proposed genrl instructions cement concrete allied works jp 03,04,05,07
TRANSCRIPT
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
1/23
General Instructions for Concreting Works:
1. At least one week before commencing the construction of any massive concrete section the SiteEngineer has to consider all aspects so as to prevent concrete cracking or loss of strength
of concrete due to release of heat of hydration and drying shrinkage behavior etc., and on
satisfaction only casting massive concrete sections are to be taken up as noted on the
drawings or as identified by Client Engineers.
2. All concrete is to be mixed in mechanically operated batch mixers complying to IS: 1791 andshall be of approved make with suitable provision for correctly controlling the water delivered
to the drum. Weigh batchers shall conform to IS:2722 and shall be capable of controlling the
weights to within one percent of the desired value. Batching Plants shall conform to IS: 4925.The mixers, weigh batchers and batching plant etc. shall be maintained in clean and serviceable
condition. Accuracy of all equipment is to be periodically checked and recorded by the QC
Lab.
3. Materials: All materials such as Coarse and Fine Aggregates, Water and Cement conform torespective Specifications. Method of Procurement, Storage of materials and quality procedures
are subjected to periodical checks record of which are to be maintained in the QC Lab.
3.1.Aggregates
Any or All Tests for Aggregates as required by Client as per IS:2386 Parts-I to VIII. shall becarried out for the aggregates. The acceptance criteria of the samples tested shall be as per
the relevant IS.
For reinforced concrete work, coarse aggregates having a nominal maximum size of 20mm
shall be used. For reinforced concrete works with large pours with no restriction to the flow of
concrete, at such locations/sections aggregates having a nominal maximum size of 40mm or
above may be used with the permission of the Client Engineers. And In concrete elements with
sections of thickness less than 100mm, closely spaced reinforcement or small cover, aggregate
with maximum nominal size of 10mm is to be used.
For heavily reinforced concrete members such as in the case of ribs of main beams, the nominalmaximum size of the aggregate shall usually be restricted to 5mm less than the minimum clear
distance between the main bars or 5mm less than the minimum clear cover to reinforcement,
whichever is smaller.
3.2 Cement
Ordinary Portland cement of 43 grade or 53 grade as per IS: 8112 or IS: 12269 respectively
shall be used in concrete. For mix design, water cement ratio shall generally be as per Table 5
of IS:456, but would not exceed 0.45. The minimum cement content shall also be be as per
Table 5 of IS: 456. Chloride free sulphonated melamine based super plasticizer conforming to
IS: 9103 would be used as per mix design and manufacturers instructions to improve
workability
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
2/23
3.3 Water
Water for use in concrete shall be clear and free from injurious oils, acids, alkalis, organic
matter, salt, silts or other impurities. Normally potable water is found to be suitable. Generally,
IS: 3550 will be followed for routine tests. In case of doubt, the acceptance test for water shall
be as per IS: 3025 and Table-I of IS:456.
3.4 Admixture
Quality admixtures as directed or permitted by the Engineer-in-Charge will be used. The
admixture shall conform to requirements of IS: 9103. Chloride free sulphonated melamine
based super plasticizer conforming to IS: 9103 would be added as per mix design and
manufacturers instructions to improve workability.
3.5
Nominal Mix Concrete
a) Nominal mix concrete shall be used only for plain cement concrete works and as indicatedin the drawings or as approved specifically by the Client Engineer. No trial mixes are done
for this concrete other than mixing in a mechanical mixer.
b) While proportioning concrete, the cement is to be measured by weight and Aggregates maybe determined by volume (for corresponding weight) but preferably by weight. Fine
aggregates if moist, the amount of surface water shall be determined and allowance shall be
made for bulking in case of volume batching, in accordance with IS:2386 (Part III). Moisture
correction is to be made for surface water present in the aggregates and recorded data is to
be recorded and maintained by the Field QC Lab to the satisfaction of the Engineer.c) The recommended proportions for Nominal Mix Concrete are specified in Table 1.
Table 1
Recommended Proportions for Nominal Mix Concrete
Grade of
Concrete
Total Quantity of Dry
Aggregates by Mass
per 50 Kg of Cement
Proportion of Fine Aggregate to
Coarse Aggregate (by Mass)
Quantity of
water per
50 Kg of
Cement,
M 5 800Generally 1:2 but subject to an
upper limit of 1:1.5 and a lower
limit of 1:2.5
60 ltrs.M 7.5 625 45 l
M 10 480 34 l
M 15 330 32 l
M 20 250 30 l
Note: The proportion of fine to coarse aggregates shall be adjusted from upper limit to lower
limit progressively as the grading of fine aggregates becomes finer and the maximum size of
coarse aggregate becomes larger. Graded coarse aggregate shall be used.
e) If nominal mix concrete made in accordance with specified proportions does not yield thespecified strength of the corresponding grade and fails to satisfy the requirements of"Acceptance Criteria for Concrete" as specified in IS:456 is to be mutually agreed upon with
Client Engineers.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
3/23
f) Nominal mix proportion shall not be classified as higher grade proportion on the ground thatthe test strengths are higher than the minimum specified.
4.3.2 Design Mix Concrete
a) Design Mix Concrete shall be used on all concrete works, except where specified otherwise
or specially permitted by the Engineer. The mix shall be designed for all grades of concrete
(except those specified under Nominal Mix Concrete) to obtain required characteristic
strength not less than the appropriate values given in Table 2. Using standard deviation
specified in IS: 456, the minimum value of target strength of design mix of various grades of
concrete shall be as per Table 2.
Table 2
Grades of Concrete
Note: The above values correspond to site having essential pre requisites such as proper
storage of cement;-weigh batching of all materials, ;Controlled addition of water; Regular
checking of all materials;-Provisions for aggregate gradings; and moisture content checks and
periodic checking of workability and strength etc., Deviation to above Preliminary Test strength
asterisk marked values are to be adopted.
b) In proportioning the concrete, the quantities of both cement and aggregates is to be determinedby mass. At the discretion of the Engineer quantity of aggregates may be allowed to be
determined by an equivalent volume basis after establishing the relationship between weightand volume after several trials and the same being verified periodically. Water shall either
be measured by volume in calibrated tanks or weighed. All measuring equipment, at site, is to
be maintained in a clean, serviceable condition, with their accuracy duly calibrated.
c) To keep the water-cement ratio to designed value, allowance are to be made for the moisturecontents to both fine and coarse aggregates and determined in accordance with IS: 2386 (Part
III). Daily recording of the same or as directed by the Engineer. Trial mix as required shall be
carried out accordingly.
d) Water quantity may be increased to any of the concrete grades with prior permission of
Engineer. Cement quantity, in such cases, shall also be increased pro rata to maintain thewater cement ratio constant as adopted during preliminary tests to that of the corresponding
grade of concrete.
