Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Project No. IND – 0164)
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
1 | P a g e
LIST OF CONTENTS
I. PREFACE ............................................................................................ 1
II. PROJECT DATA ....................................................................................... 1
III. PROJECT OBJECTIVES ........................................................................... 2
IV. PROJECT SCOPE ..................................................................................... 3
V. PMSC SCOPE OF WORK ......................................................................... 5
a. Management and Administration................................................. 5
b. DED Review and Evaluation......................................................... 5
c. Supervision of Physical Construction......................................... 5
VI. WORK PLAN AND SCHEDULE ................................................................ 5
1. Work Schedule .............................................................................. 5
2. Work Plan of December 2016 – February 2017 ........................... 7
3. Realization of work up to current period..................................... 7
4. 3-months-ahead Activity Plan ...................................................... 8
VII. DED DOCUMENT REVIEW FROM DEDC........................................... 5
7.1. Flow Chart of the Reviewing Process of DEDC Document .. 8
7.2. Review and Evaluation Process of DEDC Document ........... 11
7.3. Result of DEDC Document Review ........................................ 15
7.4. Buildings Area Data Review:.................................................. 18
VIII. ACCOMPLISHED RESULT OF ACTIVITY ............................................ 19
1. Accomplished Activities............................................................... 19
2. Coordination Meetings ................................................................. 20
IX. DISBURSEMENT PLAN....................................................................... 22
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
2 | P a g e
X. URRENT WORK STATUS................................................................... 22
XI. NEXT AGENDAS................................................................................... 23
XII. CONCLUSION ....................................................................................... 23
XIII. CLOSING …………………………………………………………………. 24
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
3 | P a g e
I.PREFACE
This is a progress report of the first 3-months of work (1st Quarterly Report) of PT.DETADECON as Project Management and Supervision Consultant (PMSC) for developmentproject of State Islamic University (UIN) Raden Fatah Palembang, with contract: PMU 4in1 /KK.02.11 / 1306/2016 dated 23 November 2017.
Development and construction of Civil Works for UIN Raden Fatah is funded by soft loans ofIslamic Development Bank (IDB). The project was later called: The Support to Developmentof Islamic Higher Education Project Package 2: UIN RADEN FATAH, Palembang.
This 1st Quarterly Report contains: Project Data, Project Objectives and Scope, WorkingScope, Work Plan and PMSC Activity during the period of the first three months (December2016 s / d February 2017), review method to documents / output of Consultant Planner(DEDC), DEDC Document Review results, Progress and Budget disbursement plan, currentstatus of the project, and Agenda / Work Plan for 3 months ahead (March to May 2017).
The supporting documents for the preparation of this 1st Quarterly Report are attached atthe end of the report, as an integral part of this report.
I. PROJECT DATA
Based on the data we collected, we compile the Project Data as follows:
1. Program Coordinator : Directorate General of Islamic HigherEducation, Ministry of ReligiousAffairs Republic of Indonesia
2. Project Name : The Support To Development OfIslamic Higher Education ProjectIND - 0164
3. No. Loan : IND – 0164, February 16th 2012
4. Loan Closure Date : December 31st 2018
5. PMS Consultant : PT. Deta Decon
6. DED Consultant : PT. Patroon Arsindo KSO PT. GRIKSACIPTA
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
4 | P a g e
7. Equipment Consultant : Tender done, no appointment yet
8. Financial Auditing Consultant : No tender yet
9. Civil Work Contractor : No tender yet
II. PROJECT OBJECTIVES
The UIN Raden Fatah project is part of the IAIN 4-In-1 Project; IAIN North Sumatra,
IAIN Raden Fatah, IAIN Walisongo Semarang and IAIN Mataram.
Major long-term objectives of the project includes:
1. Upgrading the quality of education at 4 IAINs through their capabilities to impart
knowledge and skills, and to conduct research in contemporary Islamic issues
as required by the government of Indonesia in the 21st century;
2. Modernizing the course structure of IAINs; according to the changing and
needs of Indonesian people, and strengthening the 4 lAINs’ training capabilities
in Islamic studies and interdiscplinaries of modern sciences.
