project tg04
TRANSCRIPT
-
7/31/2019 Project Tg04
1/184
1.INTRODUCTION TO TESTING OF
TURBOGENERATOR
Testing is an activity, which basically evaluates a
component, and or a product (built up of componentassemblies) as to whether it has the technical capability
that has been built into it by way of design, materials, and
technological processes employed while manufacturing
and workmanship.
As such, testing activities can broadly be classified in to a
number of categories as follows:
- Type tests.
- Routine tests.
- Process tests.
-
7/31/2019 Project Tg04
2/184
TESTING OF TURBOGENERATOR
Advantages of testing:
Provides quality assurance.
Meets the requirements of legal & contract requirements.
Reduction in rework cost.
Ensures process capability & develops checklist.
Increases confidence levels in manufacture.
Provides data for optimization of design.
Helps in building of Safety & general O&M manual.Establishes control over raw materials.
Important points for testing
Have an approved procedure.
Tabulate test levels / stages.
Check the testing equipment before use.
Calibrate the test equipment & instruments.
Ensure interlocks of the equipment
-
7/31/2019 Project Tg04
3/184
Log the results in proper formats.
Analyse failure & submit a comprehensive report for repair
/ replacement.
PERFORMANCE TESTS ON
TURBOGENERATOR:
With the increasing trend on standardization every country
has its National Standards covering a wide range of
subjects, In India, the Indian Standards are valid andapplicable. The machines produced at Hyderabad fully
conform to Indian and also International Standards, and
many machines are being exported to various countries.
The performance tests on turbo generators include the
following
Measurement of Insulation resistance.
-
7/31/2019 Project Tg04
4/184
Measurement of ohmic resistance of windings in cold
state.
Applied H.V. tests.
Measurement of vibrations and mechanical losses.
Measurement of no load characteristics.
Measurement of short circuit characteristics.
Determination of excitation on load and checks of
voltage rise (regulation).
Measurement of leakage and potier reactances.
Measurement of losses and determination of efficiency.
Heat run tests.
Retardation test.
-
7/31/2019 Project Tg04
5/184
TEST PROCEDURE
During manufacturing of Turbo-generators the following
stage tests are to be carried out on individual components
to ensure quality of the product and to reduce last minute
delay during acceptances tests. The standards for these
tests will differ from plant to plant.
1.Stator
Checking up of Resistance temperature detectors while
core building.
Ring flux test.
Tan delta measurement on stator winding after
impregnation.
H.V. test on coils during manufacturers and assembly.
-
7/31/2019 Project Tg04
6/184
Capacitance measurement.
2.Rotor
H.V. test on excitation connecting leads.
H.V. & inter- turn insulation tests on field coils during
the winding process.
Impedance measurement field coils.
3. Over-speed test.
Over-speed test involves mechanical running of the rotor at
the prescribed % over-speed for the stipulated period of
time. It is later subjected to a very close mechanical
inspection to investigating into the effects of over speed if
any.The rotor isbalancedto the required levels as per
standards. This brings us to measurement of characteristics
and losses of the generator.
-
7/31/2019 Project Tg04
7/184
Measurement or determination of efficiency of the
machine is an important step.
For determination of efficiency, losses measurement on the
drive system is to be done and derive machine losses by
subtracting drive motor losses.
4.Determination of efficiency
Having measured the losses, the efficiency can be
estimated from the formula.
Efficiency =(input losses / input = output / (Output +
losses)
Tolerance on guaranteed efficiency is 0.1 (1-efficiency)
when measured by summation of losses method.
-
7/31/2019 Project Tg04
8/184
5.Measurement for leakage & potier reactance
Leakage reactance is measured on the stator alone when
winding is completed. The procedure involves supplying
the winding from a 3-phase variable voltage source and
measuring currents voltage and power at the stator
terminals. Depending on the source capacity upto 0.25In
may be passed. Potier reactance as per accepted standard
practices is taken as 0.6 to 0.65 of total leakage reactance.It can alternatively be calculated from the zero power
factor test measurements.
6. Line-to-Line sustained short circuit test
The negative phase sequence reactance is can be
determined from the line-to-line sustained short circuit test.
-
7/31/2019 Project Tg04
9/184
Negative phase sequence reactance (X2) = P / 3. (Ik2)2
where P = Power measured and Ik2 is negative phase
sequence current measured during line-to-line sustained
short circuit test.
7.Line to line and to neutral sustained short circuit test
From this test zero phase sequence reactance can be
determined.
Zero phase sequence reactance (Xo) = Vo / Io.
Where Vo = Voltage from measured in open phase voltage
and Io is current measured in line to neutral during line to
line sustained short circuit test.
-
7/31/2019 Project Tg04
10/184
8.Retardation test for determination of Moment of
Inertia
The machine speed and time are noted during free coasting
down of the machine.
Moment of inertia =(4 x 365000 x P x T )/ N2 Kg-m2
where: P = Power input in kW to keep machine at rated
speed. N = Rated Speed in rpm.
T time in seconds from curve. (Tangent drawn at ratedrpm)
-
7/31/2019 Project Tg04
11/184
2. THEORY OF SYNCHRONOUS
GENERATOR
THEORY:
A synchronous generator is the core of any generating
power plant. A synchronous generator is a rotating
electromagnetic device that converts mechanical energy
into electrical energy by taking the mechanical input
from a prime mover (Gas turbine or Steam turbine) and
magnetic energy from excitation.
-
7/31/2019 Project Tg04
12/184
The different electromagnetic or active parts of a
generator are as follows:
- Stator core
- Stator coils/ bars
- Stator winding
- Output leads, brushings and conductors
- Rotor excitation leads
- Rotor coils
- Rotor winding
2.1.Stator core
The stator core serves the two fold function of providing
the mechanical support for the stator coils and carrying
effectively the electromagnetic flux generated by the
rotor winding. In order to minimize hysterisis and eddy
current losses the entire core is built of thin laminations.
-
7/31/2019 Project Tg04
13/184
Each lamination layer is made up from a number of
individual segments.
2.2.Stator coils/ bars
The stator coils are the individual entities, which are
placed in the slots of the stator core and finally
connected to each other as per a pre-designed scheme to
form a three phase winding. The prime purpose of the
stator bars is to carry the load current at minimal windinglosses.
These coils are provided with high voltage stresses.
Depending upon the size and rated voltage of the
machine different types of stator bars are designed.
2.3.Stator winding
The stator winding is a short pitch; two-layered type
made of individual bars. The bars are located in slots of
-
7/31/2019 Project Tg04
14/184
rectangular cross section, which are uniformly
distributed on the circumference of the stator core. In
order to minimize the losses, the bars are composed of
separately insulated stands transposed by 360 degrees.
To minimize the stray losses in the end winding, the
standards of the top and bottom bars are separately
brazed and insulated
from each other.
2.4.Output leads, brushings and phase connectors
Output leads are taken out from the exciter end of stator
from the top and supported on an insulated glass fabric
plate. Six terminals are brought out, three for phase and
three for neutral connections. The phase connections are
connections between the stator winding phase bars /coils
to the output lead brushings.
2.5.Rotor excitation leads
-
7/31/2019 Project Tg04
15/184
The excitation leads provide electrical connection
between rotor winding and output from brush less
exciter.
2.6.Rotor winding:
The construction of the rotor winding consists of
placement of pre-formed rotor coils as per the winding
scheme in the slotted rotor body, providing necessary
insulation both in the straight position and overhang,
making connections of the excitation leads, wedging ofthe straight part and mounting of the retaining rings.
-
7/31/2019 Project Tg04
16/184
CLASSIFICATION OF SYNCHROUS
GENERATORS
Synchronous generators are classified into two main
categories based on their design as: Smooth cylindrical
rotor machines and salient pole machines. Generators
driven by steam or gas turbines have cylindrical/ round
rotors with slots into which distributed field windings are
placed. These round rotor generators are usually referred
to as turbo generators and they usually have 2 or 4 poles.Generators driven by hydraulic turbines have laminated
salient pole rotors with concentrated field winding and a
large number of poles.
PRINCIPLE OF OPERATION:
The mechanical power of the prime mover rotates the
shaft of the generator on which the field winding is
-
7/31/2019 Project Tg04
17/184
installed. When the field winding is excited using dc
voltage, then a rotating dc flux is produced which
when cut by the stator winding, a 3-phase voltage is
generated owing the principle of Faradays law of
Electromagnetic Induction.
DESIGN CRITERIA:
Any generator design should be in accordance with the
international standards like IEC and National standardslike IS, BS etc. Various inputs required for the designing
purpose of a generator is MVA, MW, PF, Voltage,
frequency, speed, Type of cooling, type of excitation
system etc. The main parameters during design to be
considered are:
Stator core- outer diameter, inner diameter, and no. of
slots, each slots size and size of copper. Rotor- barrel
-
7/31/2019 Project Tg04
18/184
diameter, length, no. of slots, slot size and copper size.
The criteria of the design should be in such a way as to
ensure maximum efficiency, short circuit ratio (SCR)
and sub transient reactance as per the standard
stipulations and any other customer commitments.
