Public participation in Environmental Authorization
Erika du Plessis
Golder Associates Africa (Pty) Ltd
![Page 2: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/2.jpg)
Session 1 - Introductions
NameOrganisation / countryOne thing you’d like to learn
todayFavourite food
![Page 3: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/3.jpg)
COURSE OUTLINE
08:00 Arrival08:15 Introduction08:45 Changing role of the public09:30 International guidelines for good p210:00 Tea10:30 Public participation: What it is and is not11:00 Appropriate public participation: Good practice12:00 Tailoring public participation to project requirements12:30 Lunch13:30 Designing the process14:30 Group work – Case studies16:00 Wrap-up16:30 One last thing
![Page 4: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/4.jpg)
INTRODUCTION
P2 partial solution to environmental problems and decision making. Which stakeholders to involve when and to what degree – debate,
argument, disagreement Trade offs between economic growth, social equity and environmental
integrity. Lay people and experts see things differently. Public perception of risk differs from experts Intuitive perception of risk amongst lay people reflects far more concern
for perceived inequitable solutions Misconceptions, fear of losing control, previously inadequate processes,
pervasive mistrust. No silver bullet, process must be designed with these challenges in
mind.
![Page 5: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/5.jpg)
Session 2 - The Changing Role of the Public
![Page 6: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/6.jpg)
Drivers for changing role of the public
Community empowerment Democracy Increased access to information Increased access to international pressure
groups Increased awareness of rights Declining political acceptance of repressive
government/other practices Ability to challenge Changed power relations at the site
Changed the nature of relationship between company and stakeholders
![Page 7: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/7.jpg)
Drivers for changing role of the public
Internationalization of civil society Expectations for international
companies to be ‘global citizens’ Demonstrate corporate social
responsibility International public opinion Increasing awareness and
participation International financial, legal and
environmental standards
![Page 8: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/8.jpg)
Drivers for changing role of the public
Aarhus Convention on Public Participation - Europe Agenda 21 Equator Principles IFC Operational Directive 4.01– Environmental
Assessment IFC Operational Directive 4.30 – Involuntary Resettlement. IFC Disclosure Policy (1998); Stakeholder Engagement
(2007). Business Action for Sustainable Development (BASD) World Bank Extractive Industries Review Country laws – environmental and social; access to
information
![Page 9: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/9.jpg)
Drivers for changing role of the public
Role of the State
In most developing regions of the world….. Inability to effectively apply legislation and regulations
- lack of resources, inadequate staff training Inability to improve social conditions
- companies to act as surrogate governments Inability to maintain and guarantee rights Tendency to model laws on those of developed countries
- lack of legitimacy
![Page 10: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/10.jpg)
World Bank and IFC (many) International Hydrologic Programme, UNESCO US Environmental Protection Agency (EPA) US Departments of Energy, Defense, Transport, etc Commonwealth Foundation World Water Vision Project US Army Corps US President’s Council on Sustainable Development Canadian Standards Association Superfund Correctional Service, Canada European Bank The Intel Corporation, other companies International Association for Public Participation
P2 source books, guides, toolkits, manuals etc
Check out the SAIEA Calabash site
DRIVERS FOR CHANGING ROLE OF THE PUBLIC (4)
![Page 11: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/11.jpg)
Session 3 - Public participation in law
Environmental rights
Laws, regulations, how decisions will be made
![Page 12: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/12.jpg)
Legal requirements and standards
Legal requirements in-countryLaws International conventions signed by
country International standards (donors and
funders like IFC)Equator Principles IFC Performance Standards
Course participants page 5-7
![Page 13: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/13.jpg)
IFC Performance Standards on Social and Environmental
Sustainability
2. Labor and Working Conditions
3. Pollution Prevention & Abatement
4. Community Health, Safety &
Security
5. Land acquisition and Involuntary Resettlement
6. Biodiversity Conservation &
Sustainable Natural Resource
Management
7. Indigenous Peoples
8. Cultural Heritage
1. Social and Environmental Assessment & Management
Systems
Components of Performance Standard 1
a) Social and Environmental Assessment
b) Management Program
c) Organizational
Capacity
d) Training
e) Community Engagement
f) Monitoring
g) Reporting
Social & environmental impact assessment
Avoidance, mitigation, compensation measures
Action Plans (Resettlement, Biodiversity, etc.)
