projects emerald and emerta emerald wp5 the specific case of asas/ads-b
TRANSCRIPT
![Page 1: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/1.jpg)
Projects EMERALD and EMERTA
EMERALD WP5
The Specific case of ASAS/ADS-B
![Page 2: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/2.jpg)
Projects EMERALD and EMERTA
EMERALD WP5 Work
• Task WP5.1: Identification of potential ASAS applications
• Task WP5.2: Detailed feasibility assessment of selected ASAS applications
• Task WP5.3: Users’ Interview
• Task WP5.4: Assessment report and RTD plan
• Task WP5.5: Users’ feedback and final results presentation
![Page 3: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/3.jpg)
Projects EMERALD and EMERTA
EMERALD RTD Plan
• User Requirement or concept phase
• Feasibility phase
• Functional Requirement phase
• Prototyping Phase
• Experimentation & Validation phase
• Implementation phase
![Page 4: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/4.jpg)
Projects EMERALD and EMERTA
WP5 recommendations
• The proposed RTD plan be used as a guide for further
research into the ASAS domains by the RTD funding
authorities
• The RTD activities described in the RTD plan be
undertaken quickly in order to cope with the EATMS
schedule for ‘Co-operative ATM’
• Co-ordination between all organisations involved in ASAS
studies be undertaken
![Page 5: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/5.jpg)
Projects EMERALD and EMERTA
Project EMERTA
![Page 6: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/6.jpg)
Projects EMERALD and EMERTA
Objectives of Project EMERTA (1/3)
To establish the feasibility of using emerging NGSS services ‘as they are’ to meet Air Traffic Service (ATS) and Airline Operation Center (AOC) requirements. This will include the definition of a European-level NGSS demonstration/validation project.
To support a European input to international standardisation activities in such forums as ICAO and RTCA/EUROCAE, insofar as they are concerned with the technologies and concepts covered by Project EMERTA.
![Page 7: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/7.jpg)
Projects EMERALD and EMERTA
Objectives of Project EMERTA (2/3)
To provide inputs to the specification of detailed requirements for a second generation of Low/Medium Earth Orbit (LEO/MEO) satellite systems and services, for deployment beyond the year 2005.
To assess the practical feasibility of the early introduction, in the European ATM environment, of one or more selected ADS-B/ASAS application scenarios, paying particular attention to safety and transition aspects. This will be supported by an outline indication of the cost/benefit issues associated with the scenario(s).
![Page 8: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/8.jpg)
Projects EMERALD and EMERTA
Objectives of Project EMERTA (3/3)
To develop initial indications and guidelines on how to deploy ADS-B in Europe, in the context of the ASAS concept, in terms of the potential requirement for reserved airspace and how best to deal with a mixed aircraft population (where some aircraft have an ASAS capability, but others do not).
![Page 9: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/9.jpg)
Projects EMERALD and EMERTA
TIS-B conclusions
• TIS(-B) has a role to play in enabling the initial implementation of ASAS applications
• An ongoing role to support ASAS operations could also be identified.
• The concept of a service volume is key.• An agreed TIS(-B) concept must be defined as the
international standardisation activity continues and further requirements become available.
![Page 10: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/10.jpg)
Projects EMERALD and EMERTA
For EMERTA, two applications were chosen:• Enhanced Visual Acquisition (EVA) of other
traffic for see-and-avoid
• Station Keeping on Approach (SKA)
Two applications were also taken from EMERALD:• Closely Spaced Parallel Approaches (CSPA)• Longitudinal Station Keeping (LSK)
ASAS Applications
![Page 11: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/11.jpg)
Projects EMERALD and EMERTA
EMERTA Conclusions (1/2)• Technology is available to support basic ASAS
applications• Major gap is in the surveillance data quality• SKA has been shown to be feasible in the short-
term• TIS-B could be an enabler for early applications
and provide a consistent traffic situation picture
![Page 12: Projects EMERALD and EMERTA EMERALD WP5 The Specific case of ASAS/ADS-B](https://reader036.vdocuments.site/reader036/viewer/2022082818/56649f135503460f94c26ad2/html5/thumbnails/12.jpg)
Projects EMERALD and EMERTA
EMERTA Conclusions (2/2)
• Initial applications must be chosen carefully• Relevant procedures must be developed• Responsibilities must be defined• Issues of confidentiality• Technical data-link issues must be closed• Implement supporting ground systems • Address CDTI HMI issues