quantity surveyor's liability during pre tender stage asmah alia bt

110
QUANTITY SURVEYOR’S LIABILITY DURING PRE TENDER STAGE ASMAH ALIA BT MOHAMAD BOHARI UNIVERSITI TEKNOLOGI MALAYSIA

Upload: vanliem

Post on 01-Jan-2017

233 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: quantity surveyor's liability during pre tender stage asmah alia bt

QUANTITY SURVEYOR’S LIABILITY DURING PRE TENDER STAGE

ASMAH ALIA BT MOHAMAD BOHARI

UNIVERSITI TEKNOLOGI MALAYSIA

Page 2: quantity surveyor's liability during pre tender stage asmah alia bt

i

QUANTITY SURVEYOR’S LIABILITY DURING PRE TENDER STAGE

ASMAH ALIA BINTI BOHARI

A project report submitted in partial fulfillment of the

requirement for the award of the degree of

Master of Sciences (Construction Contract Management)

Faculty of Built Environment

Universiti Teknologi Malaysia

NOVEMBER 2009

Page 3: quantity surveyor's liability during pre tender stage asmah alia bt

iii

To my beloved parents,

Fiancé,

Family and Friends.

Thank you for your support, guidance and everything.

Page 4: quantity surveyor's liability during pre tender stage asmah alia bt

iv

ACKNOWLEDGEMENTS

With high gratitude to Allah S.W.T. who gave me the ideas and physical strength

in preparing this master project. This project would not have been completed without the

support and encouragement from the various people involved. My deepest gratitude to

my supervisor, Mr. Jamaluddin bin Yaakob for his guidance, advice and support in

completing this master project.

I am also indebted to all the lecturers of this course (Master of Science in

Construction Contract Management) for their kind advice during the process of

completing this master project and to my course mates, thank you so much for the morale

support.

Not forgetting my parents, Hj Mohamad Bohari Bol and Hjh Darot Kassim, my

dearest fiancé and my beloved family, thank you so much for the tolerance and support.

This appreciation notes are also dedicated to all the parties involved who have

provided me with great cooperation that I really need in completing the master project.

Page 5: quantity surveyor's liability during pre tender stage asmah alia bt

v

ABSTRACT

Quantity Surveyor is one of the professionals that normally involved in the pre

tender stage of the construction development. The duties of quantity surveyor the pre-

tender stage include preparing cost estimate, measuring quantities, preparing bills of

quantity and giving suggestion on credible contractor to carry the construction project.

The quantity surveyor will require delivering his duties with reasonable skill and care.

In recent time, there have been many allegations against the professionals by clients for

contractual negligent and by third party under the law of tort due to breach of duties by

the quantity surveyor in performing his task at the pre tender stage. This research seeks

to examine liability of quantity surveyor during pre-tender stage in term of producing

cost estimate, measuring quantity, preparing bills of quantity and giving suggestion on

credible contractor to carry the construction project. The analysis was carried out by

referring to relevant law cases. This study found that generally, the professional owe a

duty of care to perform his duty with diligent and with reasonable skill in accordance to

the standard of duties stated. If he fails he is liable for resulting damages to his client.

There are also claims from the third partier against clients due to the failure of the

quantity surveyors who act as their agents.

Page 6: quantity surveyor's liability during pre tender stage asmah alia bt

vi

ABSTRAK

Juruukur bahan adalah salah seorang professional yang terlibat dalam pembangunan

pembinaan semasa peringkat pre-tender. Penglibatan juruukur bahan pada peringkat

tersebut adalah sebagai penasihat berkaitan dengan kontrak dan kos yang telah dilantik

oleh pihak klien untuk memjalankan tugas seperti Anggaran kos, membuat ‘bills of

quantity’ dan memberi nasihat kepada pihak klien mengenai kontraktor yang mepunyai

kredebiliti untuk menjalankan projek tersebut. Pada masa ini, terdapat banyak pertuduhan

di majukan kepada pihak profesional di dalam industri binaan akibat kecuaian dalam

menjalankan tanggungjawab. Kajian ini bertujuan untuk menyiasat liabiliti yang di

tanggung oleh juruukur bahan semasa peringkat pre-tender berkenaan dengan

penghasilan anggaran kos, penghasilan senarai kuantiti dan memberi saranan berkaitan

kontraktor yang bakal di cadangkan di dalam laporan tender. Analisis untuk kajian ini

dijalankan dengan merujuk kes mahkamah yang menunjukkan kesalahan yang biasa

berlaku dalam perlakuan professional semasa peringkat pre tender. Kesimpulan daripada

kajian ini ialah pihak juruukur bahan mempunyai kewajipan menjalankan kerja dengan

tekun dan kemahiran yang munasabah menurut terma kontrak, jika dia gagal, dia

bertanggungjawab kerana mengakibatkan kecederaan, kerugian atau kerosakan kepada

pihak klient. Terdapat juga tuntutan daripada pihak ketiga kepada klien akibat kegagalan

juruukur bahan menjalankan tanggungjawab tugas dengan baik dan sebagai seorang agen

kepada klien, juruukur bahan bertanggungjawab untuk menanggung kerugian.

Page 7: quantity surveyor's liability during pre tender stage asmah alia bt

vii

CONTENTS

Chapter Contents Page

Declaration

Dedication

Acknowledgements

Abstract

Contents

List of Tables

List of Cases

1 INTRODUCTION

1.1 Background of the study

1.2 Statement of issues

1.3 Objective of Study

1.4 Limitation of Study

1.5 The Significant of Research

1.6 Research Method

1

5

7

7

7

7

2 QUANTITY SURVEYOR

2.1 Introduction

2.2 The Nature of Professions

2.3 Nature profession of Quantity Surveyor

2.4 Quantity Surveyor’s contract

2.5 Duties of Quantity Surveyor during pre – tender

10

12

13

16

20

Page 8: quantity surveyor's liability during pre tender stage asmah alia bt

viii

Chapter Contents Page

2.5.1 Preparing Preliminary Estimates including preparation

of Preliminary Detailed Abstract (PDA), tender

estimate and Cost Plans.

2.5.2 Measurement and Preparing Bills of Quantities

2.5.3 Evaluate tender submission and prepare tender report.

2.6 Duties of Quantity Surveyor during post – contract.

2.7 Quantity Surveyor as an agent to the Construction Client

2.8 Professional Liability

2.8.1 Nature of the liability

2.8.2 Theories of liability

2.8.3 Professional liability

2.8.4 Professional liability in contract

2.9 Standard of Care

2.10 Reasonable Skill and Care

2.11 Professional Negligence

22

24

29

32

34

29

40

41

44

47

50

54

57

3 LIABILITY OF QUANTITY SURVEYOR DURING

PRE-TENDER STAGE

3.1 Introduction

3.2 Duties to prepare the cost estimate during pre-tender.

3.2.1 Preparing estimate with honest and reasonable

Care

3.3 Liability in Preparing Bills of Quantity.

3.3.1 Prepares a bill with reasonable care and

skill

60

62

62

70

70

Page 9: quantity surveyor's liability during pre tender stage asmah alia bt

ix

Chapter Contents Page

3.3.2 Measurement must be done in accordance to Standard

Method of Measurement.

3.4. Liability in recommending the acceptance of a tender.

74

76

4 CONCLUSION

4.1 Introduction

4.2 Research finding

4.3 Study constraints

4.4 Suggestion for future study

4.5 Conclusion

80

81

81

81

82

REFERENCES 85

APPENDICES

Page 10: quantity surveyor's liability during pre tender stage asmah alia bt

x

List of Figure

Page

Figure 1.1

Figure 2.1

:

:

Research Process and Methodology.

General Relationship of the agent, the principle and the

third parties

9

36

Page 11: quantity surveyor's liability during pre tender stage asmah alia bt

xi

List of Cases

Cases

A.E. Farr Ltd v. Ministry of Transport (1965) 5 BLR

Alderson B. in Blyth v Birmingham Waterworks Co11 Ex. 781, 784

Aubrey Jacobus & Partners v. Gerrard [1981] unreported

Andrews v Ramsay & Co. [1903] 2 KB 635, 638

Bains Harding Construction & Roofing (Aust) Pty Ltd v. McCredie Richmond & partners Pty

Ltd [1988] 13 NSWLR 437.Supreme Court of New South Wales, Smart J,10.6.1998

Barnett v Cape Town Foreshore Board [1978] FSR 176

Blair And Patterson Ltd v. McDermott [2006] ABC.L.R. 05/01

Blyth v Birmingham Water Works Co. [1850] 11 Exch 781

Blyth v Birmingham Waterworks Co [1856] 11 Exch 781 at pg 784

Blyth v Birmingham Waterworks Co. [1856] 11 Ex. 781, 784

Bodin v. Gill 117 S.E.2d 32

Bolam v Friern Hospital Management Committee [1957] 1 WLR 582 13,76

Bolt v. Thomas [1859] (Hudson’s Building and Engineering Con-History of Construction

Contracts and Case Law 7, tenth edition, at page 196)

Brown v. Kendall [1850] 60 Mass 292

Bryant and Sons Ltd v. Birmingham Saturday Hospital Fund [1938] 1 All ER 503

Cardy v Taylor [1994] 38 Con. L.R. 79

Carr v. IRC Lord Justice DuParq [1944] 2 AER 163

Cheng Keng Hong v Government of Federation Malaya [1966] 2MLJ 33

City of Mounds View v. Walijarvi 263 NW2d 420 (Minn. 1978)

Copthorne Hotel (Newcastle) Limited v Arup Associates [1997] 85 BLR 22

Cunard & Anor v. Antifyre Ltd [1953] 1 KB 551; [1932] All ER Rep 558

Derry v Peek [1889] 14 Appeal Case (HL)

Dudley Corporation v. Parson and Morrin Ltd [1959] (Construction Cost Management: Learning

from Case Studies, at page 216,221)

Eckersly v. Binnie & Partners [1988] 19 Con LR 1

Page 12: quantity surveyor's liability during pre tender stage asmah alia bt

xii

Gable House Estates v The Halpern Partnership [1995] 48 Con.L.R. 1

George Hawkins v Chrysler (UK) Ltd & Burne Associates [1986] 38 BLR 40

Gilbert & Partners v. R. Knights [1968] 2 AER 248; 4 BLR 9

Gordon Shaw Concrete Products Ltd v. Design Collaborative [1986] CarswellNS 104

Greaves & Co v Baynham Meikle [1975] 1 WLR 1095

Hanafiah, Raslan, Mohamed & Partners v Weng Lok Mining Co Ltd [1977] 1 MLJ 249

Heaven v Pender [1883] 11 QBD 503

Henderson v. Merrett Syndicated Ltd [1994] 3 WLR 761

Heath v. Swift Wings, Inc 252 SE 2d 256 (NC App 1979)

Kirkwood v Morrison

Lamphier v. Phipos [1838] 8 CP 475

KC Lim and Associates Sdn Bhd v Pembenaan Udarama Sdn Bhd [1980] 2 MLJ 26

Lochgelly Iron and Coal Co Ltd v M’Mullan [1934] AC 1,at page 25

London School Board v Northcroft [1899]noted at Hudson’s building cases (4th edition) vol.2

p.147

Meigh v. Stocking ford Colliery Company Limited Cited [1922] Hudson’s Building Case 7th

Edition Pg 308

Midland Bank Trust Co. Ltd v. Hett, Stubbs & Kemp [1979] Ch 384

Mitsui Construction v A.G Hong Kong [1986] 33 BLR 14

Moneypenny v Hartland [1826] 2 C & P 378

Nye Saunders and Partners v. Alan E Bristow [1987] 37 BLR 92,53,56

Partridge v Morris [1995] CILL 1095

Pratt v. George J Hill Associate s 38 B.L.R. 25

Saif Ali v Sydney Mitchell & Co ([1980] AC 198

Savage v Board of School Trustees [1951] 3 D.L.R. 39

Sutcliffe v Thackrah [1974] AC 727, at 760

Taylor v. Hall Taylor (1870) 4 IRCL 467 at 476

Turpin v. Bilton [1843] 5 Man & G 455; 134 ER 641

Tyrer v. District Auditor of Monmouthshire [1973] 23

Vaughan v. Menlove [1837] 3 Bing N.C 467,132 E.R 490 (C.P)

Page 13: quantity surveyor's liability during pre tender stage asmah alia bt

CHAPTER 1

INTRODUCTION

1.1 Background of the study

Although quantity surveying is a relatively old profession, nature of service

has changed considerably as the nature of the construction industry has changed.

The core function of Quantity Surveyor also remains the same as described in

nineteenth century case Taylor v. Hall1 namely,

‘taking out in detail the measurement and quantity from plan prepared by

an Architect for the purpose of enabling builders to calculate the estimate for

which they would execute the plans’.

In the broadest definition, the quantity surveyor is a person to control

construction costs b y accurate measurement of required, the application of expert

1 Taylor (1870) 4 IRCL 467 at 476

Page 14: quantity surveyor's liability during pre tender stage asmah alia bt

2

knowledge of costs and prices of work, labour, materials and plant required2. The

usual duties of a quantity surveyor can be described with reference to different

stages of development process. Pre-tender stage is where at the outset and before a

building contract is entered, a quantity surveyor may be engaged by the employer

to advise him of the estimated cost of the project and prepare detailed bill of

quantities and schedules. The quantity surveyor may also be called upon to give

general advice3.

Quantity Surveyor is one of the professionals involved in the construction

industry. In accordance to Shrike4, the term professional refers to a person who is

skilled and specialized, holds some special qualifications derived from training or

experience and conforms to high standard of performance and work ethics. This

professional belongs to a regulatory body which prescribes common rules of

conduct and standard practice. This professional must perform his duty under a

standard of performance.

The explanation of Standard of Performance by Bingham LJ in Eckersly v.

Binnie & Partners 5 should be applied equally to any construction professional.

Bingham LJ commented that

‘A professional man should command the corpus of knowledge which forms

part of the professional equipment of the ordinary member of his profession.

He should not lag behind other ordinary assiduous and intelligent members of

his profession in knowledge of new advances, discoveries and developments in

his field. He should alert to the hazards and risks inherent in any professional

2 Patten, B (2003) Professional Negligence in Construction Spon Press : London at Pg 72 3 Patten, B (2003) Professional Negligence in Construction Spon Press:Great Britain Page 73 4 Shrike,S (2009) 2 MLJ cl xii 2 MLJA 162 : Professional Negligence in the Construction Industry,

MLJ Articles 5 [1998] 10 Con LR 1.

Page 15: quantity surveyor's liability during pre tender stage asmah alia bt

3

task that he undertakes to the extent that other ordinarily competent members

of profession would be alert. He must bring to any professional task he

undertakes no less expertise, skill and care than other ordinary competent

members would bring but need bring no more. The standard is that of the

reasonable average. The law does not require of a professional man that he be

a paragon combining the qualities of polymath and prophet.”

He is acting as an agent of the construction client to administer the contract on

behalf of the client. An agent is a person that is authorized to create rights and

obligations for the principle which in this particular case is the construction client

through formation of contract or by appointment of the principle without contract or

may be inferred from the principle’s conduct6.

The agent must display complete loyalty and good faith, obey instruction to

the letter and not attempt to exceed the authority that has been granted7. Extend and

nature of duties owed to the client by the quantity surveyor as well as the powers

and authority granted to the client will be determined by the contract for services

between them8.

The professional not only required to do the work but also to do it competently

where his failure to do so constitutes negligence9. Thus, the surveyors who

miscalculate the estimated cost of a project, where in a case the clients think the cost

would be cheaper, is likely to be in breach of his contractual obligation to use

reasonable skill and care10.

6 Sinha & Deeraj (2000) Legal Dictionary 2nd Edition ILBS : Reprinted Edition Malaysia 7 Hinze, J Construction Contracts 2nd Edition,McGraw-Hill Higher Education:New York Page 60 8 Ashworth, A & Hogg, K (2007) Willi’s Practice and Procedure for the Quantity Surveyor 12the

Edition Blackwell Publishing : Britian Page 83 9 Ryan v Morgan Spear Assocs.,Inc,546 S.W 2d 678,681 10 Copthorne Hotel (Newcastle) Ltd v. Arup Associates (1996) 58 Con LR 105

Page 16: quantity surveyor's liability during pre tender stage asmah alia bt

4

Negligence is defined in the Cunard & Anor v. Antifyre Ltd11 as the absence of

the care which a prudent and reasonable man would take in the circumstances. Lord

Wright in Lochgelly Iron and Coal Co Ltd v M’Mullan12 said:

“In legal analysis, it is more than heedless or careless conduct, whether in

omission or commission: it properly connotes the complex concept of duty,

breach and damage thereby suffered by the person to whom the duty owed.”

Definition given by Baron Alderson in the case of Blyth v Birmingham Water

Works Co.13 has general to apply :

“Negligence consists in the omission to do something which a reasonable man

guided upon those consideration which ordinarily regulate human affairs,

would do, or, doing something which a reasonable and prudent man would not

do”

The negligence act by the said professional resulting damages to another party

can be severe in both human and term of cost. In the event of negligence occurred, the

case-laws are then used to judge the nature of legal duties to which professional

quantity surveyor might owe their clients and the extent to which professional might

held liable to pay damages and to what extent the claims can be made towards this

professional.

11 [1953] 1 KB 551; [1932] All ER Rep 558 12 [1934] AC 1,at p 25 13 [1850] 11 Exch 781

Page 17: quantity surveyor's liability during pre tender stage asmah alia bt

5

1.2 Statement of issues

During the last fifteen or so years, there has been an explosion of claims

against professionals precipitating a liability crisis within the profession where the

professional were held liable to the project owner and others for failures to perform

their professional obligations in accordance with the standard of care14.