Grade
Designation
of
Compressive strength of a 150 mm cube at 28 days
in ( N/mm2)
Preliminary Test Strength
(target strength of trial mix)
Characteristic
strength
on works cubes
M 15
M 20
M 25
M 30M 35
21 /
22*
27 /
28*32 /
1
5
20
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
4/23
e) Suitable admixture shall be used to improve cohesion & workability, without compromising onthe quality of concrete.
4.3.3 Mix Design
a) Prior to actual commencement of the work Preliminary tests/ trial mix, as specified or as
required by the Engineer, to arrive at the grading of aggregates, for different grades of
concrete is to be made from representative samples of aggregates and cement that are
expected to be used on the works. The water-cement ratio, workability and the quantity of
cement required to give Preliminary (target)compressive strengths as specified in Table 2 are
arrived at. The mix so designed (and not the method of design) shall be approved by the
Engineer.
Type of cement and minimum cement contents for different exposures and sulphate attack
shall be as per IS: 456. However, if higher value is obtained due to strength consideration
from trial mix, minimum cement content shall be as per the requirement of trial mix.
b) At least three trial mixes shall be made and a minimum of six test cubes taken for each trialmix. Slump for each type of mix shall be checked. Three cubes from each mix, after proper
curing, shall be tested in a laboratory (approved by the Engineer) after 7 days and balance
three cubes checked after 28 days to obtain the compressive strength. Over wet mixes are to
be avoided while preparing for the design mixes
c) The Test reports of mix design are submitted to Client Engineers for his review, indicatingdesign criteria, analysis and proportioning of materials etc. The reports shall also include
design mix particulars, graphs and curves etc., indicating the permissible variation in the
grading of aggregates. These test reports shall form the basis for finalisation of mixproportion by mass and the water-cement ratio indicating achieving desired characteristic
strength and workability. The approved proportions for different grades of concrete shall not
change during all concreting operations unless there is a change in quality of the materials.
In case of change in the quality of materials or characteristic strength of concrete or water
cement ratio or workability, arrangements are made for carrying out similar trial mixes and
Preliminary tests and the revised mix proportions and water-cement ratio are ascertained
afresh.
d) At locations, where compaction of concrete is not possible by
vibration, e.g. casting of piles, the method of compacting concrete cubes for preliminary / trialmixes and work tests shall be in the similar manner to that of the compaction method
proposed to be that as used at site actually during concreting.
4.3.4 Workability of Concrete
a) At frequent intervals the workability of concrete shall be subjected to checking. Theworkability of concrete is measured in accordance with IS:1199 for every sample taken
for testing and recorded with corresponding cube test result.
b) The degree of workability depends on type and nature of the structure and is to be based onexperience and tests. Ranges of workability for different placing conditions of concrete shallconform to IS: 456. This is essential to to know about how well the concrete is
compacted and worked into the corners of formwork and around the reinforcement and
renders to achieve the required surface finish.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
5/23
4.3.5 Mixing of Concrete
a) Concrete may be mixed in a mechanical mixer conforming to IS: 1791. However, mixingpreferably may be done at a single central batching plant, conforming to IS: 4925, located
within the Project area allocated. The plant shall have a mechanically operated mixer of an
approved size and type, capable of ensuring a uniform distribution of the materials throughoutthe mass. The mass shall be uniform in colour and consistency.
b) Water shall not be added into the drum of the mixer, until all the cement and aggregatesconstituting the batch are already in the drum and dry mixed for at least one minute and are
uniformly distributed. Water added subsequently and mixing of each batch is continued
until there is a uniform mixing of the materials takes place the mass becomes uniform in
colour and consistency. In no case mixing is done for less than two minutes and less than 40
revolutions. Despite, this if there is segregation after unloading from the mixer, the concrete
shall be remixed. When absorbent aggregates are used or when the mix is very dry the
mixing time shall be extended as directed by the Engineer,.Do not over load the Mixers
beyond its rated capacity as this prevents thorough mixing of the batch.
The accuracy of measuring equipment shall be within 2 percent of the quantity of cement
being weighed and within 3 percent of the quantity of aggregate, admixtures and water
being weighed.
c) The entire contents of the drum are to be discharged before ingredients for e next batch arefed into the drum. No partly set or remixed or excessively wet concrete shall be used and it
shall be immediately removed from site. Each time if the work stops for more than 30
minutes, the mixer shall be thoroughly cleaned and when the next mixing commences, the
first batch shall have 10% additional cement.
d) Dosages of retarders, plasticizers and super plasticizers shall generally be restricted to 0.5, 1.0and 2.0 percentages respectively by weight of cementitious materials. However,
recommendations of manufacturer are also to be considered in this regard.
4.3.6 Concrete Conveying
a) Concrete shall be handled and conveyed as rapidly as practicable, from the place of mixing tothe place of final laying, by approved means, before the initial setting of the cement starts.
Concrete shall be conveyed in such a way that there is no segregation or loss of any of the
ingredients or ingress of foreign matter or water and the required workability is maintained.
During very hot or cold weather, as directed by the Engineer, concrete shall be transported in
deep containers so as to reduce the rate of water loss by evaporation in hot weather and heat
loss in cold weather.
b) Conveying equipment for concrete shall be mortar tight, well maintained andthoroughly cleaned before commencement of concrete mixing. Such equipment shall be kept
free from set concrete. Chutes shall not be used for transport of concrete without the written
permission of the Engineer. The chute, in case permitted , Chutes shall be of such size and
design which ensures practical continuous flow. Slope of the chute is to be so adjusted that
the concrete flows with out the use of excessive quantity of water and without segregation of
its ingredients. Chutes, on approved for use, shall have slopes not flatter than 1 vertical: 3horizontal. The delivery end of the chute shall be as close as possible to the point of deposit.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
6/23
c) Concrete shall be conveyed and placed by mechanically operated equipment e.g. Concretepumps or pneumatic placers with due permission of the Engineer, who shall also review
the entire scheme for which comprehensive details as required is to be furnished by the SiteEngineers..
