public sector life cycle costing for asset management

83
06/06/22 1 March 27 & 28, 2014 March 27 & 28, 2014 Toronto, Ontario Toronto, Ontario LIFE CYCLE COSTING FOR THE PLANNING, DESIGN, LIFE CYCLE COSTING FOR THE PLANNING, DESIGN, CONSTRUCTION AND OPERATION OF INTELLIGENT AND GREEN CONSTRUCTION AND OPERATION OF INTELLIGENT AND GREEN BUILDINGS BUILDINGS David Katz, MBA David Katz, MBA President President Sustainable Resources Management Inc. Sustainable Resources Management Inc. Tel: 416 - 493 - 9232 Tel: 416 - 493 - 9232 Email: [email protected] Email: [email protected] 6 th Public Sector Life Cycle Costing for Asset Management

Upload: david-katz

Post on 17-Nov-2014

295 views

Category:

Government & Nonprofit


3 download

DESCRIPTION

Life Cycle Costing for Public Sector Buildings

TRANSCRIPT

Page 1: Public Sector Life Cycle Costing for Asset Management

04/08/23 1

March 27 & 28, 2014March 27 & 28, 2014Toronto, OntarioToronto, Ontario

LIFE CYCLE COSTING FOR THE PLANNING, DESIGN, CONSTRUCTION LIFE CYCLE COSTING FOR THE PLANNING, DESIGN, CONSTRUCTION AND OPERATION OF INTELLIGENT AND GREEN BUILDINGSAND OPERATION OF INTELLIGENT AND GREEN BUILDINGS

David Katz, MBADavid Katz, MBAPresident President

Sustainable Resources Management Inc. Sustainable Resources Management Inc. Tel: 416 - 493 - 9232Tel: 416 - 493 - 9232

Email: [email protected]: [email protected]

6 th Public Sector Life Cycle Costing for Asset Management

Page 2: Public Sector Life Cycle Costing for Asset Management

04/08/23 2

Page 3: Public Sector Life Cycle Costing for Asset Management

04/08/23 3

Review the LCC issues for GREEN and Intelligent BuildingsReview the LCC issues for GREEN and Intelligent BuildingsExamples of applying LCC to Green Building optionsExamples of applying LCC to Green Building optionsOther life cycle environmental attributes covered under Life Other life cycle environmental attributes covered under Life cycle analysis and new reporting under Provincial programscycle analysis and new reporting under Provincial programsExamples of LCC for intelligent building choicesExamples of LCC for intelligent building choicesFunding for the energy savings and Smart Grid Funding for the energy savings and Smart Grid interoperabilityinteroperabilityAssociations and agencies that have programs to help pay Associations and agencies that have programs to help pay for the investments especially if they provide life cycle for the investments especially if they provide life cycle benefits.benefits.Review your interests and share info on any projects and Review your interests and share info on any projects and challenges of applying life cycle costs under budgetary challenges of applying life cycle costs under budgetary restraintrestraint

AGENDAAGENDA

Page 4: Public Sector Life Cycle Costing for Asset Management

04/08/23 4

Intelligent and Green Building InvestmentsIntelligent and Green Building Investments

Typical problems that LCC can resolve:Typical problems that LCC can resolve: Having lower life cycle costs provides the incentive to Having lower life cycle costs provides the incentive to

overcome the lower first cost or budgetary restrictions.overcome the lower first cost or budgetary restrictions. Building valuations that look at the revenues and the Building valuations that look at the revenues and the

operating costs are improved by having the lower operating costs are improved by having the lower operating costs of better facilities. operating costs of better facilities.

Making repairs to existing equipment versus advancing Making repairs to existing equipment versus advancing the purchase of new better performing equipment that the purchase of new better performing equipment that saves energy and may qualify for different utility saves energy and may qualify for different utility incentives incentives

Page 5: Public Sector Life Cycle Costing for Asset Management

04/08/23 5

Application to design and construction processApplication to design and construction process

LCC analysis has many applications in the capital asset, LCC analysis has many applications in the capital asset, buildings and infrastructure projects that use the design buildings and infrastructure projects that use the design and construction process.and construction process.

Choosing the appropriate materials and costing out the Choosing the appropriate materials and costing out the operating and maintenance cost of different alternatives operating and maintenance cost of different alternatives provides the design and construction professional the provides the design and construction professional the ability to include the owner’s financial criteria as part of ability to include the owner’s financial criteria as part of the process.the process.

LEED, BOMA BESt and other certification programs LEED, BOMA BESt and other certification programs now require using LCC. These programs also look at life now require using LCC. These programs also look at life cycle assessments for environmental impacts.cycle assessments for environmental impacts.