Similar to other profession, the standard contract or the retainer between a

quantity surveyor and client will contain express term that both parties agree at the

time contract entered.15 Therefore the surveyor will be under a duty to his client

under the contract to exercise reasonable skill and care, where in a case of breach of

the contract, the client is entitled to damages to remedy the breach16. Later, the

client has a right to recover all losses arising naturally from the breach.

The quantity surveyor involved in the various of development stage including

the pre-tender stage where the are few duties or responsibilities will be carried out

as preparing cost estimate, preparing bills of quantity and giving suggestion on

suitable contractor. Under a contract term, the quantity surveyor will need deliver

his duties with reasonable skill and care.

14 Matthew J. Sullivan & Chris S. Stacy. Theories of Liability against Architects & Engineers Retrieved

24 May 2009 , from http://www.utcle.org/eLibrary/preview.php?asset_file_id=1301 15 Wilson, S (2006) Surveys and valuations – Breach of contract and negligence, Journal of Building

Appraisal Vol 2 No 4 PP 294-300 : Palgrave Macmillan Ltd 16 Ibid

Page 18: quantity surveyor's liability during pre tender stage asmah alia bt

6

Although quantity surveyor rarely featured in negligent cases17 but there are

few cases on allegation made to the Quantity Surveyor. In one of Australian case,

Bains Harding Construction & Roofing (Aust) Pty Ltd v. McCredie Richmond &

partners Pty Ltd18, the allegation made by client towards the quantity surveyor for

the missing pages in the tender documents. The defendant is a quantity surveyor

engaged by plaintiff to prepare a quantity breakdown for a purpose pricing a tender.

However, the bill prepare by the defendant appear to have missing page causing

BHC to underbid. Plaintiff claimed its loss from the defendant and it was successful.

In addition, Information given by the quantity surveyor at the pre-contact or

tender stage would be necessary as well as helpful especially to the contractor in

determining contract pricing document. In the case of Meigh v. Stocking ford

Colliery Company Limited19, quantity surveyor is obliged to prepare an accurate

quantity for the builders or contractor to price. The mistake in preparing bills of

quantity will cause the client to the losses.

The extend of the standard of care is a subjective issue that could in fact

induce a significant effect when come to decision in the court case involve in the

law of negligence. It is a focus of this study to establish the liability of the quantity

surveyor to his client with respect to breach of duty during the pre tender stage.

17 R.W Craig (1999 ) Procurement law for Construction and Engineering Works and Services,

Blackwell Science Limited:London Pg 515 18 [1988] 13 NSWLR 437.Supreme Court of New South Wales, Smart J,10.6.1998 19 Cited [1922] Hudson’s Building Case 7th Edition Pg 308

Page 19: quantity surveyor's liability during pre tender stage asmah alia bt

7

1.3 Objective of Study

The objective of this study is to identify liability of Quantity Surveyor towards

the client with respect of breach of duties in pre-tender stage under the traditional

procurement by studying/observing principle of law governing court decision.

1.4 Limitation of Study

The scope of this study will be confined to the following areas:

• Cases fall under conventional system because this method still is the

common method used.

• This study will be limited to contractual liability between the client and the

quantity surveyor.

1.5 The Significant of Research

From the research finding, the future research on corrective measures can be

carried out later to overcome or decrease the number of claims towards the

professionals with the intention that the professionals are remain trustable and

reliable

1.6 Research Methodology

Below are several approaches that will be taken to achieve the objectives.

Page 20: quantity surveyor's liability during pre tender stage asmah alia bt

8

Firstly, initial literature review was done in order to obtain the overview of the

concept of this topic. Discussions with supervisor, lecturers, as well as course

mates, were held so that more ideas and knowledge relating to the topic could be

collected. The issues and problem statement of this research will be collected

through books, journal, cases, articles and magazines. The objective of this research

will be formed after the issue and problems had been identified.

The next stage is the data collection stage. After the research issue and

objectives have been identified, various documentation and literature review

regarding to the research field will be collected to achieve the research objectives.

Generally, primary data is collected from Malayan Law Journals and other law

journals via UTM library electronic database, namely Lexis-Nexis Legal Database

and other Legal Database, WestLaw. The secondary sources include books, articles,

seminar papers, newspaper as well as information from electronic media database

on the construction contract law. These sources are important to complete the

literature review chapter.

After the data collection stage, the author will analyse all the collected cases,

information, data, ideas, opinions and comments. This is started with the case

studies on the related legal court cases. The analysis will be conducted by reviewing

and clarifying all the facts and issues of the case.

The final stage of the research process mainly involved the writing up and

presenting the research findings. The author will review the whole process of the

research with the intention to identify whether the research objectives have been

achieved. Conclusion and recommendations will be made based on the findings

during the stage of analysis.

Page 21: quantity surveyor's liability during pre tender stage asmah alia bt

9

Figure 1.1 Research Process and Methodology

Initial Study

Fix the research topic

Fix the research objective, scope and prepare the research outline

Data Collection

Data analysis & interpretation

Data arrangement

Writing

Checking

Identify type of data needed and data sources

Approach: Documentary Analysis

• Law Journals, e.g. Malayan Law Journal, Singapore law Report, Building Law Report, etc.

• Books • Other Journals

Approach 1: Literature review

• Books, journals, internet sources Approach 2: Discussion

Data Recording

Page 22: quantity surveyor's liability during pre tender stage asmah alia bt

10

CHAPTER 2

QUANTITY SURVEYOR

2.1. Introduction

Professional such as engineers, architects and surveyors play a very important

role in the construction industry. The precise meaning of the term ‘professional’

probably depends upon the points of view of the person using it. It is understand in

the sense of sociologist and lawyers as a person whose work and attitudes contain

particular characteristic of which the work itself is generally skilled and specialized,

mental rather than manual and usually the product of training and even examination

rather than experience20.

John L. Powell21 expresses “Professional" as an acquisitive concept, acquisitive

of aspirations and expectations but also of liabilities. A professional can be either a

person in a profession (certain types of skilled work requiring formal training or

20 Patten B (2003) Professional Negligence in Construction Spon Press : London Page 1 21 John L. Powell. Professional Negligence The Changing Coastline Of Liability at

http://www.4newsquare.com/Files/PDF/Article/JP%20article.doc

Page 23: quantity surveyor's liability during pre tender stage asmah alia bt

11

education) or in sports (a sportsman or sportswomen doing sports for payment) and

indicate a special level of quality of goods or tools sometimes also known as

commercial grade22. In addition, there is an expectation that professionals are

committed to work ethic which requires them to aspire to high performance for its

own sake and not just the requirements of the particular contract23.

A profession is classically defined as an occupational group of specialists

whose practice is based on a circumscribed body of knowledge, represented by a

professional association, self regulating via code of ethics and professional conduct

and participating in a shared culture norms, values and symbols24. In Carr v. IRC

Lord Justice DuParq25 stated:

“It seems to me to be very dangerous to try to define the word ‘profession’. I

think that everybody would agree that before once can say a man is carrying

on a profession, one must see that he has some special skill or ability or some

special qualification derived from training or experience. Even then one has to

be very careful because there are many people whose work demands great

skill and ability and long experience and many qualifications who would not

be said by anybody to be carrying on a profession. Ultimately one has to ask

this question: Would the ordinary man, the ordinary reasonable man…say

now, in the time in which we live, of any occupation, that it is properly

described as a profession? Times have changed. There are professions today

which nobody would have considered to be professions in time past. Our

forefathers restricted the profession to a very small number; the work of the

surgeon used to be carried out by a barber, whom nobody would have

considered a professional man. The profession of chartered accountant has

22 Howard (2000) Professional Ethics and Rules of Conduct for the Royal Institution of Chartered

Surveyors (RICS). United Kingdom : College of Estate Management 23 R.M Jackson and J.L Powell. Professional Negligence 5th Edition 24 Greenwood, W (1965) Management and Organizational Behavior Theories : An Interdisciplinary

Approach. Cincinnati, OH : Southwestern Publishing 25 [1944] 2 AER 163

Page 24: quantity surveyor's liability during pre tender stage asmah alia bt

12

grown up in comparatively recent times and other trades or vocations…many

in future years acquire the status of professionals”.

2.2. The nature of Professions

As stated by Powell and Jackson26, a definition of ‘the professions’ is pre-

eminently a matter for social historians or for sociologists rather than lawyers.

Generally speaking, however, the occupations which are regarded as professions have

four characteristics.

a. The nature of the work

The work done is skilled and specialized. A substantial part of the work is

mental rather than manual. A period of theoretical and practical training is usually

required, before the work can be adequately performed.

b. The moral aspect

Practitioners are usually committed, or expected to be committed to certain

moral principles. They are expected to provide a high standard of service for its own

sake.

c. Collective organization

Practitioners usually belong to a professional association, which regulates

admission and seeks to uphold the standards of the profession. Such associations

26 Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell: London

Page 25: quantity surveyor's liability during pre tender stage asmah alia bt

13

commonly set examinations to test competence and issue professional codes on

matters of conducts and ethics.

d. Status

A ‘profession’ involves the idea of on occupation requiring either purely

intellectual skill, or of manual skill controlled.

2.3. Nature profession of Quantity Surveyor

A quantity surveyor is a professional working within the construction industry.

The employment of the quantity surveyor on building projects today is well

established. They also occupy a much more influential position than in the past,

particularly when they are involved at the outset of a project27.

Hudson as cited by Barrett28 rightly describes quantity surveyors as ‘in general

highly skilled’ and ‘likely to be at least as well qualified in matters of technical

building construction, as are architect. A quantity surveyor also been define in court

as person ‘whose business consists in taking out in detail the measurement and

quantities from plans prepared by an architect, for the purpose of enabling the builders

to calculate the amounts for which they would execute the plans29.

27 Ashworth, A. (2001) Contractual Procedure in the Construction Industry Fourth Edition,Malaysia:

Longman 28 Barrett, K (2008) Defective Construction Work, Wiley-Blackwell : United Kingdom 29 Taylor v. Hall (1870) 4 IRCL p476

Page 26: quantity surveyor's liability during pre tender stage asmah alia bt

14

“If a man is unqualified but holds himself out to possess a skill, he will be

judged by the standards of a reasonably competent qualified person”

One of the definition of the categories of surveyors to be found in the Shorter

Oxford English Dictionary reads as one whose business it is to inspect and examine

the land, houses or other property and to calculate and report upon its actual and

prospective value or productiveness for certain purposes30. Quantity Surveyor in

Malaysian context must be a member of a Board of Quantity Surveyors Malaysia

(BQSM) and previously he must acquire a relevant education at accredited

universities with not less than two years working experience31.

As with architect and engineers, the fact that a quantity surveyor is relatively

junior or inexperienced will not of itself provide a defence to being judged by the

standard of the ordinarily competent member of his profession as passed by in Cardy

v Taylor32.

There are a numbers of important professional bodies in Malaysia

controlling and monitoring the membership of the professional surveyors namely the

Institution of Surveyors, Malaysia (ISM) and whilst the Board of Quantity Surveyors

is the National (BQSM) is the National registration Authority for professional

Quantity Surveyors. Quantity Surveyor practice in Malaysia is governed by the

Quantity Surveyor Act 196733. Matters of professional conduct and discipline are

dealt with by the Professional Conduct Committee which will investigate

“unacceptable professional conduct” or “serious professional incompetence”.

30 Refer to case The Royal Insitution of Charted Surveyors v. Director General of Fair Trading [1981]

E.C.C 587 [55] 31 Quantity Surveyor Act 1967 Subsection (10) (1) (a) Qualifications for Registration 32 [1994] 38 Con. L.R. 79 33 Ibid Incorporating all amendments up to 28 February 2002 (Act 487)

Page 27: quantity surveyor's liability during pre tender stage asmah alia bt

15

Only those registered in subsection (2)34 or any other written law, recognized

as a registered quantity surveyor can reside, practice and perform duties as a quantity

surveyor as stated in Quantity Surveyor Act 1967 sub section 8 (1),

“Except as otherwise provided in subsection (2) or any other written law, no

person or body, other than a registered Quantity Surveyor who is residing

and practising in Malaysia or firm or body corporate practising as

consulting Quantity Surveyors in Malaysia, shall be entitled to –

(a) prepare and submit to any person, organization or authority in Malaysia,

for construction projects, any feasibility study reports, preliminary

estimates, cost plans, documents and reports for pre-qualification of

contractors, bills of quantities and other tender documents, tender estimates

and reports, contract documents, and valuation of works for interim

payments, variation and final accounts; and

(b) provide professional services such as project cost management, value

management, risk management, facilities management, project management,

construction management, construction claims management, dispute

resolution services, technical and construction cost auditing and condition

survey.”

In Malaysia, quantity surveyor is one branch of the wider family of surveyors

which were divided to four divisions namely Property Consultancy Valuation

Surveying Division (PCVS) Geomatic and Land Surveying Division (GLS) Quantity

Surveying Division (QS) Building Surveying Division (BS).

Quantity surveyors are required to comply with a strict code of professional

conduct which includes responsibility to their employers or clients and to their

34 Ibid Surveyor Act 1967 Subsection (2) Registration

Page 28: quantity surveyor's liability during pre tender stage asmah alia bt

16

profession having full regard to the public interest, conducting themselves so as to

uphold the dignity and reputation of the profession and discharging their duties to

their employers and clients in an efficient and competent manner35.

2.4. Quantity Surveyor’s contract

It is suggested by Ir Harbans Singh K.S36, the professional should be vigilant

in securing a formal services agreement and not replying merely on a letter of intent

or a letter of appointment. The prevailing local practice of delaying or postponing the

formalization of the professional services agreement in cases even well after the

completion of the works has caused and is resulting in professionals compromising

their contractual rights, an eventuality that must be avoided if professionalism is to

prevail37.

To avoid any future disputes or differences, details of what the professionals

are to advice or act must be embodied in a form retainer. A retainer is a contract

between the client and the professionals for professional services of designing and

supervision of construction project.

Oliver J in Midland Bank Trust Co. Ltd v Hett. Stubbs and Kemps38

35 Association of South African Quantity Surveyors What is a Quantity Surveyor? Assessed at

http://www.asaqs.co.za/public/history.html 36 Ir Harban Singh K.S (2002) Law and Principle , LexisNexis : Malaysia 37 Ir Harban Singh K.S (2002) Engineering Construction Contract Management Pre-Contract Award

Practise, LexisNexis : Malaysia Page 237 38 [1979] Ch 384 [1978] All ER 571

Page 29: quantity surveyor's liability during pre tender stage asmah alia bt

17

“The classical formulation of the claim in this sort of case as ‘ damages for

negligence and breach of professional duty’ tends to be a mesmeric phrase. It

concentrate attention on the implied obligation to devote to the client’s

business that reasonable care and skill to be expected from a normally

competent and careful practioner as if that obligation were not only a

compendious but also an exhaustive, definition of all the duties assumed under

the contract created by the retainer and its acceptance. But of course, it is not.

A contract give rise to a complex of right and duties of which the duty to

exercise reasonable skill and care is but one, If I employ a carpenter to supply

and put up a good quality oak shelf for me, the acceptance by him of that

employment involves the assumption of a number of a contractual duties. He

must supply wood of an adequate quality and it must be oak. He must fix the

shelf. And he must carry out the fashioning and fixing the reasonable care and

skill which I am entitled to expect of a skilled craftsman. If he fixes the

brackets but fails to supply the shelf or if he supplies and fixes a held of

unseasoned pine, my complaint against him is not that he has failed to

exercise reasonable care and skill in carrying out the work but that he has

failed to supply what was contracted for.”

There is no legal requirement for a particular form of contract to be entered

into by a quantity surveyor. The normal rules of the law of contract will apply to any

agreement between a quantity surveyor and his client. The contract is the legal

agreement by which the professional and his client agree their respective rights and

obligations. It may contain express provisions which set out those rights and

obligations relevant to the particular dispute. Alternatively if the contract is silent as

to these obligations the law will treat them as being implied.

Most professional organization produces a standard contract. The scope and

nature of the services to be provided by the quantity surveyor will vary with the

particular projects in order to meet the client’s requirement. To facilitate good

Page 30: quantity surveyor's liability during pre tender stage asmah alia bt

18

working relationship and to avoid misunderstandings a clear agreement is essential.

Such as agreement needs to set out the responsibilities of the Quantity Surveyor, the

client and others as well as the extend of the services to be provided and condition of

payment for that services39.

The most commonly employed form of agreement in Malaysia is the Terms of

Reference the Provision of Professional Quantity Surveying Services40 issued by the

Malaysia Public Work Department, the BQSM/JKR FORM C (Revised 1/83) issued

by the Board of the Quantity Surveyor Malaysia and other government agencies

which come in a number of variations which illustrate the breadth of responsibilities

commonly accorded to quantity surveyor.

The quantity surveyor’s responsibilities are defined clearly in the contract

covering the duties of the quantity surveyor from the pre-tender until the post

contract41. The mentioned Terms of Reference also mentioned the fees charged by the

quantity surveyor based on the scale of Fees42.

In some cases a valid contract exists in unambiguous terms, the court will

enforce it. In the case of Gilbert & Partners v. R. Knights43, the plaintiffs firm of

quantity surveyors agreed for a fee of £30 to arrange tenders, obtain consents for,

settle accounts and supervise certain alterations to a dwelling house on behalf of the

defendant. Initially the work value of some £600 was envisaged but in the course of

alteration the defendant changed her mind and order additional work. In the end, work

valued at almost four times the amount originally intended was carried out, the

40 Refer to Appendix : Terms of Reference the Provision of Professional Quantity Surveying Services

Revision No. 1/2002 (1 November, 2002) 41 Refer to Appendix : Clause 2.0 Scope Of Consulting Services 42 Refer to Appendix : Clause 3.0 Renumaration 43 [1968] 2 AER 248; 4 BLR 9

Page 31: quantity surveyor's liability during pre tender stage asmah alia bt

19

plaintiff continued to supervise throughout and then submitted a bill for £135. This

was met with a claim that a fee of £30 on had been agreed. It was held that the

original agreement was for an all in fee covering all work to be done, the plaintiff was

entitled to only £30.