4.3.7 Concrete Placing
a) Concrete shall be placed and compacted in its final position prior to onset of initial setting ofthe concrete and it shall be compacted in its final position within minutes of discharge from
the mixer.
b) Where ever direct placement is not possible, suitable arrangements such as chutes, tremie,elephant trunks etc. to confine the movement of concrete as directed by the Engineer are to be
made by the Site Engineers. Concrete shall not be dropped from a height or handled in a
manner causing segregation. As a general guidance, the maximum permissible free fall for
the concrete shall be limited to 1.0m.
c) Concrete placed by pumping, minimum for conveyance shall be ensured .As a generalguideline, clause 7.0 of IS: 456 is to be followed.
Prior to commencing regular pumping, the pipeline is to be lubricated by cement mortar
(1:2) and once pumping commences, stoppages shall be avoided. Care is be taken to see that
cement mortar does not get discharged in the structure being concreted.
d) Concrete shall not be placed in foundations on soft areas or where there is stagnant water ordebris is present. Such soft areas shall be removed and filled with M10 nominal mix concrete
(1:3:6) or as directed by the Engineer.
e) When ever concrete is to be laid on or in the vicinity / adjacent to rock surfaces, rock is to bechecked for its soundness. On sloping rock faces, rough steps or benches are to be made and
concrete placed.. Prior to pouring concrete, the rock surface is to be thoroughly cleaned with
a high pressure water and air jet and kept wet for three hours. Excess water if any from
depressions is to be dried and the rock surface dried and a 10 mm thick cement-sandmortar (1:6) layer shall be placed and worked into all crevices, cracks, depressions etc.,
f) The placing of concrete shall be a continuous operation with no interruptionof more than 30 minutes between the placement of continuous portions of concrete. Concrete
shall be placed in continuous horizontal layers of 150 mm or higher thickness as directed by
the Engineer and layer shall be thoroughly compacted before placing next layer. The thickness
of each layer shall be such that it is deposited before the previous layer has stiffened. When
placing concrete through reinforcing steel, care shall be taken to prevent segregation of the
coarse aggregates.
g) Slots, openings, holes, pockets etc. are to be provided in the concrete as per drawings or asdirected by the Engineer.
h) Slabs, beams and similar concrete members shall normally be poured in one operation. Inspecial circumstances, with the approval of the Engineer, these can be poured in horizontal
layers, but care must be taken to ensure that the under layer is not hardened. Bleeding of
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
7/23
under layer, if any, shall be effectively removed. Moulding, throating, drip course etc. shall be
poured as indicated on the drawings or as directed by the Engineer.
j) After the concrete has been placed, it shall be spaded and thoroughlycompacted by approved mechanical vibrators conforming to IS: 2505, IS: 2506, IS: 2514 and
IS: 4656 to a maximum subsidence without segregation and thoroughly worked around
reinforcement or other embedded fixtures into the correct form and shape. Care must be taken
to ensure that the inserts, fixtures, reinforcement and formwork are not displaced or disturbed
during placing of concrete.
k) Vibrators shall penetrate both the layer poured and the under layer to ensure good bond andhomogeneity and prevent the formation of cold joints. Immersion vibrators shall not be
allowed to come in contact with steel reinforcement after start of initial set. Also, they shall
not be allowed to come in contact with forms or finished surfaces.
l) Immersion vibrators shall have a 'no load' frequency, amplitude and
acceleration as per IS: 2505 depending upon the size of the vibrator. Immersion vibratorsshall be operated by experienced personnel. These vibrators shall be immersed not more than
450 mm apart and withdrawn when air bubbles cease to come to the surface. Such vibrators
shall always be immersed vertically into the concrete and in no case these shall be used to
push concrete inside the forms and vibrators shall be withdrawn slowly.
m) For vibrations to be applied externally, the design of formwork and the disposition ofvibrators shall receive special consideration to ensure efficient compaction and to avoid
surface blemishes. Surface vibrators and form attached vibrators shall be permitted only for
pre-cast elements. These are used with written approval of the Engineer.
n) No concrete shall be placed in wet weather or on a water covered surface. If there has beenany sign of washing of cement or sand, the entire concrete shall be removed immediately.
Suitable precautions shall be taken in advance to guard against possible rains before leaving
the fresh concrete unattended.
o) Mass concrete shall be poured in lifts not exceeding 1.0 m in height unless otherwise indicatedon drawings or directed by the Engineer.
4.3.8 Protection and Curing of Concrete
a) Newly placed concrete is to be protected by approved means from rain, sun and wind.Concrete placed below ground level is to be protected from falling earth, during post placing
operations. Concrete placed on ground containing any deleterious substances is to be kept
free in the vicinity. All seepages of water in the vicinity of such ground should be
maintained dry during and post placing of concrete for a period of at least seven days or as
otherwise instructed by the Engineer.
b) The ground water around newly poured concrete shall be kept down to an approved level bypumping or other approved means of drainage. Adequate steps are to be taken to prevent
floatation or flooding. Steps, as approved by the Engineer, are to be taken to protect
immature concrete from damage by debris, excessive loading, vibration, abrasion, mixing
with earth or other deleterious materials etc. that may impair the strength and durability of the
concrete.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
8/23
c) As soon as the concrete is hardened sufficiently for the surface not to be marked, it shall bekept in a damp or wet condition by ponding or by covering with a layer of sacking, canvas,
hessian or similar materials and kept continuously wet for at least seven days after final setting
in case of Ordinary Portland Cement and at least for 10 days where mineral admixtures or
blended cements are used. The curing period shall not be less than 10 days for concrete
exposed to dry and hot weather conditions in case of Ordinary Portland Cement and at least 14
days where mineral admixtures or blended cements are used. Curing of horizontal surfaces
exposed to drying winds shall begin immediately after the concrete has hardened. Concrete
slabs and floors shall be cured for the periods mentioned above by flooding / ponding water
to minimum 25 mm deep
d) Approved curing compounds may be used in lieu of moist curing only with the permission ofthe Engineer. Such compounds shall be applied to all exposed surfaces of the concrete, as
soon as possible after the concrete has set.
e) Quantity of water applied shall be such as to prevent erosion of freshly placed concrete.
