PS Planning
Fernando Pedrosa
2
Table of Contents
• Progress report on the activities between 12th December to 10th January 2020
• Works foreseen for the next 2 weeks
09-Jan-2020
3
12th December 2019As presented the 12th December 2019 / As performed
09-Jan-2020
4
13th December 2019As presented the 12th December 2019 / As performed
09-Jan-2020
5
16th December 2019As performedAs presented the 12th December 2019
09-Jan-2020
6
17th December 2019As performedAs presented the 12th December 2019
09-Jan-2020
7
18th December 2019As performedAs presented the 12th December 2019
09-Jan-2020
8
19th December 2019As performedAs presented the 12th December 2019
09-Jan-2020
9
20th December 2019As performedAs presented the 12th December 2019
09-Jan-2020
10
06th January 2019As performedAs presented the 12th December 2019
09-Jan-2020
11
07th January 2019As performedAs presented the 12th December 2019
09-Jan-2020
12
08th January 2019As performedAs presented the 12th December 2019
09-Jan-2020
13
9th January 2020
• LV consolidation
• Removal of the temporary
shielding blocks around
the LBE dump and BI line
(including evacuation
from the PS)
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
• Consolidate the slabs and
their supports on the
outer side of the ring
09-Jan-2020
14
10th January 2020
• Platform modification
• LV consolidation
• F16.QDN180 and
F16.STP176 re-
installation
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
• Consolidate the slabs and
their supports on the
outer side of the ring
• BHZ40 alignment
09-Jan-2020
15
13th to 15th January 2020 F61 line works
• Equipment installation
Cabling campaign C12
Installation of a rigid RF line for the SS88, SS89 and SS08 cavities
Cooling modifications for the BGI82 and BGI84
EN-CV cable installation between B355 and Septum pump in SS53
Longitudinal dumper installation works
PS SWY
activities in
the next slide
09-Jan-2020
16
13th January 2020
• Platform modification
• LV consolidation
• Install the F16.QDE180
• Install the F16.STP176
• Installation of the
“Potance” needed for the
F16.QFO165 removal
• LTB re-alignment
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
09-Jan-2020
17
14th January 2020
• Platform modification
• LV consolidation
• Removal of the
F16.QFO165 magnet
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
• LTB re-alignment
• TPS15 replacement
09-Jan-2020
18
15th January 2020
• LBS.DVT10 installation
• LV consolidation
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
• LTB re-alignment
09-Jan-2020
19
16th to 20th January 2020 F61 line works
• Equipment installation
Cabling campaign C12
Installation of a rigid RF line for the SS88, SS89 and SS08 cavities
Cooling modifications for the BGI82 and BGI84
Longitudinal dumper installation works
PS SWY
activities in
the next slide
09-Jan-2020
20
16th January 2020
• LBS.DVT10 alignment
• LTB re-alignment
• LV consolidation
• F16.STP152 (x2)
installation
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
09-Jan-2020
21
17th January 2020
• LV consolidation
• F16.STP152 (x2)
installation
• Installation of the BI line
vacuum pipe that goes
inside the shielding wall
• BI line drilling and
supports installation
• Cabling campaign PSB to
PS (BTP)
• Cabling campaign C12/23
(B355 to PS ring)
• LTB re-alignment
09-Jan-2020
22
20th January 2020
• LV consolidation
• Install the F16.QFO165
magnet
• Removal of the “Potance”
needed for the
F16.QFO165 removal and
installation
• LT.QDE70 installation
• BI line drilling and
supports installation
• Cabling campaign C12/23
(B355 to PS ring)
• Scaffolding installation
• Connection of all BTP
equipment to the services
in the area not affected by
the scaffolding
• LTB re-alignment
09-Jan-2020
23
21st January 2020 Start the MU90 re-installation
F61 line works
• Equipment installation
Cabling campaign C12
Installation of a rigid RF line for the SS88, SS89 and SS08 cavities
Cooling modifications for the BGI82 and BGI84
EN-CV cable installation between B355 and Septum pump in SS53
Longitudinal dumper installation works
PS SWY
activities in