Ashworth and Hogg44 (2007) suggested that the agreement for appointment of a

quantity surveyor whether a standard or non-standard document, will encompass

certain provisions including the following:

• Form of agreement/particulars of appointment

• Scope of services provided

• Fee details

• Payment procudes

• Professional indemnity insurance requirements

• Assignment

• Suspension

• Copyright

• Duty of Care

• Dispute procedures

According to Farial Hanum Nurul Ain bt Khalid45 (2007), the content46 of

quantity surveyor consulting services consists of:

i. Memorandum of Agreement (MOA),

ii. General condition of engagement of consulting quantity surveyor, 44 Ashworth, A & Hogg, K (2007) Willis’s Practice and Procedure for the Quantity Surveyor 12the

Edition Blackwell Publishing: Britain 45 Farial Hanum Nurul Ain Bt Khalid (2007) Comparison of Consulting Contract,Master of Science

(Construction Management): UTM, Unpublished 46 Refer to BQSM/JKR FORM C (Revised 1/83)

Page 32: quantity surveyor's liability during pre tender stage asmah alia bt

20

iii. Schedule of fess,

iv. Term of reference (TOR)

v. Appendices including the letter of appointment

In the case of Barnett v Cape Town Foreshore Board, an Architect sought an

injunction against the Employer, arguing that there was an implied term that the

Employer could not use only a part of the Architect’s plans, or depart from them,

without his approval, or, alternatively, that the Employer’s action amounted to a

breach of copyright. It was held that neither contention was valid, and that the

Employer was entitled to make such use of the Architect’s services as he saw fit,

provided that proper remuneration was paid.

The Employer is entitled to a professional standard of skill in the discharge of

all the duties necessary until the purpose of the appointment in question has been

achieved. A mere request to act in relation to a project, without specifying at the

outset the services required, will inevitably lead to doubt or dispute as to what are the

respective rights and duties of the parties and it is therefore essential, particularly

when more than one type of consultant is used on the same project, that the purpose

and extent of the respective appointments should be made absolutely clear

2.5. Duties of a Quantity Surveyor At Pre-Tender Stage

By tradition, a quantity surveyor is an agent to his client and performs his

duties based on the implied term under the agency contract between the client and the

quantity surveyor. The role of the quantity surveyor, in general terms, is to manage

and control contracts and costs within construction projects. This involves the

deployment of an extensive set of skills acquired through specialized formal

Page 33: quantity surveyor's liability during pre tender stage asmah alia bt

21

education, specific training and experience47. Jackson Rupert stated that the duties of

a quantity surveyor were judicially described in the last century as,

“taking out in detail the measurements and quantities from plans prepared by

an architect for the purpose of enabling builders to calculate the amounts for

which they would execute the plans.

He also highlighted that the above description is rather anachronistic as a

quantity surveyor’s duties today commonly extend to the preparation of estimates,

bills of quantities, and schedule for pricing by the contractors and negotiation with the

contractor. Ben Patten48 suggested that the nature of the quantity surveyor profession

has changed considerably as nature of the construction industry has changed,

particularly in response to increasing specialization of roles demand under many

modern construction contracts.

Most surveyors have acquired considerable expertise in the use of standard

forms of contract and many architects look to the surveyors with whom they regularly

work for advice and guidance on contractual matters. The surveyor also has a duty to

ensure that all actions taken in relation to the financial administration of the contract

will be fair to both parties49.

The quantity surveyor’s contract usually listed the duties of quantity surveyors

during the pre tender stage. While the duties may be added to or limited in some way

by contract, they are normally as follows:

47 Wikipedia, Quantity Surveyor assessed 2.9.2009 at http://en.wikipedia.org/wiki/Quantity_surveyor 48 Professional Negligence in Construction Pg 72 49 Ramus, Brichall & Griiffths on Contract Practise for Surveyors Pg 5

Page 34: quantity surveyor's liability during pre tender stage asmah alia bt

22

2.5.1 Preparing Preliminary Estimates

During Pre-tender stage, all aspects of the surveyor’s professional work relate

directly to costs of construction work of all kinds. This includes new building and

civil engineering project and the alteration, extension or refurbishment of existing

buildings50.

These estimates are often prepared in the early stages of design and can

influence the Employer as to whether or not he should proceed with the scheme51.

During the production of estimates, care should be taken in reporting of estimates to

indicate the degree of approximation.

The main types of estimate/cost plans encountered in a typical project include,

inter alia the follwing :

• The initial estimate

• The Preliminary Cost Estimate (PDA)

• The Project Cost Plan

• The Pre-tender estimate

As the preliminary design of the Project is being developed, the quantity

surveying shall give advice on cost implications of the design as and when required

by the design team. Upon the finalization of the preliminary design of the project, the

50 Ramus, J, Birchall, S & Griffiths,P (2006) Contract Practise For Surveyors, Fourth Edition,

Butterworth-Heinemann:UK 51 Knowles Roger. Professional Liability of Consultants in the Construction and Engineering Industries.

Unpublished.

Page 35: quantity surveyor's liability during pre tender stage asmah alia bt

23

quantity surveyor shall prepare Preliminary Detail Abstract (PDA)52. When preparing

the preliminary cost estimate, the quantity surveyor usually adapt one of the following

principal methods53:

• Unit of End Product Method

This method employs the unit quantity of the end-product such floor area

(square foot, square metre) and length (per foot run. Per mile)

• Approximate Quantity Method

It is a refinement of the unit of end product method and is used where the

design information is sufficient to enable approximate quantities to be taken

off or measured with reasonable accuracy

When the design is finalized, then the quantity surveyors will proceed with

the preparation of bills of quantity based on actual quantity. Then the tender estimate

will be produced and deemed to be the final costs of the quantity surveyor for the

particular projects before the work on site commence which is known as Pre-tender

estimate. In assessing the cost of works a quantity surveyor must have regard not

merely to the current state of prices and materials but also as to the likely trends in

both54. The quantity surveyor must use the current and updated market rate to avoid

under estimate and must take into account any inflation or price hike in his estimation.

In the event of any breach of obligation or declaration of duty by the

estimators, he can be liable for two possible causes of action:

52 Refer to Appendix : Clause 4.0 Compliance With Government Practice And Procedure 53 See JKR Malaysia, A Guide on the Administration of Public Works Contract [1998] at p 13 cited by

Ir Harban Signh in the Pre Contract Award Practise Book. 54 Refer to Patten Ben, Professional Negligence in Construction Page 78

Page 36: quantity surveyor's liability during pre tender stage asmah alia bt

24

• In contract : By breach of the express or implied of engagement e.g.

the professional services agreement and or

• In tort: By the breach of the duty of care to use reasonable skill and

care in discharging their professional duty and/or in mis-presentation

or negligent misstatement as the case may be55.

2.5.2 Measurement and Preparing Bills of Quantities

.

The bill of quantities was devised and first used in Britain to provide the

building contractor with a method by which he or she could establish in detail the

labour and materials required to construct a building and accurately cost the works56.

Quantity Surveyor will generally be asked to prepare the detailed bill of

quantities and schedules to enable the contractor to tender for the work. A bill of

quantities is prepared by a professional qualified person known as a quantity surveyor

who undertakes extensive training in construction design and contractual aspects of

the building industry57.

Bills of Quantities are contract documents and such have a specific role to

fulfill under the standard form of contract. It is therefore important that they are

55 Refer to Ir Harban Sign in the Pre Contract Award Practise Book. 56 McLagan, D (1991) An Introduction to Building Contracts, The Law Book Company Limited ,

Australia Pg 42 57 Ibid

Page 37: quantity surveyor's liability during pre tender stage asmah alia bt

25

prepared in accordance with the conditions of the contract, contain certain basic

information and are presented in a recognizable format which facilitates their use58.

Bills of quantities were described in the Placing and Management of Building

Contracts (Simon Report,1944) as putting into words every obligation or service

which be required in carrying out the building project. Bills of quantities describe the

work that is to be carried out and establish a rate or price for the item of work. The

bill therefore allows the final measure of work to be valued by simply multiplying the

rate by the quantity of measured work59.

Bills of quantities for building are divided into the following sections60:

i. Preliminaries

ii. Preambles

iii. Measured Works

iv. Prime cost and provisional sums

Bills of quantity are prepared by a quantity surveyor using standard methods

of measurement. The work included in the item is defined in detail by the rules in the

Method of Measurement and based on the format approved by the client and shall be

measured firm. The item descriptions are therefore shorthand to allow the relevant

rules of the Method to be identified. The measure may be a single item or number,

dimension (linear metre, square metre, cubic metre), time (hrs, weeks) or weight61.

58 Refer Johnson Peter et al (1980) Pre-Contract Practise For Architect and Quantity Surveyors 59 Daniel Atkinson. An error of bills at http://www.atkinson-

law.com/cases/CasesArticles/CNewsArticles/CNews_1999_06_03.htm assessed by 1 August 2009 60 Brook, M (2004), Estimating and Tendering for Construction Works 3rd edition, Elsevier: Oxford

Pg51

61Daniel Atkinson. Bills of Quantity at http://www.atkinson-

law.com/cases/CasesArticles/Articles/Bills_of_Quantities.htm assessed by 8 August 2009

Page 38: quantity surveyor's liability during pre tender stage asmah alia bt

26

The purpose of these is to introduce uniformity into the practice of describing

work in bill and to make clear what processes are and what processes are not, deemed

to be included in the items of work which are billed, since every item of work,

however detailed is on analysis a composite item62. In order to prepare bills, therefore

the surveyor must be a master of standard method of measurement and familiar in

every aspect with the scheme of the contract of which are the bills to form part.

In the Malaysian context, the two common standard forms of contract

currently require the quantity surveyor to prepare the measurement based on the

Standard Method of Measurement of Building Works (SMM) sanctioned by

Institution of Surveyors Malaysia.

The SMM in Section A (General Rules) Clause A. 1 stated that the SMM

provides a uniform basis for measuring building works and embodies the essentials of

good practice. It defines and lays down and so standardized the methods or formulae

for actually measuring the quantities of different kinds of building works and in the

process sub-divides the building work into its components parts for purposes of

separate description and pricing in the bills of quantities63.

The Standard Form of contract PWD Form 203A (Rev. 2007) clause 26.4

stated that

“ The Bills of Quantities unless otherwise expressly stated in respect of any

specified item or items, shall be deemed to have been prepared in accordance

with the principles of the Standard Method of Measurement of Building Works

as published by the Institution of Surveyors Malaysia or Civil Engineering 62 See Kishore Gajria Pg 170 63 Institution of Surveyors, Malaysia (2001) Malaysian Standard Method of Measurement of Building

Works Second Edition, ISM : Malaysia

Page 39: quantity surveyor's liability during pre tender stage asmah alia bt

27

Method of Measurement published by Insitution of Civil Engineers (London)

or Method of Measurement as set out in Bill of Quantities.”

Meanwhile in Agreement and conditions of PAM Contract 2006 (with Quantities)

clause 12.1

“…..shall be prepared in accordance with the principles of the Standard

Method of Measurement of building Works sanctioned by the Institution of

Surveyors Malaysia and currently in force.”

The first edition of the Standard Method of Measurement (SMM) was

published in 1922 with the agreement of representatives of the Surveyors’ Institution,

the Quantity Surveyors’ Association, the National Federation of Building Trades

Employers and the Institute of Builders. The situation which existed prior to the

publication of the first edition is perhaps best described in the opening paragraph of

the preface to this historic document:

‘For many years the Surveyors’ Institution and the Quantity Surveyors’

Association were accepted as the recognized authorities for deciding disputed

points in connection with the measurement of building works. The frequency of

the demands upon their services for this purpose directed attention to the

diversity of practice, varying with local custom, and even with the

idiosyncrasies of individual surveyors, which obtained. This lack of uniformity

afforded a just ground of complaint on the part of contractors that the

estimator was frequently left in doubt as to the true meaning of items in the

bills of quantities which he was called upon to price, a circumstance which

militated against scientific and accurate tendering.’

As might be expected, it took several years for the quantity surveying

profession to become aware of the SMM and to use it in practice. The development of

Page 40: quantity surveyor's liability during pre tender stage asmah alia bt

28

more sophisticated standard methods of measurement, whilst desirable in many

respects, has done little to eliminate various types of claim. In Malaysia, the Royal

Institute of Chartered Surveyors (RICS) branch at Malaysia and Singapore had

establish the first edition of SMM for Malaysian use based on fourth edition of British

DMM in 1960. The current SMM use in Malaysia is Standard Method of

Measurement Second Edition (SMM2) which is the revision from the first edition

(Noor Ashikin, 1978).

As a contractual device, although widely used, they have attracted critism

because of the risks they pose to employers by reason of:

“The opportunities they offer in conjunction with standard methods, for

securing pricing advantages because over or under estimates (or failures to

comply with the standard methods) which can be detected in the bills at the

tender stage64”.

Errors in the preparation of bills of quantity are likely to be mundane and for

most part are processing errors-addition or subtraction being incorrect parts of the

specification omitted or double counted. Whilst there are older authorities which

suggest that such errors may occur and not necessarily be negligent65, it is doubtful

whether such an approach would be followed today and as a general rule an error in a

bill of quantities can be said to be prima facie evidence of negligence without the

need for further proof lack of reasonable care66.

In Tyrer v. District Auditor of Monmouthshire67, a quantity surveyor was

found to have acted in breach of duty for approving excessive quantities and prices

64 Hudson’s Building and Engineering Contracts, eleventh edition pg226 65 See London School Board v. Northcroft, Souhthern Neighbour cited in Ben Patten’s page 78 66 Refer to Patten Ben, Professional Negligence in Construction Page 78 67 [1973] 23.

Page 41: quantity surveyor's liability during pre tender stage asmah alia bt

29

with builders not just the arithmetic calculation but because he should have

appreciated that the quantities and rates were excessive.

It is very important for a quantity surveyor to do an accurate measurement.

The taking off is an extraction from the drawings and specifications of all the labour

and material required for the projects. Before starting to take-off quantities, the

quantity surveyor will examine all of the drawings. The quantity surveyor will take a

quick look through the entire set of drawings for an idea of the layout, type of

building, number of floors and general designs and also the order of the drawings.

There are three basic rules for taking off quantities:

i. Measured everything as it shows

ii. Take off everything seen

iii. If it different, keep it separate68

2.5.3 Evaluate tender submission and prepare tender report

Although in the Term of Reference provided by the PWD excludes the duty to

prepare the tender report, but in some projects, the quantity surveyor is responsible to

evaluate and prepare the tender report.

Upon receipt of competitive tenders, they are evaluated and reported to the

client with recommendation and for consideration. The tender evaluation is conducted 68 Foster, N; Trauner T.J; Vespe R.R; Chapman W.M (1995) Construction Estimates From Take Off to

Bid. McGraw Hill : United States of America

Page 42: quantity surveyor's liability during pre tender stage asmah alia bt

30

by the quantity surveyor who checks that the following are in order69. The above

technical check is aimed to ensure that all anomalies are clarifies and agreed before

the client is committed to contract.

Tender evaluation process can be either the following two types70 :

• Single-stage type or

Under this arrangement, either the employer himself or his nominated

representative undertake all aspects of the assessment, i.e. technical and

commercial from initial review until the final recommendation without

incurring activities such as interim recommendations, interview of tenderer etc

which is the hallmark of the more elaborate two-stage evaluation.

• Two-stage type

Two stage- type of evaluation are relatively more commonly encountered in

practice and are by nature the more sophisticated as compared to the single-

stage species addressed before.

The tender evaluation or appraisal is completed by submitting a report to the

client setting out all the actions taken scrutinize, check and correct the tenders and

giving conclusions and recommendations regarding which tender to accepted71. A

tender report contains information on tender evaluation, general technical and

recommendation. The form and contents of tender report varies from project to

project but usually includes the following points72:

69 Kwakye A.A (1997) Construction Project Administration, Longman : England Pg 147 More

explanation on the items to be checked by the quantity surveyor during evaluate the tender. 70 See Ir Harbans Singh Pre Contract Award Practise Pg 476 71 Kwakye A.A (1997) Construction Project Administration, Longman : England Pg 149. 72 Ibid.

Page 43: quantity surveyor's liability during pre tender stage asmah alia bt

31

• Tender sum for which each tenderer is prepared to execute the

construction projects and tender period when this has been an object of

competition

• Arithmetical or inconsistencies found in the lowest tenderer’s bid

• The quantity surveyor’s technical observation on pricing level, method

and policy and quality of pricing

• Details any qualifications to the tender and their financial and contractual

effect on the project.

The surveyor must report to the project manager or the architect and the client

as soon as the examination of tenders is complete. The form of report will vary

according to the nature of the tender documents but usually will include the

following73:

a) The opinion of the surveyors as to the price level i.e that the tender is high,

low or about the level expected

b) The quality of the pricing, indicating any detectable pricing method or

policy

c) The extend of error and inconsistencies in pricing and the action taken in

regard to them

d) The details of any qualification to the tender

e) The likely total cost of the project if not a lump sump contract

f) A recommendation as to the acceptance or otherwise

In other word, a quantity surveyor is involved in giving advice to the client in

deciding which contractor is suitable for the work by analyzing and preparing tender

report. It is important for the quantity surveyor to give the reliable advice to their

client.