The short-term objectives of the project will focus on development of IAIN
Sumatera Utara Medan, IAIN Raden Fatah - Palembang, IAIN, IAIN Walisongo -
Semarang, and IAIN Mataram into modern Islamic educational institutions, which
will serve as models and resource centers for quality improvement of other IAINs
in Indonesia. This development involves:
1. To transform four state institutes of Islamic studies (IAIN) into modern Islamic
educational institutions.
2. To improve academic quality (human resources, teaching learning, and
research).
3. To refine existing management into good university leadership and
management.
4. To construct new buildings for existing and new faculties, laboratories, libraries,
training centers, study centers and offices.
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
5 | P a g e
III. PROJECT SCOPE
The scope of IAIN Raden Fatah Construction Project is the construction of 6 new
faculty buildings, an integrated laboratory building, public library building,
administration building and ICT Center and all supporting infrastructure, as follows:
No. Description Area ( m2 ) Unit
A. New Buildings
I. General Buildings
1 General Library and ICT Center 6,000 M2
2 Administration building 4,000 M2
3 Integrated Laboratory 5,000 M2
Total General Buildings Area 15,000 M2
II. New Faculty Buildings
1 2 (two) Faculty of Science and Technology 6,000 M2
2 2 (two) Faculty of Economics and Business 6,000 M2
3 1 (one ) Faculty of Tarbiyah and Education 3,000 M2
4 1 (one) Faculty of Psychology 3,000 M2
Total Supporting Buildings Area 18,000 M2
Total Buildings Area (I+II)
9 Buildings 33,000 M2
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
6 | P a g e
No. Description Area Unit
B Supporting Infrastructure
1 Environmental Impact Analysis (EIA) 1 Set
2 Land Clearance and reclamation 150,000 M2
3 Fence and Gate 2,915 M
4 Landscape 10,000 M2
5 Campus Street Lighting 80 Unit
6 Fire Hydrant System 1 Set
7 Roads and Parking Pavement 21,400 M2
8 Pedestrian Pavement 8,560 M2
9 Road Cansteen (separator) 4,280 M
10 Storm water Drainage 4,280 M
11 Electricity Connection 4,280 M
12 Power Generator Set 1 Unit
13 Campus Power Sub-Station 1 Unit
Notes:
: Source of Funds from IDB
: Source of Funds from GOI
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
7 | P a g e
IV. PMSC SCOPE OF WORK
PMSC scope of works cover three main parts:
a. Management and Administration
- Coordinate and undertake Detail Design Consultant activities.
- Assisting the Auction Committee in the contractor procurement process.
- Conduct supervision and control of work performed by contractors.
- Coordinate and consult with EQC related to the installation planning of the
equipment to be installed.
- Coordination and consultation with Financial auditing consultants, related to
payment of employment.
- Assisting the Bid Committee in the contractor procurement process.
b. DED Review and Evaluation
- Coordinate, direct and review the documents produced by ConsultantPlanner.
c. Supervision of Physical Construction
- Monitoring and controlling work in terms of time, quality and cost carriedout by the contractor.
V. WORK PLAN AND SCHEDULE
1. Work Schedule
The whole phase-by-phase activity of PMSC Work Plan until the project is
completed, is structured as follows:
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
8 | P a g e
NO ACTIVITIES
Year - 1 ( Month 1 - 12 ) Year - 2 ( Month 13 - 24 )
DED STAGE( 4 Month )
PROCUREMENTSTAGE
( 5 month )
Construction Stage( 14 months)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
I.PREPARATIONSTAGE
1.1. Sign of ontract Agreement forPMSC
1.2. Mobilzation Personil
1.3. KICK of Meeting PMSC
II. DED PHASE/STAGE2.1. Preparing Inception Report of
PMSC
2.2. Review Master Plan, TopographySurvey &Soil Survey
2.3 Review Design Brief andConceptual Design Drawing.
2.4Review Preliminary designDrawing & Preliminary Reportof DEDC.
