgrounds, religious structures and health centres.

5 5

5. No borrow area shall be opened with in 500mts. from a reservedor protected forest area, protected sites, wildlife movement zone andcultural heritage site.

5 5

6. No tree cutting shall be undertaken.5 5

7. Borrow area near any surface water body will be at least 100mts.away.

5 5

d) Operation 5

1. Area up to which material will be extracted shall be cleareddemarcated on ground.

5 5

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 5 5

QUARTERLY REPORT

Page 77: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 77/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

3. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level.

5 5

4. Slope at the edges will be maintained not steeper than 2:3(Vertical : Horizontal)

5 5

e) Rehabilitation of Borrow Areas:

1. Rehabilitation shall be satisfactory undertaken immediately afterthe use has ceased and at least three weeks prior to monsoon

5 5

2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

5 5

9Water Extraction /Use

Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) theindividual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

5 5

10Safety of RoadUsers and LocalResidents

a) Traffic safety arrangements (including provision of warning

signage, speed breakers etc.) shall be made by the contractor toensure safety of road users and local people, particularly in the internalvillage roads which will be used for transporting materials.

5 5

b) Material shall be covered during transportation to preventspillage, accidents and pollution.

5 5

c) All required measures to ensure safety of local residentsincluding children and other near-by residents shall be taken up by theContractor. This shall include provisions to prevent un authorised entryinto the construction.

5 5

11 Worker’s Safety

a) All measures required for ensuring safety and health of theworkers shall be taken up by the Contractor. This includes provision

and enforcement of appropriate personal protective equipment; firstaid facility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

5 5

QUARTERLY REPORT

Page 78: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 78/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) All methods steps and measures are required for ensuring safetyof workers, particularly those needed while undertaking work in oraround excavations; workings at height; and; while handlinginflammable, toxic and/or hazardous materials shall be ensured by thecontractor.

5 5

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site. 5 5

12 Air pollution a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and finematerial storage stock yards

5 5

b) Fugitive dust emissions have to be eliminated by providing dustsuppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

5 5

c) All plants and equipment shall comply with pollution controlnorms.

5 5

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100m

before the settlement)

5 5

13 Water Pollution

a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts towater bodies (such as ponds, streams, canals and rivers), watersources (such as hand pumps and wells) and adjacent farmland shallbe undertaken by the Contractor.

5 5

b) Storage of materials like fuel, chemicals, and cement shall bedone in a manner (with impervious layer on bottom and a coveredshed on top) that does not contaminate land and ground/surfacewater.

5 5

14 Noise Pollution

a) All noise causing activities shall be stopped during night time

(9.00 PM to 6.00 AM). The Contractor shall schedule constructionworks in consultation with local Panchayat Authority and SchoolPrincipal to ensure least disturbance to school children and otheradjacent residents.

5 5

b) Ear plugs shall be provided to the labour facing risk from highnoise pollution such as plant site and those working near generators,heavy equipment /machinery.

5 5

QUARTERLY REPORT

Page 79: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 79/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) Appropriate noise controlling devices including acousticgenerators shall be used to minimise noise during construction work and operation of camp.

5 5

15Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

5 5

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protectednatural habitats.

5 5

16Restoration andRehabilitation of 

Sites

 All work sites and areas under temporary use (including constructionand labour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

5 5

Completion of work(as covered under clause 55.1 of GCC) will also

include completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposalof debris/construction wastes at pre-approved locations and;restoration of borrow areas and other sites/ locations used for materialsourcing.

5 5

17 Liabilities

 Any liability arising out of Contractor’s agreement with landowners/local people/gram Panchayat ( including those related to temporary useof land, water extraction and disposal of debris) shall be settled by theContractor.

5 5

QUARTERLY REPORT

Page 80: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 80/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Third Party Quality Audit for Construction of Cyclone Shelters, Roads to CycloneShelters & Habitations, Bridges and Culverts under NCRMP (Details of EastGodavari in December,2012)

S.No Activity Measures to be implemented by the contractor COMPLICEDNOT

COMPLICEDNOT

 APPLICABLETOTAL

1Work Plan for EMPimplementation

The Contractor’s Project Manager shall be responsible for implementation of EMP provisions and will coordinate the over-allimplementation of the said plan. Along with the Work Programme, theContractor shall submit a plan including method statement and timelineabout specific actions that will be taken by him to implement theprovisions laid out in the EMP

1 1

2RegulatoryPermissions andConsents

The Contractor shall obtain all requisite statutory clearances prior tocommencement of civil works, which includes obtainingpermission/consent for plants, water and extraction and borrow areasoperations. This includes:

1

Consent for establishment and operation of plant (for concrete work)from SPCB.

1 1

PUC certification for all vehicles/equipment used for/duringconstruction.

1 1

Permission/consent of the District Administration/MiningDepartment/other agencies for quarrying and/or borrowing operationsfor materials like sand and earth.

1 1

Permission for water extraction, if applicable in the local area context. 1 1

The Contractor shall abide by all conditions laid out in the said

clearances.

1 1

3Consultationand CommunityConsent

The Contractor shall consult and obtain written consents of landowners(individual/Panchayat/govt. agency) for temporary use of land for all construction related activities including:

a) Setting-up and operation of construction camp including labour camps, stock yards etc.

1 1

QUARTERLY REPORT

Page 81: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 81/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

b) borrow areas and 1 1

c) Disposal of debris and other waste material. 1 1

4Construction/Labour Camp

a) Location: The camp and plant site/s location and establishment shallbe done in a manner that does not interfere or disturb the activities of 

local inhabitants, particularly those of schools and health facilities.Written permission (no objection certificate) shall be taken from theGramsabha and the land owner prior to location selection and a copyshall be submitted to the Engineer approval.

1 1

b) Camp site shall not be located within 250mts. From a water bodyincluding village ponds.

1 1

a) A distance of at least 500mts. Shall be maintained fromdesignated/protected natural habitats (such as National Parks,Sanctuaries, Biosphere Reserves, Reserve Forests and Ramsar Sites)and Coastal Regulation Zone.

1 1

b) Accommodation and Basic Amenities: All weather shelter with therequired tenement size and toilets shall be provided, as per provisionsof Labour Laws. Separate toilet facilities shall be provided for womenworkers. If a common mess is not provided/operated additional spacefor cooking shall be provided. The contractor shall ensure that hygienicconditions are maintained during the operation of such camps/facilities.

1 1

c) Fuel for Cooking: The Contractor shall ensure that fuel wood is notused as a cooking medium in the construction /labour camp.

1 1

d) Potable water supply: Drinking water supply of at least 40Ipcd withthe required supply points shall be provided.

1 1

e) Fire Safety: Adequate fire safety precautions shall be taken andrequired fire safety equipment (such as fire extinguishers) shall be

provided by the contractor.

1 1

5 Site Clearance

a) NO tree cutting is to carried out without the written instruction fromthe Employer, who in turn will ensure that relevant regulatorypermission/s (including those from Forest Dept., if required) areobtained prior to cutting of such trees.

1 1

b) The non-timber grade trees are to be stacked and possession is tobe given to Employer/concerned Govt. Department.

1 1

QUARTERLY REPORT

Page 82: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 82/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

c) The Contractor shall strip, store and preserve top soil from the siteof construction work and in the stock yards prior to stacking of materials. The top soil shall be reinstated in the cyclone shelter compound after the construction is over.

1 1

6Protection of Properties andResources

The Contractor shall take due care to protect and prevent damages to

the following resources during preparatory and construction work:a) Water supply lines 1 1

b) Irrigation canals 1 1

c) Cart, cattle and/or foot trail/tracks 1 1

d) Cultural properties and sites/structures of religious importance 1 1

e) Houses, Farmlands, Orchids and/or Trees. 1 1

f) School and other existing buildings adjacent to the site of construction.

1 1

In case of damage due to construction activity, the restoration/repairsshall be carried out by the contractor at his own cost.

1 1

7QuarryOperations

The Contractor shall procure material from quarries that have beenapproved/licensed by the State Govt. A copy of such an approval shallbe submitted to the Engineer prior to procuring material.

1

8 Borrow Areas

a) Borrow areas for the project will be selected by the Contractorfollowing the stipulations given below: The finalisation of all suchlocations shall be dependent on the approval of the Engineer ontechnical and environmental grounds. This includes on-site verificationto cross-check the accuracy of details provided by the contractor. Onlyafter receipt of the written approval from the Engineer, the Contractorshall enter into a formal agreement with landowner.

1 1

b) The Contractor shall not procure any kind of construction material

(such as aggregates, sand and earth) from ecologically protectedareas.

1 1

c) Identification and Selection:

1. The borrow area should not be located in agriculture field’s/unless unavoidable i.e. barren land is not available. In case borrowingneeds to be done on an agricultural land, top-soil stripping, stackingand preservation is must.

1 1

QUARTERLY REPORT

Page 83: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 83/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

2. Borrow pits shall not be located within a distance of 100mts. Fromany NH, SH or other roads.

1 1

3. Borrow pits shall be preferably located 500mts. away fromsettlements/habitations.

1 1

4. No borrow pits shall be located within 500mts. from schools,

colleges, playgrounds, religious structures and health centres.

1 1

5. No borrow area shall be opened with in 500mts. from a reservedor protected forest area, protected sites, wildlife movement zone andcultural heritage site.

1 1

6. No tree cutting shall be undertaken. 1 1

7. Borrow area near any surface water body will be at least 100mts.away.

1 1

d) Operation 1

1. Area up to which material will be extracted shall be cleareddemarcated on ground.

1 1

2. A 15cm topsoil layer will be stripped and preserved in stockpiles. 1 1

3. Borrowing of earth should be preferably limited to a depth of 1.5mtr from the existing ground level.

1 1

4. Slope at the edges will be maintained not steeper than 2:3(Vertical : Horizontal)

1 1

e) Rehabilitation of Borrow Areas:

1. Rehabilitation shall be satisfactory undertaken immediately after

the use has ceased and at least three weeks prior to monsoon1 1

2. Preserved top soil has be spread uniformly over land (except incases where borrow area is developed as a water body) used as aborrow area.