73 See Ramus, Birchall & Griffiths, Contract Practise for Surveyors Pg 93

Page 44: quantity surveyor's liability during pre tender stage asmah alia bt

32

In a case of Pratt v. George J Hill Associates, the architect was found liable to

his client for recommending unsuitable contractor for the construction works. In that

case, the contractor becomes insolvent and leaving defective works and the client

unable to recoup the losses from the contractor. The court held that, the architect is

liable to the client for the damages.

According to Ir Harban Singh74, there are no hard and fast rules to follow as

the preferred criteria to be implemented are ultimately for the employer to decide. The

common parameters, however revolve around matters of quality, cost and time. To

these are added a host of other important variables resulting in a general set of criteria

which on a whole may include75:

• Completeness of the tender

• Accuracy offer

• Reasonableness of commercial offer

• Reasonableness of work programme

• Technical conformance

• Capability of tenderer

• Other miscellaneous of relevance e.g alternative offers

2.6. Duties of Quantity Surveyor during Post Contract

Ashworth76 has suggested a list of duties of the quantity surveyor during post

contract stage. Their list of duties consists of the following :

74 Ir Harban Singh K.S (2002) Engineering Construction Contract Management Pre-Contract Award

Practise, LexisNexis : Malaysia 75 Ibid 76 Contractual Procedure in the Construction Industry 4th Edition Pg 205

Page 45: quantity surveyor's liability during pre tender stage asmah alia bt

33

• Valuations for interim certificate

• Final accounts

• Remeasurement of the whole or part of the works

• Measuring and valuing variations

• Daywork accounts

• Adjustment to prime cost sums

• Increased cost assessment

• Evaluation of contractual claim

• Cost analysis

During the construction process under the traditional procurement, a quantity

surveyor will be required to assist the architect by to prepare the interim and final

payament and work to be carried out under proposed or actual variation works.

Depending on the form of construction contract employed his duties may extend

beyond these roles and in any event he is likely to be called upon by the employer to

provide advice as to the overall the projected expenditure and cash flows.

Moreover on very small contract the quantity surveyor may find himself

engaged as contract administrator in lieu of an architect and engineer. In relation to

his valuation functions it is important to keep in mind that unless he is required to do

so by the term of his contract, a quantity surveyor is not obliged to monitor the

progress of the works or give general advice to the employer.

In Aubrey Jacobus & Partners v. Gerrard77, HH Judge Stabb QC said,

“It is suggested that the quantity surveyor was under a duty to monitor or

control the costs and advice the client. I am satisfies that no such duty exists.

The architect is the team leader, he is primarily responsible for design and the

77 [1982] unreported

Page 46: quantity surveyor's liability during pre tender stage asmah alia bt

34

cost for it. If called upon, the quantity surveyor is there to provide information

as to cost but not in my view to monitor or control it by carying out checks at

regular intervals as was suggested”

During this stage a number a surveyor are now involved in the construction

management where the building works are carried out. However, there still remains a

degree of uncertainties was demonstrated in the case of Great Eastern Hotel v. John

laing Co Ltd78 where a construction management project for the refurbishment of a

hotel. The project did not run smoothly with the end result that it exceeded the budget

by nearly 80% and overran by 44 weeks. The client considered that the construction

manager was responsible for considerable portion of delays and extra cost. As a result

of hearing, the court decides was that a professional obligation under its agreement

with the client.

2.7. Quantity Surveyor as an agent to the construction client

It is important to outline the usual position of each in relation to other persons

concern in a building project, in particular the client (a building owner) and the main

contractor. There will be a contract between the client and the contractor and another

contract between the client and the quantity surveyor.

There is no particular law regulating the responsibility of an architect or an

enginner (professional) in his functions as agent of the employer as distinct from or

beyond the general law relating to agency79.

78 [2005] 99 Con LR 45 79 Kishore Gajria(2000) Law Relating to Building and Engineering Contract in Indua Fourth Edition,

Butter worths : India Pg 103

Page 47: quantity surveyor's liability during pre tender stage asmah alia bt

35

Quantity Surveyor acts as one of the agent to the client in the construction

industry. An agency may rise under a contract. Agent is a person who is employed to

do anything in the place of another and the person whom the agent so acts is known as

the principle. In accordance to Contract Act 195080 Section 135 define agent as,

“ a person employed to do any act for another or to represent another in

dealings with third person. The person for whom such act is done or who is so

represented is called the “principle”.”

The quantity surveyor is classified as a special agent whereby he performs

duties for a particular authorized commission or function only81. The rights and

liabilities of the engineer and others concerned with the supervision of building and

engineering works are the same as those agents82.

In the case of Lamphier v. Phipos83 Trindal CJ said:

“Every person who enters a learned profession undertakes to bring to the

exercise of it, a reasonable degree of care and skill; he does not undertake, if

he is an attorney that at all events you shall gain the cause npt surgeon

undertake that he will perform a cure not does the latter undertake to sue the

highest possible degree of skill.”

80 Contract Act 1950 Part X Agency: Appoinment and Authority of Agents 81 Seel, C (1984) Contractual Procedure for Building Students : Holt,RineHart and Winston Ltd :

Oxford Page 79 82 Kishore Ibid. 83 [1838] 8 CP 475

Page 48: quantity surveyor's liability during pre tender stage asmah alia bt

36

Figure 2.1 General Relationship of the agent, the principle and the third parties84

The general function of the agent is to act in behalf of the client and protect his

interest85. He is not the agent of the contractor86. Every agent has certain obligations

towards his principal all the usual duties and in particular he will owe his principle

contractual duties to serve him with reasonable care, skill, diligence and serve with

faithful87. He must display the utmost loyalty and good faith, obey instructions and

attempt not to exceed his authority as mentioned in the section 164 Contract Act 1950

agent is bound to conduct the business of his principal according to the directions

given by the principle.

84 Sources : Hinze, J Construction Contracts Second Edition 85 See R.B Burden Ltd. V Swansea Corporation [1957] 1 W.L.R. 1167 (C.A) at p. 1172 86 See Hosier & Dicinson Ltd v. P&M Kaye Ltd [1970] I W.L.R 1611 (C.A) at p 1615 87 Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell :London Pg 50

Agent

Principle

Third Parties

Agreement for agent to act

on behalf of the principal

Agent negotiates with

third parties on behalf of

the principles.

Assume liabilities imposed by

actions of the agent when

agent has acted within the

scope of the agency

agreement

Page 49: quantity surveyor's liability during pre tender stage asmah alia bt

37

He is expected to utilize reasonable care and skill in fulfilling his duties and he

is obliged to count to his principle or client88. Section 165 Contract Act 1950 stated

that:

“Agent is bound to conduct the business of the agency with as much skill is

generally possesses by persons engaged in similar business, unless the

principal has notice his want of skill. The agent is always bound to act with

reasonable diligence and to use such skill as he possesses and to make

compensation to his principal in respect with of the direct consequences of his

own neglect, want of skill or misconduct but not in respect of loss or damage

which are indirectly or remotely caused by such neglect, want of skill and

misconduct”

In the case of Turpin v Bilton89, defendant owes a duty of care to the principal

to act with due care and skill. The standard of care will depend upon all the

circumstances. A paid agent in a profession is required to exercise the degree of skill

and diligence reasonably to be expected of a person exercising such profession

irrespective of the degree of skill he may possess.

An agent must act with the utmost good faith and loyalty in order to receive a

commission as stated in the case of Andrews’s v Ramsay & Co90 “it is only an honest

agent who is entitled to any commission” Seel, C91 in Contractual Procedure for

Building Students stated the list of obligations for an agent. These may be regarded as

giving corresponding rights to the principal. The agent :

88 Bockrath, J T (2000) Contracts and the Legal Environments for Engineers and Architects 6th Edition,

McGrawHill : United States Pg 273 89 [1843] 5 Man & G 455.58 90 [1903] 2 KB 635, 638 91 Seel, C (1984) Contractual Procedure for Building Students : Holt,RineHart and Winston Ltd :

Oxford

Page 50: quantity surveyor's liability during pre tender stage asmah alia bt

38

i. Must carry out their instruction and notify principle when this is

impossible

ii. Must exercise due diligence and whatever skill they profess

iii. Must act personally

iv. Must act honestly and account for any profit they receive in their

capacity as agent

v. Must account for any bribes or secret commissions and if they take any

may be liable to lose the contract, forfeit their remuneration and be

liable for criminal prosecution

vi. Must keep accounts and render them to their principle when required.

vii. Must not allow their own interests to conflict with those of the

principle

viii. Must not disclose confidential information

ix. Must not delegate performance of their duties to a sub agent without

authorities form the principle.

The relationship of principal and agent gives rise to a fiduciary duty on the

part of the agent. This arises because the relationship is one of trust, even though not a

relationship of trustee and beneficiary. The general principle is that the agent must not

let his own personal interest conflict with the obligations he owes to his principal.

This is an equitable duty, and is variously described. Conflict of interest must be

avoided eg - unless the agent has the consent of the principal, he must not make use

Page 51: quantity surveyor's liability during pre tender stage asmah alia bt

39

for his own personal benefit of information acquired in the course of his employment

as agent92.

In the Malaysian case of Cheng Keng Hong v. Govertment of The Federation

of Malaya93, the arbitrator held that under s 190 of the Contract (Malay States)

Ordinance 1950:

“ When agents has without authority done acts or incurred obligations to third

person on behalf of principal, the principal is bound by such acts and

obligations if he has by his words or conduct induced such third persons to

believe that such acts and obligations were within the scope of the agent’s

authority and that the architect’s assurance therefore bound the government.”

2.8 Professional liability

It is a precept of English law that if one man suffers loss or damages through

the negligent act of another then his remedy is in damage at law. It is another precept

that if a man holds himself out to be an expert, the standards to be applied to a

layman94.

However, it is important to determine the nature of the legal duties which the

professionals owe to their client or to other persons. Similarly in order to appreciate

the extend to which any particular professional might be held liable to pays damages 92 See Boardman v Phipps (1967), IDC - v - Cooley (1972) 93 [1966] 2 MLJ 33 (Malaysia) 94 Cecil Ray (1986) Professional Negligence, the Architecture Press: London

Page 52: quantity surveyor's liability during pre tender stage asmah alia bt

40

to a client or some other person it is necessary to understand the broad outlines of the

ways in which the law deals with issue of causation and compensation. It almost all

cases of professional negligence dispute between construction professionals and their

client the extend of professional legal obligations to the client are governed by his

contract with the client95.

2.8.1 Nature of the liability

Definition of liability in Osborne Concise Law Dictionary is ‘an amount

owed; or subject to legal obligation; or the obligation itself, he who commits a wrong

or break on a contract or trust is said to be liable or responsible for it’.

Similarly indicated in Dictionary of English Law96, liability is defined as

potentially subject to obligation, either generally as including every kind of obligation

or in more special sense to denote inchoate, future unascertained or imperfect

obligation, as opposed to debt, to essence of which is that they are ascertained and

certain. Liability is a present obligation of the enterprise arising from past events, the

settlement of which is expected to result in an outflow from the enterprise of

resources embodying economic benefits

A situation in which one party is legally obligated to assume responsibility for

another party's loss or burden. Liability is created when the law recognizes two

elements ‘the existence of an enforceable legal duty to be performed by one party for

95 Patten B (2003) Professional Negligence in Construction Spon Press: London Pg 4 96 Sinha & Deeraj (2000) Legal Dictionary 2nd Edition ILBS: Reprinted Edition Malaysia

Page 53: quantity surveyor's liability during pre tender stage asmah alia bt

41

the benefit of another' and the failure to perform the duty in accordance with

applicable legal standards97.

Furthermore, Frank (1988)98 noted that in law, a person may owe a duty to

another person by his own free will in a Contract or by the operation of common law

of tort. The failure to perform or negligently perform these duties or responsibilities

constitute a breach, therefore he or she will be answerable or accountable to the other

party who may have suffered as a result of his/her wrongful act.

According Siddharaj (1996)99, the main element in liability is duty and

responsibility. The duty and responsibility of the various parties in a construction

project may arise from contract or law of tort or both. It is also very much associated

with the interrelationship between them and the scope and nature of services they

provided in the project.

2.8.2 Theories of liability

In a case of Bodin v. Gill100, in which the court stated the broad rule of law

which applies to not only architects and engineers but other professional services. The

court stated that “The law imposes upon persons performing architectural,

97 Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell: London 98 Frank E. and James A. (1988). Building Subsidence: Liability and Insurance. London: Oxford

BSP Professional Books.

99 Siddharaj V. S. Param. (1996). Negligence and the Duty of Care in the Construction Industry: A

Malaysia Analysis. Workshop Papers. Kuala Lumpur: Institute of Professional Advancement. 100 117 S.E.2d 325

Page 54: quantity surveyor's liability during pre tender stage asmah alia bt

42

engineering, and other professional and skilled services the obligation to exercise a

reasonable degree of care, skill, and ability, which generally is taken and considered

to be such a degree of care and skill as, under similar conditions and like surrounding

circumstances, is ordinarily employed by their respective professions.” However, the

standards of care and the proof required differ.

According Marianne (2005)101, depending on jurisdiction, plaintiffs can sue on

any one or a combination of the following theories of liability, each with differing

types and calculations of recovery:

a. Strict liability or Negligence Per Se (i.e., violation of building code or

other law)

b. Negligence (i.e., in the exercise of a reasonable degree of care, skill

and knowledge ordinarily employed by such building professionals)

c. Breach of Contract (i.e., as set forth in the purchase and sale

documentation)

d. Breach of Implied or Express Warranty (i.e., that the completed

structure was designed and constructed in a reasonable workmanlike

manner and usable for its intended purpose)

e. Fraud (Intentional Misrepresentation) and Negligent Misrepresentation

(i.e., on the grounds that the developer or property manager

intentionally misrepresented the quality of construction in false

statements and/or advertisements)

101 Marianne, J. (2005). Building defects spoil homeowners’ dreams. Portland: The Oregonian News.

The Aldrich Law Office, P.C. 522 SW 5th Avenue.

Page 55: quantity surveyor's liability during pre tender stage asmah alia bt

43

f. Breach of Fiduciary Obligation (i.e., that directors and/or officers of

homeowners’ associations have failed to adequately protect their

residents’ rights or interests)

g. Negligent and intentional infliction of emotional distress (i.e., that, as a

result of a given action or defective condition, the homeowner has

suffered emotional distress)

h. Nuisance (i.e., loss of enjoyment and use of property as a result of a

defective condition)

i. Products Liability (i.e., claims of a defective condition in installed

components)

A design professional can limit liability to a client largely through the contract

between the design professional and the client. The primary relationship between the

design professional and his or her client is one of contract. Yet, ambiguities are

common in contract language and a contract will often not protect against a

negligence suit or third party liability (e.g., flooding of an adjacent landowner). The

primary test for determining whether the design professional has adequately

performed his or her design duties for the client is conformance with terms of the

contract. The contract typically sets forth the design professional’s duties and, to a

lesser extent, how they are to be carried out. Contract standards, where vague, are

supplemented by terms furnished by law and oral understandings102.

102 Kulser J (2007) Professional liability for Construction in Floor Hazard Area, ASFPM Foundation :

Page 56: quantity surveyor's liability during pre tender stage asmah alia bt

44

2.8.3 Professional liability

Professional liability is the exposure one is subjected to when one is found

deficient in performing professional services. Supported by Gill103, he suggested that

the professional are bound to possess a reasonable amount of skill in the art or

profession they exercise for reward and to use a reasonable amount of care and

diligence in the carrying out of work which they undertake. Every person who enters

into a profession undertakes to bring to exercise of it a reasonable degree of care and

skill104.

As quoted by Wan Basiron in his writing105, performance is gauged by the

prevailing standard of care what is reasonably prudent to expect a quantity surveyor to

do under the facts and circumstances surrounding the projects. The standard changes

from time to time and from place to place. It means what is acceptable practice today

may be not acceptable tomorrow, vice versa. As a result, professional constantly

reevaluate their performance to ensure must compliance with the prevailing standard

of care.

John L. Powell106 in his article strongly suggested that, is summated the sea

change in the attitude of society and indeed the courts towards professionals when

things go wrong. Professionals and their insurers will need to adapt accordingly.

In a claim for negligent design against an architect arising from the collapse of

a concrete roof, Erle J. in 1853 said:

103 Enden and Gill’s Building Contracts and Practise. Seventh Edition Page385 104 Lanphier v. Phipos [1838] 8 C & P 475-479 (surgeon) 105 The Architect’s Duty of Care in Respect of Design to Third Parties. Unpublished thesis. UTM 106 John L. Powell. Professional Negligence the Changing Coastline of Liability at

http://www.4newsquare.com/Files/PDF/Article/JP%20article.doc assessed on 1 October 2009.

Page 57: quantity surveyor's liability during pre tender stage asmah alia bt

45

"... if you employ [an architect] about a novel thing, about which he has little

experience, if it has not had the test of experience, failure may be consistent

with skill. The history of all great improvements show failure of those who

embark in them"107.

The claim failed.

Contrast this with Lord Edmund Davies's observation in 1980 in a negligent

design case arising from the collapse of a television transmitter mast, reflective of a

more consumer orientated society:

"The law requires even pioneers to be prudent"108.

The claim succeeded.

According Jackson and Powell (1987)109, the professions operate in spheres

where success cannot be achieved in every case. Very often success or failure

depends upon factors beyond professional man’s control. Even where the critical

factors are within the professional man’s control, he still cannot guarantee success.

107 Turner v Garland and Christopher (1853) cited in Hudson's Building Contracts (4th ed., 1914) Vol.

2, p. 1. 108 I.B.A. v E.M.I. and B.I.C.C. (1980) 14 Build. L.R. 1 (H.L.) at 28. 109 Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell: London

Page 58: quantity surveyor's liability during pre tender stage asmah alia bt

46

The problem which the courts have faced in devising a rational approach to

professional liability110 is that they must provide proper protection for the consumer.