Roles, responsibilities, authority to implement management program
Incl. regulatory requirement, IFC Performance Standards & Action Plans
Disclosure
Consultation
Grievance
Recording of information, inspections, audits, etc.
Internal reporting
External reporting on Action Plans
Indicators for Ascertaining Free, Prior and Informed Consultation
1. Company strategy, policy or
principles on Engagement
2. Stakeholder identification &
analysis
3. Community engagement
Affected communities involved in:
Identifying potential impacts
Assessing consequences of
impacts
Development of mitigation measures
New impacts that have come to light have been consulted upon
4. Information disclosure
5. Consultation
Free (support of project notelicited by coercion, etc.)
Prior (sufficient time to interpret information, etc.)
Informed (based on adequate disclosure)
6. Informed participation
Incorporating community views on required mitigation, etc.
7. Vulnerable groups
8. Grievance mechanism
9. Feedback to affected
communities
Consultation
Mitigation
Structure, procedure & application
![Page 14: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/14.jpg)
The Equator Principles
1. Review and categorisation – magnitude of impacts
2. Social and Environmental Assessment – address risks, propose mitigation
3. Applicable Social and Environmental Standards – eg IFC Performance Standards, compliance with host country laws and regs
4. Action Plan and Management System – addresses management of impacts
5. Consultation and Disclosure – structured and culturally appropriate – free, prior and informed consultation
6. Grievance Mechanism – ensuring continued consultation throughout construction and operation.
7. Independent review – expert not directly associated to review assessment.
8. Covenants – compliance, process, report, decommission
9. Independent monitoring and review – during operation
10. EPFI Reporting – publicly, annually re implementation of principles.
![Page 15: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/15.jpg)
Law and pp guidelines
Southern African Institute for Environmental Assessment (SAIEA)
Calabash project – all the resources you need
www.saiea.com click on CalabashCheck out the new handbook on
environmental law in Southern African countries
![Page 16: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/16.jpg)
EIA Process (Chapter 4 in Guide)
![Page 17: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/17.jpg)
FEASIBILITY STUDY
TECHNICAL FINANCIALENVIRONMENTAL/
SOCIAL
Where the EA fits into the developer’s feasibility study
Course participants page 9
![Page 18: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/18.jpg)
IMPACT ASSESSMENT
DECISION-MAKING
INTEGRATION & COMPILE REPORT
IMPACT ASSESSMENT
(Specialist studies)
SCOPING(issues by stakeholders, authorities, specialists)
ENVIRONMENTAL MANAGEMENT
PLAN
Identify stakeholdersProvide info (capacity building)Get issues concerns and suggestions for benefitsGet local knowledgeVerification that issues captured
![Page 19: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/19.jpg)
Objectives of public participation during an EA
To provide sufficient and accessible information to stakeholders in an objective manner to assist them to:
During the Scoping Phase: Identify issues of concern, suggestions for
enhanced benefits and alternatives Verify their issues were recorded / captured Agree on the scope of the EA
During the Environmental Assessment Phase: Verify their issues were considered Comment on findings of EA
During / after the Decision-making Phase: Understand reasons for and conditions to
decision Opportunity to appeal decision
Course participants page 10
To achieve this one must:• Identify
stakeholders• Announce
opportunity to participate and
• Provide information
![Page 20: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/20.jpg)
TEA TIME – 30 MINUTES
![Page 21: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/21.jpg)
Session 4 - PP – What it is and is not
![Page 22: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/22.jpg)
Public participation
A process leading to a joint effort by… stakeholders technical specialists the authorities the proponent
…who work together to produce betterdecisions than if they had actedindependently
![Page 23: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/23.jpg)
WHAT IS PUBLIC PARTICIPATION?