2.5Review of Preliminary EstimateCost and Engineering EstimateCost
2.6. Review of outline specificationand Technical Spesification
2.7. Review Design DevelopmentDrawing & DD Report of DEDC
2.8. Coordination with DEDC on DetailDesign.
`
2.9. Preparing PMSC Quaterly Report2.10
.Bid Documents for ConstructionCivil work submitted to IDB
2.11. Review DEDC Final Report
2.12. Preparing PMSC's Review DEDCDocument Report ( QuaterlyReport )
III. CONTRACTORPROQUREMENT PHASE
3.1. Preparing of Bidding DocumentofConstruction of Civil Work (Post Bidding ) .
3.2 Bidding Document ofConstruction of Civil Worksubmitted to IDB
3.3 Approval / NOL BiddingDocument of construction ofContractor Civil Work from IDB
3.4 Approval / NOL of DEDDocument for Civil Work from
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
9 | P a g e
IDB
3.5 Bid process for Construction ofCivil Works ( icld. rebid Meeting )
3.6 Evaluation of ContractorsBidding Document
3.7 Result of Bid Process of CivilWork submitte to IDB
3.8 Approval / NOL of Bid Result forConstructionof Civil Work fromIDB
IV. CONSTRUCTION STAGE4.1 Contract Agreement for
Contractor
4.2 Pre-Construction Meeting
4.3 Approval Contractor QualityPlanning and Target
4.4 Phisyical Monitoring
4.5 Material & Equipment Approval
4.6 Testing and Commissioning.
4.7 Weekly Meeting & PrepareMinutes of Meeting
4.8 Approval Shop Drawing.
4.9 Contractor Weekly Progress &Contractor Monthly Certificate.
4.10 Aproval As built Drawing.
4.11 Preparing Monthly Report
4.12. Preparing Quarterly Report.
4.13. Check list and First/ ProfessionalHand Over .
2. Work Plan of December 2016 – February 2017
• Implement Kick off meeting with PI and IAIN Management
• A review of the project site by the PMSC.
• Review topographic data and reports on land investigation results.
• Review master plan images and preliminary drawings and design
development produced by DEDC.
• Review of Planning Report
• Review of Planning Concepts
• Review of structural calculations
• Review Images
• Weekly coordination meetings
3. Realization of work up to current period
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
10 | P a g e
Targeted work plans generally go according to plan:
• Implementation Kick off meeting: December 2, 2016
• Project land review by PMSC: December 2, 2016
• Review results of land and topographic investigations
• Review master plan drawings and preliminary drawings and design
development
• DEDC-PMSC and PDEDC-PMSC-PIU-PMU weekly coordination
meetings.
• Coordination with PIU and Directorate General of Ministry of Religious
Affairs
4. 3-months-ahead Activity Plan
• Head to Head coordination meetings between PMSC, DEDC, PMU teams
and PIU teams
• Review the design development drawings produced by DEDC
• Review of Technical Specification and Engineering Estimate
• Plenary Finalization Meeting of Design Detail Document.
• Approval and approval of documents made by DEDC
• DEDC duplication of documents to be sent to IDB Headquarter for
approval.
• Finalization of the "Civil work bidding document" together with PMU
(Project Management Unit) and other PMS package consultants, for
further IDB approval.
• Delivery of DEDC documents.
• Approval of DEDC documents (No Objection Letter) from IDB.
VI. DED DOCUMENT REVIEW FROM DEDC
6.1. Flow Chart of the Reviewing Process of DEDC Document
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
11 | P a g e
Flow Chart of the Reviewing Process: starting from the Preparation Stage,
Design Concept, Preliminary Design, Design Development up to Detail of
Design; as well as preparation of document. For bidding is described as
figure. Flow Chart of Review Process, as Figure 1 as below.
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
12 | P a g e
DEDC Result submit to IDB :
Technical SpecificationEngineering Estimate & BOQ
Detail Drawing
Finish
DEDC Start
Draft ReviewMasterplan
;Soil Data Collectingand Topography
Survey
Yes
Draft TopografiSurvey, DraftMaster Plan andand Pre DesignConcept ,PreliminaryReport
Review/-Approval By PIU
Preliminary DesignMaster Plan 3D
D
Drawing andSoil Investigation
Report
Review Master Planby DEDC
No
Master Plan andConcept
Design Approved
Review Preliminarydesign, 3 D Drawing,Soil Report by PMSC
Review
-Approvalby PIU & PMU
Yes
YesDesign
Development
No
DEDC Result:
Design DevelopmentDrawing, Engineering
,
Estimate and Technical
Specification, DD Report.
Review Design Development,Engineering Estimate and Technical
Specification by PMSC
Reviewby PMSC -Approval
Detail Design by
DEDC
No
DEDC Result:Detail Drawing ,
Engineering Estimatedand Spesification
,Miniature andFinal Report .