Broadly speaking, the solution which has been found is to require that professional

men should possess a certain minimum degree of competence and that they should

exercise reasonable care in the discharge of their duties. In Lamphier v Phipos111 (a

medical negligence case tried in 1838) Tindal C.J directed the jury in these terms:

“Every person who enters into a learned profession undertakes to bring to the

exercise of it a reasonable degree of care and skill. He does not undertake, if

he is an attorney, that at all events you shall gain your case nor does a

surgeon undertake that he will perform a cure nor does he undertake to use

the highest possible degree of skill.”

In Greaves & Co. v Bayham Meikle112, Lord Denning M.R. stated:

“Apply this to the employment of a professional man. The law does not

usually imply a warranty that he will achieve the desired result, but only a

term that he will use reasonable care and skill. The surgeon does not warrant

that he will cure the patient. Nor does the solicitor warrant that he will win

case.”

Barros (1989)113 noted that the degree of success expected from different

professions may vary. Thus, the professional man as defendant enjoys a privileged

110 Liability must, of course, be established on balance of probabilities. In Bater v Bater [1951] P. 35 Denning L.J. said: “So also in civil cases, the case may be proved by a preponderance of probability, but there may be degrees of probability within that standard. The degree depends on the subject matter… The degree of probability which a reasonable and just man would require to come to a conclusion” 111 [1938] 8 C & P 475 112 [1975] 1 WLR 1095 113 Barros. A. A. J. (1989). Professional Liability and Construction. England: Chartered Institute Of

Building Englemere, Kings Ride, Ascot, Berkshire SL5 8BJ

Page 59: quantity surveyor's liability during pre tender stage asmah alia bt

47

position. His privileged position has been eroded in certain respects by developments

in the law of contract and tort.

2.8.4 Professional Liability in Contract

The word ‘contract’ may be defined as ‘an agreement enforceable by law’.114

In Malaysia the contract Act 1950 under section 2 (h) holds a contract to be ‘an

agreement enforceable by law’ 115.

As stated by Jackson and Powell (1987)116, the law of contract is the principal

means by which the courts have exercised control over the conduct of professional

men. In most instances there is a contract between the professional man and his

client, whereby the former agrees to render certain services and the latter agrees to

pay.

Davies (1989)117 noted that contractual liability arises from breach of duty

imposed by the terms and conditions of the contract entered into by the parties

concerned. In such a contract there is generally implied by law a term that the

professional man will exercise reasonable skill and care118.

114 Section 2(b), Contract Act 1950 115 Act 136 116 Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell: London 117 Davies, C.M. (1989). Avoiding Claims: Practical Guide for the Construction Industry. Great

Britain: St. Edmundsbury Press Ltd. 118 This common law principle is now embodied in s.13 of the Supply of Goods and Services Act 1982.

Page 60: quantity surveyor's liability during pre tender stage asmah alia bt

48

When the professionals are appointed by the client, the duties are covered by

the contract between the client and themselves. Sometimes the contract conditions are

set out in a formal document whilst quite frequently the appointment is made by way

of a brief letter or even orally. In the absence of formal conditions, the professional’s

liability in contract will implied by law.

When a professional person provides a service such as the design of a

building, in the absence of an express provision the professional liability is limited to

using all reasonable skill and care. Whether the professional has used all reasonable

care and skill is established by applying the test found in Bolam v. Friern Hospital

Committee119 as cited by McNair J.

‘……Where you get a situation which involves the use of some special skill or

competence…the test is the standard of the ordinary skilled man exercising

and professing to have a special skill. A man need not possess the highest

expert skill at risk of being found negligent. It is well established law that it is

sufficient if he exercised the ordinary skill of an ordinary competent man

exercising hat particular art.”

In the quantity surveyor’s contract, one of the duties is to provide the initial

estimate of the likely cost of the work. There is obviously a duty of care required on

the part of the quantity surveyor when preparing these estimates. In this recent case of

Nye Saunders and Partners v. Alan E Bristow120, the Architect omitted to include for

inflation in his estimate or to mention that no allowance had been made. When

tenders were received they were well in excess of the estimate due to the effects of

inflation in the intervening period. The client decided not to proceed with the scheme

and was held to be entitled to refuse to pay Architect’s fees.

119 [19 120 [1987] 37 BLR 92,53,56

Page 61: quantity surveyor's liability during pre tender stage asmah alia bt

49

Oliver J pointed out in Midland Bank v. Hett, Stubs & Kemp121 the obligation

to exercise reasonable skill and care is not only contractual term which ought to be

considered in a professional negligence action :

“The classical formulation of the claim in this sort of case as ‘damages for

negligence and breach of professional duty tends to be a mesmeric phrase. It

concentrates attention on the implied obligation to devote to the client’s

business that reasonable care and skill to be expected from a normally

competent and careful practitioner as if that obligations were not only a

compendious but also an exhaustive, definition of all duties assumed under the

contract created by the retainer and its acceptance. But of course it is not. A

contract give rise to a complex of rights and duties of which the duty to

exercise reasonable care and skill is but one”

“If I employ a carpenter to supply and put up a good quality oak shelf for me,

the acceptance by him of that employment involves the assumption of a

number of contractual duties. He must supply wood of an adequate quality

and it must be oak. He must fix the shelf. And must carry out the fashioning

and fixing with reasonable care and skill which I am entitled to expect of a

skilled craftsman. If he fixes the brackets but fails to supply the shelft or if he

supplies and fizes a shelft of unseasoned pine, my complaint against him is not

that he failed to exercise reasonable care and skill in carrying out the work

but that he has failed to supply what was contracted for.”

In the case of Kirkwood v Morrison, the judge said:-

121 [1979] Ch 384

Page 62: quantity surveyor's liability during pre tender stage asmah alia bt

50

“The measurement was made it seems, by sworn measurers or skilled persons

in their employment. It is not understood that in every instance the sworn

measurer, who may be the head of an extensive business, goes himself to the

ground, in place of sending a skilled assistant to report to him the details, he

adopting the result if it appears to him satisfactory and accepting the

responsibility.”

2.9 Standard of Care

It is the duty of a professional in performing professional services for a client

to have that degree of learning and skill ordinarily possessed by reputable peers

practicing in the same or similar locality and under similar circumstances. It is the

professional's further duty to use the care and skill ordinarily used in like cases by

reputable members of the profession practicing in the same or similar locality under

similar circumstances and to use reasonable diligence and best judgment in the

exercise of professional skill and in the application of learning, in an effort to

accomplish the purpose for which he was employed.

The Quantity Surveyor’s obligation is to exercise the degree of care, skill and

knowledge that is generally expected within the profession just like other

professionals. The Canadian Law of Architecture & Engineering, 2nd ed., sets out the

genrally-accepted professional standard of care for a consultant working on a

construction project:

“Unless expressly stated in the contract of professional services in all the

work done for the client, the architect or engineer owes a duty to exercise the

Page 63: quantity surveyor's liability during pre tender stage asmah alia bt

51

skill, care and diligence which may reasonably be expected of a person of

ordinary competence, measured by the professional standard of time.

…[A]rchitects or engineers are not obliged to perform to the standards of the

most competent and qualified members of the profession, unless they so

covenant. Unless they undertake to exercise a higher standard of care, what is

required of architects or engineers is reasonable skill, care and diligence as

judged generally by standards of competence in the profession in which they

practice…[Further],architects and engineers do not guarantee that their work

will successful. Provided that they have exercised reasonable judgement,

competence and diligence in doing the work, the fact that the work proves

unsatisfactory in some way will not render them liable to the client for breach

of contract and negligence122.

The duty arises not only as an implied (if not express) term of the contract

between the professional man and his client. It may also arise in tort. So a

professional may owe a duty of care to his client running concurrently with the like

duty in contract. He may also owe a duty of care in tort to a third party. Breach of the

tortious duty gives rise to liability in the tort of negligence.

A failure to fulfill any such duty is negligence. In Greaves & Co v Baynham

Meikle123 case, Lord Denning MR :

“ Although the judge talked about ‘the higher duty’, I feel sure that what he

meant was that in the circumstances of this case special steps were necessary in order

to fulfill the duty of care..” 122 B.M McLachlin, W.J Wallace & A.M Grant, The Canadian Law of Architecture & Engineering, 2nd

ed. (Toronto: Butterworths,1994) at 101-102 123 [1975] 1 WLR 1095

Page 64: quantity surveyor's liability during pre tender stage asmah alia bt

52

The standard of care of professionals in Greaves’ case has been cited by the

High Court of Malaysia in Hanafiah, Raslan, Mohamed & Partners v Weng Lok

Mining Co Ltd124 by Chang Min Tat J at pg 250.

The relevant standard of care of reasonable care and skill in giving advice is

reiterated in George Hawkins v Chrysler (UK) Ltd & Burne Associates125, where

Dillon LJ at 54 held:

“In this Court we are bound by the established rule that a professional man, as

in Greaves, only undertakes, when his advice is sought, to use reasonable care

and skill in his profession, and does not warrant the accuracy of his advice in

the absence of special circumstances”.

This is further affirmed by Neil LJ in his finding at 55:

“I have come to the firm conclusion, however, that it is not open to this Court,

except where there are special facts and special circumstances, to extend the

responsibilities of a professional man beyond the duty to exercise reasonable

skill and care in conformity with the usual standards of his profession. There

are many authorities which establish that this is the accepted duty of a

professional man.

In England, the House of Lords has adopted as definitive, in the case of

professional people generally, the following direction to a jury by McNair J in a case

124 [1977] 1 MLJ 249 125 [1986] 38 BLR 40

Page 65: quantity surveyor's liability during pre tender stage asmah alia bt

53

of Bolam v Friern Hospital Management Committee126

"Where you get a situation which involves the use of some special skill or

competence ... the test is the standard of the ordinary skilled man exercising

and professing to have that special skill. A man need not possess expert skill ...

it is sufficient if he exercises the ordinary skill of the ordinary competent man

exercising that particular art."

Similarly, in the case of City of Mounds View v. Walijarvi127

"Architects, doctors, engineers, attorneys and others deal in somewhat

inexact sciences and are continually called upon to exercise their skilled

judgment in order to anticipate and provide for random factors which are

incapable of precise measurement. The indeterminate nature of these factors

makes it impossible for professional service people to gauge them with

complete accuracy in every instance. Thus, doctors cannot promise that

every operation will be successful; a lawyer can never be certain that a

contract he drafts is without latent ambiguity; and an architect cannot be

certain that his structural design will interact with natural forces as

anticipated. Because of the inescapable possibility of error which inheres in

these services, the law has traditionally required, not perfect results, but

rather that exercise of that skill and judgment which can be reasonably

expected from similarly situated professionals ... Until the random element is

eliminated in the application of architectural sciences, we think it fairer that

the purchaser of the architect's services bear the risk of such unforeseeable

difficulties."

126 [1957] 1 WLR 582 13,76 127 263 NW2d 420 (Minn. 1978)

Page 66: quantity surveyor's liability during pre tender stage asmah alia bt

54

2.10 Reasonable Skill and Care

In the vast majority of cases where allegations of professional negligence are

made against construction professional liability will depend upon whether the

professional exercised ‘reasonable skill and care’128 The general principles are set out

by McNair J in the medical negligence case of Bolam v. Friern Hospital Management

Committee129 :

“Where you get a situation which involves the use of some special skill of

competence…. the test is the standard of the ordinary skilled man of exercising and

professing to have that special skill. A man need not possess the highest expert skill at

the risk of being found negligent. It is well established law that it is sufficient if he

exercises the ordinary skill of ordinary competent man exercising that.”

Supported by Evans (1979)130 the standard of care required in the particular

situation needs to be establish. In Heaven v Pender131, Brett MR held that a duty of

care exists in normal circumstances whereby if a person does not take usual degree of

precaution another person or his property may be injured or damages.

In the dictum of Alderson B. in Blyth v Birmingham Waterworks Co132:

‘Negligent is the omission to do something which a reasonable man, guided

upon those consideration which ordinarily regulate the conduct of human

128 Patten B (2003) Professional Negligence in Construction Spon Press : London Pg 5 129 [1957] 1 WLR 582 at 586 130

Evans, R. and Galbraith, A. (1979). Revision Notes on Building Law. London: Newnes –

Butterworths. 131 [1883] 11 QBD 503 132 [1856] 11 Ex. 781, 784

Page 67: quantity surveyor's liability during pre tender stage asmah alia bt

55

affairs, would do, or doing something which a prudent and reasonable man

would not do.’

In Vaughan v. Menlove133 is a famous English tort law case that first

introduced the concept of the reasonable man in law. The reasonable person standard

hold each persons owes a duty to behave as a reasonable person would under the same

or similar circumstances134.

The ordinary skill requirement skill was approved by the House of Lords in

Saif Ali v Sydney Mitchell & Co(1980) as the test for all professional people. In this

case it was said that:

“No matter what profession it may be, the common law does not impose on

those who practice it any liability for damage resulting from what in the result

turn out to have been errors of judgement, unless the error was as no

reasonably well informed and competent member of that profession could

have made”

In a cases where a human actor is a professional and is acting within her

capacity, the reasonable person under the circumstances test becomes elevated to a

standard whether a person acted how a reasonable professional under the

circumastances would have, regarless of they are actually a professional or not135.

In addition, it must be noted that, on the other hand, in setting the standard of

skill and care to be expected of professionals, the courts do not differentiate between 133 [1837] 3 Bing N.C 467,132 E.R 490 (C.P) 134 Brown v. Kendall [1850] 60 Mass 292 135 Heath v. Swift Wings, Inc 252 SE 2d 256 (NC App 1979)

Page 68: quantity surveyor's liability during pre tender stage asmah alia bt

56

those professionals at the height of their profession carrying out substantial multi-

million-dollar contracts and those engaged at a more mundane level, perhaps in

relation to very low-budget projects136. This is because the courts view each case on is

merits and decide whether the professional fell below the requisite standard care in

that case.

Barros (1989) noted that the degree of success expected from different

professions may vary. Thus, the professional man as defendant enjoys a privileged

position. His privileged position has been eroded in certain respects by developments

in the law of contract and tort.

In Eckersly v. Binnie & Partners137 in a passage which could be applied

equally to any construction professional, Bingham LJ commented on the required

standard of performance for consulting engineer thus:

“A professional man should command the corpus of knowledge which forms

part of the professional equipment of the ordinary member of his profession.

He should not lag behind other ordinarily assiduous and inttilegent members

of his profession in knowledge of new advances, discoveries and developments

in his field. He should be alert to the hazards and risks inherent in any

professional task he undertakes to the extend that other ordinarily competent

members of the profession would be alert. He must bring to any professional

task he undertakes no less expertise, skill and care than other ordinarily

competent members would bring but need bring no more. The standard is that

of the reasonable average. The law does not require of a professional man

that he be a paragon combining the qualities of polymath and prophet”.

136 See for example Wimpey Construction UK Ltd v. Poole [1984] 2 Lloyds Rep 499 137 [1988] 19 Con LR 1.

Page 69: quantity surveyor's liability during pre tender stage asmah alia bt

57

2.11 Professional Negligence

In the legal Dictionary by Sinha & Dheeraj138, negligence is defined as a

“failure to use the amount of care which under the special circumstances of the case, a

reasonable man would use. In contract, negligence in carrying out the terms may

amount to a breach”.

In English Law of Tort, professional negligence is a subset of the general rules

on negligence to cover the situation in which the defendant has represents him or

herself as having more than average skills and ability139. Alderson B in the case of

Blyth v Birmingham Waterworks Co140 defined negligence as

“Negligence is the omission to do something which a reasonable man, guided

upon those considerations which ordinarily regulate the conduct of human

affairs, would do or doing something which prudent and reasonable man

would not do.”

By virtue of the services they offer and supply, professional people hold

themselves out as having more than average abilities. This specialized set of rules

determines the standards against which to measure the legal quality of the services

actually delivered by those who claim to be among the best in their fields of

expertise.

As discussed previously, the standard contract is employed by quantity

surveyor and client in the performance of their duties. On the basis of contract which 138 Sinha & Deeraj (2000) Legal Dictionary 2nd Edition ILBS: Reprinted Edition Malaysia 139 Refer to http://en.wikipedia.org/wiki/Professional_negligence_in English_Law 140 [1856] 11 Exch 781 at p 784

Page 70: quantity surveyor's liability during pre tender stage asmah alia bt

58

the plaintiff have asserted in the statement of claim, the views of Charlesworth &

Percy141 are relevant.

A duty to take care can be imposed by law or can be created by contract or

trust. The breach of the contractual duty to take care, however, is not negligence in the

sense in which the word is now being used. It is not uncommon to speak of the

negligent performance of a contract but that in that case, the word ‘negligence’ is used

in the second meaning explained above for example in the sense of careless but it is

now well recognized that breach of a contractual duty must be dealt with according to

the law of contract and cannot be regarded as tort of negligence.

The consequences of the problems resulted from negligence act or as a breach

of duty to take care resulting damage to another can be severe in both human and term

of cost.

Powell and Jackson (1987)142 stated that an award of damages is the normal

remedy sought for breach of duty by profession man in certain circumstances he may

be deprived of his fees. Recovery of damages is subjected to the overriding

requirement that loss and damage for which compensation is sought is not too remote.

Broadly this requirement demands that the loss or damage must have been:

a. Caused by the breach of duty and

b. Foreseeable and not precluded from being compensatable by consideration

of public or social party

141 Charlesworth & Percy (1998) Negligence (9th Edition) Sweet & Maxwell Ltd : London Pg 12

142 Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell: London

Page 71: quantity surveyor's liability during pre tender stage asmah alia bt

59

The fundamental principle under laying the award of damages is to put the

injured party in position he would have been in had the breach of duty not occurred,

so far as this can be done by the award of money143.