Page 6: Public Sector Life Cycle Costing for Asset Management

04/08/23 6

Evaluating the alternativesEvaluating the alternatives

Evaluation approachesEvaluation approachesTotal present valueTotal present valueNet present valueNet present valueSimple paybackSimple paybackTrue paybackTrue paybackEquivalent uniform annual costEquivalent uniform annual costRate of returnRate of returnKWH savings/investment dollarKWH savings/investment dollarSavings/benefit to investment ratioSavings/benefit to investment ratio

Presenting the ResultsPresenting the Results

1.1.Graphic analysis – Cross over pointGraphic analysis – Cross over point

2.2.Bar and Pie Charts Bar and Pie Charts

Page 7: Public Sector Life Cycle Costing for Asset Management

04/08/23 7

How do Intelligent and GREEN buildings compliment each other?

Integrated Design approach using Life Cycle Cost Integrated Design approach using Life Cycle Cost principlesprinciples

Building type, Envelope Design and OrientationBuilding type, Envelope Design and Orientation Energy Modeling – LEED and Green GlobesEnergy Modeling – LEED and Green Globes H V A C Equipment and Building Automation ImpactsH V A C Equipment and Building Automation Impacts Operations and Maintenance –Continuous Operations and Maintenance –Continuous

CommissioningCommissioning Energy Price InflationEnergy Price Inflation Smart Grid - Distributed Energy, Storage & Demand Smart Grid - Distributed Energy, Storage & Demand

Response Programs – Intelligent Load Management Response Programs – Intelligent Load Management

Page 8: Public Sector Life Cycle Costing for Asset Management

04/08/23 8

Green Building Perspective

• Energy – Efficiency - Metering - Onsite Emergency & Renewable generation

– GridWise capable - Demand Response ready – Net Zero

• Water – Efficiency – Metering – Treatment – Cleaning- Landscaping

• Environmental Management – Storage Tanks - Mold – Maintenance – Operations

– Emergency Response - Training

• Indoor Environment – Daylighting – CO2 and CO monitoring

– IAQ Controls – Filters

• Emissions, Effluent and Other Impacts on the Environment

Noise – NOX – SO2 – Chemicals – Transportation – Heat Island Roofs

Page 9: Public Sector Life Cycle Costing for Asset Management

04/08/23 9

Oil and Gasoline Prices – NEB Site

Page 10: Public Sector Life Cycle Costing for Asset Management

04/08/23 10

Natural Gas Price (NEB) Prediction

Page 11: Public Sector Life Cycle Costing for Asset Management

Wholesale Electricity Prices in Alberta (AESO) and Ontario (IESO)

04/08/23 11

Page 12: Public Sector Life Cycle Costing for Asset Management

04/08/23 12

Page 13: Public Sector Life Cycle Costing for Asset Management

04/08/23 13

Ontario and CanadaPart of North America Smart GridElectricity and Peak Demand ChargesTime of Use RatesGlobal Adjustment more than Commodity now!

12¢ ?8¢ ?

????¢

4.7¢ / 5.5¢

Page 14: Public Sector Life Cycle Costing for Asset Management

04/08/23 14

Excerpt Ontario Government Booklet - 2011

Page 15: Public Sector Life Cycle Costing for Asset Management

04/08/23 15

Excerpt Ontario Government Booklet - 2011

Page 16: Public Sector Life Cycle Costing for Asset Management

Life Cycle Costing: Retrofit Applications

Page 17: Public Sector Life Cycle Costing for Asset Management

0 10 20 30 40 50 60 70 80

Site Structures

Garage

Balconies

Building Framing

Exterior Walls

Windows

Exterior Doors

Roofs

Heating and Cooling

Ventilation

Domestic Water Systems

Drainage

Plumbing

Power Supply & Distribution

Lighting

Emergency Power

Pre-Repair Service Life (yrs)

Total Design Life toReplacement (yrs)

Based on High-Rise Apartment Repair Needs Assessment CMHC 1998

Age of the building

Multi-Residential Building Service LifeApproximate design and pre-repair service life of the building elements

Conclusions:

First costs and rent revenues are only part of the Life Cycle Cost Story.

When all the repair items are totaled they may be as much as the cost of the original building.

Page 18: Public Sector Life Cycle Costing for Asset Management

Typical Building Maintenance CostsAnnual building renewal investment (as % of original building cost)

Page 19: Public Sector Life Cycle Costing for Asset Management

(Source: Energy Cost Savings Council)

Conventional Cost Analysis

Average Payback Period (PP) and Return on Investment (ROI) on single technology products.