The generators are classified as gas turbine generators or
steam turbine generators depending on their drive.
Generators driven by gas turbines are usually installedwith a minimum civil foundation on base frame as for
the gas turbine a perfect and proper civil structure is not
very necessary and can be installed outdoors. Gas turbine
generators can be either open circuit air-cooled or closed
circuit air-water cooled. The terminals are usually at the
top of the generator on the exciter side for the on word
-
7/31/2019 Project Tg04
19/184
connection to bus ducts through a GAC (Generator
Auxiliary Compartment).
SYNCHRONOUS GENERATORS- LOSSES AND
COOLING:
All electrical machines produce heat owing to various
losses generated inside the machine (like the I2R losses
of stator copper winding). These losses are categorized
as fixed and variable. Friction and windage losses, whichinclude hysterisis and eddy current losses, are all
considered to be fixed losses while the rotor copper
losses, are treated as variable losses. Friction and
windage losses are dependent upon speed and as
synchronous machines run at constant speed, these losses
are constant. As the magnetic flux passes through stator
laminations, hysterisis and eddy current losses result in
-
7/31/2019 Project Tg04
20/184
and are dependent on the magnitude of flux. As long as
machine is delivering power at a constant voltage, which
is normal case, these losses in the laminations are fixed.
The stator copper losses and rotor copper losses vary in
square proportion to the stator and rotor currents
respectively. These currents vary in accordance with the
load and thus in turn the losses also vary and hence
termed as variable losses.
As the synchronous machine has to deliver the output
continuously, the heat generated inside the machine has
also to be taken away at the same rate so that the
machine can operate at a stable temperature
continuously; ensuring a longer life for the insulation
system which in turn ensures a longer life of operation of
the generator itself. Thus cooling forms one of the basic
-
7/31/2019 Project Tg04
21/184
requirements of any generator and the effective working
of any generator considerably depends on the cooling
system. The insulation used and the cooling employed is
interrelated.
Various methods of cooling employed are:
Air-cooling
Hydrogen cooling and
Water-cooling
Generally Upto 125 MVA air-cooling is employed.
Hydrogen cooling is employed in the machines i.e.,above 125MVA; as it is more efficient compared to air-
cooling.
-
7/31/2019 Project Tg04
22/184
For still higher ratings like above 500MVA, Water-
cooling is employed.
Air cooled generators are the simplest in design and
either open air ventilating cooling system or a close air
close water circuit (CACW) cooling can be employed.
Open circuit air-cooling depends on the ambient
temperature unlike the CACW cooling and this open air-
cooling is employed for the Gas turbine generators where
there is scarcity of water.
EXCITATION SYSTEM:
In all industrial countries, the electrical power demand is
ever increasing, doubling itself approximately per
decade. This automatically demands for the design,
development and construction of increasingly large
capacity turbo generators. Such large capacity alternators
-
7/31/2019 Project Tg04
23/184
should be highly reliable in operation and this calls for a
reliable and sophisticated mode of excitation system. The
excitation system consists of a small generator coupled
to the main alternator through the excitation leads
running through the shaft.
Conventional D.C Excitation Systems with a D.C.
exciter enjoyed an unchallenged position till recently
was adopted universally for all alternators. With the
growth in unit size of large capacity D.C. exciterscapacity became necessary. Due to problems in
communication it became inevitable to design of large
capacity D.C. exciters at low speeds leading to increase
in the systems. Moreover, the D.C. excitation suffered
from problems like power cabling, problems associated
with commutator and brush gear and maintenance.
-
7/31/2019 Project Tg04
24/184
With the advent of high power solid state semiconductor
devices, significant strides were made in the
development of new excitation systems and thus in order
to liquidate the communication and brush gear problems
of the D.C, the A.C exciters were introduced.
A.C excitation:
Systems are classified into two types as:
High Frequency Excitation System was developed. At
present this is the system, which is widely used owing toits reliability, good transient performance and least
maintenance. The system also doesnt suffer from the
problems of communication, brush gear and power
cabling. However, the main disadvantage of the system
is that the rotor is not accessible and thus fast de-
excitation, in case of any fault on rotor winding, is not
possible.
-
7/31/2019 Project Tg04
25/184
Static Excitation Systemwas developed contemporarily
as an alternative to brush less excitation system. This
system makes use of generators upto 160 MVA. The
system has got an excellent transient response. But the
system is not free from the power cabling, slip rings,
brush gear and moreover the equipment and thus the
layout of the cubical are not compact.
-
7/31/2019 Project Tg04
26/184
3. CONSTRUCTIONAL FEATURES OF
TURBOGENERATOR
The turbo generator is designed for continuous
operation with voltage variations +/- 5% of the rated
voltage and a frequency variation of +/- 1%. In general,
the machine is designed for the altitudes of 1000 meters
and above sea level and below an ambient temperature of
60
0
maximum, with cooling water temperature of 38
0
maximum at the inlet.
The generator consists of the following components:
3.1 Stator:
Stator Frame
End Covers
Stator Core
-
7/31/2019 Project Tg04
27/184
-
7/31/2019 Project Tg04
28/184
-
7/31/2019 Project Tg04
29/184
3.1. Stator
3.1.1. Stator Frame
The stator frame is of welded construction, supports the
core and the windings. In consists of air duct pipes andradial ribs, which provide rigidly to the frame. Footings
are provided to support the stator on the skid. The stator
frame should be rigid due to the various forces and
torque during operation. The welded stator frame
consists of the two end plates, axial and radial ribs. The
arrangement and dimensioning of the ribs are determined
by the cooling air passages, the required mechanical
-
7/31/2019 Project Tg04
30/184
strength and stiffness. The end covers are Aluminum
alloy castings. The stator frame is fixed to the skid with
the help of hexagonal bolts. The skid is temporarily fixed
to the concrete foundation through bolts.
3.1.2. Stator Core
Stator core is stacked from the insulated electrical
sheet laminations and in the stator frame from insulated
dovetailed guide bars. Axial compression is fromclamping fingers, clamping plates and non-magnetic
clamping bolts which are insulated from the core. In
order to minimize the hysteresis and eddy current losses
of the rotating magnetic flux, which interacts with the
core, the entire core is built up of lamination, each layer
of which is made from a number of individual segments.
The segments are punched from the silicon steel. In the
-
7/31/2019 Project Tg04
31/184
outer circumference the segments are stacked in
insulated trapezoidal guide bars, which hold them in
position. The guide bar is not insulated to provide for
grounding the core. The laminations are hydraulically
compressed and heated during the stacking procedure.
The complete stack is kept under pressure and fixed in
the frame by means of cells.
The core packed into the stacking frame is pressedfirmly together between the end plates of the machine
frame and fixed in this position by welding the axial ribs
of the core and end of the plates of frame. End fingers on
the inside diameter of the end plates transmit the
pressure to the teeth of the core. The compressive force
produced prevents the laminations and teeth from
vibrating. An eye is welded to each end plate for
-
7/31/2019 Project Tg04
32/184
attaching suitable lifting gear with adequate lifting
capacity for transporting the complete machine. All the
forces that occur during normal operation or on short
circuits are transmitted from the stator yoke to the frame
via the seating plates and into the foundation.
3.1.3. Stator Winding
The winding is a double layer multi turn lap winding.
The half coils are made up of electrolytic copper stripsinsulated with mica based epoxy insulation of suitable
thickness to give a long and uninterrupted service. Each
strip is staggered to 360degrees and it passes through all
the sides of the coil. This process is called transposition.
The purpose of transposition is to avoid the circulation
currents due to eddy current and also to avoid corona
losses. The straight parts of the half bar are coated with
-
7/31/2019 Project Tg04
33/184
conductive varnish to prevent corona discharges in the
slot. The end winding is specially shaped to form a
basket with an inviolate shaped over hang of the bars.
The straight portion of the winding is secured by means
of wedges driven into the slot position. The resistance
thermometer elements are placed in the core teeth at
carefully selected points to measure the temperature rise
of the machine. Epoxy glass laminated brackets support
the end winding. Epoxy glass laminated spacers to give arigid structure to withstand the short circuit forces of the
three-phase winding are connected to the connecting
strips, which are also insulated and secured in position.
Six output terminals are brought out from the rings of the
insulated covers.
-
7/31/2019 Project Tg04
34/184
-
7/31/2019 Project Tg04
35/184
Fig 3.1 Wound Stator
3.1..4 End Covers
The end covers are the castings of the aluminum alloy
and are bolted to the side plates of the stator frame. The
inlet passage is specially designed with built in guide
vanes, which ensure uniform distribution of the air to the
-
7/31/2019 Project Tg04
36/184
fan. Air ceiling is provided around the shaft and at the
parting plane of the top and bottom parts of the end
covers so that suction of oil vapor from the bearings does
not take place.