1 1

9Water Extraction /Use

Water for construction and for use at construction camps (includinglabour camps) is to be extracted with prior written permission of(a) theindividual owner, in case the source is private well/tube well; (b) GramPanchayat in case the source belongs to community: and (c) IrrigationDepartment in case the source is an irrigation canal or river.

1 1

QUARTERLY REPORT

Page 84: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 84/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

10Safety of RoadUsers and Local

Residents

a) Traffic safety arrangements (including provision of warningsignage, speed breakers etc.) shall be made by the contractor toensure safety of road users and local people, particularly in the internalvillage roads which will be used for transporting materials.

1 1

b) Material shall be covered during transportation to prevent

spillage, accidents and pollution.

1 1

c) All required measures to ensure safety of local residentsincluding children and other near-by residents shall be taken up by theContractor. This shall include provisions to prevent un authorised entryinto the construction.

1 1

11 Worker’s Safety

a) All measures required for ensuring safety and health of theworkers shall be taken up by the Contractor. This includes provisionand enforcement of appropriate personal protective equipment; firstaid facility; emergency response arrangement; proper storage of hazardous/toxic and polluting materials and; measures for ensuring fireelectrical and mechanical safety arrangements in camp and in work site.

1 1

b) All methods steps and measures are required for ensuring safetyof workers, particularly those needed while undertaking work in oraround excavations; workings at height; and; while handlinginflammable, toxic and/or hazardous materials shall be ensured by thecontractor.

1 1

c) Material safety data sheet record of fuel and other inflammablechemicals shall be maintained at the site.

1 1

12 Air pollution a) Wind barriers or screens shall be provided in the downwinddirection at air pollution causing sources like plant sites and finematerial storage stock yards

1 1

b) Fugitive dust emissions have to be eliminated by providing dust

suppression/control measures, such as water sprinkling and cover onmaterials, based on activity and site conditions.

1 1

c) All plants and equipment shall comply with pollution controlnorms.

1 1

d) Water shall be sprinkled at least twice during dry day on haulageroads passing through or near settlements(including at least 100mbefore the settlement)

1 1

QUARTERLY REPORT

Page 85: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 85/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

13 Water Pollution

a) All measures (including provision of temporary silt fencing tocontrol sediment run-off) required for avoiding adverse impacts towater bodies (such as ponds, streams, canals and rivers), watersources (such as hand pumps and wells) and adjacent farmland shallbe undertaken by the Contractor.

1 1

b) Storage of materials like fuel, chemicals, and cement shall be

done in a manner (with impervious layer on bottom and a coveredshed on top) that does not contaminate land and ground/surfacewater.

1 1

14 Noise Pollution

a) All noise causing activities shall be stopped during night time(9.00 PM to 6.00 AM). The Contractor shall schedule constructionworks in consultation with local Panchayat Authority and SchoolPrincipal to ensure least disturbance to school children and otheradjacent residents.

1 1

b) Ear plugs shall be provided to the labour facing risk from highnoise pollution such as plant site and those working near generators,heavy equipment /machinery.

1 1

c) Appropriate noise controlling devices including acousticgenerators shall be used to minimise noise during construction work and operation of camp.

1 1

15Disposal Debris/wastes

a) Debris and other construction waste, if any, shall be disposed inlocations pre-approved by the Engineer in a manner that it does notcontaminate the environment.

1 1

b) Location of Debris Disposal Sites: Debris disposal sites shall belocated preferably away from farmlands, water sources and waterbodies. In no case, debris shall be disposed within 500mts. of ecologically sensitive areas, including forests, wetlands and protectednatural habitats.

1 1

16Restoration andRehabilitation of Sites

 All work sites and areas under temporary use (including constructionand labour camps, plant, sites, haul roads and borrow areas) shall berestored/rehabilitated to a better condition (if not at least to its originalcondition) and to the satisfaction of the Engineer and land owner uponcompletion of construction work by the Contractor.

1 1

QUARTERLY REPORT

Page 86: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 86/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Completion of work(as covered under clause 55.1 of GCC) will alsoinclude completion of rehabilitation and clean-up of the work sitesincluding camps, plants, in and around the construction site; disposalof debris/construction wastes at pre-approved locations and;restoration of borrow areas and other sites/ locations used for materialsourcing.

1 1

17 Liabilities

 Any liability arising out of Contractor’s agreement with landowners/local people/gram Panchayat ( including those related to temporary useof land, water extraction and disposal of debris) shall be settled by theContractor.

1 1

QUARTERLY REPORT

f f

Page 87: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 87/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9.0 Statement Showing the Inspections and Site Visits of Districts during this 3 Months:

9.1 Statement Showing the Inspections and Site Visits of Districts during the Month of October -2012

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH

OF OCTOBER 2012

SNO

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF VISIT

NO. OF VISITS

1NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

Road from Borubadra,Malagam road to Kollipadu via Seepuram,Ghantapeta in Santhabommali Mandal

5.10.12,18.10.12,

2

2NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Runku in Santhabommali Mandal.

05.10.12,10.10.12,16.10.12,18.10.12,27.10.12

5

3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Deppuru, Bahadapalli road to Onkuluru & cyclone shelter. 10.10.12 1

4 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005 Construction of Cyclone shelter at Kollipadu in SanthabommaliMandal.

05.10.12,09.10.12,

10.10.12,18.10.12,27.10.12

5

5 NCRMP/B_W/AP/Br/R&B/01/Bendigedda/004Construction of High level Bridge across Bendigedda at km 4/10 of Pundi-Parlkimidi road in Srikakulam Dist.

08.10.12,10.10.12,

2

QUARTERLY REPORT

C lt S i f Thi d P t Q lit A dit (TPQA) f N ti l C l Ri k Miti ti P j t (NCRMP)

Page 88: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 88/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6 NCRMP/B_W/AP/Br/R&B/01/Surampeta/003Construction of Minor Bridge at km 12/2-4 of NH-5 to Surampeta

road via Naruva&Mentada18.10.12 1

7 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 22.10.12 1

8 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006Road from Mabagam R&B road to Dubbakavanipeta viaGajapathinagaram.

22.10.12 1

9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005Road from R&B road Edullavalasa-Killam to jonnam viaTalasamudram

22.10.12 1

10NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003

Road from DPN road Uddandapalem10.10.12,18.10.12

2

11

NCRMP/B-

W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 10.10.12 1

12 NCRMP/B_W/BR/R&B/01/uppigedda/002Construction of HLB across Uppuguda at Km 7/6 of Srikakulam

municipal limits to Pukkalapeta09.10.12 1

13 NCRMP/B_W/AP/RCS/PRED/01/ETCHERLA/005 Road from Kotcherla road to Kollibhemavaram & cyclone shelter 12.10.12 1

14 NCRMP/B_W/AP/RCS/PRED/01/ETCHERLA/005 Road from Kotcherla road to Pathesundrapalem 12.10.12 1

15NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/00

1Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipetaconnecting Sundarapalem.

15.10.12,18.10.12

2

TOTAL 28

QUARTERLY REPORT

C lt S i f Thi d P t Q lit A dit (TPQA) f N ti l C l Ri k Miti ti P j t (NCRMP)

Page 89: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 89/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIJAYNAGARAM DISTRICT DURING THE

MONTH OF OCTOBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS

DURING THIS MONTHDATES OF

 VISITNO. OF

 VISITS

1NCRMP/B-W/ AP/ Br/ R&B/ 02/ Chakaligadda /008

Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&B road to Konathalapalem (via) Yerukonda, Pasupam, Kollayavalsa (ZP Road) in VizianagaramDistrict.

06.10.201211.10.201220.10.2012

3

2 NCRMP/B-W/ AP/ Br/ R&B/ 02/Puligedda/ 007Construction of Minor Bridge at Km. 7/2 near Puligedda of Konada –Ramatheertham R&B Road to Konathalapalem via Yerukonda,Pasupam, Kollayavalsa (Z.P. Road) in Vizianagaram District.

11.10.2012 1

3 NCRMP/B-W/ AP/ RD/ R&B/ 02/Konada/ 009

Improvements to Road from Konada Ramatheertham (R&B) Road toKonathalapalem (Via) Pasupam, Yerukonda, Kollayavalsa from Km12/0 to Km 16/5 (Km 0/0 to 4/0 i.e. up to NH-5 crossing ) in Vizianagaram District, Andhra Pradesh

11.10.2012 1

Total 5

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 90: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 90/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISHAKAPATNAM DISTRICT DURING THE

MONTH OF OCTOBER 2012

SNO

.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS

MONTH

DATES OF VISIT

NO. OF VISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem in Rambilli Mandal06.10.201231.10.2012

2

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal 16.10.2012 1

3NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Gajapathinagaram in PayakaraopetaMandal

04.10.201211.10.201216.10.201225.10.2012

4

4 NCRMP/B-W/AP/RHB/PRED/03/Anandapuram/003 R&B Road from B.P kallalu to Matchvanipalem 11.10.2012 1

NCRMP/B-W/AP/RCS/PRED/03/Anandapuram/001 B.T to the Road from NH-5 to Ramarayadupalem 11.10.2012 1

5 NCRMP/B-W/AP/RCS/PRED/03/Nakkapalli/003 Road from Upmaka Rajayyapeta R&B road to Janakayyapeta 11.10.2012 1

5 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Bangarampeta in Nakkapalli Mandal17.10.201219.10.2012

2

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 91: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 91/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

6NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Ratnayampeta in PayakaraopetaMandal

04.10.201211.10.2012

16.10.2012

3

7 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal

04.10.201216.10.201229.10.201231.10.2012

4

TOTAL 19

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 92: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 92/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EASTGODAVARI DISTRICT DURING THE

MONTH OF OCTOBER 2012

S NO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURING

THIS MONTH

DATES OF VISITNO. OF

 VISITS

1

NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

Cyclone Shelter at Avulamanda and of Thondangi Mandal,E.G.Dt.

12.10.2012,17.102012,25.10.2012,29.10.201231.10.2012

5

2Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal,E.G.Dt.