4.3.9 Construction Jointsa) When ever work is required to be interrupted, the concrete shall be rebated and/ or keyed at
the joint to such shape and size as required by the Engineer or as shown on the drawings. All
vertical construction joints shall be made with stop boards, which are rigidly fixed and
slotted to allow passage to reinforcing steel. In the case of water retaining structures,
basements, tunnels etc. water stops of approved material is to be provided, as per clause
12.4 of IS:456 and as specified on the drawings or as directed by the Engineer.
b) Construction joints shall be located as indicated the approved drawings. Where ever not
specified/indicated, the joints shall be in accordance with the following guidelines:
i) In a column, the joints shall be formed about 75 mm below the lowest soffit of thebeams framing into it, including haunches, if any. In flat slab construction, the joint
shall be 75 mm below the soffit of the column capital.
ii) Concrete in a beam shall be placed throughout without a joint. If unavoidable, the jointshall be vertical and within the middle-third of the span. When a beam intersects a
girder, the joints in the girder is to be l be given an offset equal to a distance twice the
width of the beam and additional reinforcement provided for shear. The joint shall bevertical throughout the full thickness of the concrete member.
iii) A joint in a suspended floor slab shall be vertical at one quarter points of the span andat right angle to the principal reinforcement.
iv) Construction joints in equipment foundations are to be avoided.
v) Vertical construction joints in water retaining structures is not permitted unlessindicated on the drawings.
vi) Construction Joints shall are to be placed at accessible locations to permit cleaning outof laitance, cement slurry and unsound concrete, in order to create rough / uneven
surface.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
9/23
However, any adjustments in the location of construction joints ( suiting site conditions)
from those shown on drawings or from those explained above, prior approval from
Engineer is to be taken.
c) Before fresh concrete is placed, the cement skin of the partially hardened concrete pouredearlier is to be thoroughly removed and surface made rough and aggregate exposed, by wire
brushing, hacking, water jetting, air jetting or any other method as directed by the Engineer.The exposed rough surface is to be thoroughly wetted for about 1/2 hour, allowed to dry and
then coated with 5 to 10 mm thick layer of freshly mixed cement sand slurry. The ratio of sandto cement and water to cement in this slurry shall be same as that of new concrete to be
placed. Special care is to be taken to see that the first layer of concrete placed after a
construction joint is thoroughly rammed against the existing layer.
d) In forming a joint, concrete should not be allowed to slope away to a thin edge. The location ofconstruction joints is to be planned by the Site Engineer well in advance of pouring. These
joints are to be approved by the Engineer. The Site Engineers proposals include the location of
construction joints, the sequence of pouring, formwork details and their stripping times.
f) Where ever the concrete is not fully hardened, all laitance is to be removed by scrubbing thewet surface with wire or bristle brushes, care being taken to avoid dislodgement of particles of
aggregate. The exposed surface wetted thoroughly and all free water is removed. The
exposed surface is to be coated with neat cement slurry. On this surface, a layer of concrete
not exceeding 150 mm in thickness is to be placed first and rammed well rammed against old
work, particular attention being paid to corners and close spots. Thereafter, proceed in normalmanner .
g) Suitable time gap is to be maintained between the setting of the earlier
placed concrete and the commencement of next concrete pour for multiple lift work. The timegap shall be a minimum of 4 hours for columns, piers or walls and 24 hours for beams, girders
or slabs.
h) A construction joint should preferably be placed in a low stress zone and at right angle to thedirection of the principal stress.
4.3.10 Work in Extreme Weather Conditions
During hot weather (atmospheric temperature above 40C) or cold weather (atmospheric temp
at 5C and below) the concreting shall be done as per the procedures and precautions set out in
IS: 7861 (Parts I and II).
Temperature during pouring of Concrete shall be in the range < not less than 5 degreesCentigrade and not more than> 38 degree Centigrade.
When pouring concrete in very hot weather, precautions are to be taken to maintain
temperature of wet concrete below 38 degrees Centigrade. This shall be achieved by stacking
aggregates under the shade and keeping them moist by constant spraying of chilled water and
using ice flakes, reducing the time between mixing and placing to the minimum, cooling the
formwork by sprinkling water, starting curing before concrete dries out etc. However, before
mixing/ placing concrete, when conditions vary to specified temperatures on either sides,
approval of Engineer is to be obtained for execution methods.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
10/23
4.3.11 Inspection, Cleaning and Finishing of Concrete
a) All concrete surfaces shall have even and clean finish free from honeycombs, air bubbles, finsor other blemishes, unmarred and reasonably smooth. Panels and form linings shall be of
uniform size and be as large as practicable and installed with closed joints. The formwork joint
marks on concrete work exposed to view are to be rubbed with carborandum stone and defects
repaired with a paste of cement-sand mortar (1:2) and cured. The finish shall be made to the
satisfaction of the Engineer. Concrete surfaces are to be subsequently plastered or brick work
as required is to be taken up after adequate hacking to ensure proper bonding.
b) Immediately after removal of forms, the concrete is to be inspected and defective areas aspointed out by the Engineer are to l be removed and replaced by sound concrete as directed
by the Engineer. Holes, left by form bolts etc. are to be filled up and made good with cement
sand mortar of approved mix. All superficial defects such as honeycombing, rough patches
etc. are to be made good. If the defective area is at a vulnerable location. e.g. at the ends of
beams & columns etc. then it may be necessary to cut out the member completely or in part
and reconstructed as per directions of the Engineer.
c) Epoxies are to be used on approval of Engineer. Poured concrete affected by faultyformwork is to be removed totally and replaced. As per directions of the Engineer grouting /
shotcreting is to be resorted for repairs of the area / element .
d) Proper care is to be taken to avoid rejection of Concrete subsequent to pouring. Visiblepresence of porous or honey-combed mix, or wherever the placing has been interrupted
without providing a proper construction joint, or the reinforcement got displaced beyond
specified tolerances or construction tolerances have not been met, the concreting is liable for
rejection.
e) Generally, repair work shall consist of any or all of the following operations:-
i) Sack rubbing with mortar and stoning with caboundum stone.ii) Cutting away the defective concrete to the required depth and shape.iii) Cleaning of reinforcement and embedments.iv) Roughening by sand blasting or chipping.v) Installing additional reinforcement/welded mesh fabric.vi) Dry packing with stiff mortar.vii) Plastering, guniting, shotcreting etc.
viii) Placing and compacting concrete in the void left by cutting out defective concreteix) Grouting with cement sand slurry of 1:1 mix. .