Furthermore, Evans (1979)144 emphasized that the main remedy provided by

English Law is damages. This is monetary compensation to cover the injury suffered

so afar as money is able to compensate. And he added that the damages may be

classified as liquidate and unliquidated.

a. Liquidated

Where the liquidated damages are whenever amount claimed can be

ascertained by calculation or fixed by a scale it is said to be ‘liquidated’. Often

contracting parties will make provision for sum to be paid in event of breach of

contract.

b. Unliquidated

An award assessed to put the injured person, insofar as money can do so, in as

good a situation as he would have been had he not been injured or had the contract

been properly performed.

143 See Ben Patten on Professional Negligence Pg 15 144 Evans, R. And Galbraith, A. (1979). Revision Notes on Building Law. London: Newnes –

Butterworths.

Page 72: quantity surveyor's liability during pre tender stage asmah alia bt

60

CHAPTER 3

ANALYSIS CASE : LIABILITY OF QUANTITY SURVEYOR DURING

PRE-TENDER STAGE

3.1 Introduction

Claims for professional negligence are now common. Indeed they will become

more so. This will be a product of increasing demand for their services, specialisation,

higher standards and intolerance of bad performance by highly educated societies145.

Quantity surveyor can be liable for the damages suffered by the client146 due to

the negligence in preparing documents, negligence in preparing estimates and was

found liable to client for recommending the unsuitable contractor for the construction

works147.

145 John L. Powell . Professional Negligence The Changing Coastline Of Liability at

http://www.4newsquare.com/Files/PDF/Article/JP%20article.doc assessed on 1 October 2009. 146 Refer to case Bains Harding Construction & Roofing (Aust) Pty Ltd v. McCredie Richmond &

partners Pty Ltd 147 Refer to case Pratt v. George J Hill Associates

Page 73: quantity surveyor's liability during pre tender stage asmah alia bt

61

In J Jarvis & Sons Ltd v Castle Wharf Developments Ltd, Gleeds Management

Services Ltd & Franklin Ellis Architects Ltd, the Lord Justice Gibson, in giving the

leading judgment of the court, recognized that historically there has been judicial

reluctance to impose duties of care on a professional agent acting within his authority

in the tendering process.

It follows that the standard to be applied is generally the standard recognized

to be good practice in the relevant profession. It has long been held that if a consultant

acts negligently in the performance of his duties, and the employer suffers loss as a

result, then the employer would have a claim for damages against the consultant under

the .

The court would hear expert evidence from both parties as to good practice in

the professions of architect and engineer and the correct approach to be taken by

either professional to working with professionals of another discipline. The judge

would consider the conflicting expert testimony and decide which he preferred that is,

which was the more cogent and authoritative. Occasionally he will find none of the

experts entirely persuasive and will formulate a decision which is somewhere between

the positions they adopt. Consequently it will be immediately apparent that expert

evidence plays a crucial role in professional negligence actions against

professionals.148 Quantity Surveyor can also be sued for damages arising from this

negligence.149

However, it should be noted that in deciding whether a professional exercised

reasonable skill and care the court is not merely balancing the views of the

professionals whom the parties have called to give expert evidence. There are well 148 Ben Pattern on Professional Negligence In Construction (2003) 149 Wearne Stephen (1989) Civil Engineering Contracts : An introduction to construction contract MHL

Typesetting Limited : Great Britain

Page 74: quantity surveyor's liability during pre tender stage asmah alia bt

62

established considerations which govern the meaning of reasonable skill and care. The

first of these is that the professional is not judged upon his actual expertise but the

expertise of an ordinarily competent member of his profession. Consequently a trainee

quantity surveyor who carries out some of the functions of a quantity surveyor will of

generally be judged by the standard of a trainee, but of a qualified and indeed

ordinarily experienced quantity surveyor150.

3.2. Duties to prepare the cost estimate during pre-tender

Normally, based on the architect’s and engineer’s design, the quantity surveyor

will provide a project cost estimate to the client. This cost estimate will be an

important tool for a client to make a decision whether to proceed or to postpone the

project.

3.2.1 Preparing estimate with reasonable care

The quantity surveyor is required to exercise care in preparing the estimate

and to give an alarm to the client on the uncertainties of the cost. In the Contract Act

1950 section 167, one of the duties of the agent is to communicate to the principle any

information in relation to the principle business. It is the duty of the professional to

inform and warn the client.

150 Jackson R.M. and Powell J.L., Professional Negligence (5th edition)

Page 75: quantity surveyor's liability during pre tender stage asmah alia bt

63

The professional must also asked for an estimate of the cost of the proposed

work, they should give an honest and careful estimate151. In Moneypenny v

Hartland,152 the employer refused to pay the engineer’s fees since the actual cost of a

project greatly exceeded the engineer’s estimate. The estimate is shown by tenders to

be excessively low then he is in breach of an implied term of his agreement and can

be dismissed without recompense. The court expressed the general rule to be in these

words:

“Supposing negligence or want of skill to be sufficiently made out, unless that

negligence or want of skill has been to the extent that has rendered the work

useless to the defendants, they must pay him and seek their remedy in a cross-

action”

“A man should not estimate a work at a price at which he would not contract

for it; for if he does, he deceives his employer… If a surveyor delivers an

estimate greatly below the sum at which a work can be done, and thereby

induces a private person to undertake what he would not otherwise do, then I

think he is not entitled to recover; and this doctrine is precisely applicable to

public works. There are many in this metropolis which would never have been

undertaken at all, had it not been for the absurd estimates of surveyors”.

Cost underestimation is defined as the act of assessing the cost of a future lower

than what actual cost turned out to be once the venture was implemented. Cost

underestimation causes cost overrun153 where, in example an engineer was held

negligent in failing to examine the nature of the soil in which to place foundations for

a bridge. Cost of construction was grossly underestimated.

151 Moneypenny v Hartland [1826] 2 C & P 378, Columbus Co v. Clowesc[1903] 1 KB 244 152 [1826] 2 C & P 378, 153 Refer to Flyvbjerg B, Holm M S & Buhl S (2002) Underestimating Costs in Public Works Projects

Error or Lie? APA Journal Vol 68 No 3Pg 279 assessed at http://

Flyvbjerg.plan.aau.dk/JAPAASPUBLISHED

Page 76: quantity surveyor's liability during pre tender stage asmah alia bt

64

The allegation for underestimate by the professional can be in the case of

Gordon Shaw Concrete Products Ltd v. Design Collaborative154. Defendant Design

Collaborative Ltd., an architectural firm was instructed to see if such a home could be

built for approximately $60,000 and, if it did seem feasible, to provide the final

drawings and specifications for such dwellings. For this purpose the parties entered

into a standard form architectural contract. The preliminary design report, when

submitted a few months later, estimated a building cost of $60,144. But when the final

drawings were submitted, and estimates of true prospective cost solicited, it transpired

that the design could not be implemented for less than $100,000, and perhaps much

more. The appeal was dismissed. Nova Scotia Supreme Court, Appeal Division held :

“In preparing and submitting an estimate of construction cost, an architect

was bound to do more than just submit a rough guess as to the cost of the job;

the estimate must bear some relation to reality, and reflect a competent

professional judgment. In view of the gross disparity between its estimate of

cost and the ultimate cost of implementing this design, the architectural firm

had failed to discharge that duty.”

“While a clause (cl. 4) in the agreement provided expressly that the architects

did not warrant the accuracy of their estimates, that clause did not even

purport to exonerate them from liability for negligence; and accordingly

afforded no defence.”

The mentioned Gordon’s case is where the building professional failed to

produce a design with the reasonable cost. The architect was held failed to perform

his duties to prepare a design and an accurate based on the client’s requirement. The

architect, who has enter a contract with the client must perform his job with care and

carefully prepare the design and estimate in accordance with the given budget.

Although the exemption clauses has been set out in the agreement, but in according to

154 [1986] CarswellNS 104

Page 77: quantity surveyor's liability during pre tender stage asmah alia bt

65

the court judgement, the clauses does not free them from the liability where the client

suffer the damages due to the negligence act by the architect. In relation to the

quantity surveyor duties, he must work closely with the designers in preparing the

estimate to make sure that the estimate that he produces is not beyond the client’s

budget. It is stated in the standard retainer the quantity surveyor must prepare the

estimate with care for his client.

In Copthorne Hotel (Newcastle) Limited v Arup Associates155, also enunciated

the same principle where Copthorne was suing Arup for the difference in the piling

costs as constructed from those in Arup's original estimate. The claim was rejected

due to lack of evidence but Judge Hicks said any claim would have had to be based on

the difference between the figure quoted for the piling in the original estimate and that

which an engineer, exercising all reasonable skill and care, would have included in

the cost estimate. The claim, he said, could not be based on the actual costs of the

piling because this may have increased for any number of reasons. The estimate

allowed £425,000 for this work; the successful tender was for £930,000. The Judge

said of this discrepancy as follows:-

“I hope and believe that I am not over simplifying if I record the impression

that the plaintiff’s main hope was that I would be persuaded to find in their

favour simply by the size of the gap, absolutely proportionately, between the

cost estimate and the successful tender.

In the Malaysian case, Lim KC & Associates Sdn v. Pembinaan Udarama Sdn

Bhd156, the client’s complaint against the architect for an allegedly bad initial estimate

of project cost failed because he had not actually tested the estimate by putting the

project out to tender in the form proposed. The appellant architects carried out

preliminary cost planning and feasibility study for the respondent developers on a

mixed commercial / residential development in Kuala Lumpur. The developers 155 [1997] 85 BLR 22 156 [1980] 2 MLJ 26

Page 78: quantity surveyor's liability during pre tender stage asmah alia bt

66

subsequently abandoned the scheme but refused to pay the architects for their work

and that of their quantity surveyors, on the ground that it was because of their gross

under estimate of the cost of the scheme that it had to be abandoned.

From the various cases discussed above, it is essential to provide accurate

information to clients or contractors at the initial stages of development, giving

negligent or misleading estimate to a client can cause all sorts of problems such as

project can be postpone and losses to the client.

In the case of Clarke v. Adams157, the plaintiff was treated by the defendant, a

physiotherapist, for fibrositic condition of the left heel. He suffered injury by burning,

which resulted in his having to have the leg amputated below the knee. Before

applying the treatment the defendant gave the plaintiff this warning:

'When I turn on the machine I want you to experience a comfortable warmth

and nothing more; if you do, I want you to tell me.'

Evidence was given by the chief examiner for the Chartered Society of

Physiotherapy that that warning was an entirely proper one. The learned judge said

that clearly in physiotherapy the cooperation of the patient was vital. The instrument

used was dangerous because burns caused by it could lead to serious consequences. It

was extremely unlikely that the defendant, a skilled physiotherapist, on being told by

the plaintiff that he was undergoing such pain that he could not bear it, would take no

precautions. There was no evidence that the apparatus used was defective. The sole

question was therefore whether the warning given by the defendant, said to be an

entirely proper one, was sufficient.

157 [1950] 94 Sol. Jo. 599

Page 79: quantity surveyor's liability during pre tender stage asmah alia bt

67

There must in such circumstances be a warning of danger as it would appear to

a hypothetically reasonable person. Would the words used have warned such a person

that his safety depended on his informing the defendant the moment he felt more than

a comfortable warmth? The warning must be couched in terms which made it

absolutely clear that it was a warning of danger. He was not satisfied that this

warning, although the very warning which the defendant had been taught to give, was

adequate, and on that ground the plaintiff was entitled to recover.

In the construction industry scenario, the judgment passed by Judge Esyr

Lewis Q.C in the case of Gable House Estates v The Halpern Partnership158, clearly

be evidence for a professional owes a duty to exercise standard of care in preparing

the estimate.

In this case, the plaintiff had acquired a tenanted property originally built in

1922, and had three options, refurbishment, redevelopment or resale with vacant

possession. Defendant, architects specializing in refurbishment schemes for historic

and listed buildings, were engaged under an agreement based on the standard RIBA

form and suggested four alternative development schemes with different net lettable

areas. Plaintiff chose a design based on one of Defendant 's schemes and practical

completion was achieved. Subsequently the net lettable area was found to be

substantially less than that estimated by Defendant. Plaintiff complained that

redevelopment would not have been undertaken but for Defendant 's negligent over

estimation of net lettable space.

Judge Esyr Lewis Q.C. giving judgment for Plaintiff, that the Defendant had a

contractual duty to exercise reasonable skill and care in respect of the schedules of

area they produced. The drawings produced by Defendant fell below the standard of a

158 [1995] 48 Con.L.R. 1

Page 80: quantity surveyor's liability during pre tender stage asmah alia bt

68

competent architect and in the circumstances, Defendant owed the same duty of care

relating to the schedules of area drawn up by the quantity surveyor as they did in

relation to the rest of the cost plan. Defendant did not adequately warn Plaintiff as to

the known uncertainties of the cost plan schedules. Plaintiff relied on the information

and estimates provided by Defendant in making the decision to redevelop. If Halpern

had given proper warnings it was improbable that Plaintiff would have gone ahead

with the redevelopment.

On the concurrent liability point, he followed (as he was bound to do) the

House of Lords decision in Henderson v. Merrett Syndicated Ltd 159 where in this case

the professional, architect owes a concurrent duty to his client in both contract and in

tort. This concurrent duty arises and enables a plaintiff to recover damages for

economic loss in a contract for a professional service, ‘certainly where the defendant

has special knowledge or skill and assumes responsibility towards the plaintiff’160.

The decision made by the judge in the above case is purely an important

decision in emphasizes that professional including the quantity surveyor must be

extremely careful in giving the advice especially related to the cost of the project.

In the case of Tyrer v District Auditor for Monmouthshire161, a surcharge of

GBP 12,000 was imposed on Plaintiff, a quantity surveyor, in respect of his

negligence in his employment with the Council in approving excessive quantities and

prices in some contracts with a firm of building contractors which led to irrecoverable

overpayments to the Contractor. There was, in addition, a simple mathematical error

in issuing an interim certificate. The judge emphasis in the above case that, the error

159 [1994] 3 WLR 761 160 Contract Journal (1995) Some Good advice assessed at

http://www.contractjournal.com/Articles/1995/09/21/27269/some-good-advice.html on 8 November

2009 161 [1973] WL 39721

Page 81: quantity surveyor's liability during pre tender stage asmah alia bt

69

could have happened at any time, but "the obligation was on the appellant to ensure

that adequate checks were made". Obviously the client will rely on the professional to

prepare an estimate. Hence, it is a duty of care for a professional to make sure the

estimate is correct and carries out the adequate check.

In preparing estimate, the professional must include necessary precaution in

order to make sure the estimate is reliable. Refer to the decision made in the case of

Saunders & Partners v AE Bristow.162 In 1973, defendant retained plaintiff as his

architects to prepare a planning application for the proposed renovation of his house.

Defendant told plaintiff that he had about GBP 250,000 to spend and asked for an

estimate of the likely cost. Plaintiff consulted a quantity surveyor and gave an

estimate of GBP 238,000 but no quantification in respect of future inflation was

made. In March 1974, planning permission having been obtained, defendant engaged

plaintiff to provide the services necessary for the completion of the project. In

September 1974, plaintiff gave an up to date estimate amounting to GBP 440,000.

Defendant then terminated their employment and plaintiff sued for their fees.

Defendant contended that plaintiff had failed in their duty to take care to provide a

reliable approximate estimate and in particular to draw attention to the fact that

inflation would drive the figure beyond the amount available.

Held in the Court of Appeal (Civil Division) that the increment in the estimate

was due to a large increase in inflation of which plaintiff ought to have warned

Defendant. Plaintiff was therefore in breach of duty and could recover no fees.

As shown in this case, the person who prepares the estimate will owe a duty of

care to include inflation in the estimate for future cost projection. The client can claim

for damages due to the negligence act by the estimator as they rely on the estimate

prepare by the person who is deemed to possess expert skill. The professional in

162[1987 37 B.L.R. 92 Times, April 27, 1987 1988 WL 622685

Page 82: quantity surveyor's liability during pre tender stage asmah alia bt

70

specific the quantity surveyor can succeed in raising defense by showing that have

perform the duties with care, in example to include the cost for projected inflation in

the estimate.

3.2. Liability in Measuring Quantity and Preparing bills of quantity

The courts dealt with many cases involving liability for inaccurate bills of

quantities and the decisions appear to be inconsistent. The apparent inconsistency was

due in part to the distinguishing features of the various contracts and representations

which were made regarding the quantities.

3.2.1 Prepares a bill of quantity with reasonable care and skill

Xavier163 suggested that information given at the pre-contract or tender stage

would be necessary as well as helpful especially to the contractor. Whoever (whether

a quantity surveyor, architect or engineer) prepares a bill must do so with reasonable

care and skill. This is to avoid additional claim due the inaccurate quantity by the

contractor. It is almost inevitable, where the bills of quantities have been hurriedly

prepared at the last minute by unqualified and/or inexperienced consultants, that there

will be discrepancies. Usually the discrepancies are under-measured quantities or

forgotten items164.

163 Xavier G (1998) Contractor’s Obligation in a Malaysian Construction Contract, Construction

Journal : Westlaw 164 James B Longbottom Brian E Rawling & Associates Limited, Quantity Discrepancies

in Bills of Quantities, Surveying practice: Surveyors Time Pg 19

Page 83: quantity surveyor's liability during pre tender stage asmah alia bt

71

It was held in Bolt v. Thomas165 that where it was stipulated that the client, a

developer should pay the architect for the calculation of the quantities, and he had

done so, then the builder was entitled to compensation from the architect if the bill

was not reasonably accurate.