Page 20: Public Sector Life Cycle Costing for Asset Management

Life Cycle Costing: New Building Design

Applications

Page 21: Public Sector Life Cycle Costing for Asset Management

04/08/23 21

New Building DesignLCC and Sustainable Design TechnologyAn LCC assessment

can be used to assess options concerning site design, and material and equipment selection to improve overall building energy efficiency.

Typical Sustainable Technology Applications:

Green Roofs

Greywater recycling

Photovoltaics

Ground source heat pumps

Natural ventilation

Page 22: Public Sector Life Cycle Costing for Asset Management

Natural corridor and Riparian Zone

ECD Energy and Environment Canada Ltd.

Native plant species – Bullrushes, Canadian Goldenrod, and Switchgrass

Brownfield at mouth of the Keating Channel, Toronto, ON

Sustainable EcosystemsAppropriate Site SelectionLand that is already municipally serviced or has previously been built upon should be favoured for development over previously undeveloped areas to enhance local ecology and preserved ecologically sensitive areas.

Natural CorridorsWhen linked to natural areas, community green spaces can provide valuable wildlife habitat and migration pathways. Site design should encourage interconnected natural areas and wildlife corridors.

Light Pollution ReductionMinimizing outdoor lighting, without compromising safety, can significantly reduce environmental threats to nocturnal wildlife species.

Native Species PlantingUsing plants that are native to a site reduces irrigation, lowers pesticide and fertilizer use, and cuts maintenance costs. Site design should ensure 75% of plantings are native.

Roadway NaturalizationRoadway edges and easements can support plantings that provide habitat for natural corridors and can be designed to reflect topographical and environmental conditions.

Page 23: Public Sector Life Cycle Costing for Asset Management

Microclimatic DesignBuilding design that maximizes solar access in winter for passive solar heat gain and shades windows in summer; controls wind and snow exposure; insulates against energy loss with green roofs of earth shelters, and promotes green roofs reduces energy consumption,

Passive Solar HeatingBuildings with sufficient southern exposure can capture sunlight in winter and release it as heat, reducing energy costs. In the summer, trees, window overhangs and sunshades block sunlight, keeping the building cool.

Natural or Hybrid VentilationBuildings may be ventilated and cooled passively if designed to take advantage of temperature/pressure differentials inside and outside the building, thereby creating cross-ventilation. Natural ventilation can be combined with traditional systems in a hybrid design.

Solar-Powered Street FurnitureSigns, bus shelters, street lights, and parking meters can easily function off-grid with a small solar array.

Community-Based Energy GenerationRenewable energy comes from non-fossil fuel based sources, like the sun, wind, water or earth. Governments, utilities and individuals should consider these sources both for their environmental sustainability and their stable, long-term costs.ECD Energy and Environment Canada Ltd.

Wind turbine at the Canadian National Exhibition, Toronto, ON

Photovoltaic curtain wall spandrels

Photovoltaic bus shelter

Photovoltaic light

Vegetated "green" roof, Mountain Equipment Co-op, Toronto, ON

South-facing housing, Milton Keynes, UK

Sustainable Energy Sources

Page 24: Public Sector Life Cycle Costing for Asset Management

Eco-Industrial SynergiesOne company’s waste may be another company’s resource. Encouraging regional economic exchange of by-products and energy leads to increased energy efficiency, reduces pollution, decreases waste volumes, and creates new market opportunities.

Adaptive Re-Use of Existing BuildingsNew buildings consume approximately 50% of all materials produced. Re-using existing structures, or salvaging their materials (such as brick, steel, timber, doors, fixtures, etc) conserves large quantities of resources and helps to preserve existing urban/cultural infrastructure.

Recycled Material UseTires, concrete, asphalt, fly-ash, carpet, ceiling tiles, and metal products can all be recycled for use in urban infrastructure such as roads. Materials in open spaces, such as playground equipment and surfaces, benches, tables, bike racks and signs can be recycled, recyclable or re-usable.

Sustainable Material UseThe life cycles (or cradle-to-grave environmental effects) of materials should be considered in their selection. Variations in the ways concrete, steel, timber, carpet, etc. are produced, materially composed, used, and disposed of strongly affect their environmental impact.

On-site Composting and RecyclingNiagara Region has a waste diversion goal of 65% by 2012. For this goal to be realized, areas for the handling, storage and separation of recyclables should be commonplace, and composting should be a priority where food waste is being produced.

