pymble plc plc grey house precinct accessibility review
TRANSCRIPT
Morris Goding Studio 6, Level 1 T 02 9692 9322 NSW
Access Consulting 56 Bowman Street F 02 9692 8433 QLD
ABN 70 414 330 060 Pyrmont NSW 20 09 W mgac.com.au VIC
Pymble PLC
PLC Grey House Precinct
Accessibility Review Report
19 July 2021
Pymble PLC Accessibility Review Report 2
PLC Grey House Precinct 19 July 2021
REPORT REVISIONS
Date Version Drawing No / Revision
17/06/2021 1
19/07/2021
2
This report prepared by:
Lee-May Whong
Senior Access Consultant
Morris Goding Access Consulting
Pymble PLC Accessibility Review Report 3
PLC Grey House Precinct 19 July 2021
Table of contents
1. Executive Summary 4
2. Introduction 5 2.1 Background 5 2.2 Building Classification 5 2.3 Objectives 5 2.4 Limitations 6 2.5 Statutory Requirements 6
3. General Access Planning Considerations 7
4. Ingress & Egress 8 4.1 External Linkages 8 4.2 Entrances 8 4.3 Emergency Egress 9
5. Paths of Travel 10 5.1 Circulation Areas 10 5.2 Passenger Lifts 10 5.3 Stairs & Ramps 11 5.4 D3.4 Exemptions 11
6. Facilities & Amenities 12 6.1 Sanitary Facilities 12 6.2 Accessible Car Parking 12 6.3 Hearing Augmentation 13 6.4 Signage 14
7. Conclusion 15
8. Marked Plans 16
Pymble PLC Accessibility Review Report 4
PLC Grey House Precinct 19 July 2021
1. Executive Summary
This Access Review Report is a key element in the design application of the proposed Pymble
Ladies’ College Grey House Precinct located at the Pymble campus, Sydney NSW. It is
reviewed against the relevant Australian Codes and Standards under the provision of the
Commonwealth Disability Discrimination Act (DDA).
Morris Goding Access Consulting has prepared the Access Report to provide advice and
strategies to maximise reasonable provisions of access for people with disabilities.
The aim of the review is to ensure that the accessibility considerations comply with the relevant
statutory requirements, and in addition, consideration of accessibility to meet the intent of the
DDA of inclusive, dignified, and equitable access.
Pymble PLC Accessibility Review Report 5
PLC Grey House Precinct 19 July 2021
2. Introduction
2.1 Background
Morris Goding Access Consulting has been engaged to provide a review of the proposed
development.
The proposed development consists of a new home for Junior school Years 5 and 6, Out of
School Hours Care (OSHC), Dance, Health Service, and an Early Learning Centre (ELC).
2.2 Building Classification
The development falls under the following BCA classifications to be verified by the principal
certification authority (PCA):
- Class 5 – Offices.
- Class 7a – Carpark (to be advised by project team).
- Class 9b – School.
The general building access requirements for the above classifications are:
- Class 5 – to and within all areas normally used by the occupants.
- Class 7a – to and within any level containing accessible carparking spaces.
- Class 9b – to and within all areas normally used by the occupants.
2.3 Objectives
The requirements of the investigation are to:
- Review supplied drawings of the proposed development.
- Provide a report that will analyse the provisions of disability design of the development, and
- Recommend solutions that will ensure the design complies with the Disability Discrimination Act (DDA), Building Code of Australia (BCA), and relevant Australian Standards.
The objective is to ensure compliance with statutory requirements, and in addition, considers
the over and above minimum regulatory requirements under best practice approaches.
It considers the building user groups and ensures equality, independence and functional
access for people with disability, inclusive of people:
- with a mobility impairment (ambulant and wheelchair).
- with a sensory impairment (hearing and vision); and
- with a dexterity impairment.
The report assessment aims to meet the intent of the Disability Discrimination Act; which is,
as far as possible; to eliminate discrimination against persons on the ground of disability.
Pymble PLC Accessibility Review Report 6
PLC Grey House Precinct 19 July 2021
2.4 Limitations
This report is limited to the accessibility provisions of the building in general. It does not provide
comment on detailed design issues, such as: internals of accessible/ambulant toilet, fit-out, lift
specification, slip resistant floor finishes, door schedules, hardware and controls, glazing,
luminance contrast, stair nosing, TGSIs, handrail design, signage etc. that will be included in
construction documentation.
2.5 Statutory Requirements
The relevant statutory and regulatory requirements are:
- Federal Disability Discrimination Act (DDA).
- Disability (Access to Premises – Buildings) Standards 2010.
- Building Code of Australia (BCA) Part D3, E3, F2.
- AS 1428.1:2009 – General Requirement for Access.
- AS 1428.4.1:2009 – Tactile Ground Surface Indicators.
- AS 2890.6:2009 – Parking for People with Disabilities.
- AS 1735.12:1999 – Lift Facilities for Persons with Disabilities.
Additional advisory standards not currently referenced, and other relevant guidelines may be
considered include:
- Universal Design Principles.
- Premises Standard Guideline V2 2013.
- Guide to Building Code of Australia (BCA).
- AS1428.2:1992 – Enhanced and Additional requirements.
Pymble PLC Accessibility Review Report 7
PLC Grey House Precinct 19 July 2021
3. General Access Planning Considerations
The Disability Discrimination Act 1992 (DDA) is a legislative law that protects the rights of all
people. The Act makes disability discrimination unlawful and promotes equal rights, equal
opportunity, and equal access for people with disabilities. The Australian Human Right
Commission is the governing body who control and enforce DDA compliance.
Nevertheless, building elements that provide insufficient accessible provisions for people with
disabilities remain subject to the DDA. The improvement of non-compliant building elements
and areas to meet current access requirements will mitigate the risk of a DDA complaint being
made against the building owner.
Since the 1st of May 2011, the Commonwealth’s Disability (Access to Premises – Buildings)
Standards 2010 (DDA Premises Standards) apply to all new building works and to affected
parts of existing buildings.
The DDA Premises Standards’ requirements (DDA Access Code) are mirrored in the access
provisions of the BCA. New building work and affected parts must comply with the DDA
Premises Standards and AS1428.1-2009 in the same manner as they would comply with the
BCA by meeting deemed-to-satisfy provisions or by adopting an alternative solution that
achieves the relevant performance requirements.
By utilising AS 1428 suite of Standards, the overall aim is to provide continuous accessible
paths of travel to connect the proposed development to and through public domain areas and
between associated accessible buildings in accordance with the DDA Access Code.
