pt solo ngawi jaya (snj) & pt ngawi kertosono jaya (nkj)
TRANSCRIPT
~SNJ ~ NKJ
COMPANY PROFILE & PROJECT FACTS
Introduction to Thiess Indonesia's Toll Road Companies:
PT Thiess Contractors Indonesia (TCI) is the investor in two toll road concessions on the Trans Java Toll Road (Trans Java) namely Solo - Mantingan - Ngawi and Ngawi ..:. Kertosono. These 35 year toll road concessions are to be delivered as Public-Private-Partnership (PPP) with subsidy, projects under the Government's initiative to enhance investment in badly needed infrastructure. The concession rights are held by two SPVs, namely:
• PT Solo Ngawi Jaya (SNJ) and • PT Ngawi Kertosono Jaya (NKJ).
On 28 June 2011, SNJ and NKJ signed the Concession Agreement (Perjanjian Pengusahaan Jalan ToljPPJT) with BPJT.
The Project:
The Trans Java consists of 11 Concessions, each of which consists of a number of Sections.
No Section
1 Cikampek - Palimanan
2 Palimanan Kanci 3 Kanci - Pejagan 4 Pejagan - Pemalang
5 Pemalang - Batang 6 Semarang - Batang 7 Semarang - Solo
8 Solo - Ngawi
9 Ngawi - Kertosono 10 Kertosono - Mojokerto
11 Surabaya - Mojokerto
Total
Concessionaire
PT Lintas Marga Sedaya
PT J asa Marga PT Semesta Marga Raya
PT Pejagan Pemalang Tol Road
PT Pemalang Batang Tol road PT Marga Setiapuritama
PT Trans Marga Jateng
PT Solo Ngawi Jaya PT Ngawi Kertosono Jaya
PT Marga Harjaya Infrastruktur
PT Marga Nujyasumo Agung
_ OflP.(";d
- pp
_ TnlI Rn;vt
Length Km 116.8
28.9
35.0
57.5
39.2
75.0
75.7
90.1
87.0
41.0
36.3
682.4
~SNJ ~ NKJ Location & Description:
• SNJ - Solo-Mantigan-Ngawi, is to be 90.10 km long. The western end (Solo) joins to the end of the Semarang-Solo toll road to be built by the Indonesian listed toll road entity Jasa Marga. SNJ has 6 interchanges, serving major towns adjacent to the alignment.
• NKJ - Ngawi-Kertosono, is to be 87.02 km long. It commences at the eastern termination of SNJ and ends near Kertosono where it connects with a further stage of the Trans-Java toll road which is already under construction. NKJ has 4 interchanges.
Both toll road sections will have a design speed of 120km/hr and initially 2 lanes each way, with provision for widening when required.
SNJ and NKJ form two sections of the Trans Java as shown in the map below:
"'-. , ~ .. ~ ,,~~., .-
t ~ " ___ •
Government Subsidy:
The Government has agreed to implement a subsidy by independently constructing specific portions of the toll roads, but with the concession holder then able to levy the toll on the total length.
Concession SNJ NKJ
Location Central and East Java East Java
Total Length 90.10 km 87.02km
GOI Subsidy Land: 100% Land: 100%
Construction: 23.20% Construction: 43.11 %
Construction Parts GOI: 20.90 km GO!: 37.51 km SNJ: 69.20 km NKJ: 49.50 km
Specifications:
Technical details for SNJ and NKJ are as follows:
Concession SNJ NKJ
Kartasura - Solo: 11.10km Beg.Project-Madiun: 19.68km
Solo - Kr. Anyar: 10.28km Madiun - Caruban: 8.54km Sections
Kr. Anyar - Sragen: 13.82km Caruban - Nganjuk: 29.79km
Sragen- Mantingan: 20.90km Nganjuk-End Project: 29.01km
SSNJ NNKJMantinsan - Nqawi: 30.19km
Ngawi - End Project 3.81km
No. of Lanes [email protected] [email protected] Wav 40-70m 40-70m
Interchanges 4 J
Bridges & Crossinss 140 100
Pavement t5rpe Rigid Concrete Pavement Rigid Concrete Pavement
tl CSJ COMPANY PROFILE & PROJECT FACTS
Introduction to Thiess Indonesia's Toll Road Company:
PT Thiess Contractors Indonesia (TCI) is the investor for a toll road concession on the Jakarta Outer Ring Road II (JORRII), namely Serpong - Cinere. This 35 year toll road concession is to be delivered as Public-Private-Partnership (PPP), under the Government's initiative to enhance investment in badly needed infrastructure.
The concession rights are held by a SPY, namely PT Cinere Serpong Jaya (CSJ) .
On 28 June 2011, CSJ signed the Concession Agreement (Perjanjian Pengusahaan Jalan ToljPPJT) with BPJT.
The Project:
The JORRII consists of 5 Concessions, each of which consists of a number of Sections.
No Section Concessionaire Length
KM
1 Cengkareng - Kunciran PT Marga Kunciran Cengkareng 15.22
2 Kunciran - Serpong PT Marga Trans Nusantara 11.20
3 Serpong - Cinere PT Cinere Serpong Jaya 10.14
4 Cinere - Jagorawi j Cimanggis PT Trans Lingkar Kita Jaya 14.70
5 Cimanggis - Cibitung PT Cimanggis Cibitung Tollways 25.40
6 Cibitung - Cilincing PT MTD CTP Expressway 33.90
Total 110.56
tl CSJ Location & Description:
The CSJ concession comprises one of the south western sections. The toll road is to be 10 km long, consisting of 3 lanes in each direction with a mixture of elevated structure and on grade construction, with one intermediate interchange. The road will have a design speed of 100km/h and will use a closed, manual tolling system at each interchange.
CSJ is a single section of JORRII as shown in the map below:
Government Support:
Concession CSJ
Location South Jakarta Total Length 10.14km
Gal SupportjResponsibility Land Capping and Land Revolving Fund
Specifications:
Technical details for CSJ are as follows:
CSJ
Serpong - Pamulang: 6.50 km Sections
Pamulang - Cinere: 3.64 km
No. of Lanes [email protected]
Right Of Way 40-60 m
Interchanges PamulangIC
Serpong Toll Road Junction
Bridges & Crossings 18
Pavement type Rigid Concrete Pavement
------End------