Gooderham and Worts Distillery District, Toronto, ON

ECD Energy and Environment Canada Ltd.

Mountain Equipment Co-op, Toronto, ON. Structure consists of salvaged timbers and fly-ash concrete.

Sustainable Resource Use

Page 25: Public Sector Life Cycle Costing for Asset Management

Improved Building AccessThe energy needed to transport goods and for commuting to building is often equal to the amount of energy needed to operate the building. To reduce energy consumption, access routes for goods should be optimized and walking distances to public transit should be shortened.

Pedestrian and Bicycle TrafficWalkable and bikeable communities expand transportation options, diversify neighbourhoods, and reduce reliance on automobiles. Foot and bike paths, denser urban fabric, reduced auto speeds, and sheltered bicycle parking should be a priority.

Alternative Parking Arrangements The minimum number of parking spaces required for a development is determined by the peak demand. This can be excessive in some circumstances and options such as parking in lieu and parking on alternative sites may be more desirable.

CarpoolingShared vehicle transportation reduces automobile usage and congestion. Convenient pick-ups areas and a voluntary database of occupants’ postal codes help to promote carpooling.

Alternative Fuel Re-Fueling StationsPublic interest in vehicles fuelled by alternative fuels (such as electricity, natural gas, ethanol and biodiesel) is increasing, but these vehicles need conveniently located re-fuelling stations to grow in number.

Hydrogen re-fuelling station, Canadian National Exhibition, Toronto, ON

ECD Energy and Environment Canada Ltd.

Bike lanes and bike storage facility

Designated carpool lot

Sustainable Transportation

Page 26: Public Sector Life Cycle Costing for Asset Management

Desirable and undesirable stormwater management practices

Water Table

Stream

Storm Sewer

Impermeable PavingPlanters

Permeable PavingBioswale

Riparian Zone

Stormwater ManagementSite design should focus on increasing ground infiltration of water and reducing quantity and off-site treatment of run-off. Practices include minimizing impermeable paved surfaces, storing water in catchment systems, increasing vegetation, and creating retention ponds and infiltration basins.

Bioswale DesignGrassed or vegetated drainage channels, an alternative to traditional curb and gutter stormwater management, retain water and break down road contaminants.

Snow Pile PlacementSnow piles should be placed away from drainage courses and storm drain inlets to diminish impact of salts and other toxins on stream courses.

Riparian Zone ProtectionVegetated transition areas between a body of water and upland area control erosion, filter run-off, and provide animal habitat.

Innovative Wastewater TreatmentGrey-water recycling, composting toilets, constructed wetlands and Living Machines can reduce overall water consumption and reduce BOD content in wastewater to levels lower than those produced through conventional treatment.

Bioswale, Water Pollution Control Lab, Portland, Oregon

Lving Machine wastewater facility, Nova Scotia

ECD Energy and Environment Canada Ltd.

Sustainable Water & Wastewater Services

Page 27: Public Sector Life Cycle Costing for Asset Management

Sample LCC Application to SustainabilityGreen RoofsDEARBORN, Michigan - Ford is installing an environmentally sound roof on its $2-billion redevelopment of its Rouge River manufacturing complex. Keith Schneider, program director of the Michigan Land Use Institute, praised the green roof plan as innovative, if not a little risky. The new Ford Rouge Center assembly plant construction is one of the largest industrial redevelopment projects in the US. The green approach is designed to save Ford $35

million, when compared with the cost of installing a conventional treatment system, Schneider says.

Page 28: Public Sector Life Cycle Costing for Asset Management
Page 29: Public Sector Life Cycle Costing for Asset Management

Greg Kats latest book is based on extensive financial and technical analysis of 150 green buildings across the U.S. and in 10 countries and provides the most detailed findings to date on the costs and financial benefits of building green.

04/08/23 29

Page 30: Public Sector Life Cycle Costing for Asset Management

Among the study’s key findings: - Green buildings cost roughly 2% more to build than conventional non-green buildings and provide a wide range of financial, health and social benefits.1 - Green buildings reduce energy use by an average of 33%, resulting in significant cost savings. - Green buildings create roughly $1/square foot of value in increased employment by shifting spending from fossil fuel-based energy to more labour intensive domestic jobs in energy efficiency, renewable construction and new green industries.

04/08/23 30

Page 31: Public Sector Life Cycle Costing for Asset Management

04/08/23 31

Softcoat LowE

Meets the Code and provides lowest first cost.