MGAC supports the use and consideration of universal design (UD) principles into the design
to maximize access for all people. We will assist the design team to incorporate UD principles
where possible within the project, while still meeting mandatory compliance requirements.
Universal design principles consider the needs of a broad range of people including older
people, families with children and pushing prams, people from other cultures and language
groups, visitors in transit and people with disability. By considering the diversity of users, the
design will embed access into and within it, so that benefits can be maximized, without adding
on specialized ‘accessible’ features that can be costly, visually unappealing and may
perpetuate exclusion and potential stigma.
The seven key Universal design principles to consider in the on-going design include:
- Principle 1: Equitable Use
- Principle 2: Flexibility in Use
- Principle 3: Simple and Intuitive Use
- Principle 4: Perceptible Information
- Principle 5: Tolerance for Error
- Principle 6: Low Physical Effort
- Principle 7: Size and Space for Approach and use
Pymble PLC Accessibility Review Report 8
PLC Grey House Precinct 19 July 2021
4. Ingress & Egress
4.1 External Linkages
The BCA and DDA Premises Standards contain requirements for site approaches for the use
of persons with disabilities. These requirements can be summarised as follows:
- An accessible path of travel from main pedestrian entry points at the site allotment
boundary to all building entrances compliant with AS1428.1:2009.
- An accessible path of travel between buildings (or parts of buildings) that are connected
by a pedestrian linkage, within the site allotment boundary, compliant with
AS1428.1:2009 is also required.
- An accessible path of travel to building entrances (required to be accessible) from
associated accessible car-parking bays, compliant with AS1428.1:2009 is required.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
On the basis of the current level of detail, all access requirements appear capable of achieving
compliance subject to recommendations and comments on markups being addressed at
subsequent design stages. As advised, this will be reviewed and comply at further design
stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
4.2 Entrances
The BCA and DDA Premises Standards contain requirements for building entry for the use of
persons with disabilities. These requirements can be summarised as follows:
- Access through at least 50% of entrances, including the principal pedestrian entrance/s
to all buildings or parts of buildings (ie. when they have a separate function and/or use
eg. external retail tenancy). Note it is preferred that all entrances are accessible.
- A non-accessible entry located no more than 50m distance from an accessible entry
(for buildings greater than 500msq).
- All accessible doors with 850mm min. clear width opening and suitable door circulation
area, compliant with AS1428.1:2009.
- An accessible path of travel eg. ramp or lift provided adjacent (or in reasonable
proximity) to any stair access. Note: providing choice of access route directly adjacent
so that people can start and finish in the same location/travel similar route promotes
inclusion and UD principles.
Pymble PLC Accessibility Review Report 9
PLC Grey House Precinct 19 July 2021
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
On the basis of the current level of detail, all access requirements appear capable of achieving
compliance subject to recommendations and comments on markups being addressed at
subsequent design stages. As advised, this will be reviewed and comply at further design
stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
4.3 Emergency Egress
BCA 2016 Part D2.17 has requirements for all fire-isolated egress stairs from areas required
to be accessible (not communication stairs) to include at least one continuous handrail
designed to be compliant with AS1428.1 Clause 12.
Provision of an off-set tread at the base of stair flights or an extended mid-landing that will
allow a 300mm extension clear of egress route is considered appropriate for achieving a
consistent height handrail (without vertical or raked sections). Such an off-set tread
configuration has not been shown at the majority of stairs and would appear to be possible
elsewhere, subject to further detail design.
Where fire-isolated egress stairs will also be used for communication stair purposes between
levels, they should be designed to meet AS1428.1:2009. Confirmation is required on the likely
use of certain stairs for this purpose.
There is currently no mandatory requirement within BCA or DDA Premises Standards for
provision of independent accessible egress for people with a disability in accordance
AS1428.1 and this remains an important DDA issue. Consideration of an accessible egress
strategy with emergency evacuation plan should be considered as a minimum starting point.
Consideration of management systems and fire wardens for emergency egress for people with
disabilities is advised.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
On the basis of the current level of detail, all access requirements appear capable of achieving
compliance subject to recommendations and comments on markups being addressed at
subsequent design stages. Note off-set tread configuration has not been shown, refer mark-
ups. As advised, this will be reviewed and comply at further design stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
Pymble PLC Accessibility Review Report 10
PLC Grey House Precinct 19 July 2021
5. Paths of Travel
5.1 Circulation Areas
The BCA and DDA Premises Standards contain requirements for circulation areas for the use
of persons with disabilities. These requirements can be summarised as follows:
- Wheelchair passing bays (1800mm width x 2000 length) when a direct line of sight is
not available and are to be provided at 20m max. intervals along access-ways.
- Turning spaces (at least 1540mm W x 2070mm L) within 2m of every corridor end and
at 20m.max intervals along all access-ways. This is needed for wheelchairs to make
a 180 degree turn, compliant with AS1428.1:2009.
- All common-use doors (ie. not excluded under Part D3.4) with 850mm min. clear width
opening (each active door leaf) and suitable door circulation area, compliant with
AS1428.1:2009.
- All common-use corridors and accessible paths of travel with at least 1000mm min.
width when travelling in linear direction Note: Increased clear width paths of travel
required for doorway circulation, turning areas etc.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
On the basis of the current level of detail, all access requirements appear capable of achieving
compliance subject to recommendations and comments on markups being addressed at
subsequent design stages. As advised, this will be reviewed and comply at further design
stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
5.2 Passenger Lifts
The BCA and DDA Premises Standards contain requirements for passenger lifts and
circulation areas for the use of persons with disabilities. These requirements can be
summarised as follows:
- Passenger lifts with min. internal size at floor of 1400mm width x 1600mm depth, compliant with BCA/DDA Access Code Part E3.6 and AS1735.12.
- All lift lobbies and main corridors on each level with 1800mm min. clear width to allow two wheelchairs ability to space pass each other.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements. On the basis of the current level of detail, all access requirements appear
capable of achieving compliance. Further work will be required during design development
stage to ensure appropriate outcomes are achieved.