3.1.5. Location of Bars
A semi-conducting wrapper of graphite paper in the
slot protects the bar. The stator winding is protected
against the effects of current forces in the slot section. Toensure tight seating of the bar at the slot bottom, a slot
bottom-equalizing strip of stress path is inserted. A top
ripple spring is arranged between two compression strips
to exert a continuous pressure on the bars. The bars are
shaped so that, cone shaped end windings are obtained.
In order to reduce the stray losses a small cone taper of
-
7/31/2019 Project Tg04
37/184
(13-20deg) is used. On the wide sides of the bars spacers
of insulating material are inserted at regular intervals.
3.1.6. Enclosure
The enclosure consists of the inner and outer
components. The inner components comprises of the
winding covers, which from an angular enclosure of top
and bottom parts and is designed as required for
particular degree of protection, as indicated in thedimension drawing or in the Technical data. The
ventilating circuit is of the double-ended symmetrical
arrangement.
-
7/31/2019 Project Tg04
38/184
3.1.7. Electrical Connections of Bars and Phase
Connection
Brazing makes electrical connection of Bars: Electrical
connection between the top and bottom bars, one top bar
being brazed to the associated bottom bar. The coil
connections are wrapper depends on the machine
voltage. After tapping, an insulating varnish is applied.
3.1.8. Phase Connectors:
The phase connectors consist of flat copper sections,
the cross section of which results in a low specific
current loading. The connections to the stator winding
are of riveted and soldered type. The phase connectors
are wrapped with resin rich mica type, which contain
synthetic resin having very good penetration properties.
The phase connectors are then cured at a certain
-
7/31/2019 Project Tg04
39/184
temperature, with the shrinking tapes contracting so that
a void free insulation is obtained.
3.1.9. Output leads
The beginning and ends of three phase windings are
solidly bolted to the output leads with flexible. The
output leads consist of flat copper sections with mica
insulation. To prevent eddy-current losses and
inadmissible temperature rises: the output leads arebrought put.
-
7/31/2019 Project Tg04
40/184
-
7/31/2019 Project Tg04
41/184
Photo 3.2. Phase connectors and rings
3.2. ROTOR:
The rotor is forged from a homogeneous steel ingot of
specially alloy steel properly heat treated to meet the
required mechanical, metallurgical and magnetic
properties. Axial slots are milled through out the active
-
7/31/2019 Project Tg04
42/184
length of the rotor body to accommodate the conductors.
The slots are dovetailed at the top of housing the wedges.
3.2.1. Rotor shaft
The rotor shaft is forged from a vacuum cast steel ingot.
The high mechanical stresses resulting from the
centrifugal forces and short circuit torque call for high
quality heat-treated steel. The rotor consists of an
electrically active portion and two shafts end.Approximately 60% of the rotor body circumference has
longitudinal slots, which hold the field winding. Slot
pitch is selected so that 1800 displace the two solid poles.
The rotor wedges act as damper winding within the
range of winding slots. The rotor teeth at the ends are
provided with the axial and radial holes, enabling the
-
7/31/2019 Project Tg04
43/184
cooling gas to be discharged into the air gap after,
intensive cooling of the end windings.
3.2.2. Rotor Winding
The field winding consists of several series connected
coils inserted into the longitudinal slots of the rotor body.
The coils are wound so those two poles are obtained. The
solid conductors have a rectangular cross-section and are
provided with axial slots for radial discharge of thecooling gas. The individual conductors are bent to obtain
half turns. After insertion into the rotor slots, these turns
are combined to form full turns of the series connected
turns of one slot constituting one coil. The individual
coils of the rotor winding are electrically series
connected so that one north and one south magnetic pole
are obtained.
-
7/31/2019 Project Tg04
44/184
3.2.3. Rotor Slot Wedges
To protect the winding against the effects of the
centrifugal force, the winding is secured with wedges.
The slot wedges are made from an alloy high strength
and good electrical conductivity, and are also used as
damper wedged bars. The retaining rings act as short
circuit rings to induced current in the damper windings.
3.2.4. Cooling of Rotor Windings
Each turn is subdivided into four parallel cooling zones.
One cooling zone includes the slot from the center to the
end of the rotor body, while another covers half the end
winding to the center of the rotor body. The cooling air
-
7/31/2019 Project Tg04
45/184
for the slot portion is a limited into the slot bottom ducts
below the rotor winding. The hot gas at the end of the
rotor body is then discharged into the air gap between the
rotor body and stator core through the radial openings in
the conductors and in the rotor slot wedges. The cooling
air for the end windings is drawn from below the rotor-
retaining ring. It rises radically along the individual coils
and is then discharged into the air gap.
3.2.5. Rotor Retaining Rings
The rotor retaining rings with stand the centrifugal forces
due to the end windings one end of each ring is shrunk
on the rotor body, while the other end of the ring
overhangs the end winding without contact on the shaft.
The shrunk on the hub at the free end of the retaining
serves to reinforce the retaining ring and secures the end
winding in the axial director at the same time. The shrink
-
7/31/2019 Project Tg04
46/184
seat of the retaining ring is silver plated, ensuring a low
contact resistance for the induced current. To reduce the
stray losses and have high strength, the rings are made of
non-magnetic core worked materials.
3.2.6. Slip Rings
These are made of forged steel and shrunk on either side
of the rotor between the end cover and the bearing. Themica splitting is used to insulate the slip rings from the
rotor body. The excitation to the rotor winding is taken
from these slip rings. The connection leads are suitably
insulated and taken through slots milled on the surface of
the rotor. Wedges are provided to keep the leads in
position. A helical groove is machined on the outer
-
7/31/2019 Project Tg04
47/184
surface of the slip rings to have better dissipation of heat,
thus minimizing the brush wear.
3.2.7. Rotor Fan
The generator cooling air circulated by the two axial
flow fans located on the rotor shaft at either end. To
augment the cooling of the rotor winding the pressure
established by the fan works in conjunction with the air
expelled from the discharge ports along the rotor shaft.The blades are screwed into the rotor shaft. The blades
are forged from an aluminum alloy. Threaded root
fastening permits the blade permits the blade angle to be
changed.
-
7/31/2019 Project Tg04
48/184
-
7/31/2019 Project Tg04
49/184
Photo 3.3 Rotor over hang Portion
-
7/31/2019 Project Tg04
50/184
3.2.8. Rotor Balancing
The rotor is balanced with the help of sophisticated
balancing machine. The balancing weights are provided
in the hubs under retaining rings and in the fans. The
rotor is dynamically balanced and subjected to an over
speed of 20% for 2min.
3.2.9. Field Connections
The field connections provide the electrical connection
between the rotor winding and the exciter.
3.2.10. Terminal Lugs
-
7/31/2019 Project Tg04
51/184
Consists of a copper conductor of rectangular cross-
section. One end of the terminal lug is brazed to the rotor
winding, while the other end is screwed to the radial bolt.
3.2.11. Radial Bolt
The field current lead located in the shaft bore is
connected to the terminal lug through a radial bolt. The
radial bolt is made from steel and screwed into the field
current lead into the shaft bore.
3.3 BEARINGS
The generator rotor is supported at two-journal bearing.
The bearings consist of a bearing pedestal and bearing
shell is split into two halves to facilitate assembly. The
bearing pedestals are iron castings and the bearing shells
are the steel castings. The bearing pedestals are
-
7/31/2019 Project Tg04
52/184
providing with a spherical seating surface and bearing
shell rests into with its outer spherical surface. The inner
surface of the bearing shell is provided with spherical
grooves and cast with Babbitt metal.
3.3.1. Bearing Oil Supply
The oil required for the bearing lubrication and cooling
is obtained from the turbine oil supply system supplied
to the lubricating groove in the bottom-bearing sleeve.The upper bearing sleeve consists of a wide overflow
groove through which oil is distributed over the shaft
journal and fed to the lubricating pump.
3.3.2. Bearing Temperatures
One double-element resistance temperature detectors
monitor the temperatures of each bearing. The resistance
-
7/31/2019 Project Tg04
53/184
temperature detector is screwed in the position on side of
the low bearing sleeve from outside with the detector
extending to the Babbitt liner.
3.4. VENTILATION AND PROTECTION
EQUIPMENT:
3.4.1. Ventilation Arrangement
The turbo generator is cooled by air circulated by meansof two axial fans. Air coolers cool the air after
circulation. The air is drawn through suction ducts by
axial fans mounted on either side of the rotor. The warm
air flows out through the exhaust at the bottom of the
stator frame.
3.4.2. Space heaters
-
7/31/2019 Project Tg04
54/184
These heaters are used to circulate warm air inside the
turbo generator and during outages to prevent
condensation of the moisture inside the machine. They
are of strip type and robust design. The heating elements
are enclosed in a steel sheet with specific rating of 15W
per sq. inch of the surface. They are so designed that
they may be fixed in the suction ducts of the turbo
generator. The heaters are completely covered in order to
prevent the accidental contact with the heat units.3.4.3. Resistance Temperature Detectors
The resistance temperature detectors are made up of
Platinum resistance elements. The detectors are placed in
a groove cut in a rectangular glass laminate and
embedded in different positions like stator teeth, stator
core, and slots. There are 12 active and three spare
elements distributed in different locations in 3 different
-
7/31/2019 Project Tg04
55/184
planes, 5active plus 3 spare elements are placed in stator
slots, 4 active are placed in stator core, 3 are placed in
teeth to measure the hot and the cold air temperatures.
