PROJECTS

Fiscal Year 21-22

Waxhaw

Page 2: PROJECTS Waxhaw Fiscal Year 21-22

1

TABLE OF CONTENTS:

Message from Town Manager / Introduction 2

Summary 3

Downtown Improvements 4—9

DowntownParkDesign/Infrastructure 4

BridgeStepsAddition 5

StreetLightReplacement 6

McDonaldStreetParking 7

EastNorthMainStreet&Vicinity/TAPSupplemental 8

BarnesParkRestroomReplacement 9

Town Campus: Design & Construction Administration 10

Crosswalks NC 16 & Kensington Drive 11

Sunbonnet Lane Rehabilitation 12

Powell Bill Street Maintenance 13

Nesbit Park Drainage Improvements 14

Broadband Improvements McDonald House to Meeting Place 15

Page 3: PROJECTS Waxhaw Fiscal Year 21-22

2

Message from Town Manager TheTownofWaxhawhasexperiencedtremendousgrowthoverthelasttenyears.Waxhawanticipatesthe2020Censustoshowapproximately20,000people,representinga100%increaseinpopulationfrom2010.Whilethistypeofpopulationincreasenaturallyleadstoanever-growingdemandforincreasedservicesandoperatingexpenses,ithasmorethananythingshownthatWaxhawisbehindinkeepingupwithcapitalneeds.Townoperationshavegrownoutofmanyofitscurrentbuildingsasservicedemandshaveincreased.Existingparkinfrastructurehasnotbeenrepairedasoftenasitshould.Smaller-scaletransportationandpedestrianprojectsrequirecompletion.

WaxhawwillcontinuetopursuethedemandsforserviceswhilemaintainingthefiscalintegrityoftheTown.Startingwiththisupcoming2021-22fiscalyearbudget,theTownWaxhawwillprioritizecapitalprojectneedstoserveourpopulacedecadesintothefuturebetter.IamdelightedtopresentWaxhaw’sfirstproperCapitalImprovementPlan(CIP).TheCIPwillbeadoptedasafive-yearplanandwillbere-assessedannually.ThisplanincorporatedintothebudgetannuallywillallowWaxhawtoproperlyplanforcapitalimprovementexpendituresinthebestintereststoservetheTownanditsresidents.

IinviteyoutotakeafewmomentstoreadabouttheprojectsthatWaxhawhasinYear1oftheCapitalImprovementPlan.Citizensarewelcometocontactusanytimetoseekmoreinformationonanyproject.Ialsoinvitecitizenstoletusknowifyouhaveaprojectinmind.SomeoftheprojectsontheCIPMasterListhavecomedirectlyfromanideafromacitizenorcitizengroup.Thelistofprojectsisever-growing,foreveryprojectcompletedtherewillbemoretoaddtothelist.

Jeffrey Wells TownManager

Page 4: PROJECTS Waxhaw Fiscal Year 21-22

Summary CapitalImprovementPlans(CIPs)areverycommoninlocalgovernment.Theyareplansthataccountforlong-rangeinfrastructureandequipmentneedstoserveandmaintainpublicneedsadequately.CIPsarelong-rangeandusuallyspanbetween4to10years.Waxhawwillutilizeafive-yearCIP.Thisplanwillbere-evaluatedandre-adoptedonanannualbasisalongwiththeoperatingbudget.TheCIP2022-26willconsistof:

3

Page 5: PROJECTS Waxhaw Fiscal Year 21-22

4

Thetownowns9.9acresoflandonthesouthsideofdowntownthathasbeenidentifiedbytheComprehensiveParksMasterPlanasthetopprioritytodevelopintoaneighborhoodpark.ArevisedconceptplanwasapprovedinJanuary2021,andfulldesignoftheparkisunderwaywiththegoalofbeginningconstructionofPhase1inFall2021.Phase1willbetheinfrastructure(clearing/grading,utilities,drives,parking).Phase2willbetheamenities.

DOWNTOWN PARK DESIGN/ INFRASTRUCTURE

Location: Givens Street, 2 blocks south of South Main Street (NC 75) between Broad and Church Streets.

Funding Source: Capital Projects for design and Phase 1. Financing for Phase 2.