Pymble PLC Accessibility Review Report 11
PLC Grey House Precinct 19 July 2021
5.3 Stairs & Ramps
The BCA and DDA Premises Standards contain requirements for stairs and ramps for the use
of persons with disabilities. These requirements can be summarised as follows:
- Ramps maximum 1:14 gradient with landings at no more than 9 metre intervals
- Ramps with handrails on both sides with minimum 1 metre clearance in accordance
with AS1428.1
- Landings 1200mm length with 1500mm length at 90 degree turns
- Stairs handrails on both sides in accordance with AS1428.1
- Stairs and ramps with offset to ensure no encroachment of handrail extensions into
from transverse path of travel at top and bottom of stair/ramp
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
On the basis of the current level of detail, all access requirements appear capable of achieving
compliance subject to recommendations and comments on mark-ups being addressed at
subsequent design stages. As advised, this will be reviewed and comply at further design
stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
5.4 D3.4 Exemptions
The following areas are not required to be accessible:
- An area where access would be inappropriate because of the particular purpose for
which the area is used (plant room, cleaner, for example. Note some storage rooms
will require access such as administration store for stationery, paper etc).
- An area that would pose a health or safety risk for people with a disability.
- The path of travel to those areas that are exempt.
Assessment:
Areas currently identified as applicable for D3.4 exemptions are:
Level 00: Plant Room, Cleaners.
Level 1: Main S/Room, Main Comms Room.
Level 4: Plant, Cleaners Store.
It would appear other areas may fall under this exemption. As advised, this will be reviewed
and comply at further design stages.
Pymble PLC Accessibility Review Report 12
PLC Grey House Precinct 19 July 2021
6. Facilities & Amenities
6.1 Sanitary Facilities
The BCA and DDA Premises Standards contain requirements for sanitary facilities suitable for
the use of persons with disabilities. These requirements can be summarised as follows:
- For Class 5, 6, 7a, 9b: At least 1 unisex accessible toilet, adjacent to every bank of
toilets (where provided) on each storey, compliant with AS1428.1 under BCA/DDA
Access Code part F2.4. If more than 1 toilet bank provided on each level, accessible
toilet is required at 50% min. of toilet banks at each level.
- For Class 9b: If common-use change facilities provided (ie. both toilets and showers)
a separate combined accessible WC/shower adjacent to male and female change
rooms is required, compliant with AS1428.1 under BCA/DDA Access Code Part F2.4.
- An even number of left hand (LH) and right hand (RH) transfer WC pans (accessible
toilets) within the building. Alternating LH/RH layouts on each subsequent level is the
most appropriate and inclusive approach.
- Accessible WC with 2300mm x 1900mm around the pan with the basin to sit outside
this area in accordance with AS1428.1.
- An ambulant cubicle within every standard toilet bank adjacent to an accessible toilet
under DDA Access Code Part F2.4 compliant with AS1428.1:2009.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
On the basis of the current level of detail, all access requirements appear capable of achieving
compliance subject to recommendations and comments on mark-ups being addressed at
subsequent design stages. As advised, this will be reviewed and comply at further design
stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
6.2 Accessible Car Parking
The BCA and DDA Premises Standards contain requirements for parking which are applicable
to this project. These requirements can be summarised as follows:
- Accessible car bays 2.4 metre with 2.4 metre shared area.
- All accessible car bays located near relevant lifts and/or associated building entry
points to minimise distance to relevant lift and ensure accessible path of travel between
these areas.
Pymble PLC Accessibility Review Report 13
PLC Grey House Precinct 19 July 2021
- 2.5m min. height clearance, compliant with AS2890.6 fig 2.7 over accessible car bays
with 2.2 m min. vertical clearance leading to the accessible and adaptable unit car bays
(Note: consideration for 2.3 or 2.4m min. height preferred for higher vans/adapted
vehicles is recommended as good practice).
- Class 5: 1:100 or part thereof.
- Class 9b School: 1:100 or part thereof.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
Accessible carparking requirements has not yet been provided. Refer mark-ups for further
comments. As advised, this will be reviewed and comply at further design stages.
Further work will be required during design development stage to ensure appropriate
outcomes are achieved.
6.3 Hearing Augmentation
The BCA and the Premises Standards have access requirements for the provision of Hearing
Augmentation Systems. The key requirements of this provision are:
- A hearing augmentation system must be provided where an inbuilt amplification system
is provided (other than the emergency warning).
- In a room in a Class 9b building; or
- In an auditorium, conference room, meeting room or room for judicatory proposes; or
- At ticket office, teller’s booth, reception area where the public is screened from the
service provider.
- An induction loop to cover minimum 80% of the floor area.
- Receiver systems to cover minimum 95% of the floor area.
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
Hearing augmentation details have not been provided at this stage of the design process.
Where required by the BCA, ensure details to BCA and AS 1428.1 requirements. Refer mark-
ups for further comments. As advised, this requirement will comply.
Confirm all details at subsequent design stages.
Pymble PLC Accessibility Review Report 14
PLC Grey House Precinct 19 July 2021
6.4 Signage
The BCA and the Premises Standards have signage requirements. The key requirements are:
- Signage be provided to all male, female, accessible and ambulant toilets. It is to
include:
Braille and tactile.
International symbol of access.
‘LH’ or ‘RH’ to indicate a left-hand or right-hand transfer onto toilet pan.
Appropriate font size.
- At required fire exits.
- Where hearing augmentation systems are provided.
- Ensure all signage is detectable with raised symbols and 30% luminance contrast to
its background, and in turn, contrasts with the background wall surface.
- Directional signage is required at:
Banks of toilets without an accessible toilet, to direct person to the nearest
accessible toilet.
Non-accessible entrances to direct persons to an accessible entrance.
- Signage to be located on the wall, adjacent to latch side of the door, between 1200 -
1600mm AFFL (or for single line of tactile text: located between 1250 - 1350mm AFFL).
Assessment:
MGAC has reviewed the drawings and documentation in relation to the aforementioned
requirements.
Signage details is not provided at this early stage of the design process. Ensure details to BCA
and AS 1428.1 requirements. Refer mark-ups for further comments.
Confirm all design development and construction details at subsequent design stages.
Pymble PLC Accessibility Review Report 15
PLC Grey House Precinct 19 July 2021
7. Conclusion
MGAC has reviewed the proposed scheme for Pymble Ladies’ College Grey House Precinct.
The drawings indicate that access requirements can readily be achieved subject to the
recommendations noted in the marked plans and within this report being addressed in further
design stages.
It is advised that MGAC will work with the project team as the scheme progresses to ensure
appropriate outcomes are achieved in building design and external domain design.