The resistance thermometers are fixed in the exhaust
hood of the stator frame and the end covers. The leads
from these resistance thermometers are brought out and
connected to the terminal board. The leads coming from
the spare elements are brought up to the terminal board
and left inside the machine. These resistance temperaturedetectors operate on the principle that the resistance of
the elements will change depending on the temperature
coefficient of the element. The change in resistance can
be accurately measured in a bridge circuit. A graph is
drawn showing the variation of resistance with
temperature, which is used to know the temperature rise
-
7/31/2019 Project Tg04
56/184
under different operating conditions of the turbo
generator.
3.4.4. Fire Detectors
For the protection of turbo generator against any possible
fire hazards 12 fire detectors relays are provided on
either side of the stator winding. These relays have a set
of normally open contacts. The set of contacts will close
when the temperature surrounding the first relay exceeds80deg Celsius. The other relay set of contacts close when
the temperature exceeds 1000. These contacts are wired
up to the terminal board provide on the stator frame for
the resistance temperature detectors. Both the sets of
contacts are used for automatic fire alarm shutting down
of the turbo generator system and for the release of CO2
gas from the Carbon dioxide system.
-
7/31/2019 Project Tg04
57/184
3.5. Insulating systems are of two types:
1.Resin rich system of insulation
2.Resin poor system of insulation
3.5.1. Resin rich system
- Conductor cutting and material used is same as
resin poor system.- Transposition is done same as that of resin poor
system.
- Stacking of coils is done. In this case high resin
glass cloth is used for preventing inter half shorts.
- Putty work.
-
7/31/2019 Project Tg04
58/184
- Nomex is used as transposition pieces. Putty
mixture is a composition if mica powder, china clay and
SIB 775 Varnish.
- Straight part baking is done for 1hour at a
temperature of 160OC and a pressure of 150kg/ sq.cm
- Then bending and forming is done.
- Half taping with resin rich tape is done for over
hangs and reshaping is done.
- To ensure no short circuits half testing of coils isdone.
- Initial taping is done and final tapings is done with
resin rich tape to about 13-14 layers.
- Final baling is done for 3hrs at a temperature of
160OC in cone furnace.
- Gauge suiting is done.
-
7/31/2019 Project Tg04
59/184
-
7/31/2019 Project Tg04
60/184
3.6. VACUUM PRESSURE IMPREGNATION
Siemens electrical machines quality is highly
dependent on the vacuum pressure impregnation
insulation system. All the high voltage machines, pole
coils irrespective of size and shape are being
impregnated under vacuum and pressure of self
developed Siemens patent resin systems. The stringent
quality tests on the resin mixtures and strictly following
the vacuum pressure impregnation and systematiccooling and heating cycle of resin mixture and
sophisticated automatic control systems made the
insulation systems for better and better quality for more
than 30 years, made Siemens pioneers in this field. The
insulating materials used by Siemens for wedges are
resin poor and accelerator treated. For eg. Main
insulation tapes, mica paper tapes, overhang protective
-
7/31/2019 Project Tg04
61/184
tapes, shrink tape and glass mates HM693 are treated
with accelerator. After impregnation, they become hard
experiments were conducted for voltage endurance at
room temperature and at evaluated temperature
continuously for more than 3 years. Though the mica
tape can withstand 20kv per mm, the extrapolation has
been done at 4kv/mm and life expectancy is around
100yrs. With an operation stress level of less than
4kv/mm, factor of safety is considerable. The Vaccumpressure impregnation system was brought by Dr.Meyer
with the collaboration of westinghouse in the year 1956.
The resins used were of polyester. Siemens developed
the present Vaccum pressure impregnation system with
epoxy resin and treated accelerator on tapes. The mica
tapes used for Vaccum pressure impregnation systems
are ROGS 275, ROGS 275.1 and ROV 292. ROGS 275
-
7/31/2019 Project Tg04
62/184
tapes are with glass cloth baking upto 13.8 kV voltage
levels ROV 292 mica paper tapes are with polyester
fleece above and more penetration of resin. ROGS 275.1
tape is special glue varnish for tropical countries like
India and Brazil to resist higher humidity. The glue
being used for main insulation tape is X2026 and for
conductor insulation is X2027.
The resin used for Vaccum pressure impregnation is ET884, a mixture of epoxy resin E1023 (lekuther m x 18)
and hardener H1006 in 1:1.2 ratio by weight. In kwu, the
components are mixed in 1:1 ratio.
E1023: The resin is in drums of 220 kgs weight. It is in
crystal form at temperature of 14 or 20deg.C the
container is resin is available in drum the reason is faster
-
7/31/2019 Project Tg04
63/184
heating in furnace, the resin in liquid state shall not come
out of the container. The drums are kept in oven and
heated up to 1000 C for about 18hrs. If the resin is not
fully in liquid condition, can be heated up to 1250C the
storage tank is filled with resin first depending on the
volume and ratio of mixture at a temperature of 600 C
through hose pipes. Resin filling is being done by
creating 0.2 bar vacuum in the tank.
RESIN MIXTURE: The mixing ratio of resin to harden
is 46:54 parts.
The resin mixture required for the siemens Impregnation
tank is 27000lts. A job of 1.9m height and 4.5m dia can
be impregnated.
-
7/31/2019 Project Tg04
64/184
Size of the tanks
-Main impregnation tank = 4.5m pie x 3.0m ht.
-There are 3-inch vessels for different sizes jobs
impregnation.
(a) Vessel (1) 3.8m pie x 2.25m ht.
(b) Vessel (2) 3.0m pie x 2.3m ht.
(c) Vessel (3) 2.0m pie x 2.3m ht.
3 Storage tanks of each resin capacity 9000 litres are inthe operation for storing. The resin mixture cooling and
heating cycle is by circulating the resin through the heat
exchangers. Oil heated by water is being used for heat
exchangers.
The Vaccum pressure impregnation cycle is as per WIV
114.1 standard.
Job preheating 70oc 12 hrs.
-
7/31/2019 Project Tg04
65/184
The job is kept in an oven for a period of 12hrs at a
temperature of 70OC. 6 nos thermocouples are inserted
on the back of the core and measured the temperature.
Job insertion in the impregnation tank at 70oc
The lid of the impregnation tank in open condition. The
vessels are kept clean. Resin is available is wiped out by
methylene. Traces of resin shall not be allowed on the
inner side of the tank. It reacts with humidity and scale
formation will takes place. These component andobstruct the filters also. The resin at the time of cleaning
is carefully removed by wiping with rubber sheets.
Keeping the vessel in slant position on the ground also
cleans the inner vessels. After ensuring the perfect
cleaning, the tank should allowed for further operation.
The job is inserted in the tank the temperature
monitoring thermocouples are placed on the back of the
-
7/31/2019 Project Tg04
66/184
core. The lid is allowed to come down by hydraulic
motor. Silicon grease is applied on the surface of tank
where the lid is touching. A rubber gasket is also
provided on the rim not to allow any leakage. Air pipes
are closed and vacuum pumps will be started.
Vacuum creation 0.35 torr for 2 hrs:
The job temperature is to be maintained always above
65
O
C , if found less, tank can be heated up. In practice,the vacuum can be created in 2 hrs. Siemens adept before
starts of 2nd shift (3.0 pm), they create 0.35 torr vacuum
and it will be continued till next day morning 1st shift
(6.00 am) min. requirement is 2hrs.
During this time the resin cooling is being carried out to
reach 10deg.C and heated up automatically to 70deg.C.
-
7/31/2019 Project Tg04
67/184
IMPREGRATION:
The resin mixture is to be heated to 70deg.C. Everyday
morning a 20ml sample will be taken to laboratory tests.
Viscosity will be measured at 70deg.C. It should not be
more than 45 CD +10%. Anew resin will beat 15 CP.
New resin and hardener mixture is to be added if the
viscosity is more. The resin filling is being completed in
25 minute. At this time, the vacuum reduces to 0.5 Torr 1 Torr level. The resin is to be allowed to settle for 15
min. The level of resin is above 100mm over the job.
Pressuring 3 bar
With the hydrostatic pressure of the resin, only surface of
the insulation can be filled with resin. To have an
effective penetration up to the end of a barrier, pressure
-
7/31/2019 Project Tg04
68/184
is to be created to 3 bar (2 bar over atm. Pressure of 1
bar).
Gelling time:The polymerization of resin and accelerator take place at
this time. At 65OC, the time required is 170 min. The
insulation gets hardened.
Curing 14 hr at 140 O C
The resin is to be pumped back to the storage tank. The
job is to be removed from the tank and allowed for
dripping. It is kept in oven at 140deg.C for min of 14 hrs.
-
7/31/2019 Project Tg04
69/184
The accelerator B1057.1 is to be placed at 4 corners of
the oven. In curing process the accelerator vapors will
react with surface resin and cures.