the next slideMU90 re-
installation
09-Jan-2020
24
21st January 2020
• LV consolidation
• Cabling campaign from
the PSB (BI, LBE and
LBS lines)
• Cabling campaign C12/23
(B355 to PS ring)
• Scaffolding installation
• Connection of all BTP
equipment to the services
in the area not affected by
the scaffolding
• LTB re-alignment
• F16.STP152 (x2) +
F16.STP176 +
F16.QDE180 +
F16.QDN165 alignment
• LT.QDE70 Alignment
09-Jan-2020
25
22nd January 2020 Finish the MU90 re-installation
F61 line works
• Equipment installation
Cabling campaign C12
Installation of a rigid RF line for the SS88, SS89 and SS08 cavities
Cooling modifications for the BGI82 and BGI84
EN-CV cable installation between B355 and Septum pump in SS53
Longitudinal dumper installation works
PS SWY
activities in
the next slideMU90 re-
installation
09-Jan-2020
26
22nd January 2020
• LV consolidation
• Cabling campaign from
the PSB (BI, LBE and
LBS lines)
• Cabling campaign C12/23
(B355 to PS ring)
• Lifting rail installation
• Connection of all BTP
equipment to the services
in the area not affected by
the scaffolding
• LTB re-alignment
• F16.STP152 (x2) +
F16.STP176 +
F16.QDE180 +
F16.QDN165 alignment
• LT.QDE70 Alignment
ACCESS to LT, LTB, BI, LBE, LBS:
Preferably from B353/central ring
/gallery 3/MU27
09-Jan-2020
27
23rd January 2020 MU90 alignment
F61 line works
• Equipment installation
Cabling campaign C12
Installation of a rigid RF line for the SS88, SS89 and SS08 cavities
Cooling modifications for the BGI82 and BGI84
EN-CV cable installation between B355 and Septum pump in SS53
Longitudinal dumper installation works
PS SWY
activities in
the next slide MU90
alignment
09-Jan-2020
28
23rd January 2020
• LV consolidation
• Cabling campaign from
the PSB (BI, LBE and
LBS lines)
• Lifting rail installation
• Connection of all BTP
equipment to the services
in the area not affected by
the scaffolding
• LT vacuum connection
and pump down
ACCESS to LT, LTB, BI, LBE, LBS:
Preferably from B353/central ring
/gallery 3/MU27
09-Jan-2020
29
24th January 2020 F61 line works
• Equipment installation
Cabling campaign C12
Installation of a rigid RF line for the SS88, SS89 and SS08 cavities
Cooling modifications for the BGI82 and BGI84
EN-CV cable installation between B355 and Septum pump in SS53
Longitudinal dumper installation works
PS SWY
activities in
the next slide
09-Jan-2020
30
24th January 2020
• LV consolidation
• Cabling campaign from
the PSB (BI, LBE and
LBS lines)
• Scaffolding dismantling
• Connection of all BTP
equipment to the services
in the area not affected by
the scaffolding
• LT vacuum connection
and pump down
ACCESS to LT, LTB, BI, LBE, LBS:
Preferably from B353/central ring
/gallery 3/MU27
09-Jan-2020
31
TT2
Apart of the cabling campaign this week we
don’t have much activities
09-Jan-2020
B.151• RF ISTs approved
in the LS2C
• Vacuum works
09-Jan-2020
B.269 - Report• Cabling campaign C17 ongoing
• Cabling between transformers and switchboard ongoing
• New HVAC Unit under test
09-Jan-2020
B.269 – Next 2 weeksIn the coming 2 weeks we will have some co-activity in the building that has
been discussed and documented in specific VICs
Note:
Planning and conditions agreed in the VIC must be respected – any change
needed must be re-discussed and documented
09-Jan-2020
AC CablingWIC
Smoke detection installation
False floor tiles installation
AC + C17 Cabling
B.355 – Next 2 weeks
TFB equipment
installation
C18b cabling
campaign
TE-EPC maintenance
works
EN-CV works in the new PS
CV cooling station
09-Jan-2020
36
B.359 – next 2 weeks
09-Jan-2020
TE-ABT control
works
AOB
• We are experiencing some difficulties on having the EDH
transport request made on time
• Please discuss the EDH requests with Yann if you have
questions and do it at least 1 week in advance for
everything that is in the planning
• If possible we would like to ask the equipment responsible
to remove the LTB line equipment shown in the picture to
avoid it gets damaged by accident:
09-Jan-2020
AOB
Sector under vacuum
• SS70 to SS80
• SS01 to SS10
09-Jan-2020