4.4 Sampling and Testing
4.4.1 General
a) Concrete cubes for work tests are to l be cured under laboratory conditions, except when inthe opinion of the Engineer, extreme weather conditions prevail, at which time, these may
require curing under job conditions.
b) For the purposes of statistical analysis, any substandard cube result, which in the opinion ofthe Engineer is due to improper sampling, moulding or testing, is to be discarded and a
dummy result shall be substituted. The value of a dummy result shall be equivalent to the
average value of the cubes from the same grade of concrete tested immediately before and
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
11/23
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
12/23
floor. However, the reservoir shall be retested and the walls shall also be treated if required
by the Sub-contractor.
v) The reservoir/ tank shall be retested as described above or asdirected by the Engineer for water tightness after rectification. The reservoir / tank shallbe treated and tested again, if leakage is observed during retesting.
g) For basement type structures like track-hopper tunnel, neutralising pit etc. the test for ingress
of sub-soil water shall be carried out and leakages shall be rectified.
4.4.2 Sampling of Concrete
a) Sampling Frequency
i) Trial Mixes: At least three trial mixes are to be made with min. 6 testcubes for each mix.
ii) Works tests: The minimum frequency of sampling of concrete of each grade shall beaccording to IS: 456. However, after getting continuous satisfactory results and in case
of voluminous concrete work, the Engineer may at his discretion reduce the frequency
of sampling as follows:
For each grade of concrete, and for each 8 hours (shift) of work or part thereof, at least
one sample consisting of six specimens shall be taken from each 100 cum of concrete
or part thereof. 3 specimens shall be tested at 7 days and remaining 3 shall be tested at
28 days. However, in all cases, the 28 days compressive strength shall be the criterion
for acceptance or rejection.
b) To control the consistency of concrete from every mixing, slump tests and compaction factor
tests in accordance with IS: 1199 are to be carried out every two hours or as directed by the
Engineer. Slumps corresponding to the test specimens are to be recorded for reference.
Concrete sampling for te, making test specimens, curing and testing procedure etc. shall be as
per IS:516 and IS:1199 with specimen size being 15 cm cubes. Normally, only compression
tests are to be performed apart from other tests as per IS: 516. Sampling procedure, frequency
of sampling and test specimen shall conform to clause 15 of IS: 456. Acceptance criteria for
the concrete shall be in accordance with clause 16 of IS: 456. Concrete work found unsuitable
for acceptance is to be dismantled and replaced/redone as per approved specification. During
dismantling, care is to be taken to avoid damages to embedded items or adjacent structures.
Despite precautions if any damages takes place the same are to be made good to the
satisfaction of the Engineer.
4.4.3 Acceptance Criteria
a) The acceptance criteria of concrete shall be in accordance with IS: 456. The concrete shall be
deemed to comply with the strength requirements when both the following conditions are
satisfied:
i) The mean strength determined from any group of four consecutive test results complies
with the appropriate limits in column 2 of Table 3.
ii) Any Individual test result complies with the appropriate limits in column 3 of Table 3b) Unacceptable concrete work shall be dismantled and replaced by fresh work, meeting the
specification requirements. In the course of dismantling, if any damage is done to the
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
13/23
embedded items or adjacent structures, the same shall be made good, to the satisfaction of
the Engineer.
Table 3
Characteristic Compressive Strength Compliance Requirements
Specified
Grade
Mean of the Group of 4 Non Overlapping
Consecutive test results N/sqmm)
Individual Test
Results (N/sqmm)
M 15 fck + 0.825 X established standard deviation
(rounded off to nearest 0.5 N/sqmm)
or fck+3 whichever is greater
fck - 3
M 20 or
above
fck + 0.825 X established standard deviation
(rounded off to nearest 0.5 N/sqmm)
or fck+4 whichever is greater
fck - 4
Note: In the absence of established value of standard deviation, the values given in Table
4 may be adopted and attempt shall be made to obtain result of 30 samples as early as
possible.
Table 4
Assumed Standard Deviation
Grade of Concrete Assumed Standard Deviation(N/sqmm)
M10, M15 3.5M20, M25 4.0
M30 to M50 5.0
Note: The above values correspond to the site control having proper storage of cement,
weigh batching of all materials, controlled addition of water, regular checking of all
materials, aggregate gradings and moisture content; and periodic checking of workability
and strength. Where there is a deviation from the above the values given in Table 4 shall
be increased by 1 N/sqmm.
4.4.4 Load Test
If any work is found unacceptable whereupon the Engineer requires its removal and
reconstruction, and if requests for retesting is made, the same shall be load tested in
accordance with the provision of IS:456 as given below :
a) Load tests shall be carried out as soon as possible after expiry of 28 days from the time ofplacing of concrete. The structure shall be subjected to load equal to full dead load of the
structure plus 1.25 times the imposed load for a period of 24 hours and then the imposed load
shall be removed. Dead load includes self weight of the structural members plus weight of
finishes and walls or partitions, if any, as considered in design. Struts strong enough to take
the entire superimposed, dead and imposed loads are to be placed in position, leaving a smallgap under the members.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
14/23
b) The maximum deflection shall be measured after the test load is in position for 24 hours.Thereafter, the test load shall be removed.
c) 24 hours after removal of the load, if the structure does not show a recovery of at least 75percent of the maximum deflection, registered as in (b) above, the test shall be repeated after
a lapse of 72 hours. The structure shall be considered to have failed to pass the test if the
recovery after the second test is less than 80% of the maximum deflection during the second
test.
d) If the maximum deflection in mm, shown during 24 hours under load, is less than 40 l2/D,where l is the effective span in m and D is overall depth of the section in mm, it is not
necessary for the recovery provision of the above mentioned clauses to be applied.
e) If the member shows evident failure, changes as necessary to make the structure adequatelystrong, are to be undertaken as per directions of the Engineer. Under Statutory Regulations
and as per discretion of the Engineer, the structure under test or a portion thereof may be
retained as such without any modification also by de rating its load bearing capacity,
provided the design criteria allows such de rating.
f) A reinforced concrete beam, floor or roof shall be deemed to have passed the test, if themaximum deflection at the end of 24 hours does not exceed the deflection given in clause
16.5 of IS: 456. If a portion of the structure is found to be unacceptable, it shall be dismantled
and replaced by a new structure as specified. If, in the course of dismantling, any damage
done to the embedded items and or other adjacent structures, is to be made good, to the
satisfaction of the Engineer.