CHARACTERISTICS OF VPI INSULATION
SYSTEM:
1) Higher mechanical bond
2) Void free insulation
3) High dielectric strength, low dissipation factor,hence longer electrical life.
4) Better heat transfer
5) Higher thermal stability, ensures class-F under
running conditions
6) Less maintenance
7) Cost effective
-
7/31/2019 Project Tg04
70/184
8) Low inflammability, hence limited damage
during abnormal operations.
9) High resistance to oil, acid, alkali and moisture.
10) Manufacturing cycle is less
11) Frame size is small, machine cheaper.
12) Elastic response to thermo-mechanical stress,
machine suitable peak load operation
VACUUM PRESSURE IMPREGNATION
PROCESS:
Four stages of Vacuum pressure impregnation cycle
1) vacuum drying:
-
7/31/2019 Project Tg04
71/184
temperature : 60oc +/- 3oc
pressure : 0.2 millibar
duration : ~ 16-18 hrs
drying check: 0.06 mbar drop in 10min
2) Imprgnation:
resin temperature : 60oc +/- 2oc
resin filling : ~ 20 min
resin level : ~ 100 mm above
settling time : ~ 10 minresin (epoxy bisophenol a) & hardener ratio 1:1
3) Pressurisation:
N2 pressure : ~ 4 bar
rising : ~ 80 min
holding time : ~ 2 hrs
capacitance measurement to ensure effective
-
7/31/2019 Project Tg04
72/184
peneteation and gelling
4) Post curing:
temperature of job : 140oc +/- 5oc
duration : ~ 20 hrs
INSULATING MATERIALS USED IN THE
STATOR WINDING:
USAGE MATERIAL
DESCRIPTION
A foam insulation forslot bottom layer of
stator coil
Semi conductive foamfleece
Slot bottominsulation
Semi conductive fleece
Inter layer insert Glass mat
(compressible)
-
7/31/2019 Project Tg04
73/184
Top insulation -do-
Spacers in overhang -do-
Bandage ring spacers -do-Slot wedge Glass mat (Hard)
Fillers for Slot Mergespacer
-do-
Slot Merge spacer -do-
Stiffeners between top& bottom layers
Glass mat (repressed ina hydraulic fixture)
Interlacing for ring andstiffeners
Glass Sleeve
Typing of spacers b/wcollector rings
Glass tape
Insulation of rings Fine mica paper glass
tapeShrink and protectionlayer
Polyester shrink tape
Adhesive varnish fortape ends
Adhesive varnish
-
7/31/2019 Project Tg04
74/184
Bandage rings Polyester resin + glassravings
Terminal boards Glass mat (hard)
Table 3.1 List of
insulating materials
Photo 3.4 Wound Stator at VPI Plant
-
7/31/2019 Project Tg04
75/184
Photo 3.5 Impregnation Plant
-
7/31/2019 Project Tg04
76/184
3.7.EXCITER
3.7.1. Design Features
The exciter consists of
- Rectifier wheels
- Three-phase main exciter
- Three-phase pilot exciter
The three-phase pilot exciter has a revolving field with
permanent-magnet poles. The three-phase ac is fed to the
field of the revolving-armature main exciter via astationary regulator and rectifier unit. The three-phase ac
induced in the rotor of the main exciter is rectified by the
rotating rectifier bridge and fed to the field winding of
the generator rotor through the dc lead in the rotor shaft.
A common shaft carrier the rectifier wheels, the rotor of
the main exciter and the permanent magnet rotor of the
pilot exciter. The generator and exciter rotors are thus
-
7/31/2019 Project Tg04
77/184
supported on a total of three bearings. Mechanical
coupling of the two-shaft assemblys results in coupling
of the dc leads in the central shaft bore through the multi
contract electrical contact system.
3.7.1.1. Rectifier wheels:
The main components of the rectifier wheels are the
silicon diodes, which are arranged in the rectifier wheels
in a three-phase bridge circuit. A plate spring assemblyproduces the contact pressure for the silicon water of the
diodes. One diode each is mounted in each light metal
heat sinks and then connected in parallel. Associated
with each diode is a fuse, which serves to switch off the
diode from the circuit if it fails. Each arm of the diode
bridge is provided with one RC block. The three-phase
connection between the armature and diodes is obtained
-
7/31/2019 Project Tg04
78/184
-
7/31/2019 Project Tg04
79/184
-
7/31/2019 Project Tg04
80/184
with the help of hexagonal bolts. Footings are provided
to support the stator on the skid.
-
7/31/2019 Project Tg04
81/184
Photo 3.6 Exciter
4. TESTING OF TURBOGENERATOR
4.1. Objectives of testing
-
7/31/2019 Project Tg04
82/184
Testing is the most important process to be conducted
on a machine after it is designed. The testing of
machine is necessary primarily to establish that the
machine performance complies with the customer
specifications. Tests ensure that the piece of
equipment concerned is suitable for and capable for
performing duty for which it is intended.
Testing is done under condition simulating closely aspossible to those, which will apply when the set is
finally installed with a view to demonstrate to
purchasers representative its satisfactory operation.
Test provides the experimental data like efficiency,
losses, characteristics, temperature limits, etc. for the
use of design office, both as confirmation of design
-
7/31/2019 Project Tg04
83/184
-
7/31/2019 Project Tg04
84/184
-Ensures process capability and develops checklist.
- Increases confidence levels in manufacture.
- Establishes control over raw materials.
-Helps in building of safety and general operation
and manual.
4.2. TYPES OF TESTS
Tests on turbo generators are classified under the
following headings, which is also the order in whichthese are performed during the course of manufacture.
1.Tests on the materials and components during the
manufacture so as to control the quality of the materials
in process also known as Process tests.
2. Performance tests on the machine to prove the
performance of the generator in accordance with the
required standard.
-
7/31/2019 Project Tg04
85/184
4.3. TESTS DURING MANUFACTURE/
PROCESS TESTS:
Tests on rotor winding
Tests on stator coils.
Balancing and over speeding of rotor.
4.3.1.Rotor winding
The rotor coils and their insulation are subjected to a high
stress when in normal operation. Thus a thorough
inspection of these is necessary before putting them in the
rotor slots as otherwise any replacement of the faultyinsulation or cell would necessitate
removing the coil binding rings and the wedges, which is
a cumber job. A series of graded voltage tests are
-
7/31/2019 Project Tg04
86/184
conducted on the rotor cell and coils dusting assembly and
also when finished to test its electrical strength against
likely creep age to ground or inter turn breakdown.
4.3.2.Tests On The Rotor Coils
1. Between turns:
The rotor coils turns are made up of a number of turns
which are formed in halves and then assembled withtheir inter turn insulation and boned with an adhesive in
the steam heat press. Although the normal working
voltage per turn is very small, a turn to test of 240 volts
is done to exercise quality control.
2.Top turn trough:
The insulation the top and bottom of the rotor slot
provides adequate and safe creep age distance between
-
7/31/2019 Project Tg04
87/184
copper and rotor steel, in case of slotted copper 500 volts
for one minute to test the top trough.
3. Collecting leads:
A high voltage equivalent to the shipping test plus
1500v is applied to the collector leads when fitted in
bore with studs of seals fitted but before connecting to
the windings.
4.3.3.Tests on stator coils
As per the standards the stator winding has to be
subjected to a shipping pressure test of (2 x line
voltage +1kv). This power frequency voltage applied
for one minute.
In order that machine when found with stands this
final voltage test and any faulty coil is eliminated
during various stages of coil manufacture and
-
7/31/2019 Project Tg04
88/184
winding. Because of the continued application of HV
tests overstress the winding insulation, the voltage is
reduced in various stages.
1.Tests between parallel strips
This is a test of strip insulation provided for eddy emf,
on low voltage at the order of 350V for 3 seconds is
applied.
2.Coils in manufacturing and Winding Sections:
When the coils are first tested, a voltage of 8kV in excess
of shipping pressure test is applied, and this voltage tests
are repeated.
3.Tests on Thermocouples:
1000V Megger test is applied to the thermocouples.
-
7/31/2019 Project Tg04
89/184
4.3.4. Balancing and over speeding of rotors
1.Balancing:
One of the most important preliminaries to testing is that
of balancing the rotors. Before over speeding, the rotor is
dynamically balanced, in cold as well as hot conditions.
A set of run up and run down is taken sure those critical
speed is well away from the running speed.
2.Over Speeding:
In order to check the soundness of all parts and fitting on
rotor assembly, the rotor is run at an over speed of 14%
for five minutes or 30% for one minute.
4.4. PERFORMANCE TESTS/ TESTS ON
COMPLETED MACHINE:
-
7/31/2019 Project Tg04
90/184
The machine is assembled and erected at the heavy
rotating plant test bay for test.
1. Dry out insulation resistance of rotor & stator
windings
- Before starting with running tests, the stator
windings are dried out by circulating current in the
winding from an external dc source Input of power is
so controlled as to limit the temperature of the endwindings to a maximum of 800C by thermometer.