Life cycle cost considerations with simple example

Page 32: Public Sector Life Cycle Costing for Asset Management

04/08/23 32

Triple Glazing & Heat Mirror

Alternatives cost more – but save more energy

Page 33: Public Sector Life Cycle Costing for Asset Management

04/08/23 33

IG Insulating PropertiesIG Insulating Properties

Data obtained using L.B.L. (Lawrence Berkeley Laboratories) Window 5.2 analysis program (nfrc/ashae)

2.223.45 4.00

8.009.09

14.30

-

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

Page 34: Public Sector Life Cycle Costing for Asset Management

04/08/23 34

IG Solar Heat Gain IG Solar Heat Gain CoefficientCoefficient

0.700.67

0.38

0.32 0.30

-

0.10

0.20

0.30

0.40

0.50

0.60

0.70

Double

Hard L

ow-E

Soft Low

-E

Triple

Low

-E

Sunlite

Trip

le

Page 35: Public Sector Life Cycle Costing for Asset Management

04/08/23 35

Reduce Energy Bills(Operating Costs)

Page 36: Public Sector Life Cycle Costing for Asset Management

04/08/23 36

Reduce HVAC Requirements(Capital Costs)

Page 37: Public Sector Life Cycle Costing for Asset Management

04/08/23 37

Reduced Lighting Requirements(Capital & Operating Costs)

Page 38: Public Sector Life Cycle Costing for Asset Management

04/08/23 38

Break-even Analysis using cash flow method

$-

$50,000

$100,000

$150,000

$200,000

$250,000

$300,000

$350,000

$400,000

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Low E 2 Triple Glazing Heat Mirror

Page 39: Public Sector Life Cycle Costing for Asset Management

04/08/23 39

Risk and sensitivity to above analysis. Fuel Escalation could less than 4% causing

Breakeven to be longer R value energy saving assumptions may not be

proportional as assumed. Solar Gain may have greater energy saving and

peak shaving impacts. Difference in initial HVAC capital costs should

also be considered. Other positive attributes like quiet and no mold

may be more valued than energy savings.

Page 40: Public Sector Life Cycle Costing for Asset Management

04/08/23 40

Investment

Source: Sustainable Building Technical Manual

Page 41: Public Sector Life Cycle Costing for Asset Management

04/08/23 41

Comfort

Page 42: Public Sector Life Cycle Costing for Asset Management

04/08/23 42

Eliminate Condensation & Mould

Page 43: Public Sector Life Cycle Costing for Asset Management

04/08/23 43

Sound Control

Page 44: Public Sector Life Cycle Costing for Asset Management

04/08/23 44

Triple Glazing- Optimum Daylighting

Page 45: Public Sector Life Cycle Costing for Asset Management

04/08/23 45

Is this Tinted Glass Building Green and Intelligent ?What are the tradeoffs in HVAC, Daylighting & Productivity

Page 46: Public Sector Life Cycle Costing for Asset Management

04/08/23 46

Comfort “The best sustainable designs are not just environmentally

responsible. They also produce buildings where employees can thrive and productivity can soar”

Christine Ervin President and CEO

U.S. Green Building Council

“Using green building strategies can result in increases in occupant performance measures by 6 to 26 percent.”

William D. Browning Founder of Green Development Services

and Senior Associate of Rocky Mountain Institute

Page 47: Public Sector Life Cycle Costing for Asset Management

04/08/23 47

Financial Benefits of Green Buildings

Page 48: Public Sector Life Cycle Costing for Asset Management

04/08/23 48

Green and Intelligent Building Convergence Review

Energy management for HVAC, Lighting & Demand Response – CBIP – Energy Star

Green Buildings – Environment - LEED & Green Globe Access and Security for safety of occupants and visitors Cabling and Wireless to increase revenue and lower costs Communications to increase value and productivity Digital Signage for instant information and advertising Interconnectivity to other buildings and the community

Page 49: Public Sector Life Cycle Costing for Asset Management

04/08/23 49

CABA INTELLIGENT & INTEGRATED BUILDINGS COUNCIL

Developed the BIQ Rating System for IB with Appraisal Institute and EPA Energy Star support www.caba.org/biq

Life-Cycle Cost Analysis Tool with Reed Construction Data/RSMeans www.caba.org/lifecycle

Developed a New Intelligent Building Roadmap www.caba.org/ibrm

Who is working on bringing these issues all together to evaluate alternatives and make sound economic choices?