“They can help us think”“They can give us an up-front
indication of environmental (social, economic, environment) issues
which may cause future difficulties”
“Capitalizing on the collective wisdom of people representing
various perspectives of society”
![Page 24: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/24.jpg)
BENEFITS OF PUBLIC PARTICIPATION
· Builds public understanding of need for proposed policy, program, plan or project and leads to better and more durable decisions
· Creates trust in decision-makers and processes, leading to stable policies and enduring decisions
· Provides an early warning of issues that require mitigation· Builds public ownership and stronger stake in initiatives leading to
participants carrying out their responsibilities during implementation · Identifies local customs or institutions that could be barriers to
implementation, with opportunities to adapt activity before implementation begins
· Creates opportunities for stakeholders to discuss their differences directly, often leading to creative new solutions
· Manages single-issue viewpoints through interactive process which allows a broad range of balancing perspectives and values
· Enriches decision-making through diversity of opinion and the local and traditional knowledge and collective wisdom of stakeholders
· Builds legitimacy for decisions that allows them to withstand changes in government or company policy and leadership
![Page 25: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/25.jpg)
![Page 26: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/26.jpg)
RESULT OF NO COMMON GOAL
GovernmentP
roponent
EIA Team
Soc
ial
Env
ironm
ent
advocacyanimosityconflicting needsmistrust
= 2m3/a/xx2ab/ml/s
*&&!!**
&&!!**!
*?!!&&$$
!!&?11**
![Page 27: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/27.jpg)
COMMON GOAL – SUSTAINABLE DEVELOPMENT
StakeholderStakeholderAgriculture
Developer
StakeholderSocial
GovernmentLocal
EIA Specialist
StakeholderLabour
GovernmentCentral
EIA Specialist
StakeholderEnvironment
StakeholderMining Industry
Developer
GovernmentProvincial
Can we achieve...
sustainability?
Economicindustry
Ecologicalintegrity
Socialequity
![Page 28: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/28.jpg)
PUBLIC PARTICIPATION : WHAT IT IS NOT
Not public relations Not the DAD principle Does not promote project or developer Cannot practically consult with every individual or
organisation Not the developer’s neighbour or community
relations Cannot on behalf of developer enter into
negotiations Not intended to satisfy grievances; rather to
record issues of concern Not environmental dispute resolution
![Page 29: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/29.jpg)
Difference between PR and P2
ongoing
2003
2004
2005
2006
2007
PUBLIC RELATIONS
health
business safety
finances
shareholding
environment
other
PUBLIC PARTICIPATION
Specific project or activity. Finite.
Decision-orientated
Neighbour relations programme
8
2002
social
project progress
production
![Page 30: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/30.jpg)
Session 5 - Appropriate PP – Good practice
![Page 31: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/31.jpg)
Background Information Document and comment sheet
Posters PowerPoint presentations
at meetings Small group and Focus
Group meetings Site visits to existing mine Media releases Radio Three-monthly 4-page
newsletter
A mix of written, visual and verbal methodologies
was used to share information
Information provision
![Page 32: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/32.jpg)
A mix of written, visual and verbal methodologies
was used to share information
Information provision
![Page 33: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/33.jpg)
Comprehensive public consultation at the start of the EIA for the proposed new mine:
Methodologies consisted of a mix of personal contact, written and visual information in lay person’s language.
Senior company personnel were present at most meetings to ensure that stakeholders perceived the company as being committed to public consultation, and to ensure that relationships were being built.
Personal interviews, small group meetings and focus group meetings (maximum 25 people) with different sectors of society were held in preference to large, emotive public meetings.
Information provision
![Page 34: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/34.jpg)
Documents that were available for stakeholder comment:
Full EIA and RAP reports (for more technically minded people), English and French
Summary of EIA report (in lay person’s language), English, French and Swahili
Comment sheets
Summary reports distributed in advance through- Personal delivery- Mail- Email- Web
Information provision
According to ability
![Page 35: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/35.jpg)
modern mining, mitigation of its impacts and benefits
Ghanaian legislation international lender and
good practice requirements
Substantial effort was put into building stakeholder capacity of:
Information provision
![Page 36: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/36.jpg)
Building capacity to participate
Explanatory posters
Background Information Document
Small group meetings
Information provision
![Page 37: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/37.jpg)
Not forgetting the process information
ScopingGetting issues and
suggestions
Impact assessment
Specialists evaluate and recommend
Environmental Report
Presents findings
Authority decision
May project proceed and what conditions?
Environmental Management Plan
Measures
EIA process
Environmental rights
Laws, regulations, how decisions will be made
Building capacity to participate
![Page 38: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/38.jpg)
Getting issues
Comment boxes at notice boards and Information Centres
![Page 39: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/39.jpg)
Site visits to the hill that will be mined
Getting issues
![Page 40: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/40.jpg)
Company personnel always sat in between stakeholders, never at a speakers’ table in the front.
This created a feeling of working together, rather than “Us and Them.”