12.10.2012,17.10.2012,25.10.2012

29.10.2012

4

3NCRMP/B-W/ AP/RCS/

PRED/04/Uppalaguptam/003Road from R&B Road to Chinaraghavulapeta Cyclone Shelter

13.10.2012 & 19.10.2012

2

4NCRMP/B-W/ AP/MPCS/

PRED/04/Uppalaguptam/002Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt.

01.10.2012,06.102012,13.102012,19.10201230.102012

5

TOTAL 16

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 93: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 93/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURING THE

MONTH OF OCTOBER 2012

S NO. PACKAGE NO NAME OF WORK

TPQA INSPECTIONS DURING THIS

MONTH

DATES OF VISITSNO. OF

VISITS

1.

NCRMP/B-W/AP/RHB/

PRED/05/Mogalthuru/001

Road from NH 214 A at Ranga Statue center to Harijanawada of 

Kalipatnam (E) (Mogalthuru Mandal W.G.Dist.)09.10.2012 1

2.R&B road at Panchayat Office to Pulaparthivarithota via Badava

(Mogalthuru Mandal W.G.Dist.)09.10.2012 1

3. Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge toGogulamma Harijanapeta (Mogalthuru Mandal W.G.Dist.)

09.10.2012 1

4.From Narsapur Mogalthuru R&B road to Dayadaldaspeta via

Venkateswara Swamy temple (Mogalthuru Mandal W.G.Dist.)09.10.2012 1

5.Road from NH 214 A road to Harijanapeta of Kothota

(Mogalthuru Mandal W.G.Dist.)09.10.2012 1

6.

NCRMP/B-W/AP/RHB/

PRED/05/Narsapur/002

R&B Road to Indira nagar (via) Pochamma temple (Narsapur

Mandal W.G.Dist.)09.10.2012 1

7.Road from R&B road to Pedalanka (Narsapur Mandal

W.G.Dist.)09.10.2012 1

8.Road from LB Cheria CC road to Chillapalem of LB Cheria

(Narsapur Mandal W.G.Dist.)09.10.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 94: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 94/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

9.

NCRMP/B-W/AP/RHB/

PRED/05/Kalla/003

From A-U R&B Road to Satyanarayanapuram, (Kalla Mandal

W.G.Dist.)16.10.2012 1

10. From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.) 16.10.2012 1

Total 10

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 95: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 95/259

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING

THE MONTH OF OCTOBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURING THISMONTH

DATES OF VISITS NO. OF VISITS

1NCRMP/B-

W/AP/RHB/PRED/06/Machilipatnam/002

Road from Potalapalem Z.P road to Chikativanipalem 18.10.2012 1

2NCRMP/B-W/AP/RHB/PRED/

06/Machipatnam/001Road connecting R&B road through Gantlammapalem 19.10.2012 1

3NCRMP/B-W/AP/RCS/PRED/

06/Machipatnam/001Road from Potalapalem ZP road to Pothepalli 18.10.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 96: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 96/259

y y Q y ( Q ) y g j ( )

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING

THE MONTH OF OCTOBER 2012

S NO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURING

THIS MONTH

DATES OF VISITNO. OF

 VISITS

1 NCRMP/B-W/AP/RCS/PRED/07/Karlapalem/002

Road from Pedagollapalem PR. Road to Bonthagoralapalem. 30.10.2012 1

Road from Ganapavaram R&B Road to Pedamarpuvaripalem.19.10.2012,29.10.2012,30.10.2012,

3

Road from R&B road to chinapuluguvaripalem19.10.2012,29.10.2012,30.10.2012,

3

Road from R&B road to Pedagollapalem Cyclone Shelter.4.10.2012,30.10.2012

2

Road from R&B road toYaramvaripalem 30.10.2012 1

2NCRMP/B-

W/AP/RCS/PRED/07/Nizampatnam/003Road form R&B Road to Gurunadhanagar

9.10.2012,17.10.2012,30.10.2012

3

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 97: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 97/259

y y Q y ( Q ) y g j ( )

Road from R & B Road to Atlavaripalem9.10.2012,17.10.2012,30.10.2012

3

3 NCRMP/B-W/AP/RCS/PRED/07/Bapatla/003

Road from R & B Road to Adarsh nagar. 1.10.2012 1

Road from R & B Road to Hanumanth nagar. 1.10.2012 1

NCRMP/B-W/AP/RHB/PRED/07/Karlapalem/001Road from Ganapavaram R & B Road to Kesavapuri STColony.

30.10.2012 1

NCRMP/B-W/AP/RCS/PRED/07/Pv Palem/001 Road from R & B Road to Mandevaripalem 4.10.2012 1

5 NCRMP/B-W/AP/Br/R&B/07/Bapatla/010Reconstruction of HLB @ km 5/2 of Bapatla - Suryalanka

road across perali drain in Guntur District.1.10.2012,30.10.2012

2

6 NCRMP/B-W/AP/Br/R&B/07/Bapatla/011Reconstruction of HLB @ km 2/4 of Bapatla -

Pandurangapuram road across perali drain in Guntur District.1.10.2012 1

TOTAL 23

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 98: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 98/259

y y Q y ( Q ) y g j ( )

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASHAM DISTRICT

DURING THE MONTH OF OCTOBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS

DURING THIS MONTHDATES OF

 VISITNO. OF

 VISITS

1 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu 02.10.2012 1

2 NCRMP/B-W/APMPCS/PRED/08/NG Padu/004Kanaparthy cyclone shelter in Naguluppapadu Mandal Prakasamdistrict

10.10.201212.10.201219.10.201226.10.2012

31.10.2012

5

3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu 29.10.2012 1

4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 29.10.2012 1

5 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne02.10.201229.10.2012

2

6 NCRMP/B-W/AP/Br/R&B/08/ Kanaparthy/012Construction of High level Bridge at Km 16/10 of Naguluppapadu

 – Kanaparthy road in Prakasam District

12.10.201219.10.201231.10.2012

3

7 NCRMP/B-W/AP/RCS/PRED/08/Vetapalem/002 Road from NH Road to Challareddypalem 31.10.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 99: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 99/259

8 Phase-IIProviding BT Surface to the road from Pallepalem of Chakicharla inUlavapadu Mandal

10.10.2012 1

9 Phase-II Road from ZP road to Sriramapattapupalem in Ulavapadu Mandal 10.10.2012 1

10 Phase-II Road from MC Road to Veerapalli in Ulavapadu mandal. 10.10.2012 1

11 Phase-II Road from R&B Road to Kothapalem in Chirala Mandal 11.10.2012 1

12 Phase-IIConstruction of Cyclone shelter at Vodarevu of Chirala Mandal inPrakasam District.

11.10.2012 1

13 Phase-IIRoad from Vedullapalli-Vodarevu R&B Road to Cyclone Shelter at

 Vijaya Lakshmi Puram in Chirala Mandal11.10.2012 1

14 Phase-II Road from R&B road to Nayunipalli in Vetapalem 11.10.2012 1

15 Phase-II Road from R&B road to Sainagar in Vetapalem mandal 11.10.2012 1

16 Phase-IIRoad from Vutukuru Subbaiah Palem to Tenkayachetla Palem in Vetapalem mandal

11.10.2012 1

17 Phase-IIRoad from R & B Road to Motupalli Cyclone Shelter inChinaganjam Mandal.

11.10.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 100: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 100/259

18 Phase-IIRoad from Motupalli R & B Road to Nirikshanagiri (via)Rudramambapuram Cyclone Shelter in Chinaganjam Mandal.

11.10.2012 1

19 Phase-IIRoad from Motupalli R & B Road to Krishna Nagar in ChinaganjamMandal.

11.10.2012 1

20 Phase-IIRoad from Jeedichetlapalem R & B Road to Kunkuduchetlapalem inChinaganjam Mandal.

11.10.2012 1

Total 27

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 101: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 101/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT

DURING THE MONTH OF OCTOBER 2012

SLNO

Package Number Name of work  

TPQA INSPECTIONS DURING THIS

MONTH

DATES OF VISITSNO. OF

 VISITS

1 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005Road from KT R&B road to Allaganipadu to

vavilla08.10.2012 1

2 NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005Road from R&B road Kancharlapalam HW to

 Alaganipadu.08.10.2012 1

3 NCRMP/B-W/AP/RHB/PRED/09/V.CHALEM/007Road from Suvepalli-Pudiparthi road to Srikanth

Colony13.10.2012 1

4 NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/RHB/007providing BT Surface to the road from R&B road

to Edagali kandriga13.10.2012 1

5 NCRMP/B-W/AP/RCS/PRED/09/TADA/009Providing BT road to Peda Pannam Gadu in Tada

Mandal of Nellore Dt.18.10.2012 1

6 NCRMP/B-W/AP/RCS/PRED/09/KAVALI/006Road Connecting R&B Road through Voturu

 Village in SPSR Nellore District.08.10.2012,27.10.2012 2

7 NCRMP/B-W/AP/RCS/PRED/09/Muthukur/002Road from R&B Road Kappaladoruvu to

Bandlapalem H.wada in Muthukur mandal30.10.2012 1

8 NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006 Road from R&B road to Patuvarikandriga 30.10.2012 1

Total 9

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 102: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 102/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURING THE MONTH

OF NOVEMBER 2012

S

NO.PACKAGE NO NAME OF WORK

TPQA INSPECTIONS

DURING THIS MONTH

DATES OF

VISIT

NO. OF

VISITS

1 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005Construction of Cyclone shelter at Runku in SanthabommaliMandal.

07.11.12,14.11.12,17.11.12

3

2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Deppuru, Bahadapalli road to Onkuluru & cycloneshelter.

16.11.12 1

3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram06.11.12,16.11.12

2

4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komaralthada &Cyclonic shelter 16.11.12 1

5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 16.11.12 1

6 NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005Construction of Cyclone shelter at Kollipadu in SanthabommaliMandal.

17.11.12 1

7 NCRMP/B_W/AP/Br/R&B/01/Bendigedda/004Construction of High level Bridge across Bendigedda at km 4/10 of Pundi-Parlkimidi road in Srikakulam Dist.