Page 50: Public Sector Life Cycle Costing for Asset Management

04/08/23 50

Produced by: Thomas J. Lohner, P.E. Vice President, TENG Solutions

Analyzing the Life Cycle Cost of Integrated Building Systems

Page 51: Public Sector Life Cycle Costing for Asset Management

04/08/23 51

Systems Integration - Comparative Life Cycle Cost

You Can Not Afford Not to do it Right

Page 52: Public Sector Life Cycle Costing for Asset Management

04/08/23 52

Facility Systems Integration Life Cycle Costs

First Cost Changes, Additions & Upgrades Operating & Maintenance Utility Costs

Page 53: Public Sector Life Cycle Costing for Asset Management

UPS

Computer Room A/C

Emergency Generator

Fire Management System

Door Access Control & Intrusion Detection

Lighting Control System

HVAC Control System

Typical Building Approach to AutomationTypical Building Approach to Automation

Main Service Switchgear

5 User Interface Workstations!

No Integration !No Integration !

Page 54: Public Sector Life Cycle Costing for Asset Management

04/08/23 54

Non-Integrated Building Engineering Left up to Contractors Sole Sourcing Required to Provide

Integration - $$$$ Stand Alone Systems - Single Purpose Nobody Responsible for Technology

Integration

Page 55: Public Sector Life Cycle Costing for Asset Management

UPS

Computer Room A/C

Fire Management System

Emergency Generator

Main Service Switchgear

SNMP over IP

Web Server Web

ServerWeb Server

Web Server

Modbus

Web Server

Facility IP Network

Client FMS Workstation

Database Server

Partial Integration Concept Partial Integration Concept

HVAC Control System

Lighting Control System

Door Access Control & Intrusion Detection

Security Console

Proprietary Control Sub-systems

Page 56: Public Sector Life Cycle Costing for Asset Management

04/08/23 56

Partial Integration Issues Software Integration on IP networks Use Web Enabled - FMS Application

Program Methodology Employed for Existing

Buildings Hardware Intensive - Many I/O Servers

Page 57: Public Sector Life Cycle Costing for Asset Management

04/08/23 57

BENEFITS Partial Integration

Single User Interface for all Systems Web based GUI - Defacto Standard Permits Migration to Open Control Networks -

Competitive Bids !

Permits Development of Campus Wide Relational Database

Database Permits - Maintenance Management , Energy Management , Asset Management, etc.

Page 58: Public Sector Life Cycle Costing for Asset Management

UPS

Computer Room A/C

Fire Management System

Modbus

Emergency Generator

Main Service Switchgear

SNMP over IP

Web Server

Web Server

Facility IP Network

Client FMS Workstation Database Server

Full Integration Concept Full Integration Concept Open Standards Based Control Sub-systems

LONTALK - EIA 709.1 & BACNET – ANSI/ASHRAE 135A

Door Access Control, Intrusion Detection, Lighting & HVAC Control System

Web Server

Security Console

Page 59: Public Sector Life Cycle Costing for Asset Management

04/08/23 59

Full Integration Issues Open Standards Applied Where Possible I/O Servers Minimized Number of Devices Reduced - Shared

Information

Page 60: Public Sector Life Cycle Costing for Asset Management

04/08/23 60

BENEFITS Full Integration

Same as Partial Integration ApproachPLUS

Competitive Bids in each Building Integrated Building Sub-systems

Lighting, HVAC, Power Management and Security

Lowest Life Cycle Cost Approach

Page 61: Public Sector Life Cycle Costing for Asset Management

04/08/23 61

Life Cycle Cost Analysis Assumptions

150,000 SF Building Major M & E Equipment Cost - $6.00/SF ($18.00/SF TOTAL) Proprietary Systems Life Cycle - 7 years (FAR)

Replacement Cost = 125% of the Initial System Cost 50% of the Proprietary Systems are Replaced (Next Generation) 20% of the Open Systems are Replaced (Age & Obsolescence)

Average Cost per Control Device - $400 Open and Proprietary Control Devices Base Bid Costs are the Same Training Costs - $3000/ GUI; $1500/ Protocol; 50% of 1st year cost

for years 2 and up

Page 62: Public Sector Life Cycle Costing for Asset Management

Life Cycle Cost Analysis Assumptions

Dynamic Control Sub-

systems

Initial Cost

($/SF)

Base Year Service Contract

($)

Base Year Annual Changes & Modificatons (% of 1st Cost)

HVAC Controls $1.5/SF 15,000 2%Lighting Controls $1.0/SF 10,000 3%Power Monitoring $0.5/SF 5,000 1%Intrusion Detection $0.3/SF 3,000 2%Total $3.3/SF 33,000$ $39,000

Page 63: Public Sector Life Cycle Costing for Asset Management

Comparative First Costs

System Component

Non-Integrated Building

Partial Integration

Full Integration

Graphical User Interface - Hardware & Software 5 @ $15K 1 @ $20k 1 @ $20kEquipment Networking Uprades 0 4 @ $2k 4 @ $2kWeb Servers 0 5 @ $10k 3 @ $10kControl Device Reduction (5%) 0 0 -24750

TOTAL $75,000 $78,000 $33,000

Full Integration Savings $42,000 $45,000

No Account For Division 17000 Savings - 20 to 30%!!!

