SECTION - 1

1413Government of Balochistan

CSR-1998 (Volume I)

SECTION - 2

Sr.

No.DescriptionUnitRate

(Rs.)

2-1Loading or unloading into or from Railway wagons, shingle, sand, ballast, surkhi, ashes, kankar, brick bats, coall or lime etc. lead upto 30 meters.Cu.m

%Cft.49.15

139.18

2-2Loading or unloading bricks or tiles into or from Railway wagons properly laid and stacked lead upto 30 meters.%Nos.143.00

2-3Loading or unloading into or from Railway wagons cement in bags (from inside or outside the godown) and stacking lead upto 30 meters.%Nos.178.75

2-4Loading or unloading into or from Railway wagons empty cement bags (from inside or outside the godown) and stacking lead upto 30 meters.%Nos.13.40

2-5Loading or unloading into or from Railway wagons (from inside or outside the godown) and stacking, white lime in bags lead upto 30 meters.%kg

Cwt2.70

1.37

2-6Loading or unloading into or from Railway wagons structural steel, R.S. joists, broad, narrow, or meter gauge rails and rail fastenings etc lead upto 30 meters.Tonne

Ton75.95

77.16

2-7Loading or unloading 205 litre drums fuel into or from Railway wagons, lead upto 30 meters.Each10.70

2-8Loading or unloading packages of sorts weighing upto 50 kgs (1 Cwt).Each5.35

2-9Loading or unloading sleepers, other than wooden, including stacking lead upto 30 meters.

a)Broad gauge sleepers.%Nos.357.50

b)Meter gauge and narrow gauge sleepers.%Nos.178.75

2-10Loading or unloading timber logs or timber for shuttering, into or from Railway wagons including stacking lead upto 30 meters.Tonne

Ton40.20

40.84

2-11Loading or unloading bhoosa into or from Railway wagons lead upto 45m.%kg

Cwt.10.70

5.43

2-12Loading or unloading timber scrap or wooden plugs into or from Railway wagons, and stacking lead upto 30 m.Tonne

Ton67.05

68.11

2-13Loading or unloading pitching stone or spawl from Railway wagons (including clearing 1.5 m away from the rail).Cu.m

%Cft.24.15

68.39

2-14Loading or unloading building stone (including clearing 1.5 m away from rails).Cu.m

%Cft.24.15

68.39

2-15Unloading oils.

a)Crude oil (to be pumped from tank wagon into tank).%litre

%gallon40.20

182.51

b)Crude oil (drained by gravity)%litre

%gallon40.20

182.51

c)Crude oil material from Railway wagons.Cu.m.

%Cft.8.05

22.80

d)Fuel oil into empty drums including stacking upto 30 m.Tonne

Ton65.25

66.29

e)Petrol (4.5 litre tin).%No.53.65

f)Kerosene (18 litre tin)%No.178.75

2-16Removing and stacking lead upto 30 m.

a)Stone, spawl, brick bats, shingle, sand lime, surkhi, ashes, kankar and coal etc.Cu.m.

%Cft.25.00

70.80

b)Bricks%Nos.205.55

c)Broad gauge wooden sleepers.%Nos.111.70

d)Meter gauge or narrow gauge wooden sleepers.%Nos.62.55

e)Rails, girders, pipes, cement etc.Tonne

Ton31.30

31.80

f)Baily bridges and wooden structural members.Cu.m.

%Cft.35.75

101.25

2-17Loading into wagons girders, rails, permanent way material (except wooden sleepers) iron work, pipes, etc. including lead upto 30 M and stacking inside wagons.Tonne

Ton89.4

90.82

2-18Unloading from wagons girders, rails, permanent way material (except wooden sleepers) iron work, pipes, etc.Tonne

Ton44.70

45.41

2-19Loading into wagons wooden broad gauge sleepers, including lead upto 30 M and stacking.%Nos.286.00

2-20Unloading wooden broad gauge sleepers from wagons, including 30 M lead and stacking.%Nos.143.00

2-21Loading meter gauge or narrow gauge wooden sleepers including 30 M lead and stacking inside wagons.%Nos.156.40

2-22Unloading meter gauge or narrow gauge wooden sleepers, including 30 M lead but excluding stacking.%Nos.77.75

2-23Loading or unloading bitumen, asphalt or tar drums, into or from Railway wagons lead upto 30 M.Tonne

Ton40.20

40.84

2-24Loading bailey bridge wooden structural members including stacking lead upto 30 M.Cu.m.

%Cft.49.15

139.20

2-25Unloading bailey bridge wooden structural members excluding stacking lead upto 30 M.Cu.m.

%Cft.25.00

70.80

2-26Loading into wagons, steel fabrication/bars including lead upto 30 M and stacking inside wagons.Tonne

Ton98.30

99.86

2-27Unloading from wagons, steel fabrication/bars including lead upto 30 M an stacking.Tonne

Ton53.65

54.50

LOADING,

UN-LOADING

AND

STACKING

THE RATE FOR LOADING INTO AND UNLOADING FROM MOBILE TRUCKS, TROLLIES AND BOATS WILL BE THE SAME AS FOR RAILWAY WAGONS.