Another successful claim held in the case Dudley Corporation v. Parson and

Morrin Ltd166, where in this case a rate for excavating in rock included in the bill of

quantities was far too low. The contractors price an item for excavating 750 cu yd in

rock at £75 in example two shillings a cube. In carrying out the excavations described

in the drawings and bills, the contractor excavated a total of 2230 cu yd of rock. The

architect valued the work at two shillings a cube for 750 cu yd and the balance at £2 a

cube. The final account quantity greatly exceeded the bills of quantity. The contractor

claimed for the payment of an enhanced rate for the quantities is excess of the bills of

quantity. It was the decision of the Court of Appeal that all the final account quantities

should be paid for at bill rates.

‘Should any error appear in the Bills of Quantities other than in the

Contractor’s prices and calculations, it shall be rectified, and such

rectification shall constitute a variation of the Contract, and shall be dealt

with as hereinafter provided.167’

Appear in the above cases that, the client needs to bear the additional cost as a

result of the inaccurate the bills of quantity prepare by the professional. As an agent to

the client, the professional must be competence in delivering their duties. Failure to

perform a duty with reasonable skill and competence is a breach of contract. It is

165 [1859] (Hudson’s Building and Engineering Con-History of Construction Contracts and Case Law

7, tenth edition, at page 196) 166 Court of Appeal 167 Model Form of Contract (RIBA) clause 12a

Page 84: quantity surveyor's liability during pre tender stage asmah alia bt

72

obvious that the professional owe a concurrent liability to both clients under a

contract and in tort to a third party.

The provisions in the above contract have survived to the present day in

various form of contract and court judgement, in the case of Savage v Board of

School Trustees168, the estimate of $110,000 was twice given in respect of proposed

works. When tenders were received, the lowest was $157,800, 43% over the

estimated cost. The scope of the project was significantly reduced. The claimant

again estimated that the project would cost no more than $110,000, yet the lowest

tender for even the scaled down project was $132,900. The Judge commented;

“So on this one school, the plaintiff was three times gravely in error in his

estimates. And three times are a lot”.

The finding that the plaintiff had been negligent was based largely upon the

scale of the underestimation, and the frequency with which it was repeated. But on

analysis, the Court’s conclusion was based in large part upon a careful consideration

of the plaintiff’s workings, and the conclusion that “much of the plaintiff’s difficulty

was caused by his methods of checking and re-checking his estimates”.

Mistakes in the bill descriptions or quantities are unlikely to be remedied as a

legal rectification of the terms of the contract to reflect the true intention of the

parties. It is more likely than not, that the common intention will be that the tendered

price should prevail, rather than a price revised to account of the error. Most standard

forms of contract which adopt Bills of Quantities make provision to deal with errors

in bill descriptions and quantities, distinct from the effect of variations169.

168 [1951] 3 D.L.R. 39 169 Atkinson (2000) Bills of Quantity, assessed at http://atkinson-law.com/library/article.php?id=125

Page 85: quantity surveyor's liability during pre tender stage asmah alia bt

73

This means that the claimant only has to prove that the bills of quantities were

untrue or inaccurate. The burden is then transferred to the respondent who has to

show he had reasonable grounds to believe the bills of quantities were true170.

The standard of reasonable care and skill is not a standard of perfection. It is not

sufficient to show an error in order to establish a failure to exercise reasonable care

and skill. Actual negligence must be proven171. In the House of Lords decision in

Sutcliffe v Thackrah172 Lord Salmon held as follows:

“It by no means follows that a professional valuation was negligently given

because it turns out to be have been wholly wrong. Nor does the fact that an

architect’s certificate was given for the wrong amount of itself prove

negligence against the architect. Whether or not there has been negligence

is, of course, a pure question of fact depending upon the particular

circumstances of each case.”

.

The leading case is Derry v Peek173 where the English House of Lords held

that for there to be a fraudulent misrepresentation, the claimant must prove fraud by

showing that the respondent falsely made statements either:

• knowingly; or

• without belief in the truth; or

• recklessly, careless whether it be true or false.

A quantity surveyor’s task involves very large numbers of arithmetical

calculations, the question whether an occasional slip or error may be insufficient to

170 Ibid 171 PB Malaysia Sdn Bhd v. Samudra (M) Sdn Bhd In the High Court of Malaya at kuala Lumpur

(Commercial Division) Suit No. D5-22-2025 OF 2000 172 [1974] AC 727, at 760 173 [1889] 14 Appeal Case (HL)

Page 86: quantity surveyor's liability during pre tender stage asmah alia bt

74

sustain an allegation of professional negligence against quantity surveyor174. There

are few court cases in relation to the above issue.

In the case of London School Board v Northcroft in 1889 a school board

employed a quantity surveying for measuring up buildings of a value of £12,000

which had been completed. They brought an action against him for negligence in

making two clerical errors in the calculations, whereby the board had overpaid two

sums, one of £118 and the other of £15. It was held that as the quantity surveying had

employed a competent skilled clerk who had carried out hundreds of intricate

calculations correctly, the quantity surveying was not liable for these two errors.

Clients seek the services of a professional person of preeminent standing in

their field, and pays appropriately higher remuneration for their services, then a higher

standard will be expected than that of the ordinary, everyday practitioner in that field .

The employer, who is paying the quantity surveyor, should get the proper price for the

job based upon correct or corrected quantities, items and descriptions determined in

accordance with the Standard Method of Measurement in return.

3.3.2 Measurement must be done in accordance to Standard Method of

Measurement

The quantity surveyor requires following the standard work listed in the

standard method of measurement in order to prepare bills of quantity as stated in the

174 Frank E. and James A. (1988). Building Subsidence: Liability and Insurance. London: Oxford

BSP Professional Books.

Page 87: quantity surveyor's liability during pre tender stage asmah alia bt

75

Standard Form Contract as supported by the case of Bryant and Sons Ltd v .

Birmingham Saturday Hospital Fund175.

It was held that the contractor’s claim must succeed for excavation in rock

which was not measured in accordance with the principle of the Standard method of

Measurement under the RIBA form of contract. The standard method of measurement

therein required excavation in rock to be measured separately but this was not done

therein. Nevertheless if the Government here desires to depart from the principles of

the SMM, the Government must specifically state so expressly and this usually

provided in the preamble section of the Bills of Quantities.

This reference to the Bills of Quantities having been prepared in accordance

with the principles of the SMM is ambiguous by reason that it is not stated which

edition of SMM is applicable. The sensible interpretation would be the current edition

at the time of entering of the Contract.

Any work carried out by the contractor which is not measured separately in

accordance with the CESMM may unless there is a statement to the contrary be

subject to a claim for additional payment.

In the case of A.E. Farr Ltd v. Ministry of Transport,176 the appellants were

civil engineering contractors who undertook to carry out excavations and roadworks

for the construction of an underpass. The contract, in the ICE (4th ed.) standard form,

was a measurement and value contract; the work done by the contractor was measured

when completed and paid for at the rates stated in the bills of quantities. Rates were

stated in the bills of quantities for excavations necessary to accommodate the structure

175 [1938] 1 All ER 503 176 (1965) 5 BLR 94.

Page 88: quantity surveyor's liability during pre tender stage asmah alia bt

76

of the underpass but no rates were stated for excavations required to provide working

space.

The appellants contended that clause 16 constituted a promise to pay a

reasonable price for items which did not appear in the bills of quantities, which were

unpriced, and could only be written into the contract subsequently when the necessary

measurements of additional excavation had been made. Held, on a case stated, on the

true construction of cl. 16 in the light of all the contractual documents the appellants

were entitled to be paid reasonable rates for the working space excavations.

The bills of quantity having prepared ‘in accordance with the principles of the

Standard Method of Measurement’ is said to be ambiguous and obscure. In the

Standard Form of JKR 203A, stated that the measurement must be prepared in

accordance to the SMM produced by Institution of Surveyors Malaysia. However in

the PAM 2006 it is clearly stated that the contract bills are deemed to have been

prepared in accordance with “current edition” as sanctioned by the Institution of

Surveyors Malaysia. The term current edition used on the PAM 2006 is the new

improvement in the sense that the current SMM is effectively incorporated into a

contract by such reference.

It is incumbent on the architect and the quantity surveyor to make clear any

departure of SMM. This may be done either by a warning preamble in each case or by

measuring and describing the items in such a way as to show that a departure has been

made and it’s extend177.

177 Sundra Rajoo (1999) The Malaysian Standard Form of building Contract (The PAM 1998 Form)

Second Edition MLJ Journal : Kuala Lumpur

Page 89: quantity surveyor's liability during pre tender stage asmah alia bt

77

4.4. Liability in recommending the acceptance of a tender

After tenders have been received the quantity surveyor will draw up

comparisons and will advice the employer. In the larger projects the quantity surveyor

will then be part of the employer’s team for the purposes of negotiating with short

listed contractor so that the employer will get the best price. A construction

professional will be liable to the Employer if they carelessly give a positive

recommendation in favour of a Contractor. Failure to take reasonable steps in

selecting contractor will later cause damages to the principal, leads the quantity

surveyor to the negligent act.

In the case of Pratt v George Hill & Associates, an architect wrote to their

client saying that two firms of tendering contractors were “very reliable”. The client

chose one of them. In fact, the chosen contractor was wholly unreliable, leaving the

work in such a state that it needed to be effectively reinstated from slab level. The

client had paid some £2,000 on interim certificates and subsequently incurred costs of

just under £4,000 in an arbitration against the contractor before the contractor became

insolvent.

The judge found that the architect had been in breach of their duty of care to

their client and that the disastrous state of the works was due to the unreliability and

incompetence of the contractor, but disallowed these two sums on the ground that

they actually arose from the insolvency of the contractor. The case then went to the

Court of Appeal, which held that as a matter of causation, the losses concerned were

caused by the contractor’s lack of competence and the state in which he had left the

work, and the two sums were recoverable by the claimant.

Page 90: quantity surveyor's liability during pre tender stage asmah alia bt

78

More recently, in Partridge v Morris178, the Judge held that the Architect’s

duty of advising the Employer of the relative merits of tenders extended to the

consideration of financial acceptability.

In this case where a house holder engaged an architect to prepare the designs

for a house alteration. The defendant, architect also assisted in the tendering process

and recommended a contractor to the house holder which in case is the plaintiff.

Unfortunately the recommended contractor was on the verge of insolvency which

affected the quality of the work carried out. The householder terminated the

contractor’s employment and consequently incurred considerable extra expense in

getting the works completed. There was a little point in pursuing the original

contractor for these costs as he was insolvent.

As a result Partridge, the householder sought to recover damages from the

architect, part of the claim was that Morris should have reviewed the financing

standing of the contractor prior tp recommending the acceptance of their tender.

Although there was no express term in the agreement between Partridge and Morris

requiring to carry out a financial check the court referred to an RIBA publication,

which outlined an architect’s duties where it was stated that an architect should

discreetly check the financial status of firms providing a tender. He said:

“In my view the duty which the defendant undoubtedly undertook of advising

the plaintiff on the relevant merits of the tenders extended to consideration of

the financial acceptability of the tenderers. It was a matter upon which the

plaintiff needed advice; there was no other member of the professional team,

as there might be, more immediately concerned with that responsibility, and it

therefore remained with the defendant as the plaintiff’s general professional

adviser in relation to the review of tenders and the choice of a contractor”.

178 [1995] CILL 1095

Page 91: quantity surveyor's liability during pre tender stage asmah alia bt

79

The Judge held that the Architect should have undertaken one or more of the

following checks on the Contractor’s financial standing:-

• Checking with Builders Merchants;

• Obtaining a bank reference;

• Obtaining trade credit references;

• Making enquiries of other Architects as to the Contractor’s financial

standing;

• Undertaking a Company Search or asking the Contractor themselves for

their audited and latest management accounts.

He held that the failure to make the necessary enquiries was causative of

damage because, but for the failure by the Architect to make one or more of these

enquiries, the Contractor would not have been selected. The quantity surveyors are

sometimes asked by their client to provide advice on the selection and appointment of

contractors and in such cases it is important to be aware of what liabilities may be

associated with the advice provided

.

Page 92: quantity surveyor's liability during pre tender stage asmah alia bt

80

CHAPTER 4

CONCLUSION AND RECOMMENDATION

4.1 Introduction

As it now stands, contractors are unlikely to succeed in claims for damages

against consultants if the claim is one which the contractor can make against the

employer. The Court of Appeal of British Columbia held that where an architect's

estimates for a school building were 43 per cent out this was an unreasonable error

and the burden of disproving negligence rested on him179.

4.2 Research Finding

The quantity surveyor has been long establishing in the Construction Industry

and their duties have been widely recognized as important to the industry in terms of

179 Savage v Board of School Trustees of School District

Page 93: quantity surveyor's liability during pre tender stage asmah alia bt

81

contractual advice and costing. .

In performing his duties during the pre tender stage, the quantity surveyor has

to ensure that all action taken with care and skillful in accordance to the standard by

the professional. As an agent to the client the quantity surveyor is liable to his client

in the event of negligence. The client has the right to claim for damages from the

quantity surveyors

4.3 Study Constraint

Time was the main constraint for this study, the quantity surveyor’s liability is

a very broad study and it has to be narrowed down as stated in the limitation of the

study.

4.4 Suggestion for Future Study

This study is only focusing on the liability of quantity surveyor during pre

tender stage for certain duties such as preparing estimate, preparing quantities and

bills of quantity and liability in giving recommendation of contractor to the client in

the tender report. Due to the constraint mentioned above, the are various liabilities of

quantity surveyor that can be conducted as a further study especially during the post

contract stage. Further study also can be focusing on the liability of the quantity

surveyor under the Malaysian case in accordance to the Malaysian Standard Form of

Contract. Perhaps by expanding the study for future research can contribute to the

more clear view of the extend of the liability of the quantity surveyor.

Page 94: quantity surveyor's liability during pre tender stage asmah alia bt

82

4.5 Conclusion

The duties of a quantity surveyor to his construction client can be apply to the

principal of the agency law. Where the quantity surveyor acts as agent appointed by

the principal, he must perform the duties in accordance to the engagement contract

between them with reasonable skill and diligence.

The profession of the quantity surveying is governed by a professional body

that set rules and regulation and standard of duties that surveyors must follow. Only a

person registered a full member of the professional bodies which is in Malaysia,

Board of Quantity Surveyor Malaysia (BQSM) and possessed two years of working

experience can be classified as a quantity surveyor.

The quantity surveyors must perform their duties under a standard of care. In

performing their duties, the quantity surveyors carry a liability. Failure to perform the

duties with a reasonable skill and care will cause the quantity surveyor to owe a duty

to their client. Although the surveyor has no direct contractual relationship with a

third party, they are liable for losses or damages suffered by the third party through

the allegation to their client.

In the construction industry, a quantity surveyor is involved from the

beginning until the completion of a project. During the pre tender stage, a quantity

surveyor’s duties are more on the contractual and cost advisor to the client.

• The responsibility to prepare the cost estimates

Page 95: quantity surveyor's liability during pre tender stage asmah alia bt

83

Based on the research carried out, the quantity surveyor should give an honest

and careful estimate and responsible to exercising care 180 when they are required to

prepare a cost estimate for a particular project.181 They have to be extremely careful to

avoid the underestimation which later can caused the losses to the client. In addition

the quantity surveyor is responsible to collaborate with the designers in order to make

sure the estimate is not exceeding the client’s budget. He must make necessary

precaution in example providing inflation in his preparing estimate for future cost

projection. It is a duty for a quantity surveyor to make adequate check to ensure the

accurate estimate.

• The responsibility to prepare bills of quantity

In preparing the bills of quantity the quantity surveyor has to be aware of a

few liabilities that may face as appear in a certain court case. The quantity surveyor

must be aware that the contractor will rely on their quantity during the construction

stage. Thus, it is the great burden for a quantity surveyor to make sure the information

produce the bills of quantity during the pre contract stage will be reliable.

As the person who is expected to have an adequate skill to do a measurement

and bills of quantity, the quantity surveyor will be liable for producing inaccurate

quantity, discrepancy and not in accordance to Standard Method of Measurement.

• Wrongful advice on the selection of the contractor

As has been decided in the court case, the quantity surveyor must be very

careful in giving a recommendation to the client. The professional are expected to do 180 Ibid 181 Moneypenny v Hartland [1826] 2 C & P 378, Columbus Co v. Clowesc[1903] 1 KB 244

Page 96: quantity surveyor's liability during pre tender stage asmah alia bt

84

investigation and verify the background of the contractor to make sure he is

competent to carry out the works in future. Failure to make an adequate check will

cause the professional liable or responsible for the damages that the client might face

upon rely on the advice.

As a conclusion, the quantity surveyor owes a liability to the client under the

contractual agreement made between them to perform certain duties stipulated in the

agreement. Failure to perform, will leads to the breach of contract and the quantity

surveyor liable for the damages. In the recent case Blair And Patterson Ltd v.

McDermott 182 once again the court decided that the professional is liable to the

perform the duties in accordance to the standard retainer of the professional.