5.0 GROUTING
Furnishing and placement of grout in block outs, foundation bolt holes and underpinningof base plates with proper side shuttering.
5.1 General Requirements
5.1.1 The space between the top surface of the foundation, the underside of the base plate,
pockets, etc are to be filled with appropriate grout by providing proper side form work to
retain the grout.
5.1.2 Crushing strength of grout shall be at least one grade higher than the foundation concrete.
The minimum crushing strength of grout shall be 25 N/mm2. The grout strength for
machine bases shall be based on the recommendations of equipment manufacturer.
5.1.3 The contact area between the grout and base plate shall not be less than 90%.
5.2 Grout Materials shall be in accordance with Technical specification
5.2.2 For flow able grout, clean and well graded sand conforming to grade zone-4 shall be used.
5.2.3 Admixtures
Non-shrink grouting admixtures of approved make shall be used.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
15/23
5.3 Mixing and Placing
5.3.1 Ready mixed non-Shrink cementitious grouts
Mixing and placing of Ready mixed non-Shrink cementitious grouts shall be according to
manufacturers recommendations.
5.3.2 Type of Mix for other grouts
Generally following two types of grout mix are used:
a) Cement-Sand Grout: The proportion of cement to sand shall generally be 1:2, unless
otherwise specified.
b) Cement Aggregate Grout: The approximate proportions of cement, sand and coarse
aggregate shall be 1:1.25:2, with a maximum size of aggregate as 10mm. This mix shall be
used for grout thickness above 40 mm.
5.3.3 Mixing
Depending upon the case of placement and method of application, following shall be thegrout consistencies.
a) Fluid mix: Water-cement ratio shall be between 0.5 and 0.6. Plasticizer conforming to IS:9103 may be added to increase workability, wherever required. This grout mix shall be
suitable for application with low pressure grouting equipment like pressure grout pump of
adequate capacity or self flowing and suitable for grouting of pockets / blackouts, etc.,
b) Plastic Mix: Water-cement ratio shall be about 0.5. This grout mix shall be suitable forapplication with trowel or rod.
c) Stiff Mix: Water-cement ratio shall generally be 0.4. This grout mix shall be suitable fordry-pack application. The consistency should allow pressurising into firm hard ball without
cracking.
5.3.4 Placing
a) The block outs, bolt holes etc. which are to be grouted, are to be cleaned thoroughly by use
of compressed air prior to taking up the grouting operations.
b) Cement, sand, aggregate and anti-shrinkage admixture of approved quality and of provenmake shall be first blended thoroughly in the required proportion as per manufactures
specifications. Grout shall then be prepared by mixing this admixture with water. Any
grout, which has been mixed for a period longer than half an hour shall not be used on the
work.
c) Immediately after preparation, the grout shall be poured into the block outs, pockets andbolts holes either from the sides or through the holes provided for the purpose in the base
plate, by using special equipment for pressure grouting. It shall be ensured by rodding
and by tapping of bolts that the block out is completely filled without leaving any voids.The pouring shall cease as soon as each hole is filled and any excess grout found on the
surface of the concrete foundation shall be completely removed and the surface dried.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
16/23
d) The space between the top surface of the foundation concrete and the underside of the baseplate shall be filled with appropriate grout type. Grouting, once commenced, shall be done
continuously. Grout shall be worked from one end to the other (to prevent air entrainment)
and continued till the grout oozes out through the grout holes provided in the base plates.
e) In case of stiff mix, the space between the top surface of foundation concrete and theunderside of the base plate shall be dry packed by firmly pressing or ramming into placeagainst fixed supports.
f) When it is clear that the centre of base has been properly filled, the grout outside the baseplate shall be briefly rammed to ensure compaction below the edges. Shims provided for
the alignment of plate bases shall be positioned at the edges of the base to permit
subsequent removal, if required; Shims shall not be removed before 7 days after the
grouting has been executed. The resulting cavities after removal of shim plates shall be
made good with the same grade of grout as has been used for grouting under the base plate.
g) The work shall be cured for a period of at least 7 days commencing 24 hours after thecompletion of the grouting. The curing shall be done by covering the surfaces with wet
gunny bags, constant water spraying and flooding.
6.0 ENCASEMENT OF STEEL STRUCTURES / ELEMENTS
This section of the specification deals with the requirement for encasement of steel work in
concrete with necessary formwork, placing, finishing and curing, complete as per drawings
and specifications.
6.1 General Requirements
6.1.1 All concrete work, reinforcement, formwork & staging work shall be done as per
stipulations of clause 3.0, 4.0 and 5.0 of this specification.
6.1.2 The reinforcement to be provided for encasement of steel elements shall be mild steel bars
or in the form of wire netting. The wire shall be at least 5 mm in diameter. The
reinforcement shall be in the form of stirrups with binding at not more than 150mm pitch
so arranged as to pass through the centre of the covering of the edges and outer faces of
the flanges and supported by longitudinal spacing bars not less than four in number. Such
reinforcement shall be kept 20 mm away from the steel member and held securely to it.
6.1.3 The minimum grade of concrete to be used for encasing shall be M15. The aggregate to be
used in concrete shall be 10 mm maximum size unless specified otherwise. Where the
clear cover to steel is more than 75mm, concrete with 20mm coarse aggregate shall be
used. In case of box type steel sections, encasement shall be done with cement-sand
plaster (1:4) with thickness of 50 mm over 0.9 mm size wire netting conforming to IS:
3150, or as shown on the drawings.
6.1.4 In the case encasement of beams with concrete, if the gap between the edge of the shuttering
and flange is insufficient for placing the concrete, the workability of the concrete shall be
increased suitably by increasing the water-cement ratio or adding admixtures as per
instruction of Engineer.
6.1.5 Minimum cover for reinforcement in concrete encasement shall be 25 mm.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
17/23
6.2 Materials
The materials shall be in accordance with the relevant parts of technical specification
Common Civil Construction Material.