Review Detail Design ( Head toHead Review n Revision DEDC,PMSC , PIU and PMU ) : I & II
PRINT FINALDOCUMENT
Legalization Validation, ,
DEDC Document
by PIU
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
13 | P a g e
6.2. Review and Evaluation Process of DEDC Document
DEDC has been appointed in early October 2016. Project Management
Consultant and Supervision (PMSC) were appointed at the end of November
2016.
The DEDC and PMSC Coordination Meeting was first held on November 25,
2016, where the meeting material was DEDC Overview Progress to PMSC. This
meeting was held at the Office of PT. Patroon .Atrsindo
At the Meeting, it is reported some of the things that have been carried out by
DEDC, such as:
- Topographic survey
- Soil investigation
- Review of Master Plan and Site Plan images
- Architecture & Architecture preliminary design concept
- Concept of structural planning
- Concept of Mechanical Planning
- Electrical planning concepts
- Plumbing Planning Concepts
- Concept of Infra Structural Planning
- Create an Introduction Report
- Create Preliminary Design Report.
Based on DEDC's explanation, PMSC conducts the following Review and
Evaluation of Documents in the following order:
1. Review of topographic survey report
2. Review soil investigation
3. Review the Master Plan / site Plan
4. Review of Introduction Report
5. Review Preliminary Design Report:
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
14 | P a g e
Review the concept and preliminary design of Architecture
Review the concept of structural planning
Review the concept of Mechanical Planning
Review of Electrical planning concepts
Review of Plumbing Planning Concepts
Review of Infrastructure Planning Concept
Review Process is as follows:
No. DED Output Details Review Process
1. Topography Report
- See the completeness of the Topographic
Report
- Reviewing the Topography image’s
compatibility with the technical data of the
Reports book.
2. Soil Investigation
- Reviewed whether Soil Investigation work is
adequate for the purposes of planning
Foundation, plaster and others.
- Evaluation whether Bearing capacity of the
foundation correct based on existing soil
data.
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
15 | P a g e
3. Master Plan / Site Plan - Information from DEDC: when they
conduct a field review on the land, they
found that in the area has been made a
small island surrounded by water funnel
(Canal). For that purpose DEDC use the
condition of the land by putting 9 new
buildings in the area, which is bordered by
water funnel. The remaining land is used
for future development.
- Consequences of the arrangement of
such buildings: it required a car / people
bridge to enter access entrance.
- PMSC asks DED Consultant to pay
attention to funnel condition so that water
inside funnel always keeps flowing to
clean environment.
4. Inception Report - PMSC requests the material of Inception
Report to be more comprehensive and
improved, as directed from PMSC.
5. Preliminary DesignReport
- In the PMSC Preliminary Report, it
requests the DEDC to add the Report
material with ideas from the proposed
design concept and the reason for
choosing the concept.
- Program area of each building on each
floor is requested by PMSC to be
arranged in table form and given a
description column.
- In Concept of Design Structure, it is
required to add the explanation of the
latest regulatory reference references
used in the planning.
- For the Concept of Electrical Design, it is
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
16 | P a g e
asked to explain the reasons for Electrical
Voltage System selection: TM, TM, TR.
- For Mechanical Design, it has to be
equipped with calculation of elevator
capacity.
- The Preliminary Design report comes with
One Line Diagram drawing that supports
the MEP Design Concept.
Preliminary design drawing has been approved by PIU, as attached on attachement I.
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
17 | P a g e
6.3. Result of DEDC Document Review
1. Master Plan/ Site Plan:2.
3.