Getting issues
![Page 41: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/41.jpg)
Getting issues
Open Houses included seating for Focus Groups where senior company personnel assisted to explain proposed project and members of the EIA team assisted to explain impacts and mitigation.
Open houses
![Page 42: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/42.jpg)
Senior company personnel met with smaller groups of stakeholders during Open Houses to build trust and show commitment. As these two photos show, initially angry
stakeholders relaxed and entered into discussion with the
company
Getting issues
![Page 43: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/43.jpg)
Giving feedback
Issues and response reportIssues and response postersSummary document
![Page 44: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/44.jpg)
COMMENTS/RESPONSE REPORT: REFLECTING STAKEHOLDER ISSUES BACK TO THEM
ISSUE RAISED COMMENTATOR RESPONSE
Issues related to water allocation
That crop farmers in this water management area have always had the major share of water, leaving little for other interprises
Mr Ben Hefer, Hernic Ferrochrome
In order to prevent the new plant from contributing to pollution, there has to be total assurance that the new plant is a closed system. WMB therefore thoroughly reviewed and confirmed that the designs put forward by the client are rigorous and is confident that it remains a closed system
Issues related to water quality
That the plant will use onemillion litres of water per day; that it be indicated whether there will be enough water for residential purposes and the plant
Ms Selinah Motha, Name Community, date
The residential areas of Brits will not experience decreased availability of domestic water as a result of the plant, as confirmed by the Local Council during the public meeting on 25 July
![Page 45: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/45.jpg)
![Page 46: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/46.jpg)
![Page 47: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/47.jpg)
![Page 48: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/48.jpg)
Giving feedbackSummary document including issues and responses
Full Issues and Response Report (over 100 pp) was available
![Page 49: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/49.jpg)
Emphasis was placed on potential impacts and how these could be mitigated during modern mining
Giving feedback
![Page 50: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/50.jpg)
Notice Boards, Information Points and
Comment Boxes
![Page 51: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/51.jpg)
Respect cultural diversity
![Page 52: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/52.jpg)
Session 7 - Designing the process
Chapter 8 of Guide
![Page 53: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/53.jpg)
Session 6 - Tailoring PP to suit project requirements
Design considerations Previous processes Degree of trust in authorities and
proponent Level of understanding of stakeholders Degree to which s/h are already organised Sectors of society in area Number of languages Degree of previous (or other) problems Local circumstances
![Page 54: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/54.jpg)
CRITERIA FOR DETERMINING SCALE OF IMPACTS AND SENSITIVITY
Scale and significance of impacts Size of footprint of impacts Greenfields vs Brownfields Aggregate and cumulative impacts Scale of impacts: national, provincial, local Number of issues
Sensitivity of receiving environment Important water catchment areas Major drainage lines Proclaimed nature reserves, National Parks Heritage Sites Areas of archaeological, cultural or historic value
![Page 55: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/55.jpg)
CRITERIA FOR DETERMINING SCALE OF IMPACTS AND SENSITIVITY (2)
Sensitivity of public perceptions Linked to sensitivity of receiving environment Areas with a “sense of place” Areas with a spiritual sense Fear of contamination Perceived past environmental neglect by government
or proponent Emotive issues (hazardous waste, relocation) Time pressure Recent negative press Tarnished neighbour relations
![Page 56: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/56.jpg)
LOW
HIGH
HIGHPublic sensitivity
Ris
ks /
im
pac
ts
Sensitive environment; hazardous materials; relocation; people’s pockets; people’s health; company reputation …
High risks / Impacts
High public Sensitivity
(Long complicated EIA)
Low risks / impactsHigh public Sensitivity
(“Standard” EIA)
High risks / impactsLow public Sensitivity
(“Standard” EIA)
Low risks / impacts
Low public Sensitivity
(Basic assessment)
HIGHCOST, HIGH PUBLICITY, LONG TIME
‘Pitching’ your process
![Page 57: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/57.jpg)
DETERMINING THE SCALE / PITCHING YOUR PROCESS
SCALE OF ANTICIPATED IMPACTS AND PUBLIC
SENSITIVITIESPUBLIC PARTICIPATION REQUIREMENTS
UP TO DSR COMMENT
VERY LOW • Advert, local paper• Letters and phone calls to immediate neighbours• DSR in local library
LOW • Advert, local paper• Letters and phone calls to neighbours,perhaps interview