Pymble PLC Accessibility Review Report 16
PLC Grey House Precinct 19 July 2021
8. Marked Plans
DC E F H IGBA
1D10-AA-01
2D10-AA-01
1D10-AA-02
4D10-AA-02
C10-AA-021
C10-AA-011
C10-AA-012
C10-AA-022
154.1 m²HALL
7.3 m²LIFT
AMENITIES
CIRC
COLA
DANCE
ELC
HEALTH
JUNIOR SCHOOL
JUNIOR SCHOOL BREAKOUT
OSHC
OUTDOORS
SERVICES
STAFF
STEM
136.9 m²COVERED OUTDOOR PLAY
L
5
J
3
4
6.9 m
²ST
ORE
6000 9000 9000 6000 9000 7518 4483 9000 9000
16.8 m²CHANGE
118.5 m²MOVIE
5.2 m²CLNRS
24.4 m²STUDENT WC
46.8 m²OFFICE /RECEPTION
84.5 m²CRAFT
28.5 m²KITCHEN
1
2
6
34.7 m²PLANT ROOM
5.1 m²ACC WC
POTABLE AND REUSE PLANT ROOM (5000 X 3000).
126.6 m²DINING
2D10-AA-02
COMMS
EDB
HYD FIRE HYDRANT750X3501
D10-AA-03
1100
075
0075
0075
0070
00
FIRE HYDRANT CUPBOARD650X 350 X 1800 HIGH
HYDRAULIC RISER700 X 200
DB CUPBOARD1000X 450
COMMS CUPBOARD1200X 1000
7.8 m²STORE
65.1 m²STUDY / MUSIC
14.2 m²MEETING
WC
22.6 m²STORE
12.4 m²STAFF CHANGE
WC WC
9.0 m²LAUNDRY 6.3 m²
STORE
DROPDOWNPROJECTOR
FIXEDPROJECTOR
26.3 m²LOCKERS
REFRIGERANT RISER2700 x 250HYDRAULIC RISER600 x 250
HYDRAULIC RISER1000 x 700
HYDMECH
HYD
CLIENT
PROJECT
BVN PROJECT NUMBER
STATUS
SCALE
ISSUE
DRAWING
GRAPHIC SCALE
DRAWING KEY
PROJECT MANAGER
TRUE NORTH PROJECT NORTH
COPYRIGHT BVN ARCHITECTURE PTY LIMITED. UNLESS OTHERWISE AGREED IN WRITING;ALL RIGHTS TO THIS DOCUMENT ARE SUBJECT TO PAYMENT IN FULL OF ALL BVN CHARGES;THIS DOCUMENT MAY ONLY BE USED FOR THE EXPRESS PURPOSE AND PROJECT FOR WHICH IT HAS BEEN CREATED AND DELIVERED, AS NOTIFIED IN WRITING BY BVN;AND THIS DOCUMENT MAY NOT BE OTHERWISE USED, OR COPIED. ANY UNAUTHORISED USE OF THIS DOCUMENT IS AT THE USER'S SOLE RISK AND WITHOUT LIMITING BVN'S RIGHTS THE USER RELEASES AND INDEMNIFIES BVN FROM AND AGAINST ALL LOSS SO ARISING.
INTELLECTUAL PROPERTY
CONSULTANT
CONSULTANT
CONSULTANT
Telephone +61 7 3852 2525Facsimile +61 7 3852 2544www.bvn.com.au
CONTRACTOR TO CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCEMENT OF WORK OR PREPARATION OF SHOP DRAWINGS. DO NOT SCALE THIS DRAWING
NOTE
CONSULTANT
500020000
SCHEMATIC DESIGN
89/07/2021 5:34:08 PM
1 : 200@A1
C:\Users\hmccabe\REVIT_LOCAL\2020\[email protected]
2010018
PYMBLE LADIES COLLEGEGREY HOUSE PRECINCT
GENERAL ARRANGEMENTPLAN - LEVEL 00
KATE BIMSONTEL 02 9855 7628
PYMBLE LADIES COLLEGE
STANTECTEL 02 9493 9700
TTWTEL 02 9439 7288
PROCLUS ADVISORY
WILLOW TREE PLANNINGTEL 02 9929 6974
NSW9356 NINOTSCHKA TITCHKOSKY4937 JAMES GROSE7115 JULIAN ASHTON7053 MATTHEW BLAIR7151 PHILLIP ROSSINGTON7439 PETER TITMUSS10447 ALISON BOUNDS
ARCHITECTS REGISTRATION BOARD / NOMINATED ARCHITECTS
QLD5527 NEIL LOGAN2709 BRIAN DONOVAN1595 MARK GRIMMER5528 DAVID KELLY5517 CATHERINE SKINNER3866 KEVIN O'BRIEN
ISSUE DATE FOR1 18/03/21 Issue to Town Planner2 14/04/21 For Information3 28/05/21 For Information4 02/06/21 For Information5 07/06/21 For Information6 25/06/21 Issued for Schematic Design7 07/07/21 For Information8 09/07/21 For Information
DC E F H IGBA
1D10-AA-01
2D10-AA-01
1D10-AA-02
4D10-AA-02
C10-AA-021
C10-AA-011
C10-AA-012
C10-AA-022
76.1 m²HOMEBASE
17.8 m²WITHDRAWAL
22.3 m²F. STAIRS
7.3 m²LIFT174.8 m²
DANCE STUDIO 04
173.6 m²DANCE STUDIO 03
175.0 m²DANCE STUDIO 02
176.4 m²DANCE STUDIO 05
176.3 m²DANCE STUDIO 06
13.8 m²RECEPTION
30.1 m²CHANGE
45.2 m²CIRCULATION
AMENITIES
CIRC
COLA
DANCE
ELC
HEALTH
JUNIOR SCHOOL
JUNIOR SCHOOLBREAKOUT
OSHC
OUTDOORS
SERVICES
STAFF
STEM
78.2 m²HOMEBASE
4.8 m²ACC WC
20.6 m²FIRE STAIR
37.1 m²STORE
130.9 m²OUTDOOR LEARNING
9.4 m²WITHDRAWAL
16.2
m²RE
TRAC
TABL
E SE
ATIN
G
38.6 m²OFFICE
21.7 m²KITCHEN / BREAKOUT
12.0 m²MEETING
127.7 m²FOYER / CIRC
20.0 m²MAIN COMMS ROOM
L
5
J
76.5 m²HOMEBASE
3
4
78.4 m²HOMEBASE
30.0 m²FOYER / CIRC
13.6 m²RECORDING STUDIO
21.6 m²STORE
175.4 m²DANCE STUDIO 01
1
2
30.7 m²CHANGE
6
MAIN SWITCH ROOM (3800 X 3100).
MAIN COMMS ROOM (2600 X 7000).