Notes:
A = Administration BuildingB = Faculty of TarbiyahC = Faculty of Business & EconomyD = LibraryE = Interacted LaboratoryF = Faculty of Science & TechnologyG = Faculty of PsychologyH = Food courtI = Sport CentreJ = Multipurpose BuildingK = Student DormitoryL = Power HouseM = Future Development of TarbiyahN = Parking AreaO = Futsal Field
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
18 | P a g e
P = Open Space for CeremonyQ = Load/Unload AreaR = CanalS = Pond with AmphitheaterT = PlazaU = Campus Forest
2. Administration Building
3. Faculty of Economics and Business Building
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
18 | P a g e
P = Open Space for CeremonyQ = Load/Unload AreaR = CanalS = Pond with AmphitheaterT = PlazaU = Campus Forest
2. Administration Building
3. Faculty of Economics and Business Building
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
18 | P a g e
P = Open Space for CeremonyQ = Load/Unload AreaR = CanalS = Pond with AmphitheaterT = PlazaU = Campus Forest
2. Administration Building
3. Faculty of Economics and Business Building
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
19 | P a g e
4. Integrated Laboratory Building
5. General Library & ICT Center Building
6. Faculty of Psychology Building
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
19 | P a g e
4. Integrated Laboratory Building
5. General Library & ICT Center Building
6. Faculty of Psychology Building
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
19 | P a g e
4. Integrated Laboratory Building
5. General Library & ICT Center Building
6. Faculty of Psychology Building
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
20 | P a g e
7. Faculty of Science and Technology Building
8. Faculty of Tarbiyah and Education Building:
6.4. Buildings Area Data Review:
No. DescriptionBased on
MOM( m2 )
Based onDEDCoutput( m2 )
A. New Buildings
I. General Buildings
1 General Library and ICT Center 6,000 6,000
2 Administration building 4,000 3.912
3 Integrated Laboratory 5,000 5.500
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
20 | P a g e
7. Faculty of Science and Technology Building
8. Faculty of Tarbiyah and Education Building:
6.4. Buildings Area Data Review:
No. DescriptionBased on
MOM( m2 )
Based onDEDCoutput( m2 )
A. New Buildings
I. General Buildings
1 General Library and ICT Center 6,000 6,000
2 Administration building 4,000 3.912
3 Integrated Laboratory 5,000 5.500
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
20 | P a g e
7. Faculty of Science and Technology Building
8. Faculty of Tarbiyah and Education Building:
6.4. Buildings Area Data Review:
No. DescriptionBased on
MOM( m2 )
Based onDEDCoutput( m2 )
A. New Buildings
I. General Buildings
1 General Library and ICT Center 6,000 6,000
2 Administration building 4,000 3.912
3 Integrated Laboratory 5,000 5.500
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
21 | P a g e
Total General Buildings Area 15,000 15.412
II. New Faculty Buildings
12 (two) Faculty of Science andTechnology 6,000 5.820
22 (two) Faculty of Economics andBusiness 6,000 5.820
31 (one ) Faculty of Tarbiyah andEducation 3,000 3.008
4 1 (one) Faculty of Psychology 3,000 3.008
Total Supporting Buildings Area 18,000 17.656
Total Buildings Area (I+II): 9 Buildings 33,000 33.068
VII. ACCOMPLISHED RESULT OF ACTIVITY
The following is the table of results accomplished by the PMSC during its activitieswithin the first 3 months:
1. Accomplished Activities
No. Activity STATUS
1 Establish a Kick off Meeting Done, according to target.
2 Project Land Review Done, according to target.
3 Reviewing the results of soil test andtopography
Done, according to target.
4 Reviewing Master plan, Preliminary, andDesign Development Images
Done, according to target.
5 Coordination Meetings Done, according to target.
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
22 | P a g e
2. Coordination Meetings
Coordination Meetings in the first 3-month period, are as follows:
No. ACTIVITIES RESULTSSUGGESTIONS /
ADVICES
1 Establish Kick Off Meeting (See Appendix)Minutes of Meeting(MoM)
- To achieve theimplementation ofthe project inaccordance with thetargets to beachieved; from thebeginning, theproject must be wellplanned to obtainmaximum projectoutcome and asexpected.
- PMSC will provideexperiencedexperts, work plan,Work scheduling,Work methodology,discipline andscientific approach,and others.
- Further support,commitment, workdiscipline and goodcooperationbetween the partiesinvolved.
- All parties mustperform the task onan agreed schedule.
2 Review of Project LandLand is relative flat,funnel workunfinished, Funnelcanal has not beenmade.
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
23 | P a g e
3 Review of Soil & TopographyTest Result
Supporting capacity ofthe foundation shouldbe checked again,given the condition ofthe soil based onDeep Drill data on theBuilding Plan.
4 Review of Master plan andPreliminary Design Images
DEDC is required toimprove the reportmaterial, as PMSCsuggests.