Estimated cost: $4,300,000.00

Estimated completion: 2023

DOWNTOWNIMPROVEMENTS

Page 6: PROJECTS Waxhaw Fiscal Year 21-22

5

Thisprojectwillconstructasetofstepstotheeasternapproachofthedowntownpedestrianbridgetomirrorthoseonthewesternapproach.ThiswillbetterfacilitateaccesstotherelocatedcrosswalkandsidewalkconnectiontoTheMillDevelopmentoncethatprojectiscomplete.

BRIDGE STEPS ADDITION

Location: Bridge in Downtown Waxhaw

Funding Source: Small Transportation Projects Fund

Estimated cost: $40,000.00

Estimated completion: 2022

DOWNTOWNIMPROVEMENTS

EXISTING NEW

Page 7: PROJECTS Waxhaw Fiscal Year 21-22

6

TheTownwillreplaceexistingdowntownpedestrianscalestreetlightswithnewfixturesthatimprovetheaestheticsandfunctionalityofthecurrentpoles.Thenewpoledesignwasselectedbyourdowntowndesigncommitteetobebothprogressiveandtimelessinformandfunction.Thepoleswillcomefromthefactoryreadytoreceivedecorativebanners,electricalreceptaclesforholidaylightingandfestivalpowersupply,aswellasbroadbandconnectivityinpartnershipwithourInformationTechnologyDepartment.Thelightitselfwillbedimmable,tonotcontrastwithretailambianceneeds.Atotalof31streetlightsalongbothNorthandSouthMainStreetswillbereplaced.Thereceptacletriphazardswillalsoberemoved.

STREET LIGHT REPLACEMENT

Location: North & South Main Street

Funding Source: Small Transportation Projects Fund

Estimated cost: $220,000.00

Estimated completion: 2022

DOWNTOWNIMPROVEMENTS

EXISTING NEW

Page 8: PROJECTS Waxhaw Fiscal Year 21-22

7

Inanongoingefforttomaximizepublicparkinginventoryinthedowntownretailarea,theTownwillutilizethesouthernportionoftheMcDonaldStreetrightofwaytoreplacetheparalleltoangleparkingandadddrivewaystoserveasatransitionalCommunityCornerparkinglot(whennotinusefortownevents.)Designindicatesanetyieldof22spaces.

McDONALD STREET PARKING

Funding Source: Small Transportation Projects Fund

Estimated cost: $100,000.00

Estimated completion: 2021

Location: McDonald Street & Community Corner

DOWNTOWNIMPROVEMENTS

Page 9: PROJECTS Waxhaw Fiscal Year 21-22

8

A50/50matchinggrantthroughtheCRTPOTransportationAlternativesProgram(TAP)wassecuredin2015toimprovedowntownpedestriansafetyandconnectivity,aswellbicycleenhancements,withthefocalpointbeingapedestrianplazaalongENorthMainandN.ProvidenceStreet.Designbeganinearnestin2017,butunfortunatelyfundingwasfrozenin2019duetoNCDOTfinancialconstraints.ThetownanticipatesthefundingfreezetobeliftedinFall2021.ENorthMainStreetwillbeconvertedtoaone-waystreet.Existingparallelandangleparkingwillremainwhilethesidewalkwillbewidenedtocreatemorespaceforpedestriansandbusinessactivity.Amid-sidewalkretainingwallprovidesadditionalseatingandeliminatesthegradedifferentialatthestreettothepedestrianzone.AngledparkingspaceswillbecreatedonthewestsideofNProvidenceStreetnettingadditionalparkingspaces.AdditionalsidewalkworkwouldalsobecompleteddownthewestsideofSChurchStreettoSK8ParkandalongBroomeStreetiffundingallows.

EAST NORTH MAIN STREET & VICINITY / TAP SUPPLEMENTAL

Funding Source: TAP/Small Transportation Projects

Estimated cost: $820,000.00

Estimated completion: 2023

Location: E North Main Street and N Providence Street

DOWNTOWNIMPROVEMENTS

Page 10: PROJECTS Waxhaw Fiscal Year 21-22

9

TheTownwillreplacetherestroomswithamoremodernfacility.ThefacilitywillbebroughtuptoADAstandards.Locationwouldbethesameareaandthedesignwouldcomplementthefutureamenities.

BARNES PARK RESTROOM REPLACEMENT

Location: Barnes Park

Funding Source: Capital Projects Fund

Estimated cost: $100,000.00

Estimated completion: 2022

DOWNTOWNIMPROVEMENTS

Page 11: PROJECTS Waxhaw Fiscal Year 21-22

10

TheTownhascontractedwithADWArchitectsforthedesignandconstructionadministrationofTownCampuslocatedat4220Waxhaw-MarvinRoad.TheCampuswillconsistofPublicServices/ParksandRecreationOperationsCenterandTownHall.ThepropertyalsoconnectsTownCreekParktoNesbitParkopeningupmoreparkandrecreationalopportunitiesoncethecampusisbuilt.