2D10-AA-02
COMMS
EDB
HYD
12.1 m²MAIN S/ROOM
15.0 m²DANCE PHYSIO
WCWCWC
DB CUPBOARD1000 x 450
EDB3.4 m²
STORE
1D10-AA-03
6000 9000 9000 6000 9000 7518 4483 9000 900011
000
7500
7500
7500
7000
BIO BOX
HYDRAULIC RISER700X 200
FIRE HYDRANT CUPBOARD650 x 350 x 1800 HIGH
HYDRAULIC RISER700 x 200
HYDRAULIC RISER700 x 300
450
FIRE HYDRANT750X350
27.4 m²MEETING ROOM
REFRIGERANT RISER2700 x 250
FIRE HYDRANT750 x 350
DB CUPBOARD1000X 450
COMMS CUPBOARD1200X 1000
HYDRAULIC RISER600 x 250
EXHAUST RISER1500 x 350
HYDRAULIC RISER500 x 350
HYDRAULIC RISER1000 x 700
MECH HYD
HYD
MECH
HYDHYD
CLIENT
PROJECT
BVN PROJECT NUMBER
STATUS
SCALE
ISSUE
DRAWING
GRAPHIC SCALE
DRAWING KEY
PROJECT MANAGER
TRUE NORTH PROJECT NORTH
COPYRIGHT BVN ARCHITECTURE PTY LIMITED. UNLESS OTHERWISE AGREED IN WRITING;ALL RIGHTS TO THIS DOCUMENT ARE SUBJECT TO PAYMENT IN FULL OF ALL BVN CHARGES;THIS DOCUMENT MAY ONLY BE USED FOR THE EXPRESS PURPOSE AND PROJECT FOR WHICH IT HAS BEEN CREATED AND DELIVERED, AS NOTIFIED IN WRITING BY BVN;AND THIS DOCUMENT MAY NOT BE OTHERWISE USED, OR COPIED. ANY UNAUTHORISED USE OF THIS DOCUMENT IS AT THE USER'S SOLE RISK AND WITHOUT LIMITING BVN'S RIGHTS THE USER RELEASES AND INDEMNIFIES BVN FROM AND AGAINST ALL LOSS SO ARISING.
INTELLECTUAL PROPERTY
CONSULTANT
CONSULTANT
CONSULTANT
Telephone +61 7 3852 2525Facsimile +61 7 3852 2544www.bvn.com.au
CONTRACTOR TO CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCEMENT OF WORK OR PREPARATION OF SHOP DRAWINGS. DO NOT SCALE THIS DRAWING
NOTE
CONSULTANT
500020000
SCHEMATIC DESIGN
89/07/2021 5:36:14 PM
1 : 200@A1
C:\Users\hmccabe\REVIT_LOCAL\2020\[email protected]
2010018
PYMBLE LADIES COLLEGEGREY HOUSE PRECINCT
GENERAL ARRANGEMENTPLAN - LEVEL 01
KATE BIMSONTEL 02 9855 7628
PYMBLE LADIES COLLEGE
STANTECTEL 02 9493 9700
TTWTEL 02 9439 7288
PROCLUS ADVISORY
WILLOW TREE PLANNINGTEL 02 9929 6974
NSW9356 NINOTSCHKA TITCHKOSKY4937 JAMES GROSE7115 JULIAN ASHTON7053 MATTHEW BLAIR7151 PHILLIP ROSSINGTON7439 PETER TITMUSS10447 ALISON BOUNDS
ARCHITECTS REGISTRATION BOARD / NOMINATED ARCHITECTS
QLD5527 NEIL LOGAN2709 BRIAN DONOVAN1595 MARK GRIMMER5528 DAVID KELLY5517 CATHERINE SKINNER3866 KEVIN O'BRIEN
ISSUE DATE FOR1 18/03/21 Issue to Town Planner2 14/04/21 For Information3 28/05/21 For Information4 02/06/21 For Information5 07/06/21 For Information6 25/06/21 Issued for Schematic Design7 07/07/21 For Information8 09/07/21 For Information
DC E F H IGBA
1D10-AA-01
2D10-AA-01
1D10-AA-02
4D10-AA-02
C10-AA-021
C10-AA-011
C10-AA-012
C10-AA-022
121.78+
+120.08
+121.83
+122.09
+120.13
AQUATIC CENTRELEVEL 00 - 120.18 FL
PE CENTRELEVEL 00 - RL 115.6LEVEL 01 - RL 118.5LEVEL 02 - RL 121.6 (ENTRY)
+ RL 115.93
+ RL 121.10
+ RL 118.72
GOODLET HOUSELEVEL 00 - RL 123.31 (ENTRY)LEVEL 01 - RL 126.59
JUNIOR SCHOOLLEVEL 00 -LEVEL 01 - RL 114.32
74.5 m²HOMEBASE
76.6 m²HOMEBASE 22.6 m²
F. STAIRS
55.3 m²4-5 CLASS (PRE-K)
20.5 m²F. STAIRS
16.7 m²DIRECTOR OFF.
10.7 m²TOILET
27.5 m²STAFF ROOM
15.7 m²WC
7.3 m²LIFT
21.0 m²STAFF OFFICE
8.6 m²RECEPTION
10.6 m²MEETING
46.5 m²2-3/4 CLASS
122600
L
5
J
3
4 4.4 m²STORE
ACC WC
WC
WC
75.3 m²HOMEBASE
74.8 m²HOMEBASE
8.9 m²WITHDRAWAL
AMENITIES
CIRC
COLA
DANCE
ELC
HEALTH
JUNIOR SCHOOL
JUNIOR SCHOOLBREAKOUT
OSHC
OUTDOORS
SERVICES
STAFF
STEM
1
2
6
COMMS
WC
WC
385.4 m²OUTDOOR PLAY
203.