15.11.12 1

8 NCRMP/B_W/AP/Br/R&B/01/Surampeta/003Construction of Minor Bridge at km 12/2-4 of NH-5 to Surampetaroad via Naruva & Mentada

05.11.12,21.11.12

2

9.2 Statement Showing the Inspections and Site Visits of Districts during the Month of November -2012

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 103: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 103/259

9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator 29.11.12 1

10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006Road from Mabagam R&B road to Dubbakavanipeta viaGajapathinagaram.

29.11.12 1

11 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005Road from R&B road Edullavalasa-Killam to jonnam viaTalasamudram

29.11.12 1

12 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from DPN road Uddandapalem 20.11.12 1

13 NCRMP/B-W/AP/RHB/PRED/01/Santhabommali/003 Road from K.Umilada to Koduru (Link road) 20.11.12 1

14 NCRMP/B_W/BR/R&B/01/uppigedda/002

Construction of HLB across uppigedda at Km 7/6 of Srikakulam

municipal limits to Pukkalapeta 20.11.12 1

15 NCRMP/B_W/AP/RCS/PRED/01/ETCHERLA/005 Road from Kotcherla road to Kollibhemavaram & cyclone shelter05.11.12,21.11.12

2

16 NCRMP/B_W/AP/RCS/PRED/01/ETCHERLA/005 Road from Kotcherla road to Pathesundrapalem05.11.12,21.11.12

2

17 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipeta

connecting Sundarapalem.

05.11.12,18.11.12,21.11.12,

28.11.12,29.11.12,30.11.12

6

TOTAL 28

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 104: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 104/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURING THE

MONTH OF NOVEMBER 2012

S

NO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURING

THIS MONTH

DATES OF VISITNO. OF

 VISITS

1NCRMP/B-W/ AP/ Br/ R&B/ 02/Chakaligadda /008

Construction of Minor Bridge at Km 15/2 near Chakaligadda of KonadaRamatheertham R&B road to Konathalapalem (via) Yerukonda,Pasupam, Kollayavalsa (ZP Road) in Vizianagaram District.

08.11.1219.11.1223.11.1224.11.1229.11.12

5

Total 5

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 105: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 105/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISHAKAPATNAM DISTRICT DURING THE

MONTH OF NOVEMBER 2012

S

NO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS

DURING THIS MONTHDATES OF

 VISITNO. OF

 VISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004Construction of cyclone shelter at Venkayyapalem in RambilliMandal

10.11.1220.11.12

2

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal11.11.1226.11.12

2

3NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal 28.11.12 1

4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone shelter at Bangarampeta in NakkapalliMandal

27.11.12 1

5NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Ratnayampeta in PayakaraopetaMandal

20.11.12 1

6 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal

10.11.1211.11.12

20.11.1226.11.12

4

TOTAL 11

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 106: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 106/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURING THE

MONTH OF NOVEMBER 2012

S NO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURING THIS

MONTH

DATES OF VISITNO. OF

 VISITS

1NCRMP/B-W/ AP/RCS/ PRED/04/

KARAPA/001ROAD FROM APPROACH ROAD TO CYCLONE SHELTER AT

 ADAVIPUDI IN E.G.Dt.Nil Nil

2NCRMP/B-W/ AP/RHB/ PRED/04/

KARAPA/001ROAD FROM GURAJANAPALLI TO BANDULAVARIPALEM Nil Nil

3NCRMP/B-W/AP/RHB/ PRED/04/

Katrenikona/003Road from PR road to Dasarivanipeta and to Cyclone

Shelter Nil Nil

4

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to G.Musalayyapeta CS Nil Nil

5 Road from R&B Road to P.Chodipallipeta CS05.11.2012, 14.11.2012,19.11.2012 & 29.11.2012

4

6 Road from R&B Road to K. Chodipallipeta CS05.11.2012, 14.11.2012,19.11.2012 & 29.11.2012

4

7 Road from R&B Road to Hukumpeta CS

05.11.2012, 14.11.2012,

19.11.2012, 22.112012 & 29.11.2012

5

8 Road from R&B Road to Gaddipeta CS05.11.2012, 14.11.2012,19.11.2012

& 29.11.20124

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 107: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 107/259

9 Road from R&B Road to Danavaipeta CS05.11.2012, 14.11.2012,19.11.2012 & 29.11.2012

4

10

NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

Cyclone Shelter at Avulamanda and of Thondangi Mandal,

E.G.Dt.

14.11.2012, 19.11.2012,

22.11.2012, & 29.11.2012

4

11Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal,E.G.Dt.

05.11.2012, 07.11.2012,14.11.2012, 19.11.2012,

22.11.2012, & 29.11.20126

12NCRMP/B-W/ AP/RCS/

PRED/04/Uppalaguptam/003Road from R&B Road to Chinaraghavulapeta Cyclone

ShelterNil Nil

13NCRMP/B-W/ AP/MPCS/

PRED/04/Uppalaguptam/002Cyclone Shelter at Pedaraghavulapeta of UppalaguptamMandal, E.G.Dt.

26.11.2012 1

TOTAL 32

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 108: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 108/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURING THE

MONTH OF NOVEMBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURINGTHIS MONTH

DATES OF

 VISITS

NO. OF

 VISITS

1.

NCRMP/B-W/AP/RHB/PRED/05/Mogalthuru/001

Road from NH 214 A at Ranga Statue centre to Harijanawada of Kalipatnam (E)(Mogalthuru Mandal W.G.Dist.)

05.11.2012 1

2.R&B road at Panchayat Office to Pulaparthivarithota via Badava (MogalthuruMandal W.G.Dist.)

05.11.2012 1

3.Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge to GogulammaHarijanapeta (Mogalthuru Mandal W.G.Dist.)

05.11.2012,22.11.2012

2

4.From Narsapur Mogalthuru R&B road to Dayadaldaspeta via Venkateswara Swamytemple (Mogalthuru Mandal W.G.Dist.)

05.11.2012 1

5.Road from NH 214 A road to Harijanapeta of Kothota (Mogalthuru MandalW.G.Dist.)

05.11.2012 1

6.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/002

R&B Road to Indira nagar (via) Pochamma temple (Narsapur Mandal W.G.Dist.) 22.11.2012 1

7. Road from R&B road to Pedalanka (Narsapur Mandal W.G.Dist.)15.11.2012,26.11.2012

2

8.Road from LB Cheria CC road to Chillapalem of LB Cheria (Narsapur MandalW.G.Dist.)

15.11.2012,26.11.2012

2

9.NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Satyanarayanapuram, (Kalla Mandal W.G.Dist.) 15.11.2012,26.11.2012

2

10. From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.) 0

Total 13

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 109: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 109/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE MONTH OF

NOVEMBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS

DURING THIS MONTHDATES OF VISITS

NO. OF VISITS

1 NCRMP/B-W/AP/RHB/PRED/06/Machilipatnam/002

Road from R&B road to Chikativanipalem 04.11.2012 1

Road from R&B road to B.V.Thota 05.11.2012 1

2 NCRMP/B-W/AP/RHB/PRED/ 06/Machipatnam/001 Road connecting R&B road through Gantlammapalem05.11.201221.11.2012

2

3NCRMP/B-W/AP/RHB/PRED/06/Kruthivennu(M)/003

Road from Intheru ZP road to Rangaraopet 05.11.2012 1

Road from R&B road to Cyclone shelter at Chandala05.11.201220.11.201221.11.2012

3

4 NCRMP/B-W/AP/RCS/PRED/ 06/Machipatnam/001

Road from Chinnapuram R&B road to Gundupalem02.11.201204.11.2012

2

Road from Potalapalem ZP road to Pothepalli04.11.201221.11.2012

2

Road from Bhogireddypalli R&B road to Ramakhandam02.11.201204.11.2012

2

Total 14

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 110: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 110/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THE MONTH OF

NOVEMBER 2012

S NO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURING THIS MONTH

DATES OF VISITNO. OF

 VISITS

1 NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002

Road from Ganapavaram R&BRoad to Pedamarpuvaripalem.

09.11.2012 14.11.201221.11.2012 22.11.2012

29.11.2012.5

Road from R&B road toChinapuluguvaripalem

09.11.2012 14.11.201221.11.2012 22.11.2012

29.11.20125

2 NCRMP/B-W/AP/RCS/PRED/07/Nizampatnam/003

Road form R&B Road to

Gurunadhanagar 14.11.2012 1

Road form R&B Road to Adavala H/o Bavajipalem

19.11.2012 1

Road from R & B Road to Atlavaripalem

14.11.2012 1

3 NCRMP/B-W/AP/RCS/PRED/07/Bapatla/003

Road from R & B Road to Adarshnagar.

21.11.2012 1

Road from R & B Road to

Hanumanth nagar.

21.11.2012 1

4 NCRMP/B-W/AP/RHB/PRED/07/Nagaram/001Road from R&B Road toMohammadalipalem.

19.11.2012 1

5 NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001Road from R & B Road Allur to Yadavapalem

21.11.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 111: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 111/259

6 NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

Reconstruction of HLB @ km 5/2of Bapatla - Suryalanka roadacross perali drain in GunturDistrict.

4.11.2012 1

7 NCRMP/B-W/AP/Br/R&B/07/Bapatla/011

Reconstruction of HLB @ km 2/4of Bapatla - Pandurangapuram

road across perali drain inGuntur District.

4.11.2012 1

8 Phase-II

Bridge in Km 14/6 of Chandolubridge to Nizampatnam road inGuntur district.

4.11.2012 1

Road from R&B road toChandramouli Nagar InNizampatnam Mandal.