7.0 JOINTS IN CONCRETE
This section of the specification deals with the requirement of furnishing & installing of
joints including joint filler materials, water bars, resilient pad type
vibration damping materials in and around the sides of concrete works etc.
7.1 General Requirements
7.1.1 Details of joints shall be as approved by Engineer or as per approved drawings. Where
necessary or / and specified, joints shall be made water tight by use of water stops.
7.2 Classification of Joints
From the point of view of utility, the joints as provided may be classified as given below:
7.2.1 Construction Joints
Construction joints shall be introduced at locations where construction stops for any
reason and when this location is not the planned location of expansion or contraction
joint. Construction joints shall generally, but not necessarily, be vertical or horizontal.
Requirements of construction joints shall be as per Technical specifications/Approved
drawings.
7.2.2 Contraction Joints
These joints are provided to eliminate tensile stresses due to shrinkage and are
commonly used where temperature variations are small and there is no likelihood of
expansion, such as spaces below water and earth levels & unexposed to atmosphere. At
contraction joints, the reinforcement shall be discontinued and bond shall not be allowed
to develop between the joint faces, thereby introducing a structural discontinuity. A
contraction joint shall also serve as a construction joint so far as break in the pouring of
concrete is concerned. Dummy type contraction joints may be provided as directed by
the Engineer for thin sections. These shall be provided by forming a groove in either or
each of the surfaces of the concrete, the total depth of groove being one-third to one-fifth
of the thickness of the section.
7.2.3 Expansion Joints
These shall be provided either to completely eliminate or to significantly reducecompressive stresses in concrete that would otherwise result from thermal expansion and
might crush, buckle or crack part of the structure. Expansion joints serve the purpose of
contraction and also construction joints.
7.2.4 Control Joints
At places where cracking is inevitable, places of weakness shall be introduced by the
provision of control joints so that the cracking takes place along these joints instead of
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
18/23
allowing it to develop in a haphazard manner.
7.2.5 Separation Joints
At places where the expansion of the structure is not expected but they are required to be
kept structurally separate so that stresses, vibrations etc. are not transferred to theadjoining structure, a separation joint shall be provided. Like expansion joint, a gap shall
be provided in separation joint also. The gap may be filled up by bitumen impregnated
fibre board or other resilient material. In case, no gap is required, the separation joint can
be obtained by using an approved alkathene sheet or equivalent stuck on the surface
against which concrete shall be placed.
7.2.6 Settlement Joints
Structures, which are likely to settle with respect to the adjacent structures, shall be
separated by a settlement joint so that the adverse effects of differential settlement are
obviated. It is like an expansion joint but with a different sealing arrangement.
7.3 Materials
The materials shall be in accordance with the relevant parts of technical specification
Common Civil Construction Material.
7.4 Installation
7.4.1 Bitumen Board / Expanded Polystyrene
The bitumen impregnated fibre board of approved manufacturer as per IS: 1838 may besecured to vertical concrete by nails in the first placed concrete. The joint filler shall be
coated on both faces with coal-tar pitch conforming to IS: 216 or bitumen of suitable grade
conforming to IS: 73 or IS: 702.
7.4.2 Resilient Pads
The resilient pads shall be installed around the foundations or at other locations as shown
on the drawings. The pads shall be installed in position by sticking the same to the
foundations by using approved glue.
7.4.3 Sealing Compound
When directed, the gap in joints shall be thoroughly cleaned and sealing compound laid as
per manufacturers specification and approved drawings. Primer shall be applied wherever
required.
7.4.4 Water Stops
a) Water stops shall be selected based on the recommendations of IS: 3414. Water stops shall
not have any longitudinal joints and shall be procured and installed in the largest
practicable lengths having a minimum number of transverse joints.
The PVC Water stop used for construction/expansion joint shall be 225 / 230 mm wideand 6 / 8 mm thick as per drawings or as per instruction of Engineer. If water table is
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
19/23
above the base level of the trench, PVC water stop shall be provided at all construction
and expansion joints. The jointing procedure shall be as per the manufacturers
recommendations and shall be reviewed and approved by the Engineer. Suitable fieldsplicing kit including heater shall be used for this purpose. The edges shall be neatly
crimped and bent to ensure proper bond with the concrete.
b) As non-metallic water stops can be easily handled in very large lengths unlike metal strips,transverse joints will be allowed only under unavoidable circumstances and with the
specific approval of the Engineer. The method of forming these joints, laps etc. shall be as
specified by the Manufacturer and/ or approved by the Engineer, taking particular care to
match the centre and the edges accurately.
c) Particular care shall be taken for the correct positioning of the water stops to prevent anyfaulty installation, which may result in joint leakage.
Adequate provision shall be made to support the water stops during progress of work and
to ensure their proper embedment in the concrete. The symmetrical halves of the waterstops shall be equally divided between the concrete pours adjacent to the joints.
Maximum density and imperviousness of concrete shall be ensured by thoroughly working
in the vicinity of joints. However, particular care should be exercised in use of vibrators in
the proximity of joints to avoid dislodging of the water stops.
d) Splices
Splices in the continuity of intersections of runs of water stops shall be jointed as per
manufacturers stipulations. In case of a cross section, over lapping must not be done
but, instead factory made cross joint shall be used. It is essential that the material is notdamaged during the splicing operation and that the continuity of the entire water stops
across the section is maintained.
e) Inspection
All water stops installations shall be subject to inspection and approval by the Engineer,
before concreting operations encasing water stops are performed.
7.4.5 Metal Cover Strips
The metal cover strips shall be pinned at one end and slotted at the other end. Exposedsurface of mild steel shall be painted with two coats of approved anticorrosive paint and/
or bituminous paint over a coat of suitable primer. Welding of Aluminium shall be in
accordance with IS: 2812.
8.0 CEMENT ADDITIVES / ADMIXTURES IN CONCRETE
This section of the specification deals with the requirements of furnishing, placing and
mixing cement additives/ admixtures, in all kinds of cement concrete, (plain or reinforced) for
all kinds of structures at all levels.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
20/23
8.1 General Requirements
8.1.1 All essential resources such as Labour, Material and Equipments etc., shall be deployed to
place and mix cement additives / admixtures, water proofing cement additives, cement
plasticizer etc., in cement mortar & concrete of any grade. Works as specified earlier in
relevant clauses of this specification for concrete & cement mortar and complete the work as
indicated on the drawing and as per specifications shall be carried out thereafter.