7 m²
COVE
RED
OUTD
OOR
PLAY
6.2 m²STORE
170.4 m²PIAZZA / CIRC
2D10-AA-02
DB CUPBOARD1000X 450
REFRIFERANT RISER1000 x 1400
COMMS CUPBOARD1000 x1000
COMMSEDB
HYD
EDB
MECH
1D10-AA-03
6000 9000 9000 6000 9000 7518 4483 9000 900011
000
7500
7500
7500
7000
82.8 m²FOYER / CIRC
WC
149.7 m²FOYER/ENTRY
13.6 m²LAUNDRY/STORE
31.9 m²0-2 CLASS
27.6 m²FOYER / CIRC
17.5 m²WITHDRAWAL
HYDRAULIC RISER1000 x 200
FIRE HYDRANT CUPBOARD650X 350 X 1800 HIGH
REFRIGERANT RISER2700 x 250
FIRE HYDRANT750 x 350
DB CUPBOARD1000X 450
COMMS CUPBOARD1200X 1000
HYDRAULIC RISER600 x 250
EXHAUST RISER1500 x 350
HYDRAULIC RISER500 x 350
HYDRAULIC RISER1000 x 700
WC
17.2 m²PLAY/ WINTER GARDEN
32.2 m²0-2 CLASS
16.1 m²SLEEP
50.8 m²3-4/5 CLASS
18.9 m²SLEEP
15.7 m²WC
15.1
m²AI
RLOC
K &
PIGE
ON H
OLES
57.0 m²4-5 CLASS (PRE-K)
14.9 m²KITCHEN
HYDRAULIC RISER700 x 200
HYDRAULIC RISER700 x 200
4.1 m²STORE
SLIDE TO LEVEL BELOW
96.6 m²BREAKOUT
2.8 m²WC
MECH
MECH
HYD
HYD
4.4 m²STORE
HYD HYD
HYD
CLIENT
PROJECT
BVN PROJECT NUMBER
STATUS
SCALE
ISSUE
DRAWING
GRAPHIC SCALE
DRAWING KEY
PROJECT MANAGER
TRUE NORTH PROJECT NORTH
COPYRIGHT BVN ARCHITECTURE PTY LIMITED. UNLESS OTHERWISE AGREED IN WRITING;ALL RIGHTS TO THIS DOCUMENT ARE SUBJECT TO PAYMENT IN FULL OF ALL BVN CHARGES;THIS DOCUMENT MAY ONLY BE USED FOR THE EXPRESS PURPOSE AND PROJECT FOR WHICH IT HAS BEEN CREATED AND DELIVERED, AS NOTIFIED IN WRITING BY BVN;AND THIS DOCUMENT MAY NOT BE OTHERWISE USED, OR COPIED. ANY UNAUTHORISED USE OF THIS DOCUMENT IS AT THE USER'S SOLE RISK AND WITHOUT LIMITING BVN'S RIGHTS THE USER RELEASES AND INDEMNIFIES BVN FROM AND AGAINST ALL LOSS SO ARISING.
INTELLECTUAL PROPERTY
CONSULTANT
CONSULTANT
CONSULTANT
Telephone +61 7 3852 2525Facsimile +61 7 3852 2544www.bvn.com.au
CONTRACTOR TO CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCEMENT OF WORK OR PREPARATION OF SHOP DRAWINGS. DO NOT SCALE THIS DRAWING
NOTE
CONSULTANT
500020000
SCHEMATIC DESIGN
89/07/2021 5:36:25 PM
1 : 200@A1
C:\Users\hmccabe\REVIT_LOCAL\2020\[email protected]
2010018
PYMBLE LADIES COLLEGEGREY HOUSE PRECINCT
GENERAL ARRANGEMENTPLAN - LEVEL 02
KATE BIMSONTEL 02 9855 7628
PYMBLE LADIES COLLEGE
STANTECTEL 02 9493 9700
TTWTEL 02 9439 7288
PROCLUS ADVISORY
WILLOW TREE PLANNINGTEL 02 9929 6974
NSW9356 NINOTSCHKA TITCHKOSKY4937 JAMES GROSE7115 JULIAN ASHTON7053 MATTHEW BLAIR7151 PHILLIP ROSSINGTON7439 PETER TITMUSS10447 ALISON BOUNDS
ARCHITECTS REGISTRATION BOARD / NOMINATED ARCHITECTS
QLD5527 NEIL LOGAN2709 BRIAN DONOVAN1595 MARK GRIMMER5528 DAVID KELLY5517 CATHERINE SKINNER3866 KEVIN O'BRIEN
ISSUE DATE FOR1 18/03/21 Issue to Town Planner2 14/04/21 For Information3 28/05/21 For Information4 02/06/21 For Information5 07/06/21 For Information6 25/06/21 Issued for Schematic Design7 07/07/21 For Information8 09/07/21 For Information
DC E F H IGBA
1D10-AA-01
2D10-AA-01
1D10-AA-02
4D10-AA-02
C10-AA-021
C10-AA-011
C10-AA-012
C10-AA-022
66.4 m²STAFF ROOM
82.0 m²HOMEBASE
74.1 m²HOMEBASE
8.9 m²WITHDRAWAL
152.2 m²CIRCULATION
22.6 m²F. STAIRS
20.5 m²F. STAIRS
AMENITIES
CIRC
COLA
DANCE
ELC
HEALTH
JUNIOR SCHOOL
JUNIOR SCHOOLBREAKOUT
OSHC
OUTDOORS
SERVICES
STAFF
STEM
10.2
m²ST
EM S
TORE
75.5 m²HOMEBASE
L
5
J
3
4
7.3 m²LIFT
COMMS
115.7 m²STEM LAB
24.4 m²CHANGE
75.5 m²HOMEBASE
1
2
84.1 m²HOMEBASE
77.8 m²HOMEBASE
STAFF
76.7 m²HOMEBASE
17.1 m²WITHDRAWAL
46.7 m²FOYER / CIRC
10.2 m²OFFICE
6
99.2
m²BR
EAKO
UT / C
IRCU
LATI
ON WC WC
WC
4.8 m²ACC WC
2.2 m²WC
2D10-AA-02
EDB
HYD
WC
MECH
COMMSEDB
1D10-AA-03
82.3 m²HOMEBASE
19.6 m²WITHDRAWAL
29.3 m²FOYER / CIRC
8.9 m²MEETING
6000 9000 9000 6000 9000 7518 4483 9000 900011
000
7500
7500
7500
7000
FIRE HYDRANT CUPBOARD650X 350 X 1800 HIGH
HYDRAULIC RISER700 x 200
WC
EXHAUST RISER1500 x 350
HYDRAULIC RISER500 x 350
STAFF
HYDRAULIC RISER700 x 200
12.0 m²WITHDRAWAL
FIRE HYDRANT750 x 350
DB CUPBOARD1000X 450
COMMS CUPBOARD1200X 1000
HYDRAULIC RISER600 x 250
HYDRAULIC RISER1000 x 700REFRIGERANT RISER2700 x 250
PLANTER
PLANTER
HYD
HYD
MECH
MECH
DB CUPBOARD1000X 450
REFRIFERANT RISER1000 x 1400
COMMS CUPBOARD1000 x1000
HYDRAULIC RISER1000 x 200
HYD HYD
HYD
CLIENT
PROJECT
BVN PROJECT NUMBER
STATUS
SCALE
ISSUE
DRAWING
GRAPHIC SCALE
DRAWING KEY
PROJECT MANAGER
TRUE NORTH PROJECT NORTH
COPYRIGHT BVN ARCHITECTURE PTY LIMITED. UNLESS OTHERWISE AGREED IN WRITING;ALL RIGHTS TO THIS DOCUMENT ARE SUBJECT TO PAYMENT IN FULL OF ALL BVN CHARGES;THIS DOCUMENT MAY ONLY BE USED FOR THE EXPRESS PURPOSE AND PROJECT FOR WHICH IT HAS BEEN CREATED AND DELIVERED, AS NOTIFIED IN WRITING BY BVN;AND THIS DOCUMENT MAY NOT BE OTHERWISE USED, OR COPIED. ANY UNAUTHORISED USE OF THIS DOCUMENT IS AT THE USER'S SOLE RISK AND WITHOUT LIMITING BVN'S RIGHTS THE USER RELEASES AND INDEMNIFIES BVN FROM AND AGAINST ALL LOSS SO ARISING.