4.11.2012 1

TOTAL 21

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 112: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 112/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE MONTH

OF NOVEMBER 2012

SNO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURINGTHIS MONTH

DATES OF VISIT

NO. OF VISITS

1 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from NH5 to Mulaguntapadu02.11.201228.11.2012

2

2 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from Pakala R&B road to Mosanaladinne

05.11.201209.11.201214.11.201228.11.2012

4

3 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002 Road from R&B road to Chalivendradibba 02.11.201209.11.2012

2

4 NCRMP/B-W/AP/RHB/PRED/08/S.Konda/002Road from R&B road to Binginapalli Harijanawada CycloneShelter

09.11.2012 1

5NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/003

Road from R&B Road Allur to M T Raju colony 19.11.2012 1

6NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

Road from KEM R & B Road to Pullareddypalem 19.11.2012 1

7NCRMP/B-W/AP/RHB/PRED/08/Kothapatnam/004

Road from KEM R&B Road to Sankuvarigunta 19.11.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 113: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 113/259

8NCRMP/B-W/APMPCS/PRED/08/NGPadu/003

Kanaparthy cyclone shelter in Naguluppapadu Mandal Prakasamdistrict

21.11.2012 1

9 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu21.11.2012

25.11.2012

2

10NCRMP/B-W/AP/Br/R&B/08/Kanaparthy/012

Construction of High level Bridge at Km 16/10 of Naguluppapadu – Kanaparthy road in Prakasam District

21.11.201222.11.2012

2

Total 17

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 114: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 114/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THE MONTH OF

NOVEMBER 2012

SLNO

Package Number Name of work  

TPQA INSPECTIONS

DURING THIS MONTH

DATES OF VISITS

NO. OF VISITS

1NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005

Road from KT R&B road to Alaganipadu to Vavilla 09.11.2012 1

2NCRMP/B-W/AP/RHB/PRED/09/VIDAVALURU/005

Road from R&B road Kancharapalem HW to Alaganipadu. 09.11.2012 1

3NCRMP/B-W/AP/RHB/PRED/09/BOGOLO/RHB/01

Road from NH5 to Sambasiva Puram 15.11.2012 1

4NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI/004

Road from5/8 of Chennayapalem Road to Gummadi bandla 15.11.2012 1

5NCRMP/B-W/AP/RHB/PRED/09/RHB/KAVALI/004

Road from Pedattapupalem R&B road to Chennayapalem H.wada 15.11.2012 1

6 NCRMP/B-W/AP/RCS/PRED/09/TADA/009 Providing BT road to Peda Pannam Gadu in Tada Mandal of Nellore Dt. 05.11.2012 1

7 NCRMP/B-W/AP/RCS/PRED/09/TADA/009Road from @ km 56/8 to CK Road to Periyavettu Kuppam CycloneShelter

05.11.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 115: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 115/259

8NCRMP/B-W/AP/RHB/PRED/09/T.P.Gudur/012

Road from R&B Road C.S. Puram Siva Rama Puram. 21.11.2012 1

9NCRMP/B-

W/AP/RHB/PRED/09/T.P.Gudur/012

Ring Road to T.P.Gudur-Salipeta R&B Road via C.S.Puram and

Mandapam Village

21.11.2012 1

10NCRMP/B-W/AP/RHB/PRED/09/BOGOLO/001

Road from 9/6 of Juvvaladinne R&B Road to 11/0 of Juvvaladinne R&BRoad Via Venkateshpalem

22.11.2012 1

11NCRMP/B-W/AP/RHB/PRED/09V.CHALEM/007

Providing BT Surface to the road from R&B road to Edagali Kandriga 22.11.2012 1

12 NCRMP/B-W/AP/RHB/PRED/09/Muthukur/006

Road from R&B road to Patuvari Kandriga 22.11.2012 1

13NCRMP/B-W/AP/RHB/PRED/09/BOGOLU/001

Road from 1/6 of Zuvvaladinne R&B Road to Tellagunta 22.11.2012 1

Total 13

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 116: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 116/259

9.3 Statement Showing the Inspections and Site Visits of Districts during the Month of December -2012

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN SRIKAKULAM DISTRICT DURINGTHE MONTH OF DECEMBER 2012

SNO

.PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF VISIT

NO. OF VISITS

1NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Runku in SanthabommaliMandal.

6.12.12,12.12.12,13.12.12,14.12.12,

26.12.12

5

2 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002Road from Deppuru, Bahadapalli road to Onkuluru & cycloneshelter.

7.12.12 1

3 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from NP Road to URK Puram 7.12.12 1

4 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from Pollada to Komaralthada &Cyclonic shelter 7.12.12 1

5 NCRMP/B-W/AP/RCS/PRED/01/V.Kotturu/002 Road from R&B ROAD TO Devunalthada 7.12.12 1

6NCRMP/B-W/AP/MPCS/PRED/01/Santhabommali/005

Construction of Cyclone shelter at Kollipadu in SanthabommaliMandal.

6.12.12,11.12.12,13.12.12,14.12.12,25.12.12,26.12.12

6

7 NCRMP/B_W/AP/Br/R&B/01/Bendigedda/004Construction of High level Bridge across Bendigedda at km 4/10 of Pundi-Parlkimidi road in Srikakulam Dist.

11.12.12 1

8 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006 Road from Talasamudram to Dola regulator

6.12.12,10.12.12,12.12.12,13.12.12,

7

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

14 12 12

Page 117: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 117/259

14.12.12,15.12.12,18.12.12.

9 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/006Road from Mabagam R&B road to Dubbakavanipeta via

Gajapathinagaram.

10.12.12,

18.12.122

10 NCRMP/B-W/AP/MPCS/PRED/01/Polaki/005Road from R&B road Edullavalasa-Killam to jonnam viaTalasamudram

1.12.12,2.12.12,3.12.12,4.12.12,10.12.12,13.12.12,18.12.12

7

11 NCRMP/B_W/BR/R&B/01/uppigedda/002Construction of HLB across uppigedda at Km 7/6 of Srikakulammunicipal limits to Pukkalapeta

20.12.12,26.12.12

2

12 NCRMP/BW/AP/Br/AR&B/01/Patnavanipeta/001Construction of Bridge at km 11/6-8 of NH-5 to Patnavanipetaconnecting Sundarapalem.

18.12.12 1

TOTAL 36

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 118: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 118/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VIZIANAGARAM DISTRICT DURINGTHE MONTH OF DECEMBER 2012

S

NO.PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF

 VISIT

NO. OF

 VISITS

1NCRMP/B-W/ AP/ Br/ R&B/ 02/ Chakaligadda

 /008

Construction of Minor Bridge at Km 15/2 near Chakaligaddaof Konada Ramatheertham R&B road to Konatalapalem (via)

 Yerukonda, Pasupam, Kollayavalasa (ZP Road) in Vizianagaram District.

26.12.12 1

Total 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 119: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 119/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN VISHAKAPATNAM DISTRICT DURINGTHE MONTH OF DECEMBER 2012

SNO

.PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF

 VISIT

NO. OF

 VISITS

1 NCRMP/B-W/AP/RCS/PRED/03/Rambilli/004 Construction of cyclone shelter at Venkayyapalem in Rambilli Mandal

3.12.125.12.126.12.1222.12.12

4

2 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Mullaparra in Nakkapalli Mandal

3.12.125.12.1214.12.1218.12.1222.12.1229.12.12

6

3NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Gajapathinagaram inPayakaraopeta Mandal

5.12.1228.12.12

2

4 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002Construction of cyclone shelter at Bangarampeta in NakkapalliMandal

8.12.1214.12.1229.12.12

3

5NCRMP/B-W/AP/MPCS/PRED/03/Payakaraopeta/003

Construction of cyclone shelter at Ratnayampeta in PayakaraopetaMandal

5.12.1228.12.12

2

6 NCRMP/B-W/AP/MPCS/PRED/03/Nakkapalli/002 Construction of cyclone shelter at Patimeeda in Nakkapalli Mandal

3.12.125.12.1214.12.1218.12.1222.12.1229.12.12

6

Total 23

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 120: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 120/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN EAST GODAVARI DISTRICT DURINGTHE MONTH OF DECEMBER 2012

S NO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF

 VISIT

NO. OF

 VISITS

1NCRMP/B-W/ AP/RCS/ PRED/04/

KARAPA/001Road from approach road to cyclone shelter at Adivipudi in E.G.Dt. 14.12.2012 Nil

2NCRMP/B-W/ AP/RHB/ PRED/04/

KARAPA/001Road from Gurjanapalli to Bandulavaripalem

14.12.201219.12.2012

Nil

3NCRMP/B-W/AP/RHB/ PRED/04/

Katrenikona/003Road from PR road to Dasarivanipeta and to Cyclone Shelter 08.12.2012 Nil

4

NCRMP/B-W /AP/RCS/PRED/04/Thondangi/004

Road from R&B Road to G.Musalayyapeta CS Nil Nil

5 Road from R&B Road to P.Chodipallipeta CS 08.12.2012 4

6 Road from R&B Road to K.Chodipallipeta CS 08.12.2012 4

7 Road from R&B Road to Hukumpeta CS 08.12.2012 5

8 Road from R&B Road to Gaddipeta CS 08.12.2012 4

9 Road from R&B Road to Danavaipeta CS 08.12.2012 4

10NCRMP/B-W/ AP/MPCS/PRED/04/Thondangi/001

Cyclone Shelter at Avulamanda and of Thondangi Mandal , E.G.Dt.12.12.2012 & 27.12.2012

4

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

12 12 2012

Page 121: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 121/259

11 Cyclone Shelter at Lakshmanudipeta of Thondangi Mandal, E.G.Dt.12.12.2012,

17.12.2012 & 27.12.2012

6

12NCRMP/B-W/ AP/RCS/

PRED/04/Uppalaguptam/003Road from R&B Road to Chinaraghavulapeta Cyclone Shelter

13.12.2012 & 21.12.2012

2

13NCRMP/B-W/ AP/MPCS/

PRED/04/Uppalaguptam/002Cyclone Shelter at Pedaraghavulapeta of Uppalaguptam Mandal, E.G.Dt.

03.12.2012,04.12.2012,05.12.2012,06.12.2012,08.12.2012,13.12.2012,21.12.20012,

7

TOTAL 22

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURING

Page 122: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 122/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN WEST GODAVARI DISTRICT DURINGTHE MONTH OF DECEMBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURINGTHIS MONTH

DATES OF VISITS

NO. OF VISITS

1.

NCRMP/B-W/AP/RHB/PRED/05/Mogalthuru/001

Road from NH 214 A at Ranga Statue centre to Harijanawada of Kalipatnam (E)(Mogalthuru Mandal W.G.Dist.)