TOWN CAMPUS: DESIGN & CONSTRUCTION ADMINISTRATION

Funding Source: Town Campus Fund

Estimated cost: $976,800.00

Estimated completion: 2023

Location: Intersection of Kensignton Drive Waxhaw-Marvin Road

Page 12: PROJECTS Waxhaw Fiscal Year 21-22

11

TheTown’s2020MasterTransportationPlanidentifiedthisprojectastheTown’ssecondhighestratedproject.Atoppriorityistheneedfornewand/orimprovedcrosswalkstomakesaferconnectionsforpedestriansacrossbusyroadwaysforbothexerciseandaccesstoretailareas.StandardhighvisibilitypavementmarkingssupplementedwithRectangularRapidFlashingBeacons(RRFB)areproposedtoalertvehiculartrafficofpedestrianactivityoncethesignalismanuallyactivated.ProposedlocationsincludeKingstonDrive,RedOaksTrail,TownHallandthePostOfficelocationalongNC16.KensingtonDriveatSunsetHillsisalsoproposedtoconnectCuretonresidentialwiththeretailsite.Whereabsent,ADAcomplaintrampswillbeinstalledasrequiredbylaw.

CROSSWALKS NC 16 & KENSINGTON DRIVE

Location: Various locations along NC 16 and Kensington Drive

Funding Source: Powell Bill

Estimated cost: $130,000.00

Estimated completion: 2021

Page 13: PROJECTS Waxhaw Fiscal Year 21-22

12

ThepreviouslyunincorporatedareaaroundSunbonnetLanewasannexedin2008andbroughtaprivategravelroadintotheTownsystem.Tocorrectthisandeliminateextensivemaintenanceandequityissues,itwillbeimprovedtoTownstandards.

SUNBONNET LANE REHABILITATION

Location: Sunbonnet Lane

Funding Source: Small Transportation Projects Fund

Estimated cost: $100,000.00

Estimated completion: 2022

Page 14: PROJECTS Waxhaw Fiscal Year 21-22

13

NorthCarolinamunicipalitiesreceivefinancialassistancefromtheStatetohelppayfortheconstruction,maintenance,andrepairofmunicipalstreets.ThesemoniesdistributedfromthestateonanannualbasisarereferredtoasPowellBillfunding.TheTownhistoricallyutilizesthisfundtoprioritizestreetsinneedofrepairandresurfacing.

POWELL BILL STREET MAINTENANCE

Location: Various Town Streets

Funding Source: Powell Bill Fund

Estimated cost: $360,300.00

Estimated completion: 2021/2022

Page 15: PROJECTS Waxhaw Fiscal Year 21-22

14

TheTownwillinstallacombinationofsurfacepipesatgradeand“flexipave”channels.Thiswilleliminatepondinginareaswherepedestrianshavedifficultytraversinginwetweatherconditions.Pipesneedpropercoverandslopestofunction.FlexipaveisnotconstrainedinthiswayandprovidesanADAcompliantsurfacewithsufficientvoidstocollectandtransmitrunoffdownstreamovertime.

NESBIT PARK DRAINAGE IMPROVEMENTS

Location: Nesbit Park

Funding Source: Capital Project Funds

Estimated cost: $99,500.00

Estimated completion: 2021

Page 16: PROJECTS Waxhaw Fiscal Year 21-22

15

Improvementstofiberopticconnectivitywillbenefit:•NetworkConsistencyandreliabilityforthecurrentTownownedbuildingslocatedonthesouthsideoftheCSXtraintracks.

•ConnectivityallowsforhighernetworkusagetosupportWi-Fiandvideosurveillanceproject.•Reducesdependanceonsatelliteconnectivity(weather,lineofsight,treesandleaves)•Provideuninterruptedsignalsforstreamingorvideoconferences.•ProvideBarnesParkwithWi-FiAccessControlSecurity,VideoSurveillance,etc.

BROADBAND IMPROVEMENTS MCDONALD TO MEETING PLACE

Location: McDonald House to Meeting Place

Funding Source: Capital Projects Fund

Estimated cost: $50,000.00

Estimated completion: 2022