project reprt shray
TRANSCRIPT
-
7/30/2019 Project Reprt Shray
1/3
Lavasa ProjectThe CAG view and MOEFs stand
In the light of Lavasa controversy, we have taken the endeavor to find
out the main causes of the dispute and identify the stand of various
parties involved, namely, the business, the government, the political
environment and the society at large. In this report, I would like to
highlight the governments stand by the findings of the Comptroller and
Auditor General of India (CAG) and the actions taken by the Ministry of
Environment and Forests (MOEF) and there implications.
Lavasa Project Overview
Lavasa is a private, planned city being built near Pune. A 25,000 acres
(100 km2)
or 8,000 acres (32 km
2) project being developed by HCC, this
as-yet-incomplete city has been controversial for multiple reasons
including procurement of land, harm to the environment, and loans
acquired through political corruption. In late 2010 the Indian
Environment and Forests Ministry ordered that construction cease
because the project violated environmental laws. As of late 2011, this
order has been rescinded, but the project's scale may have been
reduced and an IPO may not occur.
CAG Report
Claiming that the Lavasa project was driven by private interests rather
than the public one, the CAG report said that expression of interests
were not invited by the government for the development of Lavasa,
thus made the process non-transparent. The report also stated that the
-
7/30/2019 Project Reprt Shray
2/3
government had planned to develop all the six hill stations in Pune and
not considered the other hilly areas in the state, thus proving that the
development was in the interest of the developer. The report stated
that Lavasa had purchased the 22.47 hectare land at Mugaon village
from four tribals, when acquisition of tribal land was not permissible
legally. Slamming the government for the irregularity in issuing
environment clearance to the project, the report said: The
government avoided clearance from the ministry of environment and
forests (MoEF) on the grounds that the development would not be
beyond 1,000 meters. But looking at the huge ramification in terms of
eco-sensitive area on which it was being developed, a MoEF sanction
was a must.
MOEFs Stand
The MOEF ordered the construction cease because no environment
clearance from Centre was taken. Since the area is rich in
environmental resources and cultural heritage of the tribals, this cease
was said justified. Also, one more reason was the misinterpretation of
the MOEF directives by the environment department. This cease was
enforced in late 2010.
By 2011 end, the MOEF gave the go ahead for Lavasa under certain
restrictions, such as-
1.Stopping the hill cutting activities2.Building sewage treatment plant3.CSR initiative for the displaced villagers
This move has been seen as the result of political pressure on MOEF.
-
7/30/2019 Project Reprt Shray
3/3