- -

2.R&B road at Panchayat Office to Pulaparthivarithota via Badava (MogalthuruMandal W.G.Dist.)

- -

3.Mogalthuru Vempa R&B Road at Uchintha Kalava Bridge to GogulammaHarijanapeta (Mogalthuru Mandal W.G.Dist.)

- -

4.From Narsapur Mogalthuru R&B road to Dayadaldaspeta via Venkateswara Swamytemple (Mogalthuru Mandal W.G.Dist.)

- -

5.Road from NH 214 A road to Harijanapeta of Kothota (Mogalthuru MandalW.G.Dist.)

- -

6.

NCRMP/B-W/AP/RHB/PRED/05/Nasapur/002

R&B Road to Indira nagar (via) Pochamma temple (Narsapur Mandal W.G.Dist.) - -

7. Road from R&B road to Pedalanka (Narsapur Mandal W.G.Dist.) - -

8.Road from LB Cheria CC road to Chillapalem of LB Cheria (Narsapur MandalW.G.Dist.)

- -

9. NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

From A-U R&B Road to Satyanarayanapuram, (Kalla Mandal W.G.Dist.) - -

10. From A-U R&B Road to Mekaladibba (Kalla Mandal W.G.Dist.) - -

Total 0

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Phase - II

Page 123: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 123/259

Phase - II

1.NCRMP/B-W/AP/RCS/PRED /05/Achanta/002

Road from R&B road to Ayodya lanka Marrimula cyclone shelter. – –

2. NCRMP/B-W/AP/RCS/

PRED/05/Kalla/003

Road from R&B road to Modi Cyclone Shelter – –

3. Road from R&B road to S.C Bose Colony Cyclone Shleter – –

4.NCRMP/B-W/AP/RCS/PRED /05/Bhimavaram/004

Construction of approach road to cyclone shelter in Losari of Bhimavaram Mandal. – –

5.

NCRMP/B-W/AP/RCS/PRED/05/ Mogaltur /005

Road from R&B road to Kothakayalathippa cyclone shelter 19.12.2012 1

6. Road from Narsapur Perupalem R&B road to Mandavarithota 19.12.2012 1

7. Road from Mollaparru R & B road to Mollaparru Patha Colony 19.12.2012 1

8. Road from K.P Palem (N) Panchayat office to Metturevu Palli palem 19.12.2012 1

9.NCRMP/B-W/AP/RCS/PRED /05/Narsapur/006

R&B road to Chinamynavanilanka 15.12.2012 1

10. P.R road to Ramanujapuram 15.12.2012 1

11. Road from P.R road to Prakasapuram 15.12.2012 1

12.NCRMP/B-W/AP/RHB /PRED /05/Kalla/004

K.G. R&B Road to Mamidipudi of Kalawapudi. – –

13.NCRMP/B-W/AP/RHB /PRED/05/Bhimavaram/005

Road from Dongapindi R & B Road to Revu (Pallipalem) in Dongapindi of Bhimavaram Mandal.

 – –

14.Road from R & B Road to Sarvodhyanagar (Garivelladibba) H/o Losari of Bhimavaram Mandal.

 – –

15.

NCRMP/B-W/AP/RHB/

PRED /05/ Mogaltur /006 Khalipatnam R&B Road to Khalipatnam ferry 19.12.2012 1

16.

NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/007

Road from R & B Road at Metturevu to Parasavari meraka via Kandulapativarimeraka

 – –

17.Road from Narasapur Perupalem R &B Road to Janakiram Colony in Andevarimeraka of K.P.Palem (S)

 – –

18. Road from Narsapur Perupalem R & B road to Dondaparthivari meraka – –

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from Narsapur Perupalem

Page 124: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 124/259

19.

NCRMP/B-W/AP/RHB /PRED/05/ Mogaltur/008

Road from Narsapur PerupalemR & B Road to Melamvaripalem Perupalem(S)

20.12.2012 1

20.Road from Perupalem Mollaparru R & B road via Sattinenivarimeraka toK.D.Pallavapalem

20.12.2012 1

21. Road from Perupalem Dibbalapallipalem R & B road to Mellapallavapalem 20.12.2012 1

22.Road from Perupalem beach R & B Road to Challavarimeraka viaMucherlavarimeraka

20.12.2012 1

23.

NCRMP/B-W/AP/RHB/PRED/05/ Mogaltur /009

Road from Perupalem R&B road to Dindla – –

24.Road from Narsapur Perupalem R & B road to Nellipallipalem via Ambedkar colonyHarijanapeta

 – –

25. Road from Perupalem R & B Road to Kouruvaripalem – –

26.

NCRMP/B-W/AP/ RHB

 /PRED/05/ Narsapur /010

Road from SP R&B road to Pasaladeevi 26.12.2012 1

27. LT R&B road to Modi 26.12.2012 1

28. SP R&B road to Gannabathulavari palem of Chamakuripalem 26.12.2012 1

29.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/012

Road from R&B road to SC Colony of Pedalanka 15.12.2012 1

30. R&B road to Rajeev Nagar of Darbharevu 15.12.2012 1

31. SP R&B road to Pedathota of Turputallu 15.12.2012 1

32. R&B road to Peta of Turputallu 15.12.2012 1

33. R&B road to Pedathota of Turputallu 15.12.2012 1

34.

NCRMP/B-W/AP/RHB/PRED/05/Narsapur/013

R&B road to Guttulavarimeraka 26.12.2012 1

35. Road from R & B Road to Pulaparthivaripalem 26.12.2012 1

36. R&B road to Pedaedigapalem 26.12.2012 1

37. R&B road to Evanivarimeraka 26.12.2012 1

38. NCRMP/B-W/AP/RHB/ Road from PR Road to Prakashpuram SC colony of Vemuladeevi(E) 26.12.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

PRED /05/Narsapur/014 Road from PR road to Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi

Page 125: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 125/259

39.PRED /05/Narsapur/014 Road from PR road to Vemuladeevi (E) colony (Via) Ralla cheruvu of Vemuladeevi

(E)26.12.2012 1

40. Road from PR road to Addalavarimeraka of Vemuladeevi(E) – –

41. NCRMP/B-W/AP/MPCS/PRED/05/ Narsapur/001

Sardupalli Palem of Vemuladeevi – –

42. Pedamynavani lanka – –

43. NCRMP/B-W/AP/MPCS/PRED/05/ Narsapur/003

Chinamynavani lanka – –

44. Vemuladeevi East – –

45. NCRMP/B-W/AP/MPCS/PRED/05/Mogalturu/002

 Yetimondi of Perupalem – –

46. Bellamkondavarimeraka – –

Total 26

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THE

Page 126: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 126/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN KRISHNA DISTRICT DURING THEMONTH OF DECEMBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURINGTHIS MONTH

DATES OF

 VISITS

NO. OF

 VISITS

1 NCRMP/B-W/AP/RHB/PRED/06/Machil ipatnam/002Road from R&B road to Chikativanipalem 04.12.2012 1

Road from R&B road to B.V.Thota 05.12.2012 1

2 NCRMP/B-W/AP/RHB/PRED/ 06/Machipatnam/001Road connecting R&B road throughGantalammapalem

05.12.2012 1

3 NCRMP/B-W/AP/RCS/PRED/ 06/Machipatnam/001

Road from Chinnapuram R&B road toGundupalem

06.12.2012 1

Road from Potlapalem ZP road to Potepalli 04.12.2012 1

Road from Bhogireddypalli R&B road toRamakhandam 06.12.2012 1

4 NCRMP/B-W/AP/RHB/ PRED/06/Bandar/016

Road from R&B Road Satravapalem toJonnalavarimodi

12.12.2012 1

Road From R&B road tallapalem to Pallipalem 12.12.2012 1

5 NCRMP/B-W/AP/RHB/ PRED/06/Bandar/017

Road from R&B road to Kamsalipalem 12.12.2012 1

Road from Gokavaram R&B road to Sathenapalem 12.12.2012 1

Road from R&B road Jonnalavanipalem to Vuchalvanipalem via Thallapalem

12.12.2012 1

6 NCRMP/B-W/AP/RHB/ PRED/06/Bandar/018

Road From Peddapatnam R&B road toSajjavaripalem

12.12.2012 1

Road from Thallapalem R&B road to Beach Area 12.12.2012 1

Road from Pedapatnam R&B road to Thalapalem 12.12.2012 1

7 NCRMP/B-W/AP/RHB/ PRED/06/Bandar/019Road from R&B road Potlapalem to ChinnaPothepalli

12.12.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road From R&B road to Marridibba 12 12 2012 1

Page 127: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 127/259

Road From R&B road to Marridibba 12.12.2012 1

Road From Peddapatnam R &B road to Vannaru Village Via Kannuru

12.12.2012 1

8 NCRMP/B-W/AP/RCS/ PRED/06/MACHILIPATNAM/008Kammavanicheruvu R&B Road to VenkataDurgambapuram in Bandar Mandal

19.12.2012 1

9 NCRMP/B-W/AP/RCS/ PRED/06/MACHILIPATNAM/010

Raod from R&B Road Karagraharam to Pallipalem 19.12.2012 1

Road from R&B Road Kammavanicheruvu to KPTPalem

19.12.2012 1

Road from R&B Road Kammavanicheruvu toMalakayalanka

19.12.2012 1

Road from R&B road Pallithumalapalem toNelithippa

19.12.2012 1

10 NCRMP/B-W/AP/RHB/ PRED/06/Machilipatnam/020

Road from Gokavaram R&B road to Vodarevupalem

20.12.2012 1

Road from Gokavaram R&B road to

Badugovanipalem

20.12.2012 1

Road from R&B road Thallapalem to Rayapalli 20.12.2012 1

Road from Mangenepudi R&B road toPathareddypalem

20.12.2012 1

11 NCRMP/B-W/AP/RCS/ PRED/06/Nagayalanka/003

Road from R&B road to Ramakrishnapuram R&Broad via Pahaupakali

28.12.2012 1

R&B Road to Cyclone Shelter at Kothaupakali 28.12.2012 1

12 NCRMP/B-W/AP/RCS/ PRED/06/Nagayalanka/004 From R&B road Bhavadevarapalli 28.12.2012 1

13 NCRMP/B-W/AP/RCS/ PRED/06/Nagayalanka/005

Road From R&B Road to Cyclone Shelter atPedapalem

28.12.2012 1

Road from Gullalamoda R&B road to Etimoga 28.12.2012 1

Road from R&B to Cyclone Shelter at ChinaEtimoga

28.12.2012 1

Road from R&B to Cyclone Shelter at ChinaKammavaripalem

28.12.2012 1

14 NCRMP/B-W/AP/RHB/ PRED/06/Nagayalanka/009 Road from R&B Road to Kommanamolu Village 28.12.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Road from R&B Road to Nandyalavanidibba 28 12 2012 1