-Progress of dry out is observed by one minute
insulation resistance reading with 1000v Megger.
With the application of heat, the insulation resistance
will initially drop and then will rise again over a
period of time and finally becomes approximately
constant temperature. Ration of ten-minute reading
-
7/31/2019 Project Tg04
91/184
i.e. polarization index, when more than 2 gives an
indication of good dry out. Insulation resistance
readings of rotor winding to ground are taken.
2.Resistance of machine windings
Measurement of cold winding resistance, both for stator
and rotor must be very accurate since it forms the
basis of
Calculating copper under cold and hot conditionsFor determining the rise in temperature of rotor winding
by resistance method at the end of temperature test.
All precautions are taken to ascertain correct temperature
of the winding white measuring cold resistance. Since
the winding resistance of turbo generator is quite low: a
modified form of wheat stone bridge i.e. Kelvins double
-
7/31/2019 Project Tg04
92/184
bridge does away with the necessity of accounting for
the resistance of loads. Resistance between phases for
stator and between slip rings for is recorded along with
the cold winding temperature at the time of
measurement.
3.Phase sequence test:
The phase sequence test is to check the agreement of the
terminal markings that have been specified using thePhase Sequence Indicator.
4.Zero excitation rated speed run
By wattmeter method when condition is steady. From the
result of above test after deducting drive motor in gear
losses, friction and wind age losses of the machine under
test are computed. These losses are for rated speed.
-
7/31/2019 Project Tg04
93/184
Bearing oil quantities with inlet temperatures of oil can
yield calculations for bearings loss. From a previous data
on seal face losses determined from a prototype test, the
total friction loss in the bearings and seals can be
difference. Since bearing loss is computed for design
office use by the difference. Since bearing loss goes to
oil, any heat carried out on the unexcited machine will
give temperature rise due to wind age.
4.4. PERFORMANCE TESTS
The performance tests on the turbo generator are
classified as:
-Type tests
-Routine tests
-Heat run tests
-
7/31/2019 Project Tg04
94/184
4.4.1. TYPE TESTS
These are specially requested tests form the customer.
They are not performed on all machines i.e., they are
specific to machine. They include
-Mechanical measurement of leakage reactance of
stator winding
-Measurement of residual voltage of stator winding
at rated speed
- Line to line sustain short test and determination ofnegative sequence reactance [X2]
- Line-to-line and neutral sustain short circuit test and
determination of negative sequence reactance [XO]
- Retardation test for determination of GD2
4.4.1.1 Measurement of leakage reactance of stator
winding
-
7/31/2019 Project Tg04
95/184
-
7/31/2019 Project Tg04
96/184
-
7/31/2019 Project Tg04
97/184
where Z = U/ 3I,
R = P/ 3 I2
U = voltage measured during the test
I = current measured during the test
P = power measured during the test
As the value of R i.e., stator winding resistance per
phase is negligible compared to Z, measurement of P
is not required.
XL = Z = U/ 3 I ohms% XL = 100(XL / XN)
iii) Potier reactance % XP = a ( % XL)
where a = 1 for salient pole machine and
0.63 for cylindrical pole machine
-
7/31/2019 Project Tg04
98/184
-
7/31/2019 Project Tg04
99/184
-
7/31/2019 Project Tg04
100/184
parameters are recorded at three values of the short
current limited to 30% at rated current.
- Short circuit current (IK2), through current
transformer
- Voltage between the open line terminal and one of
the short circuit terminals Uk2, through potential
transformer.
-Active power p.
Evaluation of negative sequence reactance (X2)
(i) X2 = P / 3. (I K2)2 ohms
where P = power measured during the test
IK2 = line-to-line short circuit current measured
during the test %X2 = 100(X2/Xn)
-
7/31/2019 Project Tg04
101/184
-
7/31/2019 Project Tg04
102/184
IO = line to neutral current measured during
the test
% Xo = 100 (Xo / Xn)
Note: Minimum time is taken for the test because serious
overhang winding heating may result, if current is
sustained for a longer time or raised to too high a value.
-
7/31/2019 Project Tg04
103/184
-
7/31/2019 Project Tg04
104/184
-
7/31/2019 Project Tg04
105/184
4.4..1.5.Redardation test for determination of GD2
(Gravitational deterioration)
The machine along with the drive system is run at rated
speed and drive motor input power is noted. Then speed
is increased by 1hz corresponding rpm over the rated
speed and at the stage, the machine is tripped by opening
the in-comer circuit breaker of drive system. Time and
speed are noted with an interval of 5 seconds upto 30
seconds, with an interval of 10 seconds upto 1minute andso on till the machine comes to stand still.
1.Evaluation of GD2
GD2 is calculated as follows:
Time versus speed curve is plotted on a graph paper,
taking X axis as time and Y-axis as speed. A tangent is
drawn at rated speed point on the curve, which meets the
-
7/31/2019 Project Tg04
106/184
-
7/31/2019 Project Tg04
107/184
-
7/31/2019 Project Tg04
108/184
-
7/31/2019 Project Tg04
109/184
-
7/31/2019 Project Tg04
110/184
-
7/31/2019 Project Tg04
111/184
4.5.1. Static tests
4.5.1.1. Measurement of insulation resistances of stator
and rotor windings before and after high voltage test:
Equipment:
a) Megger (1000V/ 2500V)
b) Earthing rod and earthing wire/ cable.
- Insulation resistances of the stator and rotor
windings are measured separately before and afterhigh voltage test using 2500V Megger for stator and
1000V for rotor winding. These values are taken at
15 seconds and at 60 seconds. Absorption coefficient
of insulation is found out as,
Insulation resistance at 60seconds
Absorption coefficient =
------------------------------------------
-
7/31/2019 Project Tg04
112/184
-
7/31/2019 Project Tg04
113/184
value of 1.8 and 1.7 may be satisfactory, while a
value below 1.5 indicates a damp machine.
-The winding is discharged to earth after each
measurement.
4.5.1.3.Measurement of polarization index of stator
winding
The polarization index of stator winding, all the threephases together is measured using 2500V Megger after
high voltage test. The insulation resistances are noted at
1minute and at 10 minutes from starting of measurement.
The polarization index is evaluated as follows:
Insulation resistance valueat 10 minutes
-
7/31/2019 Project Tg04
114/184
-
7/31/2019 Project Tg04
115/184
The high voltage is applied to winding by increasing
gradually to required value and maintained for one
minute and reduced gradually to minimum. The
transformer is switched off and winding is discharged to
earth by shorting the terminal to earth using earthing rod
connected to earthed wire/ cable. The test is conducted
on all the phases and rotor winding separately.
High voltage test levels:Stator winding: (2Ut + 1) kV = 23 kV for 11 kV
machine.
Rotor winding: (10 Ue) volts.
(with minimum of 1500 V and maximum of 3500V).
where, Ut = Rated voltage of the machine (kv).
Ue = Excitation voltage.
1. Stator winding:
-
7/31/2019 Project Tg04
116/184
Testing of stator winding involves the testing of
connecting rings after the assembly and stator bars
during assembly.
Up = (2 Un + 1)
Where, Up is the final test voltage after the test run
and Un is the rated voltage of the generator.
- The connecting rings are tested for 1.2 UP for 1
minute. If there is sparking due to less distance
between the live joints, the same can be done with 1.1UP. If the connecting rings are assembled after laying
bars, they are tested along with the bars.
-The high potential is given to copper and the core is
earthed. The output voltage of the high voltage tester
is continuously increased to test the voltage level,
held for 1 minute and subsequently decreased to
initial level.
-
7/31/2019 Project Tg04
117/184
- After the bottom bars are laid they are tested for 1
minute with 1.1 UP. Individual strips are of each bar
are tested with 220V ac for any possible inter half
shorts and inter bundle shorts.
- After the top bars are laid, High voltage testing is
carried out with 1.1 UP for 1 minute and they are
tested for inter half and inter bundle shorts. Inter halfshorts test with 220V ac is carried out after
connecting the top and bottom bars without the
connecting rings.
- High voltage testing of the individual phases with
1.05 UP is carried out for 1 minute after the
completion of the winding . When one phase is under
test the other phases are earthed.
-
7/31/2019 Project Tg04
118/184
-Resistances of individual phases are measured .
-During high voltage testing all the instrumentation
cables assembled in the machine are to be earthed.
-Insulation resistance of each phase is to be measured
after each high voltage test.
-Whenever bunch brazing is employed for
connecting top and bottom layers, only inter half
shorts test is to be carried out.
2. Rotor winding
The rotor winding must be tested at various stages of its
manufacture and assembly.
-The output of the high voltage test equipment is
connected to the output lead or to the winding as the
case may be and shaft is earthed. The voltage is
continuously increased to test voltage level,
-
7/31/2019 Project Tg04
119/184
maintained for 1 minute and subsequently decreased
to initial value.
-To test for inter turn shorts the required voltage is
applied across the total winding of both the poles and
voltage across the winding corresponding to each
pole is measured and recorded.