Page 64: Public Sector Life Cycle Costing for Asset Management

Blinds & 24v Wiring

Non-Integrated HVAC, Lighting & Intrusion Detection Echelon World Headquarters

VAV Boxes No Occupancy Control

Dimmable Lighting Control

Page 65: Public Sector Life Cycle Costing for Asset Management

Sensor and 120v WiringLighting, HVAC & Occupancy Sensor Control Trunk

User Scene Control Switch

Integrated HVAC, Lighting, Intrusion Detection & Blind ControlEchelon World Headquarters

Page 66: Public Sector Life Cycle Costing for Asset Management

04/08/23 66

Changes, Additions and Upgrades Issues

Cost Premium Paid for Additions & Changes to Proprietary Controls

Limit Scope of Future Improvements and Modifications

Cost Premium for Non Competitive Service Contracts

Page 67: Public Sector Life Cycle Costing for Asset Management

Changes, Additions and Upgrades (Annual Costs- 2nd Year & On )

O & M Cost Issues

Non Competitive

Cost Premium

Non-Integrated Building

Partial Integration

Full Integration

Service Contracts 25% 41,250$ 41,250$ 33,000$ Future Additons & Remodeling 25% 49,500$ 49,500$ 39,600$ Future Software Upgrades 5 @ $1k 1 @ $2k 1 @ $2kYear 7 Replacement Cost Reserve ( 9% APR) 33,629$ 33,629$ 13,452$

Total 129,379$ 126,379$ 88,052$

Full Integration Savings 41,327$ 38,327$

Page 68: Public Sector Life Cycle Costing for Asset Management

Operating and Maintenance (Annual Costs- 2nd Year & On )

System Component

Non-Integrated Building

Partial Integration

Full Integration

Training 11,250$ 5,250$ 3,750$ Improved O & M Staff Efficiency 0 SOFT SOFT IT Support 5 @ $2k 1 @ $3k 1 @ $3kManagement Reporting 0 (3 @ $1k) (3 @ $1k)

Total 21,250 5,250$ 3,750$ Full Integration Savings $17,500 1,500$

Computerized Maintenace Management 25,000$ First Cost(Extend Major M & E Equipment Life; 25yrs vs 20yrs)Future Worth ($ @ Yr 20) 180,000$ Present Worth (P/F @ 9%) 32,112$

Page 69: Public Sector Life Cycle Costing for Asset Management

Typical Energy Use Profile

Lighting

HVAC

Power

Other

HVACHVAC

30% Ave Annual Energy 30% Ave Annual Energy UseUse

$0.4 / SF / YR$0.4 / SF / YR

$60,000 / YR$60,000 / YR

LightingLighting

40% Ave Annual Energy 40% Ave Annual Energy UseUse

$0.53 / SF / YR$0.53 / SF / YR

$80000 / YR$80000 / YR

PowerPower

25% Ave Annual Energy 25% Ave Annual Energy UseUse

$0.33 / SF / YR$0.33 / SF / YR

$50,000 / YR$50,000 / YR

Other (Elevators, etc.)Other (Elevators, etc.)

5% Ave Annual Energy 5% Ave Annual Energy UseUse

$0.07 / SF / YR$0.07 / SF / YR

$10,000 / YR$10,000 / YR

TOTALTOTAL

$1.33 / SF / YR$1.33 / SF / YR

$200,000 / YR$200,000 / YR

Page 70: Public Sector Life Cycle Costing for Asset Management

Energy Costs (Potential Annual Cost Savings)

System ComponentSavings Factor

Energy Cost ($)

Non-Integrated Building

Partial Integration

Full Integration

Integrated Lighting & HVAC Control 5% $60,000 0 0 $3,000Improved Load Factor ( .5 to .55) 5% $200,000 0 $10,000 $10,000Better Maintained Equipment 1% $60,000 0 $600 $600