Page 128: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 128/259

Road from R&B Road to Nandyalavanidibba 28.12.2012 1

Road from R&B Road to Pedakammavaripalem 28.12.2012 1

15 NCRMP/B-W/AP/RHB/ PRED/06/Nagayalanka/010Road from R&B Road to Indiramma Tank 28.12.2012 1

Road from R&B Road to MPUP School 28.12.2012 1

Total 38

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 129: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 129/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN GUNTUR DISTRICT DURING THEMONTH OF DECEMBER 2012

SNO. PACKAGE NO NAME OF WORK  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF VISIT

NO. OF VISITS

1

NCRMP/B-W/AP/RCS/PRED/07/Karalapalem/002

Road from Ganapavaram R&B Road to Pedamarpuvaripalem.

4.12.2012,10.12.2012,12.12.2012,14.12.2012,18.12.2012,19.12.2012,27.12.2012.

7

Road from R&B road to chinapuluguvaripalem

4.12.2012,10.12.2012,13.12.2012,14.12.2012,18.12.2012,19.12.2012,27.12.2012.

7

Road from Ganapavaram PR Road to Bonthagoralapalem.8.12.2012,12.12.2012.

2

2

NCRMP/B-W/AP/Br/R&B/07/Bapatla/010

Reconstruction of HLB @ km 5/2 of Bapatla - Suryalanka road

across perali drain in Guntur District. 10.12.2012 1

NCRMP/B-W/AP/Br/R&B/07/Bapatla/011Reconstruction of HLB @ km 2/4 of Bapatla - Pandurangapuram

road across perali drain in Guntur District.10.12.2012 1

NCRMP/B-W/AP/RCS/PRED/07/Pv palem/001 Road from R & B Road Allur to Yadavapalem 12.12.2012 1

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Phase II Const ction of C clone shelto at Ha bo of Ni ampatnam 22 12 2012 1

Page 130: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 130/259

3

Phase-II Construction of Cyclone sheltor at Harbour of Nizampatnam. 22.12.2012 1

Road from R&B Road to Gattuvaripalem inNagaram mandal(RHB).

22.12.2012 1

4Construction of Cyclone sheltor at Padamativeedi of Nizampatnam

village (Tybe c).

22.12.2012 1

5Construction of Cyclone sheltor near MRO's office of Nizampatnam (Tybe B)

22.12.2012 1

6Construction of Cyclone sheltor at fishermen colony of Nizampatnam (Tybe C).

22.12.2012 1

7 Road from krosurivari palem Road to Marakavaripalem (RCS). 22.12.2012 1

8

Road from R&B Road to Balavaripalem upto Gajulavaripalem inNizampatnam mandal. (RHB)

22.12.2012 1

Road from Gowdapalem to Mallevaripalem in Perli village inKarlapalem Mandal 27.12.2012 1

Road from Komali to Nagarajupalli in P.V.Palem Mandal 27.12.2012 1

Road from Muthayapalem to Venkatalaksmipuram in BapatlaMandal 27.12.2012 1

Road from Chandole R&B road to Kothapalem in P.V.PalemMandal 27.12.2012 1

Road from Bethapudi to Stuvartupuram in Bapatla Mandal 27.12.2012 1

Road from NH 214 to Dandubata (via) M.V.Rajupalem inKarlapalem Mandal 27.12.2012 1

TOTAL 32

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THE

Page 131: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 131/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN PRAKASAM DISTRICT DURING THEMONTH OF DECEMBER 2012

SNO.

PACKAGE NO NAME OF WORK  

TPQA INSPECTIONS DURINGTHIS MONTH

DATES OF VISITNO. OF

 VISITS

1NCRMP/B-W/AP/RHB/PRED/

08/S.Konda/002Road from NH5 to Mulaguntapadu 20.12.2012 1

2NCRMP/B-W/AP/RHB/PRED/

08/S.Konda/002Road from Pakala R&B road to Mosanaladinne 20.12.2012 1

3NCRMP/B-W/AP/RHB/PRED/

08/S.Konda/002Road from R&B road to Chalivendradibba

13.12.201220.12.2012

2

4NCRMP/B-W/AP/RHB/PRED/

08/S.Konda/002Road from R&B road to Binginapalli Harijanawada Cyclone Shelter 13.12.2012 1

5NCRMP/B-W/AP/RHB/PRED/

08/Kothapatnam/003Road from R&B Road Allur to M T Raju colony

04.12.201219.12.201228.12.2012

3

6NCRMP/B-W/AP/RHB/PRED/

08/Kothapatnam/004Road from KEM R & B Road to Pullareddypalem

04.12.201213.12.201224.12.201228.12.2012

4

7NCRMP/B-W/AP/RHB/PRED/

08/Kothapatnam/004Road from KEM R&B Road to Sankuvarigunta

04.12.201213.12.201228.12.2012

3

8NCRMP/B-W/APMPCS/PRED/

08/NGPadu/003Kanaparthy cyclone shelter in Nagulappapadu mandal Prakasamdistrict

05.12.201224.12.201228.12.2012

3

9 NCRMP/B-W/AP/RHB/PRED/08/Tangutur/09 Road from R&B road Pellur to Vasepallipadu

04.12.2012

24.12.201228.12.2012

3

10NCRMP/B-W/AP/Br/R&B/

08/Kanaparthi/012Construction of High level Bridge at Km 16/10 of Naguluppalapadu –Kanaparthi road in Prakasam District

24.12.201228.12.2012

2

Total 23

QUARTERLY REPORT

Consultancy Services for Third Party Quality Audit (TPQA) for National Cyclone Risk Mitigation Project (NCRMP)

Page 132: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 132/259

STATEMENT SHOWING THE NUMBER AND DATES OF TPQA INSPECTIONS IN NELLORE DISTRICT DURING THEMONTH OF DECEMBER 2012

SLNO Package Number Name of work  

TPQA INSPECTIONSDURING THIS MONTH

DATES OF VISITS

NO. OF VISITS

1NCRMP/B-W/AP/RHB/PRED/

09/VIDAVALURU/005Road from KT R&B road to Allaganipadu to vavilla

08.12.2012,20.12.2012,29.12.2012

3

2NCRMP/B-W/AP/RHB/PRED/

09/VIDAVALURU/005Road from R&B road Kancharlapalam HW to Alaganipadu.

07.12.201208.12.2012,15.12.2012,20.12.2012

29.12.2012

5

3NCRMP/B-W/AP/RCS/PRED/

09/KAVALI/006Road Connecting R&B Road through Voturu Village in SPSR NelloreDistrict

20.12.2012,28.12.2012

2

4NCRMP/B-W/AP/RCS/PRED/

09/TADA/009Providing BT road to Peda Pannam Gadu in Tada Mandal of NelloreDt.

03.12.2012,14.12.2012,18.12.2012

3

5NCRMP/B-W/AP/RCS/PRED/

09/TADA/009Road from @ km 56/8 to CK Road to Periyavettu Kuppam CycloneShelter

03.12.2012,14.12.2012,18.12.2012

3

Total 16

Page 133: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 133/259

In Joint Venture

Photo Presentation byThird Party Quality Audit

Consultant

of AP NCRMP Works

Page 134: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 134/259

Page 133 of 258

Page 135: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 135/259

Page 134 of 258

Page 136: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 136/259

Page 135 of 258

Page 137: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 137/259

Page 136 of 258

Page 138: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 138/259

Page 137 of 258

Page 139: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 139/259

Page 138 of 258

Page 140: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 140/259

Page 139 of 258

Page 141: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 141/259

Page 140 of 258

Page 142: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 142/259

Page 141 of 258

Page 143: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 143/259

Page 142 of 258

Page 144: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 144/259

Page 143 of 258

Page 145: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 145/259

Page 144 of 258

Page 146: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 146/259

Page 145 of 258

Page 147: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 147/259

Page 146 of 258

Page 148: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 148/259

Page 147 of 258

Page 149: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 149/259

Page 148 of 258

PD, SPIU,NCRMP’s inspection on 15-10-2012,Phase-II.Bridge

across Buckingham canal at Km.26/3 of Rajupalem - Iskapalli

Page 150: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 150/259

Page 149 of 258

PD, SPIU,NCRMP’s inspection on 15-10-2012,Phase-II.Bridge

across Buckingham canal at Km.26/3 of Rajupalem - Iskapalli

Page 151: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 151/259

Page 150 of 258

PD, SPIU,NCRMP’s inspection on 15-10-2012Construction of High level bridge at Km 7/2 of road from M.C.road to

Juvvaladinne via Mungamur in Nellore District

Page 152: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 152/259

g

Page 151 of 258

PD, SPIU,NCRMP’s inspection on 15-10-2012Construction of High level bridge at Km 7/2 of road from M.C.road to