- The final test voltage UP is ten times the rated
voltage subjected to a maximum of 3.5 kV and
manimum of 1.5 kV.- Before assembly of rotor bars HV test is carried
with UP + 2000V for one minute. Then both the poles
against earth are tested with UP + 1500 V for one
minute.
- After the assembly of the rotor bars HV test is
carried with UP + 1500 V for one minute initially pole
against pole and then against earth.
-
7/31/2019 Project Tg04
120/184
-
7/31/2019 Project Tg04
121/184
- After over speeding and balancing at standstill HV
testing of the winding against the shaft with UP+200V
ac is carried out for one minute.
- HV testing of the winding is carried out at 3000 rpm
with 500V ac for one minute. Then the winding is
tested against the shaft with UP for one minute.
-The insulation resistance value of the winding is
measured after each high voltage.
-
7/31/2019 Project Tg04
122/184
-
7/31/2019 Project Tg04
123/184
Figure no: 4.3 Single Line Diagram of H.VTesting of Stator Winding
4.5.1.5. Measurement of D.C resistance of Stator
and Rotor windings in cold
condition
Equipment:
-
7/31/2019 Project Tg04
124/184
a) Digital micro ohmmeter and its measuring
leads.
b) Thermometer (Hg in glass)
D.C resistances of stator and rotor windings are
measured separately using digital micro ohmmeter.
The instrument terminals are connected to the
machine terminals and proper range in meter is
selected. The stabilized reading is recorded.Ambient temperature from Hg in glass thermometer
is recorded. The stator resistance temperature
detectors values are noted and average value of stator
winding temperature is evaluated.
1.4.1. Evaluation of resistance at 20OC:
-
7/31/2019 Project Tg04
125/184
- Evaluation of resistances at 20OC (R20) is done by
using formula:
- R20 = {Rt (235+20)} / (235 + T) milli ohms
- Where, R20 = Resistance at 20OC in milli ohms
- T= The average temperature of the stator winding
in degrees centigrade.
Rt = Measured resistance of the winding in milli
ohms
-Variation in maximum and minimum values of d.cresistance of 3 phases of stator windings up to 5% is
acceptable.
-
7/31/2019 Project Tg04
126/184
-
7/31/2019 Project Tg04
127/184
H.V. application to one of the phases and remaining
phases are connected to body of stator. This gives the
value of Cg+2 Cm, where Cg is capacitance of winding
with respect to ground and Cm is with respect to other
winding (mutual
capacitance).
Arrangement II:
H.V. application to all the phases. This gives the value of
3Cg..
b) Equipment:
a) 50 Hz A.C. high voltage transformer
(T90, 0 - 35kV)
b) Standard capacitor (100 / 1000 pF).
c) Schering bridge
d) Isolation shunt box
-
7/31/2019 Project Tg04
128/184
e) Connecting H.T. cables.
f) Earth wire with earthing rod.
g) Voltmeter.
h)Megger (1000V).
i)Null Indicator
(galvanometer).
j) 1- phase supply source for null indicator.
c) Test preparation:i) The stator body is isolated from ground by
placing insulation packing between the body and the
base.
ii) Connections to the Schering Bridge,
standard capacitor, Null indicator and transformer are
done as per figure 4.4 for the selected arrangement.
-
7/31/2019 Project Tg04
129/184
iii) Measurements are taken at voltages 0.2Un to
1.0Un in steps of 0.2Un.
iv) The H.V. supply is switched on and raised
to the required value. The bridge is balanced with the
proper selection of variable resistances (R3+S) & the
capacitance C4 and readings are recorded. After all
measurements, voltage is reduced to zero, supply is
switched off and windings are discharged to earth.
e) Formula used:i) Capacitance:
Cn x R4 x (R3+100)Cx = -------------------------- F.
N x (R3+S)
ii) Percentage of tan
% tan = ( x R4 x C4 x 10-4 ) x 100
where, C4 & Cn are in F.
-
7/31/2019 Project Tg04
130/184
-
7/31/2019 Project Tg04
131/184
-
7/31/2019 Project Tg04
132/184
These tests are run after assembly of machine on test
bed.
Equipment:
a. D.C motor drive system.
b. Bearing lubrication system.
c. Cooling water system.
d. Current transformers 2 nos.
e. Potential transformers 2 nos.
f. D.C current shunts 2 nos.g. AC/DC Power analyzer.
h. Phase sequence indicator.
i. Multimeter for continuity checks.
j. Vibration monitor.
k. Resistance temperature detectors
monitor.
l. 50 Hz A.C High voltage test equipment.
-
7/31/2019 Project Tg04
133/184
m. Meggers.
n. Micro ohmmeter.
o. Connecting leads/copper strips and
earthing cables rods etc.
4.5.2.1 . Mechanical run and measurement of
vibrations at rated speed
The turbo-generator under test is assembled separately
without coolers and enclosures (if any), on a testfoundation frame using its own bearings and coupled to
a calibrated d.c drive motor with gearbox of suitable
capacity (1900kW/ 1300kW/ 750kW). The brushless
Exciter and Permanent magnet generator are mounted on
the overhang of the generator rotor. Testing of turbo-
generator, brushless exciter and permanent magnet
generator are done separately. The power to the drive
-
7/31/2019 Project Tg04
134/184
motor and the field of the generator are drawn
independently from the thyristor converters suited in
electrical machine controlled rooms and controlled from
test gallery independently.
Before running the machine ensure:
-Lubricating Oil is flowing through bearings and the
gear box.
-All the instruments are working-Roll the machine and check all the parameters.
Slowly raise the speed to one-sixth rated speed.
Observe slow roll vibrations, temperature and oil
flows. Raise the speed to one-third rpm slowly and
record the vibrations, temperature and oil flows.
-The vibrations are measured at rated speed on both
the bearing housings (pedestals) in horizontal,
-
7/31/2019 Project Tg04
135/184
vertical and axial directions with the help of vibration
meters, which are internally connected to the monitor
and the vibrations, are noted in the form of graphs.
-The temperature of stator is monitored by
monitoring resistance temperature detectors
embedded in core, tooth and winding. Now raise the
speed to two third the rpm by observing all the
parameters, critical speed and record them. The
machine is rolled and run at rated speed afterensuring the bearing oil and left at rated for
stabilization of bearing temperatures.
4.5.2.2. Measurement of mechanical losses, short
circuit characteristic and losses
-
7/31/2019 Project Tg04
136/184
-The machine is prepared for short circuit
characteristic using current transformers and shorting
links as shown in figure 4.5
- The machine is run at rated speed and drive motor
input voltage and current are noted and m/c is excited
gradually in steps, at 20%, 40%, 60%, 80%, 90% and
100% In
(In = Rated current of machine).
At each step the following parameters are noted:
1) Stator current (Ia & Ib)
2) Rotor current (If) corresponding to stator
current.
3) Drive motor voltage (Vd) and current (Id)
corresponding to stator current.
-
7/31/2019 Project Tg04
137/184
4) Resistance temperature detectors readings at
rated stator current (100% In).
5) Bearing vibrations at rated stator current (100%
In).
The excitation is reduced and cut off. The speed is
reduced and the machine is cooled at lower speed.
The temperatures are checked from machine
resistance temperature detectors readings. Themachine is stopped when it is sufficiently cooled
down. (The stator winding temperatures to be less
than 60OC).
From the above data, the characteristic curves are
plotted as follows:
a) % In versus If.
-
7/31/2019 Project Tg04
138/184
b) % In versus machine looses in kW.
-
7/31/2019 Project Tg04
139/184
-
7/31/2019 Project Tg04
140/184
Figure 4.5 Single line diagram for short circuit
characteristics
4.5.2.3. Measurement of mechanical losses, open
circuit characteristic and losses:
-The machine is prepared for open circuit as shown
in the figure 4.6.
- The machine is run at rated speed and drive motor
input voltage and current are noted and m/c is excited
gradually in steps, at 20%, 40%, 60%, 80%, 100%
and 120% En (En = rated voltage of machine).
At each step the following parameters are noted:
-
7/31/2019 Project Tg04
141/184
-
7/31/2019 Project Tg04
142/184
From the above data, the characteristic curves are
plotted as follows:
c) %En versus If.
d) % En versus machine looses in kW.
-
7/31/2019 Project Tg04
143/184
-
7/31/2019 Project Tg04
144/184
-
7/31/2019 Project Tg04
145/184
terminals when machine is in open circuit condition at
100%En.
4.5.2.6.. Measurement of rotor impedance (Rotor inside
stator):
Equipment:
a) 50Hz (Power frequency) A.C source.
b)AC/DC Power analyzer.
c) Current transformer (50A/5A or 100A/5A)d)Connecting leads.
Connections are made as per the figure 4.7
A variable 50 Hz A.C. voltage of single phase is
applied across the slip rings /input leads and readings
of voltage and current are noted down from 50V to
200V in steps of 50V. This test is done at 1/3, 2/3 and
at rated speed.