Coordinated Supply/Demand EMS Strategies 5% $200,000 0 $10,000 $10,000

Integrated Building Control System Savings $0 $20,600 $23,600

Page 71: Public Sector Life Cycle Costing for Asset Management

System Integration Life Cycle Cost Summary

Life Cycle Cost Component

Non-Integrated Building

Partial Integration

Full Integration

Comparitive First Cost $75,000 $78,000 $33,000Changes, Upgrades & Additions $129,379 $126,379 $88,052Operating & Maintenance $21,250 $5,250 $3,750Utility Cost $200,000 $179,400 $179,400

Net Present Value $2,325,232 $2,074,091 $1,773,493Discount Rate 9%

Life Cycle Period (yrs) 10Savings $551,739 $300,598

Page 72: Public Sector Life Cycle Costing for Asset Management

04/08/23 72

Conclusion:

Full Integration will Result in the Lowest Net Present Value

The Value of the Integrated Approach will Increase w/ IT Advances

Information will be your Competitive Advantage

Page 73: Public Sector Life Cycle Costing for Asset Management

04/08/23 73

Page 74: Public Sector Life Cycle Costing for Asset Management

04/08/23 74

Ontario Power Authority Integrated Power System Plan Conservation - LEED – Green Globe –BOMA BESt Conservation Measures - Technology Distributed Generation Opportunities Standard Offers – Renewable – Clean Energy Demand Response Programs DR Technologies – Building Sector Demand Response Shop website Smart Grid –Building2Grid optimization Questions

Demand Response and BAS Improvements

Page 75: Public Sector Life Cycle Costing for Asset Management

04/08/23 75

Previous technologies now economic New technologies save and measure it Building Automation more Intelligent Occupancy, Demand HVAC, Daylighting LEED and Green Globe Credits Life cycle costs and low cost of funds Peak and Energy reduction targets now

mandated to each of 74+ Ontario LDC’s

Old and New Technologies

Page 76: Public Sector Life Cycle Costing for Asset Management

04/08/23 76

Demand Response Technologies

Lighting – Dimming – Occupancy -Daylighting Raise Cooling Temperature – Casual Day Clothes Chiller Optimization – Hartman LOOP Chillers - Gas Driven – Absorption Thermal Storage – ICE - Water VSD – Pumps – Fans - Reprogram On site Generation – Economics? Windows - Shades -Tinting

Page 77: Public Sector Life Cycle Costing for Asset Management

04/08/23 77

NEW- Demand Response #3

Page 78: Public Sector Life Cycle Costing for Asset Management

04/08/23 78

Features & Benefits

New Building Automation Systems and Upgrades contribute to energy savings.

New chillers, VSD, Lighting Systems all offer more interoperability and controls

Most incentive programs require a measurement and verification plan as proof

You can’t manage what you can’t measure Intelligent buildings are GREEN and Sustainable

Page 79: Public Sector Life Cycle Costing for Asset Management

04/08/23 79

Federal Government Programs Ontario Energy Board funding for

Enbridge and Union Gas Demand Side Management

Ontario Power Authority Conservation Programs

LDC and others on www.saveonenergy.ca Other provincial regulators funding their utility CDM

programs – Hydro Quebec and Gaz Metro - Others Energy Service Companies (ESCO) Financial Institutions for Leasing or Borrowing Private energy companies for onsite generation

What are the opportunities to get funding for upgrades and retrofit alternatives that provide lower life cycle costs?

Page 80: Public Sector Life Cycle Costing for Asset Management

04/08/23 80

Public Sector Incentive Programs NRCan has a number of building upgrade

programs depending on size of building NRCan has developed new RETScreen tool

for energy efficiency Renewable and Clean generation incentives Peak Reduction and Demand Response

Programs pay for energy management systems that provide controls and M&V

Page 81: Public Sector Life Cycle Costing for Asset Management

04/08/23 81

Other Programs Available

Renewable and Clean Standard Offers Toronto Better Building Partnership Toronto Atmospheric Fund – Financing OPA – CDM for all LDC’s (2011-2015) OPA for Continuous Commissioning and

Next Gen Building Automation Tax credits and Class 43 Accelerated

Depreciation on qualified equipment

Page 82: Public Sector Life Cycle Costing for Asset Management

04/08/23 82

Financing Options

Self – Finance – Your cost of money Toronto Atmospheric Fund – Financing Lease or Rent – morEnergy Options Low interest loans – Banks and Credit Unions Energy Service Companies using Performance

contracts Carbon Credits and other Trading Schemes

Page 83: Public Sector Life Cycle Costing for Asset Management

04/08/23 83

Contact Info

David Katz, MBA, BADavid Katz, MBA, BASustainable Resources Management Inc. Sustainable Resources Management Inc.

6 Morning Gloryway6 Morning Gloryway