5 Coordination Meetings: Friday, November 25th
2016 at PT PATROONARSINDO Office.
Thursday, December22nd 2016 at PTPATROON ARSINDOOffice.
Monday, January 16th
2017 at PT PATROONARSINDO Office.
Tuesday, January 24th
2017 at Meeting RoomUIN Raden PatahPalembang (09.30 AM –Finished)
Tuesday, January 24th
2017 at Meeting RoomUIN Raden PatahPalembang (3.30PM –Finished)
Thursday, February 2nd
- See Minutes ofMeeting (MoM) onAttachment below.
- See Minutes ofMeeting (MoM) onAttachment below.
- See Minutes ofMeeting (MoM) onAttachment below.
- See Minutes ofMeeting (MoM) onAttachment below.
- See Minutes ofMeeting (MoM) onAttachment below
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
24 | P a g e
2017 at Meeting RoomEMIS KEMENAGBuilding, 4th Floor
Thursday, February 9th
2017 at Meeting RoomEMIS KEMENAGBuilding, 4th Floor.
Thursday, February 16th
2017 at CurriculaMeeting Room ofMadrasah KEMENAG,6th Floor.
Thursday, February 23rd
2017 at Meeting RoomEMIS KEMENAGBuilding, 4th Floor.
- See Minutes ofMeeting (MoM) onAttachment below
- See Minutes ofMeeting (MoM onAttachment below.
- See Minutes ofMeeting (MoM) onAttachment below.
- See Minutes ofMeeting (MoM) onAttachment below.
VIII. DISBURSEMENT PLAN
Payment status for work progress achieved to date:
- DEDC:- Term I : 15 % from Contract Value- Term II : 20 % from Contract Value
- PMSC:
- Term I : 10 % from Contract Value
IX. CURRENT WORK STATUS
DEDC work is completing on the Design Development Stage and Detailed
Design Stage.
Until this month, Progress of DEDC = 80%
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
25 | P a g e
The EQC has not been assigned.
FAC is not yet auctioned.
X. NEXT AGENDAS
Next PMSC Agendas are such as:
• Finalizing Head to head the DED documents (Drawings, Technical
Specification, Engineering Estimate, Bill Of Quantity) between DEDC,
PMSC, PIU teams and PMU teams.
• Discussion and finalization of civil work tender documents for all project
packages between PMSCs, PIU teams and PMU teams.
• Validation of DEDC documents at the end of March 2017.
• DEDC documents duplication and delivery to the IDB headquarters in
Jeddah to obtain NOL (No Objection Letter) from IDB Head Quarter.
XI. CONCLUSION
The following is the conclusion of the work progress for the first 3 months or until 28February 2017:
No ActivitiesStatusReview Notes Progress
1 Master plan√
Following the shape of existingcanal 100%
2 Topography andSurvey Report √ Land is relatively flat, with 40cm
elevation from around the road 100%
3 Soil Investigation √ Approval for type 40x40cm pilefoundation, carrying capacity of 70tons, depth 32-36m
100%
4 Preliminary Designand Concept √ Approved by User, PMSC and PIU 100%
Quarterly Report I, Periode : Desember 2016 – Februari 2017for Project Management & Supervision Consultant (PMSC)
The Support To The Development Of The Islamic Higher EducationPackage 2 (IDB Loan no. IND – 0164)
UIN Raden Fatah
26 | P a g e
5 Structure PlanningConcept & Image √ Partly completed, partly on the
finalization stage 65%
6 DD & DetailArchitecture Images √ Design development and detail
design are finalization stage 65%
7 Concept and Planningof MEP & IT Images √ On finalization stage 50%
8 SupportingInfrastructures √ On finalization stage 50%
9 Cost Planning &Analysis (Budget Plan) √
Will be reviewed again; (withterms) total cost should not bechanged.
60%
10 Technical Specification √Will be adjusted with the CostPlanning (Budget Plan), if there isany optimization / minimization
50%
Progress of DED Consultant = 80 %.
XII. CLOSING
This report was made as one of the outcomes of PMSC this project. May this documentprovide a clear picture of the work progress, processes, and PMSC's performance incarrying out the work integrity & trust to the assigner.
Jakarta, March 2017.
PT. Deta Decon,Project Manager & Supervision Consultant.
(Ir. Mardiana Daoed)Team Leader