8.1.2 Cement additives / admixtures shall be free from aggressive chemicals like Chlorides,
Sulphides etc., unless specified otherwise, which can cause corrosion of steel reinforcement
in RCC.
8.1.3 As per requirement and as indicated by the Engineer, the services of the manufactures
supervisor to supervise the work shall be arranged.
8.1.4 Admixtures in concrete for promoting workability, improving strength, entraining air or for
similar purposes may be used with prior permission of the Engineer. Addition of admixturesshall not reduce the specified strength or durability of concrete in any case. The admixtures
shall conform to IS: 9103 and shall be of proven make and from a reputed manufacturer.
Calcium chloride shall not be permitted to be used.
8.2 Materials
The materials shall be in accordance with the technical specification Common Civil
Construction Material.
8.3 Mixing
8.3.1 Admixtures/ water proofing additives shall be used as per dosage specified by the
manufacturer or as indicated on the drawings and shall be mixed with water, as required by
the Engineer.
8.3.2 Samples of concrete in which admixtures and/ or water proofing cement additive is added
shall be tested for waterproofness, workability, compressive strength, water absorption,
density, setting time etc. The results shall conform to relevant IS Specifications.
9.0 PRECAST CONCRETE
The specification for pre-cast concrete of grade M20 or M25 (as per construction drawing)shall be similar as for the cast-in-situ concrete described in clause no. 3.0. All pre-cast work
shall be carried out in a yard made for the purpose. This yard shall have a hard and levelled
platform made of concrete finished smooth with neat cement plaster overlaid by layer of G.I.
Plain sheets, curing tank and such other facilities. The moulds shall preferably be of steel or
of wood lined with G.I. sheet metal. The yard shall preferably be fenced.
Precast concrete elements shall be suitably marked for correct orientation and placement in
position. Precast concrete planks after 28 days of casting and curing shall be transported to
site by suitable means approved by the Engineer. Lifting hooks, protected with edge
protection angle of suitable size shall be embedded in correct position of the unit to
facilitate erection, even if not shown on the drawing, and shall be burnt off and finishedafter erection. All care shall be taken to ensure that no damage occurs during transportation.
All adjustments, levelling and plumbing shall be done as per the instructions of the
Engineer. Required help in instruments, materials and men to the Engineer for checking the
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
21/23
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
22/23
be designed for the worst combination of loading as specified hereinafter.
e. GDCL shall submit design calculations and drawing to prove adequacy of the staging forapproval of the Engineer. On receipt of final approval, GDCL shall provide 3 copies of
approved drawings for distribution.
f. The staging shall be so designed that no load from platforms is passed on to the formwork atthe top.
g. All platforms, walkways etc., shall be clear of the formwork and at least 200mm above it.The width of platforms and walkways shall be at least 1.2 metres for easy movement of
workmen both ways.
h. The platforms shall be made of planks or bamboo mats (clamped with steel strips suitablystiffened to avoid springing).
i. The formwork and staging shall be designed for a live load of 1000 Kg/m2.
j. The staging shall be braced in both the directions.
k. The staging shall be supported on rigid surfaces at ground level.
l. The staging shall be sufficiently rigid to prevent any distortion in the formwork.
m. The Site Engineer shall take all precautions to ensure concreting of TG Raft, columns and TGDeck in one pour each. Concreting shall be continuous and no break in concreting shall be
permitted.
n. The Sub-contractor shall prepare a scheme for concreting giving details of number of mixers,labour, vibrators, pouring schedule and obtain prior approval of the same from the Engineer
before commencing concreting operations.
o. Site Engineer shall ensure that at no time the temperature of the green concrete exceeds 38degree C and take suitable precautions. If required, ice shall be added to control the
temperature.
11.1 Test for Soundness of Concrete
a. After completion of the construction of TG foundations, GDCL shall get the Deck andcolumn tested for soundness of concrete by ultrasonic wave nondestructive test method
from reputed research institutions as approved by Client.
b. If the test report calls for any rectification in the concrete works by way of pressure groutingor otherwise, the same shall be carried out by GDCL.
c. Further,any additional tests required to establish the adequacy of the rectification workscarried out shall also be done by GDCL. At mutually worked out costs..
12.0 DISMANTLING/ DEMOLISHING RCC AND/ OR PCC WORK
This section of the specification deals with the requirements of dismantling/ demolishing
RCC and/ or PCC work.
-
7/29/2019 Proposed Genrl Instructions Cement Concrete Allied Works Jp 03,04,05,07
23/23
12.1.1 General Requirements
12.1.1 The dismantling implies, carefully taking up or down and removing without damage. This
activity covers dismantling of one or more parts of a structure. This includes chipping work,
making holes/ opening etc. in concrete members, according to the required shape, size, and
profile at all elevations.
12.1.2 The term demolition implies, taking up or down or breaking up of a structure/ member, in
part or full, as specified or shown on drawings or as directed by the Engineer.
12.1.3 In a structure/ member, both dismantling and demolishing work may be involved. In such
case, the portion of work treated as demolishing shall be as shown on the drawing or as
decided by the Engineer.
12.1.4 The dismantling / demolishing operation shall be carried out in proper sequence so that the
serviceable material can be salvaged, without being damaged during
the process of work. All serviceable materials obtained from demolition / dismantling
work shall be separated out and stacked properly to avoid damage up to a lead of 500
metres or shall be returned to Clients stores and all unserviceable materials, rubbish etc.
shall be disposed of by GDCL beyond the project site.
12.1.5 Necessary propping, shoring and under pinning are to be provided for the safety of the
adjoining works or property which is to be left intact, prior to commencing dismantling/
demolishing work.
12.1.6 All demolition work shall be carried out in conformance with the local safety regulations,
extreme caution being exercised to avoid damage to the works and the equipment, whichare to be left intact. The dismantled/demolished materials shall be lowered to the ground
and not thrown and then properly stacked as directed by the Engineer. Necessary
precautions shall be taken to keep the dust nuisance down. Wherever required temporary
enclosures shall be erected to minimize the dust or moisture infiltration. Safety
requirements stipulated in IS: 4130 shall also be followed.