neighbours• DSR to neighbours• DSR in local library
MEDIUM • Advert, local paper• Letters and phone calls to stakeholders• Background Information Document• Individual consultations/interviews• Letter announcing availability of DSR• DSR to stakeholders• DSR in public places• Stakeholder workshop
![Page 58: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/58.jpg)
DETERMINING THE SCALE (2)
SCALE OF ANTICIPATED IMPACTS AND PUBLIC
SENSITIVITIESPUBLIC PARTICIPATION REQUIREMENTS
UP TO DSR COMMENT
MEDIUM TO HIGH • Adverts, local and regional papers• Letters to stakeholders in footprint• Background Information Document, 2 languages• Community meeting/s• Individual consultations/interviews/focus groups• Letter announcing availability of DSR• DSR to stakeholders• DSR in public places• Public meeting
HIGH • Adverts, local, regional, national papers• Letters to stakeholders, broad range• Background Information Document, 3 languages• Community meetings• Individual consultations• Stakeholder/authority workshop• Proceedings as discussion document• Letter announcing availability of DSR• DSR widely distributed• DSR in public places• Public meeting
![Page 59: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/59.jpg)
Identify stakeholders (8.5 in Guide)
Use three dimensions of sustainability (Fig 15) Determine sectors of society according to Key
Stakeholder Figure (16) Use maps (Google Earth) Ask questions (p50 of Guide) Referrals – one farmer knows other neighbours Walk the area where practical Who plays big role in community? Chief, clergy,
women, youth?
![Page 60: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/60.jpg)
GENERIC OPEN HOUSE VENUE SET-UP
Registration Table
Tab
les
fo
r D
oc
um
en
t d
isp
lay
a
nd
ta
ke
-ho
me
ma
teri
al
Posters: Who is Company?
Posters: Environmental and Social Issues
Posters: Project Description
Tea Station
Po
ste
rs: C
om
pa
ny
Po
licy
/ prin
cip
les
/ Pro
ce
du
res
RegistrationLists, commentSheets, spare
documents
Small tables for impromptu focus group meetings
![Page 61: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/61.jpg)
Open Houses
Poster displays on walls, focus group
seating in centre of hall
![Page 62: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/62.jpg)
Document display table and take-home materials
![Page 63: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/63.jpg)
Open Houses
Document display table and take-home materials
Registration table
Full versions of documents available to those that want them
![Page 64: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/64.jpg)
Open HousesRegistration lists, comment sheets and documents on tables
Recording issues during Open House
![Page 65: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/65.jpg)
Open Houses
Company personnel conduct small-group briefings
Company personnel at hand to help stakeholders record issues
![Page 66: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/66.jpg)
Open Houses
Simple catering at most meetings
Sometimes just water or minerals
![Page 67: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/67.jpg)
Dry run before Open Houses
![Page 68: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/68.jpg)
Open HousesVery organised packing
Working in teams
![Page 69: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/69.jpg)
Open Houses
Security
Setting up the venue
![Page 70: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/70.jpg)
Session 8 - Case study – pp for an EIA
“Pitch your process” Identify stakeholders – just sectors, not organisations or individuals Design the pp process up to getting comment on the Draft Scoping
Report Identify stakeholders How will you announce the opportunity? How will you provide initial information? How will you get issues? How will you get comment on the Draft Scoping Report?
![Page 71: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/71.jpg)
Process design – sectors of stakeholders
![Page 72: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/72.jpg)
Process design – announce opportunity
![Page 73: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/73.jpg)
Process design – provide initial information
![Page 74: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/74.jpg)
Process design – get issues
![Page 75: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/75.jpg)
Process design – get comment on Draft Scoping Report
![Page 76: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/76.jpg)
Process design
![Page 77: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/77.jpg)
Was this course useful? Why?Three things I learned todayTwo things I will use in my workOne question I still haveIf you could take this course again,
what would you change?
One last task…..
![Page 78: Public participation in Environmental Authorization Erika du Plessis Golder Associates Africa (Pty) Ltd](https://reader037.vdocuments.site/reader037/viewer/2022102907/56649ddb5503460f94ad2ea2/html5/thumbnails/78.jpg)
Contact details
Erika du Plessis
Associate
Golder Associates Africa (Pty) Ltd
Regional Manager, West Africa
Stakeholder Engagement Specialist
Tel. +27 82 802 1309
33 A Senchi Street, Airport Residential, Accra, Ghana