INTELLECTUAL PROPERTY
CONSULTANT
CONSULTANT
CONSULTANT
Telephone +61 7 3852 2525Facsimile +61 7 3852 2544www.bvn.com.au
CONTRACTOR TO CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCEMENT OF WORK OR PREPARATION OF SHOP DRAWINGS. DO NOT SCALE THIS DRAWING
NOTE
CONSULTANT
500020000
SCHEMATIC DESIGN
89/07/2021 5:36:33 PM
1 : 200@A1
C:\Users\hmccabe\REVIT_LOCAL\2020\[email protected]
2010018
PYMBLE LADIES COLLEGEGREY HOUSE PRECINCT
GENERAL ARRANGEMENTPLAN - LEVEL 03
KATE BIMSONTEL 02 9855 7628
PYMBLE LADIES COLLEGE
STANTECTEL 02 9493 9700
TTWTEL 02 9439 7288
PROCLUS ADVISORY
WILLOW TREE PLANNINGTEL 02 9929 6974
NSW9356 NINOTSCHKA TITCHKOSKY4937 JAMES GROSE7115 JULIAN ASHTON7053 MATTHEW BLAIR7151 PHILLIP ROSSINGTON7439 PETER TITMUSS10447 ALISON BOUNDS
ARCHITECTS REGISTRATION BOARD / NOMINATED ARCHITECTS
QLD5527 NEIL LOGAN2709 BRIAN DONOVAN1595 MARK GRIMMER5528 DAVID KELLY5517 CATHERINE SKINNER3866 KEVIN O'BRIEN
ISSUE DATE FOR1 18/03/21 Issue to Town Planner2 14/04/21 For Information3 28/05/21 For Information4 02/06/21 For Information5 07/06/21 For Information6 25/06/21 Issued for Schematic Design7 07/07/21 For Information8 09/07/21 For Information
DC E F H IGBA
1D10-AA-01
2D10-AA-01
1D10-AA-02
4D10-AA-02
C10-AA-021
C10-AA-011
C10-AA-012
C10-AA-022
17.2 m²CONSULT
12.0 m²RECEPTION
7.6 m²SHW/WC
16.0 m²2B SICK BAY
10.5 m²1B SICK BAY
8.7 m²1B SICK BAY
14.2 m²CONSULT
22.6 m²F. STAIRS
14.8 m²CONSULT
15.1 m²CONSULT
25.9 m²MEETING
14.8 m²CONSULT
20.5 m²F. STAIRS
16.9 m²CONSULT
7.3 m²LIFT
AMENITIES
CIRC
COLA
DANCE
ELC
HEALTH
JUNIOR SCHOOL
JUNIOR SCHOOLBREAKOUT
OSHC
OUTDOORS
SERVICES
STAFF
STEM
113.5 m²PLANT
14.6 m²CONSULT
CLNR
41.1 m²COURTYARD
15.8 m²WAITING
43.4 m²SHARED RETREAT
L
5
J
VOID
3
4 6.9 m²RETREAT
17.3 m²DR. CONSULT
17.3 m²CONSULT
15.9 m²2B SICK BAY
10.5 m²RETREAT
31.5 m²COURTYARD
7.9 m²ACC WC
HYD
1
2
6
3.9 m²SHW/WC
16.2 m²CONSULT
5.7 m
²ME
DICA
TION
MECH
23.6 m²2B SICK BAY
26.9 m²STAFF / KITCHEN 17
.4 m²
ROOF
TER
RACE
2.8 m²WC
80.7 m²CIRCULATION
15.3 m²CONSULT
DB CUPBOARD1000X 450
COMMS CUPBOARD1200x1000
FIRE HYDRANT750X350
1390
0
6900
SOLAR PVs ON EXTENSIVE GREEN ROOF
COMMS
2D10-AA-02
5.9 m²SHW/WC
COMMSEDB
7.2 m²RECORDS
5.4 m²PRINT BAY/ STR
7300
LINEN
1680
680 10001
D10-AA-03
6000 9000 9000 6000 9000 7518 4483 9000 900011
000
7500
7500
7500
7000
7.3 m²SHW/WC
HYDRAULIC RISER1000 x 200
HYDRAULIC RISER700 x 200
HYDRAULIC RISER700 x 200
3.0 m²WC
3.0 m
²ST
AFF
WC
11.1 m²RETREAT
14.7 m²RETREAT
EDB
121.1 m²CIRCULATION
98.9 m²CIRCULATION
10.0 m²LARGE STORE
3.6 m
²ST
ORE
PLANTER
PLANTER
PLANTER EXHAUST RISER1500 x 350
HYDRAULIC RISER500 x 350
FIRE HYDRANT750 x 350
DB CUPBOARD1000X 450
COMMS CUPBOARD1200X 1000
HYDRAULIC RISER600 x 250
HYDRAULIC RISER1000 x 700REFRIGERANT RISER2700 x 250
MECH
MECH
HYD
HYD
HYD
HYDHYD
REFRIFERANT RISER1000 x 1400
CLIENT
PROJECT
BVN PROJECT NUMBER
STATUS
SCALE
ISSUE
DRAWING
GRAPHIC SCALE
DRAWING KEY
PROJECT MANAGER
TRUE NORTH PROJECT NORTH
COPYRIGHT BVN ARCHITECTURE PTY LIMITED. UNLESS OTHERWISE AGREED IN WRITING;ALL RIGHTS TO THIS DOCUMENT ARE SUBJECT TO PAYMENT IN FULL OF ALL BVN CHARGES;THIS DOCUMENT MAY ONLY BE USED FOR THE EXPRESS PURPOSE AND PROJECT FOR WHICH IT HAS BEEN CREATED AND DELIVERED, AS NOTIFIED IN WRITING BY BVN;AND THIS DOCUMENT MAY NOT BE OTHERWISE USED, OR COPIED. ANY UNAUTHORISED USE OF THIS DOCUMENT IS AT THE USER'S SOLE RISK AND WITHOUT LIMITING BVN'S RIGHTS THE USER RELEASES AND INDEMNIFIES BVN FROM AND AGAINST ALL LOSS SO ARISING.