-
7/31/2019 Project Tg04
146/184
Evaluation of impedance:
Using formula does evaluation of impedance:
Z = V /I ohms
where Z = impedance in ohms
V = voltage in volts
I = current in amperes
Impedance measurement:
-At rated rpm (Rotor inside stator).-At standstill (Rotor inside stator).
-At standstill (Rotor outside stator).
-
7/31/2019 Project Tg04
147/184
-
7/31/2019 Project Tg04
148/184
-
7/31/2019 Project Tg04
149/184
Figure 4.7 Single line diagram for measurement of
Rotor impedance
4.6. EVALUATION OF EFFICIENCY
Efficiency of Turbogenerator
Introduction:
-
7/31/2019 Project Tg04
150/184
-
7/31/2019 Project Tg04
151/184
Thus %Efficiency = 100{(output) / (output + losses)}
The Total loss consists of the following component
losses
1.Excitation Circuit Losses:
a. Field I2R loss: The I2R loss in the field winding.
b. Main rheostat loss: The loss in the rheostat in the
main exciting winding.
c. Electrical loss in the brushes: The summation of
I
2
R losses in the brushes and the connectors andbrush contact loss.
d. Exciter loss: All the losses of exciter mechanically
driven from the main shaft which forms part of the
complete unit and is used solely for exciting the
machine, together with the losses in the rheostat in
the field circuit of such an exciter.
2.Losses independent of Current:
-
7/31/2019 Project Tg04
152/184
-
7/31/2019 Project Tg04
153/184
a) Stray load loss determined from the primary
windings determined from the current in the
conductors.
b) Stray load loss in the conductors.
4.6.1. EVALUATION OF EFFICIENCY:
After completion of routine tests, efficiency of the
machine evaluated.
The following sequence of calculation is followed.1.Open circuit characteristics is plotted on a graph paper
from open circuit characteristics results by selecting X
axis as field current and Y- axis % of rated voltage.
Values of field current at 80%,100&,115%,130%En are
taken from the curve.
2.Short circuit characteristic is plotted from S.C.C
results by selecting X axis as field current and Y axis
-
7/31/2019 Project Tg04
154/184
as % of rated current. Values of field at 100% In are
taken from the curve.
Turbo generator looses: ref. Fig. 4.8.
Air gap line for open circuit characteristics is drawn and
field current for air gap line at 100%En is obtained.
Copper loss characteristic is plotted from S.C.C results
by selecting X axis, as %of rated current and Y axis
as losses in kW. The value of copper loss (kW cu1) at100%In is taken from the curve.
Iron loss characteristic is plotted from O.C.C results by
selecting X axis, as %of rated current and Y axis as
losses in kW. The value of iron loss (kW fe) at 100%En
is taken from the curve.
Drive motor with gearbox losses:
-
7/31/2019 Project Tg04
155/184
-
7/31/2019 Project Tg04
156/184
i). Average mechanical losses (kW mechanical.) =
Average of mechanical losses before Short circuit
characteristics and open circuit characteristics (kw
average mechanical)
ii) Losses at 100% In i.e. 100%In mech. = kW
average mech. + (kW6 kW3)
iii) Losses at 100% En i.e. 100%En mech. = kW
average mech. + (kW9 kW3)
4. Machine losses:
a. Mechanical losses (Pmech) = kW avg mech.
kW3
b. Stator copper losses at 100% In (Pcu1) = kWcul
kW 100%In mech.
-
7/31/2019 Project Tg04
157/184
c. Stator iron losses at 100% En (Pfe) = kWfe kW
100%En mech.
d.Excitation losses: This shall be taken as 5% of
rotor copper losses.
e. Brush drop losses: In case of machine with
conventional excitation system with slip rings on
rotor, the brush drop losses are calculated taking
voltage drop of 1.0 volt each polarity multiplied by
the rated excitation current. For brushless excitationsystem, this loss is non-existent.
To obtain field currents of the turbo generator at
25%, 50%, 75% & 100% loads all the data required
from the test results are fed to the computer program.
The output gives field currents, rotor copper losses
and excitation losses. After obtaining the machine
losses including exciter mechanical losses (if any),
-
7/31/2019 Project Tg04
158/184
stator copper losses, stator iron losses, rotor copper
losses, excitation losses, brush drop losses (if any);
all the losses are added to get total loss.
Percentage efficiency (%) is evaluated as follows:
Output%Efficiency = 10 0 X ------------------------
Output + totallosses
4.6.2.Evaluation of short circuit ratio (S.C.R):
From the test data S.C.R is calculated using formula:
Field current at 100% En fromopen circuit testShort circuit ratio =----------------------------------------------------------
Field current at 100% In fromShort circuit test
-
7/31/2019 Project Tg04
159/184
-
7/31/2019 Project Tg04
160/184
4.7. TESTING OF BRUSHLESS EXCITER:
-
7/31/2019 Project Tg04
161/184
This test procedure covers the procedure for routine tests
on brushless exciter and permanent magnet generator.
4.7.1.Tests conducted on brushless exciter:
Open circuit characteristic.
Measurement of D.C. resistance of armature
windings and main pole winding.
4.7.2.Tests conducted on Permanent Magnet
Generator
-Measurement of output voltage at rated speed.
-Checking of phase sequence and measurement of
frequency.
-Measurement of load characteristic.
-Measurement of insulation resistance value before
high voltage tests.
-
7/31/2019 Project Tg04
162/184
-
7/31/2019 Project Tg04
163/184
to the terminals in the control gallery where the
measurement is done.
Equipment:
-D.C. motor drive system
-Bearing lubrication system
-D.C. voltmeters
-D.C. current shunts-Phase sequence meter
-Water load resistance bank
-Current Transformers
-A.C Ammeters
-A.C. voltmeters
-Frequency meter
-Vibration probes and Vibration monitor
-
7/31/2019 Project Tg04
164/184
-
7/31/2019 Project Tg04
165/184
4.7.1.2..Load Magnetization curve:
-The machine is prepared for the load magnetization
characteristic. A variable water load resistance is
connected across the slip rings.
- The machine is run at rated speed, load breaker is
closed and the machine is excited gradually in steps.
The load resistance is maintained at R40 (R40: Turbo
generator rotor resistance at calculated for 40
0
C) byadjusting the water load resistance.
-At each step, following parameters are noted:
-Va : Output voltage of the exciter
-Ia: Load current of the exciter
-If: Field current of the exciter
-And bearing vibrations at rated load.
- Test is repeated for load resistances R70 and R100.
-
7/31/2019 Project Tg04
166/184
-
7/31/2019 Project Tg04
167/184
Rm = (kV+1) mega ohms
-where kV = Voltage in kilo volts to be applied for
H.V. test.
High voltage test is done on individual windings using
high voltage test kit by regulating primary voltage to the
transformer. Slowly HV is reached and maintained for 1
minute and is reduced to zero. The earth rod then
discharges the object and the IR values are taken. When
this test is done on one winding, the other windings areearthed.
4.7.1.4. Measurement of DC resistances of Armature
windings and main pole winding:
After dynamic tests the machine is allowed for cooling
and when it is sufficiently cooled, the DC resistances of
all the three armature windings and main pole windings
-
7/31/2019 Project Tg04
168/184
are measured separately by the micro-ohmmeter. The
ambient temperature is also recorded and the evaluation
of resistances at 20OC is done by using the formula:
R20 = Rt (235+20)/(235+T)
where, R20 = DC resistance at 20deg
Rt = DC resistance of the winding at t deg
T = Temperature of the winding in deg
4.7.2. Test Procedure of the permanent magnet
generator (PMG)
The permanent magnet generator is assembled along
with the brushless exciter on the generator rotor shaft.
The output is connected to a three-phase resistance load
(variable in steps). As permanent magnet generator has
-
7/31/2019 Project Tg04
169/184
-
7/31/2019 Project Tg04
170/184
permanent magnet generator. The sequence indicated by
the meter is recorded.
At rated speed, a frequency meter is connected across
any two phases of the permanent magnet generator PMG
output terminals and frequency is measured.
4.7.2.3.Measurement Of The Load Characteristic
-Machine is run at rated speed and loaded using
three-phase resistance bank in steps up to rated loadcurrent.
-At each step, load currents and output voltages are
noted.
-Load magnetization curve is drawn as phase-to-
phase voltage versus load current.
-
7/31/2019 Project Tg04
171/184
-
7/31/2019 Project Tg04
172/184
phase windings separately. The ambient temperature is
also recorded and the evaluation of resistances at 20deg
is done as shown in the figure.
5. CONCLUSION
In this project a sincere effort has made for the testing
of turbo generator of 90.59 MVA, 11kv,3000 RPM,
2-Pole Synchrous generator. The various activecomponents of the generator were studied and attempt
was made to acquaint us with the sophisticated design
and technologies involved.
The present project gave us an opportunity to know
above the manufacture of the turbo generator and its
structural components viz., stator, rotor, brushless
-
7/31/2019 Project Tg04
173/184
excitation systems etc. and other auxiliary equipment.
A study was also made on most update insulation
technique latest technology of vacuum pressure