Juvvaladinne via Mungamur in Nellore District

Page 153: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 153/259

g

Page 152 of 258

Page 154: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 154/259

Page 153 of 258

Page 155: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 155/259

Page 154 of 258

Page 156: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 156/259

Page 155 of 258

Page 157: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 157/259

Page 156 of 258

Page 158: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 158/259

Page 157 of 258

Page 159: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 159/259

Page 158 of 258

Page 160: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 160/259

Page 159 of 258

Page 161: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 161/259

Page 160 of 258

Page 162: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 162/259

Page 161 of 258

Page 163: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 163/259

Page 162 of 258

Page 164: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 164/259

Page 163 of 258

Page 165: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 165/259

Page 164 of 258

Page 166: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 166/259

Page 165 of 258

Page 167: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 167/259

Page 166 of 258

Page 168: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 168/259

Page 167 of 258

Page 169: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 169/259

Page 168 of 258

Page 170: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 170/259

Page 169 of 258

Page 171: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 171/259

Page 170 of 258

Page 172: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 172/259

Page 171 of 258

Page 173: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 173/259

Page 172 of 258

Page 174: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 174/259

Page 173 of 258

Page 175: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 175/259

Page 174 of 258

Page 176: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 176/259

Page 175 of 258

Page 177: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 177/259

Page 176 of 258

Page 178: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 178/259

Page 177 of 258

Page 179: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 179/259

Page 178 of 258

Page 180: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 180/259

Page 179 of 258

Page 181: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 181/259

Page 180 of 258

Page 182: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 182/259

Page 181 of 258

Page 183: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 183/259

Page 182 of 258

Page 184: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 184/259

Page 183 of 258

Page 185: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 185/259

Page 184 of 258

Page 186: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 186/259

Page 185 of 258

Page 187: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 187/259

Page 186 of 258

Page 188: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 188/259

Page 187 of 258

Page 189: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 189/259

Page 188 of 258

Page 190: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 190/259

Page 189 of 258

Page 191: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 191/259

Page 190 of 258

TPQA inspection of Providing BT road to Peda Pannam

Gadu in Tada Mandal of Nellore Dt on 03.12.2012.

Page 192: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 192/259

HT Electric line crossing GSB layer thickness checking

View of CC road and electric

pole very close to CC road

View of CC road

Page 191 of 258

Page 193: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 193/259

Page 192 of 258

Page 194: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 194/259

Page 193 of 258

Page 195: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 195/259

Page 194 of 258

Page 196: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 196/259

Page 195 of 258

TPQA-NCRMP Inspection of Talasamudram road on 02-12-12 in Srikakulam

District. Sieve analysis for WBM GR II collections from km 5/000 to 5/670.

Page 197: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 197/259

Page 196 of 258

TPQA-NCRMP Inspection of Talasamudram road on 03-12-12 in

Srikakulam District.WBM GR II is in progress from km 5/000 to

5/670.

Page 198: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 198/259

Page 197 of 258

TPQA-NCRMP Inspection of Talasamudram road on 07-12-12 in

Srikakulam District.WBM GR II completed from km 5/000 to

5/670.

Page 199: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 199/259

Page 198 of 258

NCRMP-TPQA inspection of Road from R&B road Kancharapalem

HW to Alaganipadu of Nellore Dt on 03.12.2012.

Page 200: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 200/259

View of road dam Collection of GSB

Checking of road dam width GSB layer thickness checking

Page 199 of 258

Page 201: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 201/259

Page 200 of 258

Page 202: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 202/259

Page 201 of 258

Page 203: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 203/259

Page 202 of 258

Page 204: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 204/259

Page 203 of 258

Page 205: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 205/259

Page 204 of 258

Page 206: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 206/259

Page 205 of 258

Page 207: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 207/259

Page 206 of 258

Page 208: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 208/259

Page 207 of 258

Page 209: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 209/259

Page 208 of 258

Page 210: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 210/259

Page 209 of 258

Page 211: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 211/259

Page 210 of 258

Page 212: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 212/259

Page 211 of 258

Page 213: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 213/259

Page 212 of 258

Page 214: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 214/259

Page 213 of 258

Page 215: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 215/259

Page 214 of 258

Page 216: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 216/259

Page 215 of 258

Page 217: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 217/259

Page 216 of 258

Page 218: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 218/259

Page 217 of 258

Page 219: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 219/259

Page 218 of 258

Page 220: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 220/259

Page 219 of 258

Page 221: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 221/259

Page 220 of 258

Page 222: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 222/259

Page 221 of 258

Page 223: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 223/259

Page 222 of 258

Page 224: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 224/259

Page 223 of 258

PM,TPQA NCRMP inspection of Road from R&B roadKancharapalem HW to Alaganipadu of SPSR Nellore Dt on

15.12.2012

Page 225: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 225/259

View of GSB layerView of GSB layer

GSB layer thickness checking GSB layer thickness checking

Page 224 of 258

PM,TPQA NCRMP inspection of Road from R&B roadKancharapalem HW to Alaganipadu of SPSR Nellore Dt on

15.12.2012

Page 226: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 226/259

View of GSB layer GSB layer thickness checking

View of road dam Erection of project information board

Page 225 of 258

TPQA-NCRMP Inspection of Talasamudram road on 02-

12-12 in Srikakulam District. Prime coat applied on WBM

GR III surface.

TPQA-NCRMP Inspection of Talasamudram road on 02-

12-12 in Srikakulam District.OGPC+Seal coat work is in

progress.

Page 227: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 227/259

TPQA-NCRMP Inspection of Talasamudram road on 02-

12-12 in Srikakulam District.Temprature verification forseal coat mix at site.

TPQA-NCRMP Inspection of Talasamudram road on 02-

12-12 in Srikakulam District. Bitumen extraction test

conducting at site.

Page 226 of 258

TPQA-NCRMP Inspection of Talasamudram road on 04-

12-12 in Srikakulam District. Thickness verification of 

OGPC+seal coat layer.

TPQA-NCRMP Inspection of Talasamudram road on 04-

12-12 in Srikakulam District. Thickness verification of 

OGPC+Seal coat layer.

Page 228: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 228/259

TPQA-NCRMP Inspection of Talasamudram road on 04-

12-12 in Srikakulam District. Sample collected to conductBitumen extraction test at site.

TPQA-NCRMP Inspection of Talasamudram road on 04-

12-12 in Srikakulam District. Bitumen extraction testconducting at site.

Page 227 of 258

TPQA-NCRMP Inspection of Talasamudram road on 05-

12-12 in Srikakulam District. OGPC laying work is in

progress.

TPQA-NCRMP Inspection of Talasamudram road on 05-

12-12 in Srikakulam District. Seal coat laying work is in

progress.

Page 229: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 229/259

TPQA-NCRMP Inspection of Talasamudram road on 05-

12-12 in Srikakulam District. Carriageway way widthverified at site.

TPQA-NCRMP Inspection of Talasamudram road on 05-

12-12 in Srikakulam District.WBM GR II is in progressfrom km 5/000 to 5/670.

Page 228 of 258

TPQA-NCRMP Inspection of Dola regulator road in

Srikakulam District. Temperature verification at the time

of OGPC laying.

TPQA-NCRMP Inspection of Dola regulator road in

Srikakulam District.Temprature verification of OGPC.

Page 230: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 230/259

TPQA-NCRMP Inspection of Dola regulator road in

Srikakulam District. Thickness verification of OGPC+Seal

coat layer.

TPQA-NCRMP Inspection of Dola regulator road in

Srikakulam District. Carriage way width verification.

Page 229 of 258

TPQA-NCRMP Inspection of Dola regulator road in

Srikakulam District.

TPQA-NCRMP Inspection of Dola regulator road in

Srikakulam District.

Page 231: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 231/259

TPQA-NCRMP Inspection of Talasamudram road on 03-

12-12 in Srikakulam District. Bitumen extraction test.

Page 230 of 258

Page 232: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 232/259

Page 233: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 233/259

Page 232 of 258

Page 234: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 234/259

Page 233 of 258

Page 235: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 235/259

Page 234 of 258

Page 236: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 236/259

Page 235 of 258

Page 237: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 237/259

Page 236 of 258

Page 238: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 238/259

Page 237 of 258

Page 239: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 239/259

Page 238 of 258

Page 240: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 240/259

Page 239 of 258

Page 241: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 241/259

Page 240 of 258

Page 242: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 242/259

Page 241 of 258

Page 243: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 243/259

Page 242 of 258

Page 244: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 244/259

Page 243 of 258

Page 245: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 245/259

Page 244 of 258

Page 246: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 246/259

Page 245 of 258

Page 247: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 247/259

Page 246 of 258

Page 248: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 248/259

Page 247 of 258

Page 249: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 249/259

Page 248 of 258

Page 250: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 250/259

Page 249 of 258

Page 251: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 251/259

Page 250 of 258

Page 252: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 252/259

Page 251 of 258

Page 253: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 253/259

Page 252 of 258

Page 254: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 254/259

Page 253 of 258

TPQA-NCRMP Inspection of Runku shelter on 27-10-12 in

Srikakulam District. Sand sieve analysis test conducting at

site

Page 255: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 255/259

TPQA-NCRMP Inspection of Runku shelter on 17-11-12 in

Srikakulam District. Stone dust sieve analysis testconducting at site.

Page 254 of 258

TPQA-NCRMP Inspection of Runku shelter on 08-12-12 in

Srikakulam District. Plinth beam sand filling work is in

progress.

Page 256: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 256/259

TPQA-NCRMP Inspection of Runku shelter on 08-12-12 in

Srikakulam District. Plinth beam sand filling work is in

progress.

Page 255 of 258

TPQA-NCRMP inspection on 28-11-2012.

MPCS at Gajapathinagaram in

Visakhapatnam

Ready or concreting

Page 257: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 257/259

Sieve analysis for CA Fine aggregate material test

Page 256 of 258

TPQA-NCRMP inspection on 28-11-2012.

MPCS at Gajapathinagaram in

Visakhapatnam District.Concrete temperature checking

Fine aggregate silt content test

Page 258: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 258/259

Concrete Slump test Concrete Slump test

Page 257 of 258

TPQA-NCRMP inspection on 28-12-2012.

MPCS at Gajapathinagaram inVisakhapatnam District

1st floor brick work is in progress.

Page 259: Quarterly Report - Oct 2012 to Dec 2012

7/30/2019 Quarterly Report - Oct 2012 to Dec 2012

http://slidepdf.com/reader/full/quarterly-report-oct-2012-to-dec-2012 259/259

1st floor brick work is in progress.1st floor brick work is in progress.