INTELLECTUAL PROPERTY
CONSULTANT
CONSULTANT
CONSULTANT
Telephone +61 7 3852 2525Facsimile +61 7 3852 2544www.bvn.com.au
CONTRACTOR TO CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCEMENT OF WORK OR PREPARATION OF SHOP DRAWINGS. DO NOT SCALE THIS DRAWING
NOTE
CONSULTANT
500020000
SCHEMATIC DESIGN
89/07/2021 5:36:40 PM
1 : 200@A1
C:\Users\hmccabe\REVIT_LOCAL\2020\[email protected]
2010018
PYMBLE LADIES COLLEGEGREY HOUSE PRECINCT
GENERAL ARRANGEMENTPLAN - LEVEL 04
KATE BIMSONTEL 02 9855 7628
PYMBLE LADIES COLLEGE
STANTECTEL 02 9493 9700
TTWTEL 02 9439 7288
PROCLUS ADVISORY
WILLOW TREE PLANNINGTEL 02 9929 6974
NSW9356 NINOTSCHKA TITCHKOSKY4937 JAMES GROSE7115 JULIAN ASHTON7053 MATTHEW BLAIR7151 PHILLIP ROSSINGTON7439 PETER TITMUSS10447 ALISON BOUNDS
ARCHITECTS REGISTRATION BOARD / NOMINATED ARCHITECTS
QLD5527 NEIL LOGAN2709 BRIAN DONOVAN1595 MARK GRIMMER5528 DAVID KELLY5517 CATHERINE SKINNER3866 KEVIN O'BRIEN
ISSUE DATE FOR1 18/03/21 Issue to Town Planner2 14/04/21 For Information3 28/05/21 For Information4 02/06/21 For Information5 07/06/21 For Information6 25/06/21 Issued for Schematic Design7 07/07/21 For Information8 09/07/21 For Information
DC E F H IGBA
1D10-AA-01
2D10-AA-01
1D10-AA-02
4D10-AA-02
C10-AA-021
C10-AA-011
C10-AA-012
C10-AA-022
L
5
J
3
4
1
2
6
SOLAR PVs SOLAR PVs
AMENITIES
CIRC
COLA
DANCE
ELC
HEALTH
JUNIOR SCHOOL
JUNIOR SCHOOLBREAKOUT
OSHC
OUTDOORS
SERVICES
STAFF
STEM
2D10-AA-02
1D10-AA-03
6000 9000 9000 6000 9000 7518 4483 9000 900011
000
7500
7500
7500
7000
NOTE: ROOF DRAINAGE LAYOUT TO BE DEVELOPED.
OPEN COURTYARD
LIFT
OPEN COURTYARD
PLANT BELOW
ROOF TERRACE BELOW
CLIENT
PROJECT
BVN PROJECT NUMBER
STATUS
SCALE
ISSUE
DRAWING
GRAPHIC SCALE
DRAWING KEY
PROJECT MANAGER
TRUE NORTH PROJECT NORTH
COPYRIGHT BVN ARCHITECTURE PTY LIMITED. UNLESS OTHERWISE AGREED IN WRITING;ALL RIGHTS TO THIS DOCUMENT ARE SUBJECT TO PAYMENT IN FULL OF ALL BVN CHARGES;THIS DOCUMENT MAY ONLY BE USED FOR THE EXPRESS PURPOSE AND PROJECT FOR WHICH IT HAS BEEN CREATED AND DELIVERED, AS NOTIFIED IN WRITING BY BVN;AND THIS DOCUMENT MAY NOT BE OTHERWISE USED, OR COPIED. ANY UNAUTHORISED USE OF THIS DOCUMENT IS AT THE USER'S SOLE RISK AND WITHOUT LIMITING BVN'S RIGHTS THE USER RELEASES AND INDEMNIFIES BVN FROM AND AGAINST ALL LOSS SO ARISING.
INTELLECTUAL PROPERTY
CONSULTANT
CONSULTANT
CONSULTANT
Telephone +61 7 3852 2525Facsimile +61 7 3852 2544www.bvn.com.au
CONTRACTOR TO CHECK AND VERIFY ALL DIMENSIONS ON SITE PRIOR TO COMMENCEMENT OF WORK OR PREPARATION OF SHOP DRAWINGS. DO NOT SCALE THIS DRAWING
NOTE
CONSULTANT
500020000
SCHEMATIC DESIGN
89/07/2021 5:36:46 PM
1 : 200@A1
C:\Users\hmccabe\REVIT_LOCAL\2020\[email protected]
2010018
PYMBLE LADIES COLLEGEGREY HOUSE PRECINCT
ROOF PLAN
KATE BIMSONTEL 02 9855 7628
PYMBLE LADIES COLLEGE
STANTECTEL 02 9493 9700
TTWTEL 02 9439 7288
PROCLUS ADVISORY
WILLOW TREE PLANNINGTEL 02 9929 6974
NSW9356 NINOTSCHKA TITCHKOSKY4937 JAMES GROSE7115 JULIAN ASHTON7053 MATTHEW BLAIR7151 PHILLIP ROSSINGTON7439 PETER TITMUSS10447 ALISON BOUNDS
ARCHITECTS REGISTRATION BOARD / NOMINATED ARCHITECTS
QLD5527 NEIL LOGAN2709 BRIAN DONOVAN1595 MARK GRIMMER5528 DAVID KELLY5517 CATHERINE SKINNER3866 KEVIN O'BRIEN
ISSUE DATE FOR1 18/03/21 Issue to Town Planner2 14/04/21 For Information3 28/05/21 For Information4 02/06/21 For Information5 07/06/21 For Information6 25/06/21 Issued for Schematic Design7 07/07/21 For Information8 09/07/21 For Information