“It was an implied term of his contract with the defender that it would exercise

the knowledge, skill and care reasonably to be expected of an architect of

ordinary skill and competence. An ordinary competent architect would not

have undertaken design and contract administration work unless the terms of

the contract regarding inter alia the scope of work, allocation of

responsibilities and limitation of responsibilities were clearly agreed in

writing. Reference is made to standard 4.1 of the Architects Registration

Board "Code of Professional Conduct and Practice “

182 [2006] ABC.L.R. 05/01,

Page 97: quantity surveyor's liability during pre tender stage asmah alia bt

85

REFERENCES

Ashworth, A & Hogg, K (2007) Willi’s Practice and Procedure for the Quantity Surveyor

12the Edition Blackwell Publishing: Britain

Barrett, K (2008) Defective Construction Work, and Wiley-Blackwell: United Kingdom

believes me, when you feel sad, pray to Allah, the Almighty. Insyha’Allah, you

will feel very calm been in the situation lately

Barros. A. A. J. (1989). Professional Liability and Construction. England: Chartered

Institute Of Building Engle mere, Kings Ride, Ascot, Berkshire SL5 8BJ

B.M McLachlin, W.J Wallace & A.M Grant, the Canadian Law of Architecture &

Engineering, 2nd ed. (Toronto: Butterworths, 1994)

Bockrath, J T (2000) Contracts and the Legal Environments for Engineers and Architects

6th Edition, McGrawHill : United States

Brook, M (2004) Estimating and Tendering for Construction Works 3rd edition,

Elsevier:Oxford

Cecil Ray (1986) Professional Negligence, the Architecture Press: London

Page 98: quantity surveyor's liability during pre tender stage asmah alia bt

86

Chiet, Chai Voon (2007) Professional Liability of Civil Engineer, UTM Master

Dissertation (unpublished)

Charlesworth & Percy (1998) Negligence (9th Edition) Sweet & Maxwell Ltd : London

Contract Journal (1995) Some Good advice assessed at http://www.contractjournal.com/

Articles/1995/09/21/27269/some-good-advice.html on 8 November 2009

Davies, C.M. (1989). Avoiding Claims: Practical Guide for the Construction Industry.

Great Britain: St. Edmundsbury Press Ltd.

Duty of care and negligence at http://www.villamanta.org.au/ edit/Information_Sheets/

DUTY%20OF%20CARE%20&%20NEGLIGENCE.PDF

Daniel Atkinson. An error of bills at http://www.atkinson-law.com/ cases/CasesArticles/

CNewsArticles/CNews_1999_06_03.htm assessed by 1 August 2009

Evans, R. And Galbraith, A. (1979). Revision Notes on Building Law. London:

Newnes –Butterworths.

Foster, N; Trauner T.J; Vespe R.R; Chapman W.M (1995) Construction Estimates From

Take Off to Bid. McGraw Hill: United States of America.

Farial Hanum Nurul Ain Bt Khalid (2007) Comparison of Consulting Contract,Master of

Science (Construction Management): UTM, Unpublish

Flyvbjerg B, Holm M S & Buhl S (2002) Underestimating Costs in Public Works

Projects Error or Lie? APA Journal Vol 68 No 3Pg 279 assessed at http://

Flyvbjerg.plan.aau.dk/JAPAASPUBLISHED on 1 October 2009

Page 99: quantity surveyor's liability during pre tender stage asmah alia bt

87

Frank E. and James A. (1988). Building Subsidence: Liability and Insurance. London:

Oxford BSP Professional Books.

Greenwood, W (1965) Management and Organizational Behavior Theories: An

Interdisciplinary Approach. Cincinnati, OH: Southwestern Publishing.

Hinze, J Construction Contracts 2nd Edition, McGraw-Hill Higher Education: New York

Howard (2000), Professional Ethics and Rules of Conduct for the Royal Institution of

Chartered Surveyors (RICS). United Kingdom: College of Estate Management

Ir Harban Singh K.S (2002) Engineering Construction Contract Management Pre-

Contract Award Practise, LexisNexis : Malaysia

Ir Harban Singh K.S (2002) Law and Principle, LexisNexis : Malaysia

John L. Powell. Professional Negligence the Changing Coastline of Liability at

http://www.4newsquare.com/Files/PDF/Article/JP%20article.doc assessed on 1

October 2009.

Johnson Peter et al (1980) Pre-Contract Practice For Architect and Quantity Surveyors,

Aqua Group, Granada: London

Knowles Roger. Professional Liability of Consultants in the Construction and

Engineering Industries. (Unpublished)

Marianne, J. (2005). Building defects spoil homeowners’ dreams. Portland: The

Oregonian News. The Aldrich Law Office, P.C. 522 SW 5th Avenue.

Page 100: quantity surveyor's liability during pre tender stage asmah alia bt

88

Matthew J. Sullivan & Chris S. Stacy. Theories of Liability against Architects &

Engineers Retrieved 24 May 2009, from

http://www.utcle.org/eLibrary/preview.php?asset_file_id=1301

Noor Ashikin Khalid (1978). SMM dan Penggunaanya Dalam Industri Binaan. Skudai :

Universiti Teknologi Malaysia: unpublished.

Osborn P.G. & Bone S (2001) Osborn's Concise Law Dictionary Sweet & Maxwell:

London

Patten B (2003) Professional Negligence in Construction Spon Press: London

Powell J.L & Jackson R.M (1987) Professional Negligence: Sweet & Maxwell: London

Ramus, J, Birchall, S & Griffiths,P (2006) Contract Practise For Surveyors, Fourth

Edition, Butterworth-Heinemann:UK

R.M. Jackson and J.L. Powell. Professional Negligence 5th Edition

R.W Craig (1999) Procurement law for Construction and Engineering Works and

Services, Blackwell Science Limited: London Pg 515

Seel, C (1984) Contractual Procedure for Building Students : Holt,RineHart and Winston

Ltd : Oxford

Sinha & Deeraj (2000) Legal Dictionary 2nd Edition ILBS: Reprinted Edition Malaysia

Shrike,S (2009) 2 MLJ cl xii : Professional Negligence in the Construction Industry, MLJ

Articles : Lexis Nexis

Page 101: quantity surveyor's liability during pre tender stage asmah alia bt

89

Wilson, S (2006) Surveys and valuations – Breach of contract and negligence, Journal of

Building Appraisal Vol. 2 No 4 PP 294-300: Palgrave Macmillan Ltd

Wikipedia, Quantity Surveyor assessed 2.9.2009 at

http://en.wikipedia.org/wiki/Quantity_surveyor

Xavier G (1998) Contractor’s Obligation in a Malaysian Construction Contract,

Construction Journal: Westlaw

Page 102: quantity surveyor's liability during pre tender stage asmah alia bt

Revision No. 1/2002

(1 November, 2002)

TERMS OF REFERENCE

FOR

THE PROVISION OF PROFESSIONAL

QUANTITY SURVEYING SERVICES

FOR

................................................................................................................................................

................................................................................................................................................ ................................................................................................................................................ ................................................................................................................................................

Page 103: quantity surveyor's liability during pre tender stage asmah alia bt

1

TERMS OF REFERENCE

For

The provision of Professional Quantity Surveying services

For the

…………………………………………………………………………………project name)

The Agreement for the above Project entered into on the ……day of ……..20…… by the undersigned parties refers to these TERMS OF REFERENCE which shall be read and construed as part of the Agreement. ………………………………………. ……………………………………….. Signature of Consulting Q.S. Signature of Officer Name in full: ……………………….. Name in full: ...………………………. NRIC No.:…………………………….. In the capacity of : …………………. Designation: …………………………. Duly authorised to sign for and on for and on behalf of the Government Behalf of of Malaysia ……………………………………… Seal or chop of Consulting Q.S. Witness: ……………………………. Witness: ……………………………... Name in full: ……………………….. Name in full: ………………………… NRIC No.:…………………………….. Occupation: ………………………… Designation: ………………………….

Page 104: quantity surveyor's liability during pre tender stage asmah alia bt

2

Address: …………………………….. ……………………………...

1. DEFINITIONS

Unless the context otherwise requires, the following words and phrases in the Terms of Reference shall have the meaning given below:

“Basic Services” means the services as defined under paragraph 2 hereof and not as defined under paragraph 3 of the Schedule of Fees. “Director” means the Pengarah#, Cawangan Kontrak Dan Ukur Bahan and his successors in office.

2. SCOPE OF CONSULTING SERVICES

The scope of consultancy services to be carried out by the Consulting Q.S. shall comprise the following:. (a) Basic Services

Pre-Contract Stage*.

i. Preparation of Preliminary Estimates including preparation of Preliminary Detailed Abstract (PDA) and Cost Plans.

ii. Preparation of Bills of Quantities, other Tender Documents

necessary for calling tenders and Tender Table Document.

iii. Preparation of Tender Estimate.

iv. Preparation of As Tendered Detailed Abstract (ATDA)

v. Preparation of Contract Documents. Post-Contract Stage*

# Insert the Office, which will carry out the monitoring of Consulting Q.S’s works * Delete if not applicable

Page 105: quantity surveyor's liability during pre tender stage asmah alia bt

3

vi. Preparation of Tender Documents, Tender Estimates, Tender Reports and Contract Documents for works allowed under P.C. and Provisional Sums other than those under the charge of Mechanical and Electrical Consultants.

vii. Valuation of Works in progress for Interim Valuation/ Certificates,

including measurement of variation works and preparation of all related documents for Variation of Work other than those under the charge of Mechanical and Electrical Consultant.

2.0 SCOPE OF CONSULTING SERVICES (Cont’d)

Post-Contract Stage (cont’d) ∗.

viii. Preparation of Revised ATDA (if necessary) and Adjustments of

Contract Sum. ix. Preparation of Final Account and As Completed Detailed Abstract

(ACDA).

(b) Additional Services ∗.

i Preparation of Cost Analysis based on accepted Contract Sum. ii. Preparation of Tender Price Index based on accepted Contract

Sum. 3. REMUNERATIONS

(a) The computation of fees payable to the Consulting Q.S. shall be based on Scale of Fees for projects under Building Works - Category A / B / C* or Civil Engineering Works – Category 1 / 2* as specified in paragraph 5 of the Schedule.

(b) The percentage of fees payable to the Consulting Q.S. in respect of Basic

Services i - ix in paragraph 2(a) hereof shall be as per Appendix 1 attached to this Terms of Reference and not as in Section 8.1 – 8.6 of the Schedule subject to the following exception;

∗ Delete if not applicable

Page 106: quantity surveyor's liability during pre tender stage asmah alia bt

4

The Consulting Q.S. is not required to carry out tender evaluation and tender report under Stage 8.3 (i) of the Services and the fees payable will be deducted accordingly.

(c) The fees payable for the Additional Services i – ii in paragraph 2(b) hereof

shall be based on time cost as approved by the Director (d) Claims for the fees and reimbursable expenses as specified in Section 8 and

Section 10 of the Schedule respectively shall be submitted monthly and not later than three (3) months from the events. Any claims beyond the stipulated time will not be considered.

3. REMUNERATIONS (Cont’d)

(e) For the purpose of payment of the fees due to the Consulting Q.S. only, the services of the Consulting Q.S. shall be deemed to have been satisfactorily completed upon approval of the ACDA by the Director.

4. COMPLIANCE WITH GOVERNMENT PRACTICE AND PROCEDURE

In the provision of services, the Consulting Q.S. shall comply with Government’s procurement and financial procedures. The Consulting Q.S. shall also comply with JKR tender and contract administration practice and procedure as follows: (a) As the preliminary design of the Project is being developed, the

Consulting Q.S. shall give advice on cost implications of the design as and when required by the design team. Upon the finalisation of the preliminary design of the project, the Consulting Q.S. shall prepare PDA and any revision thereof as and when directed by the Director not later than seven (7) days from the receipt of the preliminary drawings.

(b) The Consulting Q.S. shall prepare Bills of Quantities and other tender

documents within one (1) month from the receipt of the final drawings to enable the tender to be called in accordance with the implementation schedule. The Bills of Quantities shall follow the SMM2 requirements and the format approved by the Director and shall be measured firm unless otherwise instructed in writing by the Director.

(c) The Consulting Q.S. shall prepare complete tender documents based on

the Standard Government Conditions of Contract, Form of Tender,

Page 107: quantity surveyor's liability during pre tender stage asmah alia bt

5

Specifications and other documents currently used in JKR, in compliance with the JKR Quality Assurance System.

(d) The Consulting Q.S. shall submit a printed copy of the draft Bills of

Quantities and other documents to the Director for approval. Final Bills of Quantities and other tender documents shall be based on the approved draft.

(e) The Consulting Q.S. shall submit two (2) copies of the Tender Table

Documents and sufficient copies of tender documents to be issued to the tenderers within seven (7) days before the date the tender notice is scheduled to be advertised and a copy of dimension sheets showing detailed calculation of the quantities of items in the Bills of Quantities and soft copy of the Bills not later than three (3) months after the award of the tender.

4.0 COMPLIANCE WITH GOVERNMENT PRACTICE AND PROCEDURE (Cont’d)

(f) The Consulting Q.S. shall prepare an estimate of the cost of the Project based on detailed pricing of the Bills of Quantities. The estimated cost of the project shall be attested by a registered Quantity Surveyor and shall be submitted together with the priced Bills of Quantities to the Director under a confidential cover not later than seven (7) days before the closing date of the tender.

(g) The ATDA and the Letter of Acceptance shall be submitted to the Director

not later than three (3) days after the receipt of the instruction. (h) The Consulting Q.S. shall submit the original Contract Document to the

Director within twenty-one (21) days after the date of issuance of the Letter of Acceptance (L.A) for the signatory by the Officer empowered to sign the Contract. The Consulting Q.S. shall prepare certified true copies of the Contract Documents and distribute the same to the relevant parties the soonest possible but in any case shall not exceed sixty (60) days from the date of issuance of L.A. The original Contract Document shall be delivered to the Director for the safe keeping.

(i) The Consulting Q.S. shall prepare and submit two (2) copies of Cost

Analysis and Tender Price Index based on accepted Contract Sum in an approved format not later than two (2) months from the date of issuance of L.A.

Page 108: quantity surveyor's liability during pre tender stage asmah alia bt

6

(j) The Consulting Q.S. shall submit to the S.O. or S.O.’s representative eight

(8) copies of the Interim Certificates in a format approved by the Director not later than three (3) working days after the date of valuation.

(k) In the administration of Variation Works, the Consulting Q.S. shall

observe the provisions under Treasury Instruction 202 and the JKR procedures. To enable the Instruction for Variation Work to be issued by the S.O, the Consulting Q.S. shall prepare the estimate for variation works within the time frame as specified below, after the date when the variation work was identified: i). 7 days if the variation work involved is of simple nature. ii). 14 days if the variation work involved is of complex nature.

The Consulting Q.S. shall prepare all necessary documentation in the approved format and submit to the S.O. or S.O.’s representative not later than fourteen (14) days after the issuance of the Instruction for Variation Works. Measurements and valuation of the variation works must be prepared the soonest possible, as work progress. Adjustment to the Contract Sum must be made in the approved format, not later than two (2) weeks from the date of receipt of the variation work drawings or from the date of completion of the variation works, whichever is earlier.

4.0 COMPLIANCE WITH GOVERNMENT PRACTICE AND PROCEDURE

(Cont’d)

(l) The Consulting Q.S. shall, if required by the S.O. or S.O.’s representative,

prepare and submit a report on the financial progress of the project and revise the ATDA within the time frame as specified below, from the date of receipt of the instruction and all necessary information from other related parties; i) 7 days if the variation work involved is of simple nature. ii) 14 days if the variation work involved is of complex nature.

(m) The final account of the Contract must be finalised not later than six (6)

months after the issuance of the Certificate of Practical Completion. The Consulting Q.S. shall submit the ACDA to the Director not later than one (1) month from the date of the approval of the final account.

(n) The Consulting Q.S. shall, as and when notified by the Government,

attend coordination and site meetings in connection with the services rendered.

Page 109: quantity surveyor's liability during pre tender stage asmah alia bt

7

Notwithstanding the approval by the Director to any documents prepared by the Consulting Q.S., the Consulting Q.S. shall not be relieved of his obligations under the Memorandum of Agreement.

5.0 LIST OF PERSONNEL, SCHEDULES OF WORK AND PROGRESS

REPORT

The Consulting Q.S. shall submit within two (2) weeks from the date of his formal appointment in writing by the Director, a list of his personnel complete with their curriculum vitae and a schedule of work commencing from the date of formal appointment showing the dates for completion of each of the services to be provided. The Consulting Q.S. shall submit each month, a report of the progress of services provided by him in a format acceptable by the Director.

6.0 CONSULTING Q.S. REPRESENTATIVE

The Consulting Q.S. representative shall be a registered Quantity Surveyor duly authorised to act on their behalf. No other person other than the authorised representative shall be allowed to act on the Consulting Q.S. behalf without prior consent from the Director.

7.0 AGREEMENT

The Consulting Q.S. shall prepare ten (10) sets of Memorandum of Agreement (and incorporating these Terms of Reference) for signing within two (2) weeks from the date of his formal appointment in writing by the Director.

8.0 LANGUAGE TO BE USED

All documents and reports to be prepared by the Consulting Q.S. and all correspondences shall be in Bahasa Malaysia unless otherwise permitted by the Director in writing.

Page 110: quantity surveyor's liability during pre tender stage asmah alia bt

8

APPENDIX 1 The percentage of fees payable to the Consulting Q.S. tabulated in Section 8 of the Schedule shall be replaced with the following:

TYPES OF CONTRACT SERVICES

%

Building and Civil Engineering Works

8.1 Preparation of Preliminary Estimates

and Cost Plans 8.2 Preparation of Bills of Quantities and

other Tender Documents (excluding preparation of Tender Documents under Clause 8.4), including pricing of the Bills of Quantities for an estimate.

8.3 i) Preparation Tender Reports ii) Preparation of Contract Documents. 8.4 Preparation of Tender Documents,

Tender Reports and Contract Documents for P.C and Provisional Items other than those under the charge of Mechanical and Electrical Consultants.

8.5 Valuation of works in progress for

Interim Valuation/Certificates 8.6 Preparation of Final Accounts

10

45

2.5

2.5

5

15

20

Total Services 97.5

* Notes: For projects where there are no P.C. and Provisional Sum items other than those

under the charge of Mechanical and Electrical Consultants, Stage 8.4 as described above is deemed to be executed under Stage 8.2 and Stage 8.3(ii). The percentage of fees for Stage 8.2 and Stage 8.3(ii) shall be revised to 48